adjudication discussion evening (6 sep, sydney) - 1/3
TRANSCRIPT
SLIDE 2SLIDE 2
REFERENCE DATESRECENT CASES IN NSW
1
Background: Southern Han2
Practical completion3
Deemed reference dates4
5
The Act – what’s the issue?
SLIDE 3
13 (1) A person referred to in section 8 (1) who is or who claims to be entitled to a
progress payment (the "claimant" ) may serve a payment claim on the person
who, under the construction contract concerned, is or may be liable to make the
payment.
8(1) On and from each reference date under a construction contract, a person:
(a) who has undertaken to carry out construction work under the contract, or
(b) who has undertaken to supply related goods and services under the contract,
is entitled to a progress payment.
REFERENCE DATE – JURISDICTIONAL?
SLIDE 4
13 (1) A person referred to in section 8 (1) who is or who claims to be entitled to a
progress payment (the "claimant" ) may serve a payment claim on the person
who, under the construction contract concerned, is or may be liable to make the
payment.
8(1) On and from each reference date under a construction contract, a person:
(a) who has undertaken to carry out construction work under the contract, or
(b) who has undertaken to supply related goods and services under the contract,
is entitled to a progress payment.
REFERENCE DATE – JURISDICTIONAL?
SLIDE 5
13 (1) A person referred to in section 8 (1) who is or who claims to be entitled to a
progress payment (the "claimant" ) may serve a payment claim on the person
who, under the construction contract concerned, is or may be liable to make the
payment.
8(1) On and from each reference date under a construction contract, a person:
(a) who has undertaken to carry out construction work under the contract, or
(b) who has undertaken to supply related goods and services under the contract,
is entitled to a progress payment.
REFERENCE DATE – JURISDICTIONAL?
SLIDE 6
• 5 May 2015, at first instance:
[40] … an essential requirement triggering the right to make a payment claim,
which in turn triggers the adjudicator’s jurisdiction.
• 25 September 2015, on appeal to the NSW Court of Appeal:
(1) The existence of a reference date to support a payment claim is not a
jurisdictional fact; it is not an essential pre-condition for the making of a valid
payment claim.
(2) The words “on and from each reference date” in s 8(1) do not purport to
identify a person, they identify the time on and from which a person who
satisfies the description in either (a) or (b) of that sub-section is entitled to a
progress payment.
(3) The words … in s 13(1) refer, in their ordinary meaning, to a person failing
within either s 8(1)(a) or 8(1)(b).
(4) The words “or who claims to be entitled to a progress payment” in s 13(1)
make clear that the existence of a dispute as to the entitlement of a person to a
progress claim does not preclude the making of a valid payment claim.
• 21 December 2016, on appeal to the High Court of Australia:
The existence of a reference date under a construction contract within the meaning
of s 8(1) of the Act is a precondition to the making of a valid payment claim under s
13(1) of the Act.
REFERENCE DATE – JURISDICTIONAL?SOUTHERN HAN V LEWENCE CONSTRUCTIONS
SLIDE 7
• The Contract
– Based upon AS 4000 (see Ball J at first instance)
– 36.4 Practical Completion
The Contractor shall give the SI at least 14 days written notice of the date upon which the Contractor
anticipates that PC will be reached.
When the Contractor is of the opinion that PC has been reached, the Contractor shall in writing
request the SI to issue a certificate of PC.
Within 14 days after receiving the request, the SI shall give the Contractor and the Principal either a
certificate of PC evidencing the date of PC or written reasons for not doing so.
– 44.3 Final Reference Date
[(a)] For the purpose of section 8(2) of the SOP Act, there are only two reference dates after PC
being:
i) The first date for a progress claim arising immediately after PC (as determined by subclause
37.1); and
ii) The date provided in subclause 37.4 for the Contractor to give its final payment claim.
Clause 37.1, which incorporates Item 28 of the Schedule, provides that a progress claim may be
made on the 28th day of each month for “Works under Contract” done to the 28th day of that month.
– Practical Completion
... that stage in the carrying out and completion of WUC [work under the Contract] when …
– Date of Practical Completion
a) the date evidenced in a certificate of practical completion as the date upon which practical
completion was reached …
ABERGELDIE CONTRACTORS -V- FAIRFIELD CITY COUNCIL [2017] NSWCA 113
SLIDE 8
• The Contract
– Based upon AS 4000 (see Ball J at first instance)
– 36.4 Practical Completion
The Contractor shall give the SI at least 14 days written notice of the date upon which the Contractor
anticipates that PC will be reached.
When the Contractor is of the opinion that PC has been reached, the Contractor shall in writing
request the SI to issue a certificate of PC.
Within 14 days after receiving the request, the SI shall give the Contractor and the Principal either a
certificate of PC evidencing the date of PC or written reasons for not doing so.
– 44.3 Final Reference Date
[(a)] For the purpose of section 8(2) of the SOP Act, there are only two reference dates after PC
being:
i) The first date for a progress claim arising immediately after PC (as determined by subclause
37.1); and
ii) The date provided in subclause 37.4 for the Contractor to give its final payment claim.
Clause 37.1, which incorporates Item 28 of the Schedule, provides that a progress claim may be
made on the 28th day of each month for “Works under Contract” done to the 28th day of that month.
– Practical Completion
... that stage in the carrying out and completion of WUC [work under the Contract] when …
– Date of Practical Completion
a) the date evidenced in a certificate of PC as the date upon which practical completion was
reached …
ABERGELDIE CONTRACTORS -V- FAIRFIELD CITY COUNCIL [2017] NSWCA 113
SLIDE 9
ABERGELDIE CONTRACTORS -V- FAIRFIELD CITY COUNCIL [2017] NSWCA 113
• The facts
– 16 September 2015: Contractor wrote to Council – PC achieved on that date.
– 28 October 2016: Contractor sent payment claim to SI.
– 25 November 2015: SI certified PC to have been achieved on 16 September 2015.
– 25 November 2015: Contractor sent payment claim to SI.
– 7 December 2015: Payment schedule issued for nil amount – no reference date.
– Adjudication: Contractor entitled to payment on November 2016 payment claim.
– Supreme Court at first instance: PC was in September so November 2016
payment claim was invalid as it was the second payment claim after PC.
• The (primary) controversy
– Common ground: valid reference date was a precondition to service of a valid
payment claim.
– Council contended: PC occurred on 16 September 2016 with the result that the
relevant payment reference date was 28 September 2016.
– Contractor contended: PC occurred on the date the certificate of PC issued, with
the result that the relevant reference date was 28 November 2016.
– When was PC?
SLIDE 10
ABERGELDIE
• Reasons (Basten JA)
Contract’s language is consistent with Contractor’s contention that the issue
of the certificate...provides the date on which PC is achieved [at 34]:
(1) “has been” completed indicates that the event has occurred “but connotes
that the actual time of completion is unimportant”; it is likely to be something
which has just happened .
(2) Structure of clause 34.6 consists of two steps requiring Contractor’s (1)
anticipatory notice as to the date upon which PC “will” be reached and (2)
notice of an opinion that PC “has been” reached. SI then has 14 days to
consider. “When” refers to when the opinion is reached.
(3) Certificate is not said to “state” but rather “evidence” the date.
(4) Unresolved question as to whether in identifying the Date of PC the Court
is to consider the objective facts or whether the SI has formed an opinion on
the underlying facts (and if so, when). SI is the best placed person to assess.
(5) Structure and language of the contract is entirely consistent with … the
conclusive event [being] the issue of the certificate of PC, which must depend
on a contemporaneous opinion of the SI.
SLIDE 11
ABERGELDIE
• Reasons (Basten JA)
– Construction is consistent with commercial context:
• Cl14 care of works dependent on knowledge
• Cl 16 insurance
• Cl 27 removal of temporary works
– Contractor cannot know whether PC reached until it received the
certificate … which … must, by implication, be dated and the date of the
certificate will evidence the date of PC.
– Therefore the relevant reference date was 28 November 2016.
– Pursuant to clause 37.1, the claim of 25 November 2016 was made on
that date.
SLIDE 12
ABERGELDIE
Takeaways
• Construe the contract, not the conduct.
• Under AS 4000, the date of PC is properly the date of issue
of the certificate of PC.
• Abergeldie has application that is broader than the question
of determining a reference date.
SLIDE 13
• The Contract
[All Seasons] shall claim payment progressively in accordance with Item 37.
An early progress claim shall be deemed to have been made on the date for
making the claim. (Emphasis added)
Item 37 says On the 2oth day of the month.
• The facts
– On 20 June 2016 All Seasons served a payment claim.
– On 12 July 2016 All Seasons made a progress claim under the contract and
purportedly under SOPA.
– The 12 July 2016 claim was referred to an adjudicator who determined that
she had jurisdiction to deal with it.
– Adjudicator determined the adjudicated amount was the claimed amount, All
Seasons obtained a judgment upon an ANA certificate for that amount.
• The (primary) controversy
– Was All Seasons entitled to a progress payment as at 12 July 2016, in
circumstances where it had made a payment claim for the reference date
accruing (on 20 June 2016) in the previous month, and where the next
reference date (20 July 2016) had not accrued at the time its progress claim
was served? [7(1)]
REGAL CONSULTING SERVICES -V- ALL SEASONS AIR [2017] NSWSC 613
SLIDE 14
REGAL CONSULTING SERVICES -V- ALL SEASONS AIR [2017] NSWSC 613• Reasons
– Southern Han followed:
– Common ground that 12 July 2017 claim was effective under the contract
as it was deemed to have been made on the proper date.
– Did the second sentence of cl 37.1 operate for the purposes of SOPA?
– Deeming sometimes creates “statutory fictions” but not always.
– Why did the parties include the deeming provision in their bargain?
(Muller v Dalgety & Co (1909) 9 CLR 693)
– Clause 37.1 was used to create a contractual fiction. “By setting out a
timetable for the making of progress claims, their assessment, and the
payment of any amount owing, it enables the parties to plan their work
and to manage their cash flow.” [at 42] Cl 37 is not concerned with SOPA
[at 50]
– There is nothing in the contract to make the stipulated date ... a condition
of entitlement . . . The effect of the deeming provision, whilst fictitious, is
not to give an entitlement that does not otherwise exist. [at 48]
SLIDE 15
REGAL CONSULTING SERVICES -V- ALL SEASONS AIR [2017] NSWSC 613
Takeaway
• Where the reference date has not arrived in fact, the
payment claim will be ineffective [at 49]
• To put it another way, where the reference date has not
arrived in fact, the claimant cannot be described as (in the
introductory words of s 13(1)) “a person referred to in s 8(1)”
who is . . . entitled to a progress payment [at 49]
• … there was no available reference date to support the
progress claim that All Seasons served on Regal on 12 July
2016. It must follow that the adjudicator lacked jurisdiction …
[at 53]