accord energy corporation india pvt....
TRANSCRIPT
Accord Energy Corporation India Pvt. Ltd.
PRE-FEASIBILITY REPORT
ON
ENVIRONMENTAL ASPECTS
OF
PROPOSED
INCREASE IN CAPACITY
2 x 150 MW to 2 x 180 MW
OF
EXISTING ENVIRONMENTAL CLEARANCE
( J-13012/107/ 2009-IA-II (T) dated 18/05/2011 )
at
Sirupuzhalpettai Village,
Gummidipoondi Taluk, Thiruvallur District, Tamil Nadu.
October 2014
i
CONTENTS
1.0 EXECUTIVE SUMMARY ................................................................................ 1
2.0 INTRODUCTION ............................................................................................ 3
3.0 THE PROPOSED PROJECT ............................................................................ 3
4.0 PROJECT LOCATION .................................................................................... 3
5.0 LAND USE ........................................................................................................ 6
6.0 RAW MATERIALS CONSUMPTION .......................................................... 6
7.0 FUEL TRANSPORTATION ............................................................................ 6
8.0 PROCESS DESCRIPTION ............................................................................... 8
9.0 RAW WATER REQUIREMENT .................................................................... 9
10.0 ENERGY CONSUMPTION .......................................................................... 11
11.0 WORK FORCE ............................................................................................... 11
12.0 WASTE & WASTE MANAGEMENT ......................................................... 11
12.1 Air Pollution ............................................................................................ 11
12.2 Waste Water Management .................................................................... 14
12.3 Solid Waste Management ...................................................................... 14
13.0 SITE ANALYSIS, PLANNING & REHABILITATION AND
RESETTLEMENT ...................................................................................................... 15
14.0 PROJECT SCHEDULE & COST ESTIMATION ........................................ 15
15.0 CONCLUSION ............................................................................................... 15
Fig 1.0 Project Location .……………………………………………………………4
Fig 2.0 Plant Layout ………………………………………………………………...5
Fig 3.0 Route Map ………….. ………….……………………………………..……7
Pre-feasibility Report 1 Accord Energy - Gummidipoondi
1.0 EXECUTIVE SUMMARY
It is proposed to increase the capacity of 2 x 150 MW to 2 x 180 MW. The 2 x 150 MW
coal based thermal power plant was issued Environmental Clearance vide letter #
J-13012/107/ 2009-IA-II (T) dated 18/05/2011.
Present Status
The entire Land Acquisition is complete, and is awaiting issue of Consent to
Establish from TNPCB, which is in the final stages of issue.
Financial closure is also in the final stages, and is expected by December 2014.
Construction will commence after obtaining Consent to Establish from
TNPCB.
Project Location
The location of the project is at Sirupuzhalpettai Village, Gummidipoondi Taluk,
Thiruvallur District, Tamil Nadu. The plant site is devoid of any forest land. There
are no areas of ecological sensitivity or notified bio diversity area or wildlife
sanctuary etc. within 10 kms radius of the plant site.
Pre-feasibility Report 2 Accord Energy - Gummidipoondi
Products & Capacity
Increase in capacity of Thermal Power generation using imported coal from 2 x 150
MW to 2 x 180 MW. The 2 x 150 MW Thermal Power Plant was already issued
Environmental Clearance.
Raw Material Requirement
The raw material used will be 100% Imported Coal.
Raw Water Requirement & Source
Main Condensate is based on Air Condensate Cooling. The daily make water
required for 2 x 180 MW will be 150 KLD, whereas the daily water make-up as per
Environmental Clearance issued for 2 x 150 MW was 802 KLD. This conservation of
water is possible due to use of fin fan coolers for Turbine Generation Cooling.
About 150 KLD will be the daily make-up after recycling 192 KLD of treated waste
water in the 2 x 180 MW unit.
Water will be sourced from Ground / Harvested Rain Water.
Solid Waste Generation & Method of Disposal
The total Ash generation will increase by 19.35 TPD by augmentation to 2 x 180 MW
compared to 2 x 150 MW.
Fly ash will be completely disposed & Bottom ash will be stored in ash dyke.
Man Power
There will be no increase in manpower owing to augmentation of capacity from 2 x
150 MW to 2 x 180 MW ie it will be 50 Employees as was originally proposed.
Project Cost
Project cost will remain the same at Rs.1950 Crores as was originally proposed.
Pre-feasibility Report 3 Accord Energy - Gummidipoondi
2.0 INTRODUCTION
India's Electricity Act 2003 introduced structural changes to the power industry,
permitting private investment for the first time since 1948. This allowed power
producers to sell power directly to industrial consumers under the Group Captive
model.
Key features of the Group Captive and Merchant model are
Group Captive Merchant
Bilateral arrangements with consumers / traders / utilities
Offering reliable, consistent power supply, even during peak periods
Attractive prices relative to alternative tariffs
Sales with traders directly
Flexibility and risks of spot pricing
Returns dependent on available pricing
Limited to one day future trading
3.0 THE PROPOSED PROJECT
The present proposal is for increase in capacity to 2 x 180 MW of the originally
proposed 2 x 150 MW, the environmental clearance for which was obtained vide
letter # J-13012/107/ 2009-IA-II (T) dated 18/05/2011.
4.0 PROJECT LOCATION
The proposed augmentation from 2 x 150 MW to 2 x 180 MW is located at
Sirupuzhalpettai Village, Gummidipoondi Taluk, Thiruvallur District, Tamil Nadu,
wherein the Environmental Clearance for 2 x 150 MW has already been obtained.
The project location is as shown in Fig.1.0 and the Plant Layout of the project is as
shown in Fig 2.0.
Pre-feasibility Report 4 Accord Energy - Gummidipoondi
Fig 1.0 Location Map
Pre-feasibility Report 5 Accord Energy - Gummidipoondi
Fig 2.0 Plant Layout
Pre-feasibility Report 6 Accord Energy - Gummidipoondi
5.0 LAND USE
The Augmentation of Capacity ie from 2 x 150 MW to 2 x 180 MW is within
the same site, wherein the Environmental Clearance for 2 x 150 MW has
already been obtained. Hence there is no change in land use.
The land however was a dry rainfed, and moreover was vacant, barren, with
no activity. There were also no Rehabilitation or Resettlement Issues.
6.0 RAW MATERIALS CONSUMPTION
The Marginal increase in coal consumption will be as follows.
for 2 x 150 MW for 2 x 180MW Additional Coal requirement (ie from 300 MW to 360 MW)
3600 TPD 3815 TPD* 215 TPD
*Heat Rate : 2341 Kcal/KWh.
Characteristics of Coal
S. No. Particulars Imported Coal 1 Gross Calorific Value 5300 k cal/kg 2 Moisture 9 % 3 Ash 9 % 4 Fixed Carbon 19 % 5 Sulphur 1.2 % 6 Volatile Matter 35.8 % 7.0 FUEL TRANSPORTATION
The existing road, viz. NH-5, SH-52 will be used for coal transportation.
Imported Coal will be shipped by sea and unloaded at Ennore Port and then
will be transported by road by 40T capacity container. The route map from
Ennore Port to Plant Site is as shown in Fig 3.0.
As per latest amendment of MoEF Minutes of Meeting of the 34th meeting of
re-constituted Expert Appraisal Committee (Thermal) held on 10th & 11th
October, 2011, Coal will be transported by road only for a period upto 4 years
of date of Commissioning, after which the rail transportation will be
implemented.
Pre-feasibility Report 7 Accord Energy - Gummidipoondi
Fig 3.0 Route Map
Pre-feasibility Report 8 Accord Energy - Gummidipoondi
8.0 PROCESS DESCRIPTION
Upgradation of capacity of the power plant from 2 X 150MW (MCR) to 2 X 180MW (MCR)
Accord Energy Corporation India Pvt. Ltd at Sirupulalpettai Village, Gummidipoondi Taluk, Thiruvallur District, Tamil Nadu was originally finalised as 2 x 150MW – Maximum Continuous Rating (MCR) with a capacity to produce 2 x 180MW at Valve Wide Open condition (VWO). Accordingly the equipments were sized as given below: Sl.No. Description Parameters
1 Boiler and its auxiliaries 535tph with a reheater capacity of 477.4tph.
2 Steam turbine generator 150MW (MCR);180MW (VWO) Heat rate: 2125 Kcal/kWh (MCR) 2135 Kcal/kWh (VWO) Generator sized for 150MW.
3 Air cooled condenser 370tph of steam flow
4 Generator transformer 176MVA
5 MS, CRH and HRH piping Designed to carry steam equivalent to 150MW
6 Boiler feed pumps Sized for a steam generation of 580tph.
During the technical meetings with the turbine suppliers,BHEL/Skoda/Siemens, it was understood that the turbine could be modified to generate 2 x 180MW on a continuous basis with a heat rate of 2015Kcal/kwh, by redesigning the turbine and upgrading the generator equivalent to 180MW. This has the following advantages:
a. Keeping the majority of the systems same, there is a possibility of generating 30MW more in each.
b. Much lower heat rate to generate higher capacity with less coal consumption
c. Time required is the same d. Better utilisation of the investment made on the transmission line e. The clearances already obtained, will remain the same except an
amendment for augmentation capacity at 2 x 180 MW
Hence, it was decided to go ahead with this proposal.
Pre-feasibility Report 9 Accord Energy - Gummidipoondi
The increase in capacity necessitated the following changes: Sl.No. Description Parameters for 2 x 150MW
MCR Revised parameters for 2 x 180MW MCR
1 Boiler and its auxiliaries
535tph with a reheater capacity of 477.4tph each
580 tph with a reheater capacity of 510tph each
2 Steam turbine generator
2 x 150MW (MCR);180MW (VWO) Heat rate: 2125 Kcal/kWh (MCR) 2135Kcal/kWh (VWO) Generator sized for 2 x 150MW.
2 x 180MW (MCR): Heat rate: 2015Kcal/kwh Generator sized for 2 x180MW
3 Air cooled condenser 370tph of steam flow each 400 tph of steam flow each
4 Generator transformer 176MVA each 220MVA each
5 MS, CRH and HRH piping
Designed to carry steam equivalent to 2 x 150MW
Designed to carry steam equivalent to 2 x 180MW
6 Boiler feed pumps Sized for a steam generation of 535 tph each
Sized for a steam generation of 580 tph each
9.0 RAW WATER REQUIREMENT
Source of water will be Harvested Rain Water / Ground Water. Sufficient
draft is available, the total water requirement for 2 x 180 MW on daily make-
up will be 150 KLD. Clearance from Central Ground Water Authority has
already been obtained for drawl of 1300 KLD of Ground Water.
Water Consumption for 2x150 MW (As per Environmental Clearance)
Water Consumption for 2x180 MW (Daily Make-up)
802 KLD 150 KLD
Main Condensate is based on Air Condensate Cooling. There will be
reduction of water consumption by 652 KLD for 2 x 180 MW compared to 2 x
150 MW due to use of fin fan coolers for Turbine Generator.
About 150 KLD will be the daily make-up after recycling 192 KLD of treated
waste water.
Pre-feasibility Report 10 Accord Energy - Gummidipoondi
Water Balance Diagram
All Values are in KLD
Total Raw 342
Boiler Feed
D M Plant
Coal Dust Suppression/
Ash Quenching
Blowdown 285
Neutralization Pit
From Bore well / Rain Water Harvesting Reservoir
Reject Tank
48
ETP/RO 340
Septic Tank
Dispersion Trench
192
192 Domestic
150
285
55
2 1.6 1.6
55
340
Pre-feasibility Report 11 Accord Energy - Gummidipoondi
10.0 ENERGY CONSUMPTION
It is a proposed augmentation of power generation facility and hence the
auxiliary power requirement will be met internally.
11.0 WORK FORCE
There is no increase in work force required for increase in capacity from 2 x
150 MW to 2 x 180 MW, and will remain the same as was originally proposed
for 2 x 150 MW.
12.0 WASTE & WASTE MANAGEMENT
12.1 Air Pollution
The Stack height will remain the same at 220 Metres, the calculation of
which is as follows.
The daily consumption of coal for 2 x 180 MW is around 3815 Tonnes imported coal
The rate of SO2 emission due to usage of coal is calculated as given below
Sulphur content = 1.2 %
S = (3815 x 1.2 /100) = 45.78 T/D
SO2 = 45.78 x 2 T/D
= 91.56 T/D =3815 kg/hr
SO2 emission = 3815 kg/hr = 1059.72 g/s
Stack height calculation:
H = 14 Q0.3
Where,
H = height of the Stack
Q = SO2 Concentration in Kg/hr.
Hence
H = 14 x (3815)0.3 = 14 x 11.87 = 166.18 m
Pre-feasibility Report 12 Accord Energy - Gummidipoondi
The stack height proposed to be constructed is however 220 metres, after considering
stack lossess, available draft etc at chimney bottom with reference to minimum gas
velocity of 21 m/sec at the top of chimney to design the height of the chimney.
Stack Emission Characteristics
2 x 150 MW 2 x 180 MW
Single Chimney
Twin Flue
Single Chimney
Twin Flue
Material of Construction RCC RCC
Stack attached to Boiler 1 Boiler 2 Boiler 1 Boiler 2
Stack height (m) 220 220
Flue diameter (m) 3.8 3.8 4.1 4.1
Volume Flow Rate (m3/s) 234.0 234.0 280.0 280.0
Velocity of flue gas (m/s) 21.0 21.0 21.21 21.21
Temperature of flue gas (oC) 140 140 150 150
Flue gas specific volume ( kg / m³) 1.3 1.3 1.2 1.2
Fuel Consumption (Kg/s) 20.84 20.84 22.08 22.08
Sulphur content (% w/w) 1.2 1.2 1.2 1.2
Emission rate – NOx (g/s) 187.5 187.5 198.7 198.7
Emission rate – SO2 (g/s) 500.00 500.00 529.85 529.85
Emission rate – SPM (g/s) 11.7 11.7 14.0 14.0
The following environmental protection or pollution control systems have
already been considered for mitigation of impacts on Air Environment.
220 m tall stack to emit flue gas.
Space provision for retrofitting FGD (Flue Gas Desulfurisation)
systems.
High efficiency ESPs to reduce SPM level in the exhaust gas to
<50mg/Nm³.
Dust suppression and extraction system at Handling Plant area to
Control Fugitive Emission.
Green belt development and afforestation in the plant and ash disposal
areas.
Pre-feasibility Report 13 Accord Energy - Gummidipoondi
A minimum water depth will be maintained in the ash pond to prevent
fugitive dust emission.
Use of bagfilters at all transfer points.
Use of limestone to limit SO2 emission.
High efficiency Electrostatic Precipitator of 99.9% are provided for limiting
SPM concentration in the flue gas to less than 50 mg/Nm³. The tall stack of
220 m height based on maximum SO2 concentration in the flue gas is
provided for natural dispersion at high elevation so that ground level
concentration are within acceptable limits.
The emission of NOX, is reduced by burning fuel at a lower temperature and
shortening the throughput time of the fuel. NOX is also controlled by
operating at low excess air.
Fugitive Emissions
To control fugitive emissions from process units in the plant, the following
measures will be carried out.
Tarring of roads inside the factory.
Preventive maintenance of valves and other equipments.
Green belt on all sides within the project boundary, and community
plantation around the unit with help of local area development authorities
have already been done.
Ambient air quality and stack/fugitive emissions monitored regularly.
In-plant training provided to the plant personnel on operation and
maintenance of dust collectors, techniques of dust emission
measurements, particle size analysis etc.
Effective operation and maintenance of pollution control system is
ensured to contain the emissions/keep them within the CPCB limits
Pre-feasibility Report 14 Accord Energy - Gummidipoondi
A good house keeping consisting of simple, obvious task of cleaning up
spills, removing accumulations around processing equipment and in
general keeping things neat and clean form a part of normal operation and
maintenance procedure
Measures for arresting fugitive dust emissions along with the envisaged
pollution control equipments are adequate and will help to have a healthy
and cleaner environment inside the plant thereby improve the productivity
and the efficiency of the workers as well as that of plant machinery.
12.2 Waste Water Management
Waste Water Generation in KLD
For 2 x 150 MW For 2 x 180 MW
Boiler Blow Down 675 285*
D.M. Plant Regeneration Waste
50 55
Domestic Sewage 1.6 1.6
* Reduction in blowdown due to reduced water consumption by use of Fin
Fan Coolers for Turbine Generator. The entire waste water is reused and recycled thus ensuring zero discharge.
12.3 Solid Waste Management
The Ash generation will increase by 19.35 TPD upon augmentation of
capacity from 2 x 150 MW to 2 x 180 MW.
Solid Waste For 2 x 150 MW (TPD)
For 2 x 180 MW (TPD)
Additional Quantity of Solid Waste
Generation (TPD)
Fly Ash 259.20 274.68 15.48
Bottom Ash 64.80 68.67 3.87
Total 324.00 343.35 19.35
Pre-feasibility Report 15 Accord Energy - Gummidipoondi
13.0 SITE ANALYSIS, PLANNING & REHABILITATION AND RESETTLEMENT
The augmentation of the capacity from 2 x 150 MW to 2 x 180 MW is within
the same site, wherein the Environmental Clearance for 2 x 150 MW has
already been obtained.
There is no Rehabilitation and Resettlement issue.
14.0 PROJECT SCHEDULE & COST ESTIMATION
The construction of 2 x 180 MW Power plant will be started upon obtaining
Amendment in Environmental Clearance from MoEF and Consent to
Establish from TNPCB.
The scheduled to be commissioned in 24 months from the date of receipt of
Consent to Establish from TNPCB.
The project cost will be Rs.1950 Crores as was originally envisaged for 2 x 150
MW.
15.0 CONCLUSION
The proposed augmentation will result in better utilization without any
modification to the majority of existing systems.
The impact will be marginal, however, adequate measures already proposed
to mitigate negative impacts, and thus aid positive impacts.