acec presentation i85-385 kneece · 2020-02-15 · rfq published –july 1, 2013 final rfp released...

63
IͲ85/385 INTERCHANGE IMPROVEMENTS ^/'EͲh/> WZK:d DECEMBER 2, 2015

Upload: others

Post on 23-Jun-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

I 85/385 INTERCHANGEIMPROVEMENTS

DECEMBER 2, 2015

Page 2: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

PROJECT TEAMOwner

Contractor

Designers

Page 3: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

Carolina Bays ParkwayHorry County

Headquartered in Denver, ColoradoAnnual construction volume of $1 billionRanked eleventh for Top TransportationContractors and 14 of 50 for Top DomesticHeavy Contractors by ENR (2015)Constructing Carolina Bays Parkway

Reconstruction ofI 880/SR92 interchange

I 85/Yadkin River BridgeSalisbury, NC

SR60 Tampa Airport/Interchanges

Page 4: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

Headquartered in San Antonio, Texas; ranked 29 on ENR 2015 Top 400ContractorsIn the last five years has completed four DB projects with a constructionvalue of $3.2 billionRecently completed widening of I 20 in Richland County

I 20 WideningRichland County

Dallas County IH 635Interchange High FiveDallas/Fort Worth Connector Loop 375 at I 10 Interchange

Page 5: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

PROJECT HISTORYBegan in 2008 with F&H selected forinterchange designRFQ published – July 1, 2013Final RFP released – March 27, 2014Proposals Accepted

Design build proposal – July 21, 2014Cost Proposal – August 6, 2014Selection made – August 12, 2014

Notice to Proceed #1 – October 27, 2014

Page 6: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

THE INTERCHANGE

Page 7: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

THE INTERCHANGE

Page 8: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

GENERAL SCHEDULE

NTP1 – October 27, 2014NTP2 – December 14, 2015Contract Completion time – 1035 days ( September 2018)

Overall Project Delivery Time 2008 to 2018 = 10 Years

Page 9: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

Civil Engineering ConsultingServices, Inc. Roadway, Drainage, Bridge Design

T.Y. Lin International Bridge Design

Stantec Consulting Services, Inc. Maintenance of Traffic, Bridge & Wall DesignMead & Hunt, Inc. Bridge Design, Survey

ECS, Ltd. Geotechnical DesignProperty Acquisitions & Negotiations, Inc. Right of Way Acquisition Services

Thompson Engineering Geotechnical Exploration and Testing

Complete Public Relations Public/Community Relations

ARM Environmental Services, Inc. HazmatIndependent Mapping Consultants Mapping

THE DESIGN TEAM

Page 10: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

EXISTING INTERCHANGEDEFICIENCIES

LOOP RAMPSWEAVE ON CDSINGLE LANE RAMP I 85 SB TO I 385 NBLANE DROPS ON I 85 BETWEEN I 385 AND PELHAM ROAD

Page 11: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

NEW INTERCHANGE

Page 12: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

PROJECT STATISTICS

$231 Million for Design, ROW, and Construction7.1 miles of Mainline Interstate10 miles of Ramps2.9 miles of Collector/Distributor Roads1.9 miles of Local Streets and Roads4.6 miles of Interstate Rehabilitation39 Retaining Walls12 Bridges

Page 13: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

INTERCHANGE

WIDEN I 385FROM 4 TO 6 LANES

CONNECTOUTSIDE LANES

REPLACE LOOP RAMPS

ADD CD LANES

Page 14: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

ROPER MOUNTAIN ROAD

Replace Bridge over I 85Relocate Frontage RoadImprove ConnectivityREPLACE ROPER MT. RD. BRIDGE

CD LANES UNDER NEW BRIDGERELOCATE CHROME DRIVENEW INTERSECTION AT CHROME/GARLINGTONTWO LANE OFF RAMP I 85 SB TO I 385 NB

Page 15: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

ROPER MOUNTAIN ROAD

CD AND RAMP LANES

TWO LANE EXIT TO I 385

RELOCATED INTERSECTION

NEW BRIDGE OVER I 85

POTENTIAL RELOCATION AVOIDED

Page 16: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

WOODRUFF ROAD IMPROVEMENTS

GPATS PROJECT –CONGESTION REDUCTIONADD LEFT TURN LANESIMPROVE GARLINGTONAND MILLER ROADSIMPLEMENT ADAPTIVETRAFFIC SIGNALS FOR 17INTERSECTIONS

INTERSECTION IMPROVEMENTS

Page 17: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

WOODRUFF ROAD IMPROVEMENTS

DRAINAGE CHALLENGESNEW COMMERCIALCONSTRUCTIONRIGHT OF WAYRAILROAD COORDINATION

Page 18: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

REHABILITATION SECTIONS OF I 85

Cross slope correction and resurfacing forsafetyConstruction in ProgressTwo Segments

Pelham Road to north of Highway 14 2.6 milesSouth of Salters Road to 1 mile south of LaurensRoad – approximately 2.0 miles

Page 19: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

DESIGN CONSIDERATIONSRFP Goals

Minimize Environmental ImpactsMinimize ROW ImpactsMinimize Impacts to Utilities

ChallengesEndangered SpeciesStream MitigationVariable Subsurface StrataMaintenance of TrafficTight Roadway GeometricsFEMA Floodway RevisionsUtility Coordination

Page 20: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

ENVIRONMENTAL CONSIDERATIONS

Numerous NEPA DocumentsClean Water Act PermittingEnvironmental Construction Compliance

Page 21: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

NEPA DOCUMENTS

Four Categorical Exclusions (CE) for minor improvementsI 85 Northbound Exit RampI 85 RehabilitationWoodruff Road Intersection Improvement (and CE Re Evaluation)Woodruff Road Signalization

Interchange Environmental Assessment (EA)Three Interchange Re evaluations of the EA

Interchange Finding of No Significant Impact

Page 22: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

ENVIRONMENTAL CHANGES & UPDATESThe Northern Long eared Bat is listed as a protected species during the designphase.A minor expansion of the project area requires a new wetland/streamdelineation.Stream impacts are greatly reduced from original estimates. Stream impactsreduced by over 1,000 feet and wetland reduced from 0.5 to 0.415 acres.Building relocations identified in the EA are not needed.

Page 23: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

ENVIRONMENTAL PERMITTING

A complex Individual Permitapplication is submitted to theU.S. Army Corps of Engineersfor review.

Both stream and wetlandimpacts are greatly reducedfrom the original EA estimates.

Permit placed on public notice

Only 4 comments receivedfrom USACE.

Permit Approval Dec. 2015

Page 24: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

Length Spans FoundationBridge 1/2A 379’ – 11.5” 5 Driven PilesBridge 2B 379’ – 11.5” 5 Driven PilesBridge 3 319’ – 11” 4 Driven PilesBridge 4 148’ – 2” 1 Driven/Drilled PilesBridge 5 1522’ – 11.625” 8 Driven Piles/Drilled PiersBridge 6 1962’ – 10” 11 Driven PilesBridge 7 475’ – 0” 4 Driven Piles/Drilled PiersBridge 8 254’ – 10.125” 2 Driven Piles/Drilled PiersBridge 9 368’ – 3.75” 4 Driven Piles/Drilled PiersBridge 10 220’ – 0.625” 1 Driven PilesBridge 11 310’ – 2” 4 Driven Piles/Drilled PiersBridge 12 497’ – 2” 4 Driven Piles/Drilled Piers

BRIDGES

Page 25: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

BRIDGES

BR3

BR6

BR7

BR9

BR5

BR8

BR12

BR1/2A

BR2B

BR10

BR4

Page 26: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

BRIDGE 2B

APPROVED ATC FOR GIRDER TYPE

Page 27: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

BRIDGE 6

CURVED STEEL GIRDERSMAXIMUM SPAN LENGTH OF 246’

Page 28: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

BRIDGE 7

CURVED BRIDGE DECKSTRAIGHT PS CONCRETE GIRDERS

Page 29: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

BRIDGE 10

STRAIGHT ALIGNMENTSTEEL GIRDERS IN SINGLE 220’ SPAN

Page 30: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

BRIDGE 12 – PHASE I

CONSTRUCT BETWEEN EXISTING BRIDGESDEMOLISH EXISTING NB BRIDGE

Page 31: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

BRIDGE 12 – PHASE II

CONSTRUCT ADDITIONAL NEW BRIDGE ON THE NORTH SIDEDEMOLISH EXISTING SB BRIDGE

Page 32: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

WALL OVERVIEW

TALL MSE WALLSCOMBINATION MSE/SOILNAIL WALLSSOIL NAIL WALLSPILE AND LAGGINGWALLSGRAVITY WALLS

Page 33: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

MSE WALLS

Wall # Maximum Height (ft) Associated Roadway3 20 Bridge 94 28 Bridge 95 27 Bridge 126 34 Bridge 127 36 Bridge 68 25 Bridge 89 26.5 Bridge 810 20.5 Ramp 3A11 17 Ramp 413 42 Bridge 5/Ramp 1A14 44.5 Ramp 4

Page 34: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

MSE WALLS

Wall # Maximum Height (ft) Associated Roadway16A 23.5 Chrome Rd.16B 22 Bridge 1128 28.5 Bridge 429 30.5 Bridge 432 56 I 385 NBCD33 58 Bridge 7/Ramp 2B35 46 Bridge 5

36A 15 Ramp 4B36B 15 Ramp 4B37 22.5 Bridge 638 10 I 385

Page 35: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

BRIDGE 7TALL WALLSADJACENT BRIDGE 5

Page 36: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

ELEVATION – WALL 33

FOUNDATION CONSIDERATIONS

Max

Desig

nHe

ight

=67

.5Fe

etat

Brid

ge

Page 37: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

ELEVATION – WALL 12

AT BRIDGE 11 – ROPER MTN. ROADCOMBINATION OF WALL TYPES

MSE WALLPILE & PANEL WALL

Page 38: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

SOIL NAILED TYPICAL SECTIONUSED AT ROPER MOUNTAIN ROAD BRIDGE AND WOODRUFF ROADDESIGNED BY SPECIALTY WALL DESIGNERUSED IN “CUT” SITUATIONS

Page 39: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

PILE & PANEL – TYPE C

USED IN “CUT” SITUATIONLAGGING PLACED FROM TOP DOWNPANEL AND STONE PLACE IN WEB OFPILE

Page 40: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

PILE & PANEL

Page 41: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

Avoid: Culvert/Stream, Floodway, Cemetery, Restricted Right of Way

TYPICAL REINFORCED SOIL SLOPE

Page 42: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

BARRIER WALL

Page 43: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

GEOTECHNICAL CHALLENGES

Diverse Soil ProfileShallow RockTall Embankments resulting in significant downdragLiquefaction/Soil Shear Strength Loss TriggeringStability of Tall Embankments and Walls

Page 44: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

SUBSURFACE EXPLORATION

Number of borings totals 324Total linear feet = 13,570Number of Pursuit Borings = 72Number of Bridge Borings = 69Number of Wall borings = 99Number of Roadway/Drainage Borings = 84

Number of other testsAtterberg Limits = 1413Moisture Content = 1415Sieve Analysis = 1384Triaxial Compression = 20

Page 45: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

GENERALIZED SUBSURFACE PROFILE

Page 46: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

Drastic variation in subsurfaceprofile results in atypical results

Settlement = 3”+Downdrag = 10 kips Settlement = 14”+

Downdrag = 200 kips

Page 47: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

CONSIDER GROUND IMPROVEMENTMinimum Embedment,0.79H Reinforcement, andPiles on 3’x3’ SpacingResistance Factor = 0.65

RAMP 2BWALL 33

Page 48: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

CONSIDER INCREASED EMBEDMENTAND LONGER STRAPS 12 foot Embedment and

1.0H ReinforcementResistance Factor = 0.65

Page 49: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

MAINTENANCE OF TRAFFIC

Page 50: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

MAINTENANCE OF TRAFFICCHALLENGES

AVOID EXISTING BRIDGESAVOID NEW BRIDGESSTAY ON EXISTING PAVEMENT, IF POSSIBLEMEET DESIGN SPEEDS

Page 51: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

WIDEN EXISTING NB SHOULDER

MOT Example – I 85 NB CD(459 Plan Sheets)

Page 52: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

WIDEN FOR NEW NB CDCONSTRUCT TEMPORARY RAMP TR3ACONSTRUCT PIERS IN MEDIAN

Page 53: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

CONSTRUCT NEW RAMP 3A

Page 54: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

CONSTRUCT RAMP 3ACONSTRUCT RAMP 3A GAP UNDER BRIDGES

Page 55: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

CONSTRUCT INSIDE OF NB CD

Page 56: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

UTILITIES

Page 57: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

UTILITIES

Page 58: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

DRAINAGE CHALLENGES

Gilders CreekOrdinance does not allow increase in discharge

Rocky Creek Crossing under I 85 (south of PelhamRoad)

Floodplain and FIRM revised after D B proposals werereceived2004 Flood Elevation below roadway surface2014 Flood Elevation increased by 6’ (overtops I 85)History of floodingDrainage Structures

Page 59: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

STREAM/FLOODWAY MAP

ROCKY CREEK

GILDER CREEK

Page 60: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

ROCKY CREEK – NO RISE ANALYSIS

Page 61: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

CULVERT EXTENSION

Page 62: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

CONSTRUCTIONReceive NTP2 December 2015Receive USACE 404 Permit – December 2015Receive SCDHEC NPDES (NOI) Approval December 2015Construction – December 2015 thru September 2018

MAJOR QUANTITIES

Borrow Material = 350,000 CY Structural Steel = 4,748 Tons or 9,496,000 lbsExcavation = 373,000 CY Reinforcing Steel = 2,907 Tons or 5,813,930 lbsConcrete = 21,444 CY Prestressed Girders = 17,500 LFAsphalt = 234,000 Tons Drilled Shafts = 1,600 LFPCCP = 156,400 SY Steel H Piles = 95,000 LFMSE Wall = 250,400 SF

Page 63: ACEC Presentation I85-385 Kneece · 2020-02-15 · RFQ published –July 1, 2013 Final RFP released –March 27, 2014 Proposals Accepted Design rbuild proposal –July 21, 2014 Cost

THANK YOU!

QUESTIONS OR COMMENTS