a joint initiative of government of india and government of rajasthan

93
1 24x7-Power For All A joint initiative of Government of India & Government of Rajasthan December 2014

Upload: vunhan

Post on 01-Jan-2017

237 views

Category:

Documents


10 download

TRANSCRIPT

Page 1: A Joint Initiative of Government of India and Government of Rajasthan

1

24x7-Power For All

A joint initiative of

Government of India

&

Government of Rajasthan

December 2014

Page 2: A Joint Initiative of Government of India and Government of Rajasthan

2

Page 3: A Joint Initiative of Government of India and Government of Rajasthan

3

Table of Contents

1. INTRODUCTION .................................................................................................... 5

2. POWER SUPPLY POSITION ...................................................................................... 7

2.1. POWER SUPPLY POSITION .......................................................................... 7

2.2. DEMAND PROJECTIONS ............................................................................. 8

3. GENERATION PLAN ............................................................................................. 12

3.1. EXISTING GENERATION CAPACITY ............................................................... 12

3.2. POWER PROCUREMENT COSTS ................................................................... 14

3.3. ISSUES REGARDING COAL PROCUREMENT PLAN ................................................ 14

3.4. ACTION PLAN – STATE ............................................................................ 18

3.5. GOI INTERVENTION ............................................................................... 18

3.6. FUND REQUIREMENT ............................................................................. 19

3.7. RENEWABLE ENERGY PLAN ....................................................................... 19

3.8. GOI INTERVENTION ......................................................................... 20

4. TRANSMISSION PLAN ........................................................................................... 21

4.1. INTER-STATE TRANSMISSION SYSTEM ............................................................ 21

4.2. INTRA STATE TRANSMISSION SYSTEM ........................................................... 27

5. DISTRIBUTION PLAN ............................................................................................ 31

5.1. EXISTING DISTRIBUTION SYSTEM .......................................................... 31

5.2. SCHEMES UNDER IMPLEMENTATION ............................................................. 31

5.3. PROPOSED SCHEMES ............................................................................. 32

5.4. CONNECTING THE UNCONNECTED ............................................................... 37

5.1. FUND REQUIREMENT ............................................................................. 38

5.2. ACTION POINT- STATE ............................................................................ 39

5.3. GOI INTERVENTION .............................................................................. 39

5.4. RENEWABLE ENERGY INITIATIVES OF GOVT OF RAJASTHAN AT CONSUMER LEVEL ............ 40

5.5. ACTION PLAN - STATE –RENEWABLE ENERGY .................................................. 41

5.6. GOI INTERVENTION .......................................................................... 41

6. ENERGY EFFICIENCY ........................................................................................... 42

7. FINANCIAL VIABILITY OF DISTRIBUTION COMPANIES .............................................. 50

7.1. FINANCIAL POSITION OF DISTRIBUTION UTILITIES ............................................ 50

7.2. FINANCIAL RESTRUCTURING SCHEME OF GOI (OCTOBER 2012).............................. 50

7.1. LOSS REDUCTION, ENERGY MANAGEMENT &, ENERGY ACCOUNTING ..................... 54

7.2. GOI INTERVENTION .............................................................................. 58

7.3. ACTION POINTS ( DISCOMS / STATE GOVT) ...................................................... 58

7.4. MANAGING THE RISKS ............................................................................. 59

7.5. INVESTMENT PLANNING AND MONITORING MECHANISM ....................................... 60

Page 4: A Joint Initiative of Government of India and Government of Rajasthan

4

8. OTHER INITIATIVES............................................................................................. 62

8.1. COMMUNICATION ................................................................................. 62

8.2. INFORMATION TECHNOLOGY (IT) INITIATIVES .............................................. 62

8.3. INSTITUTIONAL ARRANGEMENT .................................................................. 63

8.4. CAPACITY BUILDING .............................................................................. 64

9. YEAR WSIE ROLL OUT PLAN ................................................................................. 65

10. SECTOR WISE INVESTMENT PLAN AND FUND REQUIREMENT ..................................... 67

11. ANNEXURES ....................................................................................................... 70

Page 5: A Joint Initiative of Government of India and Government of Rajasthan

5

1. INTRODUCTION

Rajasthan is the largest state in geographical

area in the country. It comprises of vast arid

land and desert region. Agriculture is the main

vocation of the people in the State. State has

very little surface water irrigation potential,

which has been almost fully exploited. Ground

water is main source of irrigation.

The power sector in Rajasthan has witnessed

substantial improvement over the past decade

due to increase in generation capacity and

strengthening of network infrastructure

leading to an improvement in the overall

power supply position of the state. Currently,

most connected consumers in the state are

being provided with at least 21-22 hours of

power supply. However, there are areas in the

state which experience unduly long

interruptions in power supply due to

inadequacies in the distribution infrastructure.

Moreover, a large portion of non-agriculture

consumers in rural areas are supplied through

single phase only. Further, there is a large

section of households in the state i.e. about 29

%, which is yet to be electrified.

Electricity is a concurrent subject and

distribution of electricity falls under the

purview of the respective State

Government/State Power Utility. As per

Electricity Act 2003, it is the duty of a

distribution licensee to develop and maintain

an efficient, co-ordinated and economical

distribution system in his area of supply and to

supply electricity in accordance with the

provisions contained in the Act. The State

Electricity Regulatory Commission (SERC)

shall specify or enforce standards with respect

to quality, continuity and reliability of service

by licensees. Accordingly, State Electricity

Regulatory Commissions (SERCs) have

notified the Standards of Performance

specifying maximum allowable time for

restoration of supply due to forced

breakdowns and Supply Code specifying the

supply voltages & frequency etc, to be

followed by Discoms. SERCs also monitors

the performance of distribution companies on

the basis of notified Performance of Standards.

To supplement the efforts of State

Government, Government of India and

Government of Rajasthan have taken a joint

initiative to provide 24 X 7 power in the state

to all consumers (except agriculture

consumers). Agriculture consumers will be

provided 6.5 -7 Hrs. of supply daily. This

initiatives aims at ensuring uninterrupted

supply of quality power to existing consumers

by the end of 12th

plan and providing access to

electricity to all unconnected consumers in the

next five years.

An exercise has been carried out to assess the

additional energy requirement for providing

24x7 power supply to all households in the

state, financial implications on utilities for

procuring additional energy and per unit

implication on tariff for additional energy.

Based on the exercise, the sensitivity analysis

has been carried out for cost of service and

resulting Financial Gap under multiple

scenarios on various parameters namely, tariff

hike, reduction in power procurement cost,

increase in interest and moratorium period,

AT&C loss reduction, etc.

An assessment of the adequacy of availability

of power to the state from various sources i.e.

from generating sources owned by the state

both existing and under construction, from

central sector stations both existing and under

construction, Common projects, generating

sources owned by private sector and PPAs

have been made. Inter State Transmission

System (ISTS), Intra state Transmission

System and distribution infrastructure have

been reviewed to ensure their adequacy for

providing 24x7 power in the states. Works

required for strengthening and augmentation

of distribution infrastructure have been

identified for supplying uninterrupted power

to the consumers. Central Government will

supplement the efforts of the State

Page 6: A Joint Initiative of Government of India and Government of Rajasthan

6

Government through schemes which are being

finalised by Ministry of Power for funding of

works required for strengthening and

augmentation of distribution infrastructure,

feeder segregation and 100% metering.

The initiatives for providing 24x7 power in the

state mainly includes-

1. Reliable 24X7 supply to the consumers

(except agriculture) within a period of

three years of commencement of the

program. Agriculture consumers will be

supplied power for 6.5-7 Hrs daily.

2. All unconnected households to be

provided access to electricity in a time

bound manner in next five years i.e. by FY

2018-19.

3. To ensure adequate capacity addition

planning & tie ups for power from various

sources at affordable price to meet the

projected increase in power demand for

future.

4. Strengthen the Transmission and

Distribution network to cater to the

expected growth in demand of existing as

well as forthcoming consumers.

5. Financial measures including optimizing

investments and undertaking necessary

balance sheet restructuring measures to

ensure liquidity in the utility finances.

6. To ensure reduction of AT & C losses as

per the agreed loss reduction trajectory.

7. Measures such as energy mix

optimization, reduction in power

procurement costs, improving operational

efficiency of state generation plant(s) and

optimal fuel procurement costs including

sources of supply.

8. Introduce modern technologies to monitor

reliable supply like sub-station automation,

providing adequate communication

infrastructure, GIS, Reliability, Centralised

Network Analysis and Planning tools, SAP

driven ERP systems, DMS (Distribution

Management Systems), OMS (Outage

Management System), etc.

9. Monitoring the timely commissioning of

various generating plants, transmission and

distribution infrastructure to meet the

expected growth in demand.

10. To meet the performance standards of

supply of electricity as mandated by the

Regulators.

An Action plan has been drawn based on the

above covenants which will be executed by

the State Govt with the support of Govt of

India, wherever necessary, as per their

approved plans, schemes and policies. This

joint initiative of Government of India and

Government of Rajasthan aims to enhance the

satisfaction levels of the consumers, improve

the quality of life of people, and increase the

economic activities resulting into inclusive

development of the State.

Page 7: A Joint Initiative of Government of India and Government of Rajasthan

7

2. POWER SUPPLY POSITION

2.1. POWER SUPPLY POSITION

Maximum peak demand in Rajasthan attained

so far was 10,047 MW during last year (2013-

14) which was also met almost in full.

Similarly, the energy availability was 58042

MUs against the requirement of 58202 MUs.

The gap between energy requirement and

energy availability in Rajasthan is on the

decline since 2011-12 when it was 3.9% and it

has now come down to less than 1%.

Similarly, demand-supply gap during peak

hours in the state has reduced from 7.1% in

2011-12 to almost Nil at present due to

significant addition in generation capacity

during the 11th Plan and the 12th Plan period

so far. The table 2.1 shows the trends of power

supply position in Rajasthan.

Rajasthan got benefit of about 2339 MW

(Excluding RES) from the power projects

commissioned during 11th

Plan with 434 MW

from Central sector stations, 1290 MW from

State Sector stations, 540 MW from private

sector stations and 75 MW from Mundra

UMPP.

The state’s likely benefit from the power

stations planned to come up by the end of 12th

plan period would be about 4859 MW, which

includes 1307 MW from Central sector projects,

1260 MW from State sector projects and 2292

MW from Private Sector projects. All the State

and Private sector power projects and a few

Central sector projects, which were planned to

come up during the 12th

plan period, already

stand commissioned providing a benefit of

about 3,813 MW to the state. Additional benefit

of about 1050 MW will be available to

Rajasthan from the Central Sector projects,

which have to come up by the end of the 12th

Plan.

The sizable benefit of about 6,150 MW from the

power projects commissioned in Rajasthan and

other parts of the country subsequent to the end

of 10th

Plan has helped Rajasthan become

almost self-reliant in meeting the demand of

power in the state today.

Table 2.1: POWER SUPPLY POSITION IN RAJASTHAN SINCE 9th

PLAN END

PERIOD

PEAK

DEMAND

(MW)

PEAK

MET

(MW)

PEAK

DEFICIT/

SURPLU

S

(MW)

(- / +)

PEAK

DEFICIT/

SURPLU

S

( % )

(- / +)

ENERG

Y

REQUI-

RMENT

(MU)

ENERGY

AVAIL-

ABILITY

(MU)

ENERGY

DEFICIT/

SURPLUS

(MU)

(- / +)

ENERGY

DEFICIT/

SURPLU

S

( % )

(- / +)

9TH PLAN

END 3700 3657 -43 -1.2 24745 24495 -250 -1.0

10TH PLAN

END 5794 4946 -848 -14.6 33236 31715 -1521 -4.6

2007-08 6374 5564 -810 -12.7 36738 35597 -1141 -3.1

2008-09 6303 6101 -202 -3.2 37797 37388 -409 -1.1

2009-10 6,859 6,859 0 0.0 44,109 43,062 -1,047 -2.4

2010-11 7,729 7,442 -287 -3.7 45,261 44,836 -425 -0.9

2011-12 8,188 7,605 -583 -7.1 51,474 49,491 -1,983 -3.9

2012-13 8,940 8,515 -425 -4.8 55,538 53,868 -1,670 -3.0

2013-14 10,047 10,038 -9 -0.1 58,202 58,042 -160 -0.3

Page 8: A Joint Initiative of Government of India and Government of Rajasthan

8

2.2. DEMAND PROJECTIONS

The present energy requirement of Rajasthan

is of the order of 58.9 BU per year and the

introduction of 24X7 supply across the State is

likely to increase the electricity consumption

substantially in the State. The demand can be

classified in three broad categories.

(a) Demand on account of 24X 7 power

supply to already electrified households

(b) Demand on account of 24X7 power

supply to already electrified other than

domestic category

(c) Demand from electrification of un-

electrified households

Estimation of demand considering the 24X7

supply program

As per Census 2011 data, there were about

125.81 Lakhs households in the State and

67% households were using electricity as

main source of lighting in the state. The

details of households as per census 2011 are

as under:

Census 2011 Data of Rajasthan

No. of Households in Rajasthan

Households using

Electricity as Main

Source of Lighting

Balance Un-electrified Households

Total 1,25,81,303

84,30,040 (67%)

41,51,263 (33%)

Urban 30,90,940 (24.6%)

29,01,680 (93.9%)

1,89,260 (6.1%)

Rural 94,90,363 (75.4%)

55,28,360 (58.3%)

39,62,003 (41.7%)

(Source: Census of India )

The no of Households in the state in 2014

based on census 2011 data and Compound

Annual Growth Rate (CAGR) of 20 years

(census of 1991 & 2011) works out to be

139.99 Lakhs ( 105.22 Lakhs Rural & 34.77

Lakhs Urban). However, as per GoR, as on

01-Apr-2014 there are about 125 Lakhs

households in the State (Rural 93.05 lakhs and

Urban 32.16 lakhs). Out of this 58.20 lakhs

households in rural area and 30.26 lakhs

households in urban area are electrified

leaving a balance of 34.85 lakhs households in

rural area and 1.9 lakhs households in urban

areas yet to be electrified. The total no of un-

electrified households in the State of

Rajasthan based on Census figures and as per

GoR are as under-

Particulars As per

Census

figures

As per GoR

Total Households 139,98,504 125,21,000

Rural Households 105,21,699 93,05,000

Urban Households 34,76,805 32,16,000

Total Electrified

H/H

88,47,763

Rural Electrified

H/H

5,820,819

Urban Electrified

H/H

30,26,944

Total Un-electrified

H/H

51,50,741 36,73,237

Urban Un-

electrified H/H

4,49,861 1,89,056

Rural Un-

electrified H/H

47,00,880 34,84,181

In urban area, only 15,000 applications are

pending for connections and remaining

households may be utilizing electricity on

share basis as a united family. Out of 34.85

lakhs un-electrified rural households in the

state, only about 25 lakhs households may be

considered as un-electrified as balance

households may be using the electricity on

shared basis as a united family. Considering

the fast growth in urban area and looking to

the past trend, 5 lakhs connection are likely to

be released in urban areas in next five years

considering one lakh connections per year.

To compute the demand from hitherto un-

electrified households the following steps have

been adopted:

(a) The number of electrified and un-

electrified households in 2014 has been

taken as per Govt of Rajasthan data.

Page 9: A Joint Initiative of Government of India and Government of Rajasthan

9

(b) The electrification of 30 Lakh un-

electrified households have been

considered as per GoR data.

(c) Based on the urban & rural consumption

data provided by GoR, present per

household consumption has been assessed.

(d) Energy requirement for rural & urban

households have been computed based on

the latent demand and considering growth

of per household consumption from the

current levels of 1.96 units/day to 3 units/

day in rural areas by 2018-19 and from 5.5

units/day to 8 units /day in urban areas by

2018-19.

(e) Demand projections for consumers other

than domestic have been taken as per

Financial Restructuring Plan (FRP).

(f) Basis the above, the overall consumption

for domestic & non domestic have been

estimated for the state.

The overall energy requirement for state of

Rajasthan by 2018-19 based on the above is

given in the tables below.

(a) Demand from electrified households

The improvement of supply as well as natural load growth will result in increase of the consumption

levels in the hitherto electrified households. The overall consumption and the additional

consumption have been estimated by projecting an increase in per household consumption from the

current levels of 1.96 units/day to 3 units/ day in rural areas by 2018-19 and from 5.5 units/day to 8

units /day in urban areas by 2018-19 in the table below.

Table 2.2: ENERGY REQUIREMENT FOR ALREADY ELECTRIFIED HOUSEHOLDS

S.

No.

Particulars→

Calculation

steps

Rajasthan

2014-

15

2015-

16

2016-

17 2017-18 2018-19

A DEMAND PROJECTIONS FOR ELECTRIFIED HOUSEHOLDS

1 Consumption of Rural Electrified Households

2 Consumption (units per

day per household)

Units 2.0 2.3 2.5 2.8 3.0

3 Annual Energy

Requirement for

58,20,819 Rural

Household

MUs 4,249 4,905 5,592 6,312 7,066

4 Consumption of Urban Electrified Households

5 Consumption (units per

day per household)

Units 5.50 6.1 6.8 7.4 8.0

6 Annual Energy

Requirement for

30,26,944 Urban

Household

MUs 6,077 6,969 7,910 8,901 9,944

7 Total Annual Energy

Requirement due to

existing electrified

households(A3+A6)

(A3 + A6) MUs 10,326 11,875 13,503 15,213 17,010

A1 ADDITIONAL ENERGY REQUIREMENTS FOR ELECTRIFIED DOMESTIC CONSUMERS

1 Additional Energy

Required for Electrified

Households

(A7-presnet

consumption

i.e. 9010

MUs)

MUs 1,316 2,865 4,493 6,203 8,000

Page 10: A Joint Initiative of Government of India and Government of Rajasthan

10

(b) Demand from un-electrified households

Table 2.3: ENERGY REQUIREMENTS ON ACCOUNT OF ELECTRIFICATION OF UN-

ELECTRIFIED HOUSEHOLDS

ELECTRIFICATION OF UN-ELECTRIFIED HOUSEHOLDS ( 25 Lakh @5 L / year)

2014-15 2015-16 2016-17 2017-18 2018-19

B URBAN

1 Electrification of un-

electrified Household

500,000 Nos. 100,000 100,000 100,000 100,000 100,000

2 Cumulative Annual

Energy Requirement

for unelectrified Urban

Household

MUs 201 447 739 1,077 1,460

RURAL

3 Targeted Electrification

of unelectrified

households

2500000 % 20% 20% 20% 20% 20%

4 Electrification of

unelectrified Household

Nos. 500,000 500,000 500,000 500,000 500,000

5 Cumulative Annual

Energy Requirement

for unelectrified Rural

Households

MUs 365 821 1,369 2,008 2,738

6 Total households

electrified

(B1 +B4) No. 600,000 600,000 600,000 600,000 600,000

7 Annual Energy

Requirement due to

Electrification of un-

electrified Household

(B2 +B5) MUs 566 1,268 2,108 3,084 4,198

(c) Demand from other than domestic consumer categories

The following are the estimates of energy demand from other than domestic consumer categories.

The growth in energy requirement for other than domestic consumers has been as per Financial

Restructuring Plan (FRP). The table also provides the overall energy demand from all categories

including the electrified and to be electrified households.

Page 11: A Joint Initiative of Government of India and Government of Rajasthan

11

Table 2.4: ENERGY REQUIREMENTS FOR OTHER THAN DOMESTIC CATEGORY

CONSUMERS AND TOTAL ENERGY REQUIREMENT

C ANNUAL ENERGY

REQUIREMENTS

2014-15 2015-16 2016-17 2017-18 2018-19

1 Total Domestic Annual

Energy Requirement (Current

+ Projection)

MUs 10,892 13,143 15,611 18,298 21,207

2 Current Energy Requirement

- Other than Domestic

33,676 MUs

3 Annual Energy Requirement -

Other than Domestic

Consumers ( Growth as per

FRP)

MUs 36,563 39,721 43,178 46,963 51,108

4 Total Energy Requirements

for sale

C1+C3 MUs 47,454 52,864 58,789 65,261 72,316

5 Distribution losses % 21.75 20.00 18.50 17.25 16.00

6 Total Energy required at

Discom Periphery

MU 60,645 66,080 72,133 78865 86090

7 Transmission losses % 4 4 4 4 4

8 Total Annual Energy

Purchase Requirement

MU 63171 68834 75138 82151 89677

9 Peak Demand (MW)

LF=64%

MW 11268

12278 13402 14653 15995

`

The above figure of energy requirement is

also in line with the projections made in 18th

EPS by CEA for the state of Rajasthan. As per

18th

EPS of CEA, the projected energy

requirement of Rajasthan is 89,792 MU by

2018-19 and after assuming load factor of

64% for Rajasthan, the anticipated Peak

demand of the state would be around 16004

MW.

By using energy efficient irrigation pump-sets

and energy efficient lighting (use of LEDs),

the energy consumption of the state is

expected to reduce by 7950 MUs during

2018-19. This would also help in reducing the

peak demand by around 800-1000 MW by

2018-19. Further reduction in peak demand

may also be achieved by adopting demand

side management initiatives like introduction

of Time of Day (TOD) tariff in the state

Keeping in view the above requirement, an

assessment of the adequacy of Generation,

Transmission and Distribution infrastructure

has been done to meet the projected demand

and the same are covered in the subsequent

chapters.

Page 12: A Joint Initiative of Government of India and Government of Rajasthan

12

3. GENERATION PLAN

3.1. EXISTING GENERATION CAPACITY

The total installed capacity as on June 2014

(including allocated share in Joint & Central

Sector plants) was 15,201 MW including 56%

from coal based generation, 11 % from hydro

based generation and 24 % from renewable

energy sources. The installed capacity has

grown from 10160 MW to 15201 MW which

is a growth of over 19.6 % per annum during

the last two and a quarter year i.e. from

31.03.2012 to 30.06.2014 - contributed from

additions to coal based (3469 MW) and

renewable based (1274 MW) generation

capacity. The figure 1.1 and table 3.1 provide

the fuel-wise and sector-wise generation

capacity mix respectively in Rajasthan, as on

30th

June, 2014.

Figure 1.1: Generation capacity Fuel Mix

Source: CEA

Rajasthan has met a peak demand of 10,038

MW during 2013-14 and it is expected that

the peak demand of Rajasthan would be

around 16000 MW by 2018-19 considering

the additional energy requirement for

providing 24X7 power supply to the State.

The present energy requirement is of the order

of 58.29 BU per year and is likely to increase

to 89.6 BU per year by 2018-19.

To meet the expected demand of the state,

capacity addition of 6145.15 MW is expected

in the state by 2018-19 from under

construction projects. Out of which about 625

MW is from non-conventional energy sources

and 5520.15 MW from conventional sources.

As such the total anticipated available

capacity by 2018-19 is expected to be

21346.14 MW. (17081 MW–Conventional &

4265 MW–Renewable). Taking into

consideration the 70% contribution from

conventional installed capacity and 8% from

non-conventional installed capacity to meet

the peak demand, the capacity available for

meeting the peak demand of 16000 MW

would be around 12298 MW.

Conventional

Non

Conventional Total

Existing

Capacity 11561 3640 15201

Capacity

addition by

2018-19 5520 625 6145

Total Capacity

by 2018-19 17081 4265 21346

Capacity

Available out

of Total

capacity to

meet the peak

demand by

2018-19 11957 341 12298

Additional

Capacity

required to

meet the peak

demand of

16000 MW by

2018-19 3702

Further, GoR has planned coal based projects

of 4520 MW in the states which includes

projects of 2920 MW in state sector ( i.e

Kalisindh TPS Unit # 3 & 4 (2 X 660 MW) &

Banswara TPS Unit #1 & 2 (2 X 800 MW))

and projects of 1600 MW (Banswara TPS

Unit # 1 & 2 (2 X 800 MW)) under case -2.

Also 3600 MW of renewable energy is also

planned to be available for the state by 2018-

19. Although, there are issues of coal linkage

for these project, however, these coal based

projects are important to meet the expected

peak demand of the state. The list of projects

under construction and future projects are

provided in table no – 3.2 & 3.3

Page 13: A Joint Initiative of Government of India and Government of Rajasthan

13

Table 3.1: Existing Installed capacity (MW) (June 2014)

Sector Hydro Thermal

Nuclear NES Total Coal Gas Total

STATE 987.96 4715 603.80 5318.80 - 23.85 6330.61

PRIVATE 0.00 2,800 0.0 2800.00 - 3616.30 6416.30

CENTRAL 645.13 1014.72 221.23 1235.95 573.00 - 2454.08

TOTAL 1633.09 8529.72 825.03 9354.75 573.00 3640.15 15200.99

% 10.7% 56.1% 5.4% 61.5% 3.8% 23.9% 100%

Source: CEA

Table 3.2: Projects under construction

Name of project Capacity

(MW)

Commissioning

Schedule

State sector

Chhabra TPS Stage-I Ph2 250 Unit-4 – Dec 14(COD)

Kalisindh TPS Stage-I unit-2 (in state sector) 600 Unit-2 – Dec 14 (Comm)

Dec 14 (COD)

Ramgarh RGTPP Stage-IV 160 Jan-17 and Mar-17

subject to finalization of

gas prices

STPS Stage –V unit 7&8 1320 Sept – 16 and Dec – 16

Chhabra TPS Stage-II unit 5 660 Sept – 16

Sub-total (State Sector) 2990

Chhabra TPS Stage –II Unit 6 (State Sector) 660 Conditional EC

received* (Expected

commissioning June-

2018)

Partnership projects

BBMB uprating 13.65 2014-15

Central sector Allocation

Barh STPP Stage-1 (3x660) 186 2016-17 to 2017-18

Kol Dam HEP (4x200) 86 2014-15 to 2016-17

Barh STPP Stage-2 (2x660) 132 2014-15

RAPP Unit # 7 & 8 (2 X 700 MW) 700 2018-19

Parbati II HEP 86 2016-17

Kishanganga HEP 36 2016-17

Tapovan Vishnugarh HEP 56 2016-17

Kameng HEP 28 2017-18

Lower Subansiri HEP 46.5 2018-19

Sub-total (Central Sector) 1356.5

Private Sector Projects (Case -1) 500 2016-17

Sub-total (Private Sector) 500

Total ( Conventional ) 5520.15

NES Projects

Wind/Solar/Biomass for the state 625 2014-15 to 2016-17

Grand Total 6145.15

Page 14: A Joint Initiative of Government of India and Government of Rajasthan

14

Table 3.3: Future Projects

Name of Project Capacity Commissioning Schedule

Kalisindh TPS Stage-2 Unit # 3 & 4

(in state sector) 2 X 660 MW 2018-19 subject to coal linkage

Banswara TPS Unit # 1 & 2 (in state

sector) 2 X 800 MW 2018-19 subject to coal linkage

Banswara TPS Unit # 1 & 2

(Case-2) 2 X 800 MW 2018-19 subject to coal linkage

Solar & Wind Projects 3600 MW

Projected capacity expected to be

developed under JNNSM, Rajasthan Solar

& wind energy policy by 2018-19

Grand Total 8120 MW

3.2. POWER PROCUREMENT COSTS

The power purchase cost accounts for ~ 66 %

of the total expenditure of distribution

companies in FY 2013-14. These can further

increase due to dependency on the imported

coal on account of shortages in supply of

domestic coal.

The breakup of power purchase cost from

various sources is shown below:

Source Average Unit

Rate

Procured from State plants

(RVUN) during 2013-14

Rs. 3.78 per

unit

Average rate procured from

allotted CGSs during 2013-14

Rs. 3.33 per

unit

Procured from exchange for the

last 3 year

Rs 3.47 per

unit

Procured through bilateral

contracts in the last 3 years

Rs 3.77 per

unit

Procured through IPP’s in the

last 3 years

Rs 3.80 per

unit

Power purchase cost of Rajasthan Less than Rs

4 /unit and is

competitively

priced.

3.3. ISSUES REGARDING COAL

PROCUREMENT PLAN

(a) Unit 6 of Chhabra SCTPS of 1X660

MW

This unit is expected to be commissioned by

June’18. However conditional environmental

clearance (EC) has been received for this unit,

on the basis of which four old units of Kota

Thermal Power Stations Unit-I to Unit-IV

aggregating to 640 MW would have to shut

down and coal allocated to these units be used

for 660 MW CTPP Unit#6. Retirement of

Kota units is not desirable as the units have

been operating at good efficiency and plant

availability levels.

The EC for Chhabra unit-6 should be delinked

from the KTPS Unit-I to Unit-IV. Though

coal for Chhabra Unit # 6 has been linked

from enhanced mining capacity of 10 to 15

MTPA of RVUN’s ‘Parsa East & Kanta

Basan’ coal blocks, yet it requires EC for 15

MTPA capacity which will take long time.

RVUN has already awarded order for

execution of this unit in 2013 and work for

this unit could not commence at site for want

of Environment Clearance.

Mining Plan has been approved in Nov 2013

and enhanced mining capacity will not require

any additional land. In view of above, MOEF

Page 15: A Joint Initiative of Government of India and Government of Rajasthan

15

to consider to grant EC for unit 6 based on 15

MTPA approved mining Plan or Ministry of

Coal to grant tapering linkage of coal (3.25

MTPA) for this unit.

(b) Coal Requirement:

(i) Coal Requirement Based on Linkage

with CIL

Letter of assurance (LOA) / linkage

quantity of RVUN’s post 2009

commissioned units i.e. Suratgarh TPS

Unit # 6 (250 MW), Kota TPS Unit # 7

(195 MW) and Chhabra Unit #1 & 2 (2

X 250 MW) is for 65% PLF which

need to be enhanced. Apart from this,

in order to achieve higher efficiency of

the plants materialization of coal

supply need to be increased to 100 %

of LOA.

Further, a statement showing coal

requirement, availability, shortage and

additional coal requirement in Million

Tonnes Per Annum (MTPA) based on

linkage with CIL is as under;

Particulars FY14-

15

FY15-

16

FY

16-17

FY17-

18

FY18-

19

Domestic

Raw Coal

Requirement

(A)

19.7 19.7 19.7 19.7 19.7

Coal

Linkage (B)

16.4 16.6 16.8 17.1 17.1

Materializati

on 90% (C)

14.7 14.9 15.2 15.3 15.3

Shortfall in

Raw coal as

per linkage

(E)=(A-B)

3.16 2.95 2.72 2.50 2.50

Additional

coal

requirement

based on

linkage with

CIL

3.16 2.95 2.72 2.50 2.50

(ii) Coal Requirement Based on Coal

Blocks Allotted for on Going Projects

Parsa East & Kanta Basan Coal

Block

Parsa East and Kanta Basan(PEKB)

coal blocks in the state of Chhattisgarh

have been allotted to

Rajasthan(RVUN) in June 2007 by

Ministry of Coal, Govt. of India for

meeting coal requirement of Chhabra

TPS (Unit# 3&4-2X250MW) &

Kalisindh (Unit#1&2 -2X600MW) and

part coal requirement for STTPP

Unit#7& 8 and CTPP Unit# 5&6.

Mining plan of Parsa East and Kanta

Basan coal blocks (10 MTPA) was

approved by MoC in July, 2009.

Ministry of Coal, GoI in Feb 2012

accorded ‘in principle’ approval to

allow the use of coal mined from ‘Parsa

East & Kanta Basan’ coal blocks in the

Super Critical Projects of 2x660 MW

Chhabra (Unit#5&6) and 2x660 MW

Suratgarh (Unit # 7 & 8) after

considering mining capacity

enhancement from 10 MTPA to 15

MTPA and directed RVUN to furnish a

revised mining plan of enhanced

capacity. Subsequently, Revised

Mining Plan of Parsa east and Kanta

Basan (15MTPA) coal blocks was

approved by Ministry of Coal in Nov

2013. The requirement of coal for these

super critical projects will be from July

2016.

GoR need to pursue for expediting

Environment Clearance from MoEF for

enhanced mining capacity from 10

MTPA to15 MTPA in respect of Parsa

East & Kanta Basan Coal Blocks. GoI

to facilitate in expediting the

environment clearance for 15 MTPA

capacity.

Page 16: A Joint Initiative of Government of India and Government of Rajasthan

16

Kente Extn. Coal Block

Ministry of Coal, Govt. of India had

allocated Kente Extn. Coal block to

RVUN in August 2013 subject to certain

clarifications/ confirmations. The

required clarifications/confirmations on

above were furnished in Oct /Nov 2013.

The formal allotment letter in this regard

is still awaited and RVUN has not been

able to proceed further for obtaining

necessary clearances, licenses and

approvals etc. from the concerned

authorities. The coal from this coal block

shall be used in meeting balance

requirement of coal for Suratgarh Super

Critical TPP Unit 7&8 (2x660 MW) and

Chhabra Super Critical TPP Unit 5&6

(2x660 MW).

GoR need to pursue for early issuance of

formal allocation letter from Ministry of

Coal in respect of Kente Extension Coal

Block. GoI to facilitate in expediting the

same.

(c) Allocation of Coal Linkage/Coal Blocks

for Future Power Projects

Government of Rajasthan has sanctioned

Supercritical Power Project at Kalisindh

(2x660 MW Unit# 3&4) & Banswara

(2x800 MW Unit# 1&2) under State

Sector on 24.06.2010 & one Supercritical

Power Project at Banswara (2x800 MW)

under Case-2 Tariff based Competitive

Bidding Route (IPP) on 13.01.2009.

The Govt. of Rajasthan has entered into a

MoU with Ministry of Railways, Govt. of

India in 2011 for construction of new

broad gauge Rail Line between Ratlam

(MP) and Dungarpur (Rajasthan) via

Banswara. Rail Link project cost is Rs

2083 Crores out of which 50% cost of

project and 100 % cost of acquisition of

land in Rajasthan & MP (approx. Rs.

1200 Crores) will be borne by GoR.

RVUN has already deposited Rs. 200

Crores with Railways in the month of

March, 2011. The construction work of

new rail line has commenced.

Rajasthan Vidyut Utpadan Nigam

(RVUN) had applied to MoC for grant of

long term linkage of coal for Kalisindh

(Unit 3 & 4) & Banswara (Unit 1 & 2)

State sector projects on 19.01.2010 and

subsequently applied for allocation of

coal blocks on 14.12.2012 & 30.01.2013

for Kalisindh & Banswara State sector

Projects. MoP has already recommended

on 05.05.10 to MoC for allocation.

Ministry of Coal has allocated a small

captive Kente Ext coal bock on

05.08.2013 against the above application

dated 30.01.2013 for meeting the coal

requirement of under construction

projects only & not for these new

projects.

RVUN had also applied to MOC for grant

of long term linkage of coal for IPP

project on 16.04.2009 and for allocation

of coal block on 30.01.2013. Ministry of

Power has already recommended for

grant of coal linkage for IPP project to

Ministry of Coal on 20.08.2010.

Environmental Clearance could not be

granted by MOEF for want of assurance

of Long Term Linkage of Coal/allocation

of Coal Block for these State sector &

IPP projects.

GoR need to pursue for allocation of new

coal block(s) / grant of Long Term

Linkage of Coal for execution of these

power projects. GoI to facilitate in

expediting the same.

Page 17: A Joint Initiative of Government of India and Government of Rajasthan

17

S.

No.

PARTICULAR

S

2 X 660 MW KALISINDH

(UNIT-3 & 4)

2 X 660 MW BANSWARA

(UNIT-1 & 2)

1 Land Sufficient 216 Ha land of stage-I is

available and some additional land will

be acquired if needed

Total 462.52 Ha land has been

identified .Section-4, Section-6 and

Section-9 issued for acquisition of

238.05 Hectare private land. Award

has been issued by land acquisition

officer but land owners are not

accepting cheques.

2 Water 1320 Mcft water has been allocated by

WRD from Kalisindh Dam for which

height of the Kalisindh Dam to be raised

from RL 316 M to RL 319 M.

2000 Mcft water has been allocated

by WRD from Mahi Dam.

3 Term of

Reference (ToR)

Term of Reference (ToR) granted by

MOEF on 10.12.2013.

Term of Reference (ToR) granted by

MOEF 07.12.2011.

4 Rapid

Environment

Impact

Assessment

(REIA) Studies

Completed REIA Could not be started/ carried

out due to resistance / agitation by

local people.

5 Public hearing –

Required for

grant of

Environment

Clearance(EC)

by MoEF

Conducted at site Jhalrapatan by

Rajasthan State Pollution Control Board

on 8.7.2014.

Not yet scheduled

(d) RAMGARH GAS TPS EXTN. ST- IV

(110 MW GT + 50 MW STG) ;-

RVUN has already awarded Boiler

Turbine Generator (BTG) contract to M/s.

BHEL for 160 MW Ramgarh (Stage-IV)

in Sept, 2012 and material worth Rs. 185

Crs has been supplied to site up to Nov,

13. Order for Balance of Plant (BoP) is

under finalization and expected to be

awarded by Oct, 2014. GAIL has

confirmed the availability of 0.75

MMSCMD gas for Ramgarh Stage-IV but

finalization of gas price is under

consideration at Ministry of Petroleum &

Natural Gas. Units are now scheduled to

be commissioned by Jan, 17 and Mar , 17

subject to finalization of Gas prices by

MoP&NG, GoI.

GoI is requested to finalize Gas price for

Ramgarh Stage-IV Gas based Power

Project at discounted prices to be supplied

from isolated gas fields in Jaisalmer

(Rajasthan) and also not to increases gas

prices beyond USD 5 per MMBTU.

Page 18: A Joint Initiative of Government of India and Government of Rajasthan

18

3.4. ACTION PLAN – STATE

1. To complete the generating capacities of

State and to monitor the Central Sector &

Private Sector projects as per following Roll

out Plan-

Power for

all - Roll

out Plan

FY

2014

-15

FY

2015-

16

FY

2016-

17

FY

2017-

18

FY

2018

-19

Total

Generation

(State

Sector

U/C)

850 110 2030 660 3650

Future

State

Projects

2920

Subject to

coal

linkage

Central

Sector

145.

65 0 264 214

746.

5 1370.15

Private

sector 500 500

2. To take up the matter of coal linkage /

environment clearance with Ministry of Coal

and MOEF for the ongoing and future

projects as per requirement.

3. To procure more power, if required, from

the market to meet the demand for providing

24x7 power in the state.

3.5. GOI INTERVENTION

a. The Environment Clearance for

Chhabra unit-6 should be delinked

from the KTPS Unit-I to Unit-IV and

tapering linkage for coal need to be

provided for by Ministry of Coal or

grant Environment Clearance for

CTPP unit 6 based on approved

mining Plan for 15 MTPA for Parsa

East and Kanta Basan.

b. To facilitate allocation of new coal

block(s) / grant of Long Term Linkage

of Coal for execution of the power

projects in the state for Kalisindh

(Unit 3 & 4) & Banswara (Unit 1 & 2)

c. To facilitate Environment Clearance

from MoEF for enhanced mining

capacity from 10 MTPA to15 MTPA

in respect of Parsa East & Kanta

Basan Coal Blocks.

d. To permanently delete the names of

Power Stations of RVUN from the list

of Thermal Power Stations identified

for import of coal and Ministry of

Coal to allocate full Annual

Contracted Quantity of coal to all

power stations of RVUN

e. Ministry of Coal, Govt. of India had

allocated Kente Extn. Coal block to

RVUN in Aug-2013. Ministry of

Power, Govt. of India is requested to

extend cooperation for early issuance

of formal allocation letter from

Ministry of Coal.

f. To finalize Gas price for Ramgarh

Stage-IV Gas based Power Project at

discounted prices to be supplied from

isolated gas fields in Jaisalmer

(Rajasthan).

Though, Govt of India would make all

possible efforts within the framework/

policies to assist the Govt of Rajasthan as

requested above, but if, there is any

problem in meeting the above requests of

the State Govt , a back up plan would be

worked out by State Govt to procure

adequate power to meet the projected

requirement.

Page 19: A Joint Initiative of Government of India and Government of Rajasthan

19

3.6. FUND REQUIREMENT

Estimated fund requirement for under

construction Projects of Capacity 3650 MW

will be Rs. 28993.51 Crores with debt equity

ratio 80:20 and for Future Projects of Capacity

2920 MW fund requirement will be Rs.

18980.00 Crores with debt equity ratio 70:30.

Till now RVUNL is operating its business on

NO PROFIT NO LOSS basis, and does not

claim Return on Equity. Thus no internal

surplus is available for investment on

construction projects. Now for under

construction projects, the cost of the project is

financed by way of 30% Equity contribution by

the State Government and the balance 70% is

financed through LOAN from the Financial

Institutions. RUVNL is 100% Government of

Rajasthan undertaking.

The details of fund requirement are as under-

Generat

ion

(RVUN)

Total

Cost

of

projec

ts

Expen

diture

up to

Mar -

14

FY

15

FY

16

FY

17

FY

18

FY

19

U/C Projects

28994 13201 4717 5100 5024 837 113

Future Projects

18980 - 500 5000 5000 5000 3480

Total 47974 13201 5217 1010 10024 5837 3593

3.7. RENEWABLE ENERGY PLAN

Rajasthan is endowed with abundant

potential of renewable energy sources

particularly wind and solar. State has

already issued liberal policies for

promotion of renewable energy

generation.

It is proposed to set up renewable

energy plants of about 10,240 MW

capacity in the state by 2018-19. Out of

this, 7500 MW would be from solar &

2740 MW from wind.

The solar capacity of 7500 MW would

be developed as under-

• Through VGF based competitive

bidding – 1000 MW

6500 MW • Open access scheme within state

and other than state /captive use

• REC (solar) mechanism

• Nation Solar Mission Ph-II, Batch I

& II

• Nation Solar Mission Ph-III, Batch I

Out of 7500 MW Solar capacity, 1000

MW is planned to be set up for the state

through competitive bidding on VGF

base @ Rs 2.5 Crores / MW to make

available solar power at a lower rate of

Rs 5.5 / unit to ensure less burden on the

state discoms. The other 6500 MW of

solar projects will be developed by IPPs.

2740 MW from wind – These projects

will be developed by IPPs as per Govt of

Rajasthan wind Policy up to the RPO

target set up by SERC. As such no

funding from State or Central Govt

would be required from these projects.

Page 20: A Joint Initiative of Government of India and Government of Rajasthan

20

It is proposed that 4225 MW (625MW

U/C +3600 MW) of renewable energy

will be available for the state for its own

use.

Table 3.4: Solar year-wise proposed capacity

addition plan S. No. FY Capacity Addition (MW)

1 2014-15 500

2 2015-16 1000

3 2016-17 1500

4 2017-18 2000

5 2018-19 2500

Total 7500 MW

Table 3.5: Wind year-wise proposed

capacity addition plan

S. No. F.Y Capacity Addition (MW)

1. 2014-15 500

2. 2015-16 500

3. 2016-17 500

4. 2017-18 620

5. 2018-19 620

Total 2,740

Fund requirement

For developing 6500 MW solar and 2740 MW

wind based renewable energy plants in the

state, no Grant / financial assistance is required

from central Govt as all these projects will be

developed by private investors/ IPPs.

However, total fund required for these

proposed projects are as under –

(Rs in crores)

Renew

able

energy

FY

14-15

FY

15-16

FY

16-17

FY

17-18

FY

18-19 Total

Wind 3000 3000 3000 3720 3720 16440

Solar 3500 7000 10500 14000 17500 52500

Total 6500 10000 13500 17720 21220 68940

Action plan – State

The state has to ensure the completion of

renewable generating capacities in the state as

per following Roll out Plan-

Renewable

energy

FY

14-

15

FY

15-

16

FY

16-

17

FY

17-

18

FY

18-

19

Total

Solar

Capacity

Addition

MW 500 1000 1500 2000 2500 7500

Wind Power

Addition MW 500 500 500 620 620 2740

3.8. GOI INTERVENTION

To consider sanctioning the Viability Gap

Fund (VGF) @ Rs.2.5 Crores / MW for 1000

MW so that the solar bidding may be carried

out on VGF, fixing the tariff at Rs. 5.45 /KWh

for developers following similar guidelines

that have been used for the JNNSM Phase –II

Batch-1 procurement process.

GoR may submit their proposals to MNRE for

VGF funding as per norms of prevailing

schemes.

Page 21: A Joint Initiative of Government of India and Government of Rajasthan

21

4. TRANSMISSION PLAN

4.1. INTER-STATE TRANSMISSION

SYSTEM

Presently about 8200 ckt km of transmission

lines & 9 nos. of 400/220 kV substations with

a total transformer capacity of about 6855

MVA are existing in Rajasthan under the Inter

State transmission system. In Rajasthan, 3

Nos. of existing Central sector generating

stations (Anta CCGP, RAPP-B and RAPP-C)

with a cumulative generation capacity of

1300MW is being evacuated by ISTS. The

details of Inter State Transmission system, to

transfer power from these Inter-state

generating stations are listed below:

Anta CCGP Generation:

� Anta-RAPP-C – RAPP-B 220 kV S/c

� Anta - Bhilwara-I – 220 kV D/c

� Anta – Sawaimadhopur - Dausa 220 kV

D/c

RAPP-B (2x220MW) Nuclear Generation:

� Rapp-B - Anta 220 kV S/c

� RAPP – Chittorgarh 220 kV D/c

� RAPP – Udaipur 220 kV S/c

RAPP-C (2x220MW) Nuclear Generation:

� Rapp-C - Kota 400kV S/c

� RAPP-C – Kankroli 400kV D/c

For import of Rajasthan’s share of power

from central sector generations outside

Rajasthan, a

strong reliable ISTS network has been

established. Major 400kV transmission lines

connecting Rajasthan to other states is listed

below:

From Haryana:

� Bhiwadi – Hissar 400kV S/c

� Gurgaon – Bhiwadi 400kV S/c

� Manesar – Neemarana 400kV D/c

From Uttar Pradesh:

� Balia - Bhiwadi 2500 MW HVDC

Bipole

� Agra - Bassi 400kV S/c

� Agra - Jaipur 400kV D/c

� Agra - Bhiwadi 400kV D/c

� Agra - Sikar 400kV D/c

From Gujarat (WR)

Zerda –Kankroli 400kV D/c (one ckt via

Bhinmal)

From Punjab ( NR)

Moga- Bhiwadi 400 KV D/C

Presently, 9 Nos of 400/220 KV Sub-stations

with 6855 MVA Transformation Capacities

have been established under Inter State

Category in the State.

Table 4.1 shows the substation and their

transformation capacity.

Table 4.1: Substations and their transformation capacity

Sl. No Name of the S/S Voltage ratio No. of Trf. MVA Capacity Tot. trf Capacity

1 Bassi 400/220 2 315 630

2 Jaipur South 400/220 2 500 1000

3 Kota 400/220 2 315 630

Page 22: A Joint Initiative of Government of India and Government of Rajasthan

22

4 Kotputli 400/220 2 315 630

5 Bhiwadi 400/220 3 315 945

6 Neemarana 400/220 1 315 + 500 815

7 Sikar 400/220 2 315 630

8 Bhinmal 400/220 2 315 630

9 Kankroli 400/220 3 315 945

Total MVA Capacity 6855

To facilitate drawl of power by Rajasthan and

to meet projected peak load of 16000 MW by

2018-19 a robust Inter-state transmission

system (ISTS) has been planned and is under

construction. Further for evacuation of power

from state generating stations as well as for

transfer to various load centres within

Rajasthan, a vast Intra State Transmission

Network has been developed by Rajasthan

Rajya Vidyut Prasaran Nigam Ltd

(RRVPNL). ISTS projects under construction

are as below:

4.1.1. ISTS Projects under construction

a) Gwalior–Jaipur-Bhiwani 765kV 2xS/c

line – 1100 Ckm

Construction of 1100 circuit km of 765kV

line is under implementation as part of

various schemes. Gwalior – Jaipur 765 kV

lines would facilitate import from the pit head

coal based generating stations located in

Eastern and Western regions. From these lines

power of the order of about 2000-3000 MW

can be transferred to Rajasthan. Similarly,

Jaipur – Bhiwani 765 kV lines would

facilitate import of power from the various

hydro power stations located in the states of

Himachal and J&K. During off peak period, it

would facilitate export of power from

Rajasthan.

b) RAPP–Kota-Jaipur 400kV D/c–

(480ckms) and RAPP-Shujalpur 400kV

D/c-(500ckm):

To improve evacuation of power from RAPP

generation complex to load centres of

Rajasthan and to facilitate evacuation of

power from proposed RAPP-C (2x700MW)

generation - a 400kV D/c from RAPP

generation complex to Jaipur with one circuit

via Kota has been proposed and is to be taken

up by POWERGRID.

RAPP-Shujalpur 400kV D/c would connect

RAPP generation complex with Shujalpur in

Madhya Pradesh, Western Region. The line

would help Rajasthan to receive power from

WR - as and when need arises. Further, when

Rajasthan is surplus, the power can be

exported to WR. The line is being taken up

under Tariff Based competitive bidding and is

expected by November 2016.

c) State-of-the-Art Static Var

Compensator (SVC) at Kankroli

Kankroli is a major substation located in the

south western part of Northern Grid. It is

connected to RAPP-5&6 nuclear generations

by a 400kV D/c line. Further, it is also

connected to Western Region via Kankroli-

Zerda / Bhinmal 400kV D/c line. However the

Kankroli area faces voltage constraints.

Accordingly (+) 400 MVAR / (-300) MVAR

Static Var Compensators has been proposed at

Kankroli S/s. The Static Var compensator

Page 23: A Joint Initiative of Government of India and Government of Rajasthan

23

shall help in controlling the voltage and

providing reliable supply to the area.

d) System strengthening

To meet the growing power demand of

Rajasthan - various augmentation and system

strengthening activities are proposed to be

carried out progressively such as

augmentation of transformer capacity by 500

MVA at Bassi 400/220 substation, Sikar –

Jaipur 400 kV D/c- 340 ckm and Sikar –

Ratangarh 400 kV D/c-160 ckm lines are also

under implementation.

e) Transmission System for integration of

Large Scale Renewable

In Rajasthan, existing renewable energy

capacity is about 3,524 MW (As on Mar’14).

The transmission system has been planned for

7333 MW out of the proposed capacity of

10,240 MW renewable capacity by 2018-19

which is mainly through solar and wind

generation. The additional evacuation system

for balance RE capacity, if required, will be

planned and implemented in due course of

time in consultation with State Govt.

Table 4.2: Details of Renewable capacity

for which Tx system has been planned in

2018-19

Wind Solar

Total

Renewable

Capacity*

Existing RE

capacity (MW)

(As on Mar’14)

2798

726

3524

Transmission

system planned

for capacity

Addition by

(2018-19)

3033 4300 7333

Total (MW) 5831 5026 10857

*Excluding Biomass

Renewable capacity in Rajasthan is mainly

confined to Western (Jaisalmer, Barmer,

Jodhpur & Bikaner) and Southern (Banswara

& Pratapgarh) parts of Rajasthan.

Details of pocket wise wind and solar

capacity in Rajasthan for which the

transmission system has been planned are

provided in Table 4.3

Table 4.3: Pocket wise Wind Generation in

Rajasthan

S.N

o Pocket

Existin

g

(Mar’1

4)

(MW)

Additio

n by

(2018-

19)

Total

(MW

)

1 Jaisalmer/Barmer 2254 2240 4494

2 Jodhpur/Bikaner 391 60 451

3 Banswara/Pratapg

arh 141 604 745

4 Other parts of

Rajasthan 12 129 141

Total(MW) 2798 3033 5831

Table 4.4: Pocket wise Solar Generation in

Rajasthan

S.No Pocket

Existing

(Mar’14)

(MW)

Addition

by

(2018-

19)

Total

(MW)

1 Jaisalmer/Barmer 70 1444 1514

2 Jodhpur/Bikaner 656 2856 3512

Total (MW) 726 4300 5026

Based on the capacity additions, it is expected

that Rajasthan may have more RE capacity

than required for meeting their Renewable

Purchase Obligations (RPO). Further,

Rajasthan may not be able to absorb the entire

RE energy locally - particularly during off-

peak period - when renewable generation is at

its peak. In addition, the IEGC stipulates the

renewable energy plants as “MUST RUN”

Page 24: A Joint Initiative of Government of India and Government of Rajasthan

24

and not to be subjected to “merit order

dispatch” principles.

To address above aspects and the

intermittency nature of renewable energy

generation, development of strong and

reliable grid interconnections is important.

There is a need to strengthen Interstate

transmission which shall facilitate transfer of

power outside the RE resource rich states.

In order to facilitate integration of large scale

renewable generation capacity by 2018-19, a

comprehensive transmission plan comprising

of intra state and interstate transmission

system strengthening has been evolved as a

part of “Green Energy Corridors”. As part of

this corridor, under ISTS four Nos. of

765/400kV substation would be established in

Rajasthan i.e. at Chittorgarh, Bhadla, Ajmer

& Suratgarh.

The corridor envisages high capacity 765kV

D/c lines which would traverse across

Rajasthan from Southern to Northern part of

Rajasthan as well as from Western to Central

part. The corridor would connect major

renewable pockets in Rajasthan and would

facilitate export of power from Rajasthan.

Further the corridor would be integrated with

ISTS station at Moga. This would facilitate

Rajasthan to integrate with Hydro generation

complex of NR for facilitate balancing

requirement. An additional ISTS

strengthening which includes establishment of

new 400/220kV substation at Akal-II and its

connectivity with 400 kV Jodhpur (new) and

Bhadla (new) Substation is also proposed. As

part of this corridor 400kv Jodhpur is also

proposed to be connected to high capacity

765/400 kv Ajmer substation which would be

connected to planned Green Energy

Corridors.

Figure 4.1Proposed ISTS Transmission

Corridor for RE in Rajasthan

To facilitate pooling of power from various

RE generations at various points of common

coupling (PCC), transfer to various load

centres and interconnection with the ISTS

points - the intra state strengthening scheme

has been evolved by RVPN / PGCIL

Summary of proposed Inter-state transmission

system strengthening schemes - for which

investment is to be made as a part of Green

Energy Corridor is as shown below:

Table 4.5: Summary of proposed Inter-

State Transmission System

S.No Item Length

(Ckm)

Substation

capacity

(MVA)

1 Inter State 3650 15000

The details of inter-state schemes (ISTS) for

Rajasthan as a part of green energy corridor is

as under:

Page 25: A Joint Initiative of Government of India and Government of Rajasthan

25

Interstate transmission scheme for

Rajasthan for integration of renewable

generation as part of Green Energy

Corridor

a) Transmission scheme to be implemented

by POWERGRID

• Ajmer (New)- Ajmer (RVPN) 400kV

D/c (Quad)

• Chittorgarh (New)- Chittorgarh

(RVPN) 400kV D/c (Quad)

• Chittorgarh – Ajmer(New) 765kV D/C

• Establishment of 2x1500 MVA,

765/400kV S/s at Chittorgarh

• Establishment of 2x1500 MVA,

765/400kV S/s at Ajmer (New)

Estimated cost (a): 1663 Crores

b) Implementation agency is yet to be

finalized

• Ajmer(New) – Suratgarh (New)

765kV D/c

• Suratgarh(New)-Moga(PG) 765kV

D/c

• Suratgarh (New)- Suratgarh (existing)

400kV D/c (Quad)

• Bhadla (New)-Ajmer (New) 765 kV

D/c*

• Bhadla (New)-Bhadla (RVPN) 400 kV

D/c (Quad)*

• Bhadla (New)-Pokhran New (RVPN)

400 kV D/c (Quad)*

• Establishment of 2x1500 MVA,

765/400kV S/s (AIS) at Suratgarh

(New)

• 765/400/220kV (765/400 kV-2x1500

MVA & 400/220kV- 2x500MVA)

substation at Bhadla (New)*

Estimated cost (b): 5237 Crores

* The system was discussed and approved in 32nd

standing committee meeting of NR. However, it

was decided that this system shall be taken up for

implementation only after receipt of application

for Connectivity and LTA for sufficient quantum

from Solar/ wind generation developers

around Bhadla area

c) Additional Inter State Transmission

Scheme proposed for renewable

generation projects during 2017-19 in

Rajasthan – The System is yet to be

approved

• Establishment of 4x500 MVA,

400/220kV S/s at Akal-II (new)

• Akal - Bhadla (New) 400 kV D/c

(Quad)

• Akal (New) - Jodhpur (New) 400 kV

D/c (Quad)

• Jodhpur (New) - Ajmer (New) 400 kV

D/c (Quad)

Estimated cost (c): Rs 1700 Cr

Total Estimated cost (a+b+c): Rs 8600 Cr

f) Renewable Energy Management

Centres (REMC)

Renewable generation especially wind is

characterized by its intermittent & variable

characteristics. Therefore other controlling

infrastructure such as forecasting of

renewable generation, balancing

infrastructure, dynamic compensation,

establishment of Renewable Energy

Management centres (REMC), at

SLDC/RLDC/NLDC level, real time

measurement/monitoring, Energy storage etc.

have also been identified as part of the green

energy corridors.

Establishment of Renewable Energy

Management Centres (REMC) has also been

proposed for the State of Rajasthan

considering the high level of renewable

penetration. REMC shall perform real time

Page 26: A Joint Initiative of Government of India and Government of Rajasthan

26

monitoring of renewable generation as well as

renewable generation forecasting exclusively

on different time scales. Integration of REMC

with existing control centres would facilitate

scheduling & dispatch of RE power. Further,

in order to facilitate real time dynamic state

measurement at RE pooling stations or point

of common coupling, installation of

PMU/PDC and associated Fibre optic

communication links are considered to be

established in a unified manner.

g) Adequacy of ISTS

• The planned ISTS system is sufficient

to meet the power transfer requirement

of Rajasthan by 2018-19 to meet the

projected demand of about 16000MW.

• Interstate transmission system for

integration of renewable generation is

adequate for 7333MW capacity

addition, however in case of for

increased quantum, additional

transmission system is required, and

the same would be planned after

discussion with the State Govt.

Note: The proposed tr. system is evolved considering a

particular load generation scenario and network

configuration, which may change from time to time

depending upon actual load growth, generation

capacity addition, network development etc. In case of

any change in the above consideration, the proposed

transmission system needs to be reviewed.

h) Fund requirement :

Total estimated cost in Rajasthan for Inter

State Transmission Network strengthening

(ISTS) is Rs 12,216 Crs. The inter-state

scheme of Rs 3616 Cr is under

implementation, therefore balance (8600 Crs)

investment is required for ISTS strengthening.

� Interstate: Rs 12,216 Cr

• Rs 3616 Cr (for schemes listed under

4.1.1(a) to (d)) [Under

implementation]

• Rs 8600 Cr for Green energy corridor

i.e. integration of renewables

� Rs 1663 Cr (implemented by

POWERGRID with 70% loan

and 30% equity)

� Rs 6937 Cr (Implementing

agency yet to be tied up)

The debt component (70%) of transmission

system being developed by POWERGRID

(Rs 1663 Cr) is funded through concessional

loan from KfW, Germany. The implementing

agency (ies) for balance transmission system

(Rs 6937 Cr) is yet to be identified for which

funding would be through own resources and

external borrowing. However to rationalize

the transmission tariff soft loan from

multilateral funding agencies is required. In

such cases sovereign guarantee is required

from GoI.

Action Points- CTU

• POWERGRID/Implementing agency

to ensure development of interstate

transmission as indicated above

progressively by 2018-19

• State nodal agency shall ensure that

Renewable generation developer apply

for connectivity/Long term access for

its integration in the ISTS.

• To plan and develop the additional

transmission system (if required) for

evacuation of anticipated RE power

more than 7333 MW in the state.

• In order to integrate large scale

variable generation and address its

inherent characteristics of

intermittency & variability, there is a

need of addressing it through suitable

mitigating measures like balancing &

control infrastructure. Balancing

infrastructure includes enlargement of

balancing area through strong grid

interconnection, flexible generation

Page 27: A Joint Initiative of Government of India and Government of Rajasthan

27

resources like Pumped storage plants

(PSP), large scale battery storage etc.

In addition control infrastructure like

Renewable forecasting system,

Renewable Energy Management

Centre (REMC), Dynamic reactive

compensation, Real time monitoring

etc. are also required to be provided.

To address the issue, a technical

consultancy on aspects like strategy &

road map for providing balancing

infrastructure, assessment of balancing

capacity of control areas & measures

to enhance it, technological roadmap

etc. is being carried out as part of

technical assistance (upto Eur 2

million grant) from GIZ, Germany to

be completed in 2014-15.

GOI Intervention

GoI may identify implementing agency

(ies) for development of balance ISTS

(Rs 6937 Cr) for integration of

renewable.

4.2. INTRA STATE TRANSMISSION

SYSTEM

To meet with a projected load demand of

16000 MW by 2018-19 a robust intrastate

transmission system has been planned and

same is under various stages of

implementation.

4.2.1 Existing System

The transmission network that presently

caters to the load across the State as on 31-

March-2014 is as follows:

462 Nos. of EHV sub-stations having

Capacity: 53248 MVA along with 31092 Ckt.

kM of associated transmission lines consisting

of -

� 9 Nos of 400 kV grid substations

(Heerapura – Jaipur, Ratangarh, Bikaner,

Jodhpur, Jaisalmer, Barmer, Hindaun,

Bhilwara & Merta City) with 6420 MVA

capacity and 3278 ckt kM. of associated

lines.

� 93 Nos of 220 kV grid substations with

22105 MVA capacity and 12236 ckt kM.

of associated lines.

� 360 Nos of 132 kV grid substations with

24724 MVA capacity and 15153 ckt kM.

of associated lines.

4.2.2 Under Construction/ Planned Intra

State Transmission System:

� 2 Nos. of 765 kV grid substations at Anta

and Phagi (Jaipur) with 7500 MVA

capacity are under construction.

� 6 Nos. of 400 kV grid substations at

Chittorgarh, Ajmer, Babai, Jodhpur

(New), Ramgarh and Bhadla with 4965

MVA capacity are under construction/

implementation. 2 Nos. of 400kV grid

substations at Banswara & Jaisalmer-2

with 2000 MVA capacity planned for

implementation and 4 nos. of 400kV GSS

with 4000 MVA capacity are being

identified.

Page 28: A Joint Initiative of Government of India and Government of Rajasthan

28

The details of proposed physical plan are as follows:

Table 4.6: Proposed physical plan 2014-15 to 2018-19

Project Voltage

Level Unit 2014-15 2015-16 2016-17 2017-18 2018-19

Intra-State

Transmission

network

765 KV

No./

MVA 2/3000 0/4500 0/0 0/0 0/0

Ckm. 425* 0 0 0 0

400 KV

No./

MVA 1/315 2/945 0/630 1/1000 2/2000

Ckm. 271 1618 0 150 300

220 KV

No./

MVA 6/940 6/720 8/1240 7/1300 5/1160

Ckm. 1219 334 594 321 273

132 KV

No./

MVA 20/725 16/475 4/100 13/400 13/425

Ckm. 1016 659 289 325 325

Green Energy

Corridor

765 KV

No./

MVA 0/0 0/0 0/0 0/0 0/0

Ckm. 0 0 0 0 0

400 KV

No./

MVA 0/0 0/0 3/1315 1/2815 2/2000

Ckm. 0 820 520 1490 1570

220 KV

No./

MVA 2/260 2/260 0/0 1/160 3/640

Ckm. 299 504 20 230 390

132 KV No./

MVA 0/0 0/0 6/150 7/150 7/200

Ckm. 10 32 300 364 640

* 425 kM of 765 kV lines already completed and charged on 400 kV voltage level which will be upgraded to 765 kV

voltage level during 2014-15.

All the above schemes are approved except 4

nos. 400kV GSS, 4000 MVA with 600kM

transmission lines, 1 no. 220kV GSS, 320

MVA with 100 CkM transmission lines and

18 nos. 132kV GSS, 450 MVA with 625 cKM

transmission lines. These schemes will be

approved & constructed in phased manner for

evacuation of power from generating stations

(RE and conventional sources), for system

strengthening and normal development works.

Projects under Tariff Based Competitive

Bidding (TBCB):

In addition to the planned transmission system

mentioned above, the following projects are

proposed to be implemented through Private

participation wherein the entire investment is

to be made by the private parties/developers:

(a) There are 3 projects which are under

advanced stage of implementation

under TBCB mode as per following

details:

Page 29: A Joint Initiative of Government of India and Government of Rajasthan

29

Table 4.7: Projects under Tariff Based

Competitive Bidding (TBCB) under

advanced stage of implementation

S

.

N

o

.

Name of GSS with

associated lines

Devel

oper

sched

uled

com

missi

oning

Est

Cost

( Rs in

crores)

1

.

400kV GSS at Deedwana

with following lines:

i. 400kV S/C Bikaner-

Deedwana line

ii. 400kV S/C Ajmer-

Deedwana line

iii. 220 kV D/C

Sujangarh-Deedwana

line

GMR 2014-

15

284.12

2

.

400kV GSS at Alwar with

400kV S/C Hindaun-

Alwar line

GMR 2014-

15

188.31

3

.

220kV GSS at Nawalgarh

with following lines:

i. 220kV S/C Sikar-

Nawalgarh line

ii. 220kV Nawalgarh-

Jhunjhunu line

EMC

O

2015-

16

36.27

(b) The following three projects have also

been identified and proposed to be

implemented through TBCB with VGF

support upto 2018-19:

Table 4.8: Projects identified and proposed

to be implemented through TBCB through

VGF funding upto 2018-19

S.

No. Name of GSS with associated lines

Est Cost

(Rs in

crores)

1

.

400kV GSS at Jaipur (North) with

400kV D/C Babai-Jaipur (North)

line.

221.81

2

.

400kV D/C Bikaner-Sikar(PGCIL)

line. 265.00

3

.

400kV S/C Suratgarh (STPS) -

Bikaner line. 157.79

(c) Apart from the above, one more project

of 400kV D/C Udaipur-Jodhpur line (490

ckM) with 400/220kV, 630 MVA GSS at

Udaipur having estimated cost of Rs. 379.53

Crores has also been identified which is likely

to be implemented through TBCB or through

TBCB with VGF support.

4.2.3 Investment for intra state

transmission network:

Total investment of Rs 11,530 Crs:

• Rs 6,848 Crs for intra state system

(incl. cost of Augmentations,

SCADA, IT items, establishment of

metering , communication & data

control centres, ERP, RMU, PLCC

equipment etc.)

• Rs 4,682 Crs for Green energy

corridor (incl. Rs 1018.31 Crs

scheme proposed under KFW

funding)

The funding for the above investment will be

arranged by borrowing from financial

institutions with required equity support

from GoR. The recovery of the above

investment will be done through wheeling

charges which will be factored in the tariff.

Details of above investment for intrastate

transmission network are given at Annexure –

IV

4.2.4. Adequacy of State Transmission

system - Rajasthan Transco

The above proposed transmission

system will be capable of meeting

projected peak load of 16000 MW

upto 2018-19 and RE power of about

10800 MW (3524 MW existing and

7333 MW addition by 2018-19). The

additional transmission system (if

required) for evacuation of anticipated

RE power more than 10800 MW shall

also be identified, approved and

implemented as per system

requirement matching with the RE

generation.

Page 30: A Joint Initiative of Government of India and Government of Rajasthan

30

4.2.5 Action Points - Rajasthan Transco

1. The proposed transmission system

upto 2018-19 needs to be implemented

as per schedule for ensuring 24x7

power supply in the State.

2. The funding for implementation of

Intra State transmission system

amounting to Rs. 6848 Crores shall be

timely arranged/tied up wherein 30%

equity support shall be provided by

Govt. of Rajasthan.

3. The funding for implementation of

transmission system for Green Energy

Corridor (Rs 4,682 Crs with 30%

equity support from Govt. of

Rajasthan) shall also be arranged by

Rajasthan Transco wherein 40%

Grant/Aid (Rs. 1874 Crores) has been

proposed to be provided by MoP from

National Clean Energy Fund (NCEF)

and Clean Technology Fund (CTF).

4.2.6 GOI intervention

1. The transmission company of the

State (i.e. RVPN) has developed

transmission system through its own

resources for evacuation of RE

generation by incurring huge

investment. Due to low Capacity

Utilization Factor (CUF) of the order

of (18-22%) of RE generators. the

incidence of transmission charges is

very high on consumers/generators.

Therefore, there is need to provide

support for developing evacuation

system for promoting RE generation.

For implementation of transmission

system for Green Energy Corridor

Projects and to avoid high incidence

of transmission charges in the State,

grant from Govt. of India is required

from National Clean Energy Fund

(NCEF) and Clean Technology Fund

(CTF).

GoR may submit their proposals to

MNRE for funding as per norms of

prevailing schemes.

2. To overcome the operational practical

difficulties in injection of RE power

due to intermittency and variability,

suitable balancing mechanisms are

required to be installed. A Policy in

this regard would be formulated in

consultation with CEA/CERC.

Page 31: A Joint Initiative of Government of India and Government of Rajasthan

31

5. DISTRIBUTION PLAN

5.1. EXISTING DISTRIBUTION SYSTEM

At the end of March 2014, the distribution

network of Rajasthan consists of 2,40,203 ckt

km low tension lines, 3,56,641 ckt km 11 kV

lines and 47,293 ckt km 33 kV lines with a

1,63,017 Km network of AB cables.

There are 4585 No of 33 kV substations and

11, 79,684 Nos of 11/0.4 kV distribution

transformers. The total transformer capacity is

20,763 MVA at 33 kV level and 34,937 MVA

at 11 kV level. HT to LT ratio has increased

substantially from 0.92 in FY 05 to 1.68 at the

end of FY 14.

In Rajasthan, at present, there are about 1.14

Crores of electricity consumers including

about 12.0 lacs under agriculture category.

The category wise break up of consumers, per

unit tariff, Billing & collections in the state is

given at Annex-V

All categories of consumers in the state are

given supply without load shedding. After

executing virtual feeder separation in rural

areas in the year 2008, the State has been

supplying 24x7 power to the rural domestic

consumer. For agriculture consumers, the

power supply is being given 6.5 hours in day

block and 7 hours at night block.

However, during the preceding 4-5 years, the

distribution system has suffered due to lack of

maintenance and lack of supervision resulting

into increase in frequent unscheduled

breakdowns and tripping in the system. To

provide quality 24x7 power supply to rural

areas, there is an urgent need to augment/

strengthen the rural 11KV feeders which are

16,397 in numbers as well as to improve the

infrastructure on the 33 KV sub-stations

which are 3991 in number.

5.2. SCHEMES UNDER

IMPLEMENTATION

RAPDRP

Government of India has launched

Restructured-Accelerated Power

Development and Reforms Programme (R-

APDRP) as a central sector scheme to

encourage energy audit and accounting

through IT intervention and to reduce the

AT&C losses upto 15%. The focus of R-

APDRP Scheme is on actual demonstrable

performance by utilities in terms of sustained

AT&C loss reduction. Projects under the

scheme are being taken up in two Parts. Part-

A includes the projects for IT applications for

energy accounting / auditing, GIS, consumer

indexing, SCADA & IT based consumer

service centres etc. and Part-B includes

regular distribution strengthening projects

including separation of agricultural feeders

from domestic and industrial ones and High

Voltage Distribution System (HVDS) etc.

Under Part-A of R-APDRP, 87 projects at an

estimated cost of Rs 315.95 Crores have been

approved for the state of Rajasthan and Rs

130.25 Crores have been disbursed till date.

Part-A SCADA projects for 5 towns for the

states have also been sanctioned at an

estimated cost of Rs 150.90 Crores and Rs

45.28 Crores have been disbursed

Under Part-B of R-APDRP, 81 projects at an

estimated cost of Rs 1540 Crores have been

approved for the State and Rs 548 Crores

have been disbursed and the work would be

completed within next 2 years. For these

works, 50% funding of around Rs. 770 crores

has to be arranged by the State.

Page 32: A Joint Initiative of Government of India and Government of Rajasthan

32

RGGVY

At present, the un-electrified households are

being electrified under RGGVY scheme of

Govt of India. Under this scheme electricity

connections are being provided for the rural

households in the habitations with population

of more than 100 only. The status of these

plans is as under:

RGGVY 10th

& 11th

Plan:

The scheme was approved at an estimated

cost of Rs. 1331 crores covering electricity

connection to 11.84 lakhs BPL households.

Out of which electricity connection of around

11.69 lakh BPL households has already been

released. The remaining electricity

connections of around 0.15 lakh BPL -

amounting to Rs.19.9 Crores is expected to be

completed by December 2014. The state share

required for meeting this obligation would be

around 2.0 Crores.

RGGVY 12

th Plan: The 12

th plan RGGVY

scheme for providing access to all the

remaining rural households in the habitations

with population more than 100 for the state of

Rajasthan was approved with 28 schemes

covering 27 districts at an estimated cost of

Rs. 1453.19 Crores covering electricity

connection to 13.36 lakhs households

including 4.43 lakhs BPL households.

Table 5.1: GoI Schemes Sanctioned and Under Implementation GoI Schemes already Sanctioned and under implementation

2014-

15 2015-16 2016-17 2017-18 2018-19 Total Remarks

RGGVY 12th plan

(sanctioned 28

schemes)

150 450 450 403.19 0 1453.19 Sanctioned

RAPDRP- Part- A for

IT enablement under

RAPDRP – Part A

(For towns with

population more than

30,000)

185 0 0 0 0 185

Sanctioned

Rs 315.95 Cr and

Rs 130 Cr disbursed

RAPDRP Part A –

SCADA projects for 5

big towns

50 61.83 - - - 111.83

Sanctioned Rs

157.11 cr and Rs

45.28 cr disbursed

RAPDRP- Part-B –

81 towns 500 492 992

Sanctioned Rs 1540

Cr, and Rs. 548 cr.

Disbursed from

GoI/Counter

Funding

Total Sanctioned GoI

Schemes 885 1003.83 450 403.19 0 2742.02

5.3. PROPOSED SCHEMES

To eliminate the frequent occurrence of

shutdowns and number of tripping, feeder and

substation improvement programs are

proposed to be implemented in the State

comprising the following activities:

(a) Feeder Improvement Programme

Activities involved for improvement of 16397

Nos. 11 kV feeders requiring an investment of

Rs. 1500 Cr. Anre provided below:-

1. Replacement of 3, 35,246 numbers

damaged M&P boxes of 3 phase

transformers.

Page 33: A Joint Initiative of Government of India and Government of Rajasthan

33

2. Replacement of 1,02,724 numbers

damaged protection boxes of 1 phase

transformers

3. Replacement of 40,003 kms single

phase and 15,142 Kms 3 phase

obsolete AB cables.

4. Augmentation of capacity of 53,181

numbers single phase transformers in

Abadi areas and Dhanies.

5. Drawing 3 phase system for 1,756

number of villages near to the 33 KV

substations.

6. Providing 8, 93,009 insulated

connectors to eliminate direct tapping

of AB cables.

7. Replacement of 3, 43,787 number

agricultural, 23,591 other categories

three phase and 6, 94,054 single phase

defective meters.

8. Providing earthing of 1, 15,441

numbers single phase transformers.

9. Augmentation of existing capacity of

41,750 kms conductor

10. Drawing of 73,278 kms neutral wire

and 4, 21,239 intermediate pole.

Meter

Installation /

Replacemen

t

Qty FY'

15

FY'

16

FY'

17

FY'

18

FY'19

Target

Agricultural Consumers

Metering for

unmetered

agricultural

consumers

141K 50K 50K 30K 11K -

Replacemen

t of existing

defective

Meters

343K 75K 75K 75K 75K 43K

Single Phase Consumers

Replacemen

t of existing

defective

Meters

694K 150

K

150

K

150

K

150

K

94K

(b) Providing three phase supply to

villages near to the existing 33/11 kV

substations: To ensure 24 hrs. supply

to the domestic, commercial, Industrial

and other loads (other than Agriculture

loads) in the villages, Discoms have

already laid 3-phase feeder to around

2000 villages of population more than

4000 and 1756 villages have been

identified for laying 3 phase feeder

under feeder improvement programme

situated nearer to the existing 33 kV

Sub-stations. Cost of the above work

has been included in Feeder

Improvement Programme.

(c) Providing three phase supply to big

villages :-

To ensure 24 hours supply to the

domestic, commercial, industrial and

other loads (other than agriculture

loads) in the villages, Discoms have

already laid 3phase feeder to around

2000 villages of population more than

4000. To enhance the benefit of 24 x 7

to more villages, it is proposed as

under :-

i. Separate 3 phase feeder is proposed

to be laid in villages having

population more than 2000. There

are 3338 villages in Rajasthan

having population more than 2000

and less than 4000.

ii. The estimated cost to execute the

above work is Rs.1007 crs.

iii. The works are proposed to be

implemented in phased manner

during F.Y. 2015-16 to 2018-19

(d) Substation Improvement Programme

Activities to improve 3991 numbers 33-KV

Rural substations requiring an investment of

Rs. 400 cr are provided below:-

1. Replacement of 679 non operative

Roster switches on 11KV Feeders.

2. Installation of 10,102 new Roster

switches on 11 KV Feeders.

3. Repair/replacement of non-

operative circuit breakers on 2022

Nos 11KV feeders.

4. Installation of new circuit breakers

on 6843 nos 11 kV feeders.

5. Replacement of non-functional

2986 feeder meters

6. Installation of 4672 new feeder

meters

Page 34: A Joint Initiative of Government of India and Government of Rajasthan

34

7. Improvement of earthing required

at 1976 nos, 33 kV substations.

Work is expected to be completed by

March 2015. It is proposed to undertake

the above initiatives which are essential

steps for providing reliable, affordable

& quality 24x7 power for all the

consumers

(e) Requirement of additional 33/11 KV

S/S in rural area for 24x7 supply

The 24x7 power supply for all to rural

areas including electrification of un-

electrified households in rural area will

cause additional demand (over and

above the existing/usual) and it is

necessary to create additional 33/11 kV

substation (other than State plan) for

providing reliable power supply

satisfactorily in rural areas.

To achieve the 24x7 supply, it is

therefore proposed to create 2 Nos. 5

MVA 33/11 kV sub-station per year in

each District during next four years i.e.

F.Y. 2015-16 to 2018-19. The estimated

cost of the above will be Rs.444 crores

and the works will be executed in a

phased manner in next four years.

(f) IT enabled services to the towns with

less than 30 thousand population and

in rural areas under RAPDRP- Part-A

Under RAPDRP Part –A, 87 towns of

Rajasthan were covered with population

of more than 30,000 for IT enabled

services. In order to implement

RAPDRP scheme in the entire state

irrespective of the coverage of Sub

Division / Town of more than 30,000

population in RAPDRP, it was

considered that all modules under Part

A of RAPDRP would also be

implemented in the towns of population

of less than 30 thousand and in rural

areas.

As per the sanctioned scheme for 87

towns, State Data Centre is to be

established at Jaipur City and all the

requisite software viz. application

software, Data Base software and the

requisite hardware will be installed

through RAPDRP funding. It is

pertinent to mention that sizing of the

Software and Hardwares were

considered taken into account that the

consumers and sub divisions of entire

state will be served through the state

Data Centre, if the entire scheme is

implemented in entire Rajasthan.

Discoms has to bear only the cost of

field activities like GIS based network

and asset mapping, sub station metering

etc. for the remaining areas which are

not covered under RAPDRP to achieve

the following objectives:

1. IT enablement of entire Discom.

2. Parity in business Process in entire

Discom. Even in some cases only

part of subdivision has been

covered under R-APDRP under

such circumstances it would be

difficult to maintain the parity in

business process within one sub-

division if scheme is not

implemented entirely.

3. Facilitate all the consumers of all

Discom with the benefits of

RAPDRP scheme.

4. Avoid future fragmentation, which

may take place if the scheme is not

implemented in entire Discom.

5. Adoption of common technology

with Integration of entire System.

6. To take the benefit of huge

investment made for Data center.

GoI is requested to provide assistance of Rs.

235 Cr. so that IT enabled services to the

consumers may also be provided to the rural

areas and towns less than 30 thousand

population at par with the RAPDRP towns of

urban areas and to monitor 24x7 supply with

authentic energy audit by utilising the DATA

centre, software & IT applications with other

infrastructure being laid for RAPDRP part-A.

Page 35: A Joint Initiative of Government of India and Government of Rajasthan

35

State of Rajasthan was the first one to launch

R-APDRP program Part- A, inviting IT

Implementation Agency and ambitiously

covering both R-APDRP towns and non- R-

APDRP towns. However, the Implementation

progress has been very slow and project is yet

to go-live.

Since five years that the IT Implementation

Agencies (ITIA) was selected to build in

critical components of the IT infrastructure

like Customer Relationship Module, Billing

System, Automatic Meter Reading, Web Self

Service, Security, MIS, Centralized Call

Centre, etc. is not being implemented

successfully.

Other critical diagnostic tool such as energy

audit, Inventory management system,

Geographical Information System are yet to

be implemented.

Infact there has not been any process to

capture data changes post Consumer

Indexation that was carried out few years

back and suspect that the data captured might

not be put to use.

For taking benefits of the huge investment

already made under RAPDRP and meeting

the program objective, GoR should focus on

addressing the critical gaps in the existing

system and ensure for an early

implementation for both RAPDRP & NON-

RAPDRP towns else the infrastructure such as

hardware, servers may soon be out of

warranty.

(g) Reduction of AT&C losses for non

RAPDRP towns:

Substantial reduction in AT&C losses has

been achieved after introduction of High

Voltage Distribution System (HVDS) in rural

areas during FY 06 (41.21%) to FY 10

(28.03%) through feeder renovation program

by doing virtual segregation of single phase

load from three phase agricultural load and

putting distribution transformers with

metering equipment nearer to agriculture

consumers installations. AT & C losses

during 2013 -14 were 26.74 %. The details of

energy availability, sales and AT&C Loss

from FY 10 to FY 14 are given at Annexure

VI

The State Govt. has initiated measures for

making 100% metering, billing, and revenue

collection a requisite. Only about 1.42 lakh

agriculture consumers (out of total of 12 lakh

agriculture consumer) are yet to be metered.

State Govt proposes to undertake the

following works for reduction of AT&C

losses -

i. Providing metering equipments

with all 11 KV feeders for reliable

energy audit.

ii. Provide metering equipment for

unmetered flat rate 1.41 lakhs

agriculture connections out of total

of 12 lakhs Ag. Consumers. To

ensure proper & reliable energy

accounting.

iii. Replace 3.43 lac defective

/damaged metering equipment of

Agriculture consumers out of the

total 10.6 lakhs metered

agriculture consumers, under

Feeder Improvement Programme.

iv. Replace all defective meters by

March 15 as identified in feeder

improvement programme. Apart

from one time meter replacement

there should be periodic drive for

testing of meters and the

replacement of defective meter as

per SOP guidelines issued by

RERC.

v. Augment capacity of conductor as

per load requirement

vi. Augment distribution transformers

capacity as per connected load

growth.

vii. Organize intensive vigilance

checking’s to curb the theft of

energy. Government of Rajasthan

can help the Distribution

Companies by setting up Special

Police Station, Special court for

Page 36: A Joint Initiative of Government of India and Government of Rajasthan

36

speedy resolution of the Electricity

cases.

viii. Maximize the collection payment

avenues thereby maintaining more

than 99.5% collection efficiency

ix. Install prepaid meters to the

Government connections

x. Use IT enabling tools to identify

the high loss areas to take

measures for loss reduction.

xi. Capturing of actual energy

consumption by utilizing IT

interface.

xii. Most state DISCOM’s Grids are

manned on 24x7 basis and duty

registers/log sheets are maintained

in the grid for recording the

voltage, current and other data

with respect to all the feeders. The

data are recorded in register by the

shift people by manually reading

the data from the meters. However,

with R-APDRP roll-out both in R-

APDRP and non-APDRP towns, ,

it is expected that the electronic

meters with downloading facilities

are been installed and hence

DISCOM may enforce the practice

of data downloading through

CMRI for feeder meter data and

carry out data analysis/ energy

audit on such data

(h) Improving Consumer Convenience:

Improving consumer convenience should be

the focus of any distribution utility. For

improving consumer convenience in

Rajasthan Standard of Performance

guidelines has been recently issued by the

Regulator.

DISCOM should submit the compliance on

SOP in the time period as prescribed by the

regulator. For improving further and make the

process more transparent state regulator can

undertake Customer Satisfaction Survey

through some independent agency.

Customer segmentation in terms of

differentiated service delivery can also be

prescribed by state regulator in the next

phase.

(i) Revamping Maintenance Philosophy:

Presently DISCOMS are only engaged in

Break Down repair work of the various

equipments. In order to increase reliability of

the system DISCOM should look for

implementing system driven preventive

maintenance system. Power Transformers,

Distribution Transformers, Circuit Breakers

can be checked periodically for identification

of any faults and correction thereof. Further,

Discom should have defined roadmap to

adapt Predictive Maintenance as well.

(j) Performance Monitoring Mechanism: In order to implement appropriate reform

measures and meet the objective, baseline

parameters needs to be verified and

established, and hence it is proposed that a

Third Party Audit should be carried out for

establishing the baseline parameters for the

KPI indicated below and thereafter following

performance parameters needs to be

monitored at the DISCOM Corporate level

Corporate

Strategic

Objectives

KPI UOM

Maximize

Rate of

Return

PAT Rs Crs

No of households

to be electrified

Nos in

Lakhs

CAPEX Rs. Crs

Sustain

AT&C loss

level &

achieve

further

reduction

AT&C Losses %

Collection

Efficiency

%

Billing Efficiency %

Monitoring

Distribution

Cost

Establishment

Cost

Rs. Crs

R&M Cost Rs. Crs

Page 37: A Joint Initiative of Government of India and Government of Rajasthan

37

Corporate

Strategic

Objectives

KPI UOM

A&G Cost Rs. Crs

Power Purchase

Cost

Rs./unit

Enhancing

Customer

Satisfaction

CSI Overall Index

Total Consumer

Complaints/ '000

consumers

Nos.

New initiatives to

enhance customer

convenience

Nos.

Addition in

regards to Payment

Avenues

Nos.

PA Compliance

Index

Index

Operational

Efficiency

No. of customers

served /employee

Ratio

System

Reliability

SAIDI Hrs

SAIFI nos.

DTR Failure Rate %

PADCI

(Project Av.

Duration Closure

Index)

Months

No of Accidents

(Fatal/ Non Fatal)

Nos

5.4. CONNECTING THE

UNCONNECTED

As per GoR, there are about 36.75 lakhs un-

electrified households in the state including

34.85 lakhs in the rural areas and 1.9 lakhs in

urban areas.

5.4.1 Urban Area

As per GoR, in urban areas, at present only 15

thousand applications are pending for

connections and it is expected that remaining

urban households are using electricity on

sharing basis as a united family. Keeping in

view of the fast growth of households in the

urban areas due to migration from rural to

urban, target of release of connection of 1

lakh per year has been estimated as per trend

of last five years.

5.4.2 Rural Area

Out of 34.85 lakhs un-electrified rural

households in the state, only about 25 lakhs

households may be considered as un-

electrified which would be provided

electricity through grid and balance

households may be located in remote places

or using the electricity on shared basis as a

united family. Out of the balance 9.85 Lakhs

un electrified rural households, about 1.5 lakh

household have already been provided solar

domestic lighting system and 1.1 lakh

households will be provided Solar Domestic

Lighting System (SDLS) in next five years.

Balance 7.25 lakh households are located in

agriculture fields or using electricity on

sharing basis as united families, living in

carvan, forest areas, remote far flung areas

etc. The details of the above are as under-

Rural uneletrified Households No in lakhs

Total 34.85

To be electrified under RGGVY 18.80

Dhanies with population less than

100

2.12

To be electrified from existing

grid in already electrified villages

& Dhanies

4.08

Already provided solar domestic

lighting system

1.50

Solar domestic lighting system to

be provide in next 5 years

1.10

H/Hs located in Ag fields, forest

areas, carvans, remote far flung

areas etc

7.25

Page 38: A Joint Initiative of Government of India and Government of Rajasthan

38

5.4.2.1 Electrification of 18.80 Lakhs

Households under RGGVY

• About 15000 households would be

electrified under the already approved 10th

& 11th

Plan RGGVY

• 13.36 lakhs households have already been

sanctioned under 12th

plan RGGVY.

• 6 more schemes at an estimated cost of

Rs. 813 Crores covering 5.44 lakhs

households in six districts have been

submitted to REC for sanction under 12th

plan RGGVY.

5.4.2.2 Electrification of 2.12 lakhs

Households located in Dhanies with population less than 100:

Around 2.12 lakhs households are estimated

to be located in about 30 thousand un-

electrified /partially electrified Dhanis

households in the state which are not eligible

to be covered under RGGVY. As per GoR,

majority of the households located in these

Dhanis may be electrified by extending

supply from the grid at an estimated cost of

Rs. 1839 Crores.

5.4.2.3 Out of the remaining 13.25 Lakh un-

electrified households in the state, Govt of

Rajasthan may identify such households

which can not be electrified by extending

supply from the existing grid in next 3

months. A detailed plan will thereafter be

formulated in next 3 months to see which

households are economically feasible to be

connected with the grid and which would

need off grid solutions. The plan would be

implemented in the time frame indicated

earlier. The details of various off grid

solutions of MNRE are at Annexure –VII.

5.1. FUND REQUIREMENT

The summary of total fund required for these proposed distribution works are as under–

Table 5.2: Details of Investment Planned (Rs in crores)

Distribution

FY 14-

15 FY 15-16 FY 16-17 FY 17-18 FY 18-19 Total Remarks

State Plan 1513 1437.00 1372.00 1549.74 1595.17 7466.91 No central assistance is

required

Centrally sponsored

Schemes already

approved (RGGVY &

RAPDRP)

885 1003.83 450 403.19 0 2742.02 Approved by GOI

Electrification of 6

lakh un-electrified

H/h located in

Dhanies

0 450 450 450 489 1839 As indicated in 5.4.2.3

RGGVY submitted

schemes 63 250 250 250 813

Earlier sanction of

RGGVY schemes

submitted to REC

Other development

distribution schemes 2532 754.23 417 372 394.94 4470.17

May be covered under

GOI new schemes which

are being finalised by

MOP as per the norms of

the schemes / policies

Details of investment plan for next five years for state funding & fund requirement from GoI are

given at Annexure –VIII & IX

Page 39: A Joint Initiative of Government of India and Government of Rajasthan

39

5.2. ACTION POINT- STATE

1. To complete all the distribution works

necessary for providing 24x7 quality

supply to all the connected consumers.

2. To take necessary steps to meet the

agreed trajectory for reduction of

AT&C losses

3. To identify such un-electrified

households which can not be

electrified by extending supply from

the existing grid in next 3 months and

to formulate a detailed plan in next 3

months to finalise the economical

feasible for connection with the grid

and off grid solutions. Accordingly,

take necessary steps to provide access

to electricity to all unconnected

households in a time bound manner in

next five years i.e. by FY 2018-19.

4. To introduce modern technologies to

monitor reliable supply like sub-

station automation, providing adequate

communication infrastructure, GIS,

Reliability, Centralised Network

Analysis and Planning tools, SAP

driven ERP systems, DMS

(Distribution Management Systems),

OMS (Outage Management System),

etc.

5.3. GOI INTERVENTION

1. GoR has requested assistance form GoI

for an amount of Rs. 4470.17 Crores for

strengthening of distribution network for

providing 24x7 supply like feeder

improvement, substation improvement,

creation of new 33 kV sub-stations,

separation & providing three phase

system to the electrified villages of

population more than 2000 and system

augmentation in non RAPDRP towns etc.

Two Schemes i.e. Integrated Power

Development scheme (IPDS) and Deen

Dayal Upadhyaya Gram Jyoti Yojna

(DDUGJY) for funding for strengthening

& augmentation of sub transmission and

distribution works, 100% metering,

capacity building, ERP and feeder

segregation have been launched by

MoP. As RAPDRP scheme has been

subsumed in a newly launched scheme of

Integrated Power Development scheme

(IPDS) GoR may seek funding for the

above works under this scheme.

2. Six(6) schemes at estimated cost of

Rs.813 Crore have been submitted by

GoR to REC for sanction under 12th

Plan RGGVY and requested for early

sanction of the same.

As RGGVY scheme has been subsumed in a

newly launched scheme of DDUGJY, GoR

may seek assistance under this new scheme.

Page 40: A Joint Initiative of Government of India and Government of Rajasthan

40

5.4. RENEWABLE ENERGY

INITIATIVES OF GOVT OF

RAJASTHAN AT CONSUMER

LEVEL

• Grid connected Roof Top Scheme

During the year 2013-14, an approval of 5

MW capacity for grid connected roof top

system had been received from MNRE to

RRECL which is state nodal agency for

the promotion & development of

renewable energy in the state. This

scheme is having a provision of 30%

subsidy from MNRE and 70% has to be

borne by the beneficiary. The scheme is

proposed to be taken during 2014-15

subject to finalisation of Net Metering

Regulations by Regulatory Commission.

The petition is pending in this regard with

SERC.

• Solar water Pumping Scheme

This is a scheme by MNRE. Presently the

scheme is being implemented by state

Horticulture Deptt. Since 2010-11. Total

subsidy provided is 86 %( 30% from

MNRE & 56% from Rastriya Krishi

Vikas Yojana) of the bench mark cost of

the pump Balance 14% is to be borne by

the beneficiary. The details of the pumps

installed during last 4 years is as follows-

Year No of Pumps

2010-11 34

2011-12 1675

2012-13 4280

2013-14 6900

It is proposed that around 5,000 pumps/

year would be installed in the state if the

above subsidy pattern is continued.

• Solar Off-Grid Systems

It is an ongoing scheme of MNRE in

which domestic lighting system (DLS) /

home lighting system (HLS) are being

provided to the beneficiaries in rural and

urban areas having one solar module of 37

W, 2 CFLs each of 9 W and one battery of

40 Ah capacity. This scheme is having a

provision of 30% subsidy from MNRE

and 70% has to be borne by the

beneficiary. So far more than 1.5 Lakhs

systems have been installed in the state.

The Government buildings, hospitals,

Public Health Centres (PHCs) in rural and

semi-urban areas are proposed to be

provided with Solar Off-Grid Systems

with battery support.

DPRs for above schemes would be

prepared and submitted to MNRE for

approval on yearly basis. The projected

figures of above scheme are mentioned in

the given below table:

Table 5.3: Details of Renewable Energy initiatives ( Physical & Investement)

Sl.

No. Particulars Unit FY 14-15 FY 15-16 FY 16-17 FY 17-18 FY 18-19 Total

A Grid connected

Solar Rooftops No.

3.5MW

100 no’s

10MW

300 no’s

10MW

300 no’s

10MW

300 no’s

10MW

300 no’s

43.5MW

1300 no’s

Investment

required

Rs.

Cr. 25 70 70 70 70 305

Assistance req

under NCEF % 30% 30% 30% 30% 30% 30%

B Solar off-grid

systems No.

2 MW

(10000)

5 MW

(25000)

5 MW

(25000)

5 MW

(25000)

5 MW

(25000)

22 MW

(110000)

Investment

required

Rs.

Cr. 37 92.5 92.5 92.5 92.5 407

Assistance req

under NCEF % 30% 30% 30% 30% 30% 30%

Page 41: A Joint Initiative of Government of India and Government of Rajasthan

41

C Solar pump

systems No. 5000 5000 5000 5000 5000 25000

Investment

required

Rs.

Cr. 360 360 360 360 360 1800

Assistance req.

under NCEF

% 30% 30% 30% 30% 30% 30%

Assistance

discontinued

under Rashtriya

Krishi Vikas

Yojana, which

may be

continued by

GOI

% 56% 56% 56% 56% 56% 56%

5.5. ACTION PLAN - STATE –RENEWABLE ENERGY

DPRs for above schemes would be prepared and submitted to MNRE for approval on yearly basis.

5.6. GOI INTERVENTION

1. To facilitate the earlier approval of DPRs for the above schemes under National Clean Energy

Fund (NCEF)

2. Continuation of 56% assistance under Rashtriya Krishi Vikas Yojana for Solar Pump system

Page 42: A Joint Initiative of Government of India and Government of Rajasthan

42

6. ENERGY EFFICIENCY

With increasing importance being given to low carbon growth these days, the cheapest and more

affordable option to overcome the energy deficit is Demand Side Management and implementation

of energy efficiency measures in various sectors such as agriculture, municipalities, buildings,

domestic, industries etc. In this chapter, the demand side energy savings potential that exist in

Rajasthan, interventions and timelines are discussed.

A. SAVINGS POTENTIAL & INVESTMENT

Table 6.1 summarizes the sector specific demand side energy savings potential vis-à-vis the

investments required in the state of Rajasthan.

Table 6.1

S.

No Sector

Percentage of

energy

consumption

Consumption

(MU)

Savings

Potential

per annum

(MU)

Investment

to achieve

potential

savings

(INR crores)

Techniques to be

incorporated

1. Agriculture 41 % 17839 4770 7200

Replacement with

energy efficient

pump sets

2. Domestic 21% 9009.6 2100 1604

Replacement of

ICLs with LED

bulbs

3. Commercial

Buildings 7% 3226.5 480* 720*

Retrofitting of

energy efficient

equipments

4. Public Water

Works 4% 1541.5 400 250

Replacement with

energy efficient

pump sets

5.

Municipal

Street

lighting

1% 389.1 200 400

Replacement of

existing street lights

with LED.

Total 32004 7950** 10174**

* For commercial buildings sector only 50% (i.e. 1613 MU) having connected load greater than 100 kW or with contract demand of

120 kVA or more are considered.

**Around 7950 MU of energy savings annually can be achieved at an investment of Rs. 10174 crores.

Page 43: A Joint Initiative of Government of India and Government of Rajasthan

43

B. INTERVENTIONS

The agricultural sector accounted for about

41% of the state’s energy consumption i.e.

17.8 BU during 2013-14 and the subsidy

burden of the State for the year 2014-15 is

estimated at Rs. 6000 crores for about 1.2

million pump sets.

Two successful pilots in Agricultural Demand

Side Management have proved that

investment in agricultural pump sets

efficiency can payback in a short time, refer

Table 6.2 below:

Table – 6.2

No. Parameters Solapur Hubli

1. No. of pumpset

replaced

2209 590

2. Annual energy savings

achieved (MUs)

6.1 2.9

3. Energy Savings (%) 25 37

4. Investment (INR crores) 8 2.6

5. Annual Reduction of

subsidy (INR crores)

1.2 1.01

There are about 12 lakhs agricultural pump

sets which are eligible to receive subsidy from

the state government. The State Govt. is

providing subsidy of Rs 3.03 per unit of

energy consumption in Agriculture sector. As

per the DRP prepared by BEE in JVVNL for

1800 pump sets, the energy saving potential is

around 45%. Taking the average energy

savings outcome of the two pilots, a 30%

reduction in energy consumption and subsidy

is possible by replacing all existing pumps

with star rated energy efficient pump sets.

The average pump sizes in JVVNL &

AVVNL are 6.5 KW, while in JDVVNL it is

16 KW. The estimated investment in

replacement of 12 lakhs pump sets, taking an

average cost of efficient pump sets to Rs.

60,000 will be of Rs. 7200 crores with an

estimated savings of around 4.77 BU per

annum. Apart from the

energy savings, this would result in annual

subsidy savings of Rs. 1200 crores to the state

Based on the estimated subsidy reduction, the

simple payback on investment is around 6

years. Farmers have little financial obligation

to pay electricity bills, therefore apart from

monetary savings on account of electricity

bills, the reduced maintenance cost of farmers

is the biggest incentive in such interventions.

Doemstic sector accounted for an energy

consumption of 9.1 BU which is nearly 21%

of the total consumption in 2013-14. In order

to stimulate investments in energy efficient

lighting projects, high quality LED lamps are

proposed to be given to households at the cost

of incandescent lamps (ICLs) to encourage

them to invest in energy efficiency under the

DSM based Efficient Lighting Program

(DELP).

The main features of DELP includes

replacement of 60 W ICL with 8 W LED with

5-6 years free replacement warrantee on

lamps against technical defects, distribution of

3 LEDs to each household on getting back the

working ICLs and monitoring of projects as

per international standard methodology

approved by CDM Executive Board for BLY.

There are an estimated 12.6 million

households in the state as per 2011 Census

data. Thus, the total energy savings from

replacement of ICLs to DISCOMs will be

2100 MU annually at an investment of Rs.

1604 crores. Puducherry has become the first

state to undertake implementation of DELP

on a large scale.

Page 44: A Joint Initiative of Government of India and Government of Rajasthan

44

In 2013-14, the commercial sector in the state

of Rajasthan accounted for nearly 7% of the

total energy consumption, i.e., 3226 MU of

which the targeted baseline for energy

conservation is around 50% (i.e. 1613 MU) in

the organized sector in buildings having

connected load greater than 100 kW or with

contract demand of 120 kVA or more.

Techno-commercial analysis for energy

efficiency project implementation at Vidyut

Bhawan and Rajasthan Secretariat in Jaipur

shows energy savings of 0.13 MU and 0.85

MU per annum with estimated investments of

Rs. 0.42 crores and Rs. 2.4 crores

respectively. As per details available, energy

savings to the tune of 30% are achievable in

the end use functional areas of lighting,

cooling & ventilation, refrigeration, etc.,

which can help the state alleviate 480 MU,

with an estimated investment requirement of

Rs. 720 Crores. In addition to these, Rajasthan

Government has already adopted Energy

Conservation Building Code (ECBC) for new

commercial buildings, the effective

implementation of which will also result is

significant energy savings.

The municipal sector accounted for 5% of the

energy consumption, with public water works

comprising 4% (1540 MU) and street lighting

constituting of around 1% (389 MU). Various

energy audit studies have revealed a savings

potential of 25% - 30% through replacement

of inefficient drinking and sewage water

pumping systems with energy efficient ones.

Thus, it can be estimated with an investment

of around Rs. 250 crores all the drinking and

sewage water pumping systems can be made

energy efficient and savings of around 400

MU annually can be achieved.

In Rajasthan, almost the entire public lighting

is based on conventional lights and it has been

demonstrated that replacement of these

existing lights with LEDs can lead to an

energy savings between 55-60%. In addition

to energy savings, LED street lights also

reduce maintenance costs as they come with

5-7 years free replacement warranties enhance

the light output and meet national lighting

standards, allow automatic controls to

enhance savings by remote switching,

daylight savings and dimming. In addition,

LED lamps improve the power factor of the

system and enhance the savings to DISCOMs.

Replacement of all street lights with LEDs in

Rajasthan with an investment of around Rs.

400 crores can lead to energy savings of 200

million units annually.

C. APPROACH / STRATEGY

All the above interventions involve

replacement of inefficient equipment /

appliances with energy efficient ones for the

agriculture, domestic, commercial buildings

and municipalities. These can be undertaken

by the State Govt. at no upfront cost by

using the Energy Service Company (ESCO) model. The model is based on the

concept of promoting Performance Contract

mode where the company invests in any

project by entering into a contract agreement

with the facility owner which is recovered

through the savings accrued due to reduced

electricity bills.

D. TIMELINES

Agriculture Sector:

Under AgDSM, a plan to cover the entire 12

lakh pump sets is indicated below in Table 6.

3. The year wise investment required, savings

to be achieved and reduction of subsidy

burden is also indicated. The project will also

evolve standard operating processes as well as

robust payment security mechanisms so as to

replicate the same in an accelerated manner.

Assuming the state government is paying

subsidy of Rs 2.50/ per unit of energy

consumption in agriculture sector. The

estimated simple payback period is around 6

years.

Page 45: A Joint Initiative of Government of India and Government of Rajasthan

45

Table 6.3

2014-15 2015-16 2016-17 2017-18 2018-

19

Total

Total pumps to be replaced 50000 250000 300000 300000 300000 1200000

Amount of energy savings (MU) 198.75 993.75 1192.5 1192.5 1192.5 4770

Investment (INR crores) 300 1500 1800 1800 1800 7200

Domestic Sector:

A plan to cover the entire state having 12.6 million households has been prepared which is in Table

6.4 below. The year wise investment required and savings to be achieved is also indicated.

Table -6.4

Parameters 2014-15 2015-16 2016-17 2017-18 2018-19 Total

No. of Households 600000 3000000 3000000 3000000 3000000 12600000

No. of LED replaced 1800000 9000000 9000000 9000000 9000000 37800000

Annual Energy Saved (MU) 100 500 500 500 500 2100

Investment (INR crores) 76 382 382 382 382 1604

Assuming electricity price in the domestic sector to be Rs. 4/kWh, the simple payback period is around 2

years.

Commercial buildings:

The plan to cover the commercial buildings in Rajasthan is at Table 6.5 below:

Table 6. 5

Parameter 2014-15 2015-17 2016-17 2017-18 2018-19 Total

Coverage of

retrofitting in

commercial buildings

Government

buildings

(20%)

Government

buildings

(40%) + 10%

of Private

buildings

Government

buildings (40%)

+ 20% of

Private

Buildings

30% of

Private

buildings

40% of

Private

buildings

100%

Govt. +

Private

buildings

Annual Energy Saved

(MU)

19.2 76.8 115.2 115.2 153.6 480

Investment (INR

crores)

28.8 115.2 172.8 172.8 230.4 720

Assuming electricity price in the non - domestic sector to be Rs. 4 / kWh, the simple payback period

is around 4 years.

In addition to above, the following activities to promote the efficient use of energy and its

conservation in commercial buildings (refer Table – 6.6) may be undertaken:

Page 46: A Joint Initiative of Government of India and Government of Rajasthan

46

Table – 6.6 S.

No. Activity Timelines

1 Amendment in Schedule of Rates and Plinth Area rates of PWD 2014-15

2 Amendment of standard design template of public buildings On going

3 Training and capacity building of compliance officials and design professional

through Institutional framework

On going

Municipal Sector (Public Water Works & Street Lights):

A plan to cover the entire municipal sector (public water works and street lights) of the state is

given below in Table – 6.7 and Table -6.8.

Public Water Works:

Table -6.7

Parameters 2014-15 2015-16 2016-17 2017-18 2018-19 Total

% of water pumping systems to

be covered

12.5 12.5 25 25 25 100

Annual Energy Saved (MU) 80 80 80 80 80 400

Investment (INR crores) 50 50 50 50 50 250

Assuming electricity price in the public water works to be Rs. 4/kWh, the simple payback period is

around 1.5 years.

Street Lights:

Table – 6.8

Parameters 2014-15 2015-16 2016-17 2017-18 2018-19 Total

% of street lights to be covered 12.5 12.5 25 25 25 100

Annual Energy Saved (MU) 25 25 50 50 50 200

Investment (INR crores) 50 50 100 100 100 400

Assuming electricity price in street lighting to be Rs. 4/kWh, the simple payback period is around 5

years.

Sector-wise investments to achieve the savings potential through various energy efficiency

measures for 5 years are given below at Table -6. 9:

Table – 6.9

Sectors

2014-15 2015-16 2016-17 2017-18 2018-19

Investmen

t

(INR cr)

Saving

s

(MU)

Investmen

t

(INR cr)

Saving

s

(MU)

Investmen

t

(INR cr)

Saving

s

(MU)

Investmen

t

(INR cr)

Saving

s

(MU)

Investmen

t

(INR cr)

Saving

s

(MU)

Agricultur

e 300 198.75 1500 993.75 1800 1192.5 1800 1192.5 1800 1192.5

Domestic 76 100 382 500 382 500 382 500 382 500

Commerci

al

Buildings

28.8 19.2 115.2 76.8 172.8 115.2 172.8 115.2 230.4 153.6

Page 47: A Joint Initiative of Government of India and Government of Rajasthan

47

Public

Water

Works

50 80 50 80 50 80 50 80 50 80

Street

Lights 50 25 50 25 100 50 100 50 100 50

Total 504.8 422.95 2097.2 1675.5

5 2504.8 1937.7 2504.8 1937.7 2562.4 1976.1

Cumulativ

e

saving(MU

)

422.95 2098.5

0 4036.2 5973.9 7950

E. ACTIONS POINTS

The sector-wise Central Government and

State Government actions envisaged to

facilitate implementation of energy efficiency

measures as mentioned above are detailed

below:

Agriculture Sector

• Funds Required: Rs. 7200 crores

• Savings: 4770 MU

Central Government:

• M/o Agriculture may amend the

guidelines of various schemes like

Rashtriya Kisan Vikas Yojana (RKVY) to

promote use of star rated energy efficient

pump sets (EEPS) under these schemes

• BEE may expand its star labelling

programs to cover higher size pump sets.

• Energy Efficiency Services Limited

(EESL) to take up project design and

project development.

State Government:

• Distribution Companies / Utilities may

file DSM petition with Rajasthan

Electricity Regulatory Commission for

getting sanction of the proposed DSM

plan.

• Rationalization of agricultural tariff so

that benefit of energy efficiency is

distributed to utility and consumer

optimally.

• State may issue mandatory notification for

use of energy efficient pump set for new

agriculture connections. Also encourage

and continue the schemes for promoting

EEPS like the present scheme of

providing financial assistance of Rs. 500/-

per HP for up gradation of existing pump

sets or procurement of new EEPS.

• Ensure formulation of a detailed time line

in consultation with concerned

departments like Distribution Companies

for implementation of energy efficiency

measures in agriculture.

• Ensure establishment of a payment

security mechanism so that the company

making investments under the ESCO

mode recovers the same through the

savings accrued due to reduced electricity

bills.

Domestic Sector

• Funds Required: Rs. 1600 crores

• Savings: 2028 MU

Central Government:

• BEE may consider formulation of

specification for LED bulbs and

introducing star label scheme for LED

bulbs.

Page 48: A Joint Initiative of Government of India and Government of Rajasthan

48

• Energy Efficiency Services Limited

(EESL) to take up project design and

project development.

State Government:

• Distribution Companies / Utilities may

file DSM petition with Rajasthan

Electricity Regulatory Commission for

getting sanction of the proposed DSM

plan.

• Ensure formulation of a detailed time line

in consultation with concerned

departments like Distribution Companies

for implementation of energy efficiency

measures in municipalities.

• Ensure establishment of a payment

security mechanism so that the company

making investments under the ESCO

mode recovers the same through the

savings accrued due to reduced electricity

bills.

Commercial buildings

• Funds Required: Rs. 720 crores

• Savings: 480 MU

Central Government:

• BEE may provide technical support for

effective enforcement of ECBC and

promotion of ESCO based retrofitting

works in Government buildings. BEE can

provide support for capacity building of

state department through establishment of

ECBC cells for compliance of ECBC and

retrofitting in Government buildings.

• Energy Efficiency Services Limited

(EESL) to take up project design and

project development for retrofitting in

commercial buildings.

State Government:

• Government of Rajasthan has adopted

ECBC Directives for new commercial

building design and mandated energy

audit of existing commercial building

once in a three-year period. Effective

enforcement of ECBC compliance and

mandating retrofitting in energy-audited

buildings may result in reduction of

electrical consumption from commercial

sector. Government of Rajasthan may

consider mandatory retrofitting in

Government buildings with an objective

of reduction of electricity bills, which

state government is paying against

electricity bill of these buildings. This

would also demonstrate impact of ESCO

based retrofitting projects to private

building owners to adopt the same.

• As per the Planning Commission’s

projection; residential building are

becoming one of the larger consumers of

electricity in the county by 2030. BEE is

introducing design guidelines for energy

efficient multi storey residential

apartments including in the composite and

hot & dry climatic zone. State

Government may mandate compliance of

these guidelines through institutional

framework in the state.

• Ensure formulation of a detailed time line

in consultation with concerned

departments like Public Works

Department, for implementation of energy

efficiency measures in municipalities.

• Ensure establishment of a payment

security mechanism so that the company

making investments under the ESCO

mode recovers the same through the

savings accrued due to reduced electricity

bills.

• For residential buildings, the state could

adopt the star labelling scheme for multi-

storey residential apartment buildings,

being prepared by BEE.

Municipal Sector (Public Water Works &

Street Lights)

(i) Public Water Works

Funds Required: Rs. 250 crores

Savings: 400 MU

Page 49: A Joint Initiative of Government of India and Government of Rajasthan

49

(ii) Street Lights

Funds Required: Rs. 400 crore

Savings: 200 MU

Central Government:

• BEE may consider formulation of

specification for LED street lights and

provide some financial assistance for one

pilot project under MuDSM program.

• Energy Efficiency Services Limited

(EESL) to take up project design and

project development.

State Government:

• Ensure formulation of a detailed time line

in consultation with concerned

departments like Public Health &

Engineering Department and Urban

Development Department for

implementation of energy efficiency

measures in municipalities.

• Ensure establishment of a payment

security mechanism so that the company

making investments under the ESCO

mode recovers the same through the

savings accrued due to reduced electricity

bills

In addition to the above, Rajasthan Electricity

Regulatory Commission (RERC) may be

requested to issue directives for creation of

DSM funds by DISCOMs / Utilities of the

State so that DSM activities can get extra

emphasis. Such funds can be utilized for

meeting incremental cost of efficiency

improvement.

Page 50: A Joint Initiative of Government of India and Government of Rajasthan

50

7. FINANCIAL VIABILITY OF DISTRIBUTION COMPANIES

7.1. FINANCIAL POSITION OF

DISTRIBUTION UTILITIES

After unbundling of the erstwhile Rajasthan

State Electricity Board (RSEB) in July 2000,

Rajasthan Discoms commenced their

operations with a loss of Rs. 680.00 cr. in FY

2001, which increased to Rs. 3908 cr. in FY

2003-04 and thereafter touched to Rs. 15,643

cr. in FY 2008-09. The primary reasons for

increasing the loss level from FY 2003-04 to

FY 2008-09 were one tariff hike only during

the period in Jan. 2005 that too 10.15% and

higher quantum of power purchase at

comparatively higher cost due to state

generation projects lagging behind their

schedules.

During this period Feeder Renovation

Programme was aggressively implemented

which resulted in drastic reduction in

distribution loss level from 42.62% in FY

2003-04 to 26.59 % in FY 2008-09. Had this

ambitious programme not been there, the

above accumulated financial loss level would

have been phenomenally on much higher side.

The accumulated financial loss further

ballooned to Rs. 74,280 cr. (Prov.) in FY

2013-14 despite three consecutive tariff hikes

after 2008-09. Moreover, the distribution loss

also stood at 24.38 % (AT&C losses 26.74%)

in FY 2013-14.

The recovery of total cost of power supply

from revenue stood at 85 % during FY 2003-

04, which remained 60% in FY 2008-09 and

62% in FY 2013-14 (Prov.). Despite three

tariff hikes in a row during the period, there

was only a marginal improvement in recovery

of cost in FY 2013-14. This also indicates that

the expenditure during the period also

increased commensurately with the

incremental revenue, chiefly on account of

ever rising interest and finance charges,

increasing trend in power purchase cost and

almost static distribution loss levels amongst

others. The interest and finance charges are

disturbing the cost economics of Discoms so

adversely that in case the interest and finance

charges are excluded from the total cost, then

the above stated cost recovery would stand as

82% in FY 2013-14, leaving a gap of 18%

only which can be addressed by suitable tariff

hikes and internal operational efficiencies. In

case the liability of the short term outstanding

loans is fully taken out from the Discoms’

books, the Discoms shall not only manage

their cost of power supply but also will not

require working capital support on one hand

and on the other they would also not be in

need of steep tariff hikes again and again .

In the beginning of FY 2011-12, the banks had

stopped funding to the Discoms, resulting in

over delay in various payment obligations to

power generators/ suppliers and others,

leading to likely disruption of power supply as

the various power generators/suppliers started

cautioning to stop the power supply including

serving of regulation notices, invocation of

Letter of Credits (LCs) established in their

favor. Repayments along with interest

servicing to banks/FIs had to be stopped

resulting in accruing of penal interest as well

as turning of various loan accounts on the

verge of Non-Performing Assets (NPA).

Likewise, over delayed payment to various

power generators attracted late payment

surcharge which in turn further deteriorated

liquidity crisis already looming over.

Moreover, other suppliers/contractors denied

to further supply and execute the contracts

resulting in various capital projects and

maintenance works held up.

7.2. FINANCIAL RESTRUCTURING

SCHEME OF GOI (OCTOBER

2012)

Taking a serious view over the ever

deteriorating financial condition of the state

owned Discoms across the country, the

Page 51: A Joint Initiative of Government of India and Government of Rajasthan

51

Planning Commission set-up a Committee

headed by Sh. B.K. Chaturvedi, Member,

Planning Commission to come out with a

sustainable and viable scheme for long term

viability of the distribution utilities

particularly in the most critical States, referred

as the focused states including Tamil Nadu,

UP, Haryana and Rajasthan. Based on the

recommendations of the said Committee, the

Ministry of Power, Govt. of India notified a

Scheme on 5.10.2012 for long term

sustainability of the Discoms in the country.

Rajasthan was one of the early movers for

providing consent to participate in the above

Scheme.

• On the cut- off date 31st March 2012 the

accumulated losses of the Discoms were to

the tune of Rs.40, 942 cr. against which

the outstanding short term loans were

Rs.31, 906 cr. and power purchase

payables outstanding for more than 60

days Rs. 4132 cr making a total of Rs.

36,038 cr.

• As such Discoms were eligible for full

outstanding liabilities as on 31st March

2012 of Rs. 36038 cr. Out of this, bonds

worth Rs. 18019 cr were to be issued by

the Discoms and to be taken over by the

State Govt. over a period of time in a

phased manner. The remaining short term

loans were to be restructured by banks.

Some of the key commitments on the part of various stakeholders as envisaged in the Scheme vies-

a-vies their compliances as of now are given as under:-

Sr. No. Commitments Compliances

1. Financial Restructuring Plan (FRP) is to be

chalked out by the Discoms and to be

approved by the state govt. state regulatory

commission and by the banks/FIs.

Has been prepared and finalized after approval

of all the required stakeholders.

2. Bonds against 50 % short term liabilities

(including power purchase payables )

outstanding as on 31st March 2012 are to

be initially issued by Discoms;

Bonds amounting to Rs. 17961 Cr. have been

issued to the various banks at a coupon rate of

9.95% p.a. on 18th

October 2013;

3. Remaining 50% short term loans

outstanding as on 31st March 2012 are to

be restructured for a period of 10 years

with a moratorium on principal of 3

years;

Outstanding short term loans amounting to Rs.

15,928 Cr. have been restructured by the

banks.

4. The bonds issued by the Discoms are to

be taken over by GoR through special

Govt. securities in a phased manner

within next 2 to 5 years

GoR has committed to take over the bonds

worth Rs. 3,000 Cr. in FY 2013-14, Rs. 4,500

Cr. in FY 2014-15 Rs. 5700 Cr. in FY 2015-16

and the balance Rs. 4,761 cr. in 2016-17;

During previous FY 2013-14 bonds amounting

to Rs. 3,340 cr. instead of committed Rs. 3000

cr. have already been taken over by GoR.

5.. Banks/FIs to provide loan against

operational funding during next three

years starting from FY 2013 on a

diminishing scale;

Banks have provided fresh working capital

loans amounting to Rs. 10,952 Cr. in FY

2012-13, Rs. 9016 Cr. in FY 2013-14, and

have sanctioned Rs. 1101.01 cr. (up to July

14) against the committed of Rs. 2878 cr. for

current FY 2014-15 and the remaining is in

process of sanctioning at the end of the banks.

Page 52: A Joint Initiative of Government of India and Government of Rajasthan

52

6. Filing of tariff petitions regularly. Being done regularly.

7. Pass through of adjustment of fuel cost to

offset power purchase cost.

Being done regularly.

8. Constitution of monitoring committees State Level Monitoring Committee (SLMC)

constituted by the GoR vide order dated

11.12.2012, three meetings already held, last

one held on 4th June 2014.

9. Conversion into equity/ deferment of

repayment of outstanding state govt. loans.

Following the condition of the Scheme, GoR

is not insisting the repayment of interest free

loans provided to Discoms.

10. Central Govt. would provide incentive by

way of grant

(i) equal to the value of the additional

energy saved by way of accelerated AT&C

loss reduction i.e. reduction beyond 1.5%

annually; and

(ii) 25% of reimbursement to the state

Govt. of bonds taken over by the latter.

To be complied with in due course.

11. 100% consumer metering. Consumer metering is complete. There are

only 1.41 lacs flat rate agriculture consumers

being not billed on metered energy basis.

However, meters have also been installed to

these consumers to ensure recording of actual

consumption.

12. Outstanding dues of State Govt.

departments to be paid off till 30th Nov.

2012.

Done.

Besides the above, the other conditions

relating to installation of prepaid meters and

involvement of private participation etc. are in

process of implementation.

The implementation of the above mandatory

conditions has cushioned the distribution

companies to partially mitigate the issues

being faced to the extent as briefed below:

1. Filing of tariff petitions annually from

FY 2011-12 and onwards and roll over

of tariff orders and pass through of fuel

cost adjustment have improved the

revenue streams;

2. Repayment and interest servicing on

50% outstanding short term liabilities as

on 31st March 2012 have been taken

over by the State Government w.e.f.

18.10.2013(date of issue of bonds)

resulting in a relief of around 810 cr.

during FY 2013-14;

3. Moratorium on repayment of remaining

50% short term loans outstanding as on

31st March 2012 stands extended till 31

st

March 2015 to tide over the prevailing

liquidity crisis to this extent.

4. Annual accounts of the companies are

being audited and finalized in time.

Though the Discoms have partially been

eased out on account of the

implementation of the Scheme, yet the

following compelling factors have

Page 53: A Joint Initiative of Government of India and Government of Rajasthan

53

necessitated updating of the existing FRP

so as to effectively garner the envisaged

benefits of the GoI Scheme.

• Bonds were to be issued effective from

1.4.2012 but delay in notifying the

guidelines on issuance of bonds and

subsequent frequent discussions with

Banks to evolve a consensus on

coupon rate and cut-off date, the

bonds could be issued only on 18th

Oct. 2013. This has resulted in burden

of interest liability on the bonds

portion shouldered by Discoms from

1st April 2012 to 17

th Oct 2013;

• The benefit of tariff hike during FY

2011-12, 2012-13 and 2013-14 could

not be available for the full year as the

tariff orders were made effective from

the date mentioned against each as

under:

Financial Year Effective month

2011-12 September 2011

2012-13 August 2012

2013-14 June 2013

For current Financial Year 2014-15

tariff petitions could be filed only on

6th

June 2014 as the finalization of the

MYT regulations by the regulator was

done only in the first quarter of the

current Financial Year. The tariff order

for the FY 2014-15 is expected soon

but the benefit may not be available

for more than six months.

• The regulatory assets during the last

four years have been building up

substantially for two reasons. One, the

regulator did not allow the proposed

ARR in the tariff petitions to avoid

tariff shocks. The other, benefit of

tariff order was not available for full

financial year.

• Independent energy audit by a central

agency in respect of the distribution

losses in the financial year 2013-14

was got conducted. As per findings of

the energy audit agency, the

distribution losses are at the level of

24.38 % in the FY 2013-14, much

much higher than the loss level of 16.3

% projected in the FRP. This factor

alone has made the present FRP

document unworkable.

• Due to increase in cost of coal and

freight etc., the average power

purchase cost of Rs. 3.79 per unit as

envisaged in FRP has actually stood as

Rs. 4.10 per unit (Prov.) in FY 2013-

14.

In view of above mentioned significant

deviations in the key parameters of the

present FRP document, the State Level

Monitoring Committee (SLMC) has directed

to update the FRP, subject to acceptance by

all concerned with consequential amendments

in obligations. Accordingly the updating work

is already in process in consultation with M/s

PWC, the Discoms’ consultant. This work is

likely to be completed within next 3-4 weeks.

The revision/updation of the existing FRP is

being carried out in anticipation of

consideration by GoI of the following

requests made by the Discoms:

• The cut-off date of the Scheme be

considered as 1.04.2014 in place of

01.04.2012.

• Moratorium on repayment of loans to

Banks/FIs outstanding as on 31st

March 2014 be kept upto March 2018

in place of March 2015;

• Full Operational Funding Requirement

to be provided by the Banks/FIs for

FY 2015-16, 2016-17 and 2017-18

also.

After the above revision/updation of the

existing FRP, Discoms expect their

turnaround in FY 2017-18 mainly due to

gradual reduction in AT&C losses from the

Page 54: A Joint Initiative of Government of India and Government of Rajasthan

54

level of 26.78% in FY 2013-14 to 15% in FY

2019-20. Such reduction in AT&C loss level

is expected to yield a saving of approximately

10,000 cr. during the above period, giving

much needed reprieve to the Discoms’

financials. Gradual tariff hike till the full

recovery of total cost of power supply from

revenue will augment the revenue stream of

the Discoms ultimately paving the way for

their scheduled turnaround. Operational

efficiency is also expected to take place up to

the expected levels.

7.1. LOSS REDUCTION, ENERGY

MANAGEMENT &, ENERGY

ACCOUNTING

The high AT&C loss levels in the Discoms

remains a concern and all efforts shall be

made to reduce the distribution losses to

improve the financial health of the Discoms.

To manage this effectively a concrete plan for

energy management, energy accounting and

loss reduction shall be put in place.

Energy accounting and energy management

have proved to be the biggest challenges in

most Indian states. Till date there is no

credible mechanism for identifying the true

levels of distribution losses in the states. The

available data has mostly lacked in credibility

and have been often restated to the extent that

it changes the loss picture completely. This is

true in Rajasthan as well where the

distribution losses have climbed up from less

than 20% in 2011-12 and 2012-13 to about

25% in 2013-14.

The Targets for Distribution losses for FY 15

onwards is given in table titled “DISCOM-

WISE DISTRIBUTION LOSS TRAJECTORY”.

The Targets for FY 15 & FY 16 are

aggressive and since only few months are left

in FY 15, it will require extraordinary efforts.

Efforts will be made to make up for any short

fall in a year in subsequent years.

REPORTED T&D LOSS TRENDS*

Year FY 08 FY 09 FY 10 FY11 FY 12 FY 13 FY 14

T&D Loss 35.5% 31.5% 31.0% 26.8% 24.3% 23.8% 27.5%

Transmission

Loss

6.0% 6.7% 6.6% 5.8% 5.8% 5.6% 4.1%

Distribution

Loss

31.4% 26.6% 26.1% 22.3% 19.6% 19.2% 24.4%

*The losses in transmission and distribution are not simple addition since the basis of measurement

is at different points in the network

DISCOM-WISE DISTRIBUTION LOSS TRAJECTORY

Year FY 15 FY 16 FY 17 FY18 FY 19 FY 20 FY 21

Jaipur Discom 24.50% 22.50% 20.50% 19.00% 17.50% 16.00% 15.00%

Ajmer Discom 19.60% 18.50% 17.50% 16.50% 15.50% 14.50% 14.25%

Jodhpur

Discom

21.14% 19.22% 17.30% 16.00% 15.00% 14.50% 14.25%

All Discoms 21.75% 20.00% 18.50% 17.25% 16.00% 15.00% 14.50%

Proposed Improvement trajectory (including Loss Reduction, Billing & Collection efficiencies)

subjected to adjustments in baseline data

Page 55: A Joint Initiative of Government of India and Government of Rajasthan

55

Page 56: A Joint Initiative of Government of India and Government of Rajasthan

56

Before embarking on the journey of loss

reduction, baseline AT&C losses should be

re-established for the each of the DISCOMs.

This will help in removing the ambiguity in

terms of loss level. Baseline AT&C losses can

be fixed by following the method as

prescribed for TPIA by PFC. Baseline AT&C

losses will also help in resolving other

important matter such as level of subsidy

requirement, category wise billing details etc.

The R-APDRP has already initiated a number

of measures in this regard including energy

audit and accounting with IT intervention.

These initiatives now need to be strengthened

and expanded in other areas. To meet this

objective, the backbone infrastructure for

improving measurement and visualization will

be created across the state and would include:

1. Implementation of Geographic

Information Systems (GIS) to map the

network assets and consumers

comprehensively and always updated

for operational purposes. Activities

that would be supported by the GIS

capabilities would include fault

detection and restoration, new service

connection issuance, connection –

disconnection, network expansion, etc.

To achieve its real potential accuracy

and regular updations of asset &

consumer mapping needs to be carried

out both for the existing and new set

of asset and consumer. It is also

important for the utility to identify and

regularly update the incremental

changes that is happening in the

network. Currently, in Rajasthan

DISCOM, GIS has not been

implemented successfully due to

various reasons.

2. As per RAPDRP plan, Government

has thought of installation of meter for

in all the distribution transformer &

feeder in the urban areas in the state.

As the scheme has not progressed

successfully, a comprehensive feeder

and distribution transformer metering

programme needs to be rolled out that

would cover all feeders and

transformers in the State. Measures in

this regard have been continuing in the

state over the past several years. This

will be made more comprehensive,

and will be backed by an expeditious

Page 57: A Joint Initiative of Government of India and Government of Rajasthan

57

restoration plan in case the meters turn

defective or damaged;

3. Metering standards and standard

installation guidelines needs to be

formulated before procurement &

installation of meter.

4. Consumer metering would be put in

place to ensure 100% metering of all

supplies including agriculture in the

next 3 years. This will be implemented

by the support of the State

Government and Government of India.

5. A properly devised pricing policy can

create incentives for the consumers to

shift load from peak hours to off peak

hours. Time of use (TOU) Time of

day(TOD) pricing is one of the options

of Demand Side Management in

which the consumer pays more for

energy used during peak hours and

less during off-peak hours. This

encourages consumers to shift load

during cheaper time periods of the day

which helps in reducing the peak

demand thereby flattening out the load

curve. Rajasthan Discoms may

approach Rajasthan Electricity

Regulatory Commission for

introduction of TOD pricing in their

next tariff notification.

6. Advanced Metering Infrastructure

(AMI) is a system which allows the

utilities to remotely measure, collect,

and analyze the consumption data. The

foundation blocks of AMI includes

smart meters, associated hardware,

software, data management,

programming and communications

devices that collect time-differentiated

energy usage from smart meters.

Smart Meters which constitute one of

the vital components of AMI are new

generation of meters which are

capable to simultaneously perform

basic functionality of core metering

and advance functionalities like

sending meter data via Head End

System (HES) using two-way remote

communication network, giving access

to utility to execute remote commands

like load connect/ disconnect, ability

to inform consumer about real time

pricing/ time of usage and performing

periodic meter maintenance via over

the air firmware upgrades. Data

collected from meters are processed

for various applications like billing,

consumption analysis, outage

management, address customer

grievances etc.Govt. of Rajasthan may

draw a roadmap for implementation of

AMI in a phased manner starting with

big cities and towns in the State.

7. Network analysis of the system to base

on power flows and network status to

ensure that the losses and line outages

can be predicted or identified in a

timely manner; As per RAPDRP

program Network analysis application

would have been supplied to

DISCOM. However one can assume

that without a credible GIS database

the same has not been utilized fully in

the DISCOM. Through change in

process management, DISCOMS have

to ensure that the entire new capital

investment program are routed

through network analysis module

rather than existing stopgap approach.

8. Loss measurement and verification

methodology implemented through

external agencies to be implemented

Page 58: A Joint Initiative of Government of India and Government of Rajasthan

58

9. To carry out independent feeder-wise

energy audits that would be carried out

by the independent energy audit

agency at the corporate office and

reporting directly to the management.

10. To arrest the high AT&C losses,

involvement of private participation

by way of PPP/franchising will be

promoted. Towns with loss levels of

more than 20% shall be identified for

PPP/ distribution franchisee, Urban

areas needing high reliability should

be an ideal choice for PPP model.

Rajasthan has already moved forward

in identifying Jaipur, Udaipur, Jodhpur

& Bikaner as target areas for PPP

model and should be then extended to

other urban towns like Ajmer, Kota,

Chittorgarh, Bhilwara, etc. Also, a

provision would be useful to be build

up in the RFP to include concentric

areas of the towns selected over period

of time. For their other areas different

models such as Input based urban

franchise / Collection based / rural

franchise with Self Help Group

(SHG), can be thought of

11. Aggressive vigilance checking shall be

intensified.

12. Incentive scheme would be introduced

for each circle, which is at all district

headquarters and headed by a

Superintending Engineer. Such

incentives could be distributed

amongst concerning Discoms officials,

police personnel, district officials etc.

For this purpose, external verification

through competent accredited certification

agencies shall be taken up. Such agencies

shall carry out an annual verification of the

energy accounting and audit facilities, the

energy measurements of the utilities and rate

them on various parameters to ensure that the

loss measurements and supply parameters for

the 24X7 supply are transparent and credible.

7.2. GOI INTERVENTION

GoI is being requested to approve the recast

FRP covering the following basic features

therein at the earliest to ensure the projected

turnaround in FY 2017-18:

a. The cut-off date as stipulated in Scheme

be extended from 1.4.2012 to 1.4.2014;

b. The moratorium period be extended by

Banks/FIs by 3 years- accordingly the

repayments would commence from April

2018 in place of April 2015;

C. Full Operational Funding Requirement be

provided by the Banks/FIs for further 3

years also i.e. in FY 2015-16, 2016-17 and

2017-18.

d. To provide capital reimbursement support

upfront against the TFM to ease out the

State Government financials due to

accepting the Scheme.

e. Banks/FIs be persuaded to reduce their

prevailing rate of interest on working

capital loans at least by 5 per cent,

facilitating the Discoms to use the savings

accrued on account of this less outgo of

interest to honour the scheduled

repayments.

The above request of Govt of Rajasthan

would be considered by Govt of India as per

its policies or otherwise Govt of Rajasthan

would make arrangements for funding from

other sources.

7.3. ACTION POINTS ( DISCOMS /

STATE GOVT)

Discoms

Page 59: A Joint Initiative of Government of India and Government of Rajasthan

59

i. Implementation of FRP including

compliances of the mandatory

conditions;

ii. Regular tariff filing and rolling over of

tariff orders ;

iii. Regular pass through of fuel cost

adjustment;

iv. Reduction in AT&C losses as per

projections

v. Timely preparation and finalization of

annual accounts

GoR

i. Timely release of subsidy to the

Discoms

ii. Timely adherence to FRP

implementation liabilities

7.4. MANAGING THE RISKS

Time-bound and successful implementation of

the 24X7 Power Supply Scheme is dependent

on the some key parameters that are critical to

the financial health of the distribution

segment. For providing 24x7 power supply to

all households in the state, financial

implications on utilities for procuring

additional energy and per unit implication on

tariff for additional energy has also been

carried out and the details are at Annex- X.

Based on the exercise, a sensitivity analysis

has been performed to understand the impact

of various factors on the financial health of the

utilities. The sensitivity of various factors is

shown as under:

Sensitivity Analysis

Sl. No. Measure Degree of Sensitivity

1 T&D Loss Reduction Trajectory Highly sensitive

2 Tariff changes Highly sensitive

(especially to initial years)

3 Power procurement optimization Highly sensitive

4 Extension of Interest Moratorium by

2 years

Low sensitivity

5 Reduction of interest rates Highly sensitive

6 Higher feeder improvement investments Low sensitivity

7 More energy efficient consumption Low sensitivity*

8 Lower Agriculture Consumption Highly sensitive

*This is because of lack of differentiation in AT&C loss and ABR in the domestic category. If these are

considered, then sensitivity would be significant and in reverse direction. The details of sensitivity analysis

are at Annex-XI

Page 60: A Joint Initiative of Government of India and Government of Rajasthan

60

The performance of the utilities is sensitive to

the risks, which must be handled consciously

and mitigated accordingly.

1. The burden of short term liabilities needs

to be addressed for the sector to turn

around for providing reliable 24X7 supply;

2. Investments needs to be efficiently and

rigorously planned and adequately

financed through cost efficient means.

Wherever possible, private financing

should be promoted.

3. Energy accounts and AT&C losses needs

to be monitored through a comprehensive

program;

4. Energy efficiency will be promoted at the

end use consumption levels

5. Power procurement and associated risks

(including fuel risks) needs to be managed

efficiently

6. Release of timely subsidy by the State

Government to the Discoms

7. Timely filing of tariff petitions by state

utilities to rationalize the tariff so as to

reduce the gap between ACS & ARR

The above measurers would require strong

implementation planning, project monitoring

and Information Technology (IT) backbone.

The progress against the FRP and the

measures taken to manage the risks of

repeated slippage against the FRP objectives

shall be monitored independently through the

institutional mechanism.

7.5. INVESTMENT PLANNING AND

MONITORING MECHANISM

The investments required for 24X7 power

supply have already been articulated in the

previous chapters. However it is important to

ensure that the investments is made on time as

per plans and to deliver the desired results.

For effective implementation, a Project

Monitoring Unit (PMU) is proposed to be

established by government of Rajasthan. The

role of the PMU shall be to ensure the

following:

• Develop, compile and update (or require

the same to be done) detailed project

plans for all capex related to 24X7

supply and related aspects (including

the renewable energy related

infrastructure and monitoring

investments);

• Monitor progress against the plans,

analyse and advise the utilities on

any delays and bottlenecks on

critical measures to promote 24X7

supply and also ensure broader

financial viability by tracking

measures on loss reduction,

investments, etc. and prepare

financial/physical progress of the

projects as per defined periodicity;

• Timely availability of information

about various projects, their

sources of the finance, the terms

and conditions that govern the

projects (including the externally

aided projects and those supported

by Government of India and

Government of Rajasthan).

• Identify the issues to where

intervention of GoI is required

and take up these issues with

concerned ministries under

intimation to MoP

• Arrange initial dialogue/interaction

with the external agencies. Support

negotiation arranged by the

concerned entity/department for

project assistance.

• Maintain data base records of

projects under its purview in a

structured manner and ensure

timely availability when required

• To organise the monthly/quarterly

review meetings chaired by Chief

Secretary/Energy Secretary &

Director, PMC.

Page 61: A Joint Initiative of Government of India and Government of Rajasthan

61

The PMU shall use state of the art IT tools to

ensure that the information on projects

tracked is always updated and available in the

manner required for decision making by

Government of Rajasthan and other

concerned entities. The PMU shall be

manned by an independent external agency

that shall be responsible for reviewing and

reporting progress on a monthly basis.

Page 62: A Joint Initiative of Government of India and Government of Rajasthan

62

8. OTHER INITIATIVES

8.1. COMMUNICATION

Successful implementation of 24X7 Power Supply Scheme requires clear communication

among all the stakeholders across the value chain, including the consumers. In order to avoid

potential roadblocks in implementation due to poor communication and flow of information, the

following table lists the primary responsibility of each stakeholder and the corresponding

method in which it will be carried out.

A centralized corporate communication team can be formed at headquarters of the DISCOM for

looking at activities of overall communication strategy.

The financial situation in Rajasthan makes it imperative to raise tariffs while other initiatives

including 24X7 supply are implemented. Such tariff increases would inevitably impact

consumers and meet with resistance. To address this, the utilities would clearly communicate

their plans on implementing the reliable 24X7 supply scheme along with the other reliability and

efficiency improvement measures that they are implementing. A high level of involvement of

the Government of Rajasthan will also be required.

Table: Proposed communication responsibilities

Communication Objective Responsibility Frequency

“ Power for all” - Roll Out Plan Energy Secretary Quarterly

Power Supply Position CMD Transco Daily

Energy Savings & Conservation CEO, State Energy Efficiency

Deptt Monthly

Planned Outages & Disruption CMD, Discom Daily

Real time feeder-wise Information CMD, Discom Daily

Status update on Deliverables Secretary, Energy Quarterly

Renewable Power CEO, State Renewable Energy

Deptt Quarterly

Generation- Projects, PLF & Fuel MD, State Genco Monthly

Transmission Projects – Physical Progress and

Achievements CMD, Transco Monthly

Distribution – Progress ,Achievements, Losses,

Consumer Initiatives etc.

CMD,

Discom Monthly

Page 63: A Joint Initiative of Government of India and Government of Rajasthan

62

8.2. INFORMATION TECHNOLOGY

(IT) INITIATIVES

The need to adopt IT in every sphere of utility

operation is pervasive. Power is a complex

product that must be consumed on a real time

basis. The overall value involved in the

process is very high. Even more importantly

it touches all citizens. Yet, the information

systems that drive the operations of the sector

are generally very basic and information

transparency and consistency is poor. While

sporadic efforts have been made in the past to

improve this, quantum changes are required to

increase IT adoption in all spheres of power

sector operation.

In Rajasthan, IT adoption on a massive scale

will be pursued in the following areas:

� At the corporate level, the operations need

to be integrated through implementation

of Enterprise Resource Planning Systems

(ERP). This would cover critical aspects

like Finance and Accounts, Asset

Management, Inventory Management,

Human Resource Management, Project

Management, Personal information

System (PIS). ERP will help in timely

capitalization of asset, deriving better

business value of investment etc.

� At the commercial operations level there

is a need to comprehensively implement

Customer Management Systems (CMS)

for undertaking customer related

processes including billing and

collections, customer complaint

management, new connection provision

etc.;

� Centralized Information & Monitoring

System for operational , enforcement &

litigation, vigilance activities and analysis

� Power management would require the

institution of technically capable

controlling facilities equipped with tools

like SCADA and Distribution

Management Systems (DMS) that allow

for adequate visualization of the networks

and response capabilities. Technologies

for sub-station automation, GIS, SCADA,

DMS, OMS, etc., shall be adopted. For the

urban areas SCADA is quite useful for

improving reliability and reduction of

network downtime.

� Regional Distribution Control Centres

(RDCC) within the State are proposed to

be established. These will initially cater to

the principal load centres, but would

thereafter be expanded to all load centres

of the state. This will be a key initiative,

not only for effectively managing 24X7

supply, but also thereafter for other

functions like forecasting.

� Renewable Energy Management centres

shall be established and equipped with

adequate capabilities through financing

availed from KfW and ADB.

� Smart Cities will be implemented to inter-

alia, reduce the intensity of electricity

consumption in the cities while

simultaneously improving supply quality,

reliability and integration of renewable

energy resources

� Power procurement optimization tools

will be implemented to reduce the power

procurement costs and improve supply

reliability. This shall be achieved through

the institution of technically robust

forecasting, scheduling and dispatch (Unit

Commitment) and settlement tools. The

tools shall be used to ensure that the

control room operators have the ability to

take real time decisions to ensure cost

reduction.

� Project monitoring tools shall be

incorporated in the PMU to ensure that

progress on the investments in the state

are monitored rigorously and bottlenecks

identified.

� Standards of service specified under

Section 57 of the EA 2003 shall be

monitored. The utilities shall use IT tools

to gather the information with regards to

service standards with minimal manual

Page 64: A Joint Initiative of Government of India and Government of Rajasthan

63

intervention to ensure transparency and

credibility.

The above need to be implemented urgently,

and also need to be integrated with each other

to ensure that the systems are inter-operable

(i.e., they can talk to each other). For this the

utilities shall evolve a detailed IT plan to

implement the above in a well-coordinated

manner.

8.3. INSTITUTIONAL ARRANGEMENT

A strong monitoring framework is essential to

ensure the success of the “Power for all”

scheme. The following structure is being

proposed to undertake regular monitoring of

the progress of all initiatives being under-

taken in this scheme.

� Government of India (GOI) Level Committee: It is proposed that this

committee will review the overall

progress of the scheme on a

quarterly basis and provide

necessary support to ensure a

coordinated response from the

Central Govt. - where necessary.

The committee may be constituted

with the following members – PFC,

REC, CEA, SECI, EESL, Ministry

of Power Ministry of Coal, and

MNRE.

� State Government Level Committee: It is proposed that a

State level committee headed by the

Chief Secretary will be formed to

review the progress of the scheme

on a quarterly basis. This committee

will monitor the progress of the

works undertaken as part of the

scheme and issue directions to

enable faster execution. This

committee will be constituted with

the following Principal Secretaries/

Secretaries of the Power, Finance,

Urban Development, Agriculture

and other relevant departments along

with the CMD/Chairman/MD of

RVUNL, RVPNL and the Discoms

and RRECL.

� Department Level Committee: It is

proposed that the Department level

committee headed by the Energy

Secretary will be formed and shall

undertake steps required to ensure

the projects are progressing as per

the action plan. This 9999committee

will undertake progress reviews on a

monthly basis. The committee will

be constituted with the following

members –Secretary (Energy), CMD

RVPNL, MD of Discoms and

RRECL.

� District Level Committee – It is

proposed to constitute a district level

committee headed by the District

Collector to take action that is

necessary to ensure the projects are

completed in a timely manner and

address any issues pertaining to land

or other relevant approvals. The

committee will be constituted with

the following members – District

Collector, S.E RVPNL, S.E Discom

and RRECL representatives.

� Project Monitoring Unit (PMU) –

A project monitoring unit shall be

set to up for monitoring the progress

of the works being undertaken under

this scheme. The PMU will operate

under the Secretary, Energy and

shall be operated by an external

independent agency. The PMU shall

be responsible for undertaking

coordination, preparing the action

plans and monitoring progress of all

works under the “Power for all”

scheme. The PMU would also help

facilitate in tracking the action steps

and providing feedback to the

various committee that are proposed

to be set up under the scheme.

Government of India shall provide

grants for the PMU operations.

The committees that are being proposed

above are required to be set up at the earliest

to kick start the whole scheme. It is

important that the committees keep meeting

on a regular basis as per the frequency/

timelines mentioned above – to ensure that

Page 65: A Joint Initiative of Government of India and Government of Rajasthan

64

the objectives set out under the “Power for

all” scheme are achieved.

8.4. CAPACITY BUILDING

With the increase of IT in the Generation,

Transmission & Distribution system and to

meet the expectations of 24 X 7 power supply

for the consumers in the state, it is important

to focus on capacity building of the

employees for enhancement of technical

know-how for latest technological

developments and to increase the consumer

satisfaction. The capacity building may also

include consumer grievance system,

awareness regarding importance of working

with safety, outage management system,

demand side management etc. It is also

imperative to state that for serving the

consumers in a different way change of

mindset of the employees would be required.

It is critical that Change Management

initiatives are roll out and institutionalize

through out the DISCOM for achieving better

results. The details of the present employee in

the Rajasthan Discoms is as under:

Table 10.1: Employee base of Discoms

Jaipur Discom Ajmer Discom Jodhpur Discom Total

Regular

1 Technical

a Officers 432 364 317 1113

b Junior engineers 739 723 764 2226

c subordinates 15268 12571 12041 39880

Total-1 16439 13658 13122 43219

2 Non-Technical

a Officers 88 76 67 231

b Ministerial staff 2077 2095 1720 5892

c Fourth class 785 582 414 1781

Total -2 2950 2753 2201 7904

Total (1 + 2) 19389 16411 15323 51123

In view of the importance of the training on

new technologies, there is a requirement for

development and implementation of Human

Resource training programme so as to realize

the dream of 24 X 7 power supply system in

the state in its true sense.

There is already a provision for Demand

Side Management (DMS) trainings under

various programmes of Bureau of energy

Efficiency (BEE) and the same should be

implemented to achieve the goal of 24 X 7

power for goal. The training for the class C &

D employees are also being provided under

RAPDRP Part C scheme.

A state level officers training institute may be

required to be opened in the state to fulfil the

ongoing training requirement for employees

of Discoms. A provision of approximately Rs.

25 Crores would be required for the same.

Also at each district headquarters, training

schools needs to be opened for training of

subordinate technical staff for which

approximately Rs. 50 Crores will be required

by considering Rs. 1.5 Crores for each district

headquarter. Following training programmes

are proposed to be implemented for Discoms:

1. Two Weeks trainings for technical

staff including officers & engineers

once in every two years.

2. One week training for non-technical

officers every two years.

3. One week training for subordinate

technical staff at each district

headquarters every year.

Page 66: A Joint Initiative of Government of India and Government of Rajasthan

65

9. YEAR WSIE ROLL OUT PLAN

Year wise deliverables are given in the table below-

Table : Summary of deliverables

Deliverables

Power for all - Roll out

Plan

Units FY

2014-15

FY

2015-16

FY

2016-17

FY

2017-18

FY

2018-19

Total

Generation

State Sector U/C MW 850 0 2140 0 660 3650

Future State Projects MW 2920 Subject to

coal linkage

Central Sector MW 145.65 0 264 214 746.5 1370.15

Private sector MW 500 500

Transmission

Inter State

Substation Nos - - - - - 0

Lines ckt kM 1310 600 290 380 - 2580

Green energy Corridor

Substation - - - 3 2 5

Lines - - - 1680 1970 3650

Intra-state

Substation Nos 29 24 12 21 20 106

Lines ckt KM 2,506 2,611 883 796 898 14,448

Green energy Corridor

Substation Nos. 2 2 9 9 12 34

Lines ckt KM 309 536 320 594 1,030 2,789

Distribution

AT&C Losses % 21.75% 20.00% 18.50% 17.25% 16.00% 15.00%

33/11kV S/s – As per

state Plan Nos. 220 200 200 200 200 1020

33/11kV S/s – Additional

required for 24x7 supply Nos. 0 66 66 66 66 264

Separate Three phase

system for 24x7 supply

to 2000-4000 population

villages

Nos 0 800 800 800 938 3338

No of households to be

electrified

Lakhs

Nos. 4.5 6 6.5 6.5 6.5 30

Renewable Energy

Solar Capacity Addition MW 500 1000 1500 2000 2500 7500

Wind Power Addition MW 500 500 500 620 620 2740

Solar rooftop grid-

connected MW 3.5 10 10 10 10 43.5

Solar off-grid MW /

Nos

2 MW

(10000)

5 MW

(25000)

5 MW

(25000)

5 MW

(25000)

5 MW

(25000)

22 MW

110000

Solar Agl pump-sets Nos. 5000 5000 5000 5000 5000 25000

Page 67: A Joint Initiative of Government of India and Government of Rajasthan

66

Energy Efficiency

LED Distribution -

Households

Lakhs

Nos. 1800000 9000000 9000000 9000000 9000000 37800000

Ag Pump sets

replacement No 50000 250000 300000 300000 300000 12 Lakhs

Street lighting -

Municipalities %age 12.5 12.5 25 25 25 100

Consumer care centres districts 5 7 8 10 3

Page 68: A Joint Initiative of Government of India and Government of Rajasthan

67

10. SECTOR WISE INVESTMENT PLAN AND FUND REQUIREMENT

(Rs in Crores)

FY 14-15 FY 15-16 FY 16-17 FY 17-18 FY 18-19 Total Remarks

Generation

(RVUN)

Under Construction

(3650 MW) 4717.34 5100.00 5024.26 837.18 113.41

15792.19

(Out of total cost

of Rs 28993.51

Crores)

Funds have been

tied up on 80:20

ration

Future projects

(2920MW) 500.00 5000.00 5000.00 5000.00 3480.00 18980.00

Total ( Generation)

(6570 MW) 5217.34 10100 10024.26 5837.18 3593.41

34772.19

( Out of total req of

47973.51 Crores)

Transmission

Inter

state

(PGCIL)

ISTS 888 628 321 85 0

1922

(Expenditure of RS

1694 Crores till 31

March 2014)

PGCIL

Green energy

corridor 456 1178 2166 2875 1925 8,600

PGCIL/Any other

agency selected

by GOI

Inter state

total 1344 1806 2487 2960 1925 12216 PGCIL

Intra

state

System

strengthening 1133.55 957.6 481.5 912 1345 4829.65 State Plan

Green energy

corridor 293.5 970 1461 1102 855 4681.5

Support required

under NCEF

Others 383 452 438 372 373 2018 State plan

Intra state

total 1810.05 2379.6 2380.5 2386 2573 11529.15

Distribution

State plan

Base capex 728 615 638 641 641 3263 State plan

Rural electrification

including release of new

agriculture connections

785 822 734 908.74 954.17 4203.91 State Plan

Total (state Plan) 1513.00 1437.00 1372.00 1549.74 1595.17 7466.91

Schemes for which GoI assistance is required

RGGVY 12th plan (5

schemes under sanction,

one is under preparation

)

0 63 250 250 250 813

Schemes have

been submitted to

REC for sanction

Electrification of un

electrified / partially

electrified Dhanis /

Habitations having

population less than 100

0 450 450 450 489 1839

GoR may identify

the H/H which

can be grid

connected or req.

off grid solutions

in next 3 months

and a detailed

plan may be

prepared in this

regard

RAPDRP- Part- A Addl.

Funding for IT

enablement under

RAPDRP – Part A (For

0 117 117 0 0 234

Page 69: A Joint Initiative of Government of India and Government of Rajasthan

68

towns with population

less than 30,000)

RAPDRP- Part- B Addl.

Funding under R-

APDRP Part-B due to

increase in ordered

Prices

(JVVNL 293 Cr. &

Jd.VVNL:160 Cr.)

300 153 0 0 0 453

Investment under

RAPDRP part B for

enabling SCADA in

Jaipur city

90 57.23 0 0 0 147.23

RAPDRP total 390 327.23 117 0 0 834.23 May be covered

under GOI new

schemes which

are being

finalised by MOP

as per rules of

the schemes /

policies

Feeder improvement

program

300 800 400 0 0 1,500

Substation improvement

program

300 100 0 0 0 400

Additional 33 kV sub-

station for 24x7 supply

in rural areas

0 111 111 111 111 444

Separate 3 Phase system

for villages of population

2000 to 4000

0 241 241 241 284 1007

Technology

improvements

20 50 40 0 0 110

DDG (Solar) 20 80 0 0 0 100

Capacity building 5 25 25 20 0 75

Total GOI Assistance

required 1035 2247.23 1634 1072 1134 7122.23

GoI Schemes already Sanctioned and under implementation

GoI Schemes

already

sanctioned &

under

implementation

RGGVY 12th plan

(sanctioned 28 schemes)

150 450 450 403.19 0 1453.19 Sanctioned

RAPDRP- Part- A for IT

enablement under

RAPDRP – Part A (For

towns with population

less than 30,000)

185 0 0 0 0 185 Sanctioned

Rs 315.95 Cr

from above Rs

130 Cr disbursed

RAPDRP Part -A

SCADA projects for 5

big Towns

50 61.83 0 0 0 111.83 Sanctioned

Rs. 157.11 Cr.

and Rs. 45.28

Cr. disbursed RAPDRP- Part-B – 81

towns

500 492 992 Sanctioned Rs

1540 Cr, from

above Rs. 548 cr.

Disbursed from

GoI/Counter

Funding

Total of sanctioned

GoI Schemes

885 1003.83 450 403.19 0 2742.02

Renewable

energy

Wind 3000 3000 3000 3720 3720 16440 IPP

Solar 3500 7000 10500 14000 17500 52500 IPP

(including

support

required under

NCEF for Rs

2500 Crores for

VGF funding of

Page 70: A Joint Initiative of Government of India and Government of Rajasthan

69

1000 MW @ 2.5

Crore/ MW)

Grid connected solar

rooftops

25 70 70 70 70 305 Support required

under NCEF

Solar off-grid systems 37 92.5 92.5 92.5 92.5 407

Solar pump systems 360 360 360 360 360 1800

Renewable total 6922 10522.5 14022.5 18242.5 21742.5 71452

Energy Efficiency 504.8 2097.2 2504.8 2504.8 2562.4 10174 EESL/BEE

Page 71: A Joint Initiative of Government of India and Government of Rajasthan

70

ANNEXURES

Annexure-I

Circle-wise AT&C loss trajectory

FY 15 FY 16 FY 17 FY 18 FY 19 FY 20 FY 21 FY 22%

Distrib

ution

Loss

%

Realisati

on

ATC ATC ATC ATC ATC ATC ATC ATC ATC

1 2 3 4 5 6 7 8 9 10 1 1 12 1 3

1 Alwar 28.82 97.40 30.67 25.00 22.00 21.00 19.75 18.50 17.00 16.00 15.00

2 Bharatpur 41.12 91.14 46.33 35.00 30.00 26.00 22.00 20.00 19.00 18.00 17.50

3 Dholpur 49.23 90.59 54.01 40.00 35.00 30.00 25.00 21.00 19.00 18.00 17.00

4 Dausa 40.72 96.61 42.73 33.00 29.00 25.00 22.00 20.00 18.00 17.00 16.00

5 Karauli 44.00 88.85 50.25 35.00 30.00 26.00 22.00 20.00 19.00 18.00 17.00

6 JCC 9.83 99.74 10.06 9.70 9.60 9.50 9.25 9.00 8.75 8.50 8.25

7 JPDC 29.89 97.21 31.84 25.00 22.00 20.00 19.00 18.00 16.75 15.25 14.50

8Sawaimadh

opur31.24 93.85 35.46 24.85 22.00 20.00 18.00 16.67 15.68 16.00 15.00

9 Tonk 26.33 97.76 27.98 23.00 21.00 19.00 18.00 17.00 16.00 15.50 15.00

10 Jhalawar 41.09 83.60 50.76 35.00 30.00 26.00 23.00 20.00 18.00 17.00 16.00

11 Baran 31.27 81.42 44.04 28.00 24.00 31.00 20.00 19.00 18.00 17.00 16.00

12 Kota 24.74 93.34 29.75 19.00 17.86 18.00 17.00 16.00 15.50 15.00 14.50

13 Bundi 26.48 98.05 27.92 23.00 21.00 20.00 19.00 18.00 17.00 16.00 15.00

27.85 96.07 30.69 24.50 22.50 20.50 19.00 17.50 16.00 15.00 14.39

1 Ajmer City 17.1 98.9 18.0 16.00 15.00 14.00 13.00 12.00 11.00 10.00 9.00

2 Ajmer Distt 10.8 99.4 11.4 11.00 10.90 10.80 10.70 10.60 10.40 10.30 10.00

3 Bhilwara 14.29 99.51 14.71 14.00 13.00 12.50 12.00 11.75 11.50 11.25 11.00

4 Nagaur 30.34 97.84 31.85 26.50 23.50 21.50 20.50 18.50 16.00 17.00 16.00

5 Banswara 24.80 96.90 27.13 23.00 21.00 20.00 19.00 18.00 17.00 16.00 15.00

6 Dungarpur 16.74 98.13 18.29 16.75 16.25 16.00 15.90 15.65 15.35 15.25 15.00

7 Chitrgrh 23.13 98.05 24.63 22.00 21.00 20.00 19.00 18.00 17.00 16.50 16.00

8 Prtapgrh 16.01 95.65 19.66 18.00 17.75 17.50 17.25 17.00 16.90 16.50 16.00

9 Rajsamnd 13.94 99.80 14.11 13.00 12.50 12.00 11.50 11.00 10.50 10.75 10.00

10 Udaipur 17.80 99.47 18.23 17.00 16.00 15.50 15.00 14.75 14.50 14.25 14.00

11 Jhunjhunu 24.87 97.64 26.65 23.00 21.00 20.00 19.00 18.00 17.00 16.00 15.00

12 Sikar 21.92 98.43 23.14 21.00 20.00 19.00 17.75 17.00 16.75 16.50 16.00

Total 20.69 98.63 21.77 19.60 18.50 17.50 16.50 15.50 14.50 14.25 13.51

1 Barmer 19.1 98.5 20.2 19.00 18.50 18.25 18.00 17.50 17.00 16.50 16.00

2 Jaiselmer 20.5 97.4 22.6 19.50 19.00 18.50 18.00 17.50 17.00 16.50 16.00

3Jodhpur

City9.78 94.94 14.34 9.50 9.10 9.20 9.20 9.10 9.00 8.90 8.80

4Jodhpur

Distt29.71 97.17 31.70 26.00 24.00 22.00 21.00 20.00 19.00 18.00 16.00

5 Jalore 14.14 98.21 15.67 14.00 13.50 13.00 12.50 12.00 11.50 11.00 10.50

6 Pali 9.4 97.3 11.8 10.50 10.00 9.90 9.75 9.50 9.35 9.25 9.00

7 Sirohi 11.0 93.6 16.8 13.50 12.90 12.75 11.50 11.25 10.90 10.80 10.00

8 Bikaner 27.44 93.58 32.10 24.00 22.00 21.00 20.00 19.00 18.00 17.00 16.00

9 Churu 29.83 95.98 32.66 25.00 22.00 21.00 20.00 19.00 18.00 17.00 16.00

10 HNGr 14.69 96.99 17.26 15.50 14.25 13.50 13.25 12.90 12.50 12.25 12.00

11 SNGr 16.22 98.67 17.33 15.00 14.75 14.25 13.90 13.30 12.90 12.50 12.00

Total 23.43 96.35 26.22 21.14 19.22 17.30 16.00 15.00 14.50 14.25 13.84

G.Total 24.38 96.91 26.71 21.75 20.00 18.50 17.25 16.00 15.00 14.50 13.96

Total

Ajmer Discom

Jodhpur Discom

S

N

o

Name of

Circle /

Discom

FY 2013-14

Page 72: A Joint Initiative of Government of India and Government of Rajasthan

71

Annexure-II

List of Discom wise District wise town getting 24 Hrs. Supply

JAIPUR DISCOM

Sr. No. Distt. / MTs Sr. No. Distt. / MTs

1 DHQ Alwar 33 KOTPUTLI

2 Behror 34 VIRAT NAGAR

3 Khairthal 35 SHAHPURA

4 Tijara 36 DHQ-JHALAWAR

5 Kherli 37 J.PATAN

6 Rajgarh 38 AKLERA

7 DHQ-BTP 39 B.MANDI

8 NADBAI 40 SUNEL

9 Bayana 41 DHQ-BARAN

10 Weir 42 ANTA

11 Bhusawar 43 MANGROL

12 Deeg 44 CHHABRA

13 Kaman 45 DHQ- BUNDI

14 Nagar 46 K.PATAN

15 Kumher 47 KAPREN

16 DHQ-Dholpur 48 LAKHERI

17 Bari 49 INDERGARG

18 Rajakhera 50 NAINWA

19 DHQ-Dausa 51 DHQ- KOTA

20 Lalsot 52 KAITHOON

21 Bandikui 53 SANGOD

22 Hindaun 54 RMG

23 Todabhim 55 DHQ- SWM

24 DHQ-Karauli 56 GGC

25 DHQ-Jaipur 57 DHQ- Tonk

26 CHOMU 58 Malpura

27 BAGRU 59 Uniara

28 CHAKSU 60 Newai

29 PHULERA 61 Deoli

30 SAMBHAR 62 Toda

31 RENWAL

32 JOBNER

Page 73: A Joint Initiative of Government of India and Government of Rajasthan

72

AJMER DISCOM

Sr. No. Distt. / MTs Sr. No. Distt. / MTs

1 DHQ- Ajmer 36 DHQ- Pratapgarh

2 Pushkar 37 Choti Sadri

3 Beawar 38 DHQ- Rajasmand

4 Kishangarh 39 Kankroli

5 Nasirabad 40 Nathdwara

6 Kekri 41 Amet

7 Sarwar 42 Deogarh

8 Bijainagar 43 DHQ- Udaipur

9 DHQ- Bhilwara 44 Kanore

10 Gangapur 45 Bhinder

11 Asind 46 Fatehnagar

12 Mandalgarh 47 Salumber

13 Bijoliya 48 DHQ- Jhunjunu

14 Shahapura 49 Pilani + Vidha Vihar

15 Jahazpur 50 Surajgarh

16 Gulabpura 51 Bagar

17 Mertacity 52 Chirawa

18 DHQ- Nagaur 53 Mandawa

19 Mundwa 54 Bissau

20 Kuchera 55 Mukandgarh

21 Kuchaman 56 Nawalgarh

22 Nawa City 57 Udaipurwati

23 Deedwana 58 Khetri

24 Parbatsar 59 DHQ- Sikar

25 Makrana 60 Laxmangarh

26 DHQ- Banswara 61 Fatehpur

27 Kusalgarh 62 Ramgarh Shekhawati

28 DHQ- Dungarpur 63 Losal

29 Sagwara 64 Srimadhopur

30 DHQ- Chittorgarh 65 Reengus

31 Begun 66 Neemkathana

32 Rawat Bhata 67 Khandela

33 Kapasan

34 Nimbahera

35 Badi Sadri

Page 74: A Joint Initiative of Government of India and Government of Rajasthan

73

JODHPUR DISCOM

Sr. No. Distt. / MTs Sr. No. Distt. / MTs

1 DHQ-Jodhpur 30 DHQ- Sri Ganganagar

2 Phalodi 31 Sadulshahar

3 Bilara 32 Kesrisinghpur

4 Pipar City 33 Raisinghnagar

5 DHQ-Pali 34 Gajsinghpur

6 Sojat City 35 Padampur

7 Jaitaran 36 Sri Karanpur

8 Falna 37 Suratgarh

9 Bali 38 Sri Bijaynagar

10 Sadari 39 Anoopgarh

11 Sumerpur 40 DHQ- Hanumangarh Jn.

12 Takhagarh 41 Hanumangarh Town

13 Rani 42 Pilibanga

14 DHQ- Sirohi 43 Bhadra

15 Sheoganj 44 Nohar

16 Pindwara 45 Rawatsar

17 Abu Road 46 Sangaria

18 MT.Abu 47 DHQ- Churu

19 DHQ-Jalore 48 Ratannagar

20 Bhinmal 49 Rajgarh

21 Sanchore 50 Taranagar

22 DHQ- Barmer 51 Ratangarh

23 Balotra 52 Rajeldesar

24 DHQ- Jaisalmer 53 Sardarsahar

25 Pokran 54 Sujangarh

26 DHQ- Bikaner 55 Bidasar

27 Nokha 56 Chhapar

28 Deshnoke+GSR 57 Ladanu

29 Dungargarh Town

Page 75: A Joint Initiative of Government of India and Government of Rajasthan

74

Annexure-III

Status of households electrification in the No. of Villages

S.No. Name of Discom Households Electrification in the No. of villages Total

0% 0%> to

<10%

=>10%to

<20%

=>20% to

<30%

30% and

More

1 2 3 4 5 6 7 8

1 Jaipur 887 480 609 779 11677 14432

2 Ajmer 1127 1051 776 776 11235 14965

3 Jodhpur 1678 1172 1074 1067 8818 13809

Sector as whole 3692 2703 2459 2622 31730 43206

Page 76: A Joint Initiative of Government of India and Government of Rajasthan

75

Annexure IV :

The Intra State Abstract of Transmission Investment Plan upto 2018-19 is as under:

Page 77: A Joint Initiative of Government of India and Government of Rajasthan

76

Annexure-V

Consumer category breakup (as on 31 March 2014)

Domestic

rural

Domestic

urban

Agriculture Industrial Commercial Others Total

Number of

Consumers

58,20,819 30,26,944 12,01,073 2,89,615 10,98,651 47,823 1,14,84,925

Connected

Load

(In MW)

3,729 3586 10,547 3,299 2606 433 24,200

Energy

consumption

(In MU)

3578 5432 17,839 11,824 3,226 786 42,686

Per unit Tariff

(Rs/unit)

4.32 5.65 3.37 5.94 7.28 7.04 4.81

Billing

(Rs. in Crores)

1547 3071 6,010 7,024 2,348 553 20,553

Collection (Rs.

in Crores)

1439 2967 5,087 6,902 2,326 493 20,014

Page 78: A Joint Initiative of Government of India and Government of Rajasthan

77

Annexure VI

Key energy input and related figures

S.No. 2010-11 2011-12 2012-13 2013-14

A Energy Availability at

Generator Point

MU 47,154.78 50,068.92 55,342.53 59,156.17

B Energy sold through

exchange

MU 103.56 15.16 31.05 276.63

C

(=A-B)

Net Energy Availability

for the state

MU 47,051.22 50,053.76 55,311.48 58,879.54

D Transmission Loss MU

%

2713.79 (5.76) 2907.03

(5.80)

3111.84

(5.62)

2432.67

(4.13)

E

(=C-D)

Net Energy Availability

at Discom Periphery

MU 44,337.43 47,146.73 52,199.64 56,446.87

F Sales MU 34,448.92 37,903.78 42,160.22 42,686.35

G

(=E-F)

Distribution Loss MU 9,888.51 9,242.95 10,039.42 13,760.52

H % Distribution loss % 22.30 19.60 19.23 24.38

I Collection efficiency % 99.45 99.43 98.80 96.88

J AT&C loss of Discoms % 22.72 20.06 20.20 26.74

Page 79: A Joint Initiative of Government of India and Government of Rajasthan

78

Annex-VII

MNRE Schemes/options for electrification of remote households

OPTION I:

• System proposed:

� 100 Wp Solar system will be provided to each household

� This system would include:

� 5 Nos. of D.C. operated LED lights (2 Luminaires of 5 watts each and 3 Luminaires of 8 watts

each) for 4 hours operation each day.

� One D. C. Fan of 12 watts for 10 hours operation each day.

� One D.C. B&W TV 12 watts for 4 hours operation each day can be attached or any other

appliance can be powered

� One Mobile Charger

• Load Estimation:

S. No. Load Description Nos. Unit Load

(W)

[DC]

Total

Load

(W)

Hours of use per

day

Energy Consumption

(Wh)/day

1 D.C. operated LED

Lights

5 8WX3

5WX2

34 4 hours 136

2 D.C. Fan 1 12Wx1 12 10 hours 120

3. D.C. B&W TV 1 12 12 4 hours 48

4. Mobile Charger 1 5 5 3 hours 15

Total 319

Say 0.3units/day

• System requirement to meet consumer demand for above consumption profiles i.e. 0.3 units per

day is estimated with autonomy for two(2) non sunshine day is as under:

S. No. System Consumption Profile (with Two day Autonomy)

1 Solar PV Module 100 Wp

2 Battery Storage (Tubular type) 12V, 75 AH

• Estimated Project Cost: Broad estimated cost for system for typical household is: Rs. 25,000/-

OPTION II:

• SYSTEM PROPOSED:

a. 200 Wp Solar system will be provided to each household

b. This system would include:

� 5 Nos. of D.C. operated LED lights (2 Luminaires of 5 watts each and 3 Luminaires of 8

watts each) for 6 hours operation each day.

� One D. C. Fan of 24watts (or 2 fans of 12 watts each) for 12 hours operation each day.

Page 80: A Joint Initiative of Government of India and Government of Rajasthan

79

� One D.C. colour TV 30 watts for 4 hours operation each day can be attached or any other

ppliance cane be powered.

� One Mobile Charger

• Load Estimation:

S. No. Load Description Nos. Unit Load

(W)

[DC]

Total

Load

(W)

Hours of use per

day

Energy Consumption

(Wh)/day

1 D.C. operated LED

Lights

5 8WX3

5WX2

34 6 hours 204

2 D.C. Fan* 1 24W X1

or

12Wx2

24 12 hours 288

3. D.C. Color TV 1 30 30 4 hours 120

4. Mobile Charger 1 5 5 3 hours 15

Total 627

Say 0.6 units/day

• System requirement to meet consumer demand for above consumption profiles i.e. 0.6 units per

day is estimated with autonomy for two (2) non sunshine day is as under:

S. No. System Consumption Profile (with Two day Autonomy)

1 Solar PV Module 200 Wp

2 Battery Storage (Tubular type) 12V, 150 AH

• Estimated Project Cost: Broad estimated cost for system for typical household is: Rs. 50,000/-

OPTION III

� TARGET GROUP : Village with a cluster of 15 “House Holds”, which cannot be

connected to the Grid

� Proposed Solution : Through Solar PV Mini Grid And Central Control Room

• Load Estimation:

S. No. Load Description Nos. Unit Load

(W)

[AC]

Total

Load

(W)

Hours of use per

day

Energy Consumption

(Wh /day)

1 Power for A.C.

LED Lights

5 8WX3

5WX2

34 6hours 204

2 Power for A.C. Fan

and or Power for

A.C. Loads like

Color TV, Set top

box / PC

and Mobile Charger

etc.

1 50W

50 6hours 300

Total 504

say 0.5 unit/day

Page 81: A Joint Initiative of Government of India and Government of Rajasthan

80

i. Proposed Load for each house hold: each house hold = 500 Whrs.

ii. Total Load for 15 households = 7500 Whrs.

iii. Solar System Specs. for the above Load:

iv. Solar PV Panel = 2.5 KWp

v. Battery = 48V, 600AH

vi. Off Grid PCU (Inverter and Charge controller) =48 V , 2.5 KW

vii. A central control room for batteries and PCU

viii. Other balance of System Components

ix. Budgeted cost of the System is Rs. 7.5 Lakhs

OPTION IV:

• TARGET GROUP : Villages with 50 “House Holds”, which cannot be connected to the Grid

• Proposed Solution : Through Solar PV Mini Grid And Central Control Room

• Load Estimation:

S. No. Load Description Nos. Unit Load

(W)

[AC]

Total

Load

(W)

Hours of use per

day

Energy Consumption

(Wh /day)

1 Power for A.C.

LED Lights

5 8WX3

5WX2

34 6hours 204

2 Power for A.C. Fan

and or Power for

A.C. Loads like

Color TV, Set top

box / PC

and Mobile Charger

etc.

1 50W

50 10hours 500

Total 704

say 0.7 unit/day

(i) Proposed Load for each house hold: each house hold =700 Whrs.

(ii) Total Load for 50 households = 35000 Whrs.

(iii) Solar System Specs. for the above Load:

(iv) Solar PV Panel =12.5 KWp

(v) Battery = 240V, 600AH

(vi) Off Grid PCU (Inverter and Charge controller) =240 V , 12.5 KW

(vii) A central control room for batteries and PCU

(viii) Other balance of System Components

Page 82: A Joint Initiative of Government of India and Government of Rajasthan

81

(ix) Budgeted cost of the System is Rs. 30 Lakh

PROPOSED SCHEME:

• MNRE may provide subsidy at the rate of 40%.through NCEF

• A network of local technicians will have to be created for service and repair.

• Some local agencies / NGO’s will have to be involved to ensure upkeep and proper use through

awareness and training of users.

• The beneficiary may be asked to keep some fixed amount as “Reserves” like for battery

replacement in future

Page 83: A Joint Initiative of Government of India and Government of Rajasthan

82

Annexure VIII

Details of Distribution Investment Planned: Schemes covered under State Plan.

Sl.

No.

Particulars Unit FY 14-15 FY 15-16 FY 16-17 FY 17-18 FY 18-19 Total

A Sub Transmission &

Distribution programme.

SS Addition

No. 220 200 200 200 200 1020

PTR Addition in SS

No. 30 30 30 30 30 150

Feeder Addition

Km 11910 9070 9900 10000 10000 50880

DTR Unit Addition

No. 14000 13000 13000 13000 13000 66000

SS Addition

Rs. Cr 369.06 335.46 335.46 335.46 335.46 1711

PTR Addition in SS

Rs. Cr 14.91 14.91 14.91 14.91 14.91 75

Feeder Addition

Rs. Cr 328.716 250.332 273.24 276 276 1404

DTR Unit Addition Rs. Cr 15.4 14.3 14.3 14.3 14.3 73

Total Base Capex

requirement

Rs. Cr 728 615 638 641 641 3263

B Rural Electrification

including release of Ag.

Connection

New Consumers Capex Rs. Cr 748.00 785.40 699.77 865.90 909.20 4133.17

Civil Infrastructure

development cost

Rs. Cr 27.00 28.35 25.23 31.26 32.82 149.19

Miscellaneous Capex Rs. Cr 10.00 8.25 9.00 11.58 12.16 55.26

Total –B Rs. Cr 785.00 822.00 734.00 908.74 954.17 4203.91

Total I= A+B 1513.00 1437.00 1372.00 1549.74 1595.17 7466.91

Page 84: A Joint Initiative of Government of India and Government of Rajasthan

83

Annex-IX

Details of Investment Planned for which assistance is required from Central Govt (in Cr.

Rs.)

FY14-15 FY 15-16 FY 16-17 FY 17-18 FY 18-19 Total Remarks

RAPDRP RAPDRP- Part- A Addl.

Funding for IT

enablement under

RAPDRP – Part A (For

towns with population

less than 30,000)

117 117 0 0 0 234 May be

covered

under GOI

new

schemes

which are

being

finalised by

MOP.

RAPDRP- Part- B Addl.

Funding under R-APDRP

Part-B due to increase in

ordered Prices

(JVVNL 293 Cr. &

Jd.VVNL:160 Cr.)

300 153 0 0 0 453 Revised cost

estimates

may be

submitted

to PFC for

approval of

Steering

Commtt.

Investment under

RAPDRP part B for

enabling SCADA in Jaipur

city

90 57.23 0 0 0 147.23

RAPDRP total 507 327.23 0 0 0 834.23

Under

RGGVY

RGGVY 12th

plan (5

schemes under sanction,

one is under preparation

)

0 63 250 250 250 813 Submitted

to REC for

sanction

under

RGGVY

Investment for

electrification of un

electrified / partially

electrified Dhanis /

Habitations having

population less than 100

0 450 450 450 489 1839 May be

covered

under under

various

schemes of

MNRE.

24x7 Supply Feeder improvement

program

300 800 400 0 0 1,500 May be

covered

under GOI

new

schemes

which are

being

finalised by

MOP.

Substation improvement

program

300 100 0 0 0 400

Additional 33 kV sub-

station for 24x7 supply in

rural areas

0 111 111 111 111 444

Separate 3 Phase system

for villages of population

2000 to 4000

0 241 241 241 284 1007

Technology

improvements

20 50 40 0 0 110

DDG (Solar) 20 80 0 0 0 100

Capacity building 5 25 25 20 0 75

Total GOI Assistance

required 1152 2247.23 1517 1072 1134 7122.23

Page 85: A Joint Initiative of Government of India and Government of Rajasthan

84

Annexure X

IMPLICATION ON TARIFF of 24x7 PFA

Item Unit 2014-15 2015-16 2016-17 2017-18 2018-19

1 Additional Energy available

for billing

MUs 4,768 10,178 14,475 22,574 29,630

2 Procurement of Additional

Energy for supply

MUs 6,422 13,392 18,677 28,665 37,038

3 Cost of Power Purchase @ Rs.

4.50/kWh

Rs.

Crores

2,890 6,026 8,405 12,899 16,667

4 Annual T&D Infrastructure

Cost (Rs. Crores)

Rs.

Crores

- - 1,244 2,022 2,373

5 Total cost of additional energy Rs.

Crores 2,890 6,026 9,649 14,921 19,040

6 Average Revenue on Subsidy

received basis

Rs./

kWh

4.84 4.84 4.84 4.84 4.84

7 Average Revenue received

from sale of additional energy

Rs.

Crores 2,308 4,926 7,006 10,926 14,341

8 Additional Cost Rs.

Crores

582 1,100 2,643 3,996 4,699

9 Total Energy Sale (Existing +

Additional Energy)

MUs 47,454 52,864 58,789 65,261 72,316

10 Impact on Tariff Rs./

kWh

0.12 0.21 0.45 0.61 0.65

Page 86: A Joint Initiative of Government of India and Government of Rajasthan

85

Annexure XI

Sensitivity Analysis and Results

The table below lists the parameters for which sensitivity analysis has been conducted.

Sensitivity Analysis

S no. Sensitivity Analysis

1 Faster AT&C Loss reduction

2 Slower AT&C Loss reduction

3 Lower tariff increases

4 Higher tariff increases (doubled) in first two years

5 Power purchase costs optimized (rates reduced by average of 5%)

6 Interest pay-outs on past STL capitalized for 2 additional years - till FY 17, instead of FY 15

7 Interest rate reduction of 2 percent for STL for FY 15 and FY 16

8 Higher Rural supply/associated investment costs

9 Lower/more efficient consumption in households

10 Lower Agricultural Sales Growth

i. Sensitivity to AT&C Loss Reduction

High and Low reduction in AT&C losses, relative to the base case reduction, has been considered in

this analysis

Base Case and Sensitivity Scenario (AT & C losses)

Scenario Assumptions 2014-15 2015-16 2016-17 2017-18 2018-19

Base Case Loss Trajectory 21.75% 20.00% 18.50% 17.25% 16.00%

Sensitivity: High Reduction Case Loss Trajectory

(2.34% / year) to reach ~ 15 % by FY 2018-19

24.40% 22.06% 19.72% 17.38% 15.04%

Sensitivity: Low Reduction Case Loss Trajectory (1 % / Year) 25.74%

24.74% 23.74% 22.74% 21.74%

Base Case and Sensitivity Scenario (Percentage Change Per Year)

Scenario Assumptions 2014-15 2015-16 2016-17 2017-18 2018-19

Base Case Loss Trajectory 5.0%

1.8% 1.5% 1.3% 1.3%

Sensitivity: High Reduction Case Loss

Trajectory (2.34% / year) to reach ~ 15 % by FY 2018-19

2.34% 2.34% 2.34% 2.34% 2.34%

Sensitivity: Low Reduction Case Loss Trajectory (1 % / Year) 1.00% 1.00% 1.00% 1.00% 1.00%

Page 87: A Joint Initiative of Government of India and Government of Rajasthan

86

Result:

The table below shows the impact on Financial Gap under the three scenarios listed above. Clearly,

higher AT&C loss reduction has a significant impact on the Financial Gap. Without the past liabilities

impact, the state can return to profitability by 2016-17 even with low AT&C loss reduction.

Impact of AT&C Loss Reduction - Rs./Kwh

With Past Liability Impact 2013-

14

2014-

15

2015-

16

2016

-17

2017

-18

2018-

19

Base Case

(2.02)

(1.58)

(1.06)

(0.62)

(0.45)

(0.29)

Sensitivity: High Reduction Case

Loss Trajectory

(2.02)

(1.76)

(1.22)

(0.74)

(0.51)

(0.28)

Sensitivity: Low Reduction Case

Loss Trajectory

(2.02)

(1.86)

(1.42)

(1.06)

(0.95)

(0.85)

Without Past Liability Impact

Base Case

(1.33)

(0.86)

(0.00)

0.65

0.75

0.84

Sensitivity: High Reduction Case

Loss Trajectory

(1.33) (1.03) (0.14) 0.58 0.74 0.90

Sensitivity: Low Reduction Case

Loss Trajectory

(1.33)

(1.12)

(0.32)

0.31

0.39

0.47

ii. Sensitivities to Tariff Increase

Low tariff increase (4% per year) and higher increase in first 3 years (16% per year) has been

assumed to analyze the sensitivity of financial Gap to extent of tariff revisions.

Base Case and Sensitivity Scenario (Percentage)

Scenario Assumptions 2014-15 2015-16 2016-17 2017-18 2018-19

Average Tariff: Base Case

(as per GoR inputs)

10.0% 18.0% 10.0% 8.0% 4.0%

Sensitivity: Low Tariff Increase

(~ 4% / year)

4.38% 4.38% 4.31% 4.29% 4.18%

Sensitivity: Higher Tariff Increase (first 3 years) -

16% / year for year 1,2 and 3, followed by ~ 8%/year

16.00% 16.00% 16.00% 8.30% 8.19%

Base Case and Sensitivity Scenario (Rs. / Unit)

Scenario Assumptions 2014-15 2015-16 2016-17 2017-18 2018-19

Average Tariff: Base Case (as per GoR inputs) 5.33 6.29 6.92 7.47 7.77

Sensitivity: Low Tariff Increase (~ 4%/year) 5.06 5.28 5.51 5.74 5.98

Sensitivity: Higher Tariff Increase (first 3 years) -

16%/year for year 1,2 and 3, followed by 8%/year

5.62 6.52 7.56 8.19 8.86

Page 88: A Joint Initiative of Government of India and Government of Rajasthan

87

Result:

The table below shows the impact on Financial Gap in the tariff hike scenarios listed above. As seen

in the table below, a high tariff increase in the first 3 years leads to considerable impact on Financial

Gap. Including past liabilities, the state is expected to eliminate its losses by 2016-17.

Impact of Tariff Increase - Rs./Kwh

With Past Liability Impact 2013-14 2014-15 2015-16 2016-17 2017-18 2018-19

Base Case (2.02) (1.58) (1.06) (0.62) (0.45) (0.29)

Sensitivity: Low Tariff Increase (2.02) (1.87) (2.17) (2.29) (2.64) (2.76)

Sensitivity: Higher Tariff Increase (first 3

years)

(2.02) (1.27) (0.77) 0.14 0.46 1.11

Without Past Liability Impact

Base Case (1.33) (0.86) (0.00) 0.65 0.75 0.84

Sensitivity: Low Tariff Increase (1.33) (1.13) (1.02) (0.77) (0.99) (0.96)

Sensitivity: Higher Tariff Increase (first 3

years)

(1.33) (0.56) 0.23 1.30 1.48 1.94

iii. Sensitivity to Cost of Power Procurement

A 5% average reduction in power purchase costs over the base case has been assumed.

Base Case and Sensitivity Scenario

Scenario Assumptions 2014-15 2015-16 2016-17 2017-18 2018-19

Base Case Power Purchase Cost (Rs. Cr.) 22341 25511 28472 34960 40773

Sensitivity: 5% Lower Power Purchase Cost (Rs. Cr.) 21113 24108 26906 33037 38530

Result:

The table below shows the impact on Financial Gap. Clearly, the lowering of procurement costs,

which make up close to 70% of the total costs of Discoms, has a significant impact on the existing

Financial Gap levels.

Impact of Power Purchase Cost Reduction - Rs./Kwh

With Past Liability Impact 2013-14 2014-15 2015-16 2016-17 2017-18 2018-19

Base Case (2.02) (1.58) (1.06) (0.62) (0.45) (0.29)

Sensitivity: Lower PP Cost (2.02) (1.30) (0.74) (0.27) (0.04) 0.17

Without Past Liability Impact

Base Case (1.33) (0.86) (0.00) 0.65 0.75 0.84

Sensitivity: Lower PP Cost (1.33) (0.60) 0.26 0.92 1.05 1.15

Page 89: A Joint Initiative of Government of India and Government of Rajasthan

88

iv. Sensitivity to Interest Payments

To analyse the sensitivity to interest payment, interest on past STL is assumed to be capitalized for

additional 2 years, beyond FY15. Also, another case in which Interest on Loans for first two years

(FY 15 and FY 16) has been assumed to be reduced to 10% has been considered.

Result:

The table below shows the impact on Financial Gap.

Impact of Additional Interest Capitalization/Reduction - Rs. /Kwh

With Past Liability Impact 2013-14 2014-15 2015-16 2016-17 2017-18 2018-19

Base Case (2.02) (1.58) (1.06) (0.62) (0.45) (0.29)

Sensitivity: Additional 2 year capitalization of

interest on STL (2.02) (1.58) (0.78) (0.10) (0.20) (0.28)

Sensitivity: STL Interest Reduced to 10% (FY

15 to 17) (2.02) (1.45) (0.86) (0.36) (0.39) (0.23)

Without Past Liability Impact

Base Case (1.33) (0.86) (0.00) 0.65 0.75 0.84

Sensitivity: Additional 2 year capitalization of

interest on STL (1.33) (0.86) (0.00) 0.65 0.75 0.84

Sensitivity: STL Interest Reduced to 10% (FY

15 to 17) (1.33) (0.86) (0.00) 0.65 0.75 0.84

v. Sensitivity to Investment Costs

To analyze the sensitivity to investment costs, Higher Investment Costs (Rural Electrification and

Feeder Improvement Costs increased by 50%) have been assumed.

Base Case and Sensitivity Scenario

Scenario Assumptions 2014-15 2015-16 2016-17 2017-18 2018-19

Base Case RE & Feeder Segregation Capex 2650 950 - - -

Sensitivity: High Capex 2650 1700 750

Result:

The table below shows the impact on Financial Gap. Considering that other parameters improve as

per the base case, Higher Capex has a negligible impact on the Financial Gap.

Page 90: A Joint Initiative of Government of India and Government of Rajasthan

89

Impact of Higher Investment Costs - Rs./Kwh

With Past Liability Impact 2013-14 2014-15 2015-16 2016-17 2017-18 2018-19

Base Case (2.02) (1.58) (1.06) (0.62) (0.45) (0.29)

Sensitivity: High Capex (2.50) (1.89) (1.23) (0.78) (0.61) (0.41)

Without Past Liability Impact

Base Case (1.33) (0.86) (0.00) 0.65 0.75 0.84

Sensitivity: High Capex (1.79) (0.92) (0.13) 0.48 0.62 0.71

vi. Sensitivity to Consumption

For more energy efficient consumption, Urban and rural household consumption is assumed to reduce

by 10%, 2016-17 onwards.

Base Case and Sensitivity Scenario

Scenario Assumptions 2014-15 2015-16 2016-17 2017-18 2018-19

Base Case Urban and Rural Consumption - kwh per HH 5.5 & 2 6.1 & 2.3 6.8 & 2.5 7.4 &

2.75

8 & 3

Sensitivity: 10% Lower Consumption from FY 18 5.5 & 2 6.1 & 2.3 6.1 & 2.3 6.6 & 2.5 7.2 &

2.7

Result:

The table below shows the impact on Financial Gap. The CoS increases because lesser units are sold

for the same infrastructure/O&M costs. However, if the higher AT&C losses and lower ABR for

small customers are taken into account, Energy Efficiency would increase gains and reduce subsidy

burden.

Impact of Efficient Energy Consumption - - Rs./Kwh

With Past Liability Impact 2013-14 2014-15 2015-16 2016-17 2017-18 2018-19

Base Case (2.02) (1.58) (1.06) (0.62) (0.45) (0.29)

Sensitivity: Energy Efficient

Consumption (2.02) (1.58) (1.06) (0.69) (0.55) (0.40)

Without Past Liability Impact

Base Case (1.33) (0.86) (0.00) 0.65 0.75 0.84

Sensitivity: Energy Efficient

Consumption (1.33) (0.86) (0.00) 0.62 0.70 0.78

Page 91: A Joint Initiative of Government of India and Government of Rajasthan

90

vii. Sensitivity to Agriculture Sales Growth

Sensitivity has been analyzed by reducing the growth rate of agricultural sales in the future years.

Base Case and Sensitivity Scenario

Scenario Assumptions 2014-15 2015-16 2016-17 2017-18 2018-19

Base Case: 9.5% p.a 9.50% 9.50% 9.50% 9.50% 9.50%

Sensitivity: 4% p.a 4% 4% 4% 4% 4%

Result:

The table below shows the impact on Financial Gap. Lower agricultural growth rate has a significant

impact on the financial gap.

Impact of Agri. Growth Rate

With Past Liability Impact 2013-14 2014-15 2015-16 2016-17 2017-18 2018-19

Base Case (2.02) (1.58) (1.06) (0.62) (0.45) (0.29)

Sensitivity: Low Growth (2.02) (1.62) (1.17) (0.80) (0.73) (0.66)

Without Past Liability Impact

Base Case (1.33) (0.86) (0.00) 0.65 0.75 0.84

Sensitivity: Low Growth (1.33) (0.89) (0.07) 0.55 0.59 0.63

Page 92: A Joint Initiative of Government of India and Government of Rajasthan

91

Abbreviations

AVVNL Ajmer Vidyut Vitran Nigam Limited

ALDC Area Load Dispatch Center

APTEL Appellate Tribunal for Electricity

AT&C Aggregate Technical and Commercial

BPL Below Poverty Line

BU Billion Units

CAGR Compound Annual Growth Rate

CEA Central Electricity Authority

ckt kms circuit kilometers

CMS Customer Management Systems

Cr. Crores

DC Direct Current

Discom Power Distribution Company

DMS Distribution Management Systems

EA Electricity Act of 2003

EESL Energy Efficient Street Lighting

EHV Extra High Voltage

ERP Enterprise Resource Planning Systems

ESCO Energy Services Companies

FIP Feeder Improvement Programme

FIs Financial Institutions

FRP Financial Restructuring Plan

FY Financial Year

Genco Power Generation Company

GIS Geographic Information Systems

GoI Government of India

GoR Government of Rajasthan

InSTS Intra state transmission system

IPP Independent Power Producer

ISTS Interstate transmission system

IT Information Technology

JVVNL Jaipur Vidyut Vitran Nigam Limited

JdVVNL Jodhpur Vidyut Vitran Nigam Limited

kV Kilovolts

LED Light-Emitting Diode

M&V Measurement and Verification

MD Managing Director

MNRE Ministry of New and Renewable Energy

MoC Ministry of Coal

MoEF Ministry of Environment and Forests

MoP Ministry of Power

Page 93: A Joint Initiative of Government of India and Government of Rajasthan

92

Mtpa Metric tonnes per annum

MU Million Units

MVA Megavolt ampere

MW Megawatt

NCEF National Clean Energy Fund

NLDC National Load Despatch Centre

PFC Power Finance Corporation

PGCIL Power Grid Corporation of India

PMC Project Management Cell

PMU Project Monitoring Unit

POC Pont of Connection

PPA Power Purchase Agreement

RAPDRP Restructured Accelerated Power Development and Reforms Programme

RDCC Regional Distribution Control Centre

RE Renewable

REC Rural Electrification Corporation

REMC Renewable Energy Management Center

RERC Rajasthan Electricity Regulatory Commission

RGGVY Rajiv Gandhi Grameen Vidyutikaran Yojana

RLDC Regional Load Despatch Center

RRECL Rajasthan Renewable Energy Corporation Limited

RPPC Rajasthan Power Procurement Cell

RRVPNL Rajasthan Rajya Vidyut Prasaran Nigam Limited

SCADA Supervisory Control and Data Acquisition Systems

SECI Solar Energy Corporation of India

SIP Sub-station Improvement Programme

SLDC State Load Despatch Centre

STU State Transmission Utility

T&D Transmission and Distribution

TBCB tariff based competitive bidding

TPS Thermal Power Station

Transco Power Transmission Company

ULB Urban Local Body

VGF Viability gap funding