activity-based costing. over- and undercosting overcosting – a product consumes a low level of...
TRANSCRIPT
Activity-Based Costing
Undercosting and Overcosting
• Consider the costing of a bill for four friends who go for dinner. • Each diner orders separate entrees, desserts, and drinks. • Bill details are as follows:
Entrée Dessert Drinks Total Emma $11 $0 $4 $15 J ames 20 8 14 42 J essica 15 4 8 27 Matthew 14 4 6 24 Total $60 $16 $32 $108
Average $15 $4 $8 $27
Over- and Undercosting
• Overcosting – a product consumes a low level of resources (costs) but is allocated high costs per unit
• Undercosting – a product consumes a high level of resources (costs) but is allocated low costs per unit
Direct versus Indirect Costs
Traditional Costing
All production costs All production costs except direct materials except direct materials
and direct labor are and direct labor are lumped together in one lumped together in one
overhead cost pool.overhead cost pool.
Traditional Costing
All production costs All production costs except direct materials except direct materials
and direct labor are and direct labor are lumped together in one lumped together in one
overhead cost pool.overhead cost pool.
Activity-Based Costing
An effort is made to An effort is made to account for as many account for as many costs as possible as costs as possible as
direct costs of direct costs of production.production.
Activity-Based Costing
An effort is made to An effort is made to account for as many account for as many costs as possible as costs as possible as
direct costs of direct costs of production.production.
IndirectIndirectCostsCosts
ActivityAn event that causes the consumption of overhead
resources.
Activity Cost Pool
A “cost bucket” in which costs related to a particular activity
measure are accumulated.
$
$
$ $
$$
How Costs are Treated UnderActivity–Based Costing
Activity MeasureActivity Measure
An allocation basein an activity-based
costing system.
An allocation basein an activity-based
costing system.
How Costs are Treated UnderActivity–Based Costing
The term cost driver is also used to refer to an
activity measure.
The term cost driver is also used to refer to an
activity measure.
Homogeneous Activity Cost Pools
A homogeneous cost pool is a grouping of overhead costs in which each cost component is consumed in roughly the same proportion by each product line.
A homogeneous cost poolA homogeneous cost pooluses a single cost driver.uses a single cost driver.
Simple countof the number oftimes an activity
occurs.
Transactiondriver
A measureof the amountof time neededfor an activity.
Durationdriver
Two common types of activity measures:
How Costs are Treated UnderActivity–Based Costing
Traditional Product-Costing System
• Aerotech produces three complex printed circuit boards referred to as Mode I, Mode II, and Mode III.
• The following information is obtained from company records:
• Aerotech produces three complex printed circuit boards referred to as Mode I, Mode II, and Mode III.
• The following information is obtained from company records:
Mode I Mode II Mode IIIProduction: Units 10,000 20,000 4,000 Runs 1 of 10,000 4 of 5,000 10 of 400
Traditional Product-Costing System
Additional information includes:
Mode I Mode II Mode IIIDirect materials 50.00$ 90.00$ 20.00$ Direct labor (hr/board) 3 4 2 Setup time (hr/run) 10 10 10 Machine time (hr/board) 1 1.25 2
Manufacturing overhead is determined as follows
Traditional Product-Costing System
Budgeted manufacturing overhead Budgeted manufacturing overhead $3,894,000 $3,894,000 Budgeted direct-labor hours 118,000Budgeted direct-labor hours 118,000 = $33 per hour= $33 per hour
Traditional Product-Costing System
With these product costs, Aerotech established target selling prices (Cost × 125%).
209.00 x 1.25
Traditional Product-Costing System
Aerotech wishes to see what target selling prices would be suggested when using activity-based
costing.
Aerotech wishes to see what target selling prices would be suggested when using activity-based
costing.
Let’s see how ABC works.Let’s see how ABC works.
Activity Based Costing System (ABC)
ABC systems follow a two-stage
procedure to assign overhead costs to
products.
Assigningoverhead to products is
a
difficult process. I agree!
Activity Based Costing System (ABC)
ABC systems follow a two-stage
procedure to assign overhead costs to
products.
Let’s beginby identifying
our major activities.
Stage OneIdentify significant
activities and assign overheadcosts to each activity in
proportion to resources used.
Stage OneIdentify significant
activities and assign overheadcosts to each activity in
proportion to resources used.
Activity Based Costing System (ABC)
ABC systems follow a two-stage
procedure to assign overhead costs to
products.
Overhead assigned to activities are called
“activity cost pools.”
Stage TwoIdentify cost drivers
appropriate to each activityand allocate overhead to
the products.
Stage TwoIdentify cost drivers
appropriate to each activityand allocate overhead to
the products.
Overhead CostsOverhead Costs
Total budgeted cost = $3,894,000Total budgeted cost = $3,894,000
ActivityActivityCostCostPoolsPools
MachineryMachinerycost poolcost pool
$1,212,600$1,212,600
SetupSetupcost poolcost pool$3,000$3,000
EngineeringEngineeringcost poolcost pool$700,000$700,000
FacilityFacilitycost poolcost pool$507,400$507,400
UnitLevel
BatchLevel
Product-Sustaining
LevelFacilityLevel
Identificationof ActivityCost Pools
Identificationof ActivityCost Pools
ActivityActivitymust bemust bedone ondone oneach uniteach unit
producedproduced..
ActivityActivityperformedperformed
on eachon eachbatchbatch
produced.produced.
Activities needed to supportActivities needed to supportan entire product linean entire product line Activities that support theActivities that support the
organization as a whole.organization as a whole.
Overhead CostsOverhead Costs
Total budgeted cost = $3,894,000Total budgeted cost = $3,894,000
ActivityActivityCostCostPoolsPools
MachineryMachinerycost poolcost pool
$1,212,600$1,212,600
SetupSetupcost poolcost pool$3,000$3,000
EngineeringEngineeringcost poolcost pool$700,000$700,000
FacilityFacilitycost poolcost pool$507,400$507,400
MoreCostPools
UnitLevel
BatchLevel
Product-Sustaining
LevelFacilityLevel
Identificationof ActivityCost Pools
Identificationof ActivityCost Pools
Receiving/InspectionReceiving/Inspectioncost poolcost pool $200,000$200,000
Material-HandlingMaterial-Handlingcost pool cost pool $600,000$600,000
Quality-AssuranceQuality-Assurancecost pool cost pool $421,000$421,000
Packaging/ShippingPackaging/Shippingcost poolcost pool $250,000$250,000
MachineryMachinerycost poolcost pool
$1,212,600$1,212,600
SetupSetupcost poolcost pool$3,000$3,000
EngineeringEngineeringcost poolcost pool$700,000$700,000
FacilityFacilitycost poolcost pool$507,400$507,400
UnitLevel
BatchLevel
Product-Sustaining
LevelFacilityLevel
Various overheadVarious overheadcosts relatedcosts relatedto to machinerymachinery
Maintenance
Depreciation
Computer Support
Lubrication
Electricity
Calibration
Machinery Cost PoolMachinery Cost PoolTotal budgeted cost = $1,212,600
ActivityActivitycostcostpoolpool
STAGE ONESTAGE ONE
CalculateCalculatethe poolthe pool
raterate
Budgeted Machinery Costs $1,212,600 Budgeted Machine Hours 43,000 $28.20/hour$28.20/hour
CostCostAssignmentAssignment
STAGE TWOSTAGE TWO
=
=
Calculation ofCalculation oftotal total setup costsetup cost
Setup Cost PoolSetup Cost PoolTotal budgeted cost = $3,000
ActivityActivitycostcostpoolpool
STAGE ONESTAGE ONE
CalculateCalculatethe poolthe pool
raterate
Budgeted Setup Costs $3,000Planned Production Runs 15 runs $200 per run$200 per run
CostCostAssignmentAssignment
STAGE TWOSTAGE TWO
=
=
Various overheadVarious overheadcosts relatedcosts related
to to engineeringengineering
Engineering salaries
Engineering supplies
Engineering software
Depreciation
Engineering Cost PoolEngineering Cost PoolTotal budgeted cost = $700,000
ActivityActivitycostcostpoolpool
STAGE ONESTAGE ONE
Allocate basedAllocate basedon on engineeringengineering
transactionstransactions
CostCostAssignmentAssignment
STAGE TWOSTAGE TWO
Engineering Cost PoolEngineering Cost PoolTotal budgeted cost = $700,000
Various overheadVarious overheadcosts relatedcosts relatedto to generalgeneraloperationsoperations
Plant depr.
Plant mgmt.
Plant maint.
Property taxes
Insurance
Security
Facility Cost PoolFacility Cost PoolTotal budgeted cost = $507,400
ActivityActivitycostcostpoolpool
STAGE ONESTAGE ONE
CalculateCalculatethe poolthe pool
raterate
Budgeted Facilities Cost $507,400Budgeted Direct-Labor Hours 118,000 $4.30/hour$4.30/hour
CostCostAssignmentAssignment
STAGE TWOSTAGE TWO
=
=
Product Cost from ABCHere are the new product costs so far . . .
Additional ABC Information
Mode I Mode II Mode IIIReceiving Lots 18 72 210 Material Handling Moves 21 90 189 Quality/Inspections 40 80 80 Packaging/Shipments 8 60 132
Percentages for the above information are as follows:
Other Overhead Costs
Board Overhead × % ÷ Units = Cost/UnitMode I 200,000$ × 6% ÷ 10,000 = 1.20$ Mode II 200,000 × 24% ÷ 20,000 = 2.40 Mode III 200,000 × 70% ÷ 4,000 = 35.00
Receiving and Inspection Cost Pool
Board Overhead × % ÷ Units = Cost/UnitMode I 600,000$ × 7% ÷ 10,000 = 4.20$ Mode II 600,000 × 30% ÷ 20,000 = 9.00 Mode III 600,000 × 63% ÷ 4,000 = 94.50
Material-Handling Cost Pool
Board Overhead × % ÷ Units = Cost/UnitMode I 421,000$ × 20% ÷ 10,000 = 8.42$ Mode II 421,000 × 40% ÷ 20,000 = 8.42 Mode III 421,000 × 40% ÷ 4,000 = 42.10
Quality-Assurance Cost Pool
Board Overhead × % ÷ Units = Cost/UnitMode I 250,000$ × 4% ÷ 10,000 = 1.00$ Mode II 250,000 × 30% ÷ 20,000 = 3.75 Mode III 250,000 × 66% ÷ 4,000 = 41.25
Packaging and Shipping Cost Pool
Board Overhead × % ÷ Units = Cost/UnitMode I 250,000$ × 4% ÷ 10,000 = 1.00$ Mode II 250,000 × 30% ÷ 20,000 = 3.75 Mode III 250,000 × 66% ÷ 4,000 = 41.25
Packaging and Shipping Cost Pool
Board Overhead × % ÷ Units = Cost/UnitMode I 421,000$ × 20% ÷ 10,000 = 8.42$ Mode II 421,000 × 40% ÷ 20,000 = 8.42 Mode III 421,000 × 40% ÷ 4,000 = 42.10
Quality-Assurance Cost Pool
Other Overhead Costs
Board Overhead × % ÷ Units = Cost/UnitMode I 200,000$ × 6% ÷ 10,000 = 1.20$ Mode II 200,000 × 24% ÷ 20,000 = 2.40 Mode III 200,000 × 70% ÷ 4,000 = 35.00
Receiving and Inspection Cost Pool
Board Overhead × % ÷ Units = Cost/UnitMode I 600,000$ × 7% ÷ 10,000 = 4.20$ Mode II 600,000 × 30% ÷ 20,000 = 9.00 Mode III 600,000 × 63% ÷ 4,000 = 94.50
Material-Handling Cost Pool
$14.82$14.82
Product Cost from ABCThese are the new product costs when Aerotech uses
ABC.
Product DiversityBoth original and ABC target selling prices are based on
(Cost × 125%).
[$209.00 × 1.25] [$183.44 × 1.25]
The selling price of Mode I and II are reducedThe selling price of Mode I and II are reducedand the selling price for Mode III is increased.and the selling price for Mode III is increased.
Product DiversityCan you identify any problems Aerotech is likely to face
as a result of this distortion?
Traditional costing understates the costTraditional costing understates the costof complex, low volume products.of complex, low volume products.
Activity-Based Management
• A method of management that used ABC as an integral part in critical decision-making situations, including:– Pricing decisions– Cost reduction and process improvement
decisions– Planning and managing activities