adaptation support community case study: little...

30
C-Change Secretariat (Canada) www.coastalchange.ca C-Change Secretariat (Caribbean) Telfer School of Management, c/o Sir Arthur Lewis Institute of University of Ottawa Social & Economic Studies (SALISES) 55 Laurier Avenue East University of the West Indies, St. Augustine, Ottawa ON K1N 6N5 Canada Trinidad and Tobago, West Indies Tel: (613) 562-5800 Post 2933 Telephone: (868) 662-6965 Email: [email protected] E-mail : [email protected] C-Change Community of Practice Meeting Adaptation Support Community Case Study: Little Anse, Isle Madame, Cape Breton Volume II – Participants’ Workshop Prepared for: C-Change Community of Practice Meeting, Sainte-Anne, Petit de Grat Campus Prepared by: Dan Lane, C-Change Co-Director (Canada) Date: Meeting date - May 24, 2013

Upload: others

Post on 06-Aug-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Adaptation Support Community Case Study: Little …coastalchange.ca/images/stories/Documents_Tab/little...C-Change Community of Practice Little Anse Case Study: Volume II Université

C-Change Secretariat (Canada) www.coastalchange.ca C-Change Secretariat (Caribbean) Telfer School of Management, c/o Sir Arthur Lewis Institute of University of Ottawa Social & Economic Studies (SALISES) 55 Laurier Avenue East University of the West Indies, St. Augustine, Ottawa ON K1N 6N5 Canada Trinidad and Tobago, West Indies Tel: (613) 562-5800 Post 2933 Telephone: (868) 662-6965 Email: [email protected] E-mail : [email protected]

C-Change Community of Practice Meeting

A d a p t a t i o n S u p p o r t C o m m u n i t y C a s e S t u d y : L i t t l e A n s e , I s l e M a d a m e , C a p e B r e t o n

V o l u m e I I – P a r t i c i p a n t s ’ W o r k s h o p Prepared for: C-Change Community of Practice Meeting, Sainte-Anne, Petit de Grat Campus Prepared by: Dan Lane, C-Change Co-Director (Canada) Date: Meeting date - May 24, 2013

Page 2: Adaptation Support Community Case Study: Little …coastalchange.ca/images/stories/Documents_Tab/little...C-Change Community of Practice Little Anse Case Study: Volume II Université

C-Change Community of Practice Little Anse Case Study: Volume II

Université Sainte-Anne Workshop 2 of 30 May 24, 2013

C-Change Community of Practice Meeting Adaptation Support Case Study: Little Anse, Isle Madame

Volume II – Participants’ Workshop

This document (Volume II of III) describes the C-Change Community of Practice workshop with participants and representatives of the community of Little Anse. The workshop was held at the Université Sainte-Anne, Petit de Grat on May 24, 2013. The Little Anse Case Study Participants’ Workshop applied the C-Change adaptation decision support procedures that demonstrated: (i) the community’s problem of adapting to the changing coastal environment; (ii) the profile of Little Anse and the community’s priorities; (iii) the alternative adaptation strategies in planning for more frequent and severe storms; and (iv) the evaluation of the adaptation strategies in support of community decision-making. This report of the workshop reflects the inputs and analysis of the community feedback received from the participants at the May 24, 2013 meeting. Volume I of the C-Change Community of Practice reports provides the guide for the application of the workshop (C-Change COP 2014a). Volume III (also under separate cover) presents the summary document for politicians and media (C-Change COP 2014b).

This Case Study Participants’ Workshop summarizes the key elements for (adaptive problem solving that includes the following steps:

I. Community Profile – statement of the environmental, economic, social, and cultural position

of the community of Little Anse, Isle Madame, in the Municipality of the County of Richmond, Cape Breton as well as acknowledgement of the community’s threats and vulnerabilities.

II. Problem Formulation – statement of Little Anse’s strategic planning for the preparation of emergency conditions brought on by the expected impacts on the assets of Little Anse from severe coastal storms causing flooding, storm surge, power outage, and wind damage.

III. Community Priorities – statement of the relative importance to Little Anse stakeholders on the

community’s environmental, economic, social, and cultural pillars, and the community’s relative valuation of the significance of local threats and vulnerabilities.

IV. Alternative Adaptation Strategies – declaration of alternative strategies for adapting to the

emergency planning problem brought on by severe storms in Little Anse.

V. Strategy Evaluation and Ranking of Alternatives – evaluation and ranking of alternative adaptation strategies based on the Community feedback.

This Case Study workshop summary is presented for the case of Little Anse, Isle Madame. It is prepared as the summary of the applied C-Change adaptation decision support procedure for community decision making involving Little Anse community members and representatives. The participation of community members reflects the application of the C-Change decision support method for addressing the management of adaptation to coastal community environmental change. The C-Change project acknowledges the support and valuable participation of the participants, and the assistance of C-Change Participants at the Université Sainte-Anne, and the key role of the Municipality of the County of Richmond.

Page 3: Adaptation Support Community Case Study: Little …coastalchange.ca/images/stories/Documents_Tab/little...C-Change Community of Practice Little Anse Case Study: Volume II Université

C-C

Un

1.

feeThethe

Theof tcomCas

Thidoidetinpada I.

comwelcom

Change Com

iversité Sain

Purpos

The dback on theese inputs w following e

A. Prioriti

pairwis(ii) econvalues aweighte

B. Utility the relamain roused in

e Case Studythe adaptatiombined partise Study gui

is document ing, it summtails in the Cputs; (ii) the raptation strat

Commu

The Volummunity of Lll as acknowmmunity.

mmunity of P

nte-Anne Wo

se of the Wo

purpose of te requested i

were integral elements:

ies for Come comparisonomic, (iii) sare used in thed priority am

Measures fotive impact o

oads throughthe evaluati

y Participanton strategiesicipants’ resuide results pr

follows the marizes the reCase Study R

resulting comtegies results

unity Profil

ume I report Little Anse,

wledgement o

Practice

orkshop

orkshop Rep

this report isinput that wacomponents

mmunity Proon of commusocial, and (ihe Analytic mong the fou

or Damage of flood dam

h the communon of expect

ts’ Worksho, are presentults. The indrovided in V

steps I throuesults (comm

Report). Thesmmunity pris compared t

le

documents tIsle Madam

of the comm

port

s to provide tas provided s of the adap

ofile Pillars unity profile iv) cultural pHierarchy Pur communi

Scenarios –mage for Littnity. This inted storm im

p summary, ted individuadividual and Volume I - G

ugh VI for thmunity priorise results areiorities; (iii) to the origin

the environmme, in the Mumunity’s threa

Figure 1.https://ma

II. Pr

3 of 30

the participaduring the p

ptation strate

– C-Changepillars for thpillars of the

Process (AHPty profile pil

– C-Change Wtle Anse. Thenformation wmpacts.

including thally for eachcombined reuide.

he C-Changeties, and ran

e followed bythe impacts

nal rankings

mental, econunicipality ofats and vuln

. Little Anseaps.google.c

roblem For

L

ating C-Chanpresentation gy evaluatio

e Workshop phe relative ime communityP) procedurellars as perc

Workshop pese include t

was provided

he communih participant,esults are sim

e evaluation nked strategiy: (i) the Woutility weighfrom Volum

nomic, socialf the County

nerabilities. F

e detail. (Souca )

mulation

Little Anse C

nge Workshof the Case

ons for the ca

participants’mportance ofy. The pairwe (Saaty 198eived by the

participants pthe impact o

d in the form

ty priorities,, and, separamilarly comp

n of adaptatioes) of the ororkshop parthts; and (iv)

me I - Guide.

l, and culturay of RichmonFigure 1 show

urce: Google

Case Study: V

May 24, 2

op participanStudy, May ase and repre

’ feedback of: (i) enviro

wise comparis0) to determ

e participants

provided feeof flood dam

m of utility fu

, and relativeately, for the pared to the

on strategiesriginal case (ticipants’ pri) the resultin

al position ond, Cape Brws the map

e Maps.

Volume II

013

nts with 24, 2013. esented

on the onmental, son

mine the s.

edback on mage to the unctions

e ranking

original

. In so (see iorities

ng ranked

of the eton as of the

Page 4: Adaptation Support Community Case Study: Little …coastalchange.ca/images/stories/Documents_Tab/little...C-Change Community of Practice Little Anse Case Study: Volume II Université

C-Change Community of Practice Little Anse Case Study: Volume II

Université Sainte-Anne Workshop 4 of 30 May 24, 2013

The Little Anse adaptation problem is formulated as a hierarchical, multiple criteria problem as

presented in Figure 2 below. (Figure 2 presents the Little Anse hierarchy from the Expert Choice (2010) software used for the analysis of the Analytical Hierarchy Process (AHP) (Saaty 1980). The hierarchy categorizes the community assets according to the four sustainability pillars of the environment, the economy, the society, and the culture of the community.

Figure 2. AHP hierarchy of the Little Anse community adaptation problem.

(Source: Expert Choice 2010.) The hierarchy model of Figure 2 incorporates the pillars of the MCCAP (Municipality of the County of Richmond 2013) and the ICSP (Municipality of the County of Richmond 2010), and provides the basis for determining the importance of each pillar within the community (discussed in the next section). The valuation of Little Anse community assets around the pillars reflects the Status Quo position of the community prior to the occurrence of a severe storm event. Little Anse is an aging community with more senior residents than juveniles. There are no schools or shopping in the community. The asset base of the community, estimated at approximately $14 million (2013), includes residential buildings and land, and associated infrastructure (roads, wells, and septic systems), as well as valued greenspace. The Little Anse harbour and the community itself are regularly flooded as the result of storms from the seaward side and the failure of the breakwater. Floods result in closure of the seaside road cutting off the inhabitants to the south, inundating properties, basements, and local infrastructure (wells, septic tanks), and damaging houses and out-buildings. The deficiencies of the failed breakwater are the results of displaced armour stone, deteriorated concrete and stone quality, and lack of maintenance. Estimated damages from storms are a function of assets-at-risk exposure. Estimated damages (presented in detail in Volume I) are determined for Little Anse assets based on historical storm impacts. Total estimated storm damages for Little Anse vary between $400 thousand and $1.5 million for storms of increasing severity (C-Change COP 2014a).

Page 5: Adaptation Support Community Case Study: Little …coastalchange.ca/images/stories/Documents_Tab/little...C-Change Community of Practice Little Anse Case Study: Volume II Université

C-C

Un

III.

prioimpenv

woquemacom(1.0

ThepillpaiEnvCul

Givcomincon

Change Com

iversité Sain

. Communi

Given torities with rportance of cvironmental

Commurkshop partiestions abouakers on the impared to th0) as shown

E

E

e pairwise colars (Saaty 1rwise relativvironmental ltural Pillars

Table 2

ven the full pmmunity’s aluding the athe commun

mmunity of P

nte-Anne Wo

ity Prioritie

he anticipaterespect needcommunity sversus econ

unity Priorityicipants on tht the pairwisidea that Env

he Economic in Table 1 b

Table 1

Environment

Economic

Social

omparison m980). Using

ve comparisoPillar is the

s in decreasin

2. Commun

problem, thessessment ossignment onity pillars an

Practice

orkshop

es

ed storm impd to be determstakeholdersomic versus

y Weights - Eheir feedbacse comparisovironmental (1.3) or Cul

below:

. Pairwise C

al

matrix above this methodon values yielargest prio

ng order of p

nity Priority

e issue now if risk and thf the utility fnd impacts.

pacts on the mined. This s with respec

social versu

Example. Thk about the r

on of the diffconsideratio

ltural (1.25)

ComparisonEconomic

1.3

-

-

e provides thd, the weightelds the follority communpriority.

Weights, O

is to evaluatee assignmenfunctions tha

5 of 30

sustainabilitinformation

ct to the pillaus cultural pi

he evaluationrelative impferent pillarsons for the cpillars, but e

n Matrix for

he opportunitted and scaleowing uniqunity pillar fo

Original Cas

e the impactnt of measureat indicate th

L

ty profile of n is captured ars of the comillars.

n of prioritieortance of ths. For examp

community aequivalent in

r all SustainSocial

1.0

1.3

-

ty to developed comparisoue weights shollowed by th

se – Volume

ts of the flooes that refleche decision m

Little Anse C

f Little Anse,by comparinmmunity pro

es takes placehe sustainabiple, feedbackare slightly mn importance

nability PillaCultu

1.2

1.5

1.0

p a direct coon of the pilhown in Tabhe Economic

e I. (Expert

od scenarios.ct decision mmakers’ imp

Case Study: V

May 24, 2

, the commung the relativofile, namely

e by queryinility pillars bk from decismore importae to the Soci

ars ural

25

5

0

mparison ofllars from theble 2 in whicc, Social, an

Choice 201

This involvmakers’ risk pact of flood

Volume II

013

unity’s ve y, the

ng by asking sion ant ial pillar

f all e above

ch the nd

10)

ves the attitudes, impacts

Page 6: Adaptation Support Community Case Study: Little …coastalchange.ca/images/stories/Documents_Tab/little...C-Change Community of Practice Little Anse Case Study: Volume II Université

C-Change Community of Practice Little Anse Case Study: Volume II

Université Sainte-Anne Workshop 6 of 30 May 24, 2013

Utility Measures for Damage Scenarios - Example. It is the requirement of community decision makers to provide feedback on how expected damage measures – by item of the problem hierarchy (Figure 2) - are comparable. For example, with respect to damage estimates to Little Anse Roads (Figure 3 below), it is important to know how Little Anse community members evaluate the expected impacts of 0.5km of impassible roads (with a 1m Maximum Observable Water Level, MOWL) versus the 1.0km (1.5m MOWL) and the 1.5km (2.0m MOWL) of closed roads. For example, knowing what these road closures mean to community access, the closure of 1.5km of roads is more likely to be considered to be more than twice the impact of 0.5km of roads flooded out. The resulting feedback is expressed as a “utility curve” that captures the risk attitude of the Community decision makers with respect to Road closures (Raiffa 1968). Figure 3 below captures the significance evaluation for the expected damage of Roads for the span of the kilometers from different flood scenarios. This particular curve represents the community decision makers’ attitude (measured as “utility” on the arbitrary vertical scale of 0-1) against the impacts of potential road closures that are expected to be between 5km (worst case) or 0km (best case) road closures as a result of the floods (horizontal axis in Figure 3 below).

Figure 3. Community Pillar Utility Curve: Road Closures Assets ($) (Source: Expert Choice 2010) Feedback on both the community priority weights and the relative utility measures for expected road damages are collected from the workshop participants and the resulting recommendations for adaptation strategy evaluation compared and contrasted. This information is described in further detail below. IV. Alternative Adaptation Strategies

Little Anse adaptation strategy alternatives include the following (see also C-Change COP 2014a):

1) Protect - New breakwater arm: Build a new arm opposite to the existing breakwater and rehabilitation of the existing breakwater. This option narrows the current opening in a way that waves would go through a significant energy reduction before they reach the inner harbour area. This option is expected to mitigate significantly the surge events originating from the south and east. With the staggered structure in place, waves will be further contained before reaching the shoreline. Therefore this strategy can provide the best protection to the community from flooding (fewer houses flooded and reduced flooding costs, road more protected from over-topping). However, this option is also the most expensive capital cost strategy among all breakwater engineering alternatives. Estimated costs are over $5 million.

Utility Curve

Roads (L: .446)

.0

.2

.4

.6

.8

1.0

2,000,000

Xaxis

Page 7: Adaptation Support Community Case Study: Little …coastalchange.ca/images/stories/Documents_Tab/little...C-Change Community of Practice Little Anse Case Study: Volume II Université

C-Change Community of Practice Little Anse Case Study: Volume II

Université Sainte-Anne Workshop 7 of 30 May 24, 2013

2) Accommodate - Build New Road: Build a new road further from the shoreline, e.g., through the wooded area on the rise behind the brackish (barachois) lake in the cove. The new road is estimated to be 1400m in length. Road building includes: capital cost (material and labour), mobilization cost (machinery), and engineering. Estimated total costs are approximately $2 to $3 million. Considering that the current road is the only access route to Little Anse with the outside, building a new road is designed as an escape route to avoid being trapped by the closed road that arises from severe the storm surge impacts. 3) Retreat - This strategy, moves a selection of houses away from the coastline to somewhere safer from flooding. As noted above, many Little Anse houses are in the flood zones and are therefore candidates for removal and retreat. The cost of the retreat strategy includes: compensation for the value of property, plus mobilization cost (uncompensated cost of relocating a household to a new location). The fully costed estimates for this strategy approach $2.5 to $4 million. 4) “Do Nothing” Status Quo - The suite of adaptation strategies includes the “Do Nothing” (Status Quo) option. Ultimately, this is the current active strategy for the community that is being explicitly applied since the complete failure of the breakwater and the shutting down of the wharf as an access for Little Anse fishing vessels. Direct costs for adopting this strategy are zero.

V. Strategy Evaluation and Ranking of Alternatives The expected damages attributed to these adaptive strategies are “scored” relative to the risk attitude values, e.g., Figure 3, applied to each of the Community Profile elements of the Figure 2 problem hierarchy. The illustrative results of the ranking of the adaptation strategies for Little Anse are provided in Table 3 below after for the case of a severe storm categorized as Storm Scenario IV, e.g., similar in severity to Hurricane Gustav (September 12, 2002), and the subtropical storm of October 29, 2000. Table 3. Ranked Case Study Results of the Little Anse Storm Scenario IV (Source: Expert Choice 2010)

The results of the problem analysis for the given inputs suggest that in relative terms, the best adaptation strategy for this illustrative example is to adopt an “Accommodate” strategy meaning “Build a new road” (last row of Table 3 above – ‘Road build…’) that would represent an escape route in the event of main road flooding and closure. Preference for this strategy is followed by the option to “Protect” and “Build a new breakwater” with an additional arm (second row in Table 3 above – ‘New BW arm…’. These adaptation strategies are preferable to “Doing Nothing” (first row of Table 3 – ‘Scenario 4 Impacts…’) and much greater than the undesirable “Retreat” adaptation option (third row in Table 3 – ‘Retreat (S4)’). This result is comparable to the results of the Workshop participants, below, who provided their feedback on: (1) the

Synthesis: Summary

Synthesis with respect to: G o a l:A d a p ta t io n o f L it t le A n s e c o m m u n it y to s to rm s u rg e e v e n t s

S c e n a rio 4 I . . . .2 4 7N e w B W a rm . . . .2 6 7R e t re a t ( S 4 ) .2 0 2R o a d b u ild u . . . .2 8 4

Page 8: Adaptation Support Community Case Study: Little …coastalchange.ca/images/stories/Documents_Tab/little...C-Change Community of Practice Little Anse Case Study: Volume II Université

C-Change Community of Practice Little Anse Case Study: Volume II

Université Sainte-Anne Workshop 8 of 30 May 24, 2013

Community Priorities, and (2) the relative Road Damage Utility Measures, as alternative inputs to the Little Anse adaptation problem. The above results summarize the problem components I through V of the Little Anse case study guide (Volume I) as presented at the Community of Practice meeting. The sections below present the inputs and revised results of the case study exercises for each of the C-Change Workshop participants who contributed their feedback in the case study exercises of May 24, 2013 workshop during the Community of Practice meetings in Petit de Grat. 2. Workshop participant Inputs

The following comparative results are presented for the C-Change Community of Practice meeting, Little Anse Participants’ Workshop, May 24, 2013 at the Université Sainte-Anne, Petit de Grat campus. The results present, for each workshop participant:

A. Priorities for the Community Profile Pillars and B. Utility Measures for Damage Scenarios

These inputs received from each participant are determined from the 2-stage exercise that was conducted during the case study presentation. The input forms provided to participants are given in separate (Word format) documents and included the forms:

(A) Little Anse Case Study Exercise: Problem Priorities; and (B) Little Anse Case Study Exercise: Utility Measurement (for expected Road damages)

The inputs provided by each participant are recast, as required, for the analysis and evaluation of adaptation strategies and discussed in more detail below. 2.1 A. Evaluation of Community Profile Pillar Priorities The workshop participants included 7 members and representatives of the Little Anse community. All participants contributed case study inputs and all participants were residents of Richmond County. Participant identifiers and affiliations are noted in Table 4 below:

Table 4. Ranked Case Study Results Participant No. Affiliation

P1 Public Health Officer P2 Member of Development Association P3 Cable Television Administrator P4 Fisheries Business operator P5 University Director P6 Municiapal Government Director P7 University Researcher

The inputs and results for each of the Workshop participants’ exercises are discussed in further detail below. P1. Public Health Officer. The inputs of Table 5.P1 for this participant suggest a superior evaluation of the Environmental pillar (positive Environmental row values dominating against all other pillars in terms of

Page 9: Adaptation Support Community Case Study: Little …coastalchange.ca/images/stories/Documents_Tab/little...C-Change Community of Practice Little Anse Case Study: Volume II Université

C-Change Community of Practice Little Anse Case Study: Volume II

Université Sainte-Anne Workshop 9 of 30 May 24, 2013

relative importance), followed by secondary domination of the Economic pillar (also positive row values). The Social and the Cultural pillars are judged to be equivalent (comparison value of 1.0) with a relatively lower evaluation against the other pillars (positive column values).

Table 5.P1. Pairwise Comparison Matrix for all Sustainability Pillars for P1 Economic Social Cultural

Environmental 4.0 9.0 4.0 Economic - 4.0 4.0 Social - - 1.0

The weighted and scaled comparison of the pillars from the above pairwise relative comparison values yields overall weights for the Community Profile pillars as shown in Table 6.P1 below. The weights of Table 6.P1 reflect the pairwise comparison values of Table 5.P1 whereby the Environmental pillar dominates (weight of 0.604), followed by the Economic pillar (0.242) – less than half the weight of the most important Environmental pillar. The Social and Cultural pillars (lowest weights of 0.088, 0.067) are the least important pillars for Workshop participant P1. The AHP measure of inconsistency of these inputs, the Consistency Index, CI=0.07, is considered fully acceptable (<0.10).

Table 6.P1. Community Profile Priority Weights for P1 (Source: Expert Choice 2010)

P2. Member of Development Association. The inputs of Table 7.P2 also suggest a superior evaluation of the Environmental pillar (positive row value, dominating against all other pillars). The dominance of the Environmental pillar is followed by the relative importance of the Economic pillar. The Cultural and the Social pillars are evaluated lower against all other pillars (as evidenced by the positive column values for these pillars).

Table 7.P2. Pairwise Comparison Matrix for all Sustainability Pillars for P2 Economic Social Cultural

Environmental 2.33 2.33 2.33 Economic - 1.0 2.33 Social - - 1.0

Priority Graphs

Priorities with respect to: Goal:Adaptation of Little Anse community to storm surge events

Economic .242Environment .604Cultural .088Social .067 Inconsistency = 0.07 with 0 missing judgments.

Page 10 of 102/19/2014 10:41:26 PM

Page 10: Adaptation Support Community Case Study: Little …coastalchange.ca/images/stories/Documents_Tab/little...C-Change Community of Practice Little Anse Case Study: Volume II Université

C-Change Community of Practice Little Anse Case Study: Volume II

Université Sainte-Anne Workshop 10 of 30 May 24, 2013

The weighted and scaled comparison of the pillars from the above pairwise relative comparison values yields overall weights for the Community Profile pillars as in Table 8.P2 below. The weights of Table 8.P2 reflect the pairwise comparison values of Table 7.P2 and produce the largest weight for the Environmental pillar (0.430) followed by the Economic pillar (0.233). The Cultural and the Social pillars attain the lowest overall importance weightings (0.152 and 0.185 respectively). In comparison with Workshop participant P1, P2’s choice of lower pairwise comparison numbers (Table 7.P2) result in weights that are closer in value (Table 8.P2). The AHP measure of inconsistency, the Consistency Index, CI=0.03, which is very acceptable (<0.10).

Table 8.P2. Community Profile Priority Weights for P2 (Source: Expert Choice 2010)

P3. Cable Television Administrator. The inputs of Table 9.P3 again suggest a much superior evaluation of the Environmental over the Economic pillar (high positive value of 9.0), but a superior Economic pillar with respect to Social and Cultural pillars (2.33) – even greater than that of Environmental over Social and Cultural (1.5 and 1.0 respectively). This may suggest that the comparisons are slightly inconsistent, as measured by the AHP measure of inconsistency, the Consistency Index, CI=0.44, which is considered high relative to the rule of thumb threshold value of 0.10 (>>0.10). As for the other participants, P1 and P2, the Social and Cultural pillar are judged to be equally important equally important by Workshop participant P3 (comparison score of 1.0).

Table 9.P3. Pairwise Comparison Matrix for all Sustainability Pillars for P3

Economic Social Cultural Environmental 9.0 1.5 1.0 Economic - 2.33 2.33 Social - - 1.0

The weighted and scaled comparison of the pillars from the above pairwise relative comparison values yield the following overall weights for the Community Profile pillars. The weights of Table 10.P3 reflect the

Priority Graphs

Priorities with respect to: Goal:Adaptation of Little Anse community to storm surge events

Economic .233Environment .430Cultural .152Social .185 Inconsistency = 0.03 with 0 missing judgments.

Page 10 of 102/19/2014 10:52:12 PM

Page 11: Adaptation Support Community Case Study: Little …coastalchange.ca/images/stories/Documents_Tab/little...C-Change Community of Practice Little Anse Case Study: Volume II Université

C-Change Community of Practice Little Anse Case Study: Volume II

Université Sainte-Anne Workshop 11 of 30 May 24, 2013

pairwise comparison values of Table 9.P3 with dominant weighting of the Environmental pillar (0.498). This is followed by the lower rating of the Economic pillar (0.188). The Cultural and Social pillars have lower relative weights of 0.172 and 0.141 respectively.

Table 10.P3. Community Profile Priority Weights for P3 (Source: Expert Choice 2010)

P4. Fisheries Business operator. The inputs of Table 11.P4 for this Workshop participant suggest a slightly superior evaluation of the Economic pillar (indicated by positive row values). The Cultural pillar has slightly lower evaluation against all other pillars (positive column values).

Table 11.P4. Pairwise Comparison Matrix for all Sustainability Pillars for P4

Economic Social Cultural Environmental 1.0 1.0 1.0 Economic - 1.5 1.5 Social - - 1.5

The weighted and scaled comparison of the pillars from the above pairwise relative comparison values yields overall weights for the Community Profile pillars as shown in Table 12.P4 below. The weights of Table 12.P4 reflect the pairwise comparison values of Table 11.P4 with the relatively higher Economic pillar importance weighting (0.303) and slightly lower relative importance weights for each of the Environmental (0.247) and the Social (0.248) pillars. The lowest weight is attached to the Cultural pillar (0.201). The AHP measure of inconsistency, the Consistency Index, CI=0.02, which is considered highly acceptable (<0.10).

Priority Graphs

Priorities with respect to: Goal:Adaptation of Little Anse community to storm surge events

Economic .188Environment .498Cultural .172Social .141 Inconsistency = 0.44 with 0 missing judgments.

Page 10 of 102/19/2014 11:00:42 PM

Page 12: Adaptation Support Community Case Study: Little …coastalchange.ca/images/stories/Documents_Tab/little...C-Change Community of Practice Little Anse Case Study: Volume II Université

C-Change Community of Practice Little Anse Case Study: Volume II

Université Sainte-Anne Workshop 12 of 30 May 24, 2013

Table 12.P4. Community Profile Priority Weights for P4 (Source: Expert Choice 2010)

P5. University Director. The inputs of Table 13.P5 for this Workshop participant suggest a superior evaluation of the Economic pillar (indicated by negative column and positive row values). The Cultural pillar has lower evaluation against all other pillars (positive column values).

Table 13.P5. Pairwise Comparison Matrix for all Sustainability Pillars for P5

Economic Social Cultural Environmental -1.5 2.33 2.33 Economic - 4.0 4.0 Social - - 1.0

The weighted and scaled comparison of the pillars from the above pairwise relative comparison values yields overall weights for the Community Profile pillars as shown in Table 14.P5 below. The weights of Table 14.P5 reflect the pairwise comparison values of Table 13.P5 with highest Economic pillar weighting (0.467) with lower relative weights for each of the Environmental (0.261) and approximately equal weights for the least important Cultural (0.120) and Social (0.121) pillars. The AHP measure of inconsistency, the Consistency Index, CI=0.00886, which is considered highly acceptable (<<0.10).

Priority Graphs

Priorities with respect to: Goal:Adaptation of Little Anse community to storm surge events

Economic .303Environment .247Cultural .201Social .248 Inconsistency = 0.02 with 0 missing judgments.

Page 10 of 102/19/2014 11:07:08 PM

Page 13: Adaptation Support Community Case Study: Little …coastalchange.ca/images/stories/Documents_Tab/little...C-Change Community of Practice Little Anse Case Study: Volume II Université

C-Change Community of Practice Little Anse Case Study: Volume II

Université Sainte-Anne Workshop 13 of 30 May 24, 2013

Table 14.P5. Community Profile Priority Weights for P5 (Source: Expert Choice 2010)

P6. Municipal Government Director. The inputs of Table 15.P6 for this Workshop participant suggest a superior evaluation of the Economic pillar (indicated by the negative column and positive row values). The Cultural pillar has lower evaluation against all other pillars (positive column values).

Table 15.P6. Pairwise Comparison Matrix for all Sustainability Pillars for P6

Economic Social Cultural Environmental -1.5 -2.33 1.5 Economic - 4.0 9.0 Social - - 2.33

The weighted and scaled comparison of the pillars from the above pairwise relative comparison values yields overall weights for the Community Profile pillars as shown in Table 16.P6 below. The weights of Table 16.P6 reflect the pairwise comparison values of Table 15.P6 with highest Economic pillar weighting (0.540) and lower relative weights for each of the Social (0.212), Environmental (0.169) and the Cultural (0.079) pillars. The AHP measure of inconsistency, the Consistency Index, CI=0.13, is only slightly above the acceptable level of 0.10.

Priority Graphs

Priorities with respect to: Goal:Adaptation of Little Anse community to storm surge events

Economic .467Environment .291Cultural .120Social .121 Inconsistency = 0.00086 with 0 missing judgments.

Page 10 of 102/19/2014 11:15:52 PM

Page 14: Adaptation Support Community Case Study: Little …coastalchange.ca/images/stories/Documents_Tab/little...C-Change Community of Practice Little Anse Case Study: Volume II Université

C-Change Community of Practice Little Anse Case Study: Volume II

Université Sainte-Anne Workshop 14 of 30 May 24, 2013

Table 16.P6. Community Profile Priority Weights for P6 (Source: Expert Choice 2010)

P7. University Researcher. The inputs of Table 17.P7 for this Workshop participant also suggest a superior evaluation of the Economic pillar (indicated by positive row values). The Social pillar has lower evaluation against other pillars (indicated by positive column values).

Table 17.P7. Pairwise Comparison Matrix for all Sustainability Pillars for P7

Economic Social Cultural Environmental 1.0 1.5 -1.5 Economic - 1.5 1.5 Social - - -1.5

The weighted and scaled comparison of the pillars from the above pairwise relative comparison values yields overall weights for the Community Profile pillars as shown in Table 18.P7 below. The weights of Table 17.P7 reflect the pairwise comparison values of Table 17.P7 with slightly higher Economic pillar

Priority Graphs

Priorities with respect to: Goal:Adaptation of Little Anse community to storm surge events

Economic .540Environment .169Cultural .079Social .212 Inconsistency = 0.13 with 0 missing judgments.

Page 11 of 113/1/2014 3:31:41 PM

Page 15: Adaptation Support Community Case Study: Little …coastalchange.ca/images/stories/Documents_Tab/little...C-Change Community of Practice Little Anse Case Study: Volume II Université

C-Change Community of Practice Little Anse Case Study: Volume II

Université Sainte-Anne Workshop 15 of 30 May 24, 2013

weighting (0.301), followed closely by the Cutural pillar weighting (0.274) and the Environmental pillar (0.246). The lowest importance weight is assigned to the Social pillar (0.179). The AHP measure of inconsistency, the Consistency Index, CI=0.02, which is highly acceptable (<0.10).

Table 18.P7. Community Profile Priority Weights for P7 (Source: Expert Choice 2010)

2.2 Summary of Workshop Participants’ Comparison of Community Profile Priorities

Figure 4 below summarizes the Community Profile results for the Workshop participants and compares them to the group’s overall average and that of the original Case Study guide reported in Volume I - Guide. Among the Workshop participants, the results demonstrate a range of community priorities denoting different emphasis as reported individually above. Overall, Workshop participants clearly divide community importance between two pairs of pillars. Environmental and Economic pillars, in total, account for just over two-thirds. While the remaining one-third are allotted to the Cultural and the Social pillars. The importance of the Environmental and Economic pillar pair are twice that of the Social and Cultural pillars for the average of the 7 Workshop participants.

The range of differences among the Community Profile pillars varies among the 4 pillars with largest range for the Environmental pillar (range among Workshop participants of 0.46 on a minimum of 0.14 and a maximum of 0.604). The smallest range is for the Cultural and Social pillars (range among Workshop participants of 0.18 on similar minimums of 0.09 and 0.07 for Cultural and Social, respectively, and maximums of 0.27 and 0.25 for Cultural and Social, respectively). The smallest priority weight among all Workshop participants is for the Social pillar (0.07), while the largest single weight is for the Environmental pillar (0.604). Overall, the Workshop participants’ priority weights average out to at least 16% of importance weight assigned to the lowest priority pillars (Cultural and Social), and just over 35% and 33% of importance weight assigned to the highest priority pillars (Environmental and Economic, respectively). Given the variability among the Workshop participants, these results suggest a relative balance between the two pairs of priorities by pillar. In ranked order, average importance priority weights by pillar for the 7 Workshop participants are:

Average Priority Ranking

Sustainability Pillar

Average Priority Weight

1 Environmental 35%

Priority Graphs

Priorities with respect to: Goal:Adaptation of Little Anse community to storm surge events

Economic .301Environment .246Cultural .274Social .179 Inconsistency = 0.02 with 0 missing judgments.

Page 10 of 102/19/2014 11:30:04 PM

Page 16: Adaptation Support Community Case Study: Little …coastalchange.ca/images/stories/Documents_Tab/little...C-Change Community of Practice Little Anse Case Study: Volume II Université

C-C

Un

Change Com

iversité Sain

ACas

Wor

ksho

p Pa

rtic

ipan

t

mmunity of P

nte-Anne Wo

Figure

0.000P1P2P3P4P5P6P7Averagese Study

WPrio

Practice

orkshop

2 3 4

e 4. Worksh

0.2

Workshorities f

Econom

1

EconCultuSocia

hop Particip

00 0

op Partfor Com

P

mic Enviro

16 of 30

nomic ural al

pants’ Comm

0.400Pillar Weig

ticipantmmunity

illars

nmental C

L

33%16%16%

munity Prof

0.600ghting

ts' Weigy Sustai

Cultural So

Little Anse C

% % %

file Prioritie

0.800

ghted inability

ocial

Case Study: V

May 24, 2

es

1.000

y

Volume II

013

0

Page 17: Adaptation Support Community Case Study: Little …coastalchange.ca/images/stories/Documents_Tab/little...C-Change Community of Practice Little Anse Case Study: Volume II Université

C-Change Community of Practice Little Anse Case Study: Volume II

Université Sainte-Anne Workshop 17 of 30 May 24, 2013

2.3 B. Utility Measures for Damage Scenarios

The following results present, for each C-Change Workshop participant, the Little Anse Utility Exercise inputs for feedback on the impact of flood damage to roads to Little Anse. This information was provided as Workshop participants’ input in the form of utility functions used in the evaluation of expected impacts and community priorities. The following sections of this report illustrate the feedback in utility inputs for “Roads” (Public Works, Economics pillar) as noted in the problem hierarchy of Figure 2 above. Figures 5.P1 through 11.P7 below capture the feedback for Roads closure damage impacts as provided by each of the Workshop participants. These comparisons are provided to note similarities and differences between the utility input among participants, and for direct comparison to the Roads closure utility function used in the original Case Study data (Volume I – Guide) as shown for the original case presentation in Figure 3 above. Tables 19.P1 through 25.P7 provide the final results of the respective Workshop participants’ rankings of the Little Anse Adaptation Strategies defined in Section IV above. These ranked strategy results are the final outcome of the Case Study. The results correspond to the complete set of Workshop participants’ inputs for: (i) Community Profile priorities (Tables 6.P1, 8.P2, 10.P3, 12.P4, 14.P5, 16.P6, and 18.P7) and (ii) the utility functions including Road closure utilities (Figures 5.P1-11.P7-Workshop participants, below).

P1. Public Health Officer. The Workshop participant’s inputs are provided in graphic form and resulted in the Figure 5.P1 utility function below. Based on these graphical inputs, Road closures are highly risk seeking, i.e., highly concave, as for the original case study utility function of Figure 3. This implies that the participant’s valuation of Road closure asset impacts are lower than would be considered as ‘risk neutral’ from the highest road closure estimate of damage position of $0.8million or asset position of $1.7 million (at the lowest utility valuation of 0), to the lowest road closure impacts of $0 damage or asset position of $2.3 million (at the highest utility valuation of 1). In this case, the participant is relatively intolerant of road closures of greater than 0.5km , while utility values less than 0.20km exhibit a sharp rate of valuation (utility) increase. Figure 5.P1 below illustrates a marginally increasing rate of improved utility as road closures diminish and road assets increase. It is of interest for this participant to avoid high levels (greater than 0.20km) of road closures.

Figure 5.P1. Utility Curve: Road Closures Assets ($) for P1 (Source: Expert Choice 2010)

Utility Curve

Roads (L: .446)

.0

.2

.4

.6

.8

1.0

2,000,000

Xaxis

Page 9 of 102/19/2014 10:41:26 PM

Page 18: Adaptation Support Community Case Study: Little …coastalchange.ca/images/stories/Documents_Tab/little...C-Change Community of Practice Little Anse Case Study: Volume II Université

C-Change Community of Practice Little Anse Case Study: Volume II

Université Sainte-Anne Workshop 18 of 30 May 24, 2013

The application of the Road closures utility function of Figure 5.P1 for Workshop participant P1, together with the participant’s indicated Community Profile priorities of Table 6.P1, determine the ranked preferences for the selected alternative adaptation strategies using the AHP methodology (Saaty 1980) for the formulated case of the Little Anse Storm Scenarios IV. The results of these rankings are provided in Table 19.P1 below. As indicated in the weights of Table 19.P1 below, the dominant preferred adaptation strategy for Workshop participant P1 is effectively shared between the “Accommodate” (Build new road) and the “Protect” (Build new breakwater arm) strategies. These strategies (ranking weight: 0.296 and 0.294) dominate the suite of alternative options and therefore provide the basis for logical support of these strategies for the participant P1. The difference between the top two preferences and the third ranked strategy “Do Nothing” or “Status Quo” (ranking weight: 0.260 for “Scenario 4 Impacts: of Table 19.P1) is appreciable. The lowest preference belongs to the “Retreat” option (ranking weight: 0.150) which Workshop participant P1 considers as a lower weighted “last resort” strategy compared to the Accommodate and Protect and Do Nothing options.

Table 19.P1. Final Adaptation Strategies Ranking for P1. (Source: Expert Choice 2010.)

P2. Member of Development Association. The inputs provided in graphic form for Workshop participant P2 are illustrated in the Figure 6.P2 utility function below. This graphical input for the Road closures utility function exhibits “risk neutral” behavior, i.e., linear utility curve, in comparison to the “risk seeking”, concave original case study utility function of Figure 3 above. The participant’s utility valuations of Road closure assets have a constant rate of marginal utility with respect to increasing assets (or decreasing roads closed). As before, estimates for highest road closure damages are $0.8million, or a reduced asset position of $1.7 million assigned the lowest utility valuation of 0. The lowest road closure impacts are $0 damage, or asset position of $2.3 million at the highest utility valuation of 1. Figure 6.P2 below illustrates the linear, constant rate of marginal utility as road closures diminish and road assets increase. The application of the Road closures utility function of Figure 6.P2, together with the participant’s indicated Community Profile priorities of Table 8.P2, determine the ranked preferences for the selected alternative adaptation strategies in the case of the Little Anse flooding scenarios. The ranking results are provided in Table 20.P2 below. As indicated in the weights and bars of Table 20.P2, the dominant preferred adaptation strategy for Workshop participant P2 is the “Protect” strategy – Build anew breakwater arm. This strategy (ranking weight: 0.291) dominates the suite of alternative options for the participant P2. However, the difference between the second ranked strategy “Accommodate” – Build a new road (ranking weight: 0.283) is not significant and differences between the “Accommodate” and the “Protect” options in this case should be further investigated by reviewing all inputs and through a sensitivity analysis. The least preferred strategies are the “Do Nothing” or “Status Quo” option (“Scenario 4 impacts” in Table 20.P2).

Alternatives

Scenario 4 Impacts .260New BW arm (S4) .294Retreat (S4) .150Road build up (S4) .296

Page 19: Adaptation Support Community Case Study: Little …coastalchange.ca/images/stories/Documents_Tab/little...C-Change Community of Practice Little Anse Case Study: Volume II Université

C-Change Community of Practice Little Anse Case Study: Volume II

Université Sainte-Anne Workshop 19 of 30 May 24, 2013

Figure 6.P2. Utility Curve: Road Closures Assets) ($) for P2 (Source: Expert Choice 2010)

Finally, it is very clear from participant P2 results that the “Retreat” option (ranking weight: 0.177) is quite different compared to all other adaptive strategy actions. The “Retreat” strategy is indicated by the Workshop participant P2 as a less than effective adaptation strategy for Little Anse.

Table 20.P2. Final Adaptation Strategies Ranking for P2 (Source: Expert Choice 2010)

P3. Cable Television Administrator. The inputs provided in graphic form and resulted in the Figure

7.P3 utility function below. Based on these graphical inputs, Road closures are risk seeking, i.e., concave, as for the original case study utility function of Figure 3. This implies that the participant’s utility valuation of Road closure asset impacts are lower than would be considered as ‘risk neutral’ from the highest road closure estimate of damage position of $0.8million or asset position of $1.7 million (at the lowest utility valuation of 0), to the lowest road closure impacts of $0 damage or asset position of $2.3 million (at the highest utility valuation of 1). In this case, the Workshop participant P3 is relatively intolerant of road closures of greater than 0.75km, while utility values less than 0.3 0km exhibit an increasing valuation (utility) increase. Figure 7.P3 below illustrates a marginally increasing rate of improved utility as road closures diminish and road assets increase. It is of interest for this participant to avoid higher levels (greater than 0.30km) of road closures.

Utility Curve

Roads (L: .446)

.0

.2

.4

.6

.8

1.0

2,000,000

Xaxis

Page 9 of 102/19/2014 10:52:12 PM

Synthesis: Summary

Synthesis with respect to: G o a l:A d a p ta t io n o f L it t le A n s e c o m m u n it y to s to rm s u rg e e v e n t s

S c e n a rio 4 I . . . .2 4 9N e w B W a rm . . . .2 9 1R e t re a t ( S 4 ) .1 7 7R o a d b u ild u . . . .2 8 3

Page 20: Adaptation Support Community Case Study: Little …coastalchange.ca/images/stories/Documents_Tab/little...C-Change Community of Practice Little Anse Case Study: Volume II Université

C-Change Community of Practice Little Anse Case Study: Volume II

Université Sainte-Anne Workshop 20 of 30 May 24, 2013

Figure 7.P3. Utility Curve: Road Closures Assets) ($) for P3 (Source: Expert Choice 2010)

The application of the Road closures utility function of Figure 7.P3, together with the participant’s indicated Community Profile priorities of Table 10.P3, determine the ranked preferences for the selected alternative adaptation strategies in the case of the Little Anse flooding scenarios. The ranking results are provided in Table 21.P3 below. As indicated in the weights and bars of Table 21.P3, the dominant preferred adaptation strategy for Workshop participant P2 is the “Protect” strategy – Build new breakwater arm (ranking weight: 0.295), followed closely by the “Accommodate” strategy – Build a new road (ranking weight: 0.287). These adaptation strategies dominate for Workshop participant P3. Further, the difference between these strategies and the third ranked strategy “Do Nothing” or “Status Quo” (ranking weight: 0.251 – “Scenario 4 Impacts” in Table 21.P3) is significant. Finally, the “Retreat” option (ranking weight: 0.168) is considered by Workshop participant P3 as an unattractive strategy for Little Anse.

Table 21.P3. Final Adaptation Strategies Ranking for P3 (Source: Expert Choice 2010)

Utility Curve

Roads (L: .446)

.0

.2

.4

.6

.8

1.0

2,000,000

Xaxis

Page 9 of 102/19/2014 11:00:42 PM

Synthesis: Summary

Synthesis with respect to: G o a l:A d a p ta t io n o f L it t le A n s e c o m m u n it y to s to rm s u rg e e v e n t s

Ov era ll Inc onsistenc y = .26

S c e n a rio 4 I . . . .2 5 1N e w B W a rm . . . .2 9 5R e t re a t ( S 4 ) .1 6 8R o a d b u ild u . . . .2 8 7

Page 21: Adaptation Support Community Case Study: Little …coastalchange.ca/images/stories/Documents_Tab/little...C-Change Community of Practice Little Anse Case Study: Volume II Université

C-Change Community of Practice Little Anse Case Study: Volume II

Université Sainte-Anne Workshop 21 of 30 May 24, 2013

P4. Fisheries Business operator. The inputs provided in graphic form for Workshop participant P4 are illustrated in the Figure 8.P4 utility function below. Based on these graphical inputs, the concave Road closures utility function is considered to exhibit “risk seeking” behavior, i.e., concave, similar to the convex original case study utility function of Figure 3. This implies that the participant’s utility valuation of Road closure asset impacts are lower than would be considered as ‘risk neutral’ from the highest road closure estimate of damage position of $0.8 million or asset position of $1.7 million (at the lowest utility valuation of 0), to the lowest road closure impacts of $0 damage or asset position of $2.3 million (at the highest utility valuation of 1). In this case, the Workshop participant P4 is relatively intolerant of road closures of greater than 1km , while utility values less than 0.5km exhibit an increasing valuation (utility) increase. Figure 8.P4 below illustrates a marginally increasing rate of improved utility as road closures diminish and road assets increase. It is of interest for this participant to avoid higher levels (greater than 0.50km) of road closures.

Figure 8.P4. Utility Curve: Road Closures Assets) ($) for P4 (Source: Expert Choice 2010)

The application of the Road closures utility function of Figure 8.P4, together with the participant’s indicated Community Profile priorities of Table 12.P4, determine the ranked preferences for the selected alternative adaptation strategies in the case of the Little Anse flooding scenarios. The ranking results are provided in Table 22.P4 below. The ranking results are provided in Table 22.P4 below. As indicated in the weights and bars of Table 22.P4, the dominant preferred adaptation strategy for Workshop participant P4 is the “Accommodate” strategy – Build a new road (ranking weight: 0.281), followed closely by the“Protect” strategy – Build new breakwater arm (ranking weight: 0.277). These adaptation strategies dominate for Workshop participant P4. Further, the difference between these strategies and the third ranked strategy “Do Nothing” or “Status Quo” (ranking weight: 0.245 – “Scenario 4 Impacts” in Table 22.P4) is significant. Finally, the “Retreat” option (ranking weight: 0.198) is considered by Workshop participant P3 as an unattractive strategy for Little Anse.

Utility Curve

Roads (L: .446)

.0

.2

.4

.6

.8

1.0

2,000,000

Xaxis

Page 9 of 102/19/2014 11:07:08 PM

Page 22: Adaptation Support Community Case Study: Little …coastalchange.ca/images/stories/Documents_Tab/little...C-Change Community of Practice Little Anse Case Study: Volume II Université

C-Change Community of Practice Little Anse Case Study: Volume II

Université Sainte-Anne Workshop 22 of 30 May 24, 2013

Table 22.P4. Final Adaptation Strategies Ranking for P4 (Source: Expert Choice 2010)

P5. University Director. The inputs provided in graphic form for Workshop participant P5 are illustrated in the Figure 9.P5 utility function below. Based on these graphical inputs, Road closures are highly risk seeking, i.e., highly concave, as for the original case study utility function of Figure 3. This implies that the participant’s valuation of Road closure asset impacts are lower than would be considered as ‘risk neutral’ from the highest road closure estimate of damage position of $0.8million or asset position of $1.7 million (at the lowest utility valuation of 0), to the lowest road closure impacts of $0 damage or asset position of $2.3 million (at the highest utility valuation of 1). Like Workshop participant P1’s input, participant P5 is relatively intolerant of road closures of greater than 0.6km , while utility values less than 0.25km exhibit a sharp rate of valuation (utility) increase. Figure 9.P5 below illustrates a marginally increasing rate of improved utility as road closures diminish and road assets increase. It is of interest for this participant to avoid high levels (greater than 0.25km) of road closures.

Figure 9.P5. Utility Curve: Road Closures Assets) ($) for P5 (Source: Expert Choice 2010)

The application of the Road closures utility function of Figure 9.P5 for Workshop participant P5, together with the participant’s indicated Community Profile priorities of Table 14.P5, determine the ranked preferences for the selected alternative adaptation strategies using the AHP methodology (Saaty 1980) for the formulated case of the Little Anse Storm Scenarios IV.

Synthesis: Summary

Synthesis with respect to: G o a l:A d a p ta t io n o f L it t le A n s e c o m m u n it y to s to rm s u rg e e v e n t s

S c e n a rio 4 I . . . .2 4 5N e w B W a rm . . . .2 7 7R e t re a t ( S 4 ) .1 9 8R o a d b u ild u . . . .2 8 1

Utility Curve

Roads (L: .446)

.0

.2

.4

.6

.8

1.0

2,000,000

Xaxis

Page 9 of 102/19/2014 11:15:52 PM

Page 23: Adaptation Support Community Case Study: Little …coastalchange.ca/images/stories/Documents_Tab/little...C-Change Community of Practice Little Anse Case Study: Volume II Université

C-Change Community of Practice Little Anse Case Study: Volume II

Université Sainte-Anne Workshop 23 of 30 May 24, 2013

The results of these rankings are provided in Table 23.P5 below. As indicated in the weights of Table 23.P5 below, the dominant preferred adaptation strategy for Workshop participant P5 is clearly the “Accommodate” (Build new road) with ranking weight: 0.292. The second and third preferred strategies are the “Protect” (Build new breakwater arm) strategy, and the “Do nothing” or “Status Quo” option (“Scenario 4 Impacts” in Table 23.P5) (ranking weights: 0.260). The difference between the top preference and the other strategies is appreciable. The lowest preference belongs to the “Retreat” option (ranking weight: 0.188) which Workshop participant P5 considers as a lower weighted “last resort” strategy compared to all the other adaptation options.

Table 23.P5. Final Adaptation Strategies Ranking for P5 (Source: Expert Choice 2010)

P6. Municipal Government Director. The inputs provided in graphic form for Workshop participant

P6 are illustrated in the Figure 10.P6 utility function below. Based on these graphical inputs, Road closures are risk seeking, i.e., concave, as for the original case study utility function of Figure 3. This implies that the participant’s utility valuation of Road closure asset impacts are lower than would be considered as ‘risk neutral’ from the highest road closure estimate of damage position of $0.8million or asset position of $1.7 million (at the lowest utility valuation of 0), to the lowest road closure impacts of $0 damage or asset position of $2.3 million (at the highest utility valuation of 1). Much like Workshop participant P3, Workshop participant P6 is relatively intolerant of road closures of greater than 0.75km, while utility values less than 0.3 0km exhibit an increasing valuation (utility) increase. Figure 10.P6 below illustrates a marginally increasing rate of improved utility as road closures diminish and road assets increase. It is of interest for this participant to avoid higher levels (greater than 0.30km) of road closures.

Figure 10.P6. Utility Curve: Road Closures Assets) ($) for P6 (Source: Expert Choice 2010)

Synthesis: Summary

Synthesis with respect to: G o a l:A d a p ta t io n o f L it t le A n s e c o m m u n it y to s to rm s u rg e e v e n t s

S c e n a rio 4 I . . . .2 6 0N e w B W a rm . . . .2 6 0R e t re a t ( S 4 ) .1 8 8R o a d b u ild u . . . .2 9 2

Utility Curve

Roads (L: .446)

.0

.2

.4

.6

.8

1.0

2,000,000

Xaxis

Page 9 of 102/19/2014 11:23:25 PM

Page 24: Adaptation Support Community Case Study: Little …coastalchange.ca/images/stories/Documents_Tab/little...C-Change Community of Practice Little Anse Case Study: Volume II Université

C-Change Community of Practice Little Anse Case Study: Volume II

Université Sainte-Anne Workshop 24 of 30 May 24, 2013

The application of the Road closures utility function of Figure 10.P6, together with the participant’s indicated Community Profile priorities of Table 16.P6, determine the ranked preferences for the selected alternative adaptation strategies in the case of the Little Anse flooding scenarios. The ranking results are provided in Table 24.P6 below. As indicated in the weights and bars of Table 24.P6, the dominant preferred adaptation strategy for Workshop participant P6 is the “Accommodate” strategy – Build a new road (ranking weight: 0.290). This is followed by the “Do Nothing” or “Status Quo” (ranking weight: 0.255 – “Scenario 4 Impacts” in Table 24.P6) and the “Protect” strategy – Build new breakwater arm (ranking weight: 0.254). Finally, the least preferred “Retreat” option (ranking weight: 0.202) is considered by Workshop participant P6 as an unattractive strategy for Little Anse.

Table 24.P6. Final Adaptation Strategies Ranking for P6 (Source: Expert Choice 2010)

P7. University Researcher. The inputs provided in graphic form for Workshop participant P7 are

illustrated in the Figure 11.P7 utility function below. Based on these graphical inputs, Road closures are risk seeking, i.e., concave, as for the original case study utility function of Figure 3. This implies that the participant’s utility valuation of Road closure asset impacts are lower than would be considered as ‘risk neutral’ from the highest road closure estimate of damage position of $0.8 million or asset position of $1.7 million (at the lowest utility valuation of 0), to the lowest road closure impacts of $0 damage or asset position of $2.3 million (at the highest utility valuation of 1). As for the case of Workshop participant P3, the Workshop participant P7 is relatively intolerant of road closures of greater than 0.75km, while utility values less than 0.3 0km exhibit an increasing valuation (utility) increase. Figure 11.P7 below illustrates a marginally increasing rate of improved utility as road closures diminish and road assets increase. It is of interest for this participant to avoid higher levels (greater than 0.30km) of road closures.

Figure 11.P7. Utility Curve: Road Closures Assets) ($) for P7 (Source: Expert Choice 2010)

Synthesis: Summary

Synthesis with respect to: Goal:Adaptation of Little Anse community to storm surge events

Overall Inconsistency = .01

Scenario 4 Impacts .255New BW arm (S4) .254Retreat (S4) .202Road build up (S4) .290

Utility Curve

Roads (L: .446)

.0

.2

.4

.6

.8

1.0

2,000,000

Xaxis

Page 9 of 102/19/2014 11:30:04 PM

Page 25: Adaptation Support Community Case Study: Little …coastalchange.ca/images/stories/Documents_Tab/little...C-Change Community of Practice Little Anse Case Study: Volume II Université

C-Change Community of Practice Little Anse Case Study: Volume II

Université Sainte-Anne Workshop 25 of 30 May 24, 2013

The application of the Road closures utility function of Figure 11.P7, together with the participant’s indicated Community Profile priorities of Table 18.P7, determine the ranked preferences for the selected alternative adaptation strategies in the case of the Little Anse flooding scenarios. The ranking results are provided in Table 25.P7 below. As indicated in the weights and bars of Table 25.P7, the dominant preferred adaptation strategy for Workshop participant P6 is the “Accommodate” strategy – Build a new road (ranking weight: 0.279). This is followed by the “Protect” strategy – Build new breakwater arm (ranking weight: 0.272) and the “Do Nothing” or “Status Quo” (ranking weight: 0.249 – “Scenario 4 Impacts” in Table 25.P7). Finally, the least preferred “Retreat” option (ranking weight: 0.200) is considered by Workshop participant P7 as an unattractive strategy for Little Anse.

Table 25.P7. Final Adaptation Strategies Ranking for P7 (Source: Expert Choice 2010)

2.5 Workshop participants Comparison of Workshop participants’ Adaptive Strategies Ranking Figure 12 below summarizes the adaptive strategies ranking results for the seven Workshop participants and compares them to the group’s overall average and that of the original Case Study – Guide (Volume I). These results demonstrate that there is a general overall preference for the “Accommodate” strategy over the “Protect” strategy in 5 of the 7 participants’ inputs. The Retreat strategy is everywhere ranked as the least preferable option and has similar weight across all Workshop participants. In all of these cases, the Status Quo/Do Nothing strategy was regarded as being significantly weaker as an adaptation strategy for all Workshop participants behind the “Accommodate” (Build new road) and the “Protect” (Build new breakwater arm) adaptation strategies. This indicates clearly from the indicated priority weighting and utility inputs that Workshop participants prefer that it is better to act than not to act, i.e., the opportunity cost of not acting, or “doing nothing” is significant for all participants. The results of the four Workshop participants compare well with the original case study outcomes and are reflected in the group average as shown in Figure 12 and Table 26 below. In ranked order, average adaptive strategies ranking for the 7 Workshop participants are as follows:

Adaptation Strategy Ranking

Adaptiation Strategy Average Strategy Weight

Number of First Rankings

1 Accommodate – Build New Road 29% 5 of 7 2 Protect – Build New Breakwater Arm 28% 2 of 7 3 Do Nothing – Status Quo 25% 0 of 7 4 Retreat – Move Away 18% 0 of 7

Table 26. Adaptation Strategies Ranking for Workshop Participants

Synthesis: Summary

Synthesis with respect to: G o a l:A d a p ta t io n o f L it t le A n s e c o m m u n it y to s to rm s u rg e e v e n t s

S c e n a rio 4 I . . . .2 4 9N e w B W a rm . . . .2 7 2R e t re a t ( S 4 ) .2 0 0R o a d b u ild u . . . .2 7 9

Page 26: Adaptation Support Community Case Study: Little …coastalchange.ca/images/stories/Documents_Tab/little...C-Change Community of Practice Little Anse Case Study: Volume II Université

C-C

Un

3. thecomCom As

Change Com

iversité Sain

Discuss

This rep Little Anse

mmunity resmmunity of

noted in this (1) com

pill (2) valu

sev

mmunity of P

nte-Anne Wo

Figure 1

sion

port compilecoastal adapidents and cPractice me

s report, the

mmunity prolars of the co

ue-based intvere coastal s

P1P2P3P4P5P6P7

AverageCase Study

Wor

ksho

p Pa

rtic

ipan

t A

Practice

orkshop

12. Worksho

es and compaptation problommunity re

eetings held a

Workshop p

ofile prioritieommunity; a

terpretation ostorms.

0.000 01234567ey

LittlAdaptat

Do Nothin

2

op participa

ares the origlem with theepresentativat the Unive

participants p

es for the envand

of Little Ans

0.050 0Stra

e Anse Wtion State

ng Retre

26 of 30

ants’ Adapt

ginal illustrate results of thes as Worksrsité Sainte-

provided the

vironmental,

se Road Clos

.100 0.1ategy Prefer

Workshoegies Ra

eat Acc

L

tation Strate

tive case stuhe inputs proshop particip-Anne on Ma

e following i

, economic,

sure impacts

150 0.2rence Weigh

op Particanking C

commodate

Little Anse C

egies Ranki

udy (Guide –ovided by sepants in the Cay 24, 2013.

individual in

social, and c

s that are exp

200 0.25hting

cipants'omparis

e Prote

Case Study: V

May 24, 2

ings

– Volume I) reven (7) LittlC-Change

nformation:

cultural susta

pected to res

50 0.30

son

ect

Volume II

013

results for le Anse

ainability

sult from

0

Page 27: Adaptation Support Community Case Study: Little …coastalchange.ca/images/stories/Documents_Tab/little...C-Change Community of Practice Little Anse Case Study: Volume II Université

C-Change Community of Practice Little Anse Case Study: Volume II

Université Sainte-Anne Workshop 27 of 30 May 24, 2013

This feedback was used in the C-Change problem solving framework (described in the Volume I – Guide) to provide ranking evaluations of a set of strategies for Little Anse adaptation to severe coastal storms. These adaptation strategies included:

1. Protect – build a new breakwater arm to reduce the impact of storms; 2. Accommodate – build a new escape route road out of the community to service residents; 3. Retreat – permanently move residents from Little Anse, and, lastly 4. Status Quo/Do Nothing – the current strategy in place.

The results of the evaluations of the Workshop participants clearly and overwhelmingly indicate decision support for adaptation action as opposed to inaction. Participants’ results reject the strategy of “Retreat” that would require residents move away from the community. Participants also rejected the option to “Do nothing” or “Status Quo”. This strategy, in fact, characterizes the current situation that is the strategy that is being applied now in Little Anse. For the Workshop participants, “Doing nothing” is a less preferred option as is indicated in the results provided above. Participant’s Recommendation: The preferred adaptation action of the Workshop participants is to “Accommodate” defined by the strategy of building a new exit road for Little Anse that would allow residents an escape route in the event of main road closure and being cut off as a consequence – an event that is becoming more frequent with storms flooding out the road and making it impassable at the crossing of the barachois lake. Overall, these results reflect Workshop participants’ inherent long-term perspective to preparing and reducing environmental event damage and relief to Little Anse.

This document, Volume II of a series of documents derived from the C-Change Community of Practice research, describes the results of the Little Anse Workshop participants’ feedback. It follows from the Volume I – Guide and the descriptive process of C-Change decision support that was used to structure the Workshop participants’ feedback as presented here. Finally, this document forms the basis of direct feedback to the political leaders of the community – at all levels of government: municipal, provincial, and federal. At the May 2013 meetings, Workshop participants indicated politicians at all levels should be informed of the resulting decision support process of the C-Change Workshop and its results in order to promote and to provoke immediate action for applied adaptation and planning as recommended for the coastal community of Little Anse and the failure of its breakwater. Volume III of this series presents letters of petition to local governance representatives on behalf of Workshop participants, community members, and the C-Change Community of Practice. Acknowledgements The C-Change project acknowledges the support and valuable participation of all of the Workshop participants and their valuable feedback, input, and discussion in this analysis toward implementing adaptation for Little Anse. Special thanks to C-Change Partners at the Université Sainte-Anne, and to the Municipality of the County of Richmond for their key role in the support of this work.

Ottawa February 2014

Page 28: Adaptation Support Community Case Study: Little …coastalchange.ca/images/stories/Documents_Tab/little...C-Change Community of Practice Little Anse Case Study: Volume II Université

C-Change Community of Practice Little Anse Case Study: Volume II

Université Sainte-Anne Workshop 28 of 30 May 24, 2013

References Baird & Associates. 2010. Analysis of the Little Anse Breakwater. Unpublished report to the Municiaplity

of Richmond County. Black, R.A., Bruce, J.P., Egener, I.D.M. 2010. Adapting to Climate Change: A Risk-based Guide for Local

Governments. Volume 1. October. Natural Resources Canada, Climate Change Impacts & Adaptation Division. 29p.

Boudreau, A. and Thériault, M. 2012. Isle Madame Historical Documentation and Storm Monitoring

Project 2011-2012. Final C-Change Report. Université Sainte Anne, Marine Research Centre 2011-2012. 38p.

Burke/Longhurst Ancestry 2013. Burke/Longhurst family genealogy. Accessed February 9, 2014 at:

http://www.longhurst.ca/index.html C-Change COP. 2014a. Adaptation Support Community Case Study: Little Anse, Isle Madame, Cape

Breton. Volume I – Guide. February. C-Change Working Paper. 50p. C-Change COP. 2014b. Adaptation Support Community Case Study: Little Anse, Isle Madame, Cape

Breton. Volume III – News Release. February. C-Change Working Paper. 50p. ECBC. 2012. MINISTER MACKAY ANNOUNCES SUPPORT FOR COMMUNITY

INFRASTRUCTURE IN RICHMOND AND INVERNESS COUNTIES. News Release. Enterprise Cape Breton Corporation. December 8. Accessed February 8, 2014 at: http://www.ecbc-secb.gc.ca/index.php?cid=12&pid=325&lang=e

FCM. 2012. Municipal Climate Change Action Plan Guidebook: Canada-Nova Scotia Agreement on the Transfer of Federal Gas Tax Funds. Federation of Canadian Municipalities. Accessed October 26, 2012 at: https://fcm.ca/Documents/tools/PCP/municipal_climate_change_action_plan_guidebook_EN.pdf

Fisheries and Oceans Canada. 2004. Harbour Improvements for Cape Breton. Harbour Authorities Forum.

10(2), 4. Accessed February 15, 2014 at: http://www.dfo-mpo.gc.ca/sch-ppb/forum/pdf/10.2-eng.pdf Hartt, M. 2011. Geographic Information Systems and System Dynamics: Modelling the Impacts of Storm

Damage on Coastal Communities. M.Sc. Thesis Systems Science, University of Ottawa. Accessed September 30, 2012 at: http://www.coastalchange.ca/images/stories/Documents_Tab/Hartt_FinalThesis_2011.pdf

Hatcher, S. V., Forbes, D. L., and Manson, G. K. 2011. Coastal Hazard Assessment for Adaptation

Planning in an Expanding Arctic Municipality. C-Change Working Paper No. 23. June. 15p. Accessed September 30, 2012 at: http://www.coastalchange.ca/images/stories/Documents_Tab/workingpaper23_hatcherforbes_manson_2011.pdf

Leung, K.L. 2010. Adaptation Measures to Climate Change and Sea Level in Georgetown, Guyana. M.Sc.

Thesis Urban and Regional Planning, UWI (St. Augustine). 143p. Accessed September 29, 2012 at: http://coastalchange.ca/download_files/community_documents/Kira%20Lise%20C-Change%20Georgetown%20Case%20Study.pdf

Page 29: Adaptation Support Community Case Study: Little …coastalchange.ca/images/stories/Documents_Tab/little...C-Change Community of Practice Little Anse Case Study: Volume II Université

C-Change Community of Practice Little Anse Case Study: Volume II

Université Sainte-Anne Workshop 29 of 30 May 24, 2013

Mostofi Camare, H. 2011. Multicriteria decision evaluation of adaptation strategies for vulnerable coastal

communities. MSc thesis, Systems Science, University of Ottawa, Ottawa, Canada. Accessed September 30, 2012 at: http://www.coastalchange.ca/images/stories/Documents_Tab/Mostofi_FinalThesis_2011.pdf

Municipality of the County of Richmond. 2013a. Municipal Climate Change Action Plan. November. 80p.

Accessed Febraury 9, 2014 at: http://www.richmondcounty.ca/images/News%20&%20Events/MCCAP%202013%20final%20report.pdf

Municipality of the County of Richmond. 2013b. Emergency Management Plan. February. 14 sections.

Accessed Febraury 9, 2014 at: http://www.richmondcounty.ca/images/EMO/RICH%20CO%20E%20PLAN%202013.pdf .

Municipality of the County of Richmond. 2013c. Cape Breton’s Heritage Coast. Accessed Febraury 9, 2014

at: http://www.capebretonsheritagecoast.com . Municipality of the County of Richmond. 2010. Richmond Integrated Community Sustainability Plan

(ICSP) – Final Submission. March. 61p. Accessed October 26, 2012 at: http://www.richmondcounty.ca/images/pdf/public_works/RICHMOND%20ICSP%20-%20Final%20Submission%20-%20March%202010.pdf

New Brunswick. 2012. Perth-Andover and Tobique First Nation Mitigation Study – Final Report.

Submitted to the Government of New Brunswick. August 31. 16p. Accessed October 23, 2012 at: http://www2.gnb.ca/content/dam/gnb/Departments/env/pdf/Publications/MitigationStudyFinalReportPerthAndover.pdf

Nova Scotia. 2014a. Nova Scotia Emergency Management Office. Accessed Febraury 9, 2014 at:

http://novascotia.ca/just/EMO/ . Nova Scotia. 2014b. Nova Scotia Emergency Management Act. Accessed Febraury 9, 2014 at:

http://nslegislature.ca/legc/statutes/emergmsr.htm . Pakdel, S. 2011. Spatial–temporal modelling for estimating impacts of storm surge and sea level rise on

coastal communities: The Case of Isle Madame in Cape Breton, Nova Scotia, Canada. M.Sc. Thesis Systems Science, University of Ottawa. Accessed October 26, 2012 at: http://www.coastalchange.ca/images/stories/Documents_Tab/Pakdel_FinalThesis_2010.pdf

Public Safety Canada. 2014. Emergency Measures Act. Accessed February 9, 2014 at: http://laws-

lois.justice.gc.ca/PDF/E-4.56.pdf . Public Safety Canada. 2009. Federal Policy for Emergency Policy Management. Accessed February 9, 2014

at: http://www.publicsafety.gc.ca/cnt/rsrcs/pblctns/plc-mrgnc-mngmnt/plc-mrgnc-mngmnt-eng.pdf . Public Safety Canada. 2008. Canada’s National Disaster Mitigation Strategy. January. Accessed February

9, 2014 at: http://laws-lois.justice.gc.ca/PDF/E-4.56.pdf .

Page 30: Adaptation Support Community Case Study: Little …coastalchange.ca/images/stories/Documents_Tab/little...C-Change Community of Practice Little Anse Case Study: Volume II Université

C-Change Community of Practice Little Anse Case Study: Volume II

Université Sainte-Anne Workshop 30 of 30 May 24, 2013

RABA. 2014. Richmond Amateur Baseball Association. The Front Page. Accessed February 9, 2014 at: http://esportsdesk.com/leagues/front_pageesdNew.cfm?clientID=5405&leagueID=20678

Raiffa,H. 1968. Decision Analysis. Harvard University. Richardson, G. R. A. (2010). Adapting to Climate Change: An Introduction for Canadian Municipalities.

Ottawa, Ont. Natural Resources Canada, 40 p. Saaty, A. 1980. The Analytic Hierarchy Method. McGraw Hill, New York. Stantec. 2010. City of Charlottetown: Integrated Community Sustainability Plan. February. 115p. Accessed

October 26, 2012 at: http://www.city.charlottetown.pe.ca/pdfs/FinalPlanAdoptedByCouncil.pdf Statistics Canada. 2011. Census of Population. Nova Scotia Community Counts website. Access February

9, 2014 at: http://www.novascotia.ca/finance/communitycounts/profiles/community/default.asp?gnew=&table=&acctype=0&chartid=&mapid=&dcol=&sub=&ptype=geo&tid=&gview=1&glevel=com&yearid=2011&gnum=com1602

The Hawk, 2010. Transportation minister to tour Little Anse area to look at storm damage. Accessed: 20/11/2010 at: http://www.1015thehawk.com/index.php/2010051129305/Local-News/transportation- minister-to-tour-little-anse-area-to-look-at-storm- damage.html?option=com_content&id=29305&lang=en&view=article&Itemid=107& catid=51&fontstyle=f-larger

The Reporter. 2010a. No help for wharf and breakwater. Accessed 12/11/2010 at:

http://www.porthawkesburyreporter.com/porthawkesburyreporter.com/stories.asp?i d=2979 The Reporter. 2010b. No help for Little Anse. Accessed 28/03/2011:

http://www.porthawkesburyreporter.com/stories.asp?id=5294