abstracts of the cross check analysison the evaluation of the cores of unit 1, 2 and 3 of fukkushima...

Upload: enformable

Post on 05-Apr-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    1/53

    Attachment IV-2

    1

    Abstracts of the cross check analysis

    on the evaluation of the cores of Unit 1, 2 and 3 of Fukkushima Dai-ichi

    NPP reported by TEPCO

    Abstracts

    On the accident of Fukushima Dai-ichi NPP, a lot of works to converge it and

    collecting essential information to determine the cause are in progress. Nuclear and

    Industry Safety Agency (NISA) issued to TEPCO to submit reports of accident records

    and others related to the Fukushima Dai-ichi NPP on April 25 pursuant to the Provisions

    of Article 67, Paragraph 1 of the Act on Regulation of Nuclear Source Materials,

    Nuclear Fuel Materials and Reactors and Article 106, Paragraph 3 of the Electricity

    Business Act, with the purpose of implementing adequate measures going forward.According to the report, NISA directed TEPCO on May 16 to submit reports of

    evaluation of safety on nuclear reactor facilities regarding to the analysis of records

    before and after the earthquake.

    On the core damage unit 1 through 3 of Fukushima Dai-ichi NPP, TEPCO submitted

    evaluation reports, which were calculated by severe accident analysis code MAAP

    based on the operation records and observed parameters, to NISA on May 23

    NISA examined the reports to confirm the validity of analysis and evaluation. The

    examination was carried out by using other severe accident analysis code, Methods for

    Estimation of Leakages and Consequences of Releases (MELCOR), supported by Japan

    Nuclear Energy Safety Organization (JNES). Abstract of analysis results by MELCOR

    is described below.

    Analysis methods and conditions

    Based on the observed data, chronology, etc. of Unit 1 through 3 of Fukushima

    Dai-ichi NPP which were reported by utility, computational analysis was calculated. A

    severe accident analysis code MELCOR, which is developed by US NRC in charge and

    is used widely by regulators and TSOs as JNES, was used in this work.

    On the MELCOR analysis, transient of plant during 4 days from the accident, major

    events occurred, was calculated. We cared a lot about parameters which have great

    effect on the consequences or whose chronology is uncertain. According to the

    sensitivity analysis on them, uncertain chronology was confirmed and accident scenario

    was studied.

    For example, analysis conditions conducted by TEPCO were confirmed and

    sensitivity analyses, shown in Tables 1-a, 2-a, and 3-a, were carried out.

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    2/53

    Attachment IV-2

    2

    Results and conclusions

    Abstracts of MELCOR analysis are described below. Comparisons to the results of

    utility are shown in Table 1-1 3, Table 2-1 2, and Table 3-1 2.

    Release ratio of fission products to the environment in each analysis is shown inTable 4. Preliminary calculation of fission products, regarding inventory of each unit,

    released to the environment during the term of the analysis is shown in Table 5. This

    work was calculated by using conditions (IC operation, PCV ventilation, alternative

    water injection, etc.) based on the operation record, alarms, and plant behavior at the

    transition which were reported by TEPCO on May 16. Total amount of fission products

    released to the environment was scrutinized and total amount of I 131 and Cs-137

    (conversion to I 131) from unit 1, 2, and 3 is 840000 TBq. Compared to the reported

    value 370000 TBq (630000 TBq by NSC) for INES on April 12, it is in the same range.Information about operation and behavior of equipment is still insufficient, however,

    further investigation is conducted to reveal the cause of accident.

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    3/53

    Attachment IV-2

    3

    Table 1-a Analysis conditions on Unit 1

    Identifier Analysis conditions Remarks results

    TEPCO Correspond to utility

    s analysis Table 1-1, Fig. 1-1-111

    Case 1 Increasing of heat removal (restart IC-B with IC-A) Table 1-2, Fig. 1-2-1

    2

    Case 2 Amount of water injected through the fire protection line

    varies with RPV pressure.

    PCV leakage area at 50 hours is ca. 35 cm 2.

    Table 1-3, Fig. 1-3-1

    12

    Table 2-a Analysis conditions on Unit 2Identifier Analysis conditions Remarks results

    TEPCO-1 Correspond to utility s analysis No.1 Table 2-1 Fig.2-1-1

    13

    TEPCO-2 Correspond to utility s analysis No.2

    Amount of water injected through the fire protection line

    varies with RPV pressure.

    PCV leakage area is ca. 50 cm 2.

    S/C leakage area is ca. 300 cm2

    Table 2-2, Fig.2-2-1

    12

    Case-1 Based on the utility s analysis No.1, but

    PCV is intact

    Fig.2-3-1 2

    Case-2 Based on the utility s analysis No.1, but

    PCV leakage area is ca. 50 cm 2.

    Fig.2-4-1

    Case-3 Based on the utility s analysis No.1, but

    S/C leakage area is ca. 300 cm 2

    Fig.2-5-1

    Table 3-a Analysis conditions on Unit 3

    Identifier Analysis conditions Remarks results

    TEPCO-1 Correspond to utility s analysis No.1 Table 3-1, Fig.3-1-1

    11

    TEPCO-2 Correspond to utility s analysis No.2 Table 3-2, Fig.3-2-1

    14

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    4/53

    Attachment IV-2

    4

    Table 1-1 Result of analysis on Unit 1 [TEPCO] and comparison to the utility s result

    Event Results (this work) Utility s result

    Core exposure 16 40, Mar. 11 2 hours (relative time) 3 hours (relative time)Core damage 18 00, Mar. 11 3 hours (relative time) 4 hours (relative time)

    RPV failure 20 00, Mar. 11 5 hours (relative time) 15 hours (relative time)

    Table 1-2 Result of analysis on Unit 1 [case 1] and comparison to the utility s result

    Event Results (this work) Utility s result

    Core exposure 16 50, Mar. 11 2 hours (relative time) 3 hours (relative time)

    Core damage 18 20, Mar. 11 4 hours (relative time) 4 hours (relative time)

    RPV failure 2 50, Mar. 12 12 hours (relative time) 15 hours (relative time)

    Table 1-3 Result of analysis on Unit 1 [case 2] and comparison to the utility s result

    Event Results (this work) Utility s result

    Core exposure 16 40, Mar. 11 2 hours (relative time) 3 hours (relative time)

    Core damage 18 00, Mar. 11 3 hours (relative time) 4 hours (relative time)

    RPV failure 20 00, Mar. 11 5 hours (relative time) 15 hours (relative time)

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    5/53

    Attachment IV-2

    5

    Table 2-1 Result of analysis on Unit 2 [TEPCO-1] and comparison to the utility s result

    Event Results (this work) Utility s result (No.1)

    Core exposure 18 00, Mar 14 75 hours (relative time) 75 hours (relative time)Core damage 22 30, Mar 14 80 hours (relative time) 77 hours (relative time)

    RPV failure

    (RPV doesn t fail)

    (RPV doesn t fail)

    Table 2-2 Result of analysis on Unit 2 [TEPCO-2] and comparison to the utility s result

    Event Results (this work) Utility s result (No.2)

    Core exposure 18 00, Mar 14 75 hours (relative time) 75 hours (relative time)

    Core damage 19 50, Mar 14 77 hours (relative time) 77 hours (relative time)RPV failure 22 50, Mar 14 80 hours (relative time) 109 hours (relative time)

    Table 3-1 Result of analysis on Unit 3 [TEPCO-1] and comparison to the utility s result

    Event Results (this work) Utility s result (No. 1)

    Core exposure 7 40, Mar 13 41 hours (relative time) 40 hours (relative time)

    Core damage 10 20, Mar 13 44 hours (relative time) 42 hours (relative time)RPV failure

    (RPV doesn t fail)

    (RPV doesn t fail)

    Table 3-2 Result of analysis on Unit 3 [TEPCO-2] and comparison to the utility s result

    Event Results (this work) Utility s result (No. 2)

    Core exposure 7 40, Mar 13 41 hours (relative time) 40 hours (relative time)

    Core damage 10 20, Mar 13 44 hours (relative time) 42 hours (relative time)

    RPV failure 22 10, Mar 14 79 hours (relative time) 66 hours (relative time)

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    6/53

    Attachment IV-2

    6

    Table 4 FP release ratio

    UnitIdentifier

    of analysisNoble

    gas CsI Cs Te Ba Ru Ce La

    1

    TEPCO 9.9E-01 1.9E-03 9.1E-04 2.4E-02 1.2E-04 6.4E-09 1.1E-06 1.1E-06

    Case 1 9.5E-01 1.2E-03 8.2E-04 1.1E-02 6.2E-05 2.1E-11 8.9E-07 6.9E-07

    Case 2 9.5E-01 6.6E-03 2.9E-03 1.1E-02 4.0E-05 9.0E-10 1.4E-07 1.2E-07

    2

    TEPCO-1 8.1E-01 3.8E-03 3.4E-03 4.2E-03 4.9E-04 7.6E-10 7.4E-11 6.5E-08

    TEPCO-2 9.6E-01 6.7E-02 5.8E-02 3.0E-02 2.6E-04 5.4E-10 4.0E-06 8.4E-07

    Case 1 9.7E-01 1.3E-03 4.6E-04 2.5E-04 3.3E-04 2.0E-11 1.5E-12 1.5E-09

    Case 2 9.7E-01 3.9E-02 3.8E-02 5.1E-02 2.9E-04 4.1E-11 8.2E-06 1.1E-06

    Case 3 9.7E-01 4.1E-02 3.9E-02 3.5E-02 4.0E-04 4.6E-11 1.3E-05 1.2E-06

    3TEPCO-1 6.5E-01 8.2E-03 5.9E-03 2.7E-03 6.1E-04 2.9E-10 2.5E-11 2.7E-08

    TEPCO-2 9.9E-01 3.0E-03 2.7E-03 2.4E-03 4.3E-04 8.6E-10 5.0E-08 1.3E-07

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    7/53

    Attachment IV-2

    7

    Table 5 Preliminary calculation of FP released to the environmentin the early stage of Fukushima Ddai-ichi accident (Bq)

    Unit 1 Unit 2 Unit 3 Total

    Xe-133 5.2 d 3.410 18 3.510 18 4.410 18 1.110 19

    Cs-134 2.1 y 7.110 14 1.610 16 8.210 14 1.810 16

    Cs-137 30.0 y 5.910 14 1.410 16 7.110 14 1.510 16

    Sr-89 50.5 d 8.210 13 6.810 14 1.210 15 2.010 15

    Sr-90 29.1 y 6.110 12 4.810 13 8.510 13 1.410 14

    Ba-140 12.7 d 1.310 14 1.110 15 1.910 15 3.210 15

    Te-127m 109.0 d 2.510 14 7.710 14 6.910 13 1.110 15

    Te-129m 33.6 d 7.210 14 2.410 15 2.110 14 3.310 15

    Te-131m 30.0 h 9.510 13 5.410 10 1.810 12 9.710 13

    Te-132 78.2 h 7.410 14 4.210 11 1.410 13 7.610 14

    Ru-103 39.3 d 2.510 09 1.810 09 3.210 09 7.510 09

    Ru-106 368.2 d 7.410 08 5.110 08 8.910 08 2.110 09

    Zr-95 64.0 d 4.610 11 1.610 13 2.210 11 1.710 13

    Ce-141 32.5 d 4.610 11 1.710 13 2.210 11 1.810 13

    Ce-144 284.3 d 3.110 11 1.110 13 1.410 11 1.110 13

    Np-239 2.4 d 3.710 12 7.110 13 1.410 12 7.610 13

    Pu-238 87.7 y 5.810 08 1.810 10 2.510 08 1.910 10

    Pu-239 24065 y 8.610 07 3.110 09 4.010 07 3.210 09

    Pu-240 6537 y 8.810 07 3.010 09 4.010 07 3.210 09

    Pu-241 14.4 y 3.510 10 1.210 12 1.610 10 1.210 12

    Y-91 58.5 d 3.110 11 2.710 12 4.410 11 3.410 12

    Pr-143 13.6 d 3.610 11 3.210 12 5.210 11 4.110 12

    Nd-147 11.0 d 1.510 11 1.310 12 2.210 11 1.610 12

    Cm-242 162.8 d 1.110 10 7.710 10 1.410 10 1.010 11

    I-131 8.0 d 1.210 16 1.410 17 7.010 15 1.610 17

    I-132 2.3 h 4.510 14 9.610 11 1.810 13 4.710 14

    I-133 20.8 h 6.510 14 1.410 12 2.610 13 6.810 14

    I-135 6.6 h 6.110 14 1.310 12 2.410 13 6.310 14

    Sb-127 3.9 d 1.710 15 4.210 15 4.510 14 6.410 15

    Sb-129 4.3 h 1.610 14 8.910 10 3.010 12 1.610 14

    Mo-99 66.0 h 8.110 07 1.010 04 6.710 06 8.810 07

    Evaluated by using the results of case2(unit 1), TEPCO-2(unit 2), TEPCO-2(unit3) in table 4

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    8/53

    Attachment IV-2

    8

    0.0

    0.2

    0.4

    0.6

    0.8

    1.06.0

    7.0

    -4000

    -2000

    0

    2000

    4000

    6000

    0 12 24 36 48 60 72 84 96

    P r e s s .

    ( M P a

    )

    a t e r

    l e v e

    l ( m m

    )

    Relative time (h)

    (,)Observed data1F1

    RPV press. TAF

    RPVwater level

    3/12 3/13 3/14 3/15 3/16

    Date

    Fig. 1-1-1 RPV pressure and water level (unit 1) [TEPCO]

    IC stop, PCV failure (assumption), W/W ventilation (open), W/W ventilation (close), sea water inject., expansion of PCV failure (assumption)

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    0 12 24 36 48 60 72 84 96

    D/W press.

    2Pd

    1Pd

    3/12 3/13 3/14 3/15 3/16

    P r e s s .

    ( M P a

    )

    Relative time (h)

    ()Observed data

    Date

    Fig. 1-1-2 D/W pressure (unit 1) [TEPCO] IC stop, PCV failure (assumption), W/W ventilation (open), W/W ventilation (close), sea water inject., expansion of PCV failure (assumption)

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    9/53

    Attachment IV-2

    9

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    0

    100

    200

    300

    400

    500

    600

    700

    0 12 24 36 48 60 72 84 96

    T e m p .

    ( K )

    1F1

    D/W press.

    S/C press.

    3/12 3/13 3/14 3/15 3/16

    D/W temp.

    S/C temp.

    Saturation temp.

    P r e s s .

    ( M P a

    )

    Relative time (h)

    (,)Observed data

    Date

    Fig. 1-1-3 PCV pressure and temperature (unit 1) [TEPCO]

    IC stop, PCV failure (assumption), W/W ventilation (open), W/W ventilation (close), sea water inject., expansion of PCV failure (assumption)

    0

    500

    1000

    1500

    2000

    2500

    3000

    0 12 24 36 48 60 72 84 96

    M a x

    i m u m

    t e m p .

    o f c o r e

    K

    3/12 3/13 3/14 3/15 3/16

    Relative time (h)

    Date

    Fig. 1-1-4 Maximum temperature of the core (unit 1) [TEPCO] IC stop, PCV failure (assumption), W/W ventilation (open), W/W ventilation (close), sea water inject., expansion of PCV failure (assumption)

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    10/53

    Attachment IV-2

    10

    0

    10

    20

    30

    40

    50

    60

    70

    80

    0 12 24 36 48 60 72 84 960.0

    0.2

    0.4

    0.6

    0.8

    1.0

    M a s s

    ( t o n

    )

    R a t

    i o ( - )

    1F1

    3/12 3/13 3/14 3/15 3/16

    Intact fuel

    Debris

    Relative time (h)

    Date

    Fig. 1-1-5 Mass of the core (unit 1) [TEPCO] IC stop, PCV failure (assumption), W/W ventilation (open), W/W ventilation (close), sea water inject., expansion of PCV failure (assumption)

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    11/53

    Attachment IV-2

    11

    Top

    Bottomperiphery periphery

    Top

    Bottomperiphery periphery

    Top

    Bottom

    periphery peripherycentert = 40 h

    centert = 5 h

    centert = 6 h

    ratio1.0

    0.8

    0.6

    0.4

    0.2

    0.0

    ratio1.0

    0.8

    0.6

    0.4

    0.2

    0.0

    ratio1.0

    0.8

    0.6

    0.4

    0.2

    0.0 Fig. 1-1-6 Distribution of intact fuel (unit 1) [TEPCO]

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    12/53

    Attachment IV-2

    12

    0

    200

    400

    600

    800

    1000

    1200

    0 12 24 36 48 60 72 84 96

    H y

    d r o g e n

    k g

    Relative time (h)

    Date

    3/12 3/13 3/14 3/15 3/16

    Generated hydrogen

    Leakage from PCV

    Fig. 1-1-7 Hydrogen generation (unit 1) [TEPCO]

    IC stop, PCV failure (assumption), W/W ventilation (open), W/W ventilation (close), sea water inject., expansion of PCV failure (assumption)

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    13/53

    Attachment IV-2

    13

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    0

    0.2

    0.4

    0.6

    0.8

    1

    0 12 24 36 48 60 72 84 96

    F P r e

    l e a s e r a t i o

    ( - )

    A c c u m u

    l a t e

    d F P r e

    l e a s e r a t i o ( -

    )1F1 Noble gas(accumulated)

    Noble gas

    3/12 3/13 3/14 3/15 3/16

    Relative time (h)

    Date

    0

    1 10 -4

    2 10 -4

    3 10 -4

    4 10 -4

    5 10 -4

    0

    1 10 -2

    2 10 -2

    3 10 -2

    4 10 -2

    5 10 -2

    0 12 24 36 48 60 72 84 96

    CsICsTeBa

    1F1

    3/12 3/13 3/14 3/15 3/16

    F P r e

    l e a s e r a t i o

    ( - )

    A c c u m u

    l a t e

    d F P r e

    l e a s e r a t

    i o ( - )

    Relative time (h)

    Date

    Fig. 1-1-8 FP release ratio to the environment (1/2) (unit 1) [TEPCO] IC stop, PCV failure (assumption), W/W ventilation (open), W/W ventilation (close), sea water inject., expansion of PCV failure (assumption)

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    14/53

    Attachment IV-2

    14

    10 -4

    10 -3

    10 -2

    10 -1

    100

    10 -9

    10 -7

    10 -5

    10 -3

    10 -1

    0 12 24 36 48 60 72 84 96

    Noble gasCsI

    Cs

    Te

    Ba

    Ru

    Ce

    La

    1F1

    3/12 3/13 3/14 3/15 3/16

    Solid line(left axis)Dashed line(right axis)

    F P r e

    l e a s e r a t i o

    ( - )

    A c c u m u

    l a t e

    d F P r e

    l e a s e r a t i o ( -

    )

    Relative time (h)

    Date

    Fig. 1-1-9 FP release ratio to the environment (2/2) (unit 1) [TEPCO]

    IC stop, PCV failure (assumption), W/W ventilation (open), W/W ventilation (close), sea water inject., expansion of PCV failure (assumption)

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    0 12 24 36 48 60 72 84 96

    C

    s I d

    i s t r

    i b u t i o n

    ( - )

    1F1

    3/12 3/13 3/14 3/15 3/16

    W/W

    D/W

    RPV

    Relative time (h)

    Date

    Fig. 1-1-10 Distribution of CsI (unit 1) [TEPCO] IC stop, PCV failure (assumption), W/W ventilation (open), W/W ventilation (close),

    sea water inject., expansion of PCV failure (assumption)

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    15/53

    Attachment IV-2

    15

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    0 12 24 36 48 60 72 84 96

    C s

    d i s t r

    i b u t i o n

    ( - )

    1F1

    3/12 3/13 3/14 3/15 3/16

    W/W

    D/W

    RPV

    Relative time (h)

    Date

    Fig. 1-1-11 Distribution of Cs (unit 1) [TEPCO] IC stop, PCV failure (assumption), W/W ventilation (open), W/W ventilation (close), sea water inject., expansion of PCV failure (assumption)

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    16/53

    Attachment IV-2

    16

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    6.0

    7.0

    -4000

    -2000

    0

    2000

    4000

    6000

    0 12 24 36 48 60 72 84 96

    P r e s s .

    ( M P a

    )

    a t e r

    l e v e

    l ( m m

    )

    (,)Observed data1F1

    RPV press. TAF

    RPVwater level

    3/12 3/13 3/14 3/15 3/16

    Relative time (h)

    Date

    Fig. 1-2-1 RPV pressure and water level (unit 1) [case 1]

    IC stop, PCV failure (assumption), W/W ventilation (open), W/W ventilation (close), sea water inject., expansion of PCV failure (assumption)

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    0 12 24 36 48 60 72 84 96

    P

    r e s s .

    M P a

    () Observed data

    D/W press.

    2Pd

    1Pd

    3/12 3/13 3/14 3/15 3/16

    Relative time (h)

    Date

    Fig. 1-2-2 D/W pressure (unit 1) [case 1] IC stop, PCV failure (assumption), W/W ventilation (open), W/W ventilation (close),

    sea water inject., expansion of PCV failure (assumption)

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    17/53

    Attachment IV-2

    17

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    -4000

    -2000

    0

    2000

    4000

    6000

    0 12 24 36 48 60 72 84 96

    P r e s s .

    ( M P a

    )

    a t e r

    l e v e

    l ( m m

    )

    (,)Observed data1F1

    RPV press.

    TAF

    RPVwater level

    3/12 3/13 3/14 3/15

    Relative time (h)

    Date

    Fig. 1-3-1 RPV pressure and water level (unit 1) [case 2]

    IC stop, PCV failure (assumption), W/W ventilation (open), W/W ventilation (close), sea water inject., expansion of PCV failure (assumption)

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    0 12 24 36 48 60 72 84 96

    P r e s s .

    M P a

    ()Observed data

    D/W press.

    2Pd

    1Pd

    3/12 3/13 3/14 3/15

    Relative time (h)

    Date

    Fig. 1-3-2 D/W pressure (unit 1) [case 2] IC stop, PCV failure (assumption), W/W ventilation (open), W/W ventilation (close), sea water inject., expansion of PCV failure (assumption)

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    18/53

    Attachment IV-2

    18

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    0

    100

    200

    300

    400

    500

    600

    700

    0 12 24 36 48 60 72 84 96

    P r e s s .

    ( M P a

    )

    T e m p .

    ( K )

    (,)Observed data

    1F1

    D/W press.

    S/C press.

    3/12 3/13 3/14 3/15 3/16

    D/W temp.

    S/C temp.

    Saturation temp.

    Relative time (h)

    Date

    Fig. 1-3-3 PCV pressure and temperature (unit 1) [case 2]

    IC stop, PCV failure (assumption), W/W ventilation (open), W/W ventilation (close), sea water inject., expansion of PCV failure (assumption)

    0

    500

    1000

    1500

    2000

    2500

    3000

    0 12 24 36 48 60 72 84 96

    M a x

    i m u m

    t e m p .

    o f c o r e

    K

    3/12 3/13 3/14 3/15 3/16

    Relative time (h)

    Date

    Fig. 1-3-4 Maximum temperature of the core (unit 1) [case 2]

    IC stop, PCV failure (assumption), W/W ventilation (open), W/W ventilation (close), sea water inject., expansion of PCV failure (assumption)

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    19/53

    Attachment IV-2

    19

    0

    10

    20

    30

    40

    50

    60

    70

    80

    0 12 24 36 48 60 72 84 960.0

    0.2

    0.4

    0.6

    0.8

    1.0

    M a s s

    ( t o n

    )

    R a t i o

    ( - )

    1F1

    3/12 3/13 3/14 3/15 3/16

    Intact fuel

    Debris

    Relative time (h)

    Date

    Fig. 1-3-5 Mass of the core (unit 1) [case 2] IC stop, PCV failure (assumption), W/W ventilation (open), W/W ventilation (close), sea water inject., expansion of PCV failure (assumption)

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    20/53

    Attachment IV-2

    20

    Top

    Bottomperiphery periphery

    Top

    Bottomperiphery periphery

    Top

    Bottomperiphery peripherycenter

    t = 18 h

    centert = 6 h

    centert = 12 h

    ratio1.0

    0.8

    0.6

    0.4

    0.2

    0.0

    ratio1.0

    0.8

    0.6

    0.4

    0.2

    0.0

    ratio1.0

    0.8

    0.6

    0.4

    0.2

    0.0 Fig. 1-3-6 Distribution of intact fuel (unit 1) [case 2]

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    21/53

    Attachment IV-2

    21

    0

    200

    400

    600

    800

    1000

    1200

    0 12 24 36 48 60 72 84 96

    H y

    d r o g e n

    k g

    3/12 3/13 3/14 3/15 3/16

    Generated hydrogen

    Leakage from PCV

    Relative time (h)

    Date

    Fig. 1-3-7 Hydrogen generation (unit 1) [case 2]

    IC stop, PCV failure (assumption), W/W ventilation (open), W/W ventilation (close), sea water inject., expansion of PCV failure (assumption)

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    0

    0.2

    0.4

    0.6

    0.8

    1

    0 12 24 36 48 60 72 84 96

    F P r e

    l e a s e r a t i o

    ( - )

    A c c u m u

    l a t e

    d F P r e

    l e a s e r a t i o

    ( - )1F1 Noble gas (accumulated)

    Noble gas

    3/12 3/13 3/14 3/15 3/16

    Relative time (h)

    Date

    Fig. 1-3-8 FP release ratio to the environment (1/3) (unit 1) [case 2]

    IC stop, PCV failure (assumption), W/W ventilation (open), W/W ventilation (close), sea water inject., expansion of PCV failure (assumption)

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    22/53

    Attachment IV-2

    22

    0

    1 10 -4

    2 10 -4

    3 10 -4

    4 10 -4

    5 10 -4

    0

    5 10 -3

    1 10 -2

    1.5 10 -2

    2 10 -2

    0 12 24 36 48 60 72 84 96

    CsICs

    TeBa

    1F1

    3/12 3/13 3/14 3/15 3/16

    F P r e

    l e a s e r a t i o

    ( - )

    A c c u m u

    l a t e

    d F P r e

    l e a s e r a t i o

    ( - )

    Relative time (h)

    Date

    Fig. 1-3-9 FP release ratio to the environment (2/3) (unit 1) [case 2] IC stop, PCV failure (assumption), W/W ventilation (open), W/W ventilation (close), sea water inject., expansion of PCV failure (assumption)

    10 -6

    10 -5

    10 -4

    10 -3

    10 -10

    10-8

    10 -6

    10 -4

    10 -2

    100

    0 12 24 36 48 60 72 84 96

    Noble gas

    CsI

    Cs

    Te

    Ba

    Ru

    Ce

    La

    1F1

    3/12 3/13 3/14 3/15 3/16

    Solid line (left axis)Dashed line (right axis)

    F P r e

    l e a s e r a t i o

    ( - )

    A c c u m u

    l a t e

    d F P r e

    l e a s e r a t i o

    ( - )

    Relative time (h)

    Date

    Fig. 1-3-10 FP release ratio to the environment (3/3) (unit 1) [case 2]

    IC stop, PCV failure (assumption), W/W ventilation (open), W/W ventilation (close), sea water inject., expansion of PCV failure (assumption)

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    23/53

    Attachment IV-2

    23

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    0 12 24 36 48 60 72 84 96

    C s I

    d i s t r

    i b u t i o n

    ( - )

    1F1

    3/12 3/13 3/14 3/15 3/16

    W/W

    D/W

    RPV

    Relative time (h)

    Date

    Fig. 1-3-11 Distribution of CsI (unit 1) [case 2] IC stop, PCV failure (assumption), W/W ventilation (open), W/W ventilation (close), sea water inject., expansion of PCV failure (assumption)

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    0 12 24 36 48 60 72 84 96

    C

    s d i s t r

    i b u t i o n

    ( - )

    1F1

    3/12 3/13 3/14 3/15 3/16

    W/W

    D/W

    RPV

    Relative time (h)

    Date

    Fig. 1-3-12 Distribution of Cs (unit 1) [case 2] IC stop, PCV failure (assumption), W/W ventilation (open), W/W ventilation (close),

    sea water inject., expansion of PCV failure (assumption)

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    24/53

    Attachment IV-2

    24

    0

    20

    40

    60

    80

    100

    0

    500

    1000

    1500

    2000

    0 24 48 72 96 120 144

    I n j e c t e d w a t e r

    ( m 3 / h )

    T o t a l

    a m o u n t

    ( m 3 )

    1F2

    Total

    RCIC

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    Fire protection

    Injected from the outside

    Relative time (h)

    Date

    Fig. 2-1-1 Amount of water injection (unit 2) [TEPCO-1]

    RCIC start manually, SBO, Water source change from CST to S/P, RCIC stop, Seawater inject., RPV depressurized, S/R valve-2 open, Impact sound

    0.0

    1.0

    2.0

    3.0

    4.0

    5.0

    6.0

    7.0

    8.0

    -4000

    -2000

    0

    2000

    4000

    6000

    0 24 48 72 96 120 144

    P r e s s . (

    M P a )

    a t e r

    l e v e

    l ( m m

    )

    ()Observed data1F2

    RPV press.

    TAF

    Downcomer

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    Core

    Relative time (h)

    Date

    Fig. 2-1-2 RPV pressure and water level (unit 2) [TEPCO-1]

    RCIC start manually, SBO, Water source change from CST to S/P, RCIC stop, Seawater inject., RPV depressurized, S/R valve-2 open, Impact sound

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    25/53

    Attachment IV-2

    25

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    0 24 48 72 96 120 144

    P r e s s .

    M P a

    () Observed data

    D/W press.

    2Pd

    1Pd

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    Relative time (h)

    Date

    Fig. 2-1-3 D/W pressure (unit 2) [TEPCO-1]RCIC start manually, SBO, Water source change from CST to S/P, RCIC stop, Seawater inject., RPV depressurized, S/R valve-2 open, Impact sound

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    0 24 48 72 96 120 1440

    100

    200

    300

    400

    500

    P r e s s .

    M P a

    ()Observed data

    D/W press.

    2Pd

    1Pd T e m p .

    K

    S/C press.

    Saturation temp.

    D/W temp.

    S/P temp.

    3/12 3/133/14 3/15 3/16 3/17 3/18

    Relative time (h)

    Date

    Fig. 2-1-4 PCV pressure and temperature (unit 2) [TEPCO-1]

    RCIC start manually, SBO, Water source change from CST to S/P, RCIC stop, Seawater inject., RPV depressurized, S/R valve-2 open, Impact sound

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    26/53

    Attachment IV-2

    26

    0

    500

    1000

    1500

    2000

    2500

    3000

    0 24 48 72 96 120 144

    M a x

    i m u m t e m p .

    o f c o r e

    ( K )

    1F2

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    Relative time (h)

    Date

    Fig. 2-1-5 Maximum temperature of the core (unit 2) [TEPCO-1]

    RCIC start manually, SBO, Water source change from CST to S/P, RCIC stop, Seawater inject., RPV depressurized, S/R valve-2 open, Impact sound

    0

    20

    40

    60

    80

    100

    0 24 48 72 96 120 1440.0

    0.2

    0.4

    0.6

    0.8

    1.0

    M a s s

    ( t o n

    )

    1F2

    Intact fuel

    Debris

    R a t

    i o ( - )

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    Relative time (h)

    Date

    Fig. 2-1-6 Mass of the core (unit 2) [TEPCO-1]RCIC start manually, SBO, Water source change from CST to S/P, RCIC stop, Seawater inject., RPV depressurized, S/R valve-2 open, Impact sound

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    27/53

    Attachment IV-2

    27

    Top

    Bottomperiphery periphery

    Top

    Bottomperiphery periphery

    centert = 70 h

    centert = 90 h

    ratio1.0

    0.8

    0.6

    0.4

    0.2

    0.0

    ratio1.0

    0.8

    0.6

    0.4

    0.2

    0.0

    Fig. 2-1-7 Distribution of intact fuel (unit 2) [TEPCO-1]

    0

    200

    400

    600

    800

    1000

    0 24 48 72 96 120 144

    H y d r o g e n

    ( k g )

    1F2

    Generated hydrogen

    Leakage from PCV

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    Relative time (h)

    Date

    Fig. 2-1-8 Hydrogen generation (unit 2) [TEPCO-1]

    RCIC start manually, SBO, Water source change from CST to S/P, RCIC stop, Seawater inject., RPV depressurized, S/R valve-2 open, Impact sound

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    28/53

    Attachment IV-2

    28

    0.000

    0.010

    0.020

    0.030

    0.040

    0.050

    0.060

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    0 24 48 72 96 120 144

    1F2

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    F P r e

    l e a s e r a t i o

    ( - )

    A c c u m u l a t e d

    F P r e

    l e a s e r a t i o

    ( - )

    Relative time (h)

    Date

    Noble gas(accumulated)

    Noble gas

    Fig. 2-1-9 FP release ratio to the environment (1/3) (unit 2) [TEPCO-1]RCIC start manually, SBO, Water source change from CST to S/P, RCIC stop, Seawater inject., RPV depressurized, S/R valve-2 open, Impact sound

    0

    1 10 -4

    2 10 -4

    3 10 -4

    4 10 -4

    5 10 -4

    6 10 -4

    0.0

    2.0 10-3

    4.0 10 -3

    6.0 10 -3

    8.0 10 -3

    1.0 10 -2

    0 24 48 72 96 120 144

    CsICsTeBa

    1F2

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    F P r e

    l e a s e r a t i o

    ( - )

    A c c u m u l a t e d

    F P r e

    l e a s e r a t i o

    ( - )

    Relative time (h)

    Date

    Fig. 2-1-10 FP release ratio to the environment (2/3) (unit 2) [TEPCO-1]RCIC start manually, SBO, Water source change from CST to S/P, RCIC stop, Seawater inject., RPV depressurized, S/R valve-2 open, Impact sound

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    29/53

    Attachment IV-2

    29

    10 -5

    10 -4

    10 -3

    10 -2

    10 -1

    10 -11

    10 -9

    10 -7

    10 -5

    10 -3

    10 -1

    0 24 48 72 96 120 144

    Noble gasCsICsTeBaRuCeLa

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    F P r e

    l e a s e r a t i o

    ( - )

    A c c u m u l a t e d

    F P r e

    l e a s e r a t i o

    ( - )

    Relative time (h)

    Date

    Solid line (left axis)Dashed line (right axis)

    Fig. 2-1-11 FP release ratio to the environment (3/3) (unit 2) [TEPCO-1]RCIC start manually, SBO, Water source change from CST to S/P, RCIC stop, Seawater inject., RPV depressurized, S/R valve-2 open, Impact sound

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    0 24 48 72 96 120 144

    C s I d i s t r

    i b u t

    i o n

    ( - )

    1F2

    W/W

    RPV

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    Relative time (h)

    Date

    Fig. 2-1-12 Distribution of CsI (unit 2) [TEPCO-1]

    RCIC start manually, SBO, Water source change from CST to S/P, RCIC stop, Seawater inject., RPV depressurized, S/R valve-2 open, Impact sound

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    30/53

    Attachment IV-2

    30

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    0 24 48 72 96 120 144

    C s

    d i s t r i

    b u t i o n

    ( - )

    1F2

    W/W

    RPV

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    Relative time (h)

    Date

    Fig. 2-1-13 Distribution of Cs (unit 2) [TEPCO-1]

    RCIC start manually, SBO, Water source change from CST to S/P, RCIC stop, Seawater inject., RPV depressurized, S/R valve-2 open, Impact sound

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    31/53

    Attachment IV-2

    31

    0

    20

    40

    60

    80

    100

    0

    500

    1000

    1500

    2000

    2500

    3000

    0 24 48 72 96 120 144

    1F2RCIC

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    I n j e c t e d w a t e r

    ( m 3 / h )

    T o t a l

    a m o u n t

    ( m 3 )

    Total

    Fire protection

    Relative time (h)

    Date

    Fig. 2-2-1 Amount of water injection (unit 2) [TEPCO-2]

    RCIC start manually, SBO, Water source change from CST to S/P, RCIC stop, Seawater inject., RPV depressurized, S/R valve-2 open, Impact sound

    0.0

    1.0

    2.0

    3.0

    4.0

    5.0

    6.0

    7.0

    8.0

    -4000

    -2000

    0

    2000

    4000

    6000

    0 24 48 72 96 120 144

    1F2

    TAF

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    P r e s s . (

    M P a )

    a t e r

    l e v e

    l ( m m

    )

    ()Observed data

    RPV press.

    Relative time (h)

    Date

    Water level

    Fig. 2-2-2 RPV pressure and water level (unit 2) [TEPCO-2]

    RCIC start manually, SBO, Water source change from CST to S/P, RCIC stop, Seawater inject., RPV depressurized, S/R valve-2 open, Impact sound

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    32/53

    Attachment IV-2

    32

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    0 24 48 72 96 120 144

    P r e s s .

    M P a

    ()Observed data

    2Pd

    1Pd

    D/W press.

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    Relative time (h)

    Date

    Fig. 2-2-3 D/W pressure (unit 2) [TEPCO-2]RCIC start manually, SBO, Water source change from CST to S/P, RCIC stop, Seawater inject., RPV depressurized, S/R valve-2 open, Impact sound

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    0 24 48 72 96 120 1440

    100

    200

    300

    400

    500

    P r e s s .

    M P a

    Relative time (h)

    ()Observed data

    D/W press.

    2Pd

    1Pd

    Date

    T e m p .

    K

    S/C press.

    Saturation temp.D/W temp.

    S/P temp.

    3/12 3/133/14 3/15 3/16 3/17 3/18

    Fig. 2-2-4 PCV pressure and temperature (unit 2) [TEPCO-2]

    RCIC start manually, SBO, Water source change from CST to S/P, RCIC stop, Seawater inject., RPV depressurized, S/R valve-2 open, Impact sound

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    33/53

    Attachment IV-2

    33

    0

    500

    1000

    1500

    2000

    2500

    3000

    0 24 48 72 96 120 144

    M a x

    i m u m t e m p .

    o f c o r e

    ( K )

    1F2

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    Relative time (h)

    Date

    Fig. 2-2-5 Maximum temperature of the core (unit 2) [TEPCO-2]

    RCIC start manually, SBO, Water source change from CST to S/P, RCIC stop, Seawater inject., RPV depressurized, S/R valve-2 open, Impact sound

    0

    20

    40

    60

    80

    100

    0 24 48 72 96 120 1440.0

    0.2

    0.4

    0.6

    0.8

    1.0

    M a s s

    ( t o n

    )

    1F2

    Relative time (h)

    Date

    Intact fuel

    Debris

    R a t

    i o ( - )

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    Fig. 2-2-6 Mass of the core (unit 2) [TEPCO-2]RCIC start manually, SBO, Water source change from CST to S/P, RCIC stop, Seawater inject., RPV depressurized, S/R valve-2 open, Impact sound

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    34/53

    Attachment IV-2

    34

    Top

    Bottomperiphery periphery

    Top

    Bottomperiphery periphery

    centert = 80 h

    centert = 90 h

    ratio1.0

    0.8

    0.6

    0.4

    0.2

    0.0

    raio1.0

    0.8

    0.6

    0.4

    0.2

    0.0

    Fig. 2-2-7 Distribution of intact fuel (unit 2) [TEPCO-2]

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    35/53

    Attachment IV-2

    35

    0

    200

    400

    600

    800

    1000

    0 24 48 72 96 120 144

    H y d r o g e n

    ( k g )

    1F2

    Generated hydrogen

    Leakage from PCV

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    Relative time (h)

    Date

    Fig. 2-2-8 Hydrogen generation (unit 2) [TEPCO-2]

    RCIC start manually, SBO, Water source change from CST to S/P, RCIC stop, Seawater inject., RPV depressurized, S/R valve-2 open, Impact sound

    0.000

    0.005

    0.010

    0.015

    0.020

    0.025

    0.030

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    0 24 48 72 96 120 144

    1F2

    Noble gas

    Noble gas(accumulated)

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    F P r e

    l e a s e r a t i o

    ( - )

    A c c u m u

    l a t e

    d F P r e

    l e a s e r a t i o

    ( - )

    Relative time (h)

    Date

    Fig. 2-2-9 FP release ratio to the environment (1/2) (unit 2) [TEPCO-2]RCIC start manually, SBO, Water source change from CST to S/P, RCIC stop, Seawater inject., RPV depressurized, S/R valve-2 open, Impact sound

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    36/53

    Attachment IV-2

    36

    10 -5

    10 -4

    10 -3

    10-2

    10 -10

    10 -8

    10 -6

    10 -4

    10 -2

    10 0

    0 24 48 72 96 120 144

    Noble gasCsICsTeBaRuCeLa

    1F2

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    F P r e

    l e a s e r a t i o

    ( - )

    A c c u m u l a t e d

    F P r e

    l e a s e r a t i o

    ( - )

    Relative time (h)

    Date

    Solid line (left axis)Dashed line (right axis)

    Fig. 2-2-10 FP release ratio to the environment (2/2) (unit 2) [TEPCO-2]RCIC start manually, SBO, Water source change from CST to S/P, RCIC stop, Seawater inject., RPV depressurized, S/R valve-2 open, Impact sound

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    0 24 48 72 96 120 144

    RPV

    W/W

    D/W

    R/B

    FHB

    Environment C s I

    d i s t r

    i b u t

    i o n

    ( - )

    1F2

    W/W

    RPV

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    Relative time (h)

    Date

    Fig. 2-2-11 Distribution of CsI (unit 2) [TEPCO-2]

    RCIC start manually, SBO, Water source change from CST to S/P, RCIC stop, Seawater inject., RPV depressurized, S/R valve-2 open, Impact sound

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    37/53

    Attachment IV-2

    37

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    0 24 48 72 96 120 144

    RPV

    W/W

    D/W

    R/B

    FHB

    Environment

    C s

    d i s t r i

    b u t i o n

    ( - )

    1F2

    W/W

    RPV

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    Relative time (h)

    Date

    Fig. 2-2-12 Distribution of Cs (unit 2) [TEPCO-2]

    RCIC start manually, SBO, Water source change from CST to S/P, RCIC stop, Seawater inject., RPV depressurized, S/R valve-2 open, Impact sound

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    38/53

    Attachment IV-2

    38

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    0 12 24 36 48 60 72 84 96

    P r e s s .

    M P a

    ()Observed data

    D/W press.(no leakage)

    2Pd

    1Pd

    3/12 3/13 3/14 3/15

    Relative time (h)

    Date

    Fig. 2-3-1 D/W pressure (unit 2) [case-1]RCIC start manually, SBO, Water source change from CST to S/P, RCIC stop, Seawater inject., RPV depressurized, S/R valve-2 open, Impact sound

    0.0

    1.0

    2.0

    3.0

    4.0

    5.0

    6.0

    7.0

    8.0

    -4000

    -2000

    0

    2000

    4000

    6000

    0 12 24 36 48 60 72 84 96

    1F2

    RPV press.

    TAF

    Water level

    3/12 3/13 3/14 3/15

    P r e s s . (

    M P a )

    a t e r

    l e v e

    l ( m m

    )

    Relative time (h)

    Date

    ()Observed data

    Fig. 2-3-2 RPV pressure and water level (unit 2) [case-1]

    RCIC start manually, SBO, Water source change from CST to S/P, RCIC stop, Sea

    water inject., RPV depressurized, S/R valve-2 open, Impact sound

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    39/53

    Attachment IV-2

    39

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    0 12 24 36 48 60 72 84 96

    2Pd

    1Pd

    3/12 3/13 3/14 3/15

    P r e s s .

    M P a

    () Observed data

    D/W press.

    Relative time (h)

    Fig. 2-4-1 D/W pressure (unit 2) [case-2]RCIC start manually, SBO, Water source change from CST to S/P, RCIC stop, Seawater inject., RPV depressurized, S/R valve-2 open, Impact sound

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    0 12 24 36 48 60 72 84 96

    P r e s s .

    M P a

    ()Observed data

    D/W press.

    2Pd

    1Pd

    3/12 3/13 3/14 3/15

    Relative time (h)

    Date

    Fig. 2-5-1 D/W pressure (unit 2) [case-3]RCIC start manually, SBO, Water source change from CST to S/P, RCIC stop, Seawater inject., RPV depressurized, S/R valve-2 open, Impact sound

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    40/53

    Attachment IV-2

    40

    0

    50

    100

    150

    200

    0

    500

    1000

    1500

    2000

    2500

    0 24 48 72 96 120 144

    1F3

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    RCIC

    HPCI

    I n j e c t e d w a t e r

    ( m 3 / h )

    T o t a l

    a m o u n t

    ( m 3 )

    Total

    Fire protection

    Relative time (h)

    Date

    Fig.3-1-1 Amount of water injection (unit 3) [TEPCO-1]

    RCIC start manually, RCIC stop, HPCI start, HPCI stop, S/RV(open), PCV vent (open),Water inject., PCV vent (close), Sea water inject., PCV vent (open close)

    0.0

    1.0

    2.0

    3.0

    4.0

    5.0

    6.0

    7.0

    8.0

    -4000

    -2000

    0

    2000

    4000

    6000

    0 24 48 72 96 120 144

    1F3

    TAF

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    P r e s s .

    ( M P a

    )

    a t e r

    l e v e

    l ( m m

    )

    ()Observed data

    RPV press.

    Downcomer

    Core

    Relative time (h)

    Date

    Fig.3-1-2 RPV pressure and water level (unit 3) [TEPCO-1]

    RCIC start manually, RCIC stop, HPCI start, HPCI stop, S/RV(open), PCV vent (open),

    Water inject., PCV vent (close), Sea water inject., PCV vent (open close)

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    41/53

    Attachment IV-2

    41

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    0 24 48 72 96 120 144

    2Pd

    1Pd

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    P r e s s .

    M P a

    () Observed data

    D/W press.

    Relative time (h)

    Date

    Fig.3-1-3 D/W pressure (unit 3) [TEPCO-1]

    RCIC start manually, RCIC stop, HPCI start, HPCI stop, S/RV(open), PCV vent (open),Water inject., PCV vent (close), Sea water inject., PCV vent (open close)

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    0 24 48 72 96 120 1440

    100

    200

    300

    400

    500

    2Pd

    1Pd

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    P r e s s .

    M P a

    ()Observed data

    D/W press.

    T e m p .

    K

    S/C press.

    Saturation temp.D/W temp.

    S/P temp.

    Relative time (h)

    Date

    Fig.3-1-4 PCV pressure and temperature (unit 3) [TEPCO-1]

    RCIC start manually, RCIC stop, HPCI start, HPCI stop, S/RV(open), PCV vent (open),Water inject., PCV vent (close), Sea water inject., PCV vent (open close)

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    42/53

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    43/53

    Attachment IV-2

    43

    Top

    Bottomperiphery periphery

    t = 50 h

    Top

    Bottomperiphery periphery

    t = 90 h

    center

    center

    ratio1.0

    0.8

    0.6

    0.4

    0.2

    0.0

    ratio1.0

    0.8

    0.6

    0.4

    0.2

    0.0

    Fig.3-1-7 Distribution of intact fuel (unit 3) [TEPCO-1]

    0

    200

    400

    600

    800

    1000

    0 24 48 72 96 120 144

    1F3

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    H y d r o g e n

    ( k g ) Generated hydrogen

    Leakage from PCV

    Relative time (h)

    Date

    Fig.3-1-8 Hydrogen generation (unit 3) [TEPCO-1]

    RCIC start manually, RCIC stop, HPCI start, HPCI stop, S/RV(open), PCV vent (open),

    Water inject., PCV vent (close), Sea water inject., PCV vent (open close)

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    44/53

    Attachment IV-2

    44

    0.0

    0.1

    0.2

    0.3

    0.4

    0.5

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    0 24 48 72 96 120 144

    1F3

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    F P r e

    l e a s e r a t i o

    ( - )

    A c c u m u l a t e d

    F P r e

    l e a s e r a t i o

    ( - )

    Relative time (h)

    Date

    Noble gas(accumulated)

    Noble gas

    10 -5

    10 -4

    10 -3

    10 -2

    10 -1

    100

    10 -11

    10 -9

    10 -7

    10 -5

    10 -3

    10 -1

    0 24 48 72 96 120 144

    Noble gasCsICsTeBaRuCeLa

    1F3

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    F P r e

    l e a s e r a t i o

    ( - )

    A c c u m u l a t e d

    F P r e

    l e a s e r a t i o

    ( - )

    Relative time (h)

    Date

    Solid line (left axis)Dashed line (right axis)

    Fig.3-1-9 FP release ratio to the environment (unit 3) [TEPCO-1]

    RCIC start manually, RCIC stop, HPCI start, HPCI stop, S/RV(open), PCV vent (open),Water inject., PCV vent (close), Sea water inject., PCV vent (open close)

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    45/53

    Attachment IV-2

    45

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    0 24 48 72 96 120 144

    1F3

    W/W

    RPV

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    C s I

    d i s t r

    i b u t

    i o n

    ( - )

    Relative time (h)

    Date

    Fig.3-1-10 Distribution of CsI (unit 3) [TEPCO-1]

    RCIC start manually, RCIC stop, HPCI start, HPCI stop, S/RV(open), PCV vent (open),Water inject., PCV vent (close), Sea water inject., PCV vent (open close)

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    0 24 48 72 96 120 144

    1F3

    W/W

    RPV

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    C s

    d i s t r i

    b u t i o n

    ( - )

    Relative time (h)

    Date

    Fig.3-1-11 Distribution of Cs (unit 3) [TEPCO-1]

    RCIC start manually, RCIC stop, HPCI start, HPCI stop, S/RV(open), PCV vent (open),Water inject., PCV vent (close), Sea water inject., PCV vent (open close)

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    46/53

    Attachment IV-2

    46

    0

    50

    100

    150

    200

    0

    500

    1000

    1500

    2000

    0 24 48 72 96 120 144

    1F3

    HPCI

    RCIC

    I n j e c t e d w a t e r

    ( m 3 / h )

    T o t a l

    a m o u n t

    ( m 3 )Total

    Fire protection

    Relative time (h)

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    Fig.3-2-1 Amount of water injection (unit 3) [TEPCO-2]

    RCIC start manually, RCIC stop, HPCI start, HPCI stop, S/RV(open), PCV vent (open),Water inject., PCV vent (close), Sea water inject., PCV vent (open close)

    0.0

    1.0

    2.0

    3.0

    4.0

    5.0

    6.0

    7.0

    8.0

    -4000

    -2000

    0

    2000

    4000

    6000

    0 24 48 72 96 120 144

    1F3

    TAF

    P r e s s . (

    M P a )

    a t e r

    l e v e

    l ( m m

    )

    ()Observed dataRPV press.

    Water level

    Relative time (h)

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    Fig.3-2-2 RPV pressure and water level (unit 3) [TEPCO-2]

    RCIC start manually, RCIC stop, HPCI start, HPCI stop, S/RV(open), PCV vent (open),Water inject., PCV vent (close), Sea water inject., PCV vent (open close)

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    47/53

    Attachment IV-2

    47

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    0 24 48 72 96 120 144

    2Pd

    1Pd

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    P r e s s .

    M P a

    () Observed data

    D/W press.

    Relative time (h)

    Date

    Fig.3-2-3 D/W pressure (unit 3) [TEPCO-2]

    RCIC start manually, RCIC stop, HPCI start, HPCI stop, S/RV(open), PCV vent (open),Water inject., PCV vent (close), Sea water inject., PCV vent (open close)

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    0 24 48 72 96 120 1440

    100

    200

    300

    400

    500

    600

    2Pd

    1Pd

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    P r e s s .

    M P a

    ()Observed data

    D/W press.

    T e m p .

    K

    S/C press.

    Saturation temp.

    D/W temp.

    S/P temp.

    Relative time (h)

    Date

    Fig.3-2-4 PCV pressure and temperature (unit 3) [TEPCO-2]

    RCIC start manually, RCIC stop, HPCI start, HPCI stop, S/RV(open), PCV vent (open),Water inject., PCV vent (close), Sea water inject., PCV vent (open close)

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    48/53

    Attachment IV-2

    48

    0

    500

    1000

    1500

    2000

    2500

    3000

    0 24 48 72 96 120 144

    1F3

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    M a x

    i m u m t e m p .

    o f c o r e

    ( K )

    Relative time (h)

    Date

    Fig.3-2-5 Maximum temperature of the core (unit 3) [TEPCO-2]

    RCIC start manually, RCIC stop, HPCI start, HPCI stop, S/RV(open), PCV vent (open),Water inject., PCV vent (close), Sea water inject., PCV vent (open close)

    0

    20

    40

    60

    80

    100

    0 24 48 72 96 120 1440.0

    0.2

    0.4

    0.6

    0.8

    1.0

    1F3

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    M a s s

    ( t o n

    )

    Intact fuel

    Debris

    R a t

    i o ( - )

    Relative time (h)

    Date

    Fig.3-2-6 Mass of the core (unit 3) [TEPCO-2]

    RCIC start manually, RCIC stop, HPCI start, HPCI stop, S/RV(open), PCV vent (open),Water inject., PCV vent (close), Sea water inject., PCV vent (open close)

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    49/53

    Attachment IV-2

    49

    Top

    Bottomperiphery periphery

    Top

    Bottomperiphery periphery

    centert = 50 h

    centert = 80 h

    ratio1.0

    0.8

    0.6

    0.4

    0.2

    0.0

    ratio1.0

    0.8

    0.6

    0.4

    0.2

    0.0

    Fig.3-2-7 Distribution of intact fuel (unit 3) [TEPCO-2]

    0

    200

    400

    600

    800

    1000

    1200

    0 24 48 72 96 120 144

    1F3

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    H y d r o g e n

    ( k g )

    Generated hydrogen

    Leakage from PCV

    Relative time (h)

    Date

    Fig.3-2-8 Hydrogen generation (unit 3) [TEPCO-2]

    RCIC start manually, RCIC stop, HPCI start, HPCI stop, S/RV(open), PCV vent (open),

    Water inject., PCV vent (close), Sea water inject., PCV vent (open close)

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    50/53

    Attachment IV-2

    50

    0.0

    0.1

    0.2

    0.3

    0.4

    0.5

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    0 24 48 72 96 120 144

    1F3

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    F P r e

    l e a s e r a t i o

    ( - )

    A c c u m u l a t e d

    F P r e

    l e a s e r a t i o ( -

    )

    Relative time (h)

    Date

    Noble gas(accumulated)

    Noble gas

    0

    1 10 -4

    2 10 -4

    3 10 -4

    4 10 -4

    5 10 -4

    0

    1 10 -3

    2 10 -3

    3 10 -3

    4 10 -3

    5 10 -3

    0 24 48 72 96 120 144

    CsICs

    Te

    Ba

    1F3

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    F P r e

    l e a s e r a t i o

    ( - )

    A c c u m u l a t e d

    F P r e

    l e a s e r a t i o

    ( - )

    Relative time (h)

    Date

    Solid line (left axis)Dashed line (right axis)

    Fig.3-2-9 FP release ratio to the environment (1/2) (unit 3) [TEPCO-2]

    RCIC start manually, RCIC stop, HPCI start, HPCI stop, S/RV(open), PCV vent (open),Water inject., PCV vent (close), Sea water inject., PCV vent (open close)

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    51/53

    Attachment IV-2

    51

    10 -5

    10 -4

    10 -3

    10 -2

    10 -1

    10 0

    10 -10

    10 -8

    10 -6

    10 -4

    10 -2

    10 0

    0 24 48 72 96 120 144

    Noble gasCsICsTeBaRuCeLa

    1F3

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    F P r e

    l e a s e r a t i o

    ( - )

    A c c u m u l a t e d

    F P r e

    l e a s e r a t i o ( -

    )

    Relative time (h)

    Date

    Solid line (left axis)Dashed line (right axis)

    Fig.3-2-10 FP release ratio to the environment (2/2) (unit 3) [TEPCO-2]

    RCIC start manually, RCIC stop, HPCI start, HPCI stop, S/RV(open), PCV vent (open),Water inject., PCV vent (close), Sea water inject., PCV vent (open close)

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    0 24 48 72 96 120 144

    1F3

    W/W

    RPV

    Environment

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    C s I d i s t r

    i b u t

    i o n

    ( - )

    Relative time (h)

    Date

    Fig.3-2-11 Distribution of CsI (1/2)(unit 3) [TEPCO-2]

    RCIC start manually, RCIC stop, HPCI start, HPCI stop, S/RV(open), PCV vent (open),Water inject., PCV vent (close), Sea water inject., PCV vent (open close)

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    52/53

    Attachment IV-2

    52

    10 -4

    10 -3

    10 -2

    10 -1

    100

    0 24 48 72 96 120 144

    1F3

    W/W

    RPV

    Environment

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    D/W

    E/B

    C s I

    d i s t r

    i b u t

    i o n

    ( - )

    Relative time (h)

    Date

    Fig.3-2-12 Distribution of CsI (2/2)(unit 3) [TEPCO-2]

    RCIC start manually, RCIC stop, HPCI start, HPCI stop, S/RV(open), PCV vent (open),Water inject., PCV vent (close), Sea water inject., PCV vent (open close)

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    0 24 48 72 96 120 144

    1F3

    W.W

    RPV

    Environment

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    C s d i s t r i

    b u t i o n

    ( - )

    Relative time (h)

    Date

    Fig.3-2-13 Distribution of Cs (1/2)(unit 3) [TEPCO-2]

    RCIC start manually, RCIC stop, HPCI start, HPCI stop, S/RV(open), PCV vent (open),Water inject., PCV vent (close), Sea water inject., PCV vent (open close)

  • 7/31/2019 Abstracts of the Cross Check Analysison the Evaluation of the Cores of Unit 1, 2 and 3 of Fukkushima Dai-IchiNPP

    53/53

    Attachment IV-2

    0.0

    0.0

    0.0

    0.1

    1.0

    0 24 48 72 96 120 144

    1F3

    W.W

    RPV

    Environment

    3/12 3/13 3/14 3/15 3/16 3/17 3/18

    D/W

    R/B

    C s

    d i s t r i

    b u t i o n

    ( - )

    Relative time (h)

    Date

    Fig.3-2-14 Distribution of Cs (2/2)(unit 3) [TEPCO-2]

    RCIC start manually, RCIC stop, HPCI start, HPCI stop, S/RV(open), PCV vent (open),Water inject., PCV vent (close), Sea water inject., PCV vent (open close)