a method used to evaluate potential effects on flooding
TRANSCRIPT
Using HECUsing HEC--RAS to Project Effects RAS to Project Effects of Increased Flooding with the of Increased Flooding with the
Placement of Large Woody Placement of Large Woody DebrisDebris
Jeff Burkey Jeff Burkey –– King County DNRPKing County DNRP
Project Team: Dan Eastman, Doug Chin, John Bethel, Project Team: Dan Eastman, Doug Chin, John Bethel, Meredith RadellaMeredith Radella
(May 2008)(May 2008)
Increasing Roughness Suggests Increasing Roughness Suggests Flows may seek alternative Flows may seek alternative
paths?paths?
Jeff Burkey Jeff Burkey –– King County DNRPKing County DNRP
Project Team: Dan Eastman, Doug Chin, John Bethel, Project Team: Dan Eastman, Doug Chin, John Bethel, Meredith RadellaMeredith Radella
(May 2008)(May 2008)
Effects to stream flooding with Effects to stream flooding with the introduction of solid phase the introduction of solid phase matter in large quantities of matter in large quantities of
CCxxHHxxOOxx??
Jeff Burkey Jeff Burkey –– King County DNRPKing County DNRP
Project Team: Dan Eastman, Doug Chin, John Bethel, Project Team: Dan Eastman, Doug Chin, John Bethel, Meredith RadellaMeredith Radella
(May 2008)(May 2008)
A Method Used to Evaluate A Method Used to Evaluate Potential Effects on Flooding with Potential Effects on Flooding with the Placement of Large Woody the Placement of Large Woody
MaterialMaterial
Jeff Burkey Jeff Burkey –– King County DNRPKing County DNRP
Project Team: Dan Eastman, Doug Chin, John Bethel, Project Team: Dan Eastman, Doug Chin, John Bethel, Meredith Radella, Jeff BurkeyMeredith Radella, Jeff Burkey
(May 2008)(May 2008)
Tributaries in basin with projectTributaries in basin with project
Add complexity and you might Add complexity and you might get thisget this
Examples of complexityExamples of complexity
Site LocationSite Location
Site ConditionsSite Conditions
•• 26 Square Miles26 Square Miles•• Land Use Land Use ––
–– AgriculturalAgricultural–– ResidentialResidential–– Forest ManagementForest Management–– CommercialCommercial
Relevant Site ConditionsRelevant Site Conditions
•• Subbasin Flow RatesSubbasin Flow Rates•• River Stage ConditionsRiver Stage Conditions•• TopographyTopography•• Expected flow pathsExpected flow paths
Translate to Model SetupTranslate to Model Setup
•• Boundary ConditionsBoundary Conditions•• Landscape roughness Landscape roughness •• Channel GeometryChannel Geometry•• Overland GeometryOverland Geometry
Upstream Boundary ConditionsUpstream Boundary Conditions
Newaukum Creek Peak Annual Flow FrequencyUSGS 12108500
(Water Year 1945 - 2006)
Return Period (years)
1 10 100
Pea
k A
nnua
l Flo
w R
ate
(cfs
)
0
500
1000
1500
2000
2500
3000
Observed(Gringerton PP)17BUpper/Lower CI
2600 cfs
Does this flow create a steady-state condition?
Not likely…
Upstream Boundary ConditionsUpstream Boundary Conditions
Newaukum Creek Peak Annual Flow FrequencyUSGS 12108500
(Water Year 1945 - 2006)
Return Period (years)
1 10 100
Pea
k A
nnua
l Flo
w R
ate
(cfs
)
0
500
1000
1500
2000
2500
3000
Observed(Gringerton PP)17BUpper/Lower CI
2600 cfs
Does this flow create a steady-state condition?
Not likely…
Newaukum Creek February 1996 Storm EventAssumed Steady state
Time (hourly increments)
2/4 2/5 2/6 2/7 2/8 2/9 2/10 2/11 2/12 2/13 2/14 2/15
Hou
rly M
ean
Flow
Rat
e (c
fs)
0
500
1000
1500
2000
2500
3000
Upstream Boundary ConditionsUpstream Boundary Conditions
Newaukum Creek Peak Annual Flow FrequencyUSGS 12108500
(Water Year 1945 - 2006)
Return Period (years)
1 10 100
Pea
k A
nnua
l Flo
w R
ate
(cfs
)
0
500
1000
1500
2000
2500
3000
Observed(Gringerton PP)17BUpper/Lower CI
2600 cfs
Does this flow create a steady-state condition?
Not likely…
Newaukum Creek February 1996 Storm EventAssumed Steady state
Time (hourly increments)
2/4 2/5 2/6 2/7 2/8 2/9 2/10 2/11 2/12 2/13 2/14 2/15
Hou
rly M
ean
Flow
Rat
e (c
fs)
0
500
1000
1500
2000
2500
3000
Newaukum Creek February 1996 Storm Event(USGS 12108500)
Time (hourly increments)2/4 2/5 2/6 2/7 2/8 2/9 2/10 2/11 2/12 2/13 2/14 2/15
Hou
rly M
ean
Flow
Rat
e (c
fs)
0
500
1000
1500
2000
2500
3000
50 hrs20 hrs
Upstream Boundary ConditionsUpstream Boundary Conditions
2600 cfs
Does this flow create a steady-state condition?
Not likely…
Newaukum Creek February 1996 Storm EventAssumed Steady state
Time (hourly increments)
2/4 2/5 2/6 2/7 2/8 2/9 2/10 2/11 2/12 2/13 2/14 2/15
Hou
rly M
ean
Flow
Rat
e (c
fs)
0
500
1000
1500
2000
2500
3000
Newaukum Creek February 1996 Storm Event(USGS 12108500)
Time (hourly increments)2/4 2/5 2/6 2/7 2/8 2/9 2/10 2/11 2/12 2/13 2/14 2/15
Hou
rly M
ean
Flow
Rat
e (c
fs)
0
500
1000
1500
2000
2500
3000
50 hrs20 hrs
Downstream Boundary ConditionsDownstream Boundary Conditions
191000 192000 193000 194000 195000 196000
145
150
155
160
Plan 03
Main Channel Distance (ft)
Ele
vatio
n N
AV
D88
(ft)
Legend
WS PF 1
WS PF 2
WS PF 3
WS PF 4
WS PF 5
Ground
ROB
40.4
20
40.4
729*
40.5
25
40.5
913*
40.7
62
Green River Mainstem
Estimates of Over Bank RoughnessEstimates of Over Bank Roughness
USGS n = 0.10Newaukum Over bank area
(n = 0.10)
Model GeometryModel Geometry
•• Existing LiDARExisting LiDAR•• Existing LiDARExisting LiDAR•• Conducted SurveyConducted Survey•• Composite (LiDAR + Composite (LiDAR +
Survey) TINSurvey) TIN
•• Existing LiDARExisting LiDAR•• Conducted SurveyConducted Survey
Expected Flow PathsExpected Flow Paths
•• Main ChannelMain Channel•• Main ChannelMain Channel•• Over bank pathsOver bank paths
HoweverHowever……
LiDAR shows a Historical DeltaLiDAR shows a Historical Delta
Existing Conditions Model DesignExisting Conditions Model Design
•• CrossCross--section section alignmentalignment
•• CrossCross--section section alignmentalignment
•• Divide not absoluteDivide not absolute
•• CrossCross--section section alignmentalignment
•• Divide not absoluteDivide not absolute•• Flows Exchange Flows Exchange
between reaches at between reaches at higher flood flow higher flood flow ratesrates
•• CrossCross--section section alignmentalignment
•• Divide not absoluteDivide not absolute•• Flows Exchange Flows Exchange
between reaches at between reaches at higher flood flow higher flood flow ratesrates
•• Low point in divide Low point in divide shown with red arrowshown with red arrow
Numerical Representation of Placed Numerical Representation of Placed Large Woody MaterialLarge Woody Material
•• Concept Abstracted Concept Abstracted from Tim Abbyfrom Tim Abby
•• Multiple vertical Multiple vertical obstructions allows obstructions allows flow around, and overflow around, and over
•• Modified to assume Modified to assume 1010--percent porositypercent porosity
•• Paired CrossPaired Cross--sections sections with obstructions.with obstructions.
0 100 200 300154
156
158
160
162
164
166
168
Plan 39River = Mi ddl eNewauk Reach = R
Stati on (ft)
Elevation (ft)
.1 .04 .1
An example of Placements of Large An example of Placements of Large Woody MaterialWoody Material
164.15 118.42
96.93* 88.79*
62.34
948.89
902.47
872.16 849.39 822.97
798.44 765.06
681.22 653.30
639.26
609.39 583.85
564.95 547.59
484.19 467.29
452.33
422.82 394.28 376.383*
367.63
343.03
311.81
278.80
261.33
206.47 196.68*
186.89
Full 5Jam 100yr
Legend
Ground
Levee
Bank Sta
Ground
Ineff
Design of models are dependant on Design of models are dependant on the questions askedthe questions asked
•• Is there an increase in over bank flooding in the pasture Is there an increase in over bank flooding in the pasture area as a result of the proposed LWM?area as a result of the proposed LWM?
•• With the landscape berm in place, what is the expected With the landscape berm in place, what is the expected 100100--year water surface elevation of the impoundment year water surface elevation of the impoundment area?area?
•• At what frequency is the over bank flooding expected to At what frequency is the over bank flooding expected to occur in the proposed impoundment area?occur in the proposed impoundment area?
•• What are the projected benefits gained from this project What are the projected benefits gained from this project design with respect to flooding extents?design with respect to flooding extents?
Design Methods for Design Methods for Simulating Flow ExchangesSimulating Flow ExchangesExisting Conditions Landscape Berm: Full Containment
Design Methods for Design Methods for Simulating Flow ExchangesSimulating Flow ExchangesLandscape Berm: Short Loop Reach
Landscape Berm: Extend Cross-sections
Projection of FloodingProjection of Flooding
Results attempt to Results attempt to answer the flowing answer the flowing questions:questions:
•• Where will flooding Where will flooding occur?occur?
•• At what flow rates will At what flow rates will flooding occur?flooding occur?
•• How deep will How deep will flooding be?flooding be?
Results are under review.
Thank you!Thank you!
Photos shown were taken by Photos shown were taken by Project team membersProject team members