addendum 001 e126 - floor finish to be f7 and base to be b7.-fire riser e131- noth and west wall...

37
This Addendum shall be considered part of the Contract Documents and Project Manual for the above mentioned project as though it had been issued at the same time and shall be incorporated integrally therewith. Where provisions of the following supplementary data differ from those of the original Contract Documents and Project Manual, the Addendum shall govern and take precedence. ADDENDUM 001 project JSD Bluffdale Elementary #2 project no 17725.00 date 2018-01-26 no. pages 37 owner Jordan School District contractor bid date 2018-02-13 bid time 12:00 pm general 1.1 See attached clarifications by Olsen & Peterson Consulting regarding Mechanical/Plumbing specifications and drawings. drawings item sheet# description 1.1 A050 See attached sheet for clarifications. Detail 8 - delete title name and number at general VCT, VCT #1, VCT # 4, and VCT #5. See attached finish schedule for colors. - Detail 6 revised. - Added titles on details 1, 2, 3, 4, and 11. - Added detail references 6/A050 at classroom entries. - 1.2 A115.3 Principal E105 - North wall finish to be W9 and South wall finish to be W1. - Storage E126 - Floor finish to be F7 and base to be B7. - Fire Riser E131- Noth and West wall finish to be W5. - Storage E140 - Gyp. wall finish at the stair to be W1. - Vestibule E152 to have floor finish F6. - specifications item section# description 1.1 08 8000 See attached for clarifications. 1.2 09 0000 See attached for clarifications. 1.3 21 0000 See attached for clarifications.

Upload: lycong

Post on 23-Jun-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ADDENDUM 001 E126 - Floor finish to be F7 and base to be B7.-Fire Riser E131- Noth and West wall finish to be W5.-Storage E140 - Gyp. wall finish at the stair to be W1. -Vestibule

This Addendum shall be considered part of the Contract Documents and Project Manual for the above mentioned

project as though it had been issued at the same time and shall be incorporated integrally therewith. Where provisions

of the following supplementary data differ from those of the original Contract Documents and Project Manual, the

Addendum shall govern and take precedence.

ADDENDUM 001

project JSD Bluffdale Elementary #2 project no 17725.00

date 2018-01-26 no. pages 37

owner Jordan School District

contractor

bid date 2018-02-13 bid time 12:00 pm

general

1.1 See attached clarifications by Olsen & Peterson Consulting regarding Mechanical/Plumbingspecifications and drawings.

drawings

item sheet# description

1.1 A050 See attached sheet for clarifications.

Detail 8 - delete title name and number at general VCT, VCT #1, VCT # 4, and VCT #5.

See attached finish schedule for colors.

-

Detail 6 revised.-

Added titles on details 1, 2, 3, 4, and 11.-

Added detail references 6/A050 at classroom entries.-

1.2 A115.3 Principal E105 - North wall finish to be W9 and South wall finish to be W1.-

Storage E126 - Floor finish to be F7 and base to be B7.-

Fire Riser E131- Noth and West wall finish to be W5.-

Storage E140 - Gyp. wall finish at the stair to be W1.-

Vestibule E152 to have floor finish F6.-

specifications

item section# description

1.1 08 8000 See attached for clarifications.

1.2 09 0000 See attached for clarifications.

1.3 21 0000 See attached for clarifications.

Page 2: ADDENDUM 001 E126 - Floor finish to be F7 and base to be B7.-Fire Riser E131- Noth and West wall finish to be W5.-Storage E140 - Gyp. wall finish at the stair to be W1. -Vestibule

approvals In addition to the manufacturers called out in the contract documents, the following manufacturers, trade names and products are

acceptable with the provisions that they shall completely satisfy every requirement of the drawings, specifications, and all addenda,

and shall conform to the design, quality and standards specified, established and required for the complete and satisfactory

installation and performance of the building and all its respective parts. Any costs incurred due to the use of the following

manufacturers shall be paid by the contractor.

End of Addendum 001

1.4 22 0000 See attached for clarifications.

1.5 23 3000 See attached for clarifications.

1.6 32 8423 See attached for clarifications.

1.7 32 9000 See attached for clarifications.

section material manufacturer action

06 1643 Glass-Mat Gypsum Sheathing American Gypsum Approved

Page 3: ADDENDUM 001 E126 - Floor finish to be F7 and base to be B7.-Fire Riser E131- Noth and West wall finish to be W5.-Storage E140 - Gyp. wall finish at the stair to be W1. -Vestibule

BLUFFDALE ELEMENTARY SCHOOL #2 JORDAN SCHOOL DISTRICT MECHANICAL ADDENDUM NO. 01 January 26, 2018 Specifications: 210000-1.1.2.C: 1. Add the following to approved contractors.

Fire Services Incorporated 220000-6.2.5 - Plumbing Fixtures 1. Replace HB-5 with the following:

HB-5 Hose Bibb: Chicago Faucet #229-CP, 3/4" chrome plated hose bibb with #293-006 Tee

handle and 3/4" threaded outlet with Watts 8C vacuum breaker.

233000-1.1: 1. Add the following to approved contractors.

Empire Heating and Air APPROVED MANUFACTURERS' PRODUCTS: The following manufacturers, tradenames, and products are approved with the provision that they shall completely satisfy all and every requirement of the Drawings, Specifications, and all Addenda, and shall conform to the design, quality, and standards specified, established, and required for the complete and satisfactory installation and performance of the building and all its respective parts. PRODUCT MANUFACTURER Custom Air Handlers Temtrol HW/CHW Coils Temtrol Cabinet Unit Heaters Beacon Morris, Rittling HW Unit Heaters Beacon Morris, Sigma, Rittling HW Baseboard Radiation Beacon Morris, Sigma, Modine, Rittling HVAC Expansion Tanks Taco HVAC Air Separators Taco Air Vents Taco Multipurpose Valves Taco Flex Connectors Twin City Hose Expansion Loops Twin City Hose Circuit Setters Flow Design Flow Venturis Flow Design Thermometers Miljoco Pressure Gauges Miljoco Strainers Titan Check Valves Titan Pressure Relief Valves Conbraco Seismic Restraints & Supports Kinetics

Page 4: ADDENDUM 001 E126 - Floor finish to be F7 and base to be B7.-Fire Riser E131- Noth and West wall finish to be W5.-Storage E140 - Gyp. wall finish at the stair to be W1. -Vestibule

Modular Acoustical Plenums Commercial Acoustics Boiler Stacks Industrial Chimney Supply, Heat Fab Flex Duct Quietflex Louvers Greenheck, Ruskin, Air Rite Dryer Booster Fans Fantech, Aldes Fire Dampers Greenheck, Ruskin Fire/Smoke Dampers Greenheck, Ruskin Registers, Grilles, Diffusers Krueger Roof Hoods Loren Cook, Air Rite Packaged AC Split System Lennox VAV Re-Heat Boxes Krueger Make-Up Air Units Modine, Econ Air Air Filter Banks Flanders Domestic Water Heaters State, Laars Domestic Storage Tanks State, Laars Domestic Expansion Tanks Watts, Taco Domestic Faucets T&S Brass, American Standard Thermostatic Mixing Valves Bradley Fixture Carriers Watts Hose Bibbs Watts Floor Drains Watts, Josam Floor Sinks Watts, Josam Roof Drains Watts, Josam Downspout Nozzles Watts, Josam Toilet Seats American Standard Drawings: Sheet P504: 1. See attached revised detail 1/P504. Sheet M507: 1. See attached revised detail 2/M507. Attachments:

P504 - Addendum #1 M507 - Addendum #1

Page 5: ADDENDUM 001 E126 - Floor finish to be F7 and base to be B7.-Fire Riser E131- Noth and West wall finish to be W5.-Storage E140 - Gyp. wall finish at the stair to be W1. -Vestibule
Page 6: ADDENDUM 001 E126 - Floor finish to be F7 and base to be B7.-Fire Riser E131- Noth and West wall finish to be W5.-Storage E140 - Gyp. wall finish at the stair to be W1. -Vestibule
Page 7: ADDENDUM 001 E126 - Floor finish to be F7 and base to be B7.-Fire Riser E131- Noth and West wall finish to be W5.-Storage E140 - Gyp. wall finish at the stair to be W1. -Vestibule

Z

B

W

E

D

C

V

R

J

M

Q

P

N

O

K

L

U

T

S

H

I

G

F

YX

A

10

A704

TYP

4

A050

TYP

10

A706TYP

3

A050

SIM

10

A050

10

A050

3

A706

TYP

4

A705

TYP

1

A705

TYP

10

A704

TYP

10

A704

TYP

6

A705

TYP

6

A706

TYP

1

A050

4

A050

6

A705

TYP

6A705

TYP

7

A050

TYP

7

A050

TYP

7

A050

TYP

7

A050

TYP

8

A050

TYP

7

A060

TYP

10

A706

10

A706

3

A050

SIM

17

A705

2

A050

17

A705

10

A706

10

A706

17

A705

9

A050

4

A050

17

A705

11

A050

TYP

11

A050

TYP

10

A704

TYP

6

A050

TYP

6

A050

TYP

6

A050

TYP

A050

17725

01-09-2018

1 1-26-18 ADD#1

SCALE:

TILE PATTER OVERALL PLAN

1/16" = 1'-0"A

SCALE:

VESTIBULE E152 ENTRY MAT

1/4" = 1'-0"9

SCALE:

TYP. GYM VCT & STRIPING

1/4" = 1'-0"8

SCALE:

TYP. VCT @ CLASSROOMS

1/4" = 1'-0"7

SCALE:

VESTIBULE ENTRY MAT

1/4" = 1'-0"6

SCALE:

VESTIBULE ENTRY MAT

1/4" = 1'-0"4

SCALE:

VCT @ KINDERGARTEN ROOMS

1/4" = 1'-0"3

SCALE:

KINDERGARTEN ENTRY MAT

1/4" = 1'-0"2

SCALE:

VCT @ FACULTY ROOM

1/4" = 1'-0"1

SCALE:

CORRIDOR E121 & E127 VCT

1/4" = 1'-0"10

A B E F G H J K L

C.1 D E F G H.5 J N PH.5

C D

B.1A B.1

4

3

1

2

6

7

8

9

10

11

12

13

4

3

1

2

5

6

8

9

10

11

12

13

SCALE:

TILE @ DRINKING FOUNTAINS

1/4" = 1'-0"11

SCALE:

VCT AT ALT. COLLAB. SPACE

1/4" = 1'-0"12

1

ADD#1

1

ADD#1

1

ADD#1

1

ADD#1

1

ADD#1

1

ADD#1

1

ADD#1

1

ADD#1

1

ADD#1

153

45

Sou

th 1

20

0 W

est B

luffda

le, U

tah

84065

CO

NS

TR

UC

TIO

N D

OC

UM

EN

TS

Jord

an S

cho

ol D

istr

ict

JS

D B

luff

da

le E

lem

enta

ry #

1

153

45

Sou

th 1

20

0 W

est B

luffda

le, U

tah

84065

CO

NS

TR

UC

TIO

N D

OC

UM

EN

TS

JO

RD

AN

SC

HO

OL

DIS

TR

ICT

JS

D B

LU

FF

DA

LE

ELE

ME

NT

AR

Y #

2

Page 8: ADDENDUM 001 E126 - Floor finish to be F7 and base to be B7.-Fire Riser E131- Noth and West wall finish to be W5.-Storage E140 - Gyp. wall finish at the stair to be W1. -Vestibule

JSD BLUFFDALE ELEMENTARY SCHOOL 6 26 JAN 2018 - VCBO 17725 ADDENDUM 001 PAGE 1

JSD - BLUFFDALE ELEMENTARY SCHOOL 2 ADDENDUM 001

26 January 2018 - VCBO 17725

SECTION 08 8000 GLAZING

Delete paragraph 3.10 A and substitute the following:

"A. Solar-Control Low-E Insulating-Glass Units: 1. Products: Subject to compliance with requirements of Contract Documents, products

which may be incorporated into the Work include, but are not limited to, the following: a. Vitro Architectural Glass (formerly PPG):

1) Low-E Coating: Solarban® 60. 2) Glass: Solexia™.

b. Guardian: 1) Low-E Coating: Super Neutral 68. 2) Glass: Light Green (verify color match to PPG Solexia™ by mockup).

2. Overall Unit Thickness: 1 inch (25mm). 3. Thickness of Each Lite: 1/4 inch (6mm). 4. Interspace Content: Air 5. Outdoor Lite: Class 1 SOLEXIA float glass with Solarban 60 coating.

a. Provide HS (heat strengthened) or FT (fully tempered) glass as indicated on the drawings. If FT (fully tempered) glass is not indicated on the drawings; but is required by the governing code, provide FT (fully tempered) glass.

6. Indoor Lite: Class 1 (clear) float glass. a. Provide HS (heat strengthened) or FT (fully tempered) glass as indicated on the

drawings. If FT (fully tempered) glass is not indicated on the drawings; but is required by the governing code, provide FT (fully tempered) glass.

7. Low-E Coating: Sputtered on second surface. 8. Visible Light Transmittance: 61 percent minimum. 9. Winter Nighttime U-Factor: 0.24 maximum. 10. Solar Heat Gain Coefficient: 0.32 maximum. 11. Outdoor Visible Reflectance: 9 percent maximum."

SECTION 32 8423 IRRIGATION SYSTEM

Add this section, issued herewith, to the Project Manual. Add section to overall Table of Contents.

SECTION 32 9000 LANDSCAPE PLANTING

Add this section, issued herewith, to the Project Manual. Add section to overall Table of Contents.

SECTION 32 9200 LAWNS AND GRASSES

Add this section, issued herewith, to the Project Manual. Add section to overall Table of Contents.

END OF ADDENDUM 001 SPECIFICATION ITEMS

Page 9: ADDENDUM 001 E126 - Floor finish to be F7 and base to be B7.-Fire Riser E131- Noth and West wall finish to be W5.-Storage E140 - Gyp. wall finish at the stair to be W1. -Vestibule

CSBA: Color selected by Architect Date updated: January 2018

CCSBA: Custom Color Selected by Architect

MATERIAL FINISH

Atlas Brick Color 2 - Park Rose

Atlas Brick Color 3 - Artic White

Atlas Brick Color 4 - Tumble Weed

Split face CMU Color 1 - Amcore Mokie

Split face CMU Color 5 - Amcore Colonial Tan

Smooth face CMU Color 5 - Amcore Colonial Tan

Exterior Metal

Metal Cap @ Masonry CSBA

Vertical Metal @ Main Entry & Classroom Entries MBCI Colonial Red

Metal Roof Canopies @ Entries MBCI Colonial Red

Metal Soffits MBCI Colonial Red

Hollow Metal Doors and Frames Sherwin Williams SW 7019 Gauntlet Gray

Aluminum Storefront and Doors Clear Anodized

Aluminum Windows Aluminum Curtain Wall Clear Anodized

Overhead Door @ Shed CSBA

Louvers 1 and 2 Benjamin Moore - 1074 Alpaca

Louvers 3, 4, 5, and 6 Benjamin Moore - 1077 Great Plains Gold

Louver 7 Pratt & Lambert - 2-20 Taupe

Profile Metal MBCI Colonial Red

Interior Masonry

Honed CMU Amcor - Cinder (formerly Amber Gray with Lava)

Interior Metal

Hollow Metal Doors and Frames Sherwin Williams SW 7019 Gauntlet Gray

Aluminum Storefront & Doors Clear Anodized

Louvers in Millwork Clear Anodized

Metal Ceiling at Main Entry Vestibule

Alpro Acoustical System Wall Panel - Pattern AI, factory

paint to match MBCI Colonial Red

Metal Deck/Structure Sherwin Williams SW 7006 Extra White

Exposed Steel Above Column in Media P1 Accent Red / Sherwin Williams SW 6608 Rave Red

Railings Sherwin Williams SW 7019 Gauntlet Gray

Duct Work Exposed In Multipurpose Room P1 Accent Red / Sherwin Williams SW 6608 Rave Red

INTERIOR

Wood Doors - Species and Stain VT Cherry Venear / Clear finish CL07

Tackable Panels and Tackboards Koroseal Desert Sand with Teflon, White 5851-02

Trim @ Tackable Panels To match Tackable Panels

General Carpet and Carpet Base Lees Faculty IV DK166 Norse Blue 4277

Carpet Tiles and Carpet Tile Base Shaw - CSBA

Rubber Base and Mercer strip Johnsonite 32 Pebble WG

Tile Wainscot Daltile P686 Creme Linen (Unpolished)

Wainscot grout Mapei 93 Warm Gray

Paint Colors

General Paint Sherwin Williams SW 7006 Extra White

FINISH SELECTION - BLUFFDALE #1 ELEMENTARY SCHOOL

Exterior Masonry

JSD - BLUFFDALE ELEMENTARY SCHOOL # 2

FINISH SCHEDULE BID SET - CONSTRUCTION DOCUMENTS

16 JAN 2018 - VCBO 17725

SECTION 09 0000 - PAGE 1

2

Page 10: ADDENDUM 001 E126 - Floor finish to be F7 and base to be B7.-Fire Riser E131- Noth and West wall finish to be W5.-Storage E140 - Gyp. wall finish at the stair to be W1. -Vestibule

P1 Accent Red Sherwin Williams SW 6608 Rave Red

P2 Accent Blue Sherwin Williams SW 6802 Jacaranda

P3 Accent Orange Sherwin Williams SW 6627 Emberglow

P4 Accent Purple Sherwin Williams SW 6557 Wood Violet

VCT Colors

General VCT Armstrong 51810 Washed Linen

VCT1 Accent Red Armstrong 51880 Maraschino

VCT2 Accent Blue Armstrong 51875 Mid Grayed Blue

VCT3 Accent Orange Armstrong 51867 Cantaloupe

VCT4 Accent Purple Armstrong 57507 Dusty Plum

VCT5 Accent Neutral Armstrong 57502 Café Latte

Field Color 1 Daltile D014 Desert Gray

Field Color 2 Daltile D200 Desert Gray Speckle

FT1 Accent Red Daltile D017 Red

FT2 Accent Blue Daltile D169 Waterfall

FT3 Accent Orange Daltile D090 Pumpkin Spice

FT4 Accent Purple Daltile D044 Deep Purple

FT5 Accent Gray Daltile D618 Castle Rock

Floor Grout (EPOXY) Mapei 09 Gray

General Wall Tile Daltile 6570 Arctic White

T1 Accent Red Daltile Q094 Chianti

T2 Accent Blue Daltile QF44 Spa Blue DT

T3 Accent Orange Daltile QF71 Marmalade

T4 Accent Purple Daltile QF54 Iris DT

T5 Accent Light Gray Daltile X714 MT Desert Gray

T6 Accent Warm Gray Daltile 0109 Architectural Gray

Wall Grout Mapei 00 White

Millwork Laminate

Base Cabinets Pionite WC421 Suede / Oiled Cherry

Upper and Full-height Cabinets Wilsonart 4939K-18 Vapor Strandz

Countertops Pionite AV250 Suede / Passin Through

Storage Shelving White Melamine

Edge Banding CSBA

Interior Melamine White

General Paint Sherwin Williams SW 7006 Extra White

P1 Accent Red Sherwin Williams SW 6608 Rave Red

General VCT Armstrong 51810 Washed Linen

VCT1 Accent Red Armstrong 51880 Maraschino

Carpet Tiles and Carpet Base (Media Center) Shaw - CSBA

General Paint Sherwin Williams SW 7006 Extra White

P2 Accent Blue Sherwin Williams SW 6802 Jacaranda

General VCT Armstrong 51810 Washed Linen

RED Rooms- (Classrooms) D101, D102, D103, D104, D115, E115, E120, (Media Center) D122 (Computer Lab)

D113 (Counseling) D117, (Hearing & Speech) D116, (Kitch. Office) E137, (Cust. Office) E145, (Music Platform)

E123

BLUE Rooms - (Classrooms) A101, A102, A103, A104, A105, A106, A116, A117, D105, D106, (Conf./Reading)

A107 (Teacher Prep.) A113, (Collaboration) A115

Toilet Wall Tile Colors and Grout Color

Toilet Floor Tile Colors and Grout Color

JSD - BLUFFDALE ELEMENTARY SCHOOL # 2

FINISH SCHEDULE BID SET - CONSTRUCTION DOCUMENTS

16 JAN 2018 - VCBO 17725

SECTION 09 0000 - PAGE 2

Page 11: ADDENDUM 001 E126 - Floor finish to be F7 and base to be B7.-Fire Riser E131- Noth and West wall finish to be W5.-Storage E140 - Gyp. wall finish at the stair to be W1. -Vestibule

VCT2 Accent Blue Armstrong 51875 Mid Grayed Blue

General Paint Sherwin Williams SW 7006 Extra White

P3 Accent Orange Sherwin Williams SW 6627 Emberglow

General VCT Armstrong 51810 Washed Linen

VCT3 Accent Orange Armstrong 51867 Cantaloupe

General Paint Sherwin Williams SW 7006 Extra White

P4 Accent Purple Sherwin Williams SW 6557 Wood Violet

General VCT Armstrong 51810 Washed Linen

VCT4 Accent Purple Armstrong 57507 Dusty Plum

General Paint Sherwin Williams SW 7006 Extra White

Accent Paint Color CSBA

General VCT Armstrong 51810 Washed Linen

VCT5 Accent Neutral Armstrong 57502 Café Latte

Carpet Tiles and Carpet Base Shaw - CSBA

Bathroom Toilet Partition Colors

Wilsonart 4939K-18 Vapor Strandz

Field Color 1 (40% randomly set) Daltile D014 Desert Gray

Field Color 2 (40% randomly set) Daltile D200 Desert Gray Speckle

FT5 Accent Gray (20% randomly set) Daltile D618 Castle Rock

Field Color 1 (40% randomly set) Daltile D014 Desert Gray

Field Color 2 (40% randomly set) Daltile D200 Desert Gray Speckle

FT1 Accent Red (20% randomly set) Daltile D017 Red

Field Color 1 (40% randomly set) Daltile D014 Desert Gray

Field Color 2 (40% randomly set) Daltile D200 Desert Gray Speckle

FT2 Accent Blue (20% randomly set) Daltile D169 Waterfall

Field Color 1 (40% randomly set) Daltile D014 Desert Gray

Field Color 2 (40% randomly set) Daltile D200 Desert Gray Speckle

FT3 Accent Orange (20% randomly set) Daltile D090 Pumpkin Spice

Field Color 1 (40% randomly set) Daltile D014 Desert Gray

Field Color 2 (40% randomly set) Daltile D200 Desert Gray Speckle

FT4 Accent Purple (20% randomly set) Daltile D044 Deep Purple

General Wall Tile Daltile 6570 Arctic White

T5 Accent Light Gray Daltile X714 MT Desert Gray

T6 Accent Warm Gray Daltile 0109 Architectural Gray

General Wall Tile Daltile 6570 Arctic White

T5 Accent- Light Gray Daltile X714 MT Desert Gray

T1 Accent- Red Daltile Q094 Chianti

Toilet Floor Tile E108, E110, E111, E132, E147, E148 - NEUTRAL Areas

Toilet Wall Tile E108, E110, E111, E132, E147, E148 - NEUTRAL Areas

Toilet Floor Tile E117, E118 - RED Areas

Toilet Wall Tile E117, E118 - RED Areas

Toilet Floor Tile A110, A111 - BLUE Areas

Toilet Floor Tile B110, B111, B109 - ORANGE Areas

Toilet Floor Tile C110, C111 - PURPLE Areas

ADMIN Rooms - (Admin.) E101, E102, E103, E104, E105, E106, E107, E113, E114, (Media) D120

ORANGE Rooms- (Classrooms) B101, B102, B103, B104, B105, B106, D107, D111 (Teacher Prep.) B113

(Conf./Reading) B107

PURPLE Rooms - (Classrooms) C101, C102, C103, C104, C105, C106, C116, C117, D112, D114, (Conf./Reading)

C107 (Teacher Prep.) C113, (Collaboration) C115

JSD - BLUFFDALE ELEMENTARY SCHOOL # 2

FINISH SCHEDULE BID SET - CONSTRUCTION DOCUMENTS

16 JAN 2018 - VCBO 17725

SECTION 09 0000 - PAGE 3

Page 12: ADDENDUM 001 E126 - Floor finish to be F7 and base to be B7.-Fire Riser E131- Noth and West wall finish to be W5.-Storage E140 - Gyp. wall finish at the stair to be W1. -Vestibule

General Wall Tile Daltile 6570 Arctic White

T5 Accent Light Gray Daltile X714 MT Desert Gray

T2 Accent Blue Daltile QF44 Spa Blue DT

General Wall Tile Daltile 6570 Arctic White

T5 Accent Light Gray Daltile X714 MT Desert Gray

T3 Accent Orange Daltile QF71 Marmalade

General Wall Tile Daltile 6570 Arctic White

T5 Accent Light Gray Daltile X714 MT Desert Gray

T4 Accent Purple Daltile QF54 Iris DT

Kitchen Wall Tile, Quarry Floor Tile, and Grout Colors E134

General Wall Tile Daltile 6570 Arctic White

T6 Accent Warm Gray Daltile 0109 Architectural Gray

Wall Grout Mapei 00 White

Quarry Floor Tile Daltile 0T01 Diablo Red

Floor Grout (EPOXY) Mapei 47 Charcoal

Miscellaneous

Lockers CSBA

Back Curtain KM Fabrics 1064 Black

Operable Panels Modernfold 046 Pelican

Operable Panel Trim & Hinges Smoke Gray

Accordian Partition Modernfold Standard Koroseal Mojave II - Galvanized

Exterior glass PPG Solarban 60 #3 Solexia

Solid Surface Window Sills Corian Silver Birch

Entry Mat

Tandus-Centiva 02578 Abrasive Action II 19103 Winter

Gray

Floor Tile @ Drinking Fountains (Equal quantity of each

color randomly set)

Daltile Volume 1.1 - Victory Red, VL89 Tradition Blue,

VL88 Action Orange, VL85 VL86 Spirit Blue

Solid Surface @ Serving Counter HanStone Quartz - Bavaria BT351

Finish @ Serving Counter and Cashier's Stand Ground Stainless Steel

Joint Sealants @ Exterior & Interior C.S.B.A. by mock-up

All Electrical Devices Gray

All Cover Plates Stainless steel

Rubber Surfacing at outside play area Black, Red

Polymer-Based Cementious Elements C.S.B.A. by Submittal

Flagpoles Clear Anodized

Skylight Sliding Shade White/White

Motorized Shades White/White

Manual Shades Black/Bronze

Exterior speakers, transformer, CT cans painted to match adjacent masonry

Accent Paint at Pencil Column in Media Center SW7704 Tower Tan (Wood)

SW6904 Gusto Gold (Pencil Body)

SW6346 Fame Orange (Eraser)

Black (Pencil Lead)

Solid Surface at Reception and Media Center Counters

(SSI)

Corian Silver Birch

Toilet Wall Tile A110 & A111 - BLUE Areas

Toilet Wall Tile B110, B111 & B109 - ORANGE Areas

Toilet Wall Tile C110 C111 - PURPLE Areas

JSD - BLUFFDALE ELEMENTARY SCHOOL # 2

FINISH SCHEDULE BID SET - CONSTRUCTION DOCUMENTS

16 JAN 2018 - VCBO 17725

SECTION 09 0000 - PAGE 4

Page 13: ADDENDUM 001 E126 - Floor finish to be F7 and base to be B7.-Fire Riser E131- Noth and West wall finish to be W5.-Storage E140 - Gyp. wall finish at the stair to be W1. -Vestibule

Room Signs Match Door Frames - SW 7019 Gauntlet Gray

Hardwood Counter for Custodian Work Bench Clear Maple

Hardwood Coat Hook and Shelves at Classrooms Match Doors

(4) Fabric-wrapped Acoustical Panels at Main Entry from

left to right

LBI-Boyd, Basix 60 - L to R (1) 60475 Sienna, (2) 60752

Lilac, (3) 60175 Crystal Blue, (4) 60751 Terra

Exterior Monument Sign Match MBCI Colonial Red

Letters / Numbers - Clear Anodized

School name & address on building Letters / Numbers - Clear Anodized

JSD - BLUFFDALE ELEMENTARY SCHOOL # 2

FINISH SCHEDULE BID SET - CONSTRUCTION DOCUMENTS

16 JAN 2018 - VCBO 17725

SECTION 09 0000 - PAGE 5

Page 14: ADDENDUM 001 E126 - Floor finish to be F7 and base to be B7.-Fire Riser E131- Noth and West wall finish to be W5.-Storage E140 - Gyp. wall finish at the stair to be W1. -Vestibule

JSD – BLUFFDALE ELEMENTARY #2 26 JAN 2018 - VCBO 17725

IRRIGATION SYSTEM BID SET – CONSTRUCTION DOCUMENTS - ADD 001 SECTION 32 8423 – PAGE 1

SECTION 32 8423

IRRIGATION SYSTEM

PART 1 - GENERAL

1.1 RELATED DOCUMENTS A. Drawings including irrigation notes on plans and general provisions of the Contract, including

General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. Conduit and line voltage power to controller(s) shall conform to requirements of Division 16 Electrical Section.

1.2 SUMMARY A. This Section includes trenching, piping, valves, connection to culinary water system, backflow

preventer, flow sensor jumbo boxes, sprinklers, patching, repairing, specialties, controls, grounding grid, telecommunication lines and wiring for fully operational automatic-control irrigation system, complete.

1.3 DEFINITIONS A. Laterals/Circuit Piping: Down stream from control valves to sprinklers, specialties, and drain

valves. Piping is under pressure during flow. B. Drain Piping: Downstream from circuit-piping drain valves. Drain piping is not under pressure. C. Irrigation Main Piping: Downstream from point of connection to water distribution piping to, and

including, control valves. Piping is under water-distribution-system pressure.

1.4 PERFORMANCE REQUIREMENTS A. Design 100 percent water-coverage irrigation system for all irrigated areas indicated. B. Location of Piping, Sprinklers and Specialties: Design location is diagrammatic and only

approximate. Make adjustments necessary as directed or deemed necessary for symmetrical spacing to avoid plantings or obstructions such as utilities, boxes, signs and light standards. Maintain 100 percent water coverage of areas indicated.

C. Minimum Working Pressures: The following are pre-design minimum pressure requirements for

piping, valves, and specialties, all to be confirmed and restated on plans at time of distribution:

1. Irrigation Main Piping and Circuit Piping: 90 PSI at P.O.C., 500 under each Falcon series rotor head, 45 PSI under each 5000 series rotor head, 30 PSI under each fixed spray head.

1.5 SUBMITTALS (Electronic only if possible) A. Product Data: Include pressure ratings, sizes, dimensions, rated capacities, and settings of

selected models specified and or drawn for the following:

1. General-duty valves controlling zones. 2. Specialty valves controlling manifolds and connection to secondary water service . 3. Point of Connection, BFP, Control-valve vaults (conc.) and valve boxes. 4. Sprinklers, filters, and other required devices.

Page 15: ADDENDUM 001 E126 - Floor finish to be F7 and base to be B7.-Fire Riser E131- Noth and West wall finish to be W5.-Storage E140 - Gyp. wall finish at the stair to be W1. -Vestibule

JSD – BLUFFDALE ELEMENTARY #2 26 JAN 2018 - VCBO 17725

IRRIGATION SYSTEM BID SET – CONSTRUCTION DOCUMENTS - ADD 001 SECTION 32 8423 – PAGE 2

5. Irrigation specialties, grounding rod grids (show location to be placed), etc . 6. Controllers. Include wiring diagrams for phone and power cables, complete. 7. Control and telecommunication cables. Include splice kits, outlets, connections and conduit.

B. Operation and Maintenance Data: For irrigation systems, to include in emergency, operation, and

maintenance manuals. In addition to items noted on drawings include data for the following:

1. Automatic-control valves. 2. Sprinklers. 3. Controllers. 4. Filter and flushing devices 5. Backflow prevention devices..

1.6 QUALITY ASSURANCE A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,

Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for intended use.

B. The system has been designed with the intent to meet all existing codes. Contractor/Installer shall

verify compliance with applicable codes and install in accordance with codes and guidelines set forth by manufacturers of the applicable products specified. Discrepancies shall be rectified as a part of this contract work and noted on record drawings.

1.7 DELIVERY, STORAGE, AND HANDLING A. Deliver piping with factory-applied markings and end caps. Maintain end caps through shipping,

storage, and handling to prevent pipe-end damage and to prevent entrance of dirt, debris, and moisture.

B. Store plastic piping protected from direct sunlight. Support to prevent sagging and bending.

1.8 PROJECT CONDITIONS A. Interruption of Water Service: Do not interrupt water service to facilities or landscape areas

occupied by Owner or others unless permitted under the following conditions and then only after arranging to provide temporary water service according to requirements indicated:

1. Notify Owner no fewer than 2 days in advance of proposed interruption of water service. 2. Do not proceed with interruption of water service without Owner’s written permission. 3. Maintain viability and survivability of all plant materials while new construction is underway.

PART 2 - PRODUCTS

2.1 MANUFACTURERS A. In other Part 2 articles where titles below introduce lists, the following requirements apply to product

selection: 1. Manufacturers: Subject to compliance with requirements, provide products by the

manufacturers noted in the schedules and on the drawings or approved equal or equivalent substitutions.

Page 16: ADDENDUM 001 E126 - Floor finish to be F7 and base to be B7.-Fire Riser E131- Noth and West wall finish to be W5.-Storage E140 - Gyp. wall finish at the stair to be W1. -Vestibule

JSD – BLUFFDALE ELEMENTARY #2 26 JAN 2018 - VCBO 17725

IRRIGATION SYSTEM BID SET – CONSTRUCTION DOCUMENTS - ADD 001 SECTION 32 8423 – PAGE 3

PART 3 - EXECUTION

3.1 EARTHWORK A. Warning Tape: Install warning tape directly above all main line piping, 18 inches below finished

grades, except 6 inches below sub grade under new pavement or/ and slabs. Warning tapes are not required on lateral and spray head zones however accurate piping installation layout shall be reflected on as built plans . Install piping and wiring in sleeves under sidewalks, roadways, parking lots, and railroads.

1. Install piping sleeves by boring or jacking under existing paving if possible. 2. Install power wire and control wires in location(s) convenient to Contractor and acceptable to

District and Landscape Architect. 3. Power wire and control wires shall not be contained in the same conduit.

B. Drain Pockets and Valve Boxes: Excavate to sizes indicated. Backfill with cleaned gravel or

crushed stone. Place a sheet of asphalt-saturated felt or drain fabric at 6-8 inches below valve or drain and cover with washed gravel or crushed stone. Drawing detail may or may not reflect this directive.

C. Master control valve(s), Flow Control(s), etc. at the point of connection shall be housed in Jumbo

Valve Boxes or vault(s) of sufficient length, width, and depth to meet servicing and maintenance requirements. Submit detailed shop drawings for approval.

D. Provide minimum cover over top of underground piping according to the following:

1. Irrigation Main Piping: Minimum depth of 36 inches below finished grade.

2. Circuit Piping: 24" below finished grade rotor heads and 18" below for spray heads.

3. Drain Piping: as detailed.

4. Sleeves: as drawn, noted or detailed. Verify sleeving location needs by on-site visit.

3.2 PREPARATION A. Set stakes/flags and/or string-chalk lines to identify locations of proposed irrigation system

components to verify distances in field against distances shown on plan prior to any excavating. Identify field discrepancies with Landscape Architect and Owners representative for resolution and reconfigure as directed by Landscape Architect if field conditions require it.

B. Before any digging begins, obtain Landscape Architect's approval of each trench location(s),

precise location(s) of intended valve box(s) and location(s) of each head with correct placement or spacing before excavation. Flag, stake or paint as needed for approval. See drawing notes regarding field required changes expected of contractor.

C. Obtain District Inspectors approval of depths, components, backfill procedures including

compaction, lifts and materials before covering any piping or backfilling any trench.

3.3 PIPING APPLICATIONS A. Install components having pressure rating equal to or greater than system operating pressure. B. Piping in control-valve boxes and aboveground may be joined with flanges instead of joints

indicated. This pertains to backflow preventors and large gate valves etc. to aid in making connections or when flanged devices are present.

C. Sleeves under existing and proposed pavement: Schedule 40 PVC pipe sized to accommodate

intended piping and wiring; and socket fittings; and solvent-cemented joints.

Page 17: ADDENDUM 001 E126 - Floor finish to be F7 and base to be B7.-Fire Riser E131- Noth and West wall finish to be W5.-Storage E140 - Gyp. wall finish at the stair to be W1. -Vestibule

JSD – BLUFFDALE ELEMENTARY #2 26 JAN 2018 - VCBO 17725

IRRIGATION SYSTEM BID SET – CONSTRUCTION DOCUMENTS - ADD 001 SECTION 32 8423 – PAGE 4

D. All PVC pipe shall be rated ASTM D 1784 or 1785. E. Minimum recommended standards for PVC pipe: Schedule 40 for sizes 3/4” through 4” on lateral

lines Class 200 for sizes 3” and up on main line. Note: 1/2” PVC pipe is not allowed anywhere.

1. Maximum flow velocity in any pipe shall not exceed five feet per second; changes to piping to have friction loss/velocity calculated by contractor and approved by Landscape Architect.

F. All piping under hardscape shall be contained in sleeving separate from wire sleeving. Use multiple

sleeves as needed. Sleeving locations are generally noted but shall be expected under every run under paving without exception.

G. All piping will be capable of winterization by air blowout. Manual drains may be used on main line

pipe applications and shall include keys, and markers as needed. H. Minimum pipe depths: lateral pipe serving spray heads: 18” cover, lateral pipe serving rotor or

impact heads: 24” cover, and all main lines 36” cover, wire sleeving: Minimum 18” cover.

1. All piping will be backfilled with clean rock free material, settled and compacted to proper finish grade. Existing trench material may be screened to meet complete rock free condition or import rock free bedding material. Embedding materials shall be 2 x the pipe diameter surrounding the pipe.

I. All fittings shall be installed according to manufacturer specifications.

1. All PVC main and lateral lines shall use Schedule 80 threaded fittings. 2. Push-on ductile iron or mechanical joint cast iron fittings shall be used on gasketed 3”and

larger main lines. 3. Proper thrust blocking shall be installed on all fittings 3” and larger at all horizontal and

vertical changes in direction without exception; complete and installations shall be inspected by district inspector before covering.

3.4 VALVE APPLICATIONS A. Underground, Shutoff-Duty Valves: Use the following:

1. NPS 2DN 50 and Smaller: Curb stop with tee head, curb-stop service box, and shutoff rod.

2. NPS 3DN 80 and Larger: AWWA cast-iron gate valve with elastomeric gaskets and stem nut, valve box, and shutoff rod.

B. Control Valves:

1. As reflected on schedule or noted. Detail drawing is diagrammatic so far as actual valves or

size is shown. C. Drain Valves:

1. NPS 1/2 and NPS 3/4DN 15 and DN 20: Automatic drain valves under separate box with

marker on lateral lines where conditions warrant. Note locations on as-built record drawings.

3.5 PIPING INSTALLATION A. Location and Arrangement: Drawings indicate diagrammatic locations and arrangements of

piping systems. Install piping parallel and adjacent two walks, curbs or drives. Cluster manifolds from one to two valves in large Jumbo boxes that will still allow access and servicing of valves without having to remove the box. Locate boxes immediately next to walks or drives for

servicing without getting wet when circuits are open. Locations are generally shown on plans.

Page 18: ADDENDUM 001 E126 - Floor finish to be F7 and base to be B7.-Fire Riser E131- Noth and West wall finish to be W5.-Storage E140 - Gyp. wall finish at the stair to be W1. -Vestibule

JSD – BLUFFDALE ELEMENTARY #2 26 JAN 2018 - VCBO 17725

IRRIGATION SYSTEM BID SET – CONSTRUCTION DOCUMENTS - ADD 001 SECTION 32 8423 – PAGE 5

The Contractor shall coordinate actual placement with District Inspector and Landscape Architect and have approved prior to excavation.

B. Install piping at minimum uniform slope of 0.5 percent down toward drain valves. C. Install piping free of sags and severe bends imposing stress on pipes. D. Install groups of pipes and boxes parallel to each other with all pipe spaced to permit valve

servicing. E. Install fittings for changes in direction and branch connections with room in box(es) for servicing

valves and fittings without having to remove box(es). F. Install unions adjacent to valves and to final connections to other components with NPS 2 DN 50 or

smaller pipe connection. G. Install flanges adjacent to valves and to final connections to other components with NPS 2-1/2

DN 65 or larger pipe connection. H. Install dielectric fittings to connect piping of dissimilar metals when conditions require it. I. Lay piping on solid subbase, uniformly sloped without humps or depressions. J. Install PVC piping in dry weather when temperature is above 40 deg F 5 deg C. Allow joints to cure

at least 24 hours at temperatures above 40 deg F 5 deg C before testing unless otherwise recommended by manufacturer.

K. Install water regulators with shutoff valve and strainer on inlet and pressure gage on outlet. Install

shutoff valve on outlet. Pressure regulation devices will be installed to allow entire system including

all remote control valves and all sprinkler heads to operate at optimum pressure designated by product manufacturer. Pressure regulation devices shall include one or all of the following as field requirements deem necessary:

1. --pressure regulation valve at main line POC, 2. --pressure regulation device on/at remote control valve, 3. --pressure regulation device on individual sprinkler heads. 4. --Note: Note brand size and locations of selected device(s) on as built record drawings.

L. Water Hammer Arresters: If determined to be needed in field, install between connection to

building main and circuit valves in valve box.

3.6 JOINT CONSTRUCTION AND THRUST BLOCKING A. Refer to drawings and notes for basic pipe joint construction.

3.7 VALVE INSTALLATION A. Stop and Waste at Point of Connection tee shall be in concrete vault with meter as part of general

contract. B. Control Valves: Install in multiples where feasible fitted one or two in a control-valve box(es) of

sufficient size to allow fully servicing and removal of valves without removing boxes. C. Drain Valves: Install in >12" dia. box(es) with appropriate rubber covered valve markers. D. Air Relief Valves: Install the air relief valve(s) at all high points and at all dead ends in the main

lines as required dictated by topography encountered at time of installation.

Page 19: ADDENDUM 001 E126 - Floor finish to be F7 and base to be B7.-Fire Riser E131- Noth and West wall finish to be W5.-Storage E140 - Gyp. wall finish at the stair to be W1. -Vestibule

JSD – BLUFFDALE ELEMENTARY #2 26 JAN 2018 - VCBO 17725

IRRIGATION SYSTEM BID SET – CONSTRUCTION DOCUMENTS - ADD 001 SECTION 32 8423 – PAGE 6

3.8 SPRINKLER INSTALLATION A. Flush circuit piping with full head of water and install sprinklers after hydrostatic test is completed. B. Install sprinklers heads high to establish lawns if applicable then reset to manufacturer's

recommended heights. C. Locate part-circle sprinklers to maintain a minimum distance of 4 inches from walls and 2 inches

from other boundaries, unless otherwise indicated. Set to conform to surrounding walks, drives, curbs and grades, etc. Patterns of spray shall be accurately adjusted before final walk through and punch lists are prepared. See penalty stipulation for calling prematurely for final inspection.

3.9 AUTOMATIC-CONTROL SYSTEM INSTALLATION A. Central Control Unit: Provide and install the specified CCU, wall mounted adjacent to the

controller. Power and Cable to controllers to be coordinated between Irrigation contractor and electrical contractor to make system complete in conduit mounted per Division 16 electrical requirement.

B. Installation of control cable(s) may be in the same trench(s) as irrigation piping and at least 2 inches

50 mm below or besides piping. See requirements for wire in separate conduits elsewhere. Provide conductors of size not smaller than recommended by controller manufacturer. Install cable in separate sleeve under paved areas if irrigation piping is installed in sleeve.

C. Provide and install “an extra common and two extra control” wires to each of the farthest manifold

locations on main lines for future use by District in the event of wire failure or additional need. Location(s) may or may not be noted on drawing. Coordinate this with the Inspector and Landscape Architect at preconstruction meeting.

D. Controller wiring at outside exposure shall be contained in steel rigid conduit. Use EMT conduit for

inside installations. Sweep ell's to be used on all conduit. All work pr. Division 16 Specification. E. Provide and install the specified controllers, wall mounted, including an electrical gutter box of the

required size to house all valve wiring and misc. equipment. The power to the controller is to be provided by the General or Electrical contractor. Mount the controllers as directed by Owner representative. Connect the controller to the master valve, control valves and relays and make all required connections for complete operation of the system. Grounding grids pr. manufacturers requirements and controller signals to valves shall be fully operational prior to punch list inspection without exception.

3.10 CONNECTIONS AND ELECTRICAL A. Drawings indicate intended general arrangement of piping, fittings, and specialties. B. Tighten electrical connectors and terminals according to manufacturer's published torque-tightening

values. If manufacturer's torque values are not indicated, use those specified in UL 486A and UL 486B.

C. Power wire and control wire shall not be contained in the same conduit.

1. Remote control valve wiring shall be a minimum of 14 gauge, UF UL or PE UL rated. 2. All wire connections shall be made with watertight connectors and contained in valve box. 3. Provide slack/extra control wire at all change in directions. 4. Provide 36” of slack wire at each remote control valve in valve box. 5. Remote control valve wiring shall be installed with the main line pipe where possible, taped to

the underside of the mainline pipe at regular intervals.

Page 20: ADDENDUM 001 E126 - Floor finish to be F7 and base to be B7.-Fire Riser E131- Noth and West wall finish to be W5.-Storage E140 - Gyp. wall finish at the stair to be W1. -Vestibule

JSD – BLUFFDALE ELEMENTARY #2 26 JAN 2018 - VCBO 17725

IRRIGATION SYSTEM BID SET – CONSTRUCTION DOCUMENTS - ADD 001 SECTION 32 8423 – PAGE 7

6. Remote control valve wiring shall have separate colors for common, control, and spare. 7. Provide minimum of one spare wire for every five remote control valves in system. Spare

wire shall be available at all valve manifolds or clusters. All spare wires shall be “home run” to the respective controller. End run common.

8. All wiring under hardscaping shall be contained in sleeving. Sweep ell's meeting inspectors approval and code to be used on all conduit.

9. All electrical work to conform to code and District standards.

3.11 LABELING AND IDENTIFYING A. Equipment Name plates and Signs: Install engraved plastic-laminate equipment nameplates and

signs on each automatic control valve on box lid. Accurately reference valves and zone location descriptions and numbers to inside of controllers.

1. Text: In addition to identifying unit, distinguish between multiple units, inform Owners

Operator of operational requirements, indicate safety and emergency precautions, and warn of hazards and improper operations.

B. Warning Tapes: Arrange for installation of continuous, underground, detectable warning tape 12"

below surface over underground piping (Main lines) and Rotor/Impact circuits, during backfilling of trenches. Coordinate placement with District Inspectors.

3.12 FIELD QUALITY CONTROL A. Manufacturer's Field Service: Engage a factory-authorized service representative to inspect, test,

and adjust clock and MAXI computer controller components and equipment installation, including connections and to assist in field testing. Report results in writing to the Owner and the Landscape Architect.

B. Perform the following field tests and inspections and prepare test reports:

1. Leak Test: After installation, charge system and test for at 150 PSI for leaks after 2 hours.

Repair leaks and retest until no leaks exist. Do under District Inspector’s observation. 2. Operational Test: After electrical circuitry has been energized, operate controllers and

automatic control valves to confirm proper system operation. 3. Test and adjust controls and safeties. Replace damaged and malfunctioning controls and

equipment. 4. Trench compaction tests: Minimum 95% compaction verified by testing service in writing.

Testing service procured by Contractor through American Testing Services, Inc. (801-487-1333) and paid for by District. Contractor to provide copies of tests to Landscape Architect and District Inspector. Scarify top surface of compacted trenching prior to topsoil operation for proper soil bond. See Lawn Preparation sections.

C. Remove and replace units and retest and reinspect as specified above.

3.13 STARTUP SERVICE A. Engage a factory-authorized service representative to perform startup service at Contractor’s

expense. Verify that electrical wiring connection, installation, control system(s), data transmission, etc. functions and complies with manufacturer's submittal and installation requirements, complete.

B. Verify that controllers are installed, connected and operating according to the manufacturer=s

documents. Complete startup checks according to manufacturer's written instructions C. Provide comprehensive training to Custodian and other District personnel with vested interest in this

project for the ongoing operation of this system to the District’s satisfaction. Obtain a written sign-off

Page 21: ADDENDUM 001 E126 - Floor finish to be F7 and base to be B7.-Fire Riser E131- Noth and West wall finish to be W5.-Storage E140 - Gyp. wall finish at the stair to be W1. -Vestibule

JSD – BLUFFDALE ELEMENTARY #2 26 JAN 2018 - VCBO 17725

IRRIGATION SYSTEM BID SET – CONSTRUCTION DOCUMENTS - ADD 001 SECTION 32 8423 – PAGE 8

of satisfactory training for Contractor files and forward a copy to Landscape Architect.

3.14 ADJUSTING A. Adjust sprinklers so they will be accurately aimed, directed and set flush and perpendicular with

finish grade when settled to the satisfaction of District personnel and landscape architect and prior to punch list inspection.

B. Adjust automatic control valves to provide flow rate of rated operating pressure required for each

sprinkler circuit for optimum operation to the satisfaction of District personnel and landscape architect and prior to punch list inspection.

C. Adjust all settings of nozzles, heads, controllers, regulators, valves, etc. on this system to their

correct position and pattern to the satisfaction of District personnel and landscape architect and prior to punch list inspection.

D. Establish or re-establish lawn areas around each head where washing or erosion has occurred to

conform to intended grades with imported soil and sod as needed. Seeding will not be permitted as a re-establishment medium on this project. Note any critical deadline requirements for completion, coordinate with General Contractor.

E. Adjust grades surrounding all valve boxes and drain markers to account for any shifting, settling or

disturbance by traffic. All boxes shall be flush with ‘finish’ grades and slope gradually, evenly and consistently with surrounding grades. Abrupt and uneven slopes will not be permitted and the installation will be rejected.

3.15 CLEANING A. Flush dirt and debris from piping before installing sprinkler heads, filters, nozzles and other devices. B. Patch and repair all disturbed landscape, pavement, or site/structural surfaces as needed to make

project complete at no added cost to Owner.

3.16 DEMONSTRATION A. Engage a factory-authorized service representative to train Owner's on-site maintenance personnel

to adjust, operate, and maintain controller and automatic control devices, sensors, monitors, computerization and valves.

B. When installation of the entire mainline or portion of the mainline is completed and prior to

backfilling mainline trenches, the system shall be hydrostatically tested at 150 psi and proven tight at this pressure for two hours under the observation of District Inspector(s). All defects disclosed by this test or otherwise, shall be made good, or the work replaced without additional cost to the Owner. Upon satisfactory completion of the hydrostatic pressure test, done in the presence of District inspectors, and installation of all thrust blocking, the trenches may be back filled. Back fill to finish grade and thoroughly compact to 95% and test as specified.

3.17 SUBSTANTIAL COMPLETION A. When the project is substantially complete, the Contractor will make a request for an inspection.

Written notice requesting such inspections shall be submitted to the District Inspector at least three (3) days prior to the anticipated inspection date. If the work is found to not be substantially complete and the inspection has been called for prematurely the inspection will be back-charged and billed to the Contractor on an hourly basis. Note: this includes adjusting nozzles and spray pattern for underthrow or overthrow. A punch-list of the work found to be unsatisfactory will be furnished to the Contractor. After this list has been satisfactorily completed,

Page 22: ADDENDUM 001 E126 - Floor finish to be F7 and base to be B7.-Fire Riser E131- Noth and West wall finish to be W5.-Storage E140 - Gyp. wall finish at the stair to be W1. -Vestibule

JSD – BLUFFDALE ELEMENTARY #2 26 JAN 2018 - VCBO 17725

IRRIGATION SYSTEM BID SET – CONSTRUCTION DOCUMENTS - ADD 001 SECTION 32 8423 – PAGE 9

the project can be accepted.

3.18 GUARANTEE A. The Contractor shall guarantee all workmanship, materials, fixtures and equipment covered under

this contract to be free from defects for a period of one (1) year from the date of substantial completion of the project and shall replace any part or parts found to be defective within the period of the guarantee without cost to the Owner. Such warrantee replacement when done which causes disturbance or damage to adjacent surfaces or materials shall also be prepared at no additional cost to Owner. A written guarantee containing the above items shall be prepared by and signed by the Contractor with triplicate copies to the Owner (2) and Landscape Architect (1).

3.19 RECORD DRAWINGS A. All deviations from plan layout shall be recorded on a daily basis on field drawings. That data shall

be indicated on the final “As-Built” or “Record Drawings”. The Contractor shall make an exact measured and dimensioned drawing showing locations of all boxes, connections, piping, wiring, control and quick coupler valves. Tie dimensions to permanent features such as structures. Electronic record drawings, schedules, and notes shall be prepared by the Contractor and approved by the Landscape Architect. Electronic copies of the irrigation plan for use in developing the record drawings may be requested and secured from the landscape architect at the completion of the project for the contractors use in preparing the electronic as-built plans. In-Progress check sets of the electronic record drawings shall be paper hard copies and submitted WITH THE REDLINED FIELD SET DRAWINGS to Landscape Architect for approval prior to submitting electronic copies on CD’s. Triplicate copies of all final record drawings (both electronic and hard copy formats) shall be submitted to the Landscape Architect with or prior to submittal of final billing.

B. Accurate as-built record drawings are imperative to the successful preparation of Water

Management Audit Documents that will be provided to the District by the Landscape Architect based on data from the Contractors As-Builts.

END OF SECTION

Page 23: ADDENDUM 001 E126 - Floor finish to be F7 and base to be B7.-Fire Riser E131- Noth and West wall finish to be W5.-Storage E140 - Gyp. wall finish at the stair to be W1. -Vestibule

JSD – BLUFFDALE ELEMENTARY #2 26 JAN 2018 - VCBO 17725

LANDSCAPING BID SET – CONSTRUCTION DOCUMENTS - ADD 001 SECTION 32 9000 - PAGE 1

SECTION 32 9000

LANDSCAPING PART 1 - GENERAL 1.1 THE REQUIREMENT

A. The CONTRACTOR shall perform all the landscaping and all appurtenant work, complete, in accordance with the requirements of the Contract Documents.

B. Scope of Work: Landscaping as referred to herein shall include, but not be limited to the

following work: soil preparation, installation of headers, weed control, finish grading, furnishing and installing plant materials, tree staking and tying, cleanup, maintenance, and guarantee.

C. The Section cross references the following sections:

1. Reference Standards 01095 2. Contractor Submittals 01300 3. Project Closeout 01700 4. Irrigation System 32 8423

1.2 REFERENCE SPECIFICATIONS, CODES, AND STANDARDS

A. Codes: All codes, as referenced herein, are specified in Section 01095 - Reference Standards.

B. Federal Specifications:

FS O-F-241 D Fertilizer, Mixed, Commercial

C. Commercial Standards

ANSI/ASTM D 422 Method for Particle-Size Analysis of Soils ANSI Z601 Nursery Stock American Association of Rules and Grading Provisions Nurserymen, Inc.

1.3 CONTRACTOR SUBMITTALS

A. General: The CONTRACTOR shall furnish a certificate with each delivery or bulk material delivery, stating source, quantity, and type of material. All materials shall conform to specification requirements. All certificates shall be delivered to the LANDSCAPE ARCHITECT (here in referred to as L.A.) at time of each delivery. All bulk delivered materials shall be delivered with level load volume plainly marked on the truck bed.

B. Literature on fertilizers, Soil Pep, shredded bark mulch, tree anchors, anti-desiccant spray,

peat moss, tree wrap, etc. shall be submitted as specified in Section 01300 - Contractor Submittals

1.4 QUALITY ASSURANCE

A. Installer's Field Supervision: Contractor shall maintain an experienced full-time foreman or supervisor on Project site when planting is in progress.

B. Topsoil Analysis: Furnish soil analysis by a qualified soil-testing laboratory meeting or exceeding

soil requirements provided herein.

Page 24: ADDENDUM 001 E126 - Floor finish to be F7 and base to be B7.-Fire Riser E131- Noth and West wall finish to be W5.-Storage E140 - Gyp. wall finish at the stair to be W1. -Vestibule

JSD – BLUFFDALE ELEMENTARY #2 26 JAN 2018 - VCBO 17725

LANDSCAPING BID SET – CONSTRUCTION DOCUMENTS - ADD 001 SECTION 32 9000 - PAGE 2

C. General: All plants furnished by the CONTRACTOR shall be true to type or name as shown in the Contract Documents and shall be tagged in accordance with the standard practice recommended by the Agricultural Code of the State of Utah; however, determination of plant species or variety will be made by the L.A..

D. All plants shall comply with Federal and State laws requiring inspection for plant diseases and

infestations. Inspection certificates required by law shall accompany each shipment of plants, and certificates shall be delivered to the L.A..

E. All inspections herein specified will be made by the L.A. or its representative. The

CONTRACTOR shall request inspection at least 72 hours in advance of the time inspection is required. Inspection will be required on the following stages of the WORK:

1. During soil preparation. 2. When finish grading has been completed. 3. When trees, shrub and perennials are spotted for planting, but before planting holes

have been excavated.

4. When all specified work, except the maintenance period has been completed.

5. Final inspection at the completion of the maintenance period. 6. Final inspection at the completion of the one year warranty walk through.

F. Plants shall be subject to inspection and approval or rejection by the L.A. upon delivery to the

site and at any time before or during progress of the WORK and according to:

1. Quantity, quality, size, and variety;

2. Ball and root condition; and

3. Latent defects and injuries resulting from handling, disease, and insects.

G. Plants approved at pre-planting inspection shall still be subject to rejection during planting if found to be below Specifications.

H. Rejected plants shall be identified in an obvious manner, removed from the site and replaced

with acceptable equals.

I. Plants shall have been grown in nurseries which have been inspected by the governing authorities. Inspection of plant materials required by City, County, State, or Federal authorities shall be the responsibility of the CONTRACTOR, who shall have secured permits or certificates prior to delivery of plants to site.

1.5 CLEANUP

A. Upon completion of all planting operations, the portion of the project site used for a work or storage area by the CONTRACTOR shall be cleaned of all debris, superfluous materials, and equipment. All such materials and equipment shall be entirely removed from the project site as specified in Section 01700 - Project Closeout.

B. All walks or pavement shall be swept or washed clean upon completion of the WORK of this

Section.

Page 25: ADDENDUM 001 E126 - Floor finish to be F7 and base to be B7.-Fire Riser E131- Noth and West wall finish to be W5.-Storage E140 - Gyp. wall finish at the stair to be W1. -Vestibule

JSD – BLUFFDALE ELEMENTARY #2 26 JAN 2018 - VCBO 17725

LANDSCAPING BID SET – CONSTRUCTION DOCUMENTS - ADD 001 SECTION 32 9000 - PAGE 3

C. During the entire Contract period, plant containers that have been cut or removed from plant

materials shall be removed from the project site daily, in accordance with the provisions for maintenance and guarantee as specified in Section 01700 - Project Closeout.

1.6 MAINTENANCE OF LANDSCAPE PLANTING PRIOR TO ACCEPTANCE OF PROJECT

A. General: The CONTRACTOR shall be responsible for protecting, watering, and maintaining all planting and irrigation systems until final acceptance of all work under the contract.

B. At time of acceptance of the complete project, the lawn shall be totally established with no

bare spots, mowed a minimum of 3 times, and the grass shall be at least 1-1/2 to 2 inches in height.

C. Watering: Trees and shrubs shall be thoroughly soaked after planting and provided with

additional water at intervals as necessary to provide for good health and growth of the planting.

D. Upon completion of lawn sodding, the entire area shall be soaked to saturation by a fine

spray. The new planting shall be kept watered by the sprinkling system existing on the site during dry weather or whenever necessary for proper establishment of the lawn. Care shall be taken to avoid excessive washing or puddling on the surface and any such damage caused thereby shall be repaired by the CONTRACTOR at its own expense.

E. Protection: The CONTRACTOR shall provide adequate protection to all newly planted areas

including the installation of approved temporary fences to prevent trespassing and damage, as well as erosion control, until acceptance.

F. The CONTRACTOR shall replace any materials or equipment it has damaged or which has

been damaged by its employees or subcontractors.

G. Partial utilization of the project shall not relieve the CONTRACTOR of any of the requirements contained in the Contract Documents.

H. Mowing of Lawn Areas: First mowing of lawn areas shall begin as soon as the grass has

reached a height of 3 inches and subsequent mowing shall be at least once a week, or as often as necessary to maintain all lawn areas at a uniform height of 1-1/2 to 2 inches.

I . All lawns shall be fertilized every 3 weeks with 16-8-8 commercial fertilizer at label rate for the

first 7 weeks and fertilized thereafter once each 5 months prior to acceptance.

J. Plants shall be maintained in a vigorous, thriving condition by watering, cultivating, weeding, pruning, spraying, and other operations necessary. No trees or shrubs will be accepted unless they are healthy and show satisfactory foliage conditions.

K. All planted areas shall be cultivated at least every 2 weeks and raked smooth, to present a

neat appearance, and additional mulch shall be added where necessary.

L. Maintenance shall include, in addition to the foregoing, cleaning, edging, repairs to stakes, wire, and wrappings, the repair of erosion, and all other necessary work of maintenance. Sidewalks and other paved areas shall be kept clean while planting and maintenance are in progress.

M. Any and all sprinkler lines broken or disrupted during this construction shall be replaced to

proper working order prior to contract work and be acceptable to the OWNER. 1.7 FINAL INSPECTION AND GUARANTEE

Page 26: ADDENDUM 001 E126 - Floor finish to be F7 and base to be B7.-Fire Riser E131- Noth and West wall finish to be W5.-Storage E140 - Gyp. wall finish at the stair to be W1. -Vestibule

JSD – BLUFFDALE ELEMENTARY #2 26 JAN 2018 - VCBO 17725

LANDSCAPING BID SET – CONSTRUCTION DOCUMENTS - ADD 001 SECTION 32 9000 - PAGE 4

A. Inspection of work of lawns and planting will be made at conclusion of maintenance.

B. Written notice requesting inspection shall be submitted to the L.A. at least 72 hours prior to the anticipated inspection date.

C. Final acceptance of the WORK prior to guarantee period of the contract will be accepted

upon written approval by the L.A., on the satisfactory completion of all work, including maintenance, but exclusive of the replacement of plant material.

D. Any delay in the completion of any item of work in the planting operation which extends the

planting into more than one season shall extend the guarantee in accordance with the date of completion given above.

E. The CONTRACTOR shall replace, as soon as weather conditions permit, all dead plants and

all plants not in a vigorous, thriving condition which are noted at the end of the one year guarantee period.

F. Plants used for replacement shall be of the same size and variety specified in the plant list.

Plants shall be furnished, planted, staked, and mulched as specified.

G. All work done under this contract shall be left in good order to the satisfaction of the OWNER and the L.A. and the CONTRACTOR shall, without additional expense to the OWNER, replace any trees, shrubs, etc., which develop defects or die during the one-year guarantee period.

1.8 GUARANTEE FOLLOWING ACCEPTANCE OF PROJECT

A. General: The CONTRACTOR shall be responsible for a period of one year after date of acceptance of all work under the Contract, for all necessary plant or tree replacements. The CONTRACTOR shall provide a written guarantee to the OWNER from the landscaping subcontractor, embodying the provisions of this Section of the Specifications.

B. The WORK covered by the guarantee portions of these specifications consists of providing

all replacements of plants, labor, materials, equipment, and supplies and in performing all operations in connection with guarantees.

C. The CONTRACTOR shall clean-up and remove unused or waste materials from the site and

leave the area in a neat condition (satisfactory to the OWNER) whenever it performs work during the guarantee Period.

D. Final Inspection: The OWNER and CONTRACTOR shall make a final inspection at the end

of the one-year guarantee period. Any plants and materials found defective at time of final inspection shall be replaced within a time agreed upon by both parties. If it is too late in the planting season for replanting, the replacements shall be made during the next planting season even though such planting may run beyond the maintenance and correction period.

PART 2 -- PRODUCTS 2.1 GENERAL

A. All landscaping materials for soil conditioning, weed abatement, or planting shall be first- grade, commercial quality and shall have certificates indicating the source of material, analysis, quantity, or weight attached to each sack or container or provided with each delivery. Delivery certificates shall be given to the L.A. as each shipment of material is delivered. A list of the materials used, together with typical certificates of each material, shall be submitted to the L.A. prior to the final acceptance of the job.

Page 27: ADDENDUM 001 E126 - Floor finish to be F7 and base to be B7.-Fire Riser E131- Noth and West wall finish to be W5.-Storage E140 - Gyp. wall finish at the stair to be W1. -Vestibule

JSD – BLUFFDALE ELEMENTARY #2 26 JAN 2018 - VCBO 17725

LANDSCAPING BID SET – CONSTRUCTION DOCUMENTS - ADD 001 SECTION 32 9000 - PAGE 5

2.2 TERMINOLOGY AND QUALIFICATIONS

A. Provide plantings of sizes and grades complying with ANSI Z60.1 for type of plantings required.

B. Plants or plant material having characteristics not conforming to terms as defined will not be

accepted. The terms "plant material" or "plants" refer to all vegetation, whether trees, shrubs, ground cover, or herbaceous vegetation.

2.3 TOPSOIL

B. Imported topsoil shall be obtained from naturally drained areas and shall be fertile, friable loam suitable for plant growth. Topsoil shall be subject to inspection and approval at the source of supply and upon delivery and shall include an analysis from a qualified soils laboratory showing compliance with ideal specifications as shown herein.

C. The topsoil shall be of uniform quality, free from subsoil stiff or lumpy clay, hard clods,

hardpan, rocks, disintegrated debris, plants, roots, seeds, and any other materials that would be toxic or harmful to plant growth. Topsoil shall contain no noxious weeds or noxious weed seeds.

D. The topsoil shall contain at least 2 percent organic matter as determined by loss of weight

after ignition of dried (moisture-free) samples in accordance with current methods of the Association of Official Agricultural Chemists.

E. The acidity range of the topsoil shall be (pH 5.5 to pH 7.5). The salinity level shall be less

than 2 mmho/cm. F. The topsoil shall not exceed the ideal coarse fragment requirements as shown herein.

G. Clay shall not exceed 30 percent of the topsoil material.

2.4 FERTILIZER AND ADDITIVES

A. Fertilizer shall be furnished in bags or other standard containers with name, weight, and guaranteed analysis of contents clearly marked thereon.

B. Chemical fertilizers shall be a mixed commercial fertilizer conforming to FS O-F-241 D, Type

I, with percentages of nitrogen, phosphoric acid, and potash at 31-10-0. The combined N-P-K content shall be following percentages of total weight: 31 percent nitrogen 10 percent phosphoric acid and 0 percent potash and so forth. Fertilizers shall be uniform in composition, dry, and free flowing.

C. Tablets shall be 21 grams each 20-10-5 "Agriform," "Lesslie", or equal

A.5 MULCH

A. ‘Soil Pep’ mulch material shall be ‘Soil Pep’ as manufactured by Mountain West Bark Products, or equal.

B. Beef Hollow 1” to 3” crushed rock mulch as supplied by Staker Parsons in beds shall be washed, crushed mulch placed to an average depth of 4 inches.

C. Beef Hollow 4” to 6” crushed rock mulch as supplied by Staker Parsons in beds shall be

washed, crushed mulch placed to an average depth of 5 inches.

Page 28: ADDENDUM 001 E126 - Floor finish to be F7 and base to be B7.-Fire Riser E131- Noth and West wall finish to be W5.-Storage E140 - Gyp. wall finish at the stair to be W1. -Vestibule

JSD – BLUFFDALE ELEMENTARY #2 26 JAN 2018 - VCBO 17725

LANDSCAPING BID SET – CONSTRUCTION DOCUMENTS - ADD 001 SECTION 32 9000 - PAGE 6

2.6 PLANT MATERIALS

A. Plants shall meet requirements of the Contract Documents and shall be in accordance with the botanical names and applicable standards of quality, size, condition, and type. They shall be true to name, genera, species, and variety in accordance with reference publications.

B. Plant names are defined in "Standardized Plant Names" and "Bailey's Encyclopedia of

Horticulture." When a name is not found in either reference, the accepted name used in the nursery trade shall apply.

C. Plants shall be marked for identification. Each bundle of plants and at least 25 percent of

each species and variety of separate plants in any one shipment shall have legible labels securely attached before delivery to the site.

D. All trees and shrubs shall be measured while their branches are in their normal position.

Height and spread dimensions specified refer to the main body of the plant and not from branch or root tip to tip. No trees will be accepted with their leaders cut, or so damaged that cutting is necessary.

E. All plants shall be symmetrical and shall conform to the size, age, and condition as specified

on the plant list shown in the Contract Documents. Exceptions are as follows:

1. Plants larger than specified in the plant list may be used if approved by the L.A., but use of such plants shall not increase the contract price. If the use of larger plants is approved, the spread of roots or ball earth shall be increased in proportion to the size of the plant. Bare root plants furnished in size greater than specified shall be balled and burlapped when required by the L.A.

2. Where caliper or other dimensions of any plant materials are omitted from the Plant

List, it shall be understood that such plant materials shall be normal stock for type

F. Plants shall be of sound health, vigorous, and free from plant disease and shall be well-branched, shall have full foliage when in leaf, and shall have a healthy well-developed normal root system. Cold storage plants will not be accepted. Plants that are sensitive to shock from elevation change shall be grown at elevations close enough to site to alleviate any plant damage due to such change for at least 2 years.

G. Balled and burlapped (BB) plants shall have firm, natural balls of earth, or diameter not less

than that specified and of sufficient depth to include all the fibrous and feeding roots. No plant moved with a ball will be accepted if the ball is cracked or broken before or during plant operations, except on special approval of the L.A.

H. Roots or balls of all plants shall be adequately protected at all times from sun and drying

winds.

I. Plants (indicated to be in marked cans, pots, or other containers on the plant list) shall have been grown in the containers for a minimum of 6 months and a maximum of 2 years. Roots shall fill the containers but show no evidence of being or having been root bound.

J. Trees shall have straight trunks and all old abrasions and cuts shall be completely callused over. In no case shall trees be topped before delivery.

K. Plants shall have been transplanted or root-pruned at least once in the 2 years. Plants shall

not be pruned prior to delivery except as authorized by the L.A. 2.7 SOD GRASS

A. See Section 32 9200 – Lawns and Grasses.

Page 29: ADDENDUM 001 E126 - Floor finish to be F7 and base to be B7.-Fire Riser E131- Noth and West wall finish to be W5.-Storage E140 - Gyp. wall finish at the stair to be W1. -Vestibule

JSD – BLUFFDALE ELEMENTARY #2 26 JAN 2018 - VCBO 17725

LANDSCAPING BID SET – CONSTRUCTION DOCUMENTS - ADD 001 SECTION 32 9000 - PAGE 7

2.8 STAKING MATERIALS

A. Guying kits for trees will be Cable Guy (Alpine Nursery 1-800-356-6633) #CG-4000 and CG-800-T. Add extra hose where guy cable comes in contact with tree.

B. Hose for covering wire shall be new or used black or green 2-ply fiber-bearing garden hose,

not less than 2-inch inside diameter.

C. Wire for tree bracing and guying shall be double strand pliable No. 10-gage galvanized steel

wire or vinyl-coated steel wire. 2.9 MISCELLANEOUS

A. Anti-Desiccant: Water-insoluble emulsion, permeable moisture retarder, film forming, for trees and shrubs

B. Weed barrier: Dewitt 4.1 oz., Western Landscape Polyspun 3.5 oz. or approved equal

PART 3 -- EXECUTION 3.1 GENERAL

A. The landscape work shall not be performed at any time when it may be subject to damage by climatic conditions.

B. The CONTRACTOR shall carefully scale or otherwise verify all dimensions in the Contract

Documents. Dimensions and plant locations shown shall be coordinated with L.A. and final location shall be site-oriented by the planter and L.A. Any discrepancies or inconsistencies discovered shall be brought to the attention of the L.A.

C. In case of conflict between the plant list totals and total plant count of the Contract

Documents, the CONTRACTOR shall provide the higher number of plants.

D. Delivery of materials may begin only after samples and tests have been approved by the L.A. All materials furnished for the work shall be not less than the approved sample.

E. Substitutions for the indicated plant materials may be permitted pursuant to the Contract

Documents.

F. The CONTRACTOR shall provide temporary fencing, barricades, covering, or other protections to preserve existing landscaping items indicated to remain and to protect the adjacent properties and other structures when they may be damaged by the landscape work.

G. Waste materials shall be removed and disposed of off the OWNER's property, unless

otherwise indicated.

H. It shall be the responsibility of the CONTRACTOR to avail itself of any information regarding utilities which are in the area of work and to prevent damage to the same. The CONTRACTOR shall provide protection to the utilities as necessary.

I. Burning of combustible materials on the site shall not be permitted.

J. The CONTRACTOR shall provide protection to structures, sidewalks, pavements, and other

Page 30: ADDENDUM 001 E126 - Floor finish to be F7 and base to be B7.-Fire Riser E131- Noth and West wall finish to be W5.-Storage E140 - Gyp. wall finish at the stair to be W1. -Vestibule

JSD – BLUFFDALE ELEMENTARY #2 26 JAN 2018 - VCBO 17725

LANDSCAPING BID SET – CONSTRUCTION DOCUMENTS - ADD 001 SECTION 32 9000 - PAGE 8

facilities in areas of work which are subject to damage during landscape work. Open excavations shall be provide with barricades and warning lights which conform to the requirements of governing authorities and the State's OSHA safety requirements from dusk to dawn each day and when needed for safety.

K. Planting areas include all areas to be landscaped unless, specified or shown, otherwise.

3.2 SOIL PREPARATION

A. The landscape work shall not begin until all other trades have repaired all areas of settlement, erosion, rutting, etc., and the soils have been re-established, recompacted, and refinished to finish grades. The L.A. shall be notified of all areas which prevent the landscape work from being executed.

B. Areas requiring grading by the landscaper including adjacent transition areas shall be

uniformly level or sloping between finish elevations to within 0.10-ft above or below required finish elevations.

C. The landscape work shall not proceed until after walks, curbs, paving, edging, and irrigation

systems are in place. The contract operations shall be completed to a point where the landscape areas will not be disturbed. The subgrade shall be cleaned free of waste materials of all kinds.

D. During grading waste materials in the planting areas such as weeds, rocks (1.5 inches and

larger) building materials, rubble, wires, cans, glass, lumber, sticks, etc., shall be removed from the site. Weeds shall be dug out by the roots.

E. Fertilizers, additives, seed, peat, etc. subject to moisture damage shall be kept in a

weatherproof storage place in such a manner that they will be kept dry.

F. After removal of waste materials the planting areas subgrade shall be scarified and pulverized to a depth of not less than 6 inches and all surface irregularities below the cover of topsoil removed.

G. Finish subgrade and topsoil placement and grading shall consist of:

1. Preparing subgrade by rough grading and removing all irregularities and debris, then till and scarify subsoil to a depth of 6 inches before placing topsoil. Dig subgrade down as required in shrub beds for the placement of topsoil. Provide laser leveling on large flat areas to create a uniform level subgrade.

2. Incorporating all soil additives and fertilizers into the topsoil before placing it into the

lawn and shrub areas.

2. Placing 4 inches of topsoil over all lawn and 12 inches in shrub beds unless shown or specified otherwise on plans. Subgrade soil shall be in a loosened and rough surface finish before topsoil is placed over subgrade. (Sub-grade surface shall not be smooth, but a rough surface shall exist for a transition zone of topsoil to subsoil.) If areas of subgrade become compacted before topsoil is placed, subgrade shall be tilled again before topsoil placement.

3. Tilling lawn and planting area subsoils and top soils that are compacted.

5. After tilling, bring areas to uniform grades by floating and/or hand raking. In large

open level areas, perform laser leveling to create uniform level areas.

6. Making minor adjustment of finish grades as directed by the landscape architect or owner.

Page 31: ADDENDUM 001 E126 - Floor finish to be F7 and base to be B7.-Fire Riser E131- Noth and West wall finish to be W5.-Storage E140 - Gyp. wall finish at the stair to be W1. -Vestibule

JSD – BLUFFDALE ELEMENTARY #2 26 JAN 2018 - VCBO 17725

LANDSCAPING BID SET – CONSTRUCTION DOCUMENTS - ADD 001 SECTION 32 9000 - PAGE 9

7. Removing waste materials over 1.5" in size such as stones, roots, or other

undesirable foreign materials and finish raking, dishing, dragging, and smoothing soil ready for planting.

8. No grading or soil placement shall be undertaken when soils are wet or frozen

H. Any unusual subsoil condition that will require special treatment shall be reported to the L.A.

I. Topsoil shall be uniformly distributed over all areas where required. Subgrade and topsoil

shall be damp and free from frost.

J. Surface drainage shall be provided as shown by molding the surfaces to facilitate the natural run-off of water. Low spots and pockets shall be filled with topsoil and graded to drain properly.

K. Finish grade of all planting areas shall be 2 inches below, 3” below and 1 ½” below finish

grades of adjacent pavement of any kind for sod areas, shrub areas and perennial areas respectively.

3.3 DELIVERY, STORAGE, AND HANDLING OF PLANT MATERIALS

A. No plants other than the required samples shall be dug or delivered to the site until the required inspections have been made and the plant samples are approved

B. Plants shall not be pruned prior to delivery except upon approval by the L.A..

C. Plant material shall be planted on the day of delivery if possible. The CONTRACTOR shall

protect the stock in a temporary nursery at the project site where it shall be protected from sun and drying winds and shall be shaded, kept moist, and protected with damp soil, moss, or other acceptable material. Plants shall be planted within 2 days after delivery.

D. All balled and burlapped plants which cannot be planted immediately in delivery shall be set

on the ground and shall be well protected with soil, wet moss, or other acceptable material.

E. No plants shall be bound with wire or rope at any time so as to damage the bark or break branches.

F. Plants shall not be picked up or moved by the stem or branches, but shall be lifted and

handled from the bottom of the ball or container. Plants with balls cracked or broken before or during planting operations will not be accepted and shall be immediately removed from the site.

3.4 TREE AND PLANT LOCATIONS

A. The CONTRACTOR shall locate and stake all tree and shrub locations and have the locations approved by the L.A. before starting excavation for same. The plant locations shall be observed, and their locations shall be adjusted as directed by L.A. before final approval. This shall occur in two (2) or less site visits. Additional visits required to review planting locations will be back charged to the contractor.

B. No trees shall be located closer than 72 inches to structures unless otherwise shown.

Ground covers and shrubs shall be planted as shown. 3.5 PLANT PITS

A. Plant pits, centered on location stakes, shall be excavated circular pits with vertical sides and flat or saucer shape bottom in accordance with the following sizes unless shown otherwise.

Page 32: ADDENDUM 001 E126 - Floor finish to be F7 and base to be B7.-Fire Riser E131- Noth and West wall finish to be W5.-Storage E140 - Gyp. wall finish at the stair to be W1. -Vestibule

JSD – BLUFFDALE ELEMENTARY #2 26 JAN 2018 - VCBO 17725

LANDSCAPING BID SET – CONSTRUCTION DOCUMENTS - ADD 001 SECTION 32 9000 - PAGE 10

1. Tree pits shall be at least 3 times greater in diameter than the specific diameter of

ball or spread of roots, and at depth of ball or roots.

2. Shrubs shall be planted in pits or holes of soil the depth of ball below finished grade, or deeper as necessary to properly set the plant at finished grade. Shrubs with balls shall be planted in pits that are at least two times greater in diameter than the bottom of ball.

3.6 PREPARED BACKFILL

A. Tree and shrub pit backfilling soil shall consist of 1/3 of existing soil from pit, 1/3 sand and 1/3 peat moss.

B. Tree and shrub pits shall be provided with fertilizer tablets as follows:

1 per one-gallon can plant 3 per 5-gallon can plant 5 per 2” cal. deciduous tree 5 per 6’ tall evergreen tree

3.7 ROCKS OR UNDERGROUND OBSTRUCTIONS

A. In the event that rock or underground obstructions are encountered in the excavation of plant pits, alternative locations shall be selected by the L.A.. Moving of trees to alternative locations shall not entail additional costs to the OWNER.

3.8 SETTING PLANT MATERIALS

A. The soil shall not be worked when the moisture content is so great that excessive compaction will occur, nor when it is so dry that a dust will form in the air or that clods will not break readily. Water shall be applied if necessary to provide ideal moisture for filling and for planting as herein specified.

B. Plants shall be set in center of pits as shown in the Contract Documents. They shall be set

plumb and straight, and at such a level that after settlement that the crown of the plant will be 2 inches above the finished grade.

C. Balled and burlapped trees shall have planting soil placed and compacted around base of

ball to fill all voids. All burlap ropes or wires shall be removed from the sides and tops of balls.

D. All ground cover plants shall be evenly spaced, staggered in rows, and set at intervals specified, so as to produce a uniform effect. Plants shall be watered immediately after planting operations have been completed.

E. All shrubs and vines shall be pruned to remove damaged branches.

F. Planting soil around roots or balls shall be thoroughly compacted and watered. After planting,

the soil in the shrub beds shall be cultivated between shrubs, raked smooth, and neatly outlined. Muddy soil shall not be used for backfilling. All broken or frayed roots shall be properly cut off.

G. Trees and shrubs on slopes steeper than 6 to 1 shall be provided with watering dams or

berms at least 6 inches high and 8 inches wider than planting pit (hole) unless specified or shown otherwise.

H. All trees shall be thoroughly watered immediately after planting.

I. Remove all tags and labels when directed by L.A.

Page 33: ADDENDUM 001 E126 - Floor finish to be F7 and base to be B7.-Fire Riser E131- Noth and West wall finish to be W5.-Storage E140 - Gyp. wall finish at the stair to be W1. -Vestibule

JSD – BLUFFDALE ELEMENTARY #2 26 JAN 2018 - VCBO 17725

LANDSCAPING BID SET – CONSTRUCTION DOCUMENTS - ADD 001 SECTION 32 9000 - PAGE 11

3.9 STAKING

A. Staking of trees shall be done immediately after they are planted. Plants shall stand plumb after staking. Staking shall be as specified unless shown or indicated otherwise.

B. Evergreen trees 6 feet tall and taller to be guyed at points of branching with 3 wire guys

spaced equally around and outside the perimeter of the ball with ‘Cable Guy’ product model

#CG-4000. Trees over 3-inch caliper to be guyed with ‘Cable Guy’ product CG-6800-T. Each guy shall be positioned below crotches. Provide extra hose cushion where cable comes in contact with tree.

3.10 PRUNING AND MULCHING

A. Each tree and shrub shall be pruned in accordance with standard horticultural practice to preserve the natural character of the plant in the manner fitting its use in the landscape design, as approved by the L.A.

B. All dead wood or suckers and all broken or badly bruised branches shall be removed by

thinning out and shortening branches. All cuts shall be made just above a healthy bud. Pruning shall be done with clean, sharp tools.

C. Plants shall be mulched after planting and cultivating have been completed. A layer of mulch

materials, as hereinbefore specified, shall be spread on finished landscaping grade within all planting areas to an average depth of 4 inches. The mulch around isolated trees shall be 3 feet in diameter. All shrub beds shall be completely covered with the mulch. Rock mulch shall not be placed within an 8 inch diameter of the trunk of the tree or base of the shrub.

3.11 MISCELLANEOUS ITEMS

A. Concrete curbing shall be placed so that the top finish of curbing matches adjoining concrete curbs and walks. Curbing shall be straight and uniform both horizontal and vertically. Where curbing is next to building, curbing shall be placed against the structure without gaps between structure and curbing.

.

END OF SECTION

Page 34: ADDENDUM 001 E126 - Floor finish to be F7 and base to be B7.-Fire Riser E131- Noth and West wall finish to be W5.-Storage E140 - Gyp. wall finish at the stair to be W1. -Vestibule

JSD – BLUFFDALE ELEMENTARY #2 26 JAN 2018 - VCBO 17725

LAWNS AND GRASSES BID SET – CONSTRUCTION DOCUMENTS- ADD 001 SECTION 32 9200 - PAGE 1

SECTION 32 9200

LAWNS AND GRASSES

PART 1 - GENERAL

1.1 SUMMARY A. This Section includes sodding as called for on plans. Refer to plans and/or notes for the required

extent of sodding. Disregard any references to seeding on this project

1.2 DEFINITIONS A. Finish Grade: Elevation of finished surface of planting soil for consistency with existing lawn(s) or

intended grades adjacent to walks, curbs, and/or drives. B. Planting Soil: Existing topsoil mixed with soil amendments or imported topsoil. C. Sub-grade: Surface or elevation of subsoil remaining after general or previous contractor finishes

completing excavation, or top surface of a fill or backfill immediately beneath planting soil.

1.3 SUBMITTALS A. Product Data: For each type of product indicated. B. Product certificates. C. Contractors Planting Schedule: Indicating anticipated sodding and planting dates to meet allowed

time frames for completion.

1.4 QUALITY ASSURANCE A. Installer's Field Supervision: Require Installer to maintain an experienced full-time foreman or

supervisor on Project site when planting is in progress. B. Topsoil Analysis: Furnish soil analysis by a qualified soil testing laboratory showing topsoil meets

ideal standards set forth in the specifications.

1.5 DELIVERY, STORAGE, AND HANDLING A. Imported Sod: Harvest, deliver, store, and handle sod according to requirements in Turf Industry’s

"Specifications for Turfgrass Sod Materials" and "Specifications for Turfgrass Sod Transplanting and Installation" in its "Guideline Specifications to Turfgrass Sodding."

1.6 LAWN MAINTENANCE A. Begin maintenance immediately after each area is planted and continue until lawn is established

and accepted by Owner, but for not less than the following periods: 1. Sodded lawns or sodded areas of lawn: through installation and no less than 30 days from

Page 35: ADDENDUM 001 E126 - Floor finish to be F7 and base to be B7.-Fire Riser E131- Noth and West wall finish to be W5.-Storage E140 - Gyp. wall finish at the stair to be W1. -Vestibule

JSD – BLUFFDALE ELEMENTARY #2 26 JAN 2018 - VCBO 17725

LAWNS AND GRASSES BID SET – CONSTRUCTION DOCUMENTS- ADD 001 SECTION 32 9200 - PAGE 2

date of Substantial Completion. B. Mow all areas of lawn, as soon as top growth is tall enough to cut. Remove no more than 40

percent of grass-leaf growth in initial or subsequent mowing. C. Weed Treatments: provided as needed on any infestation that occurs prior to Substantial

Completion.

PART 2 - PRODUCTS

2.1 TURFGRASS SOD A. Turfgrass Sod: fully complying with Turf Industry's "Specifications for Turfgrass Sod Materials" in

its "Guideline Specifications to Turfgrass Sodding." Furnish viable sod of uniform density, color, and texture, strongly rooted, and capable of vigorous growth and development when planted.

B. Turfgrass Species and Supplier: Sod species shall be at least a five blend Kentucky Bluegrass

and the supplier shall be Raft River Sod or approved equivalent.

1. Blended sod mix from Raft River Sod shall be custom seed mix# 9270 and contain:

a. 29.77 percent Poa pratensis Adelphi’ b. 21.99 percent Poa pratensis ‘Quantum Leap’ or equivalent c. 21.10 percent Poa pratensis ‘Award’ d. 20.89 percent Poa pratensis ‘Nuglade’ e. 4.86 percent Poa pratensis ‘Midnight’ f. Submit samples AND bag tags for approval.

2.2 PLANTING MATERIALS A. Topsoil: ASTM D 5268, pH range of 5.5 to 7.5, a minimum 2% percent organic material content;

free of stones 1 1/2 x 1 1/2 inch or larger in any dimension and other extraneous materials harmful to plant growth.

B. Fertilizer

1. Commercial Fertilizer: Commercial-grade complete fertilizer of neutral character, consisting of fast- and slow-release nitrogen, 50 percent derived from natural organic sources of urea formaldehyde, phosphorous, and potassium in the following composition:

2. Slow-Release Fertilizer: 30 percent nitrogen, 10 percent phosphorous, and 0 percent

potassium, by weight.

2.3 LAWN SOIL MIX A. Lawn Soil Mix: Imported topsoil that meets the specifications.

1. Provide Slow-Release Fertilizer prior to sodding at label rate.

PART 3 - EXECUTION

Page 36: ADDENDUM 001 E126 - Floor finish to be F7 and base to be B7.-Fire Riser E131- Noth and West wall finish to be W5.-Storage E140 - Gyp. wall finish at the stair to be W1. -Vestibule

JSD – BLUFFDALE ELEMENTARY #2 26 JAN 2018 - VCBO 17725

LAWNS AND GRASSES BID SET – CONSTRUCTION DOCUMENTS- ADD 001 SECTION 32 9200 - PAGE 3

3.1 LAWN PREPARATION A. Newly Prepared Subgrades: Loosen subgrade in applicable areas to a minimum depth of 6".

Remove stones larger than 1 1/2 inch in any dimension and sticks, roots, rubbish, and other extraneous matter and legally dispose of them off Owner's property.

1. Apply slow release fertilizer directly to subgrade before loosening. 2. Spread planting soil as needed to meet finish grades after light rolling and natural settlement.

Do not spread if planting soil or subgrade is frozen, muddy, or excessively wet. B. Unchanged Subgrades: If lawns are to be planted in areas unaltered or undisturbed by

excavating, trenching, grading, or surface soil stripping operations, prepare surface soil as follows:

1. Remove existing unwanted areas of grass, vegetation, weed, or turf. Do not mix into surface soil.

2. Loosen surface soil to a depth of at least of 8 inches. Apply soil amendments and fertilizers

according to planting soil mix proportions and mix thoroughly into top 4 inches of soil. Roto-till soil to a homogeneous mixture of fine texture.

3. Remove all stones larger than 1 1/2 inch in any dimension and sticks, roots, trash, and other

extraneous matter. 4. Legally dispose of waste material, including grass, vegetation, and unwanted turf, off Owner's

property. C. Finish Grading: Grade planting areas to a smooth, uniform surface plane with loose, uniformly fine

texture. Grade to within plus or minus .10 ft of finish elevation. Roll and rake, remove ridges, and fill depressions to meet finish grades. Limit fine grading to areas that can be planted in the immediate future.

D. Moisten prepared lawn areas before planting if soil is dry. Water thoroughly and allow surface to dry

before planting. Do not create muddy soil. E. Restore areas if eroded or otherwise disturbed after finish grading and before planting.

3.2 SODDING A. Lay sod within 24 hours of harvesting. Provide documentation stating cutting time, date and location

if requested by Owner or Landscape Architect. B. Do not lay sod if it is dormant or if ground is frozen, muddy, or insufficiently prepared. C. Lay sod to form a solid mass with tightly fitted joints. Butt ends and sides of sod; do not stretch or

overlap. Stagger sod strips or pads to offset joints in adjacent courses. Avoid damage to subgrade or sod during installation.

D. Tamp and roll lightly if needed or directed to ensure contact with subgrade and to eliminate air

pockets or form a smooth surface. Top dress sod edges by working sifted soil or fine sand into minor cracks between pieces of sod; remove excess to avoid smothering sod and adjacent grass Lay sod parallel to contour lines (cross slope) on slopes exceeding 5:1.

1. Anchor sod on slopes exceeding 3:1 with sod staples or stakes spaced as recommended by

sod manufacturer but not less than 2 per sod strip to prevent slippage.

Page 37: ADDENDUM 001 E126 - Floor finish to be F7 and base to be B7.-Fire Riser E131- Noth and West wall finish to be W5.-Storage E140 - Gyp. wall finish at the stair to be W1. -Vestibule

JSD – BLUFFDALE ELEMENTARY #2 26 JAN 2018 - VCBO 17725

LAWNS AND GRASSES BID SET – CONSTRUCTION DOCUMENTS- ADD 001 SECTION 32 9200 - PAGE 4

E. Saturate sod with fine water spray within two hours of planting. During first week, water multiple times daily as frequently as necessary to maintain moist soil to a minimum depth of 2" inches below sod.

3.3 SATISFACTORY LAWNS A. Satisfactory Sodded Lawn: At end of maintenance period, a healthy, well-rooted, even-colored,

viable lawn has been established, free of weeds, exposed or open joints or edges, free of bare areas and surface irregularities such as ridges and depressions inconsistent with intent of grading plans or directives.

B. Reestablish lawn areas that do not comply with requirements as necessary or as directed and

continue maintenance until lawns are fully satisfactory to District and Landscape Architect.

C. Maintenance Guidelines: Shall be provided in triplicate to Owner in writing prior to final acceptance.

END OF SECTION