acc open meeting – november 18, 2010 four corners power plant 1
TRANSCRIPT
BackgroundPlant comprised of 5 generating units (2,100 MW)
Units 1, 2 & 3 solely owned by APS– Total of 560 MW
• Placed in service in 1963-1964
Units 4-5 jointly owned– Each unit is 770 MW
• Participants:– Southern California Edison (SCE)* (48%) – Arizona Public Service (15%) – Public Service of New Mexico (13%) – Salt River Project (10%) – Tucson Electric Power (7%) – El Paso Electric (7%)
• Placed in service in 1969-1970
739 MW231 MW200 MW154 MW108 MW108 MW
* SCE limited in ability to fund capital investment after 2011 is disallowed if “life extension” by
virtue of CPUC May 2010 decision
2
Challenges
• Environmental Considerations
– NOx and PM – BART compliance required mid 2016 (all FC units)
– Ash – Implementation starting 2013 (all FC units)
– Mercury – Compliance late 2014 (FC units 1-3)
• Lease Renewal & Right-of-Way Agreement – Tribal Council vote expected soon
• BHP contract renewal– negotiations underway
• Ownership/Participant Considerations – Southern California Edison (“SCE”) must exit ownership of Units 4-5
3
4
Environmental Considerations - BART• Issues
– EPA will be requiring the installation of additional pollution controls at Four Corners for particulate and NOx to improve regional haze in Class I Areas
• Status– On October 19, 2010, EPA published a proposed Regional Haze FIP
– The proposed determination would require:
• SCRs on Units 1-5
• Electrostatic Precipitators or Baghouses on Units 1-3
• Opacity limits for the stacks and on fugitive dust
• Timing– Public Hearings: December 2010
– Final Regional Haze FIP, Summer 2011
– Compliance required, Summer 2016
• Cost Impact– ~$585M Units 1-3 (baghouses + SCR)
– ~$75M Units 4-5 (APS current share)
– ~$240M Units 4-5 (SCE share)
Environmental Considerations - Ash• Issues
– In June 2010 EPA proposed a rule to regulate ash as either non-hazardous waste or hazardous waste; Either proposal will phase out the use of ash ponds for the disposal of ash
• Status
– The public comment period ends on November 19, 2010
• Timing
– Final rule expected in mid 2012
– Implementation could begin within six months following the rule. Certain disposal requirements may not be required for two to five years
• Cost Impact
5
Non-Hazardous Hazardous
~$22M Units 1-3 ~$30M Units 1-3
~$20M Units 4-5 (APS & SCE) ~$58M Units 4-5 (APS & SCE)
Environmental Considerations - Mercury
• Issues
– EPA will be requiring mercury reductions from coal fired power plants
• Status
– EPA is gathering technical information to be used in writing these requirements; Four Corners has submitted their input
• Timing
– Proposed mercury rule, late 2010
– Final mercury rule, late 2011
– Compliance will be required by late 2014
• Cost Impact
– ~$235M Units 1-3 (baghouses, included in BART values)
– Units 4-5 are not impacted by this rule
6
APS Four Corners Proposal• Purchase SCE’s share of Units 4 & 5• Retire Units 1,2 & 3• Benefits of the proposal:
1) Good for APS customers– Low-cost generating resource– Maintains a diverse portfolio
2) Good for the community– Preserves jobs & tax revenue for the Navajo Nation and local
community
3) Good for the environment– Significant emissions reductions…. lowers overall site emissions
with no increased APS carbon risk
• Proposal contingent upon ACC, CPUC, FERC approval, fuel agreement and lease renewal
7
APS Customer BenefitNPV Savings ($M)
CC Capital Cost1
CO2 Price2
Gas Prices3
$750/kW $1,253/kW
$50/ton $0/ton
$4.00/mmBtu $7.50/mmBtu
$488
-500 -250 0 250 500 750 1000 1250 1500
SAVINGS/BENEFITSCOST
1) Combined cycle cost is for the generation only, i.e., excludes transmission2) CO2 price shown is in 2013. Prices escalate at 2.5% per year over the study period3) Gas prices shown are in 2015 $/MMBtu. Sensitivity represents +/- 30% stress test
$5.75/mmBtu
$20/ton
9
Community Benefits
Four Corners & BHP Navajo Mine (annually):– Payroll – Local Vendor Support– Taxes, fees, & royalties to Navajo Nation– State, local, and federal taxes
Location TotalNative
American% Native American
Power Plant 549 406 74%
BHP Mine 491 404 82%
Total 1040 810 78%
Four Corners contributes to over 1/3 of the Navajo Nation General Fund
$100M$20M
$65M $40M
Total $225M
Native American hiring preference at Four Corner
Power Plant and BHP Navajo Mine
Employees
11