a new financial model and economic feasibility of grid ... amount of solar and biomass energy...
TRANSCRIPT
A New Financial Model and Economic
Feasibility of Grid-Connected PV Power Plants
for the Future of Renewable Energy in Turkey
Nurettin Çetinkaya Electrical and Electronics Engineering Department, Selçuk University, Konya, Turkey
Email: [email protected]
Abstract—In this study, the economic feasibility of grid-
connected photovoltaic (PV) power plants is investigated. In
addition, a new financial model for renewable power system
is proposed. The proposed structure of the financial model,
operation and economics has been examined. Other objects
of this study are to win more for both operator and the
investor, and to set out the latest legal regulation for
investment in Turkey’s emerging solar power market and to
provide some guidelines to potential investors who
appreciated country’s huge solar energy potential. Different
options customer owned systems, operation systems, and
other models are evaluated in detail. Feasibility is made for
PV power plant. The proposed financial model is applied to
PV power plant. Conclusions are discussed to find the best
financial model for solar PV power plant systems.
Index Terms—economic feasibility, photovoltaic power plant,
renewable energy support policies
I. INTRODUCTION
Today, energy is the number one problem on the world
and also will be in the future. Because energy is not the
only problem but also the social, economic and
environmental problems are also the other arising
problems. The electricity sector is a major source of the
carbon dioxide emissions that contribute to global climate
change [1]. Many countries and scientists conduct many
researches for a cleaner and more economic energy
sources [2]-[4]. Scientists also research costs of
renewable energy sources and support policies for more
green and clean world [5]-[7]. Market reforms, energy
security and environmental protection are three primary
energy policy goals of Turkish government [8]. Although
fossil fuels have been the most dominant energy resource
in meeting global energy demand for decades, it has been
recognized that these critical energy resources have
severe impacts on climate change and they are ultimately
finite. Widespread and increasing use of fossil fuels in
energy production is considered as the largest source of
anthropogenic carbon dioxide (CO2) emissions, which is
largely blamed for global warming and climate change
[9].
Manuscript received September 1, 2014; revised April 28, 2015.
Support policies in many countries are carrying on for
electrical power generation from renewable sources,
especially solar and wind. In the last decade, the
generation of electricity from solar energy, the thanks to
the support policy has become quite common. The feed-
in-tariff (FiT) policy has proven to be one of the most
effective mechanisms that encourage the deployment of
solar power. Germany is the first country to introduce a
solar FiT and has become the world leader in terms of
both installed PV capacity and solar industry. The success
of Germany gave momentum to many other countries.
Globally, more than 40 countries have adopted some type
of FiT system in order to harness their renewable energy
potential. The installed renewable power capacity has
increased considerably in many of these countries after
the introduction of FiT policy [10].
The FiTs are guaranteed for a reasonably long period
of time in order to ensure security of the investment for
investors and manufacturers [11]. The FiT term is
commonly determined such that income is guaranteed
over the lifetime of the system, i.e. at least 15-20 years.
Turkish renewable FiT is guaranteed for 10 years while
European renewable FiTs are generally guaranteed for a
longer period, i.e. 20 years or more. Turkish solar
industry calculates the return period as ten years if solar
FiT is 18-20$cent/kWh. Therefore, 10 years duration
seems to be insufficient to pay back solar investments
with a FiT of 13.3$cent/kWh [12]. But now, it can be said
that; payback times are down for unit costs are also
reduced.
Turkey is one of the fastest growing economies on the
world with economic recovery. Turkey’s annual primary
energy consumption has increased by about 8% in last
decade. Turkey has an annual electricity consumption of
246 TWh with a nearly 77 million people in 2013 that our
electricity generation was obtained from 43.8% natural
gas, 25.4% coal, 24.8% hydraulic, 2% liquid fuels and
4% renewable sources. Most of renewable resource is the
wind. Most of the resources used to generate electricity
are coal and natural gas. The share of renewable energy
sources is quite low. Moreover, the wind power plants
provide the largest contribution to renewable sources
more than the solar power plants.
International Journal of Electrical Energy, Vol. 3, No. 2, June 2015
©2015 International Journal of Electrical Energy 110doi: 10.12720/ijoee.3.2.110-114
Figure 1. Solar energy potential atlas of Turkey.
II. THE POTENTIAL OF RENEWABLE ENERGY SOURCES
IN TURKEY
The potential of renewable energy sources in Turkey
was estimated by the General Directorate of Renewable
Energy managed by Republic of Turkey Ministry of
Energy and Natural Resources (MENR) [13]. Turkey has
six different renewable and usable economic sources,
namely hydro, wind, geothermal, solar, biomass and
biogas, respectively. While the wind energy potential is
48GW, geothermal energy potential is around 32GW.
Until 2023, Turkey aims to achieve at least 30% of
electricity production obtained from renewable energy
sources [14]. At the end of 2023, 3000MW installed
capacity of solar power plants are planned to be obtained.
Turkey has a high potential for solar energy due to its
advantageous geographical position. Many studies for the
map of the solar energy potential in Turkey have been
made. Solar energy potential atlas (SEPA) of Turkey
prepared from these studies is shown in Fig. 1 [15]. Solar
Potential: It was determined that Turkey’s average period
of sunlight is 2,640 hours per year (7.2 hours per day).
The average annual radiation force amounts to 1,311
kWh/m²-year (3.6kWh/m²-per day). The solar energy
potential was calculated to be 380 billion kWh/year. As
shown in Fig. 1, the provinces of Karaman, Antalya,
Konya, Muğla, Burdur, Mersin and Van have a potential
for solar energy of striking magnitude.
Turkey supports that the renewable energy power
plants to meet the electricity needs. The law on
Electricity Production from Renewable Energy Sources
(No. 6094, Official Newspaper: 8 January 2011, No.
27809). Wind and hydroelectric power plants are
supported with 7.3$cent/kWh, geothermal power plants is
supported by the 10.5$cent/kWh.
The amount of solar and biomass energy support is at
least 13.3$cents/kWh. This support is 15.4$cent/kWh,
when domestic construction and panel manufacture are
added. The fixed ten-year guarantee of purchase price
prevent the rapid fall. The decreasing amounts of the
price support for the ten-year period allow electricity
market balancing. Especially after the fifth year, the price
must be reduced on a regular basis. In this way, the
investor deal with the installation and the operation for
the payback time is below five years.
In this paper, the feasibility studies were performed for
Antalya, Karaman and Konya provinces. The investors
are interested in these provinces due to sunshine
durations. For example, Konya province global radiation
and Konya province sunshine duration data are given in
Fig. 2 and Fig. 3, respectively.
Figure 2. Konya global radiation.
Figure 3. Konya sunshine duration.
International Journal of Electrical Energy, Vol. 3, No. 2, June 2015
©2015 International Journal of Electrical Energy 111
The sunshine durations of Antalya province and
Karaman province are higher than the sunshine durations
of Konya province.
III. PROPOSED FINANCIAL MODEL
In this study, the proposed model has four different
sections and can be referred to briefly as build-operate-
transfer-operate (boto). This model aims to combine the
investor and the operator who do not want to take all the
risks or have not 100% of money for investment. The
proposed model is suitable for the investors who are
landowner and the operators who can make installation.
The sections of the proposed model are shown in Fig. 4.
Figure 4. Sections of the proposed model.
The installation time and the operation transfer
agreement should be made in Section 1 (Build). In this
section, the investors and the operators work together.
Section 2 (Operate) is the period of the operator’s itself
financial guarantee. During this period, the operator is
solely responsible for everything. In Section 3 (Transfer),
the annual minimum power generation agreement should
be made. In Section 4 (Operate), the investors and
operators made a partnership agreement and work
together. The investors and operators are always a partner
in a company. The operator is alone in the first operation
section, but operator and investor work together in the
second operate section.
Some of these sections or different types of renewable
power systems have been proposed previously [16].
Particularly the build-own-operate (boo) and build-own-
operate-transfer (boot) models were considerably applied
[17]. The difference of this study is the investor and
operator carries on their benefits end of the feasible time.
In this way, the risk sharing will occur. The aim is to be
conscious of both sides and to consider the possible risks.
The investor, the source of the money must research
prices and the properties of the PV power plant parts. The
investor and the operator adopt PV power plant together.
A portion of installation costs shall be borne by the
investor. The rate of the installation cost will share
depends on the agreement between the investor and the
operator.
If the credit is used, the principal and the interest
payment times should never exceed the operation time in
boot model. The disadvantages of the boot model are the
service provider should bear the share capital costs and
the performance of system operation at end of life
conditions.
The operation and maintenance will be the part of the
supplier and no risk for investors in boo models. If the
PV power plant is not performing as per the defined
performance level, the financial risk will occur for the
investor.
IV. ECONOMIC FEASIBILITY OF GRID CONNECTED PV
POWER PLANT
The economic feasibility study summarizing the four
different cases is shown in Table I. The characteristics of
PV power plant are shown in Table II.
TABLE I. COMPARISON OF THE CASE STUDIES
case 1 case 2 case 3 case 4
Province Konya Konya Karaman Antalya
Financial model boo, boot boto boto boto
installed power [kWp] 1,000 1,000 1,000 1,000
land [K€] 300 0 0 0
PV panel [K€] 580 580 580 580
inverter [K€] 100 100 100 100
concrete, construct. [K€] 100 100 100 100
design, project [K€] 50 50 50 50
electrical facilities [K€] 100 100 100 100
security, fence [K€] 20 20 20 20
transport., insurance [K€] 20 20 20 20
total investment cost [K€] 1,270 970 970 970
unit cost [€/kWp] 1,270 970 970 970
ann. energy prod.[MWh] 1,480 1,480 1,530 1,590
ann. energy profit [K€/year]
151.5 175.3 181.2 188.3
carbon emissions
[tone/year] 792 792 819 851
carbon profit [€/tone] 0 20 20 20
ann. carbon profit
[K€/year] 0 15.8 16.3 17.0
ann. operation, maintenance [K€/year]
12 12 12 12
ann. land rental fee
[K€/year] 0 20 20 20
ann. net profit [€/year] 139.5 159.1 165.6 173.3
payback time [year] 9.10 6.09 5.86 5.60
The following equations were used for the
calculations in Table I.
payback time [year] = total investment cost [€] /
annual net profit [€/year] (1)
annual net profit [€/year] = annual energy profit [€/year]
+ annual carbon profit [€/year] - annual operation, maint.
[€/year] - annual land rental fee [€/year] (2)
annual energy profit [€/year] = annual energy production
[kWh] * support price [€/kWh] (3)
annual carbon profit [€/year] = carbon emissions
[tone/year] * carbon profit [€/tone] (4)
International Journal of Electrical Energy, Vol. 3, No. 2, June 2015
©2015 International Journal of Electrical Energy 112
Konya, Konya, Karaman and Antalya, respectively. The
annual energy productions of the solar power plants were
calculated using the Photovoltaic Geographical
Information System (PVGIS) values [18]. In the case1
study, the land cost has been included and the amount of
support has been taken as 13.3 dollar cents/kWh. The
carbon support has not been taken into consideration. So
case1 study can be considered as the worst case. In this
study, the payback time is the maximum. In case 2, case 3
and case 4; the cost of the land has not been taken into
consideration. The amount of support has been 15.4
dollar cents/kWh and carbon support has been taken into
consideration. So case 4 study can be considered as the
best case. In this study, the payback time is the minimum.
In the calculations, the carbon emission for Turkey is
assumed as 0.535 [kg/kWh]. Euro/dollar parity is taken as
1.3.
TABLE II. CHARACTERISTICS OF PV POWER PLANT
panel power 250 W
panel efficiency 14.50%
efficiency drop 10 years 90% 25 years 80%
operating temperatures -40/+85
inverter power 50 kW
inverter input voltage 1000 VDC
inverter efficiency 98%
total PV plant power 1000 kWp
grounding, lightning protection yes
data recording, remote monitoring yes
construction yes
transformer, switchgears yes
environmental security fence
camera recording system yes
PV plant power is taken as 1MW, because the
unlicensed electricity generation limit is 1MW in Turkey.
The goal of many investors is the 1MW power plants.
Panel power has been selected as 250W. Because, the
panels are less than 250W, the yields are lower. The
inverter power has been selected as the 50kW, because
the voltage drop problem occurs when very high and very
small power inverters are used.
V. CONCLUSION
It is clear that the support time for renewable energy
for Turkey is sufficient, and the support times for
renewable energy in fixed-price support policies
definitely should not exceed 10 years. The installation
costs are not reduced as long as the long-term support.
And the support times for renewable energy in reduced-
price support policies can be increased to 15-20 years. In
this study, the proposed model seems to be more
appropriate because the economic feasibility times are
under 10 years.
Turkey should continue the renewable energy support
policies for to reach year 2023 target. The renewable
energy support should not only be done in time and cost,
but also the panel efficiency or total power system
efficiency must also be added into the support policies.
That will accelerate the transition to more efficient
renewable systems. In this way, more informed investors
and operators will earn more.
The investors, operators, the power system
management and the legislators should work together for
cleaner and more economical power systems.
REFERENCES
[1] K. Palmer and D. Burtraw, “Cost-Effectiveness of renewable
electricity policies,” Energy Economics, vol. 27, pp. 873-894, Nov. 2005.
[2] F. Oğuz, K. A. Akkemik, and K. Göksal, “Can law impose
competition? A critical discussion and evidence from the Turkish electricity generation market,” Renewable and Sustainable Energy
Reviews, vol. 30, pp. 381-387, 2014. [3] F. Gokgoz and M. E. Atmaca, “Financial optimization in the
Turkish electricity market: Markowitz’s mean-variance approach,”
Renewable and Sustainable Energy Reviews, vol. 16, pp. 357-368, 2012.
[4] A. J. Ding and A. Somani, “A long-term investment planning model for mixed energy infrastructure integrated with renewable
energy,” in Proc. IEEE Green Technologies Conf., Grapevine,
2010, pp. 1-10. [5] R. Haasa, W. Eichhammer, et al., “How to promote renewable
energy systems successfully and effectively,” Energy Policy, vol. 32, pp. 833-839, 2004.
[6] F. Dincer, “The analysis on photovoltaic electricity generation
status, potential and policies of the leading countries in solar energy,” Renewable and Sustainable Energy Reviews, vol. 15, pp.
713-720, 2011. [7] H. Benli, “Potential of renewable energy in electrical energy
production and sustainable energy development of Turkey:
Performance and policies,” Renewable Energy, vol. 50, pp. 33-46, 2013.
[8] S. O. Topkaya, “A discussion on recent developments in Turkey’s emerging solar power market,” Renewable and Sustainable
Energy Reviews, vol. 16, pp. 3754-3765, Apr. 2012.
[9] Z. B. Erdem, “The contribution of renewable resources in meeting Turkey’s energy related challenges,” Renewable Sustainable
Energy Rev., vol. 14, no. 9, pp. 2710-2722, Dec. 2010. [10] EPIA (European Photovoltaic Industry Association) and
Greenpeace, “Solar generation: Solar photovoltaic electricity
empowering the world,” 2011. [11] M. Mendonca and J. Corre, “Success story: Feed-In-Tariffs
support renewable energy in Germany,” 2008. [12] Yenilenebilir enerji kaynaklarının elektrik enerjisi. [Online].
Available:
http://www.resmigazete.gov.tr/eskiler/2011/01/20110108-3.htm [13] Yenilenebilir Enerji Genel Müdürlüğü. [Online]. Available:
http://www.eie.gov.tr [14] S. Caynak, “Renewable energy strategy of Turkey,” in Proc. ICCI
2012 18. International Energy & Environment Fair and Conf.,
Istanbul, 2012.
http://www.eie.gov.tr/MyCalculator/Default.aspx [16] V. Bobinaite and D. Tarvydas, “Financing instruments and
channels for the increasing production and consumption of
renewable energy: Lithuanian case,” Renewable and Sustainable Energy Reviews, vol. 38, pp. 259-276, 2014.
[17] G. Somasekhar, G. Bharathi, and M. GirijaEureka, “Marketing
methodology of solar PV power packs,” Journal of Economics
and Finance (IOSR-JEF), vol. 1, pp. 38-43, 2014.
[18] Photovoltaic Geographical Information System. [Online]. Available: http://re.jrc.ec.europa.eu/pvgis/apps4/pvest.php
International Journal of Electrical Energy, Vol. 3, No. 2, June 2015
©2015 International Journal of Electrical Energy 113
Case1, case 2, case 3 and case 4 studies were made for
.[15] Güneş Enerjisi Potansiyel Atlasi (GEPA). [Online]. Available:
Nurettin Çetinkaya was born in Kayseri in 1972. He graduated from Konya, Selçuk
University electrical and electronics
engineering department in 1993. He received a master’s degree in electrical and electronic
engineering department in 1998. He received the PhD degree from Electrical-Electronics
Engineering, Graduate School of Natural
Sciences, Konya, Turkey in 2005. His research area includes power system planning, power
system control, energy efficiency, renewable energy, power system economics and management.
Until 2005 he worked as a research assistant for 10 years. He worked as
a consultant in Konya organized industrial zone. He is currently working as a lecturer in the Faculty of Engineering, Electrical and
Electronics Engineering Department, Selçuk University, Konya, Turkey. Dr. Çetinkaya received publication awards given by Scientific Research
Projects Coordination Unit and The Scientific and Technological
Research Council of Turkey.
International Journal of Electrical Energy, Vol. 3, No. 2, June 2015
©2015 International Journal of Electrical Energy 114