abcd alstom (switzerland) ltd. nhon trach 1 …eam.pv-power.vn/attachments/0000676280.pdfoperation...
TRANSCRIPT
Owner’s Consultants
ESB International
Owner PETRO VIETNAM
GPPMB
PECC2
EPC Contractor
LILAMA – CC1 CONSORTIUM
Issued by
LILAMA CORPORATION – HYUNDAI ENGINEERING
Subcontractor
abcd
ALSTOM (Switzerland) Ltd.
Project
NHON TRACH 1 CCPP PROJECT
Owner’s Identification No. EPC Contractor Identification No.
ALSTOM Document Code NHT/01/M/-------B20/MM/001
Revision History
Rev. Revision Date Created by Checked by Approved by Description
A 10.04.2008 D.E.YANG J.W.SHIN K.R.KIM First issue
Description latest Revision:
OPERATION AND MAINTENANCE MANUAL FOR CONDENSATE EXTRACTION PUMPS
(1)
PETRO VIETNAM
GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
i
TABLE OF CONTENT CHAPTER DESCRIPTION PAGE
1.0 OPERATION ---------------------------------------------------------------------- 1
1.1 Environment, Health and Safety Instruction ------------------------------------ 1
1.2 Description of Equipment ---------------------------------------------------------- 4
1.3 Operation ----------------------------------------------------------------------------- 7
2.0 MAINTENANCE ------------------------------------------------------------------ 12
2.1 Environment, Health and Safety Instruction for Maintenance ----------------- 12
2.2 General and Preventive Maintenance --------------------------------------------- 15
2.3 Corrective Maintenance ------------------------------------------------------------- 25
2.4 Decommissioning -------------------------------------------------------------------- 28
2.5 Packing, Transport and Disposal --------------------------------------------------- 35
2.6 Component Documentation --------------------------------------------------------- 38
- SECTION 1 : MOTOR
- SECTION 2 : MECHANICAL SEAL
- SECTION 3 : GEAR COUPLING
3.0 TECHNICAL DOCUMENTATION
- Data sheet NHT/01/M/-------B20/DS/001
- Performance curves
- Outline drawing
NHT/01/M/-------B20/MD/002
NHT/01/M/-------B20/MD/002
- Sectional drawing NHT/01/M/-------B20/DD/001
(2)
PETRO VIETNAM
GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
ii
- P & I diagram NHT/01/M/-------B20/DD/002
- Installation drawing NHT/01/M/-------B20/DD/003
- Aux. piping drawing NHT/01/M/-------B20/PS/001
- Nameplate drawing NHT/01/M/-------B20/DD/006
- Mechanical seal detail drawing & data NHT/01/M/-------B20/DD/004
- Coupling detail drawing & data NHT/01/M/-------B20/DD/005
- Spare and wear part list NHT/01/M/-------B20/LS/001
- Special tool list NHT/01/M/-------B20/LS/002
- Inspection & Test Plan NHT/01/M/-------B20/MP/001
- Inspection & Test Procedure NHT/01/M/-------B20/MP/002
- Painting specification NHT/01/M/-------B20/MP/003
- Erection Instructions NHT/01/M/-------B20/EI/005
- Erection follow up list NHT/01/M/-------B20/MA/001
- Erection document list NHT/01/M/-------B20/DL/006
- KKS number list NHT/01/M/-------B20/LE/001
- Measurement list NHT/01/M/-------B20/LI/001
- Signal exchange list NHT/01/M/-------B20/LM/001
- Electrical terminal list NHT/01/M/-------B20/TC/001
- Electrical consumer list NHT/01/M/-------B20/EL/002
- Electric connection diagram NHT/01/M/-------B20/WD/001
- Instrument data sheet NHT/01/M/-------B20/DS/003
- Tech. specification for Induction Motor NHT/01/M/-------B20/MD/101
- Motor data sheet NHT/01/M/-------B20/DS/101
- Motor outline drawing NHT/01/M/-------B20/DD/101
- Motor general assembly drawing NHT/01/M/-------B20/DD/102
- Motor main terminal box ass’y NHT/01/M/-------B20/DD/103
- Motor acc’y terminal box ass’y NHT/01/M/-------B20/DD/104
(3)
PETRO VIETNAM
GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
iii
- Motor heater terminal box ass’y NHT/01/M/-------B20/DD/105
- Motor speed torque & current curve NHT/01/M/-------B20/DD/106
- Motor thermal limit & time current curve NHT/01/M/-------B20/DD/107
- Motor painting procedure NHT/01/M/-------B20/DD/108
- Motor wiring diagram NHT/01/M/-------B20/TC/101
- Motor instrument list NHT/01/M/-------B20/LI/101
- Motor test plan & test procedure NHT/01/M/-------B20/MP/001
(4)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
1
1.0 OPERATION 1.1 Environment, Health and Safety Instruction
SAFETY STANDARDS Persons responsible for the equipment covered in this manual must ensure that it is properly and safely installed and maintained, operated at the specified conditions. Only appropriately qualified staff, applying acceptable standards of engineering practice and the recommendations contained in this manual, must be employed in these activities. Any similar instructions for the overall plant in which the equipment is to be incorporated, which have an influence on the equipment application, must be strictly followed. Statutory and local requirements concerning work practices, safety and/or health precautions must be observed. Where appropriate, warnings, cautions and notes are included in the manual, and are defined as follows ;
WARNINGS : A warning calls attention to instructions which must be followed to avoid danger to personnel.
CAUTION : A caution calls attention to instruction to instructions which must be followed to avoid damaging the equipment or its surroundings. NOTE : A note gives supplementary information where considered necessary. OPERATING CONDITIONS If the equipment application or operating conditions differ from the equipment was supplied, the equipment was supplied, the equipment and the operating recommendations contained in this manual may be inappropriate. In such circumstances verification of the suitability of the equipment and of the operating and maintenance manual must be obtained in writing from HHI. The contents given below should always be followed since any of them covers important notes on safety. 1. General
1) Never allow any persons other than service engineers to engage in disassembly or repair, or remodeling work.
2) Never work alone and be sure to put on helmet, safety goggles, ear plugs, safety shoes, etc. in
(5)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
2
conformity with the Labor Safety and Health Law, etc.
3) Prior to carrying out any sparking work such as welding, etc., make sure that there are no dangers of fire and explosion hazards.
4) Check the place where emission of toxic gas and deficiency of oxygen are conceivable, such as pit, manhole, etc. before starting on work and make sure of safety.
5) When carrying out the work for centering check, disassembly, etc., be sure to turn OFF the motor switch and affix a tag indicating “NO POWER ON” or the like to the switch so that the switch will not be turned ON by mistake.
6) Before starting on work, be sure to conduct checking of slinging outfits such as crane, wire rope, etc. unfailingly.
7) Install safety fences around the working area and secure an emergency passageway.
8) Since any split oil on the floor, passageway etc, may lead to a cause of slippage etc., wipe it off forthwith.
9) Shaft seal parts will not function to stop the pumped-liquid completely. When handling such a liquid which may cause serious troubles to the human body, therefore, do not touch the splashing liquid from shaft seal parts.
10) Keep away from the casing of the pump that is handling such a hot liquid as may lead to a danger of scalds if coming in contact with the human body.
11) Do not gain access to rotating parts recklessly since there is a possibility of scattering caused by breakage of rotating parts.
12) Take precautions against the possible breakage and scattering which may be caused if leaning against or stopping on the guard.
13) Do not open the thermal cover of electrical devices including motors as there is a danger of electrification while they are being energized.
2. Handling Where both pump and motor are assembled on the common bed, never hang a wire rope on the eyebolt of the motor. Furthermore, do not gain access to the underside of the suspended pump. 3. Direct-coupling For the type of coupling applied with safety cover (coupling cover), fix the safety cover securely to
(6)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
3
the predetermined position with clamping bolts. 4. Disassembly and Reassemble
1) Before carrying out the disassembly work, be sure to turn OFF the motor switch and affix a tag indicating NO POWER ON” or the like to the switch so that the switch will not be turned ON by mistake.
2) Shut off the valves on the suction side and discharge side totally and, in the case of hot liquid, discharge the pump interior liquid from drain valve at the point when the casing temperature has come down to the room temperature or so.
3) Where the pumped-up liquid is a chemical solution, it may lead to a danger of causing injuries such as inflammation and the like if adhering to the human body.
To prevent this, make sure that the casing interior liquid has been discharged thoroughly.
4) When removing parts and partly-assembled components, hang wire ropes to the positions as shown in the instruction manual and use a chain block, etc.
5) When handling hot components such as ball bearing, coupling, etc., be sure to put on protective gloves.
(7)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
4
1.2 DESCRIPTION OF EQUIPMENT
1.2.1 GENERAL DESCRIPTION
This pump has been manufactured with strict quality control and has been designed to demonstrate maximum efficiency during operation. In particular, the impeller which is the most critical part, has been designed based on the three dimensional blade theory to obtain a high efficiency with a minimum of loss. The sliding parts of the rotating body which are subjected to wear are replaceable, and interchangeability of all parts with other pumps of the same type has been taken into consideration. There are no difficulties with operation however, care must be taken to insure that the pump itself and the pipeline are always filled with water. The driver is a motor. For a full understanding of the motor, please carefully read the motor's instruction manual and become thoroughly familiar with it. After careful reading of this pump instruction manual, be sure to operate the pump unit always keeping in mind the operation of the entire plant rather than only operation of the pump alone. 1.2.2 CONSTRUCTION
The condensate extraction pump is a vertical, multi-stage type. Refer to the Pump Sectional Assembly and Outline Drawing provided for the shape, dimensions and structure of this pump. The pump is supported in the vertical position by the mounting flange which is an integral part of the can (1180). The pump driver is mounted on the motor pedestal (1131) and is coupled to the upper shaft (1310B) by means of a flexible coupling (1850). The pump thrust bearing (1440) supports the weight of the pump rotor plus any up or down thrust that is created within the pump. The mechanical seal is used to seal the liquid within the pump at the point where the upper shaft passes through the stuffing box (1610).
1.2.2.1 PUMP CASING The pump casing is composed of the suction cover, volute casing, volute discharge casing, discharge bowl, column pipe and discharge head.
1) Discharge head (1130) The discharge head consists of four parts. Suction/discharge nozzles which are flanged for
(8)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
5
connection to system piping.
Stuffing box (1610) containing mechanical seal that
control liquid leakage to the atmosphere at the pump
shaft where it protrudes through the pressure boundary.
The stuffing box to discharge head joint is sealed by gasket. Radial and thrust bearing case for pump are also mounted on the supporting flange which is bolted to the motor pedestal.
Flanges which are bolted to the can (1180) and column pipe.
The can to discharge head (1130) joint is sealed by a rubber ring.
2) Discharge bowl (1120) The bowl act in directing the flow of liquid through diffuser passage while helping to increase pressure through each successive stage. Bowl contains the bearing fit for a sleeve bearing (1540), plus the casing rings (1230). All bolts are mechanically locked to prevent loosening.
3) Column pipe (1140) The column pipe is fabricated from carbon steel plate and has sufficient strength to withstand the weight and internal pressure of pump.
4) Suction cover (1150A/B) The suction bell consists of a hub which contains sleeve bearing (1540), plus supporting ribs which serve as liquid flow guides. It also contains the suction cover casing rings (1230A) for the first stage impeller (1210A). The suction cover bolts to volute casing (1151), housing the first stage impeller. The suction cover to volute casing joint is sealed by rubber-ring.
5) Volute casing (1151), Discharge volute casing (1152) The casing (1151,1152) consist of hydraulic diffuser passage which convert fluid velocity to pressure. The volute casing contains the bearing fit for sleeve bearing (1540) which prevents the lower shaft from any radial gyrations. The discharge volute casing also houses the casing ring (1230A) for the second stage impeller (1210B). All casing to casing joint are sealed by use of rubber rings. 1.2.2.2 ROTATING PARTS
1) Impeller (1210A/B/C/D) The double suction first stage impeller (1210A) is keyed and held in position on lower shaft (1310A)
(9)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
6
by impeller nut (1212). The remaining impeller is also keyed to the lower shaft (1310A). The impeller has held in position on its respective pump shaft by use of split ring (1883). All impellers are of the enclosed type, one piece construction and are dynamically balanced.
2) Shaft (1310A/B) All shafts are special quality stainless steel and used to transmit the driving force from the motor to the pump impeller (1210).
3) Muff coupling (1840) Keyed and sleeve type coupling provide ease of assembly and disassemble. The coupling slides over the shaft and is keyed to both shafts to transmit the pump torque.
4) Flexible coupling (Gear coupling, 1850) Concentricity of bores and parallelism of machined faces are checked prior to final assemble to insure proper alignment of pump and motor shaft. 1.2.2.3 OTHER PARTS
1) Can (1180) The can encloses the pumping element and provides for immediate containment of the liquid being pumped.
2) Shaft sleeve (1320A/B) The shaft sleeves are of the replaceable type and held in position on the pump shafts(1310A/B) by use of key.
3) Sleeve bearing (1540A/B/C) Sleeve bearing for pump is composed of carbon and nickel. Spiral groove inside of this bearing help the lubrication and prevent from clogging. They are mounted within suction cover, discharge volute casing, discharge bowl, column pipe and stuffing box. The sleeve bearings are renewable and lubricated by the liquid being pumped.
(10)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
7
1.3 OPERATION
During the initial trial operation after installation and operation after disassembly, carefully follow paragraphs.
1.3.1 PIPING CHECK BEFORE START UP
1) Discharge
a) Ensure that discharge supports are located as specified on the construction drawing. b) Check the supports are properly installed. c) Discharge supports should be adequate to support and/or dampen excessive piping vibration. d) Ensure that the valves in the discharge piping are supported. e) Check valve and discharge vent are located below the static water elevation of the system. f) Ensure that all high points in minimum flow by-pass system are adequately vented.
2) Suction
a) Ensure that supports are located as specified on the construction drawing. b) Check that the suction valve is supported. c) If expansion joints are employed with the rods, ensure that they are uniformly tightened. d) The system has to be checked for water leaks. e) All high points in suction piping have to be vented. f) Provision for continuous venting have to be made for the point where air pockets cannot be avoided. g) Check provisions to monitor suction strainer head losses (blockage) are available.
1.3.2 PREPARATIONS AND CHECKS FOR PRE-START 1) Ensure that the control panel system is correctly connected to the pump set and all functions are satisfactory. 2) Check the quantity of lubricant oil for the thrust bearing. 3) Check the cooling water line for pump thrust bearing.
(11)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
8
4) Check the mechanical seal according to "Mechanical seal drawing" and "Manual for mechanical seal". CAUTION : Ensure that centering tabs shall be removed before running pump according to seal drawing. 5) Turn only the motor shaft by hand. 6) Confirm the motor rotating direction by starting it just for a moment. It should be clockwise viewed from the motor top. 7) Connect the coupling. Ensure that the reamer bolts are inserted to the coupling and all nuts are fastened. Also the coupling guard is installed in the windows of the discharge head. 8) Check the auxiliary piping. It is especially necessary to confirm the opening or closing of valves at the piping. 9) No protection relay should be actuated, if any. 1.3.3 STARTING STEP Correct starting of the pump will assure maximum service life, whereas, incorrect starting can cause premature wear. 1) Close discharge valve 2) Check that the sealing liquid is injected to the mechanical seal during the following: a) During pump running b) During "stand-by" condition if pump is operating under vacuum. 3) Open the suction valve slowly. Make sure the pump is completely filled with the liquid to be pumped.
WARNING : Before starting any centrifugal pump, the pump and suction piping must be completely filled with liquid. Damage can be caused if the pump is operated dry.
(12)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
9
4) Open the discharge and suction vent valves. 5) Start the pump. As soon as it is up to speed, open the discharge valve slowly to prevent any abrupt change in capacity. If the pump is to be used to fill or flush the system, the discharge valve must be regulated so that discharge pressure is at design pressure or above. 1.3.4 CAUTIONS FOR START-UP AND OPERATION Check to make sure that start-up requirements are completely satisfied. 1) Ensure that the seal water valves are opened. Before starting or while operating the pump, casing and suction line must be filled with the liquid being pumped. The rotating parts depend on this liquid for lubrication and the pump may seize if operated without water. 2) Discharge line to check valve should be fully primed to avoid water hammer damage. If this is not physically possible provisions should be made for slow motor starts, flywheel addition, or by-pass. 3) When operating for some time at reduced capacity, much of the pump horse power will go into the liquid in the form of heat. A by-pass must be provided under these conditions to prevent the liquid in the pump from becoming hot enough to vaporize. 4) Do not attempt any maintenance, inspection, repair or cleaning in the vicinity of rotating equipment. Such action could result in personnel injury. 5) Be careful not to start the pump under reverse flow condition, and not to operate at shut-off condition over than one (1) minute. We do not recommend that the pump be operated under prolonged or severe cavitating conditions. Avoid sustained pump operation below Min. flow. 6) For the first operation after pump installation or re-assembly, start the pump for a short time period. During this time, check that the equipment operates satisfactorily without detrimental surges, vibration, noise, etc. If operation is satisfactory, operate the pump continuously. 7) The unit must not be operated unless the coupling guard is placed at proper position. Failure to observe this could result in injury to operation personnel. 1.3.5 OPERATING CHECK
(13)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
10
1) Pay attention to abnormal noise and abnormal vibration. If air or foreign matter enters the pump, or if there is a change in the operation point or mis-operation and defect of valves in the discharge lines, abnormal noise and vibration will occur and pump discharge pressure will vary greatly or the current meter of the motor will vary suddenly during operation. In such cases, immediately check these problems and find the cause. 2) Check the motor temperature detector. After starting operation, pay attention to the temperature rise of the motor bearing. Even after the temperature reaches a steady value, occasionally check it. If an abnormal rise is noted in the temperature, immediately shut down the pump and investigate the cause. 3) Check the pump bearing temperature detector. After starting operation, pay attention to the temperature rise of the pump thrust bearing. Even after the temperature reaches a steady value, occasionally check it. 4) Emergency stopping. If following happens, it is preferred to interlock to stop the pump automatically.
a) Motor overload b) Starting delay c) Motor winding temp. rise : over 140 d) Motor bearing temp. rise : over 100 e) Pump thrust bearing temp. rise : over 90
1.3.6 SECURING THE PUMP 1) Close the discharge valve. 2) When discharge valve is completely closed, immediately trip the motor circuit to stop the pump. If pump stops abruptly when motor is shut down, investigate for pump binding. Take necessary remedial action before restarting pump. 3) Close the vent and drain valves in accordance with established plant procedures. 4) Turn off sealing liquid to stuffing box.
CAUTION : Do not close the suction valve before stopping the pump; this would cause the pump to run dry and may cause the pump to seize.
(14)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
11
1.3.7 FREEZING 1) When the pump is exposed to freezing temperatures while not in operation, care should be taken to prevent the liquid from freezing within the pump (seal flushing line, cooling water line, inside pump). If necessary, the pump should be drained. 2) Take adequate measures to protect motor from freezing temperatures while not in operation (i.e., cooling coils, when used, must be drained, etc.). See motor manufacturer's instructions.
(15)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
12
2.0 MAINTENANCE
2.1 Environment, Health and Safety Instruction for Maintenance
SAFETY STANDARDS
Persons responsible for the equipment covered in this manual must ensure that it is properly and
safely installed and maintained, operated at the specified conditions.
Only appropriately qualified staff, applying acceptable standards of engineering practice and the
recommendations contained in this manual, must be employed in these activities.
Any similar instructions for the overall plant in which the equipment is to be incorporated, which
have an influence on the equipment application, must be strictly followed.
Statutory and local requirements concerning work practices, safety and/or health precautions must be
observed.
Where appropriate, warnings, cautions and notes are included in the manual, and are defined as
follows ;
WARNINGS : A warning calls attention to instructions which must be followed to avoid danger to personnel.
CAUTION : A caution calls attention to instruction to instructions which must be followed to avoid damaging the equipment or its surroundings.
NOTE : A note gives supplementary information where considered necessary.
OPERATING CONDITIONS
If the equipment application or operating conditions differ from the equipment was supplied, the
equipment was supplied, the equipment and the operating recommendations contained in this manual
may be inappropriate. In such circumstances verification of the suitability of the equipment and of
the operating and maintenance manual must be obtained in writing from HHI.
The contents given below should always be followed since any of them covers important notes on
safety.
(16)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
13
1. General
1) Never allow any persons other than service engineers to engage in disassembly or repair, or
remodeling work.
2) Never work alone and be sure to put on helmet, safety goggles, ear plugs, safety shoes, etc. in
conformity with the Labor Safety and Health Law, etc.
3) Prior to carrying out any sparking work such as welding, etc., make sure that there are no dangers
of fire and explosion hazards.
4) Check the place where emission of toxic gas and deficiency of oxygen are conceivable, such as pit,
manhole, etc. before starting on work and make sure of safety.
5) When carrying out the work for centering check, disassembly, etc., be sure to turn OFF the motor
switch and affix a tag indicating “NO POWER ON” or the like to the switch so that the switch will
not be turned ON by mistake.
6) Before starting on work, be sure to conduct checking of slinging outfits such as crane, wire rope,
etc. unfailingly.
7) Install safety fences around the working area and secure an emergency passageway.
8) Since any split oil on the floor, passageway etc, may lead to a cause of slippage etc., wipe it off
forthwith.
9) Shaft seal parts will not function to stop the pumped-liquid completely. When handling such a
liquid which may cause serious troubles to the human body, therefore, do not touch the splashing
liquid from shaft seal parts.
10) Keep away from the casing of the pump that is handling such a hot liquid as may lead to a
danger of scalds if coming in contact with the human body.
11) Do not gain access to rotating parts recklessly since there is a possibility of scattering caused by
breakage of rotating parts.
12) Take precautions against the possible breakage and scattering which may be caused if leaning
against or stopping on the guard.
13) Do not open the thermal cover of electrical devices including motors as there is a danger of
electrification while they are being energized.
2. Handling
Where both pump and motor are assembled on the common bed, never hang a wire rope on the
eyebolt of the motor. Furthermore, do not gain access to the underside of the suspended pump.
(17)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
14
3. Direct-coupling
For the type of coupling applied with safety cover (coupling cover), fix the safety cover securely to
the predetermined position with clamping bolts.
4. Maintenance
When carrying out the work for replacement of gland packing or mechanical seal, be sure to turn
OFF the motor switch and affix a tag indicating “NO POWER ON” or the like to the switch so that
the switch will not be turned ON by mistake.
5. Disassembly and Reassemble
1) Before carrying out the disassembly work, be sure to turn OFF the motor switch and affix a tag
indicating NO POWER ON” or the like to the switch so that the switch will not be turned ON by
mistake.
2) Shut off the valves on the suction side and discharge side totally and, in the case of hot liquid,
discharge the pump interior liquid from drain valve at the point when the casing temperature has
come down to the room temperature or so.
3) Where the pumped-up liquid is a chemical solution, it may lead to a danger of causing injuries
such as inflammation and the like if adhering to the human body.
To prevent this, make sure that the casing interior liquid has been discharged thoroughly.
4) When removing parts and partly-assembled components, hang wire ropes to the positions as
shown in the instruction manual and use a chain block, etc.
5) When handling hot components such as ball bearing, coupling, etc., be sure to put on protective
gloves.
(18)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
15
2.2 GENERAL AND PREVENTIVE MAINTENANCE
2.2.1 ROUTINE MAINTENANCE
1) Daily Check
Performing daily inspections and keeping records of pump operation help in finding abnormalities
and preventing trouble in advance and record daily the followings.
Record daily the following ;
a) Discharge pressure
b) Water level of suction pit
c) Electric current
d) Electric voltage
e) Motor power
f) Temperature of motor bearings
g) Temperature of pump thrust bearings
h) Ambient temperature
i) Operation time
j) Flow at seal water line
k) Cooling water flow at pump thrust bearing line.
l) Lubrication oil level or grease quantity for bearing
2) Overhaul Check
a) Pumps should be overhauled once a year.
When overhauling a pump, check every part for wear, erosion, corrosion.
Also, measure and record the outside and inside diameter of sliding parts and their clearance. The
designed dimensions of these sliding parts are as shown in Table 2.1. If wear exceeds the allowable
value or nearly reaches it, replace any wear part with a new one.
b) Coupling and Keys
(19)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
16
Examine all keys for wear and damage. Make sure that they are flat, parallel and free from burrs,
and have a good fit in the key slot. Replace, if necessary.
c) Check the function of small valve in auxiliary piping
Table 2.1
2.2.2 DISASSEMBLY
Disassembly procedure shall be performed in the following order. Before starting disassembly, read
and study paragraph 2.2.3 CAUTIONS FOR DISASSEMBLY. Confirm that the working area is
sufficiently large and that the ground is flat enough for a crane to be used conveniently.
Prepare tools, lifting wire, temporary rust preventive, etc. Remove water from the pump and related
piping.
1) Break and tag motor circuit breaker. Disconnect electric leads and water cooling service lines.
Remove the coupling guard from discharge head.
2) Remove the coupling bolting.
3) Remove the motor to motor pedestal (1131) bolting
4) Rig the motor to an overhead hoist. Lift motor from the motor pedestal and place motor on
blocking on the floor.
Running Clearance (mm) Max. Allowable Clearance At Dry condition
1st Impeller wearing 0.45 ~ 0.553 0.83 Series Impeller wearing 0.50 ~ 0.622 0.93 Sleeve bearing (Lower) 0.13 ~ 0.16 0.24 Sleeve bearing (Inter, upper) 0.26 ~ 0.31 0.46
(20)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
17
5) Disconnect suction/discharge piping from discharge head (1130), plus auxiliary piping which will
interface with dismantling.
6) Remove flexible coupling with key from upper shaft (1310B).
7) Remove journal nut (1489), bearing cover (1443), radial bearing case (1441), radial bearing
(1430), journal (1488), thrust bearing (1440), thrust bearing case (1442) in sequence.
CAUTION : Do not disassembly the cooling water coil inside bearing box from thrust bearing case body.
8) Remove mechanical seal. (1893)
9) Remove the stuffing box(1610) from discharge head(1130).
CAUTION : Take care not to damage the mechanical seal(1893) in the process of removing the stuffing box (1610).
10) Rig sling at lifting rug hole of discharge head.
Remove bolt which secure discharge head flange to can (1180) flange.
Using overhead hoist, lift the pump proper from the can.
11) Position blocking under the volute casing, the discharge bowl, column pipe (1140) and discharge
head (1130) as shown in Fig. 1
Fig. 1
(21)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
18
12) Remove the discharge head to column pipe bolting.
13) Slide the discharge head and column pipe from the upper shaft and place them in a vertical
position on blocking on the floor. Remove rubber ring and discard. Soon after dismantling the
column pipe, support the shaft by wooden block in order to protect shaft from permanent bending.
14) Pull muff coupling toward discharge upper side and remove the upper shaft, muff coupling and
coupling collar. Place shaft on horses and block to prevent rolling.
15) Remove lower column pipe, intermediate shaft, muff coupling and coupling collar with the same
procedure as described in 13) and 14).
16) Remove bolting holding suction cover lower (1150A) to volute casing (1151).
17) Withdraw the suction cover lower and casing wear ring (1230A). This will expose the lower
shaft sleeve and first stage impeller. Remove exposed rubber ring from fit in flange of suction cover
and discard rubber ring.
18) Remove the snap ring in order to dismantle lower shaft sleeve (1320A) and key for sleeve from
the lower shaft.
19) Remove the impeller nut (1212), first stage impeller (1210A) and distance piece (1211).
20) Remove bolt holding volute casing (1151) to volute discharge casing (1152).
21) Remove volute casing (1151). After that upper suction cover (1150B) can be dismantled.
22) Remove bolt holding volute discharge casing (1152) to discharge bowl (1120A).
23) Remove volute discharge casing (1152).
24) Remove snap ring in order to dismantle inter shaft sleeve (1320B) and key for sleeve from the
(22)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
19
lower shaft (1310A).
25) Remove the split ring (1883) and the second stage impeller (1210B)
26) Remove second stage discharge bowl (1120A).
27) Remove snap ring in order to dismantle inter shaft sleeve (1320B) and key for sleeve from the
lower shaft (1310A).
28) Remove second stage split ring, impeller, discharge bowl, snap ring and inter shaft sleeve with
the same procedure as described in 25) ~ 27)
29) Remove the last stage discharge bowl (1120C).
30) Remove the split ring (1883) and the last stage impeller (1210D).
31) Remove the snap ring in order to dismantle inter shaft sleeve (1320B) and key for sleeve from
the lower shaft (1310A). Tag and record all items for reassembly purposes.
2.2.3 CAUTIONS FOR DISASSEMBLY
1) Cautions for unloading products
a) In hoisting heavy parts such as the pump proper, pay careful attention to attaching the wire rope so
that the load will be centered and the wire rope will not slip.
b) When lifting heavy parts, use soft padding under the wire to protect the coated and machined
surface from the wire. Do not raise or lower the parts too rapidly with the crane.
c) When mounting the parts on the ground, use protecting blocks between the parts and the
ground. Also, when assembling the pump parts horizontally, use protecting blocks under the pump
casing as shown in Fig. 2 to protect the coated surface and prevent rolling.
(23)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
20
d) When lifting the pump proper, be careful not to bump the wire on the coupling.
Fig. 2
2) Do not damage the surfaces of mating flanges.
3) Tape the shaft threads for protection after disassembly.
4) After disassembly, apply temporary rust prevention to the machined surfaces of the motor
pedestal, discharge elbow and outside surfaces of coupling.
5) When laying the shafts on the floor, support them more than three points per shaft (ends and
center of shaft), as horizontally as possible, to do not cause bending.
6) To prevent missing parts and confusion of parts with those from another machine, provide cases
for disassembled parts and put parts into the cases.
7) Put bolts into bags as a set, if necessary.
8) During and after disassembly, do not step on the auxiliary piping or drop anything on them,
because the auxiliary piping will be damaged.
9) Before attempting any inspection or repair on the pump the driver controls must be in the "off"
position, locked and tagged to prevent injury to personnel performing service on the pump.
(24)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
21
2.2.4 REASSEMBLY
The reassembly procedure should be performed in the opposite order of the disassembly. Before
starting the reassembly, read and study paragraph 2.2.3 CAUTIONS FOR REASSEMBLY.
For the centering of pump and motor, be careful of followings.
1) Check the level of the upper surface of the pump base. Tolerance of lever should be less than
0.05mm.
2) Mount the pump on the pump base.
3) Check the lubricant for the motor bearings and turn the motor shaft several times by hand.
4) Attach a dial gauge to the hub of motor coupling and turn the motor by hand.
To perform this centering, the motor can be moved horizontally with the push bolts, provided at the
top of motor pedestal.
a) The parallel misalignment shall be adjusted by moving the motor horizontally with the push
bolts which are fitted on the top of the motor pedestal. The parallel misalignment is the half of the
total indication reading on the dial indicator.
b) The angular misalignment shall be adjusted by inserting or removing the shim plate between
bottom side of motor flange and upper surface of motor pedestal, be sure not to touch the shaft or
coupling when taking the dial indicator reading.
The shaft centering should be less than 0.05mm as shown in Fig. 3
Between motor & pump shaft A(mm) B(mm) Below 0.05 Below 0.05
(25)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
22
Fig. 3
5) Adjust the impeller clearance.
a) First loosen the journal nut (1489) sufficiently in order to lower the pump rotor fully.
Be careful that the journal nut have left-hand thread.
b) Turn the journal nut until pump rotor is lift up to 5mm in order to adjust impeller clearance (axial
clearance between casing ring and impeller shall be 10mm) as shown in Fig.4.
Fig. 4 Adjusting of impeller clearance
6) Finally fasten the bolts between the motor and the discharge head.
7) Check the rotating direction of motor.
8) Connect the coupling of pump and motor side with the reamer bolts.
2.2.5 CAUTIONS FOR REASSEMBLY
1) Refer to paragraph 2.2.4, item 1) for unloading.
2) Clean and flush the interior of auxiliary piping just before reassembling.
(26)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
23
3) When reassembling each part, remove foreign material in the tap holes with compressed air and
check that there is no protuberancy or dust on the flange and fitting surfaces.
4) Be careful not to drop tools and small parts into the suction can. If these are sucked into the pump,
the rotating element, casing and impeller will be damaged.
5) Before reassembling, clean the temporary rust preventive from the machined surfaces of motor
base, discharge head and outside surfaces of the coupling. After completion of centering of the pump
and motor, and motor pre-commissioning, re-coat some rust preventive to the outside surfaces of the
coupling.
6) If wear of sliding parts exceeds the allowable value or nearly reaches the value, replace any worn
part with a new one. Refer to paragraph 2.2.1 2).
7) Generally, replace the consumables (such as O-rings, rubber rings, gland packing, etc.) with new
parts.
8) All reassembly must be done according to joint marks, which have been put on each part at shop
(for example, on the flange rim)
9) When assembling the impeller and coupling to the shaft and tightening the fixing bolts, spray or
coat anti-galling compound (Never Seez or equivalent) on the fitting surface, thread and reamer
surface to prevent seizing.
10) Details of "NEVER SEEZ" are shown in Table 2.2.
Table 2.2 Brand Name & Type Material Maker Prevention
NEVER SEEZ (AEROSOL AND STANDARD TYPE)
HYDRO CARBON COMPOUND, ETC.
NEVER SEEZ COMPOUND CORP.
SEIZING
11) Fastening direction of the impeller nuts : Clockwise (C.W)
(27)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
24
12) To prevent uneven tightening, tighten flange bolts in a cross-cross pattern as shown in Fig. 5
Fig. 5
13) After reassembly, repeatedly check to make sure that all bolts of each flanges and other parts are
completely and evenly tightened.
14) Touch up the coated surface with paint which has been damaged during reassembling. After
completion of centering of the pump and motor, and motor pre-commissioning, re-coat some rust
preventive to the outside surfaces of the coupling.
15) During and after reassembly, do not step on the auxiliary piping or drop anything on them,
because the auxiliary piping will be damaged.
(28)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
25
2.3 CORRECTIVE MAINTENANCE
2.3.1 TROUBLE SHOOTING
Please refer to "TROUBLE SHOOTING CHART".
This covers common troubles and measures to be taken.
It must be noted that two or more of the following causes can take place at the same time.
In case of trouble, details of the trouble should be clarified and referred to pump maker Hyundai
Heavy Ind. Co., Ltd.
TROUBLE SHOOTING CHART
TROUBLE
CAUSE REMEDY
Speed too low Check power supply to motor for correct voltage.
Incorrect direction of rotation Switch motor leads.
Foreign material in impeller Dismantle pump and remove any foreign material.
Foreign material in suction line
Check suction pit and remove foreign material.
Insufficient capacity and/or pressure
Mechanical Defects -Impeller damaged -Sheared impeller key(s)
Dismantle pump and correct.
Electric circuit problem Check the electric circuit Pump is not starting
Motor problem Check the motor
Loose mounting or coupling bolts. Tighten bolts.
Broken or damaged coupling Inspect and replace.
Motor problem Check the motor
Pump vibrates
Misalignments Check alignment and correct. See paragraph 4.5
(29)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
26
Foreign material in impeller causing unbalance
Dismantle pump and remove any foreign material.
Mechanical Defects ; - Shaft bent. - Bearings worn.
Dismantle pump and replace parts causing vibration. See paragraph 4.1-(3)
Cavitation Check the pressure of suction and discharge. And check the difference pressure of strainer
Speed too high. Check power supply for correct frequency.
Over-tighten the gland packing
Check the gland packing and loose the gland bolt.
Motor overload
Pump bearings seize or Rotating element binds
Dismantle and replace parts causing seizure, or binding.
Cavitation Check water level and keep operation range.
Loose parts Tighten or replace defective part. Pump is noisy
Noise in driver Check motor with stethoscope.
2.3.2 WORN PARTS EXCHANGE
If wear of sliding parts exceeds the allowable value or nearly reaches the value, replace any worn
part with a new one. In this chapter, the detail procedures for exchange of the worn parts are shown.
1) Wire brush and clean all pump parts thoroughly. Examine the parts for wearing corrosion and
erosion.
2) Indicate each section of shaft on "V" blocks or rollers for run-out. Maximum allowable run-out on
pump shaft (1310A/B) is 0.05 mm TIR. Run-out should be measured with the rollers or V-blocks
located at the bearing journal areas.
3) Casing rings (1230A/B/C) are locked in position by headless setscrews. With the casing ring in
(30)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
27
place, a small hole is drilled so that half of the holes is in the ring and half is in the suction bell, bowl.
The hole is then tapped, and the pin is installed. The hole should be deep enough to permit the pin to
go beyond the top thread or two. The top threads are lightly stacked. Stacking is done by use of a
thin center punch and a lightweight hammer. The depth of the stake should not exceed the top thread
or two: as its intent is to prevent the pin from ever coming out of its own accord, but not to jam the
pin tight at very bottom of its hole.
To remove the setscrew, it will be necessary to insert a thin bladed screwdriver in the hole and
carefully remove the pin. Remove the setscrew and press the casing out of its fit. If pressing is not
easy to remove the ring, drill one or more holes in the face of the worn casing ring split apart. Install
the new ring by using a pieces of steel plate and mallet to tap the ring into position.
For installing new casing ring, drill and tap holes for headless setscrews spaced half the circular
distance from the used holes. Install the setscrews and stake. Check the dimension of casing ring
I.D. versus impeller wear area diameter plus ring clearance. Original running clearance must be
reestablished.
4) The bearings can be removed by the use of a cape chisel or hammering.
5) Check the shaft sleeves and renew if worn. To replace shaft sleeve which are fixed by snap ring
and key, remove snap ring from shaft and slide shaft sleeve from shaft.
6) Inspect suction cover (1150A/B), volute casing, volute discharge casing (1151,1152), discharge
bowl(1120A/B/C) and nozzles of discharge head for cracks.
7) Renew all gasket and rubber-rings during reassembly procedures.
(31)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
28
2.4 DECOMMISSIONING
Before storage pumps and motors, read carefully this manual and examine all related drawings until
they are fully understood. If you have any question, please contact HHI/EMD immediately.
2.4.1 CAUTIONS DURING TRANSPORTATION
Please observe the following items during marine and inland transportation.
2.4.1.1 Care Marks
The care marks are printed on the packages.
Please pay attention to these marks when you are handling the packages.
2.4.1.2 Pay attention to the following items when unloading and hoisting the packages.
1) Tie up the lifting wires securely so that the packages do not slip and become damaged.
2) Tie securely the lifting wires at the position for slings shown on the packages and adjust the wires
so that the load is balanced.
3) Do not raise and set down the packages too rapidly in order to avoid damage.
NOTE : The pump and motor shall be lifted by using 4-lifting lugs.
2.4.1.3 The package shall be fixed with bolts or a suitable manner to avoid damage due to shocks,
impacts and vibration during transportation.
2.4.2 CAUTIONS DURING RECEPTION AND STORAGE
2.4.2.1 Receiving checks
When the pumps are arrived at the site, carefully unpack and immediately check the followings.
(32)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
29
1) Packing contents and quantity of the delivered goods should be checked in accordance with
Packing List.
2) Check the nameplate and confirm that it is the ordered pump.
3) Check the shipping mark, care marks, packing condition and painting condition.
4) Check that the equipment is not damaged and the fixing bolts / nuts have not been loosened during
transportation.
2.4.2.2 Cautions during storage
When the equipment is stored during the period from its delivery to the start of installation
(including transportation), the following treatment is necessary to minimize damage of equipment
during long periods of storage.
The guarantee of the equipment will remain valid for the entire guarantee period only as long as the
equipment is stored faithfully according to the following storage instruction. However, replacement
of parts which become defective due to failure to follow these instructions will be made at some
charge.
1) All packages shall be stored as packed and shall not be unpacked unless a complete repacking
shall be conducted after unpacking.
2) Storage conditions
If possible, all crates and cases shall be stored in a warehouse with a floor. If all crates are not kept in
a warehouse, please store them outdoors according to 2.4.2.2.2) ④ “Storage method”. The maximum
period of storage for equipment in the crating is 6 months after arrival at the site.
If the period is over the above specified term, please consult with the supplier and originate a better
method of storing.
※ Note : During the storage, turn the pump rotor 1 and 1/4 revolution once a week.
(33)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
30
① Environment of storage place
a. Clean, low humidity, good ventilation and temperature lower than 50
b. No dust and no generation of corrosive or harmful gas
c. No damage by small animals and insects
d. Good drainage and few weeds in case of outdoor storage
e. Storage floor or ground shall be level horizontally.
② Storage of mechanical equipment
Many of the machines are furnished with finished painting.
These should not be exposed to direct sunshine and humidity.
Ferrous materials should be protected from humidity for the purpose of anti-corrosion.
③ Storage of electrical equipment
Keep indoors and strictly observe the environment of 2.4.2.2.2) ① above.
④ Storage method
a. For cases
Indoor storage is required.
b. For crates
Indoor storage is desirable. If indoor storage is not practicable and the storage period is more than 20
days, all surfaces of packages shall be covered by vinyl sheets to prevent entrance of water and direct
exposure to the sun.
3) Care marks
For packing which must be handled carefully during transportation and storage, care marks shall be
written where clearly visible on the outside of the packing.
4) A pallet or similar material shall be put under the package to prevent direct contact with the
ground.
5) A vinyl sheet covers each package from the top to the ground level.
6) Pay attention to the weight limitation for stacking of the packages.
(34)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
31
Sleepers shall be put between each case in order to make the weight distribution as even as possible.
7) Inspection and maintenance during storage
① Visual inspection of packages
Each package shall be checked for damage or distortion every three months, and it shall be repaired
if there is anything wrong.
② Inspection for equipment
Twelve months after shipment and every six months after that, each package shall be unpacked and
the exposed machined surfaces including screw threads must be inspected visually.
③ During the above stated operation (Items 1) & 2)), the equipment shall be handled carefully and
care taken not to cause deformation of the equipment or damage to the paint. When repacking, the
package shall have the same structure or manner as before, and all the necessary care marks shall be
printed on the package.
2.4.3 MOTOR MAINTENANCE WORK DURING RELATIVELY LONG STORAGE
PERIODS BEFORE FIRST OPERATION OR WHILE SHUTDOWN FOR SERVICING
If a machine has been out of service for more than three months, the following procedures should be
followed.
The intervals depend on the operating and site conditions.
The following works are recommended under normal conditions.
Table 1. Package Conditions
Machine with export packing. Without packing or machine with domestic packing. Package
Conditions Machine should be stored in a correct mounting position. Machine should be covered with suitable water-proof canvases.
Storage locations
Machine with packing should preferably not be stored in outdoors. where possible, motors should be stored indoors in a clean, dry area. If indoor storage is impossible for machine with packing, it is recommended that the storing it under a
Machine should not be stored in outdoors. Where possible, motors should be stored indoors in a clean, dry area. If indoor storage is impossible for totally-enclosed, outdoor application machine, it is recommended that
(35)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
32
weather-proof roof or alternatively cover it with canvases.
covering it with canvases.
Works for packing
1. In the case of condition before installation. (1) Stacking of heavy machine atop one another should be avoided. Machine should be stored in such in a way that no base frame will suffer distortion. (2) Attention should be paid to the loading capacity of floor. Care should be taken the floor, on which machine is stored, is not subjected to vibration and free from moisture.
(3) Storing of machine for longer than one year is not recommended. If the storing is continued, following procedures described in Table 2 should be done in year : Seal the silica-gel within packing and replace at regular intervals. 2. Fully seal the packing.
(3) The store room should be well ventilated and selected for possible protection against moisture and dirt. 2. Cover the air intake and discharge openings of open-enclosure machine by canvases to be prevent the dust deposits inside the machine. 3. If the other works are still in progress even after completed installation of machine, machine should be protected to ingress of foreign matters by a temporary protection covering.
Table 2. Maintenance work preparatory on machine parts
During long storage Prior to operation
External, unpainted metal surfaces.
Apply the following rust-preventive materials or equal: RUST VETO 244.342. (E.F. Houghton), P101 (Nippon Sekiyu), TECTYL 506 (Valvoline Oil).
Remove the rust-preventives with suitable solvents.
Bearings
Rotate the shaft slowly at least 10 revolutions by hand (*) or for several minutes by temporarily operate (**) the machine once every three months. Exception: In machine with export packing.
Check to see that shaft locking-provisions and temporary-covers have been removed, when provided. Check for irregular noise by shaft rotation by hand. If possible, check that bearings are free from rust.
Regreasable anti-friction bearings
Supply the following amount of grease to the bearing while rotating the shaft by hand. Regreasing amount is indicated on
Remove the old grease from the grease outlet opening before beginning operation. Supply new lubricant of the amount
(36)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
33
During long storage Prior to operation
the rating plate. Supply the grease once a year. Prior to grease supply, Open the grease outlet. Remove the original grease to avoid excessive filling the bearing cavity and to avoid grease leaks from shaft seals.
indicated on rating plate while rotating the shaft by hand or while the machine is running. Remove old grease by running the machine for a few hours with the grease outlet open.
Oil lubricated bearings
1. Check the reservoir filled with lubricant up to the proper line on the oil level gauge. 2. If a machine is out of service for more than one month, the following procedures should preferably be followed monthly : (1) Lubricate a machine with combined angular-contact ball (72 or 73 series) bearings by operating it for about 10 minutes. Lubricate a bearing of large output machine, provided with oil inlet plug on the top of oil reservoir, by pouring oil through the oil inlet. Then immediately rotate its shaft at least 10 revolutions by hand. After that, drain off excess oil. (2) For a machine with a spherical-roller thrust (293 or 294 series) bearings. A machine should be run for about 10 minutes or the shaft rotated at least 10 revolutions by hand. (3) In a machine with sleeve bearings, a machine should be run for about 10 minutes or the shaft rotated at least 10 revolutions by hand. When rotate the shaft, supply about 50 to 100cm3 of the lubricating oil through the screw plug (or sight-glass) of bearing housing. 3. Replace with new oil once per year.
1. Open the drain plug and remove the original oil. Fill the reservoir with the new lubricant up to the proper line on the oil level gauge. 2. In the forced-feed, oil-lubricated bearing. (1) Clean the inside of the oil piping and refresh them, when required. (2) Fill the bearings connected to a feed-oil system with specified oil, check the system for satisfactory operation.
(37)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
34
During long storage Prior to operation
Insulated windings
Insulation resistance between winding and earth be measured every six months (Every one year in machine with export and before the machine is started). If the lower insulation resistance values is measured, open the terminal-box cover and, if the value does not increase, winding should be dried. Where surge protection system is provided in main terminal box, these accessories should be electrically disconnected during measuring for insulation resistance of winding.
Anti-condensation heater, when provided.
Heater should be energized, in machine without packing, when power-supply cables and heater leads are connected. To prevent moisture accumulation, some form of heating must be utilized to prevent condensation. This heating should maintain the winding temperature at a minimum of 5 above ambient.
Heater should be disconnected before machine is started up.
Drain water by opening the drain plug in the enclosure. Water drain plug, when provided.
At regular intervals of not longer than six months. One year in machine with export packing.
-
Openings Any unused cable entry into terminal box(s) should be closed.
Remove the temporary protection covers, when provided
Painted external surfaces
Repaint at regular intervals, when necessary.
(38)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
35
2.5 PACKING, TRASPORT AND DISPOSAL
2.5.1 GENERAL
2.5.1.1 Purpose of Packing
The purpose of packing is to safeguard materials during transport, handling and storage against
mechanical damage and environmental encroachment such as rain, humidity, temperature variations,
frost, salt atmospheres, dust, sand, etc.
2.5.1.2 Detail of Nozzle Plugging for Transport Overseas
2.5.1.3 Markings
Each package must be marked at least 3 sides in indelible paint, resistant to weather effects and light.
(One for the top side, the others for on side surfaces)
To avoid the plates becoming detached, the nails can be bent over before the case is closed.
Galvanized steel nails and wires must be used for fastening the plates.
Care must be taken not to damage any sealed bags etc. that may have been used.
The following international standard symbols shall be used:
(39)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
36
1.
2.
3.
4.
5.
6.
7.
A.
B.
Symbols Description Remarks
THIS WAY UP All Top Corners
FRAGILE HANDLE WITH CARE All Top Corners
KEEP DRY All Top Corners
KEEP AWAY FROM HEAT All Top Corners
USE NO HOOKS All Top Corners
CENTER OF GRAVITY All Sides
SLING HERE All Top Corners
STORAGE RECOMMENDATIONS Storage in heated/ventilated warehouse and with precautions (air conditioned)
All Top Corners
STORAGE RECOMMENDATIONS Storage in closed warehouse All Top Corners
(40)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
37
C.
D.
Symbols Description Remarks
STORAGE RECOMMENDATIONS Storage in open shed All Top Corners
STORAGE RECOMMENDATIONS Storage in open air (covered by tarpaulins)
All Top Corners
2.5.2 DETAIL PACKING INSTRUCTION
1) The type of packing should be a wooden case for overseas shipment and land transportation.
Equipments should be enclosed in a protective bag with containing a protective lining moisture
absorptive agent.
2) Equipments should be inspected for cleanness immediately before packing. Dirt, oil residue, metal
chips, or other forms of contamination should be removed by suitable cleaning methods. Any
entrapped water must be removed.
3) Equipments should be completely drained and thoroughly dried prior to shipment.
4) All openings and machined surface should be provided with protection to prevent damage,
corrosion and entrance of foreign matter during shipment. Exposed connections must be cleaned and
coated with a preservative.
5) All flanged openings should be provided with substantial plywood (or plastic) covers and rubber
gaskets (minimum thickness 5mm) bolted with to the connections. At least four bolts shall be used.
6) Threaded or socket weld connections should be protected by metal capping or plugging. All
tapped openings normally plugged during service should be fitted with solid steel plugs.
7) Equipments which can be damaged by condensation trapped within the package should be
packaged with desiccant inside the sealed water-vapor proof barrier or an equivalent method.
8) Equipments should be packaged with a waterproof enclosure so that water, salt spray, dust, dirt,
and other forms of contamination do not penetrate to the equipment.
9) The base of the equipment should be firmly secured to the bottom of the case by means of nuts
and bolts and battens.
10) Any moving parts should be firmly secured on the equipment so that they cannot move.
11) Unless otherwise stipulated, drive motors should normally be dispatched with their own
separated case because of heavy weight.
(41)
(42)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
38
2.6 COMPONENT DOCUMENTATION
- SECTION 1 : MOTOR
- SECTION 2 : MECHANICAL SEAL
- SECTION 3 : GEAR COUPLING
(43)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
i
SECTION 1. MOTOR
(44)
The information contained in this book is intended toassist operating personnel by providing information onthe general characteristics of the purchased equipment.IT DOES NOT relieve the user of the responsibility of usingaccepted engineering practices in the installation,operation and maintenance of this equipment.
(45)
2 << INSTRUCTIONS FOR THREE-PHASE INDUCTION MOTORS
This equipment contains hazardous voltages. Death,
serious personal injury or property damage can result if
safety instructions are not followed.
The successful and safe operation of motors is dependent
upon proper handling, installation, operation and
maintenance, as well as upon proper design and
manufacture. Failure to follow certain fundamental
installation and maintenance requirements may lead to
personal injury and the failure or loss of the motor as well
as damage to other property.
Only qualified personnel should work on or around this
equipment after becoming thoroughly familiar with all
warnings, safety notices and maintenance procedures
contained herein. Only qualified personnel should be
involved in inspection, maintenance and repair
procedures and all plant safety procedures must be
observed.
Qualified Person: For the purpose of this manual and
product labels, a Qualified Person is one who is familiar
with the installation, construction and operation of the
equipment, and the hazards involved. In addition, he or
she:
a. is trained and authorized to energize, de-energize,
clear, ground and tag circuits and equipment in
accordance with established safety procedures.
b. is trained in the proper care and use of protective
equipment, such as rubber gloves, hard hat, safety
glasses, face shields, flash clothing, etc., in accordance
with established safety procedures.
c. is trained in rendering first aid.
Motors should be installed and grounded per local and
national codes.
Do not operate this equipment in excess of the values
given on nameplate or contrary to the instructions
contained in this manual. The equipment (or a prototype)
has been factory tested and found satisfactory for the
conditions on which it was sold. Operation in excess of
these conditions can cause stresses and strains beyond
design limitations. Failure to heed this warning may
result in equipment damage and possible personal
injury.
Safety Procedures
Hazardous voltage.Will cause death, serious injury,electrocution or property damage.Disconnect all power before working onthis equipment.
For the purpose of this manual andproduct labels, Danger indicates animminently hazardous situation which,if not avoided, will result in death orserious injury.
For the purpose of this manual andproduct label, Warning indicates apotentially hazardous situation which,if not avoided, could result in death orserious injury.
For the purpose of this manual andproduct label, Caution indicates apotentially hazardous situation which,if not avoided, may result in propertydamage or minor or moderate injury. Itis also used to alert against unsafepractices.
NOTE: Many squirrel cage induction machines are drivenby various types of prime movers as induction generators.This instruction manual applies to both motors andinduction generators. However, for reasons of clarification,the machine will be referred to as a "motor."
(46)
Safety Procedures 2
1. Foreword 4
2. Receiving, Handling and Storage 5
2.1 Receiving 5
2.2 Handling 5
2.3 Storage 5
3. Inspection and Test for Initial Start-up on Site 7
3.1 Installation 8
3.2 Inspection of Installation 9
3.3 Measurement of Insulation Resistance 9
3.4 Inspection of Lubrication Oil 10
3.5 Manual Rotation 10
3.6 Connection to Power and Grounding 10
3.7 Solo Run Test 10
3.8 Alignment 11
3.9 Test Run of Motor 13
4. Inspection and Maintenance Schedule 14
5. Maintenance of Windings 17
5.1 General 17
5.2 Cleaning of Coils 17
5.3 Use of Space Heaters 18
5.4 Drying Insulation 18
6. Maintenance of Slip Rings, Brushes and
Brush Holders 20
6.1 Slip Rings 20
6.2 Brushes and Brush Holders 21
7. Terminal Box for High-voltage Supply 22
7.1 General 22
7.2 Description 22
7.3 Installation 22
7.4 Operation 23
7.5 Maintenance 23
8. Terminal Box for Auxiliary Circuits 24
8.1 General 24
8.2 Description 24
8.3 Installation 24
9. Anti-condensation Heating with Heating Tube 25
9.1 Description 25
9.2 Installation 26
9.3 Maintenance 26
10. Maintenance of Bearings 27
10.1 Flange-type Sleeve Bearings 27
(Ring Lubrication System)
10.2 Flange-type Sleeve Bearings 29
(Forced Lubrication System)
10.3 Rolling-contact Bearings 31
10.4 Insulation to Prevent Shaft Current 32
(High-voltage and Large Machines)
11. Air Filter and Cooler 35
11.1 Air Filter 35
11.2 Cooler 35
12. Protection 37
13. Induction Motor Troubleshooting 38
14. Appendix 43
14.1 HLA7 Horizontal-type Motor Construction 43
14.2 HLS7 Horizontal-type Motor Construction 44
14.3 HRA7 Horizontal-type Motor Construction 45
14.4 HRP7(4P~) Horizontal-type Motor Construction 46
14.5 HRP7(2P) Horizontal-type Motor Construction 47
14.6 HRQ7 Horizontal-type Motor Construction 48
14.7 HRP7(2P) Horizontal-type Motor Construction 49
14.8 HRS7 Horizontal-type Motor Construction 50
14.9 HLB5 Horizontal-type Motor Construction 51
14.10 HRQ7 Horizontal-type Motor Construction 52
14.11 HRQ7(Sleeve Bearing) Horizontal-type Motor
Construction 53
15. Memo 54
Instruction Manual >> 3
THREE-PHASE INDUCTION MOTORS
Contents
(47)
01
4 << INSTRUCTIONS FOR THREE-PHASE INDUCTION MOTORS
This instruction manual describes and provides instructions for
installation, operation and maintenance of induction motors.
These instructions do not purport to cover all details or
variations in equipment nor to provide for every possible
contingency to be met in connection with installation,
operation or maintenance. Should further information be
desired or should particular problems arise which are not
covered sufficiently, the matter should be referred to the
nearest HYUNDAI HEAVY INDUSTRIES business office.
Foreword
NOTE
For service shop requirements, refer to
ROTATING MACHINERY MANUFACTURE DEPT.
ELECTRO & ELECTRIC SYSTEMS DIVISION
HYUNDAI HEAVY INDUSTRIES CO., LTD.
Address: 1 JEONHA-DONG, DONG-GU, ULSAN, KOREA
Telephone: 82-52-230-6671, 6672
Fax: 82-52-230-6996
(48)
2.1 Receiving
Each shipment should be carefully examined upon arrival.
If the packing is damaged, unpacking should be made
immediately to check whether or not the motor and its
fitting are in good condition, and any damage to contents
should be photographed and reported to the carrier and
to the nearest HYUNDAI HEAVY INDUSTRIES business
office.
All large motors are equipped with a locking device, which
protects the bearing from damage due to the movement
of the rotor in transit. Do not remove this device until
transport is complete and coupling is ready to be fitted.
2.2 Handling
To ensure proper handling after unpacking, the motors
require the chain hoist, wire ropes and other handling
equipment. When hoisting the motor, wire ropes should
be attached to the lifting holes on the side of the motor
frame, and should be put in hard rubber, thick cloth, etc.
between the external covers for protective purposes.
Then the motor is slowly and carefully raised and moved
to the intended position.
2.3 Storage
If the motors are not put into service at the time of
delivery, they should be stored according to the following
conditions.
Outdoor Storage Is Not Recommended.
Variations in temperature and humidity can cause
condensation, resulting in corrosion of metal parts and
possibly in insulation failure. Therefore, the following
cover the minimum acceptable storage arrangements in
an unheated but protected environment:
It is preferable to use a heated facility, which would
simplify meeting these conditions.
When outdoor storage cannot be avoided, contact
HHI for specific instructions on minimizing damage, giving
full particulars of the circumstance.
Storage Facility Requirements
The storage facility must provide protection from contact
with rain, hail, snow, blowing sand or dirt, accumulations
of groundwater, corrosive fumes and infestation by
vermin or insects.
There should be no continuous or severe intermittent
floor vibration. Power for the space heaters and
illumination should be available. There should be fire
detection and a fire-fighting plan. The motors must not be
stored where it is liable to be accidentally damaged or
exposed to weld spatter, exhaust fumes or dirt and stones
kicked up by passing vehicles.
If necessary, use guards or separating walls to provide
adequate protection. Avoid storage in an atmosphere
containing corrosive gases, particularly chlorine, sulfur
dioxide and nitrous oxides.
Instruction Manual >> 5
THREE-PHASE INDUCTION MOTORS02 Receiving, Handling and Storage
Heavy EquipmentImproper lifting can cause death, severeinjury, or damage. Check eyebolts,lifting lug and eyenuts before lifting. Useproper slings and spreaders.
Damp Location.Can cause property damage ifequipment is operated intermittently.Use space heaters to prevent dampness.Grease machine fits when unit isreassembled to prevent corrosion.
When unpacking and handling themotor, attention should be given to thefollowing points: - Anticorrosive agent which is applied to
the coupling shaft ends should beremoved right before starting themotor. The coupling or shaft endsshould be checked to ascertainwhether or not they are in abnormalcondition.
Top Heavy.Can cause severe injury or propertydamage.When lifting motor,1. Lift only at designated locations.2. Use spreader for lifting.3. Apply tension gradually to cables.4. Do not jerk or attempt to move unit
suddenly.5. Do not use cover lugs when lifting.
(49)
02
6 << INSTRUCTIONS FOR THREE-PHASE INDUCTION MOTORS
Temperature Control.
Whenever the motor temperature is equal to and below
room temperature, water vapor can condense on and
within it, promoting rapid deterioration.
Prevent this by energizing the space heaters to keep the
motor temperature above room temperature by at least
3 However, during periods of extreme cold or rapid
temperature drops, the space heaters may not be
adequate to maintain this differential and supplementary
heating may be required.
Receiving, Handling and Storage
Fig. 1 Insulation Resistance Temperature Correction
Hazardous Voltage.Will cause death, serious injury,electrocution or property damage.Disconnect all power before working onthis equipment.
If the motor is boxed or covered in anyway when the space heaters areenergized, there should be thermostaticcontrol and sufficient surveillance todetect an over-temperature conditionquickly. Ensure that temporary packagingdoes not contact the space heaters. When windings of motor are uninjuredand their insulation resistance to groundis well above the minimum of ratedvoltage (kV) plus 1 megohm whencorrected to 40 according to IEEE 43 oras below in Fig. 1, low temperature is nota problem. However, if the resistance drops, thewindings can be permanently damagedby freezing. Therefore, the motortemperature should be kept abovefreezing point.
(50)
Generally, inspection and text of motors are performed as
in the following chart for initial start-up on site.
Instruction Manual >> 7
THREE-PHASE INDUCTION MOTORS03 Inspection and Test for Initial Start-up on Site
Inspection of installation
Confirmation of starting panel
Load running test
Inching operation
Solo running test
Measurement of insulation resistance
Inspection of connection cables
High-voltage test with outgoing cables(If necessary)
Inspection of lub. oil
Hand turning (If possible)
Inching operation
Connection withoutgoing cables
Connection withoutgoing cables
END
(51)
03
8 << INSTRUCTIONS FOR THREE-PHASE INDUCTION MOTORS
3.1 Installation
General
Ensure that the motor enclosure is suitable for its
environment, that the ambient temperature is less than
specifications for operating the motor at all times and that
all bearings are lubricated before operating the motor.
Foundation
Motors should be mounted on solid and rigid foundations
to ensure proper vibration and free operation. The
desirable foundation and anchor bolt design will
--- accommodate at least the maximum static and dynamic
foundation loads indicated on the motor outline
dimension drawings.
--- have sufficient rigidity to maintain acceptable alignment
after the application of load.
--- be free of natural frequencies, which are likely to be
excited during normal operation (this could result in
vibration problems on the motor).
In some cases where precision is required, a study of
these factors should be conducted to determine the
natural frequencies of the motor support.
Foundation Bolt
There are some different methods of installing the
foundation bolt as shown in Fig. 2. The methods depend
on the capacity and construction of the motor.
Mounting
After removing the packaging from the skidding of the
motor, remove the polyethylene shroud. Remove the
motor from the skidding. The motors should be mounted
on a flat surface and packed about with shims (shim
allowance is generally 2-3 mm thick).
The shims should support the maximum length of each
motor foot. It is preferable to use corrosion-resistant
shims such as brass or stainless steel; otherwise “shim
swell“ due to corrosion resistance may be detrimental to
good alignment. Care should be taken not to distort the
frame during “bolting down”.
Remove the Locking Device of Large Motors
All large motors are equipped with a device for preventing
the shaft from movement in order to protect the rolling
face of bearing from damages due to vibration in transit.
This locking device is fitted on the drive side or on the
non-drive side. Before connecting a motor to a machine,
the fitting bolts should be loosened, and the fitting device
should be taken off.
Inspection and Test for Initial Start-up on Site
NOTE: If normal vibration or noise will be objectionable (asin office buildings), it may be advisable to use vibrationdampeners between the machine or driven/drive unit andthe foundation.
Fig. 2 Type of Foundation Bolt
Fig. 2 Type of Foundation Bolt
NOTE: Experience has shown that any base-mountedassemblies of motor and driven units temporarily aligned atthe factory, no matter how rugged or deep, may twistduring shipment. Therefore, alignment must be checkedafter mounting.
A basic rule is to not have more than 5shims in a shim pack under any onemachine foot. Thick shim packsconsisting of many thin shims will causea soft foot and cause vibration or twistedframe (machine foot out of plane).
< J-Type >
< Plate-Type >
(52)
Instruction Manual >> 9
THREE-PHASE INDUCTION MOTORS
Hazardous voltage.Will cause death, serious injury,electrocution or property damage.Disconnect all power before working onthis equipment.
3.2 Inspection of InstallationAfter installation, check for looseness of bolts and nuts on
the terminal boxes, cooler boxes and so on. Then, the
foundation and centering of the motors should be
checked. These items are normally checked and reviewed
on the erection records.
Checklist for inspection of installation
3.3 Measurement of Insulation Resistance
3.3.1 One-Minute Test
If the motors were stored in very damp surroundings for a
prolonged period, the insulation resistance of windings to
frame should be measured at DC power for 1 minute with
a low energy source device (for example, megger).
In case a high-voltage circuit, that is 600 V and above, is
measured by a 1000-V megger, and low-voltage circuit,
less than 600 V, is measured by a 500-V megger.
Insulation resistance of winding for the high voltage motor
will be converted to 40°C-based values by IEEE 43.
The criteria of its value are (kV + 1) megaohm at 40°C for
winding, and 1 megaohm for space heater in accordance
with international standards ( IEEE 43, JEC 37, etc.). If the
insulation resistance has been reduced as a result of
extreme conditions (for example, penetration of water)
and has a value less than the criteria value, the windings
must be dried before connection to supply voltage and
operation.
3.3.2 Polarization Index.
In case the high-voltage circuit, that is 600 V and above,
provided for insulation resistance is within the acceptable
limits, then a polarization index can be performed.
Windings are applied to DC power in accordance with IEEE
43 between windings and ground when the stator coil is
tested. The rotor coil and R.T.D leads are to be earthed.
The insulation resistance at one (1) minute should be
recorded and the insulation resistance at ten (10) minutes
should be recorded.
The polarization index is the insulation resistance index at
10 minutes divided by the insulation resistance index at 1
minute. This index should be greater than 1.
If the polarization index is less than 1, contact HHI’s
service center. The windings may need to be dried before
operation.
3.3.3 High Voltage Test
1. Outside view of machine- No rusted portions.- No damaged portions/parts.- Confirmation of caution, nameplate.
2. Removal of rotor locking device(If necessary)
3. Check for no looseness- End covers.- Terminal boxes.- Cooler boxes.
4. Check around foundation- Motor leveling.- Tightness of foundation bolts.
5. Inspection of accessories- Thermometers
(indication checks at amb. temp.).- Temperature detectors
(indication checks at amb. temp.).
6. Confirmation of centering Do not operate equipment beyonddesign limitations.Can cause personal injury or damage toequipment.Operate in accordance with instructionsin the manual and nameplate ratings.
(53)
03
10 << INSTRUCTIONS FOR THREE-PHASE INDUCTION MOTORS
This test is intended for detecting the weak points of
winding for high-voltage machines. The dielectric test is
carried out before operating the motor, on windings
applied to specified voltage for one (1) minute between
the windings and ground.
Supply voltage: 2E+1000 for the line for
above 1000 V
E means rated voltage or secondary induction voltage in
case of the wound rotor; AC power condition.
If AC power is not supplied, apply DC power instead of the
power frequency voltage specified above. The DC voltage
level is at least 1.7 times of AC high-voltage test voltage.
3.4 Inspection of Lubrication Oil
Before the initial running test, inspection of lubrication oil
is very important, that is, confirmation of no oil leakage
and proper oil level.
Refer to bearing maintenance manual.
3.5 Manual Rotation
If possible, rotate the rotor manually to ensure that it is
free to move without rubbing or scraping and to lubricate
the bearing surfaces. A minimum of 10 revolutions is
recommended.
3.6 Connection to Power and Grounding
Examine the nameplate data to know the correct power
supply. Also check heater power where applicable. Check
all connections to ensure that they have not come loose
during transport. Make certain that the correct cable size
has been selected and connected to phase rotation as
shown in motor terminal box. The motor and control
wiring, overload protection and grounding should be done
in accordance with the National Electrical Code and local
requirements.
In case of the wound rotor, check to see that brushes are
“free“ in the holder and the pressure of the brushes is
applied correctly. Ensure that the slip ring surface is clean
and free from contamination. Avoid “fingerprint” marks on
ring surface. To maintain the proper degree of protection,
make sure all gaskets and cover plates are properly fixed
and sealed. Any unused entry holes should be plugged.
3.7 Solo Run Test
Before coupling with the load machine, the motor is
normally run through a solo running test.
At the initial start, the motor is inching operated for
approx. 1-2 sec.
At that time, inspection of rotation, abnormal noises, and
lubrication conditions are checked during the idling. If
these items have any problems, the supplied power shall
be taken off, checked and reported in detail.
The motor is then restarted. The motor is run during 1-2
hrs. and vibration amplitude on the bearing housing and
bearing temperature are measured and recorded.
Inspection and Test for Initial Start-up on Site
Before starting the machine, fill thebearing chamber to the center of the oilgauge. Always fill through the pipe orplug at the side of the motor. Do notoverfill, as the oil may then escape alongthe shaft and enter the unit.Avoid adding oil while unit is running.
Do not exceed number of HYUNDAI-specified hot and cold starts perhour.Will cause overheating.Allow time between starts to permitstator windings and rotor cage to cool.
Observe caution in testing as follows- In case of the wound rotor type, the
slip ring and brush support part of themotor are to be thoroughly cleaned;and dust and moisture are to becompletely removed before the highvoltage test is started.
- When the stator coil is tested, the rotorcoil and RTD leads are to be earthed.
- Electricity is to be discharged withoutfail after the high-voltage test has beenfinished.
- Ensure that the motor starter (suppliedby others) is open.
- Make the connections as in therequired rotation.
- Drill the cable entry plate (at bottom ofbox) to suit your power cable and itsfitting.
- Connect the station ground to one ofthe ground pads provided on thestator frame.
(54)
3.8 Alignment
The correct alignment of machinery is very important for
reducing the stress and vibration of the shaft and the
wear of the bearing and coupling. In case a coupling
maker gives those instructions, it is recommended that
the instructions be followed.
Flexible Coupling
The flexible coupling set forth herein means the one
driven through the rubber brush or the leather brush
including the gear coupling. In aligning the motor
equipped with the sleeve bearing, attention is to be paid
to the endplay of the motor bearing and to the position of
the coupling. The center of the motor bearing endplay is
indicated by the endplay indicator.
The bearing endplay can be equally divided by
setting the endplay indicator to the standard line of the
shaft as shown in Fig. 3.
Rigid Coupling
In case of the sleeve bearing, when both flanges are
connected to each other, the endplay indicator is referred
to install the flexible coupling in order to determine the
position of the motor.
Alignment
Alignment is made to bring the shaft centers of the motor
and machine combined with it into the same line; the
parallel and eccentricity are measured through the
coupling. Generally a thickness gauge or a taper gauge is
used in measuring the parallel, and in measuring the
eccentricity, a dial gauge is to be fitted to the coupling on
one side; the both shafts are to be turned by 0 deg, 90 deg,
180 deg and 270 deg; and the dial gauge reading is to be
taken at the four points as shown in Fig. 4. The alignment
accuracy is to be generally 0.025 mm or less (both plate
and circle).
Measurement of Eccentricity
The both shafts are to be simultaneously turned; the
values shall be obtained from the measurement made at
four points by means of a dial gauge and are to be
recorded; and the corrected value is to be obtained in the
following manners.
Instruction Manual >> 11
THREE-PHASE INDUCTION MOTORS
Do not operate equipment beyonddesign limitations.Can cause personal injury or damage toequipment.Operate in accordance with instructionsin the manual and nameplate ratings.
NOTE: The foot plane is of concern for each unit of rotatingequipment. Check driven equipment if necessary.
Fig. 3 Endplay Indicator
Fig. 4 Procedure for Alignment
(Measured Value)
Circle
270 deg
90 deg
180 deg 0 deg
In case the coupling is used, it may beconsidered that the rotor can be easilymoved in the axial direction. In fact,however, it hardly slides in the axialdirection at the coupling as the torquegrows greater. When by some reasonthe rotor has undergone some axialmovement, and the coupling does notprovide enough slip to allow the rotor toreturn to the magnetic center of themotor, it will continue to operate withthe bearing end in contact with theshoulder of the journal.
(55)
03
12 << INSTRUCTIONS FOR THREE-PHASE INDUCTION MOTORS
Measurement of parallelism
The values at the four points of E1, F1, G1 and H1 are to
be corrected after measurement made by means of a
thickness gauge at the position where both shafts were
connected to each other at the time of eccentricity
measurement; and measurements are to be made again
at the points of E2,F2, G2 and H2 after turning both shafts.
Belt Connection
If it is intended that the motor will be directly coupled
through a flexible coupling to a machine, no check for the
minimum sprocket diameter will be necessary. However,
if a chain, gear, V-belt, or flat belt drive is used on the
output shaft a check should be made.
Direction of Belt Tension
In the case of the motor with roller bearing, belt tension
may be applied in the horizontal or the vertical direction.
In case of the motor with the sleeve bearing, the belt
tension should be applied in the horizontal direction only.
Alignment of Belted Drives
Aligning a belted drive is much simpler than aligning a
direct coupling drive. To check alignment, place a straight
edge across the faces of the drive and driven sheaves. If
properly aligned, the straight edge will contact both
sheave faces squarely.
Inspection and Test for Initial Start-up on Site
(Measured Value)
(Corrected Value)
Circle
D
A
C A
(Measured Value)
Circle
H2
F2
G2 E2
(Measured Value)
Circle
H1
F1
G1 E1
Corrected value of left and right = A - C
2
Corrected value of left and right = A - C
2
(Corrected Value)
Corrected value of left and right
= ( F1 + F2 ) - ( H1 + H2 )
2
Corrected value of left and right
= ( E1 + E2 ) - ( G1 + G2 )
2
The difference between the total of themeasured values at the left and rightpoints (A-C) and the total of themeasured values at the top and bottompoints (B- D) should not exceed 0.03 mm.The improper fitting of the dial gauge andthe erection of the fitting arm, if any, maycause greater difference.
(56)
Belt Tension
The V-belt is to be stretched in the following way.
There is calculated deflection force to be applied
perpendicular to the belt at the center of the belt span as
shown in Fig. 6.
The drive is properly tensioned when the deflection of the
belt caused by the deflection force is equal to 1.6 mm for
span length of 100 mm. If the deflection force is higher
than normal values, this will result in reduced belt life,
reduced bearing life and could cause shaft failure.
Coupling Balance
The coupling should be dynamically balanced to G2.5 or
better. The motor is dynamically balanced with a half key
fitted; therefore, the proposed coupling should be
balanced accordingly, and the correct key profile fitted.
Frame Distortion Test
In addition to ensure the proper alignment of the coupling,
care should be taken to ensure that the motor frame is
not distorted during alignment.
To confirm that distortion has not occurred, we
recommend the following procedure be adopted:
1) Align the motor within tolerances as required by
section “alignment.”
2) Apply a dial gauge between the motor frame adjacent
to one mounting foot and the foundation and set
indicator to zero.
3) Loosen hold down bolt and record movement of dial
gauge measurement.
4) Re-torque hold down bolt.
5) Repeat steps 1- 4 for all hold down bolts, one at a time.
3.9 Test Run of Motor
After coupling with the load machine, the motor is inching
operated at first.
When both motor and load machine show no abnormality,
the motor is restarted with a minimum load. At that time,
the current, supplied voltage is checked and recorded.
While the motor is running continuously, the motor
vibrations on the bearing housing are controlled by the
curve of Fig. 8.
Instruction Manual >> 13
THREE-PHASE INDUCTION MOTORS
Fig. 5 Alignment of Belt Drive
Fig. 6 Belt Tension
Fig. 7 Coupling Balance
Do not exceed number of HYUNDAI-specified hot and cold starts per hour.Will cause overheating.Allow time between starts to permitstator windings and rotor cage to cool.
Carry out the initial operation inaccordance with contractual agreements.The initial operation may only be carriedout by trained personnel who have beenassigned to do this by the personresponsible for the plant.
(57)
04
14 << INSTRUCTIONS FOR THREE-PHASE INDUCTION MOTORS
The following maintenance and inspection schedules
cover the necessary steps for inspection of the motors.
Since the conditions under which the motors are required
to operate may differ considerably, the maintenance and
inspection schedules can only be recommended for the
intervals at which at least first inspection should be
carried out if operating conditions are normal. On the
basis of the experience gained with the plant, the
inspection intervals should therefore be selected to meet
such conditions as contamination, frequency of start-ups,
load, etc.
Inspection and Maintenance Schedule
A: Daily Inspection
B: First Inspection, no later than 6 months.
C: Following Inspection, no later than two (2) years (when required, dismantle the machine).
Relubricate the grease lub. Bearing
oil-lub bearing: Change the oil.
Clean and inspect the bearings.
For the intervals of maintenance work, see the lubrication instruction plate on
the machine.
Carry out the following oil changes with normal amb. temp.
Self oil lub.: 5000-8000 operating hours
Forced feed oil lub.: 15,000-20,000 operating hours
Check the machine for irregular noise and excessive vibration (Fig. 8).
Where possible, measure and record the bearing temperature.
Check the shaft sealing rubber ring for deterioration.
Where possible, measure the bearing temperature, oil pressure and flow rate.
Check that the oil-rings are operating correctly.
Check the oil flow, oil level and any oil leaks.
Check the contamination of lub. oil and change the lub. oil.
Check the axial play.
Check the shaft sealing for deterioration.
Inspect the bearing surface.
Clean and inspect the bearing insulation and insulation of the pipe.
Check the system, connections and piping for leaks.
Check the oil level.
Clean and inspect the oil filters and oil coolers.
Check to see that the enclosure is not clogging (blocking) the machine ventilation.
Check the gaskets for deterioration.
Check the enclosure for any deformities or damage.
Check the noise-suppression material for damage.
Machine part
Sleeve (white metal)
bearing
Forced feed oil
lub. system
Enclosure
Interval
A B CInspection and maintenance work
(58)
Instruction Manual >> 15
THREE-PHASE INDUCTION MOTORS
Check the enclosure including external cabling conduit connection for ingress
of water or dust.
For the wound rotor machine with continuous sliding brushes and open
enclosure machine, clean the entire winding and cooling air paths, including
the core packs-air duct.
For the open enclosed machine:
Clean entire winding and cooling air paths including the core packs-air duct.
Check end rings and support rings and the associated locking elements for
tight fit.
Check and clean the external cooling air paths.
Drain the drain plug, when provided.
Replace and clean the air filter, when provided.
Check the clearances to rotating parts.
Check the enclosure for corrosion.
Check earthing (grounding) terminals.
With loose leads: Check to see that the cable connections are properly insulated.
Check connection for good contact.
Check terminal insulators for damage.
Measure and record the winding temperature detectors, when provided.
Check and record the insulation resistance of windings.
Clean the windings, as far as possible.
For totally enclosed machines, clean the winding if required.
Check the slot wedge for tight fit.
Check condition of winding insulation, including end connections.
Check winding and bracing for tightness.
Clean the winding, as far as possible.
For totally enclosed machine, clean entire winding if required.
Check cage bars and end rings for fractures and loosely soldered connection.
Check cage for axial displacement.
Check and record the insulation resistance of windings.
Clean the winding, as far as possible.
For totally enclosed machines, clean the winding if required.
Machine part
Stator winding
Squirrel-cage rotor
Wound rotor winding
Enclosure
Junction (terminal) box,
terminals
Interval
A B CInspection and maintenance work
(59)
04
16 << INSTRUCTIONS FOR THREE-PHASE INDUCTION MOTORS
Inspection and Maintenance Schedule
For the machine with continuous sliding
brushes or open enclosure machines,
clean entire winding and cooling air paths including the core packs-air duct.
Check leads of stator winding, slip ring leads of wound rotor machine and
their locking elements for tightness.
Compare brush noise, sparking and contact marking with conditions found in
previous inspection (monthly).
Inspect contact surfaces; they should be bright, free from rubbing or
threading and have a uniform skin.
Remove deposits of carbon dust from the slip ring chamber, slip ring and
brush holders.
Check to see that the mechanism, including the sliding surface of the shaft to
the short-circuit ring, is free form dust.
Check the slot wedge for tight fits.
Check the winding-end for deposits of oil and carbon dust.
Check the banding for tightness, and check for any loosely soldered joints.
Check bracings and wedges of winding end and ring circuits for tightness.
Vent the cooler while in operation (monthly).
Where possible, measure and record the water temperature.
Check the cooler, connection and piping for leaks.
Check and clean the cooler.
Inspect the corrosion protection (when provided).
Check the brush length and replace as necessary.
Check to see that the brushes can move freely in the brush holders.
Check the pigtail (connection) leads for discoloration and damage.
Take out and clean the air filter.
Check the holder for damage.
Check the tightness of slip ring, including separators and fixing studs.
For arm type brush holder, check brushes for screw tightness.
Avoid continuously sliding the brushes.
Avoid continuously rotating the thrust roller.
Check the abnormality of thrust roller and limit switch.
Check the sliding surface of short-circuit ring for corrosion.
Check setting of short-circuit ring to shaft.
For arm type brush holders, check brushes for screw tightness.
Re-lub. the reduction gear assembly.
Check the manually operated gear unit for damage.
Machine part
Slip ring, brushes
Slip ring, brushes
(cont’d)
Brush lifting mechanism
Enclosure
Water air cooler
(heat exchanger)
Interval
A B CInspection and maintenance work
(60)
Instruction Manual >> 17
THREE-PHASE INDUCTION MOTORS
3600
1800
1200
900
720
600
60
30
20
15
12
10
0.15(3.8)
0.15(3.8)
0.15(3.8)
0.12(3.0)
0.09(2.3)
0.08(2.0)
Axial rotor placement should be kept by indication of the shaft on its
magnetic center.
Check and adjust the belt tension.
Check the external and internal fan for damage or corrosion.
Check rotor alignment.
Check the balancing weight for tightness.
Check all coupling bolts and locking elements for tightness.
Check the oil leakage of gear coupling.
Check the shaft keys for tightness.
Check the monitoring instruments and contact device for proper function.
Check the brush length and replace as necessary.
Check the holder for damage.
Machine part
Monitoring instruments
Ground brush
Shaft and coupling
Interval
A B CInspection and maintenance work
5.1 General
It is important to keep the machines in good condition by
performing periodical maintenance to prevent the
insulation from being damaged by moisture, dirt and other
foreign matter.
If the machines have been operated under high humidity
conditions, not been used for a long time, or been
subjected to sudden changes in ambient temperature, the
insulation may have absorbed considerable moisture,
causing deterioration of the insulation.
Other causes of insulation breakdown include operation of
the machines at an overcurrent exceeding the rated
current, use under an ambient temperature exceeding the
specified values as may be possible with a heated air
blower which directly radiates heat over the machines,
and overheated windings resulting from dust accumulating
on the core packs and coil ends. All of the above items
impair insulation and reduce the life of the machine.
5.2 Cleaning of Coils
The method selected will depend on the type of
machines, type of insulation, kind of dirt, and other
conditions and circumstances.
Cleaning by Wiping with Cloth
Wiping cloths can be used for cleaning when the machine
Maintenance of Windings05
Fig. 8 Values of Vibration
Speed, rpm Rotational Frequency, Hz Rotational Frequency, Hz
(61)
05
18 << INSTRUCTIONS FOR THREE-PHASE INDUCTION MOTORS
is small, the surfaces to be cleaned accessible, and the
dirt to be removed dry.
Waste should not be used, as lint will adhere to the
insulation and increase the collection of dirt, moisture,
and oil. This is particularly objectionable on high-voltage
insulation, as it tends to cause concentration of Corona.
Cleaning by Means of Compressed Air
Compressed air, used to blow out dirt with a jet of air, is
usually effective especially where dirt has collected in
places that cannot be reached with a wiping cloth.
Cleaning can be done more quickly with compressed air
than with wiping cloth especially on the large machines. If
blowing with compressed air results in simply transferring
dirt from one place to another on the machine, little is
accomplished.
There are a number of precautions to be observed when
using compressed air: Air being blown should be dry,
especially if blowing against insulation. Moisture
condenses and accumulates in air lines and hoses.
Care should be taken to assure this has been completely
dried out before using the compressed air on insulation.
Compressed air should never be more than 3 ~ 4 kg/cm2
pressure. Higher pressures can damage insulation and
force dirt under loosened tape.
Care should be taken not to blow loosened dirt into inner
recesses where it will be difficult to remove and where it
might obstruct ventilating ducts.
Cleaning by Means of Solvents
Solvents are usually required to remove grease and oil
dirt. A lint-free cloth wet with solvent may be dipped in
the fluid.
Petroleum distillates are the only solvents recommended
for cleaning electrical apparatuses. These solvents,
classed as Safety-Type Solvents, have a flash point of
above 37.8 deg and are available from most oil companies
and other supply sources under various trade names:
- Mineral spirits, cleaner’s naphtha, and similar products
with a flash point above 37.8 deg.
- Gasoline, naphtha, and similar grades must not be used
for cleaning. They are highly volatile and present a great
fire hazard.
5.3 Use of Space Heaters
When the motor is operating, its interior is not humid and
in a dry condition. But it absorbs humidity at rest.
In order to prevent absorption of humidity, the space
heater installed inside the frame should be immediately
energized after the motor comes to a stop, and the
temperature inside of the motor should be controlled 3 to
5 deg higher than the ambient temperature.
If there is no space heater, a 100-150-W incandescent
lamp may be used.
5.4 Drying Insulation
Should the insulation resistance for the winding have poor
insulation resistance due to the ingress of moisture, then
the windings must be dried to improve the insulation
resistance to the minimum specified value before the
application of insulation resistance. The preferred method
of drying windings is the external heat method. The
alternative is the internal heat method.
1) The External Heat Method.
* Temperature-controlled oven
The best method is to dismantle the motor (including
Maintenance of Windings
Wear goggles when blowing dirt outwith compressed air and be careful notto direct the air jet toward others.Failure to heed this warning can resultin injury to the eyes.
Avoid prolonged or repeated contactwith petroleum distillates or breathingtheir vapors. These solvents can causesevere skin irritation, are toxic, and arereadily absorbed into the system. Failureto heed this warning can cause severepersonal injury or death.Do not use carbon tetrachloride ormixtures containing carbon tetrachloridefor cleaning purposes. Carbontetrachloride and its fumes are highlytoxic. Failure to heed this warning canresult in serious illness or death.Avoid excessive contact with cleaningsolvents and breathing their vapors.Some solvents are extremely toxic andreadily absorbed into the system.
Connect this heating system according toits output and reference voltage.Arrange the control so that the heatingsystem- switches on after the electrical machine
switches off.- switches off before the electrical machine
switches on.
(62)
bearings) and place the motor in a temperature-
controlled oven at between 110 max. for 8-10 hours
depending on oven efficiency to remove moisture.
* The alternative external heat method is to remove end
shields and covers, connect the anti-condensation
heaters, and fit additional “black heat” resistance in and
around the motor.
A temperature controller should control additional
resistance heaters with a probe adjacent to the winding at
the top of the motor. The temperature should be set for
100 to 120 The drying process will take approximately
10 - 16 hours once the correct temperature is achieved.
< Key Points to Remember >
1) Heaters must be the “black heat” types otherwise the
insulation might be burnt.
2) The motor may need to be covered by some thermal
insulation to retain the heat.
3) A vent opening should be placed in the tip of the
thermal insulation tent for the evaporated moisture to
escape.
4) Sufficient space should be allowed between the heaters
and any winding insulation so as not to generate local
excess heating of the winding insulation.
2) The Internal Heat Method
With this method, the heat is applied by passing current
through the windings to generate heat. Extreme caution
should be exercised using this method so that you do not
damage the internal insulation before the windings are up
to optimal temperature.
< Key Points to Remember >
1) Remove brushes and short the ring together with a
copper link in case of a slip ring motor (wound rotor).
2) Connect an AC supply voltage to the stator windings.
The applied voltage should be approximately 12%. In
this case the stator nominal voltage is 3,300 V and
since 415 V AC represents 415/3,300 x 100 = 12.5%,
this will be a convenient supply voltage. In case the
current is taken from the supply, it would be typically
70% of the full load rated current.
3) The power supply should be controlled with a
temperature controller operating from the internally
connected RTDs supplied by the motor manufacturer.
4) The shaft should be locked to prevent rotation.
5) Set the temperature controller to 110 maximum.
6) Drying will take approx. 8-12 hours once the windings
have reached 100 . The windings should take 6-8
hours to heat up to 110 .
Determination of Dried Insulation
During the drying process the insulation resistance should
be checked with a 500-V (low-voltage machine) or 1,000-V
(only high-voltage machine) DC low-energy source meter
(e.g. megger) and then recorded after 1 minute.
This process should be repeated every hour until the
results show the winding is dry.
Once the winding is completely dry, the insulation
resistance will stabilize. After the windings cool down, the
insulation value should increase.
Notes on Drying Insulation
1) A temperature-controlled oven should be used if the
windings have been completely immersed in water.
2) Should the windings contain contamination, the
windings should be properly cleaned before attempting
to dry windings. Contact your factory representative for
further advice.
3) All processes for drying insulation should be performed
under the supervision of qualified personnel. Failure to
observe proper procedures may result in permanent
damage to the insulation or winding system. For further
advice contact your factory representative.
Instruction Manual >> 19
THREE-PHASE INDUCTION MOTORS
Fig. 9 Change in Insulation Resistance
This method should only be used if allwinding resistance is greater than 1megohm.
(63)
06
20 << INSTRUCTIONS FOR THREE-PHASE INDUCTION MOTORS
Maintenance of Slip Rings, Brushes and Brush Holders
Fig. 10 Examples of Good Condition
Fig. 11 Examples of Poor Conditions
6.1 Slip Rings
Good Conditions
The slip ring must run true to the center of rotation. The
maximum permissible TIR (Total Indicator Runout) must be
no greater than 0.02 mm. If the TIR is greater than this,
the slip rings must be machined true. The surface of the
slip rings must be a smooth finish. The slip ring will
normally show a running band under the brush contact
area. This can be from light straw in colour to dark brown
(almost black). The most normal colour is “light brown”.
The surface should be consistent in colour around the
periphery and across the brush track. Sparking should not
be evident during operation and the rings should be dry
with no signs of contamination.
The Brush Running Band is a film on the ring basically
consisting of copper oxide and carbon. This film occurs
naturally during normal operating and it is essential for
good brush and ring condition. Do no try to remove it. The
film is easily maintained by ensuring the area is free from
contamination and the machine is properly loaded.
Poor Conditions
Poor ring conditions can be caused by several conditions.
The common causes of poor ring conditions are:
1) Brush loading is not optimum correction:
See Section “Optimizing Brush Wear”.
2) Contamination:
Such as oil, salt air, H2S or silicone vapours (even from
Silastic) may destroy the film builds up on the rings.
Correction : The contamination should be removed and
a new set of brushes fitted and bedded in. It is
preferred that slip rings be cleaned with a dry lint-free
cloth. If required, some “non-residue/noncorrosive”
electrical cleaning solvent could be used.
3) Corrosion of Brush Rings
This condition may occur if the motor has been at
standstill for a long time (e.g. after extended storage).
Correction : This should be removed by using a fine
“ommutator” stone available from most service shops
or brush suppliers. Rotate the motor either with a small
pony motor or run the motor on no load and uncoupled
with the slip rings short-circuited after accelerating to
full speed (do not start without rotor resistance starter).
4) Threading
If threading occurs, brush optimization should be
corrected first.
1) Light threading can be corrected the same way as
“corrosion”.
2) Heavy threading should be corrected by machining
the slip rings.
5) Out of round rings
This must be corrected by machining the slip rings.
Machining Slip Rings
Method 1 - Preferred:
Dismantle the motor and remove bearings. Place the rotor
in a lathe, centre bearing journals true and machine slip
rings.
Electrical solvent, if inhaled or absorbedthrough the skin, can be dangerous toyour health. Please refer to themanufacture safety information forproper advice
Although no voltage is present across therings during this operation you should- ensure the rings cannot open circuit,
otherwise high voltages could be present.- follow electrical safety rules.This procedure should only be performedby qualified and experienced personnel.
(64)
Method 2 - Alternative:
The rings are removed from the shaft with a puller which
can be attached to the hub of the slip ring assembly.
Access to the rings can be gained by removing the drive
end endshield and carefully disconnecting the rotor leads.
After the rings have been removed they can be machined
in a lathe.
Method 3 - Alternative:
Some motor repair shops offer on-site machining. This is
not a preferred method, but may be required for
emergency repair. If on-site machining is performed, the
following precautions should be adhered to
-- replace brushes after machining operation is complete.
-- all ring swarth to be removed from slip ring enclosure.
-- this operation should only be performed by experienced
personnel.
After machining, the rings should be kept clean and free
from fingerprints until ring film has developed during
operation.
6.2 Brushes and Brush Holders
General
The brushes must make good contact with the slip ring
surface. To ensure this, they must move freely within the
brush holder and pressure lever must apply the correct
pressure. The brush holder assembly is fixed. To replace
brushes, unclip the pressure level and undo the “pigtail”
from the holder assembly.
If satisfactory brush life has been obtained, replace the
brushes with the same grade as the original. Always make
sure brushes are bedded in after replacement.
It may be possible that brushes wear out quickly. A
common cause for this is a light load or brushes not
making proper contact with the rings. In this case consult
Section “Brush Optimization” or your carbon brush supplier.
If brush holders need replacing, the brush assembly may
be removed by taking off the drive end endshield. The
brushes are to be changed when they have worked down
to about 1/3 of their original length. The wear is not the
same for all brushes. It is important to keep the brush
housing clean and grease from excess carbon dust. Clean
out housing periodically, using vacuum cleaner and clean,
dry compressed air (max. 4 bars) where possible.
Bedding Brushes
When new brushes are fitted they should be bedded in. If
the slip rings wear, the diameter can vary, so the
diameters of the brush face and the diameter of the rings
may not be exactly the same. So, in all cases, brushes
should be bedded in.
Some abrasive sandpaper
should be placed around
the slip ring and the brush
fitted in the holder with
the tensator in place. The
abrasive is drawn back
and forth until all of the
brush is in contact with
the ring.
The brush surface contact area must not be less than 80%
of the surface of each individual brush.
During the initial run, if possible, it is desirable to apply
some bedding chalk to the rings before entering under the
brush surface, this will promote the final bedding in of the
brush.
Instruction Manual >> 21
THREE-PHASE INDUCTION MOTORS
Fig. 12 Brush Holder Assembly
Fig. 13 “Bedding” Brushes In
NOTE: Bedding chalk is usually available from most serviceshops or carbon brush suppliers.
Cleaning while operating is notrecommended, except in case ofexperienced operators. High velocitycompressed air can lift brushes or shortpigtails together.
Fig. 14 Example ofPoor Surface Profile
(65)
07
22 << INSTRUCTIONS FOR THREE-PHASE INDUCTION MOTORS
7.1 General
Transport, Storage
Always keep the cover and the cable entries tightly
closed.
7.2 Description
1) Application
In the terminal box, the connection is made between the
stator winding and the supply cable from the system. The
terminal box is mounted on the machine frame at an
easily accessible location.
2) Construction
A typical construction is shown in Fig. 15
3) Degrees of Protection
The terminal boxes comply at least with degree of
protection IP55 as per IEC 34-5.
4) Connection Part for Main Terminals
The connection part is suitable for connection with cable
lug depending on the equipment complement.
7.3 Installation
1) Termination
General
Ensure that the power supply agrees with the rating plate
data. The supply cables should be matched to the rated
current and plant-specific conditions (e.g. ambient
temperature, method of cable installation, etc.). Connect
the supply-cable conductors.
Connection by Means of Cable Lugs
The size of cable lugs must be matched to the size of the
supply cable. Use appropriate units with sufficient
current-carrying capacity.
Direction of Rotation
When the power supply phase conductors L1, L2, L3 are
connected to terminals U, V, W respectively, the motor
will rotate in a correct direction. If the connections to any
two terminals are reversed, i.e. if lines L1, L2, L3 are
connected to terminals V, U, W (or U, W, V or W, V, U)
respectively, the motor will rotate in a reverse direction.
Installing and Entering the Cable
The following steps are recommended for split entry:
- Cut the sealing insert so that its opening is some
millimeters smaller than the cable diameter.
- Introduce the cable into the cable gland. In the case of a
very small cable diameter, the cable diameter should be
increased by applying insulation tape at the securing
point to ensure concentric positioning of the cable in the
sealing insert.
- Provisionally attach the terminal box cover in order to
check whether perfect sealing is achieved both at the
flange surfaces and at the entry point with sufficient
prestressing. If this is not the case enlarge the sealing
insert cut out or adjust the cable diameter by means of
insulation tape. The securing bolts should then be
tightened alternately in steps.
- Unused entry openings always must be closed off by
suitable plugs.
These must
- be of permissible resistant material,
- conform to degree of protection IP55,
Terminal Box for High-voltage Supply
Fig. 15 Construction of Terminal Box(Example, delivered design may deviate in details)
Connection cables and cable ends mustnot exert any bending or torsion forceson the connection bolts!
Terminal box bodyPackingCable holderCable grommetInsulatorConnector
PackingTerminal box coverGland platePackingTerminal lugEarthing terminal
(66)
- be tightened so that they can be removed only by means
of a tool.
Earth Connection
An earth terminal for connecting the cable earth
conductor is provided in the terminal box.
The minimum connection cross-section of earth
connections should be selected according to IEC 34-1 with
reference to live conductors.
Make sure in any case of installation and maintenance
work that the equipotential bonding is maintained.
Final Checks
Before closing the terminal box, check the following:
- Conductor connections and, if applicable, the circuit
connections have been made correctly.
- Interior of the terminal box is clean and free from
remainders of cable material.
- All terminal screws and the appropriate cable entry parts
are firmly tightened.
- Clearance in air of 8 mm at 500 V, 10 mm at 660 V,
14 mm at 1 kV, 60 mm at 6 kV, 100 mm at 10 kV
are maintained. Remove any projecting wire ends!
- Connection leads are not subject to strain and the
insulation cannot be damaged.
- Unused entry openings are closed off by suitable plugs.
- All seals and sealing surfaces are in perfect condition. If
sealing of the joints is effected by metal-to-metal joints
only, the surfaces should be cleaned and thinly
regreased.
- Entry glands fulfill all requirements concerning degree of
protection, conditions of installation, permissible lead
diameter.
7.4 Operation
Safety Advice
Covers to prevent accidental contact with live or rotating
parts and those required for proper air guidance and thus
effective cooling should not be opened during operation.
During maintenance or inspection work in the immediate
vicinity of the terminal box or of the rotating machine
suitable measures should be taken to protect personnel
against hot gases escaping under short-circuit conditions.
7.5 Maintenance
1) Safety Advice
Before any work is started on the machines, particularly
before covers are removed from live parts, make sure that
the machine/plant has been correctly disconnected from
the power supply.
Please adhere to the general “5 safety rules”
- Isolate the equipment from the power supply,
- Provide a safeguard to prevent unintentional reclosing,
- Verify safe isolation from the supply,
- Earth and short-circuit,
- Provide barriers or covers for adjacent live parts.
2) Tightness, High-current Loading
The terminal boxes should be inspected regularly to
ensure that they are tight, that the insulation in
undamaged and that the connections are firmly attached.
If the terminal box is subject to extremely high current
loading it is recommended that the insulators, connecting
parts and cable connectors be checked.
If any dust or moisture has penetrated the terminal box,
clean and dry out the terminal box. The seals and sealing
surfaces should also be checked and the cause of faulty
sealing should be remedied.
3) Tightening Torque
Max. tightening torque for current-carrying bolted joints is
given in below table.
Instruction Manual >> 23
THREE-PHASE INDUCTION MOTORS
Only switch off the electrical machineduring the main running period in anemergency, in order to protect theswitchgear and electrical machine.
High-voltage power source must bedisconnected before working onequipment.Failure to disconnect power source couldResult in injury or death.Terminal box only to be opened byskilled personnel
NOTE: Replace the cover and tighten up the screws (takingsafety elements into consideration).
ScrewStrength class
M58.8
M68.8
8.0 8.0Tightening Torque(Nm)
M128.8
M108.8
M88.8
M168.8
704020 170
*The tolerance of tightening torques is 10%
(67)
08
24 << INSTRUCTIONS FOR THREE-PHASE INDUCTION MOTORS
8.1 General
Transport, storage
Always keep the cover and the cable entries tightly
closed.
8.2 Description
1) Application
The terminal boxes are employed for connection of
auxiliary circuits.
If specially ordered for anti-condensation heater, an
auxiliary terminal box for anti-condensation heater may be
supplied.
2) Construction
The typical construction is shown in Fig. 16.
3) Degrees of Protection
The terminal boxes comply at least with degree of
protection IP55 as per IEC 34-5.
8.3 Installation
1) Termination
When making the connections of auxiliary circuits note
wiring diagram for auxiliary circuits documented in the
approval specification.
The cross-section of a supply cable should be selected on
the basis of the rated current and plant-specific
conditions.
The connection terminals for auxiliary circuits are suitable
for conductor cross-sections of at least 2.5mm2.
The ends of the conductors should be stripped in such a
way that the remaining insulation reaches almost up to
the terminal.
2) Installing and Entering the Cable
In addition to the information given for cable selection and
preparation, the following specific notes apply, depending
on the type of entry fitting used :
To maintain the degree of protection IP all screwed-in
glands must be firmly tightened and sealed by suitable
measure, e.g. by means of an adhesive or by fitting
sealing ring. The same measures are required when fitting
screwed-in plugs.
The center rings of screw glands included in the scope of
supply are always screwed in place, fixed in position and
sealed in accordance with degree of protection IP55 by
use of LOCTITE. These glands also are fitted with blind
washers for transport protection.
For adapting the cable diameter to the gland conditions it
may be necessary to apply a layer of insulation tape to the
leads to enlarge its overall diameter or to cut out some
rings of the sealing insert.
With extreme lead diameter it may be necessary to
replace the glands by those of appropriate dimensions.
Entry plates of terminal boxes may be supplied undrilled
in order to allow selection of cable entry screw glands,
whose design, number and size are suitable for the cables
employed.
Terminal Box for Auxiliary Circuits
Fig. 16 Construction of Terminal Box(Example, delivered design may deviate in details)
Terminal box bodyPackingSupport ringRailTerminal block.
Cable grommetEarthing terminalPackingTerminal box cover
Hazardous Voltage.Will cause death, serious injury,electrocution or property damage.Disconnect all power before working onthis equipment
(68)
The entry elements should be selected so that
- they are suitable for the cable diameter,
- they conform to the degree of protection,
- they are suitable for the installation conditions.
The supply leads-particularly the protective conductor-
should be laid loosely in the terminal box with an extra
length to protect the cable insulation against splitting.
Unused entry openings always must be closed off by
suitable plugs.
These must
- be of permissible resistant material,
- conform to degree of protection IP55,
- be tightened so that they can be removed only by means
of a tool.
3) Earth Connection
A earth terminal for connecting the cable earth conductor
is provided in the terminal box.
9.1 Description
1) Application
Anti-condensation heaters fitted in electrical machines
warm the air inside the stationary machine to a
temperature above that of the surroundings, thus
effectively preventing moisture condensation.
2) Construction
The typical constructions are shown in Fig. 17, 18 and 19.
Instruction Manual >> 25
THREE-PHASE INDUCTION MOTORS
Fig. 17 O Type Anti-condensation Heater(Example, delivered design may deviate in details)
Fig. 18 U Type Anti-condensation Heater(Example, delivered design may deviate in details)
Anti-condensation Heating with Heating Tube09
Insulation materialsHeating conductorHeating pipeLead cable
Insulation materialsHeating conductorHeating pipeLead cable
(69)
09
26 << INSTRUCTIONS FOR THREE-PHASE INDUCTION MOTORS
The heating tube has a heating conductor which is
embedded in insulating material and arranged inside a
corrosion-resistant metal tube. The tube ends are sealed
to prevent the ingress of moisture.
3) Installation
The anti-condensation heater consists of one or more
tubular heating elements connected together. These
heating tubes are combined to form units and are
installed in the stator frame. The arrangement constitutes
the so-called “stabilized design”, i.e. the heating
temperature stabilizes itself at the rated voltage thanks to
the optimum balance of heater rating and heat
dissipation. Special temperature monitoring devices are
therefore not necessary. This applies to explosion-proof
versions as well.
9.2 Installation
1) Connecting the Supply Cable
The heater connections are brought to terminals which
are located in a separate terminal box and may be made
without cable lugs.
Connection must be made in accordance with wiring
diagram documented in the approval specification.
Examine the data plate to see that the voltage and the
power of the heating agree with the main supply. The
supply connection of the heaters must be interlocked with
the main breaker of the machine to ensure that the
heaters are switched off when the machine is running and
switched on once the machine has come to a standstill.
Through appropriate series connection of the heating
tubes, even the temperature of explosion
-- proof machines can be limited such that these machines
meet the requirements of “stabilized design” and do not
require any additional temperature monitoring
measures. For this reason, no changes may be made in
the original heating-tube connection!
2) Insulation Testing
The heater may only be put into operation if the specified
minimum insulation value of 0.5 Mega-ohm is obtained
from measurement of the insulation resistance with the
heater connected.
For the period after commissioning of machines equipped
for anti-condensation heating, it is assumed that either
the machine itself is in operation or the anti-condensation
heater is heating the stationary machine.
9.3 Maintenance
1) Safety Advice
The anti-condensation heater is switched on when the
machine has come to a standstill. Therefore, it must be
switched off before any protecting cover is opened for
maintenance work.
2) Cleaning
With respect to maintenance, occasional cleaning
performed during routine maintenance of the machine
and the replacement of any damaged parts is sufficient.
3) Repairs
Should replacement of the heating tubes become
necessary use the same type of heaters. Install the new
tubes securely and lock the fixing elements.
The heating tube units in explosion-proof machines may
only be replaced as a whole and must be purchased as
whole preformed units to suit the particular application. If
repairs and modifications to models covered by the
certificate for these machines are not performed in a
HYUNDAI workshop, an acceptance inspection by an
authorized engineer is necessary. If modifications not
covered by the certificate are made, the machine must be
newly certified.
Anti-condensation Heating with Heating Tube
Fig. 19 Strip Type Anti-condensation Heater forExplosion-proof Machines with “increased safety”(Example, delivered design may deviate in details)
Hazardous Voltage.Will cause death, serious injury,electrocution or property damage.Disconnect all power before working onthis equipment
Insulation materialsHeating conductorHeating pipeLead cable
(70)
10.1 Flange-type Sleeve Bearings (Ring Lubrication System)
1) Mounting
The flange-type sleeve bearings of electrical machines are
of the split type. They are ring-lubricated and are subject
to the following instructions supplementing and modifying
the operating instructions of the machine:
Corresponding to the operating conditions the sleeve
bearings of new machines have a favorable bearing
clearance which should not be changed. Also scraping
(spot grinding) is not allowed to do not make worse the
antifriction qualities.
It is recommended that the contour of the transmission
element remains within the hatched range (see Fig.19) to
remove the upper part of the bearing housing for
maintenance without removing the transmission element.
Before the machines are aligned and commissioned, the
bearings should be filled with lubricating oil, because the
machines are delivered without oil in the bearings (Oil
type is indicated on the nameplate for bearing).
2) Oil Change
Check the bearing temperature regularly. The governing
factor is not the temperature rise itself, but the
temperature variations over a period of time. If abrupt
variations without apparent cause are noticed, shut down
the machine and renew the oil.
The lubrication oil indicated on the data plate is used for
starting up the machines at an ambient temperature of
above +5 At lower temperatures (to about -20 ), it is
sufficient to preheat the oil. If the ambient temperature
are below -20 another type of oil according to the
special conditions is used. Do not mix oils of different
grades. Recommended oil changing intervals are about
3000 and 6000 operating hours in the case of intermittent
and continuous duty. When cleaning, first flush the
bearings with kerosene and then with oil. Pour in the
kerosene and oil through the top sightglass hole. Leave the
drain open until all the kerosene has been removed and
clean oil runs out. Now plug the drain and fill the bearing
with oil up to the centre of the lateral inspection glass.
When the machine has run up to speed, check the oil ring
through the top inspection glass to see that it rotates
correctly, and check the bearing temperature, Should the
bearing temperature not drop to the normal value after
the oil change, it recommended that the surfaces of the
bearing shells be inspected.
If the bearings are fitted with thermometers for checking
the bearing temperature, fill the thermometer well in the
upper bearing shell for thermofeeler with oil to improve
heat transfer and top up with oil every time the
lubricating oil is changed.
3) Dismantling, Assembling
When dismantling the machine the lower part of the
bearing housing need not be unscrewed from the end
shield, When opening the bearing housing, locate before,
if on which side of the machine the adjusting shims.(upper
and lower parts)are installed. These shims must be
installed at the same place when assembling the machine.
Exceptions are possible if the stator core was changed.
Drain the oil, take off the upper part of the bearing housing
and the upper bearing shell, lift the shaft very slightly and
turn out the lower bearing shell and the sealing rings in
peripheral direction. The oil ring can be withdrawn by
holding it at an inclined position to the shaft.
If only slight damage has occurred to the bearing surface,
it may be re-conditioned by scraping as long as the
cylindrical shape of the bore is maintained, so that a good
oil film can form. The lining must be renewed if more
serious damage is found. The oil pockets and grooves of
the new lining or scraped shell should be cleaned and
finished with particular care
The replacement bearing shells are delivered by the works
with a finished inner diameter. Only if the bearing shells
were delivered unfinished, the inner diameter is 1mm
smaller than the finished diameter. Oil rings which have
become bent through careless handling will not turn
evenly. Straighten or replace such rings. Replace any
damaged sealing rings.
Instruction Manual >> 27
THREE-PHASE INDUCTION MOTORS10 Maintenance of Bearings
Maintain Proper Oil Level.May cause damage to equipment due toimproper lubrication.Follow lubricating instructions carefully.Avoid adding oil while unit is running.
Fig. 20 Oil Pockets and Oil Grooves
(71)
10
28 << INSTRUCTIONS FOR THREE-PHASE INDUCTION MOTORS
Maintenance of Bearings
Fig. 21 Ring-lubricated Flange-type Sleeve Bearings (Example, delivered design may deviate in details)
1. Screw plug(thermometer mounting)2. Inspection glass3. Sealing ring for 24. Sealing ring for 15. Bearing housing, upper part drive end6. Cylindrical pin7. Sealing ring, upper half, drive end8. Guide pin to prevent twisting9. Upper bearing shell, drive end
10. Oil ring, drive end11. Lower bearing shell, drive end12. Bearing ring, lower half, drive end13. Sealing ring, lower half, drive end14. Taper pin15. Guide pin to fix bolted parts16. Sealing ring for 1717. Drain plug18. Bearing housing, upper part, non-drive end19. Sealing ring, upper half, non-drive end20. Upper bearing shell, non-drive end21. Oil ring, non-drive end22. Lower bearing shell, non-drive end23. Bearing housing, lower part, non-drive end24. Sealing ring, lower half non-drive end25. Upper adjusting shim, drive end26. Sealing cover drive end27. Lower adjusting shim, drive end28. Upper adjusting shim, non-drive end29. Sealing cover, non-drive end30. Lower adjusting shim, non-drive end31. Protective cap32. Pressure compensation opening
123
4
5
6
7
8
9
10
11
12
13
1716
2
3
15
14
12
34
18
6
19
8
20
21
22
23
24
17
16
2
3
15
31
28
29
3032
25
32
Limiting range for transmission element
27
a
d1d2
45
26
14
(72)
10.2 Flange-type Sleeve Bearings(Forced Lubrication System)
1) Mounting
These flange bearings of electrical machines are of the
split type. They are lubricated by and oil rings and is
provided for additional forced lubrication. They are subject
to the following instructions supplementing and modifying
the operation instructions of the machine: Corresponding
to the operating conditions the sleeve bearings of new
machines have a favorable bearing clearance which
should not allowed to do not make worse the antifriction
qualities.
It is recommended that the contour of the transmission
element remains within the hatched range to remove the
upper part of the bearing housing for maintenance
without removing the transmission element.
Before the machines are aligned, the bearings should be
filled with lubricating oil (oil type is indicated on the
nameplate for bearing), because the machines are
delivered without oil in the bearings.
Connect the bearings to the oil pump, oil tank and cooler
before commissioning the machines. No reducers must be
fitted in the piping. Install a regulating orifice on the oil
supply line to protect the bearing from flooding. If the oil
pump fails, the lubrication maintained by the oil ring is
effective for about 15 to 30 minutes, provided the oil
contained in the bearing does not drain away. To prevent
this, connect the oil discharge tube on that side where the
oil rings moves downward into the oil. In addition to this,
install a non-return valve in the oil supply line. As an
alternative, the oil 100 mm high, to raise the level of the
oil in the bearing. Oil discharge tubes must terminate
flush with the inside surface of the bearing housing to
prevent the oil rings from rubbing against the tubes.
Fill the oil tank with lubricating oil indicated on the data
plate. This oil is used for starting up the machine at an
ambient temperature of above +5 At lower
temperatures preheat the oil. It is recommended to use a
control system adjusted in such a manner to have an oil
temperature of 15 to 20 in the tank and to have a
preheated oil flow through the cold bearings for 5 to 10
minutes before starting up the machine. Do not mix oils
of different grades.
The necessary pressure of the oil entered the bearings
and the oil flow rates are indicated on the data plate.
Adjust to these values when starting up the machine for
the first time and correct them when the bearing has
attained its normal running temperature. The oil in the
bearing housing must not ascend over the center of the
lateral inspection glass.
If the bearings are fitted with thermometers for checking
the bearing temperature, fill the thermometer well in the
upper bearing shell for the thermofeeler with oil to
improve heat transfer and top up with oil every time the
lubricating oil is changed.
In the case of insulated bearings, make sure that the
insulation is not bridged by the tubes; interrupt the
electrical conductivity of the tubes near the bearings, e.g.
by installing oil-resistant fittings of plastic material or
hoses of rubber or plastic material.
Switch on the oil pump before starting up the machine.
The use of a pump driven from the shaft of the main
machine is permitted only in special cases, i. e. when the
acceleration and coasting times are short.
2) Oil Change
Check the bearing temperature regularly. The governing
factor is not the temperature rise itself, but the
temperature variations over a period of time, if abrupt
variations without apparent cause are noticed, shut down
the machine and renew the oil.
Recommended oil changing intervals are about 20,000
operating hours. After the machine is come to a standstill
and the old oil is drained out of the bearings and oil tank
operate the oil pump with kerosene for a short time and
then with oil to clean the bearings, the oil pump, the oil
tank, the cooler and the pipe lines. Pour in the kerosene
and then the oil through the filling opening of the oil tank.
Leave the drains open from time to time until all the
kerosene has been removed and clean oil runs out of the
bearings and oil tank. Now, plug the drains and fill the
tank with oil. Should the bearing temperature not drop to
the normal value after the oil change, it is recommended
that the surfaces of the bearing shells be inspected.
3) Dismantling, Assembling
When dismantling the machine the lower part of the
bearing housing need not be unscrewed from the end
shield. When opening the bearing housing, locate before,
if and on which side of the machine the adjusting shims
(upper and lower parts) are installed. These shims must
be installed at the same place when assembling the
machine. Exceptions are possible, if the stator core was
changed. Drain the oil, take off the upper part of the
bearing housing and the upper bearing shell, lift the shaft
very slightly and turn out the lower bearing shell and the
sealing rings in periphera direction. The oil ring can be
withdrawn by holding it at an inclined position to the shaft.
Instruction Manual >> 29
THREE-PHASE INDUCTION MOTORS
Maintain Proper Oil Level.May cause damage to equipment due toimproper lubrication.Follow lubricating instructions carefully.Avoid adding oil while unit is running.
(73)
10
30 << INSTRUCTIONS FOR THREE-PHASE INDUCTION MOTORS
If only slight damage has occurred to the bearing surface,
it may be re-conditioned by scraping as long as the
cylindrical shape of the bore is maintained, so that a good
oil film can form.
The lining must be renewed if more serious damage is
found. The oil pockets and grooves of the new lining or
scraped shell should be cleaned and finished with
particular care.
The replacement bearing shells are delivered by the works
with a finished inner diameter. Only the bearing shells
were delivered unfinished, the inner diameter is 1mm
smaller than the finished diameter. Oil rings that have
become bent through careless handling will not turn
evenly. Straighten or replace such rings. Replace any
damaged sealing rings.
Maintenance of Bearings
Fig. 22 Flange-type Sleeve Bearing for Forced-oil Lubrication (Example, delivered design may deviate in details)
1. Screw plug(thermometer mounting)2. Inspection glass3. Sealing ring for 24. Sealing ring for 15. Bearing housing, upper part drive end6. Cylindrical pin7. Sealing ring, upper half, drive end8. Guide pin to prevent twisting9. Upper bearing shell, drive end
10. Oil ring, drive end11. Lower bearing shell, drive end12. Bearing ring, lower half, drive end13. Sealing ring, lower half, drive end14. Taper pin15. Guide pin to fix bolted parts16. Sealing ring for 1717. Drain plug18. Bearing housing, upper part, non-drive end19. Sealing ring, upper half, non-drive end20. Upper bearing shell, non-drive end21. Oil ring, non-drive end22. Lower bearing shell, non-drive end23. Bearing housing, lower part, non-drive end24. Sealing ring, lower half non-drive end25. Upper adjusting shim, drive end26. Sealing cover drive end27. Lower adjusting shim, drive end28. Upper adjusting shim, non-drive end29. Sealing cover, non-drive end30. Lower adjusting shim, non-drive end31. Protective cap32. Pressure compensation opening33. Oil supply tube with orifice34. Oil discharge tube with sight glass
12 1
3
4
18
6
19
8
20
21
22
23
24
1716
2
3
15
142
3
4
5
6
7
8
9
10
11
12
13
1317
a 2526
27
32
33
34
d2
d1
3
2
15
14
3129
28
30
32
45
Limiting range for transmission element
(74)
10.3 Rolling-contact Bearings
1) Mounting
Electrical machines fitted with rolling-contact bearings
mentioned above are subject to the following instructions
supplementing and modifying the operating instructions of
the machine:
The locating bearings are deep-groove ball bearings for
horizontally mounted machines. These bearings may also
be in pairs with cylindrical roller bearings in the case of
bearings is not guide radially and is prevented from
rotating by compression springs.
The locating bearings for vertically mounted machines are
angular-contact ball bearings of type range 72 or 73
(angular-contact ball bearings with increased axial fixation
see supplementary operating instructions).
The floating bearings are deep-groove ball bearings or
cylindrical roller bearings. In case of deep-groove ball
bearings as floating bearings, the axial play is
compensated by means of compression springs.
2) Regreasing
Initial lubrication of the bearings is normally carried out in
the works with a Alvania RL#2 grease satisfying the
conditions of running test at a test temperature of 120
to DIN 51 806. If a different type of grease is required, this
is indicated on the data plate, provided that the particular
operating conditions were given in the order.
Keep the new grease meticulously clean. Greases having a
different soap base should not be mixed since this would
reduce the grease quality.
For regreasing, clean the lubricating nipple and press in
the grease quantity indicated on a data plate, using a
grease gun. The shaft should rotate during regreasing;
hence, the machines need not be stopped. After
regreasing, the bearing temperature will rise by a few
degrees and will drop to the normal value when the
grease has reached its normal service viscosity and the
excess grease has been forced out of the bearing.
It is recommended that the lubricating instructions be
strictly followed. Special cases may require lubrication to
special instructions, e.g. where there is an extreme
coolant temperature or aggressive vapours. The old
grease from several regreasing operations gathers in the
space inside the outer bearings caps. Remove the old
grease when overhauling the machines.
The model of bearing is favorably chosen as for direction
and size of load (type of construction, forces acting on the
shaft) and therefore it should not be changed.
The permissible values of axial and radial forces may be
taken from the list of machine or may be inquired.
The machines should operate in only one type of
construction as shown the rating plate, because another
type of construction required perhaps further measures in
addition to a modification of the model of bearing. Always
in this case an inquiry is necessary.
3) Lubrication
Regrease the bearings if the machines have been stored
unused for longer than 2 years.
4) Dismantling, Assembling
For working on the locating bearing in the vertical position
of the machine, support or discharge the rotor.
It is recommended that new rolling bearings be installed
as follows: Heat the ball bearings or the inner ring of the
roller bearings in oil or air to a temperature of approx.
Instruction Manual >> 31
THREE-PHASE INDUCTION MOTORS
Fig. 23 Examples for Bearing Combination
NOTE: A common mistake is over-lubrication of bearings.When grease is added without removing the drain plug, theexcess grease must go somewhere and usually it is forcedinto and through the inner bearing cap and is then throwninto the windings. Excess grease in the bearing can causebearings to run hot and could lead to bearing failure.
May cause bearingdamage(brinelling) if outer race ofbearing is struck.BECAREFUL When replacing bearing.Avoid subjecting bearing to impact.
Deep-groove ball bearing
Cylindrical roller bearing
Angular contact ball bearing
(75)
10
32 << INSTRUCTIONS FOR THREE-PHASE INDUCTION MOTORS
80 and slip them onto the shaft. Heavy blows may
damage the bearings and must be avoided.
When installing single angular-contact ball bearings, make
sure that the broad shoulder of the inner ring (and the
narrow shoulder of the outer ring) in operating position
points upwards, i.e. in a direction opposite to that of the
axial thrust.
When assembling the machines, avoid damage to the
sealing rings. Rubber sealing rings (V-rings) should be
carefully fitted over the shaft as shown the illustration.
New felt sealing rings should be so dimensioned that the
shaft can run easily while proper sealing is still effected.
Before fitting new rings, soak them thoroughly in highly
viscous oil (normal lubricating oil N68 to DIN 51 501)
having a temperature of approx. 80
5) Locating Faults
The troubleshooting table helps to trace and remove the
causes of faults. It is partly difficult to be found the
damages of bearings. In case of doubt, it is recommended
to renew the bearings.
10.4 Insulation to Prevent Shaft Current (High-voltage and Large Machines)
To prevent the shaft current according to the unbalance of
magnetic reluctance in magnetic circuits, the insulator is
provided at end shield side as shown in Fig. 24.
With motors having one shaft extension, the bearing at
non-drive end is insulated. Motors with double end shafts
are insulated at drive & non-drive end bearings. When
double end shaft motor is coupled with driven load,
insulation must be supplied in the coupling of one end to
prevent bridging of bearing insulation.
Care should be taken to prevent shorting out this
insulation. All lines (lubrication oil pipes, B.T.D, vibration
sensors, etc.) fitted at the workshop are insulated from
the end shield, but it is necessary to ascertain whether or
not the insulation is required for all lines which are
connected at the time of the motor installation at the site.
The bearing cooling pipe for forced-oil lubrication is
insulated as shown in Fig. 25. The shaft voltage (peak to
peak) is high frequency voltage of usually 1 volt or less
and rarely several volts. When a shaft current by this
voltage flows, the shaft and journal part are tarnished and
in the worst case sparking can make minute black spots
on shaft and journal parts. There is a possibility that if the
oil film is broken locally, a bum-out trouble will develop.
When disassembling or assembling, be sure to measure
the insulation resistance. The value of 1 to 3 k will be
satisfactory.
Maintenance of Bearings
NOTE: Insulation bearing any connection to this bearingmust be insulated from it to prevent bearing current.
Fig. 24 Bearing Insulation
Fig. 25 Bearing Cooling Pipe System for Forced-oil Lubrication
Hex, bolt & nut & S/WInsulation tubePackingInsulation flangeInsulation washer
(76)
Instruction Manual >> 33
THREE-PHASE INDUCTION MOTORS
Fig. 26 Floating Bearings (Example, delivered design may deviate in details)
1. V-ring 1)
2. Outer bearing cap 1)
3. Circlip 1)
4. Grease slinger 1)
5. Bearing housing 1)
6. Lubricating nipple7. Cylindrical roller bearing 1)
8. Inner bearing cap with felt sealing rings 1)
9. Deep groove ball bearing (floating-bearing) 10. Compression spring 1)
11. Bearing housing ring12. Bearing housing bush13. Cylindrical pin
1) Floating bearing side
1
2
3
4
5
6
7
8
8
1
1
2
2
3
3
4
4
116
10
12
13
9
8
5
6
9
10
Deep-groove ball bearingwith compensation of axial play
Cylindrical roller bearing
Deep-groove ball bearing withcompensation of axial play, withbearing housing bush andintermediate ring
(77)
10
34 << INSTRUCTIONS FOR THREE-PHASE INDUCTION MOTORS
Maintenance of Bearings
Fig. 27 Locating Bearings (Example, delivered design may deviate in details)
14. Inner bearing cap with felt sealing rings 2)
15. Angular-contact ball bearing16. Bearing slinger 2)
17. Grease slinger 2)
18. Circlip 2)
19. Outer bearing cap 2)
20. V-ring 2)
21. Deep-groove ball bearing(Locatingbearing) or angular-contact ball bearing
22. Compression spring 2)
23. Deep-groove ball bearing 2)
24. Cylindrical roller bearing 2)
25. Oil seal for shaft 1) 2) 3)
1) Floating bearing side2) Locating bearing side3) Special operating conditions only
Fig. 28 Fitting Instructions for V-ring and Oil Seal for Shaft
Angular-contact ballbearing placed above
Angular-contact ball bearing placed below
14
20
19
18
17
16
6
15
14
15
18
6
17
18
19
20
14
14
14
14
21
21
24
24
23
23
22
22
16
16
16
16
6
6
6
6
17
17
17
17
18
18
18
18
19
19
19
19
20
20
Single bearing, shaft doesnot pass through the outerbearing cap
Single bearing, shaft passesthrough the outer bearing cap
Duplex bearing, shaft doesnot pass through the outerbearing cap
Duplex bearing, shaft passesthrough the outer bearing cap
Single bearing,shaft does notpass through theouter bearing cap.
(78)
11.1 Air Filter
Air Filter Cleaning Period
The cleaning period depends on the site conditions and
can change. The cleaning of the filter is requested if the
record of the stator winding temperature (using the stator
winding sensors) indicates an abnormal increase in
temperature.
Air Filter Cleaning Procedure
The filter element (flat or cylindrical) is immersed in a tank
of cold or warm water (temperature less than 50 ). Use
water with detergent added.
Shake the filter gently to ensure that the water flows
through the filter in both directions.
When the filter is clean, rinse it with clear water.
Drain the filter properly (there must be no more formation
of droplets).
Refit the filter on the machine.
11.2 Cooler
1) General Points
The purpose of the cooler is the remove machine heat
losses (mechanical, ohmic, etc). The exchanger is located
on the top of the machine.
Normal Operation
The air is pulsed by a fan fixed to the machine shaft.
Description of Air-Water Double Tube Exchanger
The double-tube technique keeps the cooling circuit from
being affected by possible water leakage. The double tube
provides a high safety level. In case of leakage, the water
goes from the inside of the internal tube to the coaxial
space between the two tubes. The water is drained axially
to a leakage chamber where it may activate a sensor. An
exchanger comprises a fin-tube block containing :
- a steel frame
- a fin-tube block expanded mechanically to the tubes.
The tube bundle is roll-expanded in the end plates. The
water distribution in the tubes is provided by two
removable water boxes. A water box is equipped with
collars for fitting the inlet and outlet lines. Neoprene seals
ensure water boxes and the end plates.
2) Cleaning
The frequency of cleaning operations depends essentially
on the purity of the water used. We recommend a
minimum of one inspection per year. The life of zinc block
for anticorrosion is about a year. Therefore, replace it with
a new one every year.
Cut off the water supply by isolating the inlet and outlet
lines and drain the water. Disconnect the leak sensor
(option with double-tube cooler) and make sure that there
are no leaks. Remove the water boxes on each side of the
machine. Rinse and brush each water box.
3) Stop the Machine
Leak detection for a double-tube exchanger. If a leak is
detected, cut off the power supply of the water in/outlet
lines and change to emergency operations, it is necessary
to ascertain and repair it. Remove the two water boxes,
apply a slight positive pressure in the leakage chamber
and thus between the two tubes (only concerns double-
tube coolers). If a tube is damaged, plug it at both ends.
Use a tapered plug. The plug should preferably be made of
saltwater-resistant aluminum bronze or of a synthetic
material.
4) Leak Detection (Float System)
A magnet float activates a switch located in the float-
guiding rod.
Instruction Manual >> 35
THREE-PHASE INDUCTION MOTORS11 Air Filter and Cooler
NOTE: Do not use a hard wire brush, as this will removethe protective tar-epoxy layer which has formed on thesurface of the water boxes. Clean each tube with a metalscraper. Rinse in soft water. Keep the leakage chamber dry(double-tube water-cooler only).
Fig. 29 Leakage Detector
Do not clean the filter using compressedair. This procedure would reduce filterefficiency.
(79)
11
36 << INSTRUCTIONS FOR THREE-PHASE INDUCTION MOTORS
5) Cooler Removal
The cooler unit is slid into its housing. It is possible to
remove the cooler from the housing without removing the
water boxes. The cooler is fastened to the housing via a
series of screws on the housing. Remove the supply and
return pipes. Provide two supports to hold the cooler
when it comes out of its housing. Remove the cooler
using slings that can be attached to the connecting
flanges.
6) Cooler Reassembly
Carry out the operations of the “Cooler Removal” in the
reverse order. Be careful to push the cooler completely
into its housing before tightening the fastening screws of
the cooler to the casing.
Air Filter and Cooler
Fig. 30 Cooler Removal
1. Cover2. Gasket for 13. Cooler housing4. Gasket for 55. Air-to-water cooling element
1
2
3
4
5
(80)
General
It is our recommendation that all electric motors are fitted
with motor protection. The preferred type of motor
protection should be provided the following protection
features:
1) Current limit by a programmable thermal limit curve
with thermal modeling based on winding temperature.
2) If RTD is installed for winding temperature detector,
winding temperature detection by RTDs should be
separated alarm and trip set points.
3) Ambient temperature RTD located in the motor ambient
air stream.
4) If installed bearing temperature indicator, alarm and trip
set points separate.
5) Calculation of motor thermal capacity available.
6) Ground fault detection.
7) Current unbalance detection.
8) Capacity for the protection system to learn motor
cooling times.
A motor protection system with these features should
reward you with better reliability and will allow you to
optimize the motor to its maximum performance
Protection Setting Recommended
Guide values for adjustment of tripping temperature.
Instruction Manual >> 37
THREE-PHASE INDUCTION MOTORS12 Protection
Insulation Class ‘F’
Description
Insulation Class ‘B’
PermissibleMax.
Temp.rise (T)
WindingTemperature
Max.140 °K
130 °K 140 °K
Max.95 °K
90 °K 95 °K
Max.100 °K
95 °K 100 °K
Max.10%
6%(10-sec delay)
10%(Inst.)
Max.155 °K
150 °K 155 °K
Max.95 °K
90 °K 95 °K
Max.100 °K
95 °K 100 °K
Max.10%
6%(10-sec delay)
10%(Inst.)
Bearing Temperature(Anti-friction*)
Bearing Temperature(Sleeve)
Current unbalance
Alarm TripPermissible
Max. Temp.rise (T)
Alarm Trip
- T means operation temperature including ambient temperature.- Max. permissible temp. rise includes ambient temperature.* When a suitable heatproof lubricant is used or a greasing interval
is changed, the limit of temperature rise shall be determined byagreement between manufacturer and purchaser.
(81)
13
38 << INSTRUCTIONS FOR THREE-PHASE INDUCTION MOTORS
Induction Motor Troubleshooting
Hazardous Voltage.Will cause death, serious injury,electrocution or property damage.Disconnect all power before working onthis equipment.
2. Great drop in voltage due to inadequate
line capacity and impedance drop
Power
source
& line
Starter
Motor
Load
a. A check is to be made on voltage at motor terminal before
and at time of starting.
b. Similar change in voltage is to be checked at motor
terminal.
a. Squirrel cage motor, rotor conductor is to be checked for
disconnection.
b. Wound motor, a check is to be made for line cutting and
unbalance.
c. Repairs or renewal is to be made.
a. Squirrel cage motor, motor is to be replaced with the one
having larger capacity and of the wound type.
b. Wound motor, tap for starting resistor is to be replaced.
a. Squirrel cage rotor, rotor bar and end ring are to be
checked for contact.
b, Wound motor, a check is to be made on coil for unbalance
and on brush for imperfect contact.
Load is to be checked, if load is normal, motor capacity is to
be changed.
A check is to be made on voltage drop of power source and
line.
Resistance and current are to be measured, and repairs are
to be made.
1. Drop in line voltage
3. Cut line or unbalanced
4. Erroneous wire connection
5. Cut line or unbalanced voltage
6. Drop in line voltage
7. Cut line or unbalance in starting resistor
8. Cutting of stator coil or of rotor coil
9. Erroneous connection of stator coil
10. Defect of rotor
11. Stator core is in contact with rotor.
12. Defective bearing
13. Insufficient starting torque
14
1. Inadequately low voltage.
2. Defective rotor.
3. Overload or inadequate torque
A check is to be made with a voltmeter.
Defective parts are to be repaired.
To be repaired
To be reconditioned
Compensator tap connection is to be raised.
Resistance is to be measured; repairs are to be made.
To be reconditioned
a. A check is to be made by turning by hand.
b. Bearing is to be disassembled and examined.
Load is to be reduced.
RemedyAbnormality
Motor fails
to start
Length of time
required for
acceleration after
starting
Probable cause
(82)
Instruction Manual >> 39
THREE-PHASE INDUCTION MOTORS
Two phases of U.V.W.(or R.S.T.) at starter or motor terminal
are to be changed.
a. A check is to be made with a voltmeter power source.
Voltage is to be raised.
b. Load is to be reduced.
A check is to be made with a voltmeter power source.
Voltage is to be reduced.
Resistance and current are to be checked and
reconditioned.
Judgment can be made according to noise; bent shaft,
bearing, etc., are to be corrected.
1. Unbalance of rotor
a. Bending of shaft
b. Loose joint
c. Residual unbalance
d. Critical speed of shafting
e. Dust attached to rotor
f. Imperfect connection between coupling
and shaft
5. Abnormal contact between shaft and
stationary part, such as end cover, etc.
9. Transmission of vibration from combined
machine
To be repaired
To be tightened by bolts securely
To be readjusted
To be cleaned
To be reconditioned
a. To be checked by turning manually
b. To be disassembled for detecting defects
Phase reversal
1. Overload
2. Overcurrent due to voltage drop
3. Excessive iron loss due to overvoltage.
4. Cut line or imperfect contact in one phase
5. Short-circuiting and grounding of coil
6. Contact between stator and rotor
7. Inadequate ventilation due to dust.
2. Improper magnetic center
3. Defective bearing
4. Coupling deflection
6. Unsatisfactory contact of brush
7. Improper alignment
8. Sinking of foundation
10. Unequal pitch of claw coupling
11. Improper bush of flexible coupling
Load is to be reduced (to rated current)
To be reconditioned
Cleaning is to be carried out.
To be reconditioned
Refer to the “Bearing” section
To be reconditioned
Brush is to be checked for contact.
To be reconditioned
To be reconditioned
Insulation for vibration
Reconditioning of pitch
Reconditioning of pitch
RemedyAbnormality
Rotation in reversal
direction
Motor body
overheated
Vibration
Probable cause
(83)
13
40 << INSTRUCTIONS FOR THREE-PHASE INDUCTION MOTORS
Induction Motor Troubleshooting
Causes of single-phase operation such as line cutting and
imperfect contact are to be detected; repairs are to be
made.
1. A check is to be made by turning manually.
2. To be disassembled for inspection
To be disassembled and defective parts are to be repaired.
1. Rotor shaft coil resistance is to be measured and
reconditioned.
2. Contact of brush or short-circuit ring is to be checked.
3. A check is to be made on endring contact of a squirrel
cage motor.
1. Care should be taken on shaft at time of assembling and
on bearing box at time of matching.
Machining accuracy and tightening of bearing box are to be
checked.
3. Short-circuits of layer and phase of stator
coil and rotor coil
4. Abnormal contact between shaft and
stationary part such as end cover
9. Crackings at brazed joint rotor bar and
end ring
1. Inclusion of dust and other foreign
substances or rust, bruises
1. Shaft or bearing box is distorted
elliptically.
1. Disagreement of air gap
2. Single-phase operation
5. Unsatisfactory foundation and installation
6. Loose bolts for foundation
7. Gap between foundation and base
8. Resonance with foundation
1. Voltage unbalance
2. Single-phase operation
3. Secondary circuit
1. Excess of tightening allowance
2. Erroneous selection of clearance
3. Minus operating clearance
4. Thermal expansion
2. Improper tightening
3. Inaccuracy due to improper matching
4. Deterioration with time
Causes are to be detected; repairs are to be made.
To be reconditioned
Readjustment of installation
Foundation bolts are to be tightened.
Reconditioning of installation
Readjustment of foundation
Power source and lines are to be checked and balanced.
Line cutting and improper contact are to be reconditioned.
2. Clearance is to be reinspected.
3. Care should be taken at time of assembly.
4. Examination of working condition
RemedyAbnormality
Noise
Unbalance of phase
current
Flaking
(a) Flaking of rolling
elements
(b) Local flaking of a
race
(c) Flaking all over a
race
(d) Flaking on
component parts
opposite to a race
Probable cause
(84)
Instruction Manual >> 41
THREE-PHASE INDUCTION MOTORS
Seizing
(a) Race ring and
rolling discolored
and turned soft
(b) Damage
Breakage
(total or partial)
(a) Fracture
(b) Cutting
Breakage of retainer
(a) Fracture
(b) Nonuniform
abrasion
(c) Wear of pocket
section
(d) Biting-off
Rust
(a) Rust formed all
over surface
(b) Rust on local
place
(c) Contact erosion
on joint surface
Wear
(a) Abnormal wear
of race and
rolling element
(b) Abnormal wear
of retainer
Electrode
(a) Crater-shaped
depression and
corrugated scars
(e) Flaking all overaround track center
(f) Flakingacross a race
(g) Flaking similar to pittingon a race
Careful handling
Examination of tightening
Examination of machining accuracy of shaft & bearing
housing
Careful handling and reconsideration of working condition
Examination of oil supply and lubricant
Inspection of storage room
Careful handling
Examination of rust-preventive reagent
Reexamination of machining of shaft & bearing housing
Reexamination of working condition
1. Advancement of flaking caused by shock
and below.
2. Great tightening allowance & large round
corner of fitted part
1. Moment load
2. Rotation at shift speed
3. Inadequate lubrication
4. Inclusion of foreign substances
1. Unsatisfactory condition of storage
2. Left alone
3. Inadequate cleaning
4. Rust-preventive reagent
1. Unsatisfactory packing
2. Sweet
1. Inadequate allowance of tightening
2. Change in load
1. Inclusion of foreign substances
2. Occurrences of wear
Inadequate lubrication
Abnormal thrust load
1. Shaft bending
2. Oblique fitting of outer and inner rings
1. Vibration during stoppage
2. Rust
1. Inadequate clearance
2. Inadequate lubrication
3. Improper overload of lubricant
Passage of current
Design of bearing system is to be checked.
Examination of working condition
Proper clearance is to be provided.
Oil amount of lubricant is to be checked.
Reconsideration of working condition and handling
Examination of lubrication and oil supply
Examination of design of bearing system
RemedyAbnormality Probable cause
(85)
13
42 << INSTRUCTIONS FOR THREE-PHASE INDUCTION MOTORS
Induction Motor Troubleshooting
Dent and
scratch
(a) Indentation (on a
race, etc.)
(b) Aventurine
hardening
(c) Dents given
during handling
(d) Scratches during
assembly
Smearing
biting-off on a
race and rolling
element
Creep
wear of outer and
inner surface,
sliking and
discoloring
Examination of lubricant and lubricating condition
1. Examination of tightening
2. Examination of machining accuracy of shaft and bearing
box
3. Examination of design
Examination of handling and assembling conditions
Careful handling
Careful assembling
Dust and foreign substances pressed
between race and body
Careless handling
(dropping, etc.)
1. Inadequate lubrication
2. Skewing of rolling element
3. Selection of lubricant
1. Inadequate tightening allowance
2. Inadequate tightening of sleeve
RemedyAbnormality Probable cause
(86)
14.1 HLA7 Horizontal-type Motor Construction
Instruction Manual >> 43
THREE-PHASE INDUCTION MOTORS14 Appendix
Fig. 1 HLA7 Horizontal-type Motor Construction (SQUIRREL CAGE)
*Disassembly and reassembly of HLA7 Type induction motor with antifriction bearingNotes: 1. Unless otherwise specified, reassembly of motors may be accomplished by reversing the disassembly steps.
2. Steps 7 to 11 are applied to both the Drive end and Non-drive end of the motors.
Uncouple, and perfom an alignment check at the motorand the drive machine
Lift the motor off and shift it to make enough room tomove the rotor
Remove the bolts securing the air seal and rest each parton the rotor shaft
Dismantle the connection box of the frame, if acc’y attached(BTD, grease pipe, etc.)
Remove the external bearing seal and slinger installed onthe bearing housing
Remove the fan cover
Remove the external fan
Remove the bearing housing
Remove the antifriction bearing
Remove the end shield (bracket) with fan guide
Remove the air guide
Remove the rotor from the stator
FLOW CHART
STEP
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
Remarks
*A distance equal to the rotor’slength may be required at bothends of the motor drive end andNon drive end.
*Heat the fan hub to approx.80 ~ 100 both for easyassembly and for removal.
(87)
14
44 << INSTRUCTIONS FOR THREE-PHASE INDUCTION MOTORS
Appendix
14.2 HLS7 Horizontal-type Motor Construction
Fig. 2 HLS7 Horizontal-type Motor Construction (WOUND ROTOR)
*Disassembly and reassembly of HLS7 Type induction motor with antifriction bearingNotes: 1. Unless otherwise specified, reassembly of motors may be accomplished by reversing the disassembly steps.
2. Steps 7 to 11 are applied to both the Drive end and Non-drive end of the motors.
Uncouple, and perfom an alignment check at the motorand the drive machine
Lift the motor off and shift it to make enough room tomove the rotor
Remove the bolts securing the air seal and rest each parton the rotor shaft
Dismantle the connection box of the frame, if acc’y attached(BTD, grease pipe, secondary t/box cable, etc.)
Remove the external bearing seal and slinger installed onthe bearing housing
Remove the fan cover
Remove the external fan
Remove the bearing housing
Remove the antifriction bearing
Remove the end-shield with brush holder
Remove the end-shield with fan guide
Remove the rotor from the stator
Remove the air guide
FLOW CHART
STEP
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
Remarks
*A distance equal to the rotor’slength may be required at bothends of the motor drive end andNon drive end.
*Heat the fan hub to approx.80 ~ 100 both for easyassembly and for removal
(88)
14.3 HRA7 Horizontal-type Motor Construction
Instruction Manual >> 45
THREE-PHASE INDUCTION MOTORS
Fig. 3 HRA7 Horizontal-type Motor Construction (SQUIRREL CAGE)
*Disassembly and reassembly of HRA7 Type induction motor with antifriction bearingNotes: 1. Unless otherwise specified, reassembly of motors may be accomplished by reversing the disassembly steps.
2. Steps 5 to 11 are applied to both the Drive end and Non-drive end of the motors.
Uncouple, and perfom an alignment check at the motorand the drive machine
Lift the motor off and shift it to make enough room tomove the rotor
Remove the bolts securing the air seal and rest each parton the rotor shaft
Dismantle the connection box of the frame, if acc’y attached(BTD, grease pipe, etc.)
Remove the external bearing seal and slinger installed onthe bearing housing
Remove the antifriction bearing
Remove the bearing housing
Remove the internal bearing seal
Remove the end shield (bracket)
Remove the internal fan
Remove the fan guide
Remove the rotor from the stator
FLOW CHART
STEP
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
Remarks
*A distance equal to the rotor’slength may be required at bothends of the motor drive end andNon drive end.
*Heat the fan hub to approx.80 ~ 100 both for easyassembly and for removal
(89)
14
46 << INSTRUCTIONS FOR THREE-PHASE INDUCTION MOTORS
14.4 HRP7(4P~) Horizontal-type Motor Construction
Appendix
Fig. 4 HRP7 (500 Fr.-2P & More Than 4P) Horizontal-type Motor Construction (SQUIRREL CAGE)
*Disassembly and reassembly of HRP7 Type induction motor with antifriction bearingNotes: 1. Unless otherwise specified, reassembly of motors may be accomplished by reversing the disassembly steps.
2. Steps 5 to 11 are applied to both the Drive end and Non-drive end of the motors.
Uncouple, and perfom an alignment check at the motorand the drive machine
Lift the motor off and shift it to make enough room tomove the rotor
Remove the bolts securing the air seal and rest each parton the rotor shaft
Dismantle the connection box of the frame, if acc’y attached(BTD, grease pipe, etc.)
Remove the external bearing seal and slinger installed onthe bearing housing
Remove the bearing housing
Remove the antifriction bearing
Remove the internal bearing seal
Remove the end shield (bracket)
Remove the internal fan
Remove the fan guide
Dismantle the air cooler box, if necessary
Remove the rotor from the stator
FLOW CHART
STEP
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
Remarks
*A distance equal to the rotor’slength may be required at bothends of the motor drive end andNon drive end.
*Heat the fan hub to approx.80 ~ 100 both for easyassembly and for removal
(90)
14.5 HRP7(2P) Horizontal-type Motor Construction
Instruction Manual >> 47
THREE-PHASE INDUCTION MOTORS
Fig. 5 HRP7 (355 Fr.~450 Fr.-2P) Horizontal-type Motor Construction (SQUIRREL CAGE)
*Disassembly and reassembly of HRP7 Type induction motor with antifriction bearingNotes: 1. Unless otherwise specified, reassembly of motors may be accomplished by reversing the disassembly steps.
2. Steps 5 to 11 are applied to both the Drive end and Non-drive end of the motors.
Uncouple, and perfom an alignment check at the motorand the drive machine
Lift the motor off and shift it to make enough room tomove the rotor
Remove the bolts securing the air seal and rest each parton the rotor shaft
Dismantle the connection box of the frame, if acc’y attached(BTD, grease pipe, etc.)
Remove the external bearing seal and slinger installed onthe bearing housing
Remove the antifriction bearing housing
Remove the bearing housing
Remove the internal bearing seal
Remove the end shield (bracket)
Remove the fan guide
Remove the rotor from the stator
Dismantle the air cooler box, if necessary
FLOW CHART
STEP
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
Remarks
*A distance equal to the rotor’slength may be required at bothends of the motor drive end andNon drive end.
(91)
14
48 << INSTRUCTIONS FOR THREE-PHASE INDUCTION MOTORS
14.6 HRQ7 Horizontal-type Motor Construction
Appendix
Fig. 6 HRQ7 (355 Fr.~450 Fr.-2P) Horizontal-type Motor Construction (SQUIRREL CAGE)
*Disassembly and reassembly of HRQ7 Type induction motor with antifriction bearingNotes: 1. Unless otherwise specified, reassembly of motors may be accomplished by reversing the disassembly steps.
2. Steps 5 to 11 are applied to both the Drive end and Non-drive end of the motors.
Uncouple, and perfom an alignment check at the motorand the drive machine
Lift the motor off and shift it to make enough room tomove the rotor
Remove the bolts securing the air seal and rest each parton the rotor shaft
Dismantle the connection box of the frame, if acc’y attached(BTD, grease pipe, etc.)
Remove the external bearing seal and slinger installed onthe bearing housing
Remove the fan cover
Remove the external fan
Remove the bearing housing
Remove the antifriction bearing
Remove the intermal bearing seal
Remove the end shield (bracket)
Remove the fan guide
Remove the rotor from the stator
FLOW CHART
STEP
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
Remarks
*A distance equal to the rotor’slength may be required at bothends of the motor drive end andNon drive end.
*Heat the fan hub to approx.80 ~ 100 both for easyassembly and for removal
Dismantle the air cooler box, if necessary
(92)
14.7 HRP7(2P) Horizontal-type Motor Construction
Instruction Manual >> 49
THREE-PHASE INDUCTION MOTORS
Fig. 7 HRP7 (355 Fr.~450 Fr.-2P) Horizontal-type Motor Construction (SQUIRREL CAGE)
*Disassembly and reassembly of HRP7 Type induction motor with antifriction bearingNotes: 1. Unless otherwise specified, reassembly of motors may be accomplished by reversing the disassembly steps.
2. Steps 5 to 11 are applied to both the Drive end and Non-drive end of the motors.
Uncouple, and perfom an alignment check at the motorand the drive machine
Lift the motor off and shift it to make enough room tomove the rotor
Remove the bolts securing the air seal and rest each parton the rotor shaft
Dismantle the connection box of the frame, if acc’y attached(BTD, grease pipe, etc.)
Remove the external bearing seal and slinger installed onthe bearing housing
Remove the internal bearing seal
Remove the antifriction bearing
Remove the bearing housing
Remove the end shield (bracket)
Remove the fan guide
Remove the rotor from the stator
Dismantle the air cooler box, if necessary
FLOW CHART
STEP
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
Remarks
*A distance equal to the rotor’slength may be required at bothends of the motor drive end andNon drive end.
(93)
14
50 << INSTRUCTIONS FOR THREE-PHASE INDUCTION MOTORS
14.8 HRS7 Horizontal-type Motor Construction
Appendix
Fig. 8 HRS7 Horizontal-type Motor Construction (WOUND ROTOR)
*Disassembly and reassembly of HRS7 Type induction motor with antifriction bearingNotes: 1. Unless otherwise specified, reassembly of motors may be accomplished by reversing the disassembly steps.
2. Steps 7 to 11 are applied to both the Drive end and Non-drive end of the motors.
FLOW CHART
STEP
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
Remarks
*A distance equal to the rotor’slength may be required at bothends of the motor drive end andNon drive end.
*Heat the fan hub to approx.80 ~ 100 both for easyassembly and for removal
Uncouple, and perfom an alignment check at the motorand the drive machine
Lift the motor off and shift it to make enough room tomove the rotor
Remove the bolts securing the air seal and rest each parton the rotor shaft
Dismantle the connection box of the frame, if acc’y attached(BTD, grease pipe, secondary t/box cable, etc.)
Remove the external bearing seal and slinger installed onthe bearing housing
Remove the antifriction bearing
Remove the bearing housing
Remove the end-shield with brush holder
Remove the end-shield with fan guide
Remove the internal fan
Remove the fan guide
Remove the rotor from the stator
(94)
14.9 HLB5 Horizontal-type Motor Construction
Instruction Manual >> 51
THREE-PHASE INDUCTION MOTORS
Fig. 9 HLB5 Horizontal-type Motor Construction (SQUIRREL CAGE)
*Disassembly and reassembly of HLB5 Type induction motor with antifriction bearingNotes: 1. Unless otherwise specified, reassembly of motors may be accomplished by reversing the disassembly steps.
2. Steps 7 to 11 are applied to both the Drive end and Non-drive end of the motors.
FLOW CHART
STEP
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
Remarks
*A distance equal to the rotor’slength may be required at bothends of the motor drive end andNon drive end.
*Heat the fan hub to approx.80 ~ 100 both for easyassembly and for removal
Uncouple, and perfom an alignment check at the motorand the drive machine
Lift the motor off and shift it to make enough room tomove the rotor
Remove the bolts securing the air seal and rest each parton the rotor shaft
Dismantle the connection box of the frame, if acc’y attached(BTD, grease pipe, etc.)
Remove the external bearing seal and slinger installed onthe bearing housing
Remove the fan cover
Remove the external fan
Remove the bracket
Remove the antifriction bearing
Remove the internal bearing seal
Remove the rotor from the stator
(95)
14
52 << INSTRUCTIONS FOR THREE-PHASE INDUCTION MOTORS
14.10 HRQ7 Horizontal-type Motor Construction
Appendix
Fig. 10 HRQ7 Horizontal-type Motor Construction (SQUIRREL CAGE)
*Disassembly and reassembly of HRQ7 Type induction motor with antifriction bearingNotes: 1. Unless otherwise specified, reassembly of motors may be accomplished by reversing the disassembly steps.
2. Steps 5 to 11 are applied to both the Drive end and Non-drive end of the motors.
Uncouple, and perfom an alignment check at the motorand the drive machine
Lift the motor off and shift it to make enough room tomove the rotor
Remove the bolts securing the air seal and rest each parton the rotor shaft
Dismantle the connection box of the frame, if acc’y attached(BTD, grease pipe, etc.)
Remove the external bearing seal and slinger installed onthe bearing housing
Remove the fan cover
Remove the external fan
Remove the bearing housing
Remove the antifriction bearing
Remove the intermal bearing seal
Remove the end shield (bracket)
Remove the fan guide
Remove the rotor from the stator
FLOW CHART
STEP
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
Remarks
*A distance equal to the rotor’slength may be required at bothends of the motor drive end andNon drive end.
*Heat the fan hub to approx.80 ~ 100 both for easyassembly and for removal
Dismantle the air cooler box, if necessary
(96)
14.11 HRQ7 (Sleeve Bearing) Horizontal-type Motor Construction
Instruction Manual >> 53
THREE-PHASE INDUCTION MOTORS
Fig. 11 HRQ7 (Sleeve Bearing) Horizontal-type Motor Construction (SQUIRREL CAGE)
*Disassembly and reassembly of HRQ7 Type induction motor with antifriction bearingNotes: 1. Unless otherwise specified, reassembly of motors may be accomplished by reversing the disassembly steps.
2. Steps 5 to 11 are applied to both the Drive end and Non-drive end of the motors.
Uncouple, and perfom an alignment check at the motorand the drive machine
Lift the motor off and shift it to make enough room tomove the rotor
Remove the bolts securing the air seal and rest each parton the rotor shaft
Dismantle the connection box of the frame, if acc’y attached(BTD, grease pipe, etc.)
Remove the external bearing seal and slinger installed onthe bearing housing
Remove the fan cover
Remove the external fan
Remove the bearing housing
Remove the antifriction bearing
Remove the intermal bearing seal
Remove the end shield (bracket)
Remove the fan guide
Remove the rotor from the stator
FLOW CHART
STEP
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
Remarks
*A distance equal to the rotor’slength may be required at bothends of the motor drive end andNon drive end.
*Heat the fan hub to approx.80 ~ 100 both for easyassembly and for removal
Dismantle the air cooler box, if necessary
(97)
15
54 << INSTRUCTIONS FOR THREE-PHASE INDUCTION MOTORS
Memo
Memo
(98)
Instruction Manual >> 55
THREE-PHASE INDUCTION MOTORS
Memo
(99)
HEAD OFFICE 1 JEONHA-DONG, DONG-GU, ULSAN, KOREA TEL. 82-52-230-6601~6 FAX. 82-52-230-6995
SEOUL HYUNDAI B/D, 140-2, GYE-DONG, JONGNO-GU, SEOUL, KOREA (Sales & Marketing) TEL. 82-2-746-7627, 8473 FAX. 82-2-746-7648
ORLANDO 3452 LAKE LYNDA DRIVE, SUITE 110, ORLANDO, FLORIDA 32817 U.S.A.TEL. 1-407-249-7350 FAX.1-407-275-4940
LONDON 11TH FL., ST. MARTIN’S HOUSE, 1 HAMMERSMITH GROVE, LONDON W6 ONB, U.K. TEL. 44-208-600-7127, 8741-0501 FAX.44-208-741-5620
TOKYO 8TH FL., YURAKUCHO DENKI BLDG.1-7-1, YURAKU-CHO, CHIYODA-GU, TOKYO, JAPAN 100-0006TEL. 81-3-3212-2076, 3215-7159 FAX. 81-3-3211-2093
CAIRO APARTMENT NO. 503, 5TH FL., BLDG. NO. 7 BLOCK 2, 9TH DIVISION, EL-NASR ROAD, NEW MAADI, CAIRO, EGYPTTEL. 20-2-520-0148~9 FAX. 20-2-754-7528
SOFIA 1271, SOFIA 41, ROJEN BLVD. BULGARIATEL. 359-2-938-1068 FAX. 359-2-936-0742
www.hyundai-elec.com
HH
IS-W
Z-R
E-006-01 2004. 1 D
esigned by Design K
orea
(100)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
i
SECTION 2. MECHANICAL SEAL
(101)
John Crane EAA Engineered Sealing Systems
GB
Instruction Manual Reference No.: IOM-K/02408
Mechanical Seal Type 1648
John Crane Assembly Code.: 0600/1648/01/K02408 John Crane Eng. Ref. No.: John Crane Order No.: Customer: HHI Customer Order No.: Plant Owner/Site/Unit HNON TRACH CCPP1 Plant Item Number
s
This seal may only be installed, commissioned and maintained by an authorised plant machinery
pecialist, paying close attention to these instructions and all other relevant regulations. Failure to do this relieves the manufacturer from any liability or warranties.
In the interest of continuous development, John Crane reserve the right to alter designs and specifications without prior notice.
For your nearest John Crane facility, please contact one of the locations below
John Crane International - Major Regional Centres North America Europe Middle East, Africa, Asia Latin America John Crane Inc. John Crane UK John Crane Middle East John Crane Brazil North America Buckingham House P.O Box 61040 Av. Paulista, 475 - 16 andar 6400 Oakton Street 361-366 Buckingham Ave Dubai Bela Vista Morton Grove Slough, England SL1 4LU United Arab Emirates 01311-980 Sao Paulo SP . Illinois 60053 USA Brazil Tel: 1- 847-967-2400 Tel: 44-1753-224000 Tel: 971-48839510 Tel: 55-11-3371-2500 Fax: 1-847-967-3915 Fax: 44-1753-224224 Fax: 971-4-883-7766 Fax: 55-11-3371-2599
Instruction Manual Author: John Crane Buckingham House Engineering 361 – 366 Buckingham Avenue Tel: 44-1753 224000 Slough, Berks. SL1 4LU Fax: 44-1753 224150
(102)
Instruction Manual
Type
Page: 2 of: 11
Edition 5
Contents 1 General ........................................................................................................3
1.1 Introduction...................................................................................................3 1.2 Range of Application ....................................................................................3 1.3 Declaration of Incorporation (98/37/EC) .......................................................3 1.4 EU “ATEX” Directive (94/9/EC).....................................................................3
2 Safety & Environment ................................................................................4 2.1 Symbols........................................................................................................4 2.2 Safety Instructions ........................................................................................4 2.3 Environmental Aspects.................................................................................5
2.3.1 Company policy extract ......................................................................5 2.3.2 Recycling ............................................................................................5
3 Transportation and Storage ......................................................................6 4 Description of the Mechanical Seal ..........................................................6
4.1 Construction .................................................................................................6 4.2 Function........................................................................................................7 4.3 Operating Conditions....................................................................................7
5 Installation and Removal ...........................................................................7 5.1 Preparation for Fitting ...................................................................................7 5.2 Installation Tolerances..................................................................................7
5.2.1 Shape and Positional Tolerances .......................................................7 5.2.2 Surface Finish.....................................................................................7
5.3 Installation ....................................................................................................8 5.3.1 Tightening Torques.............................................................................9 5.3.2 Lubricants ...........................................................................................9
5.4 Seal Removal ...............................................................................................9
6 Commissioning and Decommissioning .................................................10 7 Maintenance/Repair..................................................................................11
7.1 Maintenance ...............................................................................................11 7.2 Reconditioning............................................................................................11 7.3 Spare Parts.................................................................................................11
8 Malfunction, Causes and Correction ......................................................11 9 Accompanying Documents .....................................................................11
(103)
Instruction Manual
Type
Page: 3 of: 11
Edition 5
1 General
1.1 Introduction This Instruction Manual is provided to familiarise the user with the seal arrangement and its use. The Instructions must be read and applied whenever work is done on the seal, and must be available to the operating and maintenance personnel.
These instructions will help to avoid danger and increase reliability.
John Crane reserve the right to change the seal and specifications described in this manual where it is necessary for technical development and without prior notice. The latest issue supersedes all previous versions.
1.2 Range of Application Mechanical sealing systems are used for the sealing of rotating shafts; they must be operated within their performance limits (see
4.3 Operating Conditions).
If the process or operating conditions are changed from those referenced in this Manual, John Crane must be consulted to ensure the sealing system is safe.
1.3 Declaration of Incorporation (98/37/EC)
Only relevant to equipment operating in EEC countries, see below.
1.4 EU “ATEX” Directive (94/9/EC)
These instructions are intended for use with the mechanical seals operating in Equipment Group II, category 2GD and 3GD.
John Crane UK Engineered Sealing Systems Buckingham House 361-366 Buckingham Ave. Slough Berks, SL1 4LU Phone (01753) 224000 Fax (01753) 224150
Declaration of Incorporation
E.C. Machinery Directive (98/37/EC)
Section 1.0 - Machinery Description:
Type 1648 John Crane Assembly Code.: 0600/1648/01/K02408
Section 2.0 - Applicable Harmonised Standards:
EN 292, EN 809, EN 1127-1, EN 13463-1, EN 13463-5
Section 3.0 - Declaration:
We John Crane, declare that the seal assembly described in Section 1.0 above is intended to be incorporated into other machinery or assembled with other machinery to constitute machinery as covered by this Directive. The seal assembly, covered by this declaration must not be put into service until the machinery into which it is to be incorporated has been declared in conformity with the provisions of the Directive.
Paul Martin
Director of Design Engineering Services Date February 29, 2008. (104)
Instruction Manual
Type
Page: 4 of: 11
Edition 5
2 Safety & Environment The safety notes refer to the arrangement supplied. They must be used in conjunction with the relevant safety regulations for the machine, auxiliary equipment, plant and sealed fluid.
2.1 Symbols The following symbols are used in this Instruction Manual to highlight information of particular importance:
Danger Mandatory instructions designed to prevent personal injury or extensive damage.
ATTENTION Special instructions or information to avoid damage to the seal or its surroundings.
Note: Information for easy installation and efficient operation.
Environmental Note
2.2 Safety Instructions
ATTENTION Every working practice which compromises safety is to be avoided.
In the event of an operating problem the machinery must be switched off immediately and made safe! Problems must be solved promptly.
A slight leakage will occur during normal seal operation. Depending on the duty, this leakage can appear as a gas, a liquid or a solid. In case of a worn or defective seal the leakage will increase. The leakage may be hazardous or toxic, and a safe collection system is required.
Hot surfaces have to be protected against accidental contact.
In order to avoid unforeseen hazards do not make unauthorised changes to the fluid to be sealed, the specified duty, or the seal parts.
ATTENTION
Some mechanical seals are used in conjunction with an ancillary support system; this is clarified by the flush plan description described on the seal arrangement drawing. It is important for the safe function of the seal that the support system is assembled and incorporated into the equipment before operation. This Instruction Manual should be read in conjunction with the appropriate documentation for auxiliary systems and rotating equipment.
Alarm systems are often included in the ancillary support system and the operator must ensure appropriate action is taken promptly in the event of an alarm.
Maintenance with steel tools must be avoided in the presence of substances classed as explosive group IIc according to EN50014.
If the equipment is being used in an ATEX zone 21 or 22 regular cleaning of dust from exterior surfaces is required.
It is dangerous to smoke while handling products made from PTFE.
Compounds containing PTFE, fluorocarbons and perfluoroelastomers should never be burnt as the fumes and residues are highly toxic. If this accidentally occurs protective equipment should be worn as hydrofluoric acid may be present.
Follow the local relevant guidelines for the safe and environmentally friendly disposal of assembly lubricants, supplied fluids and scrapped components.
(105)
Instruction Manual
Type
Page: 5 of: 11
Edition 5
2.3 Environmental Aspects
2.3.1 Company policy extract “It is the policy of John Crane to manage its business activities in an environmentally responsible manner, comply with all relevant laws and regulations, prevent pollution, and continually improve its environmental performance, certification to the latest issue of ISO 14001 ensures compliance.” John Crane adopts the ‘Design For the Environment’ (DFE) principle in making this product. Using this product will benefit the environment directly by:
Reducing waste of precious resources through decreasing the risk of leakage & minimising energy consumption
Preventing pollution through controlling harmful emissions to the atmosphere
Preserving valuable materials resources through the re-use of these high quality durable seals due to their ability to be refurbished.
2.3.2 Recycling
Product refurbishment This product has been designed for potential reuse. Depending on its post operation condition, the seal may be repaired or rebuilt for further use. All metal components may be reused. The Primary & Mating Rings may be relapped and reused. Drive screws and springs are replaced. O-Rings must be replaced. Please consult John Crane for assessment of seal condition and its potential re-conditioning. Only qualified John Crane Engineers at recognised John Crane Customer Support Units should carry out re-conditioning & repair of this product
Disposal When the product is considered to be beyond economical repair and potential reuse, it should be disposed of by environmentally beneficial means. The product can be disassembled with ease.
Scrapped components These should be handled with extra care due to possible contamination. They should be recycled through local industrial recycling plants. Special materials Follow the local relevant guidelines for the environmentally friendly disposal of assembly lubricants, supplied fluids and scrapped components. Compounds containing PTFE, fluorocarbons and perfluoroelastomers should never be burned as the fumes and residues are highly toxic. Please refer to Safety Instructions- Section 2.2.
Packaging All packaging materials used are made from recyclable, environmentally friendly materials.
When in doubt or for further information and advice on this subject, please consult John Crane.
(106)
Instruction Manual
Type
Page: 6 of: 11
Edition 5
3 Transportation and Storage Transport and store the seal in its original packaging.
To ensure seals remain in good condition they should be stored in the following environment:
• dry and dust-free
• ventilated at room temperature
• protected from direct effects of heat and ultraviolet light
• elastomers require replacement after 24 months except fluoro- and perfluoro-elastomers that require replacement after 60 months
• for further information on elastomer storage refer to ISO 2230
If used seal parts are to be transported to the manufacturer or a third party they have to be cleaned, decontaminated and require safe handling instructions externally attached.
For additional information on transportation and storage refer to John Crane document I-Storage-E.
The sealing system does not require any preservatives, it is resistant against all normal environmental conditions.
If any machine, with an installed seal, has been stored with preservatives before putting it back into operation then seal must be removed, cleaned and dried. Particular attention must be applied to the cleanliness of the faces and condition of the elastomers.
Ensure preservatives and cleaning agents do not affect the elastomers. Once the seal is fitted on the equipment and the position is set using setting devices do
not re-engage them for transportation and storage.
4 Description of the Mechanical Seal
4.1 Construction All mechanical seals are composed of the same basic elements (also refer to the installation drawing in Section 9).
Fig. 1: Typical Pusher Mechanical Seal Primary seal components
a) primary ring b) mating ring
Secondary seal component
c) dynamic seal d) static seal
Spring component
e) multiple spring
Drive and retaining components f) retainer
ATTENTION Fig. 2: Typical Metal Bellows Mechanical Seal Primary seal components
ATTENTION a) primary ring b) mating ring
Secondary seal component
c) static seal
d) static seal
Spring component
e) metals bellows
Drive and retaining components f)compression collar
(107)
Instruction Manual
Type
Page: 7 of: 11
Edition 5
4.2 Function The hydraulic pressure and the spring force press the rotating and axially flexible primary ring against the stationary mating ring. Wear at the primary seal is minimised by a very thin lubricating film. Lubrication is provided by the sealed fluid; in the case of gas, the mechanism is usually enhanced by spiral grooves. The leakage is minimised by flat lapping to a fine surface finish.
Without the intended lubrication the seal face temperatures will
PaIw
4•
•
•
•
•
•
•
•
1,5 mm
1 mmRadius
20°
Fig. 3
5.2 Installation Tolerances The performance and reliability of the sealing
increase and may provide an ignition source in a potentially explosive atmosphere.
roper operation of the equipment and dherence to the recommendations in this nstruction Manual and associated manuals ill prevent this occuring.
.3 Operating Conditions Refer to data recorded on drawing in
Section 9.
If no data available refer to John Crane’s published Data Sheet specific to the seal type used, or consult John Crane direct.
Maximum static seal chamber pressure is equal to the maximum dynamic pressure rating – see published data sheet.
Maximum Surface Temperature, zones 1, 2, 21 and 22. (ATEX, 94/9/EC only) = 85 °C
5 Installation and Removal
5.1 Preparation for Fitting Check whether the seal is complete, clean
and undamaged.
Clean all machinery abutments, sealing and fitting surfaces (use only absorbent and fluff-free polishing cloth for cleaning).
Remove any protective coatings.
Check all relevant machinery dimensions, and that correct chamfers (see fig. 3) exist on all leading edges. Refer to drawing in annex.
system is influenced by the installation tolerances. Ensure that the tolerances do not exceed the required limits.
5.2.1 Shape and Positional Tolerances
Component Type Tolerance
Shaft to Housing Squareness 0.08 mm*
Shaft to Housing Concentricity 0.13 mm
static ± 0.25 mm**Shaft End Float Axial _______________________________
dynamic ± 0.04 mm
Shaft or Sleeve Ovality 0.05 mm
Housing to Shaft Runout 0.05 mm* API requires <0.5 µm/mm of chamber bore, FIM. **Figure stated on general arrangement drawing (Section 9) should take precedence
5.2.2 Surface Finish
Seal Type Value
dynamic O-ring 0.3/0.8 µm Ra (ground or polished)
static O-ring <1.6 µm Ra (turned)
elastomer bellows 0.8/1.2 µm Ra (turned)
PTFE bellows 0.8/1.2 µm Ra (turned)
dynamic and static wedge
0.1/0.25 µm Ra (polished)
(108)
Instruction Manual
Type
Page: 8 of: 11
Edition 5
5.3 Installation Carefully protect the lapped sealing surfaces of primary
and mating rings during fitting. Minor damages to sensitive surfaces, such as scratches and chips, reduce the sealing effectiveness of the mechanical seal.
ATTENTION
ATTENTION
Carry out fitting according to the installation drawing (section 9) and with the following procedure: • Maintain cleanliness during fitting.
• Lubricate shaft with a suitable fluid in the installation area.
• Lubricate the shaft and housing sealing components with a suitable fluid (see Section 5.3.2), also ensuring they maintain their correct position during fitting.
EP-elastomer O-rings and bellows are not resistant to mineral oil or grease.
Silicone-elastomer O-rings are not resistant to silicone oil or grease.
When the sleeve is fixed to the shaft by shrink disc, the area under the clamp must be kept free of lubricant.
The seal faces should not be lubricated with oil or grease as this may prevent introduction of the sealed fluid in operation, leading to overheating and failures.
• Ensure the seal arrangement is orientated correctly, according to the housing, pipework, and shaft connections (e.g. studs, keyways, pins and drive holes).
On double-ended pumps ensure the drive-end and non-drive-end seals are appropriately selected
• Slide the seal assembly over the shaft and into position.
If a flexible graphite seal is used as the shaft/sleeve seal remove this before sliding the seal assembly into position. Follow-up by inserting the flexible graphite sealsand the follower.
• Tighten bolts, nuts and fasteners evenly to the torque levels indicated in the installation drawing. If not indicated refer to Section 5.3.1. Torque levels for gland plate studs or bolts must conform to those given in the relevant rotating equipment manual.
ATTENTION
For high temperature metal bellows seals eg, 1604, 2609,
3609 etc the pump shaft must be dimpled to ensure adaquate drive. Bolt the seal assembly to the pump back plate and finish assemble the pump so that the shaft is in its final position relative to the casing. In the case of hot pumps where thermal growth is known to be a problem, allowance can be made by offsetting the shaft by the required amount. Remove the collar set screws and using a drill of clearance size, drill through to mark the centre of each screw. The shank of the drill should be protected by masking tape to avoid damaging the threads. Remove the seal assembly and using a drill 2mm larger, dimple the shaft to the full diameter. Carefully remove all burrs to avoid damaging the seal sleeve.
ATTENTION
ATTENTION
ATTENTION
ATTENTION If setting devices are used, they must be removed after the seal is fixed securely in place in its final position. They can then be disengaged and fixed or appropriately stored.
ATTENTION
On double ended pumps the drive collar set-screws or sleeve drive component must be tightened after the bearing brackets have been fitted. When the seal is radially located from the shaft (no gland spigot) the gland nuts must also be tightened after the bearing brackets have been fitted.
ATTENTION
• If possible check for freedom of movement by hand turning the shaft.
Check on all pipework, hoses and fittings: ATTENTION • Correct location, alignment and support
(109)
Instruction Manual
Type
Page: 9 of: 11
Edition 5
• Correct connections. Refer to installation drawing (see Section 9) and relevant rotating equipment manual.
• Correct specification
• All unused connections must be plugged with the as supplied metal pipe plugs. Check whether drain connection should be open or piped to a collection area.
• All pipework on liquid barrier/buffer systems and cooling circuits are orientated to ensure effective venting.
• Lack of damage and leaks
5.3.1 Tightening Torques
Tightening Torques [Nm] (u 0.125 lubricated)
Socket Socket Socket Thread Size Setscrew Setscrew Setscrew
Size Code (ASTM A453-Gr
(316) (High Tensile Steel (14.9)
660 C) Part Code Part Code Part Code Size/305/712 Size/305/001 Size/305/050
M4 77** 1.5 2.3 M5 78** 3 4.5 M6 79** 4 7.5 M8 80** 11 18 M10 81** 30 16 36 M12 82** 50 40 60 M14 83** M16 84** M20 86** 1/4 - 20 35** 6 4.5 8.8 5/16 - 18 36** 10 17.5 3/8 - 16 37** 13.5 30 7/16 - 14 38** 32 48 1/2 - 13 39** 45 69
Thread Size Steel Screw Steel Screw Size Code (Class 12.9) (316 A4-70)
Part Code Part Code Size/301/050 Size/310/001
M4 77** 4.5 2 M5 78** 9.4 4 M6 79** 16 6,5 M8 80** 38 16 M10 81** 77 32 M12 82** 135 55 M14 83** 215 90 M16 84** 340 140 M20 86** 663 275
5.3.2 Lubricants The following lubricants are recommended by John Crane
Lubricant Note elastomeric O-rings except silicon rubber
Silicone grease, (Chloride Free) potable water or glycerine
Apply very thinly by hand
O-rings of silicone rubber
PTFE paste Apply very thinly by hand
Bolts, screws, nuts and fasteners
Molybdenum or nickel based anti-seize compound
Apply with brush or by hand
Elastomer bellows on shaft
Potable water or glycerine
Apply with sprayer
5.4 Seal Removal Removal is essentially the reverse procedure to installation.
Work on the seal must only be carried out when the machine is stationary, and secured against any unforeseen start-up.
Before the seal is removed the seal chamber or machinery must be depressurised and drained.
If the equipment has been used on toxic or hazardous fluids, ensure all precautions are taken to avoid personnel hazards, such as correct
decontamination. Note, fluid is often trapped during draining and may exist outside the seal. The relevant rotating equipment manual should be consulted to check for any special precautions.
(110)
Instruction Manual
Type
Page: 10 of: 11
Edition 5
ATTENTION
ATTENTION
6 Commissioning and Decommissioning
Note before start-up: • ensure transit plugs are removed and
seal drain connections are correctly piped or open.
• ensure valves controlling circulation, flush and quench are correctly positioned.
If a heat exchanger is included in the support system and isolating valves are used in the coolant supply, a pressure relief valve should be incorporated between the isolating valves.
• ensure the seal chamber and/or barrier, buffer and cooling circuits are fully vented. (Not necessary on 2800 range of seals).
With liquid lubricated seals avoid dry running under any circumstances, as it will damage the seal. (Not relevant to 2800 range of seals and dry containment seals).
For hot duties (above 150°C) ensure pump has been brought up to operating temperature prior to start-up. Rapid axial differential thermal growth between shaft and pump casing could result in seal malfunction.
• If the seal is unidirectional, check the correct rotation direction.
Check the correct setting and operation of electrical warning systems associated with seal operation.
Before start-up, ensure that all personnel and assembly equipment have been moved to a safe distance, that guards are fitted and there is no contact with rotating parts.
To meet ATEX equipment specification it is important to ensure seal flush rates, temperatures, and cooling water flow rates are to specification.
In case of pressurised double seals note:
• The sealant system must be pressurised before priming the machine.
• For wet seals refer to the system drawing for barrier pressure settings. If not given the minimum barrier pressure must
be 1 bar plus 10 % above the maximum process seal chamber pressure. The maximum barrier pressure should be within the published seal operational limits.
• For gas seals the barrier pressure must be (2 bar for 2800ER, 3 bar for 2800BD and 5 bar for 2800HP) above the maximum process seal chamber pressure, unless other values have been given.
• Use a suitable and clean medium as the barrier fluid. This must have an auto ignition temperature above the maximum operating temperature of the pump.
• When using thermosyphon systems, ensure that the circuit minimises flow restrictions and can be effectively vented. Contact John Crane for more information.
ATTENTION
When the machine is stopped, the seal system pressure should be maintained until the machine itself is unpressurised.
Notes on decommissioning see Removal, Section 5.4.
ATTENTION
If a water test has been applied when flexible graphite seat/mating ring seals are used, they must be replaced or thoroughly dried before use on a hydrocarbon service.
(111)
Instruction Manual
Type
Page: 11 of: 11
Edition 5
7 Maintenance/Repair
7.1 Maintenance Carry out the following procedures for trouble free operation: Check daily:
• that the connections are leak free • seal leakage • barrier gas flow for 2800 range of
seals • Condition of alarm signals
in addition for double seals • barrier/buffer liquid level • barrier/buffer liquid temperature • barrier/buffer pressure
in addition for dry containment seals
• For dry contacting containment seals (S48SC, 48SC, SBOP & ECS) a monthly check with a 1.0 bar gas test is recommended.
• buffer gas flow when applied, check monthly
• Wear parts for dry contacting containment seals require replacement after 24000 hrs dynamic operation.
If buffer or barrier liquid systems need replenishment this should only be done with fill systems that exclude air ingress and/or prevent gas leakage to the atmosphere.
7.2 Reconditioning The mechanical seal will always require reconditions after operation. In order to maximise reliability, and minimise safety risks, it is strongly recommended that used seals are returned to John Crane for rebuilding to as-new specification (essential for 2800 range of seals). Alternatively ask for John Crane service personnel to visit site.
It is the responsibility of the equipment user to ensure that any parts being sent to a third party have appropriate safe handling instructions or decontamination
certification externally attached to the package. Without this information there may be a refusal to handle the goods. Rebuilding seals to as-new specifications must be carried out by qualified personnel.
Note: It is recommended that a low pressure integrity test is carried out after repair and before installation on the equipment.
7.3 Spare Parts Only John Crane spare parts should be used to recondition seals.
It is advised to stock on site a spare seal cartridge or the minimum replacement parts shown on the installation drawing (Section 9). The order codes for spare parts can be found in the parts list on the installation drawing. (Section 9). In the case of the 2800 range of seals only complete cartridges should be stored.
The following data is necessary for spare part orders: seal assembly code part description component code quantity.
8 Malfunction, Causes and Correction
John Crane must be consulted in the event of any malfunction of the sealing installation or sealing system. Excessive leakage rate, premature failure, high relative temperatures are all considered examples of abnormal malfunction.
9 Accompanying Documents Drawing K/02408
(112)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
1
SECTION 3. GEAR COUPLING Contents 1.0 Structure --------------------------------------------------------------------------------------- 2
2.0 Installation ------------------------------------------------------------------------------------- 3
3.0 Lubrication ------------------------------------------------------------------------------------- 5
4.0 Maintenance ----------------------------------------------------------------------------------- 6
(113)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
2
1. STRUCTURE
NR Gear coupling consists of the internal spur gears in its sleeves and the external spur gears with crowned teeth on its hubs, both of which are in mesh when assembled.
NARA GEAR COUPLINGS
G SERIES 1. Sleeve A 2. Sleeve B 3. Two hubs 4. Reamer bolts sets 5. Lubrication plugs 6. Side 0-Rings 7. Center 0-Ring
CROWNED HUB TEETH (Pitch diameter on a curve type)
Since these spur gears are so designed as to employ an involute tooth profile and to have a specialform on the top and bottom lands of their teeth, taking account of the tilting and lubrication, and equal speed rotation and smooth power transmission can be obtained even when a little tiltingsoccur between the sleeves and the hubs .
(114)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
3
2. INSTALLATION
2.1 ASSEMBLING
1) Ensure all parts are clean.
2) Apply a light coat of grease to the 0-Rings and insert 0-Rings into grooves of sleeves.
3) Place sleeves over shaft ends. Care should be taken not to damage 0-Rings.
4) Install hub on their respective shafts with the longest hub end towards shaft end or towards machine bearing depending on the type. Hub faces have to be flush with shaft end.
5) Install units to be connected in place and check the spacing between hubs. See below tabulation for correct hub spacing. (Table. 1)
6) Align the two shafts, check alignment using a dial gauge. (Fig.1) (Table.2)
7) Coat hub and sleeve gearings with grease and slide sleeves over hubs.
8) Insert reamer bolts into bolt holes of sleeve and sleeve or, sleeve and flange.
9) Remove both lube plugs of one sleeve and add grease in sufficient amount to overflow with lubricant holes in horizontal position. Re-install the 2 plugs.
10) In case of doubt, please consult us.
2.2 DISASSEMBLING AND INSPECTION
1) Remove bolts.
2) Slide sleeves off hubs.
3) Control gearing and sealing.
4) Control alignment.
5) In case of doubt, please consult us.
2.3 CENTERING
1) SPACING BETWEEN HUBS AND ALLOWABLE ERROR
(115)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
4
TABLE 1.
2) ALIGNMENT
FIG.1
SIZE 125 140 160 180 200 224 250 280 315 355 400
GAP 8 8 10 10 10 12 12 14 14 16 16
∆d -0.5 ~ 2.5
-0.5 ~ 2.5
-0.5 ~ 3.0
-0.5~ 3.0
-0.5~ 3.0
-0.5~ 4.0
-0.5~ 4.0
-0.5~ 4.5
-0.5 ~ 5.5
-0.5 ~ 5.5
-0.5~ 6.5
(116)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
5
TABLE. 2
3. LUBRICATION
3.1 GREASE FEEDING
When assembling, pack the coupling sleeve and the coupling hub with the recommended grease until their become invisible, and after tightening the reamer bolts, add the grease through the oil plug hole using a grease gun, etc. (Fig.2)
FIG. 2
HOW TO APPLY GREASE
ALIGNMENT ALIGNMENT SIZE
OFF-SET ANGULAR SIZE
OFF-SET ANGULAR
125 BELOW 0.03 BELOW 0.06 250 BELOW 0.07 BELOW 0.14
140 BELOW 0.04 BELOW 0.06 280 BELOW 0.08 BELOW 0.16
160 BELOW 0.04 BELOW 0.08 315 BELOW 0.10 BELOW 0.19
180 BELOW 0.05 BELOW 0.09 355 BELOW 0.11 BELOW 0.21
200 BELOW 0.05 BELOW 0.10 400 BELOW 0.11 BELOW 0.24
224 BELOW 0.06 BELOW 0.12
(117)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
6
3.2 RECOMMENDED LUBRICANTS AND QUANTITY
1) Recommended lubricants
TABLE. 3
2) Lubricant quantity list
TABLE.4
4. MAINTENANCE After about 3 months of the initial operation, feed fresh oil or grease to the coupling after thoroughlyremoving the old oil or old grease and abrasion particles from the inside of the coupling by means of disassembly, and thereafter add or change the oil or grease using the plug hole every 6 months (every 4000 hours).
Makers Grease
Esso Pen-o-led EP 35
Shell Alvania EP grease 1
Caltex Multifak EP 1
Mobil Sovarex L O
Grease(gf) Size
Upper Lower
250 390 265
280 500 345
315 750 500
355 900 600
400 1350 900
Grease(gf) Size
Upper Lower
125 50 35
140 70 50
160 90 65
180 130 90
200 180 120
224 270 180
(118)
PETRO VIETNAM GPPMB
OPERATION AND MAINTENANCE MANUAL
FOR CONDENSATE EXTRACTION PUMPS
abcd POWER SYSTEMS
7
1) Remove both plugs of one sleeve.
2) Position lube holes at horizontal and by means of a grease gun, force grease into grease flows one hole until clean out of the opposite hole.
3) Re-install the plugs.
(119)
Owner’s Consultants
ESB International
Owner
PETRO VIETNAM GPPMB
PECC2
EPC Contractor
LILAMA – CC1 CONSORTIUM
Issued by
LILAMA CORPORATION – HYUNDAI ENGINEERING
Subcontractor
abcd
ALSTOM (Switzerland) Ltd.
Project
NHON TRACH 1 CCPP PROJECT
Owner’s Identification No. EPC Contractor Identification No.
ALSTOM Document Code NHT/01/M/-------B20/DS/001
Revision History
Rev. Revision Date Created by Checked by Approved by Description
A 25.04.2007 D.E.YANG J.W.SHIN Y.H.KIM First issue
B 10.05.2007 D.E.YANG J.W.SHIN Y.H.KIM 2nd issue
C 10.04.2008 D.E.YANG J.W.SHIN K.R.KIM Title page updated
Description latest Revision:
DATA SHEET FOR CONDENSATE EXTRACTION PUMPS © ALSTOM 2007. All rights reserved.
(120)
Enclosure D1 Rev.B
. Originator ALSTOM Power Turbo-Systems
Identification number NHT/01/M/-------B20/ES/001
Rev. B
Date 10.05.2007
Lang.en
Sheet 1/3
© ALSTOM 2007. All rights reserved.
EQUIPMENT DESIGN DATA
1. GENERAL Plant : Nhon Trach 1 System / component : Condensate Extraction Pump Quantity x Duty : 3 x 50 % KKS No. :
Manufacturer : _Hyundai Heavy Industries Co., Ltd._________________ Type : _Vertical Can _________________
2. OPERATING DATA 2.1 Main Pump units rated normal normal normal normal normal normal runout Temperature °C 36.7 35.1 42.30 40.20 36.70 35.10 36.70 36.70 Vapour pressure
bara 0.06 0.06 0.08 0.07 0.06 0.06 0.06 0.06
Spec. gravity kg/m³ 994.37 994.94 992.21 993.05 994.37 994.94 994.87 994.37 Flow m³/h 334.87 298.51 280.59 247.25 309.54 271.37 324.02 402.00 Total head m 120 125.5 127.8 131.6 124 128.9 121.8 105.4 Speed rpm 1486 1486 1486 1486 1486 1486 1486 1486 Efficiency % 79 77.3 76 73.2 78 75 78.5 79 NPSH required *
m -0.5 -0.7 -0.7 -0.6 -0.7 -0.7 -0.5 0.4
*corresponding to erection level ( see Enclosure C2, section 2 )
2.4 Complete Unit
units rated max normal min flow Power required kW 138 145.2 127.8 81.6 Recommended driver power
kW 160 160 - -
2.5 Maximum / Minimum Data
Data units values ** remarks Max. flow * m³/h 402 contin. allowable Min. flow * m³/h 100 contin. allowable Shut-off head*** m 144.3 range f. constructional tolerance ±5% units sound pressure level
dBA 82 at 1 m distance
* for pumps with variable speed the max. and min. flow should be defined for any speed
(characteristic curve) ** all data at rated speed *** to be guaranteed
삭제됨: A
삭제됨: __________________
삭제됨: __________________
삭제됨: A
삭제됨: 19.01.2006
(121)
Enclosure D1 Rev.B
. Originator ALSTOM Power Turbo-Systems
Identification number NHT/01/M/-------B20/ES/001
Rev. B
Date 10.05.2007
Lang.en
Sheet 2/3
© ALSTOM 2007. All rights reserved.
3. CONSTRUCTION 3.2 Main Pump
Shaft position : [] vertical Nuber of stages : [] ___four______________________
Casing type : [ ] vertical split (ring section)
[] ___Diffuser___________________
Bearing type : [ ] ball [ ] roller [] sleeve & ball / roller [ ] sleeve & tilt segment [ ] _____________________________ Lubrication : [ ] grease [] oil / Thrust bearing [ ] circulating oil[] self pumped water / sleeve bearing
Thrust compensation : [ ] disc with mechanical/magnetic lifting device [] roller bearing [ ] drum & tilt segment Shaft seal : [ ] packing [ ] _____________________________ [] mechanical seal [ ] _____________________________ Rotation from motor to pump : [] clockwise [ ] counter clockwise Nozzle position suction : [ ] top [] side
discharge : [ ] top [] side 4. MATERIALS OF CONSTRUCTION 4.1 Main Pump
Casing : _____A48 CL.35B_______________ Stage casing : _____A48 CL.35B ______________ Shaft : _____A276 410H_________________ Shaft sleeve : _____A276 410H ________________ Impeller first stage : _____A743 CA15_________________ Impeller further stages : _____A48 CL.35B _________________ Casing ring : _____A743 CA40_________________ Diffuser (Bowl) : _____A48 CL.35B _______________ Balancing disc/drum : ________N/A_____________________ Gland (Mechanical seal) : _____A276 304____________________
5. DIMENSIONS
삭제됨: A
삭제됨: A
삭제됨: 19.01.2006
(122)
Enclosure D1 Rev.B
. Originator ALSTOM Power Turbo-Systems
Identification number NHT/01/M/-------B20/ES/001
Rev. B
Date 10.05.2007
Lang.en
Sheet 3/3
© ALSTOM 2007. All rights reserved.
5.1 Main Pump
Impeller diameter variations : minimum _255 / 330_____ (1st / Following) Design _265 / 342_____ maximum _275 / 355_____ Nozzle diameter/class suction : _DN 400_ / _CL. 150 discharge : _DN 250_ / _CL. 300
6. CUSTOMER DATA SHEETS
Enclosed Customer Data Sheets Part 4 Volume 1 Section 6.3
삭제됨: A
삭제됨: A
삭제됨: 19.01.2006
(123)
Enclosure D2 Rev.B
. Originator ALSTOM Power Turbo-Systems
Identification number NHT/01/M/-------B20/ES/001
Rev. B
Date 06.03.2007
Lang. en
Sheet 1/2
© ALSTOM 2007. All rights reserved.
ACCESSORIES DESIGN DATA 1. GENERAL
Plant : Nhon Trach 1 Accessories to : Condensate Extraction Pump KKS - No. :
Pump unit accessories : [] unit internal piping & valving [] electric motor [ ] standard coupling [] spacer coupling 2. UNIT INTERNAL PIPING AND VALVING Sealing water system : [] shaft sealing The entire unit internal sealing water piping and valving shall be provided with one common inlet connection. Venting system : [] suction nozzle [] pump head The entire unit internal venting piping and valving shall be provided with one common connection to the condenser vacuum system.
5. ELECTRIC MOTOR
Manufacturer : Hyundai Heavy Industries Co., Ltd. Type : squirrel cage induction Frame, size : _____315______________________ Position of shaft : [] vertical Rated motor power : ________160_______________ kW Frequency : _________50_______________ Hz Rated speed : ________1486_____________ rpm Rated voltage : _________400_______________V Service factor : _________1.1________________ - Efficiency at rated load : _________94________________ %
(100% load) Motor enclosure : [ ] IPW 24 [] IP 54 [] IP55 [ ] ___________________________ [ ] ODP [ ] WP I
삭제됨: A
삭제됨: A
삭제됨: 19.01.2006
(124)
Enclosure D2 Rev.B
. Originator ALSTOM Power Turbo-Systems
Identification number NHT/01/M/-------B20/ES/001
Rev. A
Date 19.01.2006
Lang. en
Sheet 2/2
© ALSTOM 2007. All rights reserved.
[] TEFC [ ] WP II [ ] ___________________________
Motor cooling : [] fan cooled [ ] water cooled Class of insulation : ___________F_____________________ Motor bearing : [] ball [] roller [ ] sleeve Lubrication : [] grease [ ] oil [ ] circulating oil Space heaters : [ ] no [] yes Rated voltage : __________230_______________ V
6. COUPLING
Intermediate Flexible Coupling
Manufacturer : _________Nara____________________ Type, size : ___Flexible gear, SVAM 224 (BE=200)_
삭제됨: A
(125)
PetrovietnamPECC2/ESBI
Nhon Trach 1 CCPP ProjectBidding Document
6-3. CONDENSER & OTHER ASSOCIATED PLANT continuedHogging Air Ejector (continued)
* MaterialsEjector bodyNozzle
* Characteristic curve Ref. No.
CONDENSATE EXTRACTION PUMPSPumps
* Description* Manufacturer Hyundai Heavy Industries Co., Ltd.* Place of Manufacturer South Korea* Number per unit 3* Type Vertical Can* Pumped fluid
Density kg/m3 994.41Temperature oC 36.6Viscosity cP -Vapour pressure bar a 0.06Performance requirements :
* Duty capacity m3/n 334.87* Suction head m -* Discharge head m -* Total head m 120* Efficiency % 79* NPSH required m -0.5 (at pump floor level)* NPSH available m 1.96 (at pump floor level)* Absorbed power kW 138
Pump description :* No of stages 4 (four)* Speed rpm syn. 1500* Type of pump bearings Thrust : Anti-friction
Radial : Carbon+NiMaterials of major parts :
* Casing A48 CL.35B* Bowl A48 CL.35B* Column A36+A53 GR.A* Impeller (1st / Following) A743 CA15 / A48 CL.35B* Shaft A276 410H* Shaft sleeves A276 410H
* Operating characteristic curve Ref. No. K320-CV2230
Signature:For and on behalf of:Date:
Part 4 - Volume 1 - Section 6Version 3 - July 2006 Page 1 of 2
(126)
PetrovietnamPECC2/ESBI
Nhon Trach 1 CCPP ProjectBidding Document
6-3. CONDENSER & OTHER ASSOCIATED PLANT continuedCONDENSATE EXTRACTION PUMPS continuedElectric motors
* Manufacturer H.H.I* Place of Manufacturer Korea* Type designation TEFC* Frame size 315* Enclosure classification (IP No.) IP55* Class of insulation F* Rated power kW 160* Speed rpm 1486
Direction of rotation facing driving end C.W* Voltage V 400* Efficiency at rated output (100% load) % 94* Power factor at rated output 0.89
Full load current A 276Max. starting current A 1794Min. starting voltage V 320Max. starting torque % FLT 80% / 210%
* Type of bearings Anti-FrictionBearing lubrication GreaseBearing size (dia τ length) mm -
Weight (per pump set)
Pump kg 2200Motor kg 1500Others kg 1680Total kg 5380
Signature:For and on behalf of:Date:
Part 4 - Volume 1 - Section 6Version 3 - July 2006 Page 2 of 2
(127)
Owner’s Consultants
ESB International
Owner
PETRO VIETNAM GPPMB
PECC2
EPC Contractor
LILAMA – CC1 CONSORTIUM
Issued by
LILAMA CORPORATION – HYUNDAI ENGINEERING
Subcontractor
abcd
ALSTOM (Switzerland) Ltd.
Project
NHON TRACH 1 CCPP PROJECT
Owner’s Identification No. EPC Contractor Identification No.
ALSTOM Document Code NHT/01/M/-------B20/MD/002
Revision History
Rev. Revision Date Created by Checked by Approved by Description
A 25.04.2007 D.E.YANG J.W.SHIN Y.H.KIM First issue
B 10.05.2007 D.E.YANG J.W.SHIN Y.H.KIM 2nd issue
C 10.04.2008 D.E.YANG J.W.SHIN Y.H.KIM Title page updated
Description latest Revision:
PERFORMANCE CURVE FOR CONDENSATE EXTRACTION PUMPS © ALSTOM 2007. All rights reserved.
(128)
(129)
(130)
(131)
(132)
(133)
(134)
Owner’s Consultants
ESB International
Owner
PETRO VIETNAM GPPMB
PECC2
EPC Contractor
LILAMA – CC1 CONSORTIUM
Issued by
LILAMA CORPORATION – HYUNDAI ENGINEERING
Subcontractor
abcd
ALSTOM (Switzerland) Ltd.
Project
NHON TRACH 1 CCPP PROJECT
Owner’s Identification No. EPC Contractor Identification No.
ALSTOM Document Code NHT/01/M/-------B20/DD/004
Revision History
Rev. Revision Date Created by Checked by Approved by Description
A 30.05.2007 D.E.YANG J.W.SHIN Y.H.KIM First issue
B 28.06.2007 D.E.YANG J.W.SHIN K.R.KIM 2nd issue
C 14.09.2007 D.E.YANG J.W.SHIN K.R.KIM 3rd issue
D 10.04.2008 D.E.YANG J.W.SHIN K.R.KIM Title page updated Description latest Revision:
MECHANICAL SEAL DETAIL DRAWING & DATA FOR CONDENSATE EXTRACTION PUMPS © ALSTOM 2007. All rights reserved.
(135)
(136)
(137)
(138)
Owner’s Consultants
ESB International
Owner
PETRO VIETNAM GPPMB
PECC2
EPC Contractor
LILAMA – CC1 CONSORTIUM
Issued by
LILAMA CORPORATION – HYUNDAI ENGINEERING
Subcontractor
abcd
ALSTOM (Switzerland) Ltd.
Project
NHON TRACH 1 CCPP PROJECT
Owner’s Identification No. EPC Contractor Identification No.
ALSTOM Document Code NHT/01/M/-------B20/DD/005
Revision History
Rev. Revision Date Created by Checked by Approved by Description
A 30.05.2007 D.E.YANG J.W.SHIN Y.H.KIM First issue
B 28.06.2007 D.E.YANG J.W.SHIN K.R.KIM 2nd issue
C 14.09.2007 D.E.YANG J.W.SHIN K.R.KIM 3rd issue
D 10.04.2008 D.E.YANG J.W.SHIN K.R.KIM Title page updated Description latest Revision:
COUPLING DETAIL DRAWING & DATA FOR CONDENSATE EXTRACTION PUMPS © ALSTOM 2007. All rights reserved.
(139)
(140)
(141)
Owner’s Consultants
ESB International
Owner PETRO VIETNAM
GPPMB
PECC2
EPC Contractor
LILAMA – CC1 CONSORTIUM
Issued by
LILAMA CORPORATION – HYUNDAI ENGINEERING
Subcontractor
abcd
ALSTOM (Switzerland) Ltd.
Project
NHON TRACH 1 CCPP PROJECT
Owner’s Identification No. EPC Contractor Identification No.
ALSTOM Document Code NHT/01/M/-------B20/LS/001
Revision History
Rev. Revision Date Created by Checked by Approved by Description
A 30.05.2007 D.E.YANG J.W.SHIN Y.H.KIM First issue
B 02.04.2008 D.E.YANG J.W.SHIN K.R.KIM 2nd issue
Description latest Revision:
SPARE AND WEAR PART LISTS FOR CONDENSATE EXTRACTION PUMPS
(142)
SPARE PART LIST (for start-up, commissioning and performance test)
KKS NO. 18LCB10AP001 18LCB20AP001 18LCB30AP001
EQUIP.NAME Main Condensate Pumps
Document Code : NHT/01/M/-------B20/LS/001 PROJECT NAME : Nhon Trach 1 CCPP, Vietnam REV. NO. : A SHEET NO. : 1 OF 5
Description QUANTITY (UNIT) PRICE (in USD CIF, Free site)SERIAL
NO. PARTS NAME
Material INSTALLED
PER ONE SETPROVIDED QUANTITY
MAKER'S NAME &
MODEL NO.
ADDRESS (CONTACT
POINT) UNIT PRICE
TOTAL PRICE
REMARKS (Erection item No.)
Φ4×1220ℓ EA EA 1 Rubber Ring
NBR 2 6
HHI 400x250VWDB4
ULSAN, KOREA (Hyundai Heavy
Industries Co., Ltd.) - -
M01B20V001
Φ4×1000ℓ EA EA 2 Rubber Ring
NBR 2 6
HHI 400x250VWDB4
ULSAN, KOREA (Hyundai Heavy
Industries Co., Ltd.) - -
M01B20V002
Φ4×905ℓ EA EA 3 Rubber Ring
NBR 2 6
HHI 400x250VWDB4
ULSAN, KOREA (Hyundai Heavy
Industries Co., Ltd.) - -
M01B20V003
Φ4×1220ℓ EA EA 4 Rubber Ring
NBR 1 3
HHI 400x250VWDB4
ULSAN, KOREA (Hyundai Heavy
Industries Co., Ltd.) - -
M01B20V004
Φ6×2702ℓ EA EA 5 Rubber Ring
NBR 1 3
HHI 400x250VWDB4
ULSAN, KOREA (Hyundai Heavy
Industries Co., Ltd.) - -
M01B20V005
- EA EA 6 Gasket
Non-asbestos 3 9
HHI 400x250VWDB4
ULSAN, KOREA (Hyundai Heavy
Industries Co., Ltd.) M01B20V006
(143)
SPARE PART LIST (for start-up, commissioning and performance test)
KKS NO. 18LCB10AP001 18LCB20AP001 18LCB30AP001
EQUIP.NAME Main Condensate Pumps
Document Code : NHT/01/M/-------B20/LS/001 PROJECT NAME : Nhon Trach 1 CCPP, Vietnam REV. NO. : A SHEET NO. : 2 OF 5
Description QUANTITY (UNIT) PRICE (in USD CIF, Free site)SERIAL
NO. PARTS NAME
Material INSTALLED
PER ONE SETPROVIDED QUANTITY
MAKER'S NAME &
MODEL NO.
ADDRESS (CONTACT
POINT) UNIT PRICE
TOTAL PRICE
REMARKS (Erection item No.)
P-345 EA EA 7 O-Ring
NBR 1 3
HHI 400x250VWDB4
ULSAN, KOREA (Hyundai Heavy
Industries Co., Ltd.) - -
M01B20V007
G-265 EA EA 8 O-Ring
NBR 1 3
HHI 400x250VWDB4
ULSAN, KOREA (Hyundai Heavy
Industries Co., Ltd.) - -
M01B20V008
(144)
RECOMMENDED SPARE PART LIST FOR 2 YEARS (OPTION)
ITEM NO. 18LCB10AP001 18LCB20AP001 18LCB30AP001
EQUIP.NAME Main Condensate Pumps
Document Code : NHT/01/M/-------B20/LS/001 PROJECT NAME : Nhon Trach 1 CCPP, Vietnam REV. NO. : A SHEET NO. : 3 OF 5
DRAWING NO QUANTITY (UNIT) PRICE (in USD CIF, Free site)SERIAL
NO. PARTS NAME
PARTS NO. INSTALLED
PER ONE SETPROVIDED QUANTITY
MAKER'S NAME &
MODEL NO.
ADDRESS (CONTACT
POINT) UNIT PRICE
TOTAL PRICE
REMARKS
NHT/01/M/-------B20/DD/001 SET SETS
1 Mechanical Seal 1893 1 1
HHI 400x250VWDB4
ULSAN, KOREA (Hyundai Heavy
Industries Co., Ltd.) - -
NHT/01/M/-------B20/DD/001 EA EA
2 Shaft Sleeve 1320A/B-1,2,3,4,
1320C 7 7
HHI 400x250VWDB4
ULSAN, KOREA (Hyundai Heavy
Industries Co., Ltd.) - -
NHT/01/M/-------B20/DD/001 EA EA
3 Sleeve Bearing 1540A/B-1,2,3,4,
1540C 7 7
HHI 400x250VWDB4
ULSAN, KOREA (Hyundai Heavy
Industries Co., Ltd.) - -
NHT/01/M/-------B20/DD/001 EA EA
4 Casing Ring 1230A/B/C 6 6
HHI 400x250VWDB4
ULSAN, KOREA (Hyundai Heavy
Industries Co., Ltd.) - -
NHT/01/M/-------B20/DD/001 EA EA
5 Thrust Bearing 1440 1 1
HHI 400x250VWDB4
ULSAN, KOREA (Hyundai Heavy
Industries Co., Ltd.) - -
(145)
RECOMMENDED SPARE PART LIST FOR 2 YEARS (OPTION)
ITEM NO. 18LCB10AP001 18LCB20AP001 18LCB30AP001
EQUIP.NAME Main Condensate Pumps
Document Code : NHT/01/M/-------B20/LS/001 PROJECT NAME : Nhon Trach 1 CCPP, Vietnam REV. NO. : A SHEET NO. : 4 OF 5
Description QUANTITY (UNIT) PRICE (in USD CIF, Free site)SERIAL
NO. PARTS NAME
Material INSTALLED
PER ONE SETPROVIDED QUANTITY
MAKER'S NAME &
MODEL NO.
ADDRESS (CONTACT
POINT) UNIT PRICE
TOTAL PRICE
REMARKS
Φ4×1220ℓ EA EA 6 Rubber Ring
NBR 2 6
HHI 400x250VWDB4
ULSAN, KOREA (Hyundai Heavy
Industries Co., Ltd.) - -
Φ4×1000ℓ EA EA 7 Rubber Ring
NBR 2 6
HHI 400x250VWDB4
ULSAN, KOREA (Hyundai Heavy
Industries Co., Ltd.) - -
Φ4×905ℓ EA EA 8 Rubber Ring
NBR 2 6
HHI 400x250VWDB4
ULSAN, KOREA (Hyundai Heavy
Industries Co., Ltd.) - -
Φ4×1220ℓ EA EA 9 Rubber Ring
NBR 1 3
HHI 400x250VWDB4
ULSAN, KOREA (Hyundai Heavy
Industries Co., Ltd.) - -
Φ6×2702ℓ EA EA 10 Rubber Ring
NBR 1 3
HHI 400x250VWDB4
ULSAN, KOREA (Hyundai Heavy
Industries Co., Ltd.) - -
- EA EA 11 Gasket
Non-asbestos 3 9
HHI 400x250VWDB4
ULSAN, KOREA (Hyundai Heavy
Industries Co., Ltd.)
(146)
RECOMMENDED SPARE PART LIST FOR 2 YEARS (OPTION)
ITEM NO. 18LCB10AP001 18LCB20AP001 18LCB30AP001
EQUIP.NAME Main Condensate Pumps
Document Code : NHT/01/M/-------B20/LS/001 PROJECT NAME : Nhon Trach 1 CCPP, Vietnam REV. NO. : A SHEET NO. : 5 OF 5
Description QUANTITY (UNIT) PRICE (in USD CIF, Free site)SERIAL
NO. PARTS NAME
Material INSTALLED
PER ONE SETPROVIDED QUANTITY
MAKER'S NAME &
MODEL NO.
ADDRESS (CONTACT
POINT) UNIT PRICE
TOTAL PRICE
REMARKS
P-345 EA EA 12 O-Ring
NBR 1 3
HHI 400x250VWDB4
ULSAN, KOREA (Hyundai Heavy
Industries Co., Ltd.) - -
G-265 EA EA 13 O-Ring
NBR 1 3
HHI 400x250VWDB4
ULSAN, KOREA (Hyundai Heavy
Industries Co., Ltd.) - -
(147)
(148)
Owner’s Consultants
ESB International
Owner
PETRO VIETNAM GPPMB
PECC2
EPC Contractor
LILAMA – CC1 CONSORTIUM
Issued by
LILAMA CORPORATION – HYUNDAI ENGINEERING
Subcontractor
abcd
ALSTOM (Switzerland) Ltd.
Project
NHON TRACH 1 CCPP PROJECT
Owner’s Identification No. EPC Contractor Identification No.
ALSTOM Document Code NHT/01/M/-------B20/LS/002
Revision History Rev. Revision Date Created by Checked by Approved by Description
A 26.03.2008 D.E.YANG J.W.SHIN K.R.KIM First issue
Description latest Revision:
SPECIAL TOOL LIST FOR CONDENSATE EXTRACTION PUMPS © ALSTOM 2007. All rights reserved.
(149)
(150)
Owner’s Consultants
ESB International
Owner
PETRO VIETNAM GPPMB
PECC2
EPC Contractor
LILAMA – CC1 CONSORTIUM
Issued by
LILAMA CORPORATION – HYUNDAI ENGINEERING
Subcontractor
abcd
ALSTOM (Switzerland) Ltd.
Project
NHON TRACH 1 CCPP PROJECT
Owner’s Identification No. EPC Contractor Identification No.
ALSTOM Document Code NHT/01/M/-------B20/LE/001
Revision History Rev. Revision Date Created by Checked by Approved by Description
A 12.28.2007 D.E.YANG J.W.SHIN K.R.KIM First issue
B 01.10.2008 D.E.YANG J.W.SHIN K.R.KIM 2ND issue
C 03.26.2008 D.E.YANG J.W.SHIN K.R.KIM 3RD issue
Description latest Revision:
KKS NUMBER LIST FOR CONDENSATE EXTRACTION PUMPS © ALSTOM 2007. All rights reserved.
(151)
MAIN CONDENSATE PUMPS- KKS LABEL LIST -
REV: A
KKS-No. (Line 1) DESCRIPTION (Complete; notpart of the label)
DescriptionVietnamese
Line 2 (max. 20 char's incl. blanks)
DescriptionVietnamese
Line 3 (max. 20 char's incl. blanks)
DescriptionEnglish
Line 4 (max. 20 char's incl. blanks)
DescriptionEnglish
Line 5 (max. 20 char's incl. blanks)
18LCB10AP001 MAIN CONDENSATE PUMP MAIN CNDS PUMP #1 N/A18LCB10AM001 MOTOR FOR MAIN CEP MOTOR CNDS PUMP18LCB10CT001 THRUST BEARING TEMP.
TRANSMITTERTEMP. TRANSMITTER THRUST BEARING
18LCB10CL001 LEVEL INDICATOR FOR LUBEOIL BOX
LEVEL INDICATOR LUBE OIL BOX
18LCB10CP001 SUCTION PRESSURE GAUGE PRESSURE GAUGE PUMP SUCTION
18LCB10CP002 DISCHARGE PRESSUREGAUGE
PRESSURE GAUGE PUMP DISCHARGE
18LCB10AA001 GLOBE VAVE FOR BRGCOOLING INLET
GLOBE VALVE BRG COOLING INLET
18LCB10AA002 GLOBE VAVE FOR BRGCOOLING OUTLET
GLOBE VALVE BRG COOLING OUTLET
18LCB10AA004 CHECK VALVE FOR M/SEALINLET
CHECK VALVE M/SEAL INLET
18LCB10AA005 GAUGE ROOT VALVE FORSUCTION PG
ROOT VALVE SUCTION PRESSURE GAUGE
18LCB10AA006 GAUGE ROOT VALVE FORDISCHARGE PG
ROOT VALVE DISCHARGE PRESSURE GAUGE
18LCB10AA007 GLOBE VALVE FOR SUCTIONVENT LINE
GLOBE VALVE SUCTION VENT
18LCB10AA009 GLOBE VALVE FOR DRAINLINE
GLOBE VALVE DRAIN LINE
18LCB10CF001 SIGHT GLASS FOR M/SEALINLET
SIGHT GLASS M/SEAL INLET
18LCB10CF002 SIGHT GLASS FOR M/SEALOUTLET
SIGHT GLASS M/SEAL OUTLET
18LCB10CT008 THERMISTOR ("U" PHASE) N/A N/A18LCB10CT009 THERMISTOR ("V" PHASE) N/A N/A18LCB10CT010 THERMISTOR ("W" PHASE) N/A N/A18LCB10CT011 THERMISTOR ("U1" PHASE) N/A N/A18LCB10CT012 THERMISTOR ("V1" PHASE) N/A N/A18LCB10CT013 THERMISTOR ("W1" PHASE) N/A N/A18LCB10CT002 MOTOR BEARING TEMP.
TRANSMITTER(DE SIDE)TEMP. TRANSMITTER(DE)
MOTOR BEARING
18LCB10CT003 MOTOR BEARING TEMP.TRANSMITTER(NDE SIDE)
TEMP. TRANSMITTER(NDE)
MOTOR BEARING
18LCB10AU001 COUPLING COUPLING N/A
18LCB20AP001 MAIN CONDENSATE PUMP MAIN CNDS PUMP #2 N/A18LCB20AM001 MOTOR FOR MAIN CEP MOTOR CNDS PUMP18LCB20CT001 THRUST BEARING TEMP.
TRANSMITTERTEMP. TRANSMITTER THRUST BEARING
18LCB20CL001 LEVEL INDICATOR FOR LUBEOIL BOX
LEVEL INDICATOR LUBE OIL BOX
18LCB20CP001 SUCTION PRESSURE GAUGE PRESSURE GAUGE PUMP SUCTION
PAGE 1 OF 3 (152)
MAIN CONDENSATE PUMPS- KKS LABEL LIST -
REV: A
KKS-No. (Line 1) DESCRIPTION (Complete; notpart of the label)
DescriptionVietnamese
Line 2 (max. 20 char's incl. blanks)
DescriptionVietnamese
Line 3 (max. 20 char's incl. blanks)
DescriptionEnglish
Line 4 (max. 20 char's incl. blanks)
DescriptionEnglish
Line 5 (max. 20 char's incl. blanks)
18LCB20CP002 DISCHARGE PRESSUREGAUGE
PRESSURE GAUGE PUMP DISCHARGE
18LCB20AA001 GLOBE VAVE FOR BRGCOOLING INLET
GLOBE VALVE BRG COOLING INLET
18LCB20AA002 GLOBE VAVE FOR BRGCOOLING OUTLET
GLOBE VALVE BRG COOLING OUTLET
18LCB20AA004 CHECK VALVE FOR M/SEALINLET
CHECK VALVE M/SEAL INLET
18LCB20AA005 GAUGE ROOT VALVE FORSUCTION PG
ROOT VALVE SUCTION PRESSURE GAUGE
18LCB20AA006 GAUGE ROOT VALVE FORDISCHARGE PG
ROOT VALVE DISCHARGE PRESSURE GAUGE
18LCB20AA007 GLOBE VALVE FOR SUCTIONVENT LINE
GLOBE VALVE SUCTION VENT
18LCB20AA009 GLOBE VALVE FOR DRAINLINE
GLOBE VALVE DRAIN LINE
18LCB20CF001 SIGHT GLASS FOR M/SEALINLET
SIGHT GLASS M/SEAL INLET
18LCB20CF002 SIGHT GLASS FOR M/SEALOUTLET
SIGHT GLASS M/SEAL OUTLET
18LCB20CT008 THERMISTOR ("U" PHASE) N/A N/A18LCB20CT009 THERMISTOR ("V" PHASE) N/A N/A18LCB20CT010 THERMISTOR ("W" PHASE) N/A N/A18LCB20CT011 THERMISTOR ("U1" PHASE) N/A N/A18LCB20CT012 THERMISTOR ("V1" PHASE) N/A N/A18LCB20CT013 THERMISTOR ("W1" PHASE) N/A N/A18LCB20CT002 MOTOR BEARING TEMP.
TRANSMITTER(DE SIDE)TEMP. TRANSMITTER(DE)
MOTOR BEARING
18LCB20CT003 MOTOR BEARING TEMP.TRANSMITTER(NDE SIDE)
TEMP. TRANSMITTER(NDE)
MOTOR BEARING
18LCB20AU001 COUPLING COUPLING N/A
18LCB30AP001 MAIN CONDENSATE PUMP MAIN CNDS PUMP #3 N/A18LCB30AM001 MOTOR FOR MAIN CEP MOTOR CNDS PUMP18LCB30CT001 THRUST BEARING TEMP.
TRANSMITTERTEMP. TRANSMITTER THRUST BEARING
18LCB30CL001 LEVEL INDICATOR FOR LUBEOIL BOX
LEVEL INDICATOR LUBE OIL BOX
18LCB30CP001 SUCTION PRESSURE GAUGE PRESSURE GAUGE PUMP SUCTION
18LCB30CP002 DISCHARGE PRESSUREGAUGE
PRESSURE GAUGE PUMP DISCHARGE
18LCB30AA001 GLOBE VAVE FOR BRGCOOLING INLET
GLOBE VALVE BRG COOLING INLET
18LCB30AA002 GLOBE VAVE FOR BRGCOOLING OUTLET
GLOBE VALVE BRG COOLING OUTLET
18LCB30AA004 CHECK VALVE FOR M/SEALINLET
CHECK VALVE M/SEAL INLET
PAGE 2 OF 3 (153)
MAIN CONDENSATE PUMPS- KKS LABEL LIST -
REV: A
KKS-No. (Line 1) DESCRIPTION (Complete; notpart of the label)
DescriptionVietnamese
Line 2 (max. 20 char's incl. blanks)
DescriptionVietnamese
Line 3 (max. 20 char's incl. blanks)
DescriptionEnglish
Line 4 (max. 20 char's incl. blanks)
DescriptionEnglish
Line 5 (max. 20 char's incl. blanks)
18LCB30AA005 GAUGE ROOT VALVE FORSUCTION PG
ROOT VALVE SUCTION PRESSURE GAUGE
18LCB30AA006 GAUGE ROOT VALVE FORDISCHARGE PG
ROOT VALVE DISCHARGE PRESSURE GAUGE
18LCB30AA007 GLOBE VALVE FOR SUCTIONVENT LINE
GLOBE VALVE SUCTION VENT
18LCB30AA009 GLOBE VALVE FOR DRAINLINE
GLOBE VALVE DRAIN LINE
18LCB30CF001 SIGHT GLASS FOR M/SEALINLET
SIGHT GLASS M/SEAL INLET
18LCB30CF002 SIGHT GLASS FOR M/SEALOUTLET
SIGHT GLASS M/SEAL OUTLET
18LCB30CT008 THERMISTOR ("U" PHASE) N/A N/A18LCB30CT009 THERMISTOR ("V" PHASE) N/A N/A18LCB30CT010 THERMISTOR ("W" PHASE) N/A N/A18LCB30CT011 THERMISTOR ("U1" PHASE) N/A N/A18LCB30CT012 THERMISTOR ("V1" PHASE) N/A N/A18LCB30CT013 THERMISTOR ("W1" PHASE) N/A N/A18LCB30CT002 MOTOR BEARING TEMP.
TRANSMITTER(DE SIDE)TEMP. TRANSMITTER(DE)
MOTOR BEARING
18LCB30CT003 MOTOR BEARING TEMP.TRANSMITTER(NDE SIDE)
TEMP. TRANSMITTER(NDE)
MOTOR BEARING
18LCB30AU001 COUPLING COUPLING N/A
PAGE 3 OF 3 (154)
(155)
(156)
(157)
(158)
(159)
(160)
(161)
(162)
(163)
(164)
(165)
(166)
(167)
(168)
(169)
(170)
(171)
(172)
(173)
(174)
(175)
(176)
(177)
(178)
(179)
(180)
(181)
(182)
(183)
(184)
(185)
(186)
(187)
(188)
(189)
(190)
(191)
(192)
(193)
(194)
(195)
(196)
(197)
(198)
(199)
(200)
(201)
Owner’s Consultants
ESB International
Owner
PETRO VIETNAM GPPMB
PECC2
EPC Contractor
LILAMA – CC1 CONSORTIUM
Issued by LILAMA CORPORATION – HYUNDAI ENGINEERING
Subcontractor
ALSTOM (Switzerland) Ltd.
Project
NHON TRACH1 CCPP PROJECT
Owner’s Identification No. EPC Contractor Identification No.
ALSTOM Document Code NHT/01/M/-------B20/MD/101
Revision History Rev. Revision Date Created by Checked by Approved by Description
A 30.04.2007 I.J.KANG J.W.SOHN K.J.KANG First issue
B 08.06.2007 I.J.KANG J.W.SOHN K.J.KANG Second issue
C 09.08.2007 I.J.KANG J.W.SOHN K.J.KANG Third issue
D 04.03.2008 I.J.KANG J.W.SOHN K.J.KANG For Final
Description latest Revision:
TECHNICAL SPECIFICATION FOR INDUCTION MOTOR © ALSTOM 2007. All rights reserved.
(202)
1. 2 sheets
2. 1 sheets
3. 1 sheet
4. 1 sheet
5. 1 sheet
6. 1 sheet
7. 2 sheets
8. 2 sheets
9. 4 sheets
10. 1 sheet
11. 2 sheets
12. 11 sheets
Heater Terminal Box Ass'y(NHT/01/M/-------B20/DD/105) ------------------------------
Main Terminal Box Ass'y (NHT/01/M/-------B20/DD/103) -------------------------------
General Assembly Drawing (NHT/01/M/-------B20/DD/102) -----------------------------
Acc'y Terminal Box Ass'y(NHT/01/M/-------B20/DD/104) --------------------------------
CONTENTS
Motor Data Sheet (NHT/01/M/-------B20/DS/101)-------------------------------------------
Outline Dimension Drawing(NHT/01/M/-------B20/DD/101) -----------------------------
Painting Procedure (NHT/01/M/-------B20/DD/108) ---------------------------------------
Speed Torque & Current Curve (NHT/01/M/-------B20/DD/106) -----------------------
Thermal Limit & Time Current Curve (NHT/01/M/-------B20/DD/107) ---------------
Motor Test Plan & Test Procedure(NHT/01/M/-------B20/MP/101----------------------
Wiring Diagram Drawing(NHT/01/M/-------B20/TC/101) --------------------------------
Instruments List(NHT/01/M/-------B20/LI/101) ---------------------------------------------
(203)
Owner’s Consultants
ESB International
Owner
PETRO VIETNAM GPPMB
PECC2
EPC Contractor
LILAMA – CC1 CONSORTIUM
Issued by LILAMA CORPORATION – HYUNDAI ENGINEERING
Subcontractor
ALSTOM (Switzerland) Ltd.
Project
NHON TRACH1 CCPP PROJECT
Owner’s Identification No. EPC Contractor Identification No.
ALSTOM Document Code NHT/01/M/-------B20/DS/101
Revision History Rev. Revision Date Created by Checked by Approved by Description
A 30.04.2007 I.J.KANG J.W.SOHN K.J.KANG First issue
B 08.06.2007 I.J.KANG J.W.SOHN K.J.KANG Second issue
C 09.08.2007 I.J.KANG J.W.SOHN K.J.KANG Third issue
D 30.10.2007 I.J.KANG J.W.SOHN K.J.KANG Fourth issue
E 04.03.2008 I.J.KANG J.W.SOHN K.JKANG For Final
Description latest Revision:
MOTOR DATA SHEET © ALSTOM 2007. All rights reserved.
(204)
kW - P
DESIGN NO :
Item No. Rev. No. [ ] Project No. Quantity
)D.O.L. Y-
VΦ A
F B H A
Less than meterLess than %
(Max.)
B
Kg.mKg.mKg.m
Load GD referred to motor shaft Direct V-Belt Single Double Motor GD
Main Steel Cast Iron dB(A) Terminal Aux. Yes No mm/sec.(rms) Box Location Refer to Outline Drawing 3 \ 2
Paint Application Area Classification Outline Dimension Drawing \ Motor Weight(Approx.) Applicable Standard B3
B5 HHI Stand. V1
ACCESSORIES1) Thermistor : 2EA/PHASE2) Bearing Temp. Detector(Pt 100Ω, Dual type) : 2EA/Motor3) Space Heater : 230V,164W,1PH Acc'y Terminal Box Ass'y
Wiring Diagram
SPARE PARTS
HHI W230-131-1 * In case of Inverter or V.V.V.F Motor:Performance data is based on sine wave tests. A4(210mm X 297mm)
%100
80
B5 V1
Starting6218C3/7219DB
40
NEMA Design100% Load
Indoor Outdoor
90
1.1 0.89
220.3
Speed at Rated Load RPM1486 Torque (D.O.L)
Rated83.9
%104.9
Rotor Type55 Squirrel Cage
Output Poles
HP 160 KWP4
400
% Power Factor(P.U)
94.0100% Load
Note: Others not mentioned in this specification shall be in accordance with HHI standard. Above technical data are only design values and shall be guaranteed with tolerance of applicable standard.
Grease(Alvania RL2)
(Viewed from Drive End)
Lubricant
Coupling Method Shaft Extension
External Thrust Not applicable
Not applicable
Frame No.
Maker Test Report
TEFCIC4A1A1
315HLB4 310-40V
(IP
1000
Type
3
Model No.or RFQ No.
GENERAL SPECIFICATION PERFORMANCE DATA Project Name 3Sets
2
50 Hz
Enclosure(Protection)
Frequency Phase
Cooling Method
Location Altitude
at 1.0 S.F
Humidity
Insulation Class Temp. Rise at full load (by resistance method)
210
1794.0
80
Bearing DE/NDE Type
%
Ambient Temp. Duty Service Factor Electric Design Construction
K.J.KANG
Date DSND CHKD
2007.06.08 I.J.KANG J.W.SOHN S.H.KO
CHKD APPD
of TEFC
REMARK
Munsell No. 7.5 BG 6/1.5 Starting Duty
SUBMITTAL DRAWING
Starting Method(*)
160
Efficiency(%)
Rated Voltage Rated Load Start'g-D.O.L
Current276.0
4DATA SHEET
Noise Level (dB(A)) Vibration(Velocity)
Break down
AC INDUCTION MOTOR
Continuous(S1)
Anti-frictionB3
20071150RMM062 ALSTOM
Cold timetimes Hot
Kg.m80 at 1m from motor(No-load)
3.8
Kg
General Ass'y
NHT/01/M/--------B20/TC/101
Main T-Box Ass'yNHT/01/M/--------B20/DD/102
NHT/01/M/--------B20/DD/104NHT/01/M/--------B20/DD/103
CONDENSATE PUMP
Inspection and Performance TestIEC
- Kg.m8.0
1500NHT/01/M/--------B20/DD/101
2
2
2
2
2
1
1
(205)
(206)
(207)
(208)
(209)
(210)
Owner’s Consultants
ESB International
Owner
PETRO VIETNAM GPPMB
PECC2
EPC Contractor
LILAMA – CC1 CONSORTIUM
Issued by LILAMA CORPORATION – HYUNDAI ENGINEERING
Power Island Contractor
ALSTOM (Switzerland) Ltd.
Subcontractor
NHON TRACH1 CCPP PROJECT
Owner’s Identification No. EPC Contractor Identification No.
ALSTOM Document Code NHT/01/M/-------B20/DD/106
Revision History Rev. Revision Date Created by Checked by Approved by Description
A 30.04.2007 I.J.KANG J.W.SOHN K.J.KANG First issue
B 08.06.2007 I.J.KANG J.W.SOHN K.J.KANG Second issue
C 09.08.2007 I,J,KANG J.W.SOHN K.J.KANG Third issue
D 04.03.2008 I,J,KANG J.W.SOHN K.J.KANG For Final
Description latest Revision:
SPEED- TORQUE & CURRENT CURVE © ALSTOM 2007. All rights reserved.
(211)
CURVE NO.
-
MOTOR TYPE : Kw P HZ
RATED TORQUE : kg.m RATED SPEED : RPM
GD² OF MOTOR : kg.m² VOLTAGE : V
GD² OF LOAD : kg.m² RATED CURRENT : A
A: SPEED-TORQUE CURVE AT RATED VOLTAGEB: SPEED-CURRENT CURVE AT RATED VOLTAGEC: SPEED-TORQUE CURVE AT 80 % RATED VOLTAGED: SPEED-CURRENT CURVE AT 80 % RATED VOLTAGEE: SPEED-TORQUE CURVE AT 75 % RATED VOLTAGEF: SPEED-CURRENT CURVE AT 75 % RATED VOLTAGEL: SPEED-TORQUE CURVE OF LOAD
REV. CONTENTS DATE DSN CHK APPD
0RM-W230-091-1 A4(210mm x 297mm)
7RMM062
HLB4 310-40V
276.0
104.9
400
1486
8
7
SPEED-TORQUE & CURRENTCURVE
STARTING WITH VALVE CLOSED
ORIGINAL ISSUE 2007-04-23 J.H.CHOI Y.S.KIM
STC
160 4 50
K.J.KANGORIGINAL ISSUE1 2007-06-09 J.H.CHOI Y.S.KIM K.J.KANG
REMARK.
NOTE
B
D
A
C
F
E
L
(212)
Owner’s Consultants
ESB International
Owner
PETRO VIETNAM GPPMB
PECC2
EPC Contractor
LILAMA – CC1 CONSORTIUM
Issued by LILAMA CORPORATION – HYUNDAI ENGINEERING
subcontractor
ALSTOM (Switzerland) Ltd.
Project
NHON TRACH1 CCPP PROJECT
Owner’s Identification No. EPC Contractor Identification No.
ALSTOM Document Code NHT/01/M/-------B20/DD/107
Revision History Rev. Revision Date Created by Checked by Approved by Description
A 30.04.2007 I.J.KANG J.W.SOHN K.J.KANG First issue
B 08.06.2007 I.J.KANG J.W.SOHN K.J.KANG Second issue
C 09.08.2007 I.J.AKNG J.W.SOHN K.J.KANG Third issue
D 04.03.2008 I.J.KANG J.W.SOHN K.J.KANG For Final
Description latest Revision:
THERMAL LIMIT & TIME CURRENT CURVE. © ALSTOM 2007. All rights reserved.
(213)
CURVE NO.
-
MOTOR TYPE : Kw P HZ
RATED TORQUE : kg.m RATED SPEED : RPM
GD² OF MOTOR : kg.m² VOLTAGE : V
GD² OF LOAD : kg.m² RATED CURRENT : A
NOTE : A: THERMAL LIMIT CURVE AT HOT CONDITIONB: THERMAL LIMIT CURVE AT COLD CONDITIONC: TIME - CURRENT CURVE AT RATED VOLTAGED: TIME - CURRENT CURVE AT 80% RATED VOLTAGEE: TIME - CURRENT CURVE AT 75% RATED VOLTAGE
REMARK. REV. CONTENTS DATE DSN CHK APPD
0RM-W230-091-1 A4(210mm x 297mm)
7RMM062
310-40VHLB4
ORIGINAL ISSUE
276
104.9
8
7
400
1486
STARTING WITH VALVE CLOSED
THERMAL LIMIT & TIME CURRENTCURVE
2007-04-23 J.H.CHOI Y.S.KIM
TLC
160 4 50
K.J.KANG1 ORIGINAL ISSUE 2007-06-09 J.H.CHOI Y.S.KIM K.J.KANG
B
A
D
C
E
(214)
Owner’s Consultants
ESB International
Owner
PETRO VIETNAM GPPMB
PECC2
EPC Contractor
LILAMA – CC1 CONSORTIUM
Issued by LILAMA CORPORATION – HYUNDAI ENGINEERING
Subcontractor
ALSTOM (Switzerland) Ltd.
Project
NHON TRACH1 CCPP PROJECT
Owner’s Identification No. EPC Contractor Identification No.
ALSTOM Document Code NHT/01/M/-------B20/DD/108
Revision History Rev. Revision Date Created by Checked by Approved by Description
A 30.04.2007 I.J.KANG J.W.SOHN K.J.KANG First issue
B 08.06.2007 I.J.KANG J.W.SOHN K.J.KANG Second issue
C 09.08.2007 I.J.KANG J.W.SOHN K.J.KANG Third issue
D 04.03.2008 I.J.KANG J.W.SOHN K.J.KANG For Final
Description latest Revision:
PAINTING PROCEDURE FOR MOTOR © ALSTOM 2007. All rights reserved.
(215)
NO : 20071150
1 / 3
1. SCOPE This procedure defines the painting and rust prevention procedure at shop.
But non-ferrous metal will not be painted.
2. SURFACE PREPARATION All surfaces to be painted shall be cleaned of oil or grease or other similar
materials with solvent and then shall be brushed and blasted with air to remove
rust or scale.
Prior to above preparation, mill scale, rust scale, chips and other foreign
materials shall be removed in accordance with painting schedule.
3. PROCEDURE 3.1 Detail painting procedures refer to attached data sheet.
3.2 Painting conditions.
3.2.1 Temperature : Min. 10 deg. C (50 deg. F)
Max. 43 deg. C (109.4 deg. F)
3.2.2 Humidity : 40 ~ 80%
3.2.3 Drying : Natural drying
3.3 Related conditions
No paintings shall be applied outdoor when it is foggy, rainy or excessive
wind. If chemical contamination occurs in paint it should be removed by
by washing with water or solvent before painting.
4. APPLICATION DETAILS 4.1 Preparation of paintings
Paintings should be prepared for application according to the instructions.
Individual components of multi-component paintings must be stirred before
mixing. If the thinner is required, only designated thinner should be used
and thinning rate may be adjusted according to the job condition.
4.2 Application method
4.2.1 Airless spray may be most effective in obtaining specified thickness
at once.
4.2.2 Keep the spary gun at constant distance and perpendicular to the surfaces.
4.2.3 Brush or roller may be required to achieve the specified thickness.
PAINTING PROCEDURE FOR MOTOR
(216)
NO : 20071150
2 / 3
4.3 Application work
4.3.1 Welding seams, corners and edges should always receive a stripe coat
before full coating in order to obtain adequate film built.
4.3.2 Bolt jointing surroundings and flange matching faces should be blanked
off or otherwise protected from painting unless otherwise accepted.
4.3.3 Special care should be taken to gain uniform thickness.
4.3.4 Each coat should be allowed enough to dry and interval between coats.
4.4 Cleaning of tools
The application tools and equipments should be cleaned with the thinner
immediately after use.
5. INSPECTION After painting, the surfaces shall be inspected visually for wrinkle, swelling
and other harmful defects.
If repair coating is required, applicable surfaces shall be arranged by sand
paper and re coated with the same paint.
6. STORAGE OF PAINT The storage area should be well ventilated and protected from sparks, flame,
direct exposure to sun or excessive heat, preferably located in isolated room.
PAINTING PROCEDURE FOR MOTOR
(217)
NO : 20071150
3 / 3
7. PAINTING SYSTEM 7.1 Item : Motor
7.2 Painting schedule
KOREPOX ZINC RICH PRIMER
First or External and Maker : KOREA CHEMICAL CO., LTD
Prime coat. internal Manufacturer's designation : EZ175C
surface of motor (Two - Component)
Colour : Metallic gray 1184
Dry film thickness : 30 x 2 coat
Coating time : After preparation of surface.
Coating method : spary and/or brush
KOREPOCX MICACEOUS IRON OXID
Intermediate External surface Maker : KOREA CHEMICAL CO., LTD
coat. of motor Manufacturer's designation : EM877
Colour : Metallic gray 9210
Dry film thickness : 50 x 1 coats
Coating time : After preparation of surface.
Coating method : spary and/or brush
POLYURETHANE
Finish coat. External surface Maker : KOREA CHEMICAL CO., LTD
of motor Manufacturer's designation : UT2578
Colour (Munsell No.) : 7.5BG 6/1.5
Dry film thickness :50 x 1 coats
Coating method : spary and/or brush
Curing method : Self Curing
Total Dry film thickness Min. 160
PAINTING PROCEDURE FOR MOTOR
(218)
(219)
Owner’s Consultants
ESB International
Owner
PETRO VIETNAM GPPMB
PECC2
EPC Contractor
LILAMA – CC1 CONSORTIUM
Issued by LILAMA CORPORATION – HYUNDAI ENGINEERING
Subcontractor
ALSTOM (Switzerland) Ltd.
Project
NHON TRACH1 CCPP PROJECT
Owner’s Identification No. EPC Contractor Identification No.
ALSTOM Document Code NHT/01/M/-------B20/LI/101
Revision History Rev. Revision Date Created by Checked by Approved by Description
A 30.04.2007 I.J.KANG J.W.SOHN K.J.KANG First issue
B 08.06.2007 I.J.KANG J.W.SOHN K.J.KANG Second issue
C 09.08.2007 I.J.KANG J.W.SOHN K.J.KANG Third issue
D 04.03.2008 I.J.KANG J.W.SOHN K.J.KANG For Final
Description latest Revision:
LIST OF INSTRUMENTS © ALSTOM 2007. All rights reserved.
(220)
INSTRUMENT LISTPROJECT NAME : Vietnam / Nhon Trach 1 CCPP Project - Main Condensate Pump Document No. : NHT/01/M/-------B20/LI/101
1 18LCB10CT008 TH THERMISTOR FOR MOTOR WINDING TEMP. SENSOR ('u' Phase)
- 0-180 DryContact ≥130 N/A Lead Wire Type - PN2-13 HHI NHT/01/M/-------B20/FD/001 Embedded in the startor
winding 'U' Phase. B
2 18LCB10CT009 TH THERMISTOR FOR MOTOR WINDING TEMP. SENSOR ('v' Phase)
- 0-180 DryContact ≥130 N/A Lead Wire Type - PN2-13 HHI NHT/01/M/-------B20/FD/001 Embedded in the startor
winding 'V' Phase. B
3 18LCB10CT010 TH THERMISTOR FOR MOTOR WINDING TEMP. SENSOR ('w' Phase)
- 0-180 DryContact ≥130 N/A Lead Wire Type - PN2-13 HHI NHT/01/M/-------B20/FD/001 Embedded in the startor
winding 'W' Phase. B
4 18LCB10CT011 TH THERMISTOR FOR MOTOR WINDING TEMP. SENSOR ('u1' Phase)
- 0-180 DryContact ≥140 N/A Lead Wire Type - PN2-13 HHI NHT/01/M/-------B20/FD/001 Embedded in the startor
winding 'U1' Phase. B
5 18LCB10CT012 TH THERMISTOR FOR MOTOR WINDING TEMP. SENSOR ('v1' Phase)
- 0-180 DryContact ≥140 N/A Lead Wire Type - PN2-13 HHI NHT/01/M/-------B20/FD/001 Embedded in the startor
winding 'V1' Phase. B
6 18LCB10CT013 TH THERMISTOR FOR MOTOR WINDING TEMP. SENSOR ('w1' Phase)
- 0-180 DryContact ≥140 N/A Lead Wire Type - PN2-13 HHI NHT/01/M/-------B20/FD/001 Embedded in the startor
winding 'W1' Phase. B
7 18LCB10CT002 TE Motor bearing Temperature sensor(Drive Side) - 0-200 Resistande (Ω) ≥100
≥105N/A
Pt100ohm -dual-3Wire
- 4m-040819 HHI NHT/01/M/-------B20/FD/001 B
8 18LCB10CT002 TIZA Motor bearing TemperatureTransmitter (Drive Side) - 0-200 4 ~20mA ≥100
≥105N/A - - T32.30.000 WIKA NHT/01/M/-------B20/FD/001 Without local indication B
9 18LCB10CT003 TE Motor bearing Temperature sensor(Non Drive Side) - 0-200 Resistande (Ω) ≥100
≥105N/A
Pt100ohm -dual-3Wire
- 4m-040819 HHI NHT/01/M/-------B20/FD/001 B
10 18LCB10CT003 TIZA Motor bearing TemperatureTransmitter (Non Drive Side) - 0-200 4 ~20mA ≥100
≥105N/A - - T32.30.000 WIKA NHT/01/M/-------B20/FD/001 Without local indication B
ELEMENTMATERIALSETTINGMEASURING
RANGESIGNALRANGE
PROCESSCONN. SIZE
ELEMENTTYPE REVMODEL NO. MAKER P & ID NO.
(ALSTOM Document Code) REMARKSERVICE FLUIDNO. KKSTAG NO.
INST.TYPE
1 OF 2 (221)
Owner’s Consultants
ESB International
Owner
PETRO VIETNAM GPPMB
PECC2
EPC Contractor
LILAMA – CC1 CONSORTIUM
Issued by LILAMA CORPORATION – HYUNDAI ENGINEERING
Subcontractor
ALSTOM (Switzerland) Ltd.
Project
NHON TRACH1 CCPP PROJECT
Owner’s Identification No. EPC Contractor Identification No.
ALSTOM Document Code NHT/01/M/-------B20/MP/101
Revision History Rev. Revision Date Created by Checked by Approved by Description
A 30.04.2007 I.J.KANG J.W.SOHN K.J.KANG First issue
B 08.06.2007 I.J.KANG J.W.SOHN K.J.KANG Second issue
C 09.08.2007 I.J.KANG J.W.SOHN K.J.KANG Third issue
E 04.03.2008 I.J.KANG J.W.SOHN K.J.KANG\ For Final
Description latest Revision:
MOTOR TEST PLAN & TEST PROCEDURE © ALSTOM 2007. All rights reserved.
(222)
: REV. No. : 2
INSPECTION & TEST PROGRAM :
: PAGE : 1 OF 2
WORK DESCRIPTION : THREE PHASE INDUCTION MOTOR.
20071150RMM062 160KW 400V 4P 50Hz ------ 3 SETS
HYUNDAI HEAVY INDUSTRIES CO., LTDELECTRO ELECTRIC SYSTEMS DIVISIONROTATING MACHINERY DESIGN DEP'T (TEL.82-52-202-6619)
2 2007. 07. 03 J. H. CHOI Y. S. KIM K. J. KANG FOR APPROVAL
1 2007. 06. 21 J. H. CHOI Y. S. KIM K. J. KANG FOR APPROVAL
0 2007. 05. 31 J. H. CHOI Y. S. KIM K. J. KANG FOR APPROVAL
REV. NO. DATE PREPARED BY REVIEWED BY APPROVED BY DESCRIPTIONHHI A24-418(A)-1 A4 (297mmx210mm)
I.T.P No.
ALSTOM(SWITZERLAND) LTD.
VIETNAM/NHON TRACH,CEP
ITP-71150RMM062
PROJ. NAME
CUSTOMER
(223)
I. INSPECTION & TEST PROGRAM CUSTOMER ; ALSTOM(SWITZERLAND) LTD INSP. & TEST DESCRIPTION: PROJECT No.: 20071150 REV. NO. 2 CONTACT No.; THREE PHASE INDUCTION MOTOR I.T.P.No.: ITP-71150RMM062 PAGE 2 OF 2
DESCRIPTION OF APPLIED INSPECTED BYNO. CLASSIFICATION TEST & INSPECTION CODE
ALSTOMQ'TY LOCATION REMARK
1 FINAL INSPECTION 1.1 Visual & dimensional inspection APP.SPEC.,IEC60034 H W W T HHI/ULSAN 1.2 Measurement of winding resistance IEC 60034 H W W T KOREA 1.3 Locked rotor test IEC 60034, IEEE 112 H W W S 1.4 No-load test and direction of rotation IEC 60034 H W W T 1.5 Measurement of noise level IEC 60034 H W W S 1.6 Measurement of vibration IEC 60034 H W W T 1.7 Determination of characteristic IEC 60034, IEEE 112 H W W T 1.8 Temperature rise test IEC 60034, IEEE 112 H W W S 1.9 Measurement of insulation resistance IEC 60034 H W W T 1.10 High voltage test IEC 60034 H W W T 1.11 Overspeed test IEC 60034 H W W S 1.12 Shaft voltage measurement H W W T 1.13 Bearing temperature rise test APP.SPEC.,IEC60034
1.14 Other tests (RTD & SPACE HEATER) M.STD H W W T
INSPECTION CATEGORY : M.STD : MAKER STANDARD W : WITNESS POINTH : HOLD POINT R : REVIEWT : TOTAL INSPECTION S : SAMPLE INSPECTION (1SET PER EACH SAME TYPE)
HHI A24-418(B)-1 A4 (297mm×210mm)
HHI
W SIEEE 112
H W1
2
(224)
1 OF 9
HHI Ⅱ. INSPECTION & TEST PROCEDURE WORK DESCRIPTION : THREE PHASE INDUCTION MOTOR PJT. No : 20071150
I.T.P No. : ITP-71150RMM062 REV. No. : 2 PAGE :
: VIETNAM/NHON TRACH,CEP
: ALSTOM(SWITZERLAND) LTD.
: THREE PHASE INDUCTION MOTOR
: 160KW 400V 4P 50Hz ------ 3 SETS
HYUNDAI HEAVY INDUSTRIES CO., LTDELECTRO ELECTRIC SYSTEMS DIVISIONROTATING MACHINERY DESIGN DEP'T (TEL.82-52-202-6619)
2 2007. 07. 03 J. H. CHOI Y.S.KIM K. J. KANG FOR APPROVAL
1 2007. 06. 21 J. H. CHOI Y.S.KIM K. J. KANG FOR APPROVAL
0 2007. 05. 31 J. H. CHOI Y.S.KIM K. J. KANG FOR APPROVAL
REV. DATE PREPARED BY REVIEWED BY APPROVED BY DESCRIPTIONHHI-A24-716(A)-0 A4(210mmx297mm)
3. WORK DESCRIPTION
2. CUSTOMER
1. PROJECT NAME
20071150RMM062
(225)
2 OF 9
HHI Ⅱ. INSPECTION & TEST PROCEDURE WORK DESCRIPTION : THREE PHASE INDUCTION MOTOR PJT. No : 20071150
I.T.P No. : ITP-71150RMM062 REV. No. : 2 PAGE :
1. Final Inspection
1.1 Visual & dimensional inspection
1.1.1 Method of inspection1) Outline dimensions of main parts and dimensions related to outside connectionshall be confirmed to be in conformity to the approved drawings.
2) The following items shall be confirmed to be in conformity to the relatedspecifications and the approved drawings.- Model, form & type, rating, class of insulation, name plate, painting, accessories, and quantities.
1.1.2 Judgment1) In accordance with approved spec. & drawings.
1.2 Measurement of winding resistance
1.2.1 Method of test1) The resistance of the stator winding shall be measured between terminals at anambient temperature.
2) The measurement shall be carried out by digital meter.
1.2.2 Judgment1) Maximum unbalance of resistance between phase and phase shall not exceed±1% of mean value.
HHI-A24-716(B)-0 A4(210mmx297mm)
(226)
3 OF 9
HHI Ⅱ. INSPECTION & TEST PROCEDURE WORK DESCRIPTION : THREE PHASE INDUCTION MOTOR PJT. No : 20071150
I.T.P No. : ITP-71150RMM062 REV. No. : 2 PAGE :
1.3 Locked rotor test
1.3.1 Method of test
1) With the rotor locked at the appropriate position at an ambient temperature,primary current, supply voltage, and input power shall be measured by applyingapproximately the rated load current of the rated frequency, 1/2 the rated frequencyand 1/4 the rated frequency to the stator windings.
2) For special squirrel cage motors, locked rotor test shall also be carried out atthe rated frequency and approximately 200% of the rated primary current.
1.3.2 Judgment1) In accordance with judgment of determination of characteristics
1.4 No load test and direction of rotation
1.4.1 Method of test
1) The no-load test of the motor shall be performed by measuring the primarycurrent, the input power and nominal speed by operating the motor at no-loadcondition with rated voltage and frequency at an ambient temperature.
2) During operation with no-load, the following items shall be confirmed.(a) Direction of rotation(b) Direction of cooling air flow(c) Noise and vibration
1.4.2 Judgment1) The difference between the no-load current in each line and mean value shallnot exceed 5% above or below of the mean value.
HHI-A24-716(B)-0 A4(210mmx297mm)
(227)
4 OF 9
HHI Ⅱ. INSPECTION & TEST PROCEDURE WORK DESCRIPTION : THREE PHASE INDUCTION MOTOR PJT. No : 20071150
I.T.P No. : ITP-71150RMM062 REV. No. : 2 PAGE :
1.5 Measurement of noise level
1.5.1 Method of test1) With the motor driven at its rated speed at no-load and giving its rated voltage,noise level of the motor shall be measured with sound level meter.
2) It is desirable to select the place and method such that the sound reflection isas small as possible.
3) The measurement shall be made at 4 points 1[m] apart from both sides and bothshaft ends of motor respectively at the height of shaft center.
4) The noise level of the motor shall be obtained by the mean value of each points.
1.5.2 Judgment1) In accordance with approved spec.
1.6 Measurement of vibration
1.6.1 Method of test1) The motor shall be run at no load with rated frequency and rated voltage.2) The levels of vibration severity shall be measured on the bearing housings in thethree coordinate directions of horizontal, vertical and axial.
1.6.2 Judgment1) The vibration value shall not exceed the limit specified in the approved spec.2) If not specified in approved spec., the levels of vibration severity shall notexceed the following:
Application code : IEC 60034Maximum r.m.s. values of the vibration velocity
Nominal speed for the shaft height H (mm)Machines measured in a state of free suspension Rigid mounted
(rev/min) 56 ≤ H ≤ 132 132 < H ≤ 225 H > 225 H > 400(mm/s) (mm/s) (mm/s) (mm/s)
≥ 600 ≤ 1800 1.8 1.8 2.8 2.8>1800≤3600 1.8 2.8 4.5 2.8
HHI-A24-716(B)-0 A4(210mmx297mm)
(228)
5 OF 9
HHI Ⅱ. INSPECTION & TEST PROCEDURE WORK DESCRIPTION : THREE PHASE INDUCTION MOTOR PJT. No : 20071150
I.T.P No. : ITP-71150RMM062 REV. No. : 2 PAGE :
1.7 Determination of characteristics
1.7.1 Method of determination of characteristics1) Determination of load characteristics shall be calculated based upon theequivalent circuit calculation method based on the result obtained from no-load, locked rotor test and winding resistance.
2) Below data shall be submitted for each load ; 25%,50%, 75%, 100% & 125%- Primary current - Power factor- Efficiency - Slip
3) Others- Locked rotor current - Locked rotor torque- Breakdown torque
1.7.2 Judgment1) Tolerances in (Table 2) are applied to the guaranteed values of characteristicsof induction motor.
2) In case where the minimum or maximum value is guaranteed in the specifications,no tolerances shall be applied.
3) Applicable code : IEC 60034-1
(Table 2)Performance Tolerance Remark1 Efficiency (η)
a) Conventional efficiency up to and including 150kW (-) 15% of (1 - η) above 150kW (-) 10% of (1 - η)
2 Power factor at rated output (cosφ) (-) 1/6 × (1 - cosφ) Min. : 0.02Max. : 0.07
3 Slip (%) (±) 20% × Guaranteed value4 Breakdown torque (-) 10% × Guaranteed value5 Locked rotor torque (%) (-) 15% × Guaranteed value6 Locked rotor current (%) (+) 20% × Guaranteed value
HHI-A24-716(B)-0 A4(210mmx297mm)
(229)
6 OF 9
HHI Ⅱ. INSPECTION & TEST PROCEDURE WORK DESCRIPTION : THREE PHASE INDUCTION MOTOR PJT. No : 20071150
I.T.P No. : ITP-71150RMM062 REV. No. : 2 PAGE :
1.8 Temperature rise test
1.8.1 Method of test1) Reference ambient temperature ;In case temperature of air is taken as the reference ambient, it shall be measuredby means of thermometers or RTD, place at different points around and at a distanceof one or two meters from the motor and half as high as its height, and protectedso as to avoid effect of heat radiation and stray draughts.The mean of the measured values shall be taken.
2) Loading method ; Equivalent Loading MethodThe motor to be tested is operated at no-load from a main power source, and auxiliary power of different frequency is superposed.Generally, temperature rises are determined by adjusting the voltage and frequency of auxiliary power generator so that the primary current is nearly equal to the rated value.
3) Temperature rise of windings are determined by resistance method as followingformula. They give the mean temperature rises of windings.t = (R2 / R1) (235 + t1) - (235 + t2)where, R2 = resistance of windings hot, [ohm]
R1 = resistance of windings cold, [ohm]t1 = temperature of windings at the time when R1 is measured.t2 = the ambient temperature at the time when R2 is measured.235 = constant for copper
4) The measurement of temperatures after shutdown by the resistance methodrequires a quick shutdown of the motor at the end of the temperature test.If the initial resistance reading is obtained within the time interval indicated in thefollowing (Table 3), this reading is accepted as the temperature measurementand extrapolation to the instant of switching off power is unnecessary.
(Table 3)Rated output, PN [kW] Time interval after switching off power [s]
1.8.2 Judgment1) In accordance with approved spec.
HHI-A24-716(B)-0 A4(210mmx297mm)
3090120201 to 5000
50 or LESS51 to 200
(230)
7 OF 9
HHI Ⅱ. INSPECTION & TEST PROCEDURE WORK DESCRIPTION : THREE PHASE INDUCTION MOTOR PJT. No : 20071150
I.T.P No. : ITP-71150RMM062 REV. No. : 2 PAGE :
1.9 Measurement of insulation resistance
1.9.1 Method of test1) The measurement shall be carried out before and after high voltage test.2) Insulation resistance shall be measured between windings and earth withD.C 2500(V) megger on high voltage windings and D.C 500(V) meggeron low voltage windings.
1.9.2 Judgment1) Shall be more than 100 Mega-ohm
1.10 High voltage test
1.10.1 Method of test
1) The test voltage shall be applied, as specified in (Table 4), between the windingsunder test and the frame of the machine, with core and any windings or sections ofthe windings not under test and electrical circuits of auxiliary components connectedto the frame.
2) The test voltage shall be of power frequency and as near as possible to a sinewave form. However, for machines with a rated voltage 6kV or greater, whenpower frequency equipment is not available, then by agreement a d.c. test maybe carried out at a voltage 2.7 times the r.m.s value given in Table 4.
3) The test shall be started at a voltage not exceeding half of the full test voltage,and then the voltage shall be increased to the full value, steadily or in steps of notmore than 5% of the full value, the time allowed for the voltage increase from halfto full value being not less than 10 s. The full test voltage shall be maintained for1 minute.(Table 4)Item
23
HHI-A24-716(B)-0 A4(210mmx297mm)
Auxiliary components 1500V
1 Primary windings 1000V plus twice the rated voltagewith a minimum of 1500V.
Secondary windings 1000V plus twice the secondary voltage
Parts to be tested Test voltage (r.m.s)
(231)
8 OF 9
HHI Ⅱ. INSPECTION & TEST PROCEDURE WORK DESCRIPTION : THREE PHASE INDUCTION MOTOR PJT. No : 20071150
I.T.P No. : ITP-71150RMM062 REV. No. : 2 PAGE :
1.10.2 Judgment1) All windings shall withstand without any injury.
1.11 Over speed test
1.11.1 Method of test1) The motor shall be run for 2 minutes at 120% of the maximum rated speed.
1.11.2 Judgment1) The motor shall withstand without any mechanical injury.
1.12 Shaft voltage test
1.12.1 Method of test1) The shaft voltage shall be measured between D.E shaft-end and N.D.E shaft-end while the motor is running under the no-load condition at the rated frequency and voltage.
1.12.2 Judgment1) Where bearing is not insulated to prevent flow of shaft currents, Shaft voltage shall not exceed 0.5 V(peak).2) Where bearing is insulated to prevent flow of shaft currents, the shaft voltage value is only reference ( Judgement is not applied ) (Applicable code : IEEE 112)
1.13 Bearing temperature rise test
1.13.1 Method of test1) Ambient temperature (1) In case temperature of air is taken as the reference ambient, it shall be measured by means of thermometers or RTD, place at different points around and at a distance of one or two meters from the motor and half as high as its height, and protected so as to avoid effect of heat radiation and stray draughts. The mean of the measured values shall be taken. (2) If coolant is in bearing cooling system, the ambient temperature is inlet coolant temperature.
HHI-A24-716(B)-0 A4(210mmx297mm)
(232)
9 OF 9
HHI Ⅱ. INSPECTION & TEST PROCEDURE WORK DESCRIPTION : THREE PHASE INDUCTION MOTOR PJT. No : 20071150
I.T.P No. : ITP-71150RMM062 REV. No. : 2 PAGE :
2) Temperature rise of bearing are determined by means of RTD or thermometers as following formula.
t1 = T1 - T2where T1 = Temperature of bearing at the time T2 = Ambient Temperature at the time
1.13.2 Judgment1) Shall not exceed 55 degree.
1.14 Other tests (RTD & SPACE HEATER)
1.14.1 Method of test1) Measurement of resistance2) Measurement of insulation resistance3) High voltage test
1.14.2 Judgment1) In accordance with approved spec.2) The value shall be more than 10 Mega-ohm3) Shall withstand without an damage.
HHI-A24-716(B)-0 A4(210mmx297mm)
(233)
(234)