a case study of ppp procurement of railway infrastructure

27
A case study of PPP procurement of railway infrastructure including ERTMS Level 2 High-speed line Madrid-Castilla la Mancha-Comunidad Valencia-Murcia: Section Albacete-Alicante DG MOVE and INEA In collaboration with Adif, Alstom and the European Investment Bank 28 May 2014

Upload: others

Post on 25-Dec-2021

4 views

Category:

Documents


0 download

TRANSCRIPT

A case study of PPP procurement of railway

infrastructure including ERTMS Level 2

High-speed line Madrid-Castilla la Mancha-ComunidadValencia-Murcia: Section Albacete-Alicante

DG MOVE and INEAIn collaboration with Adif, Alstom and the European Investment Bank28 May 2014

Table of contents

SLIDE 2 Objectives of the case studySLIDE 3 The Global Project: Albacete-Alicante HSLSLIDE 4 The PPP Project profileSLIDE 5 Project main counterpartiesSLIDE 6 Project financingSLIDE 7 Project budgetSLIDE 8 Project descriptionSLIDE 10 PPP tender preparationSLIDE 11 PPP tender processSLIDE 12 Project TEN-T grant supportSLIDE 13 ERTMS deployment action timelineSLIDE 14 Risk sharing analysisSLIDE 17 Construction and certificationSLIDE 18 Main lessonsSLIDE 19 ReplicabilitySLIDE 20 ANNEX I ERTMS

Main contributors

Objectives Outline the process underlying the decision to

proceed with the PPP procurement model Identify the role of Private-Public Partnership

(PPP) procurement and TEN-T support in thecase of an ERTMS deployment project in Spain

Investigate risk identification, risk transfer,contract management and certificationprocedure

Discuss the possibility of replicating theapproach in other projects and regions

Motivation

The case study explores best practice in the PPP procurement of ERTMS

Objectives of the case study

The case study was developed on the initiativeof the European Commission in closecooperation with the main stakeholdersincluding Spanish publicly-owned railwayinfrastructure management authority, Adif;Alstom, the key private sector technologyprovider; and the EIB as structurer andlender.

The case study is developed on the basis of anERTMS deployment project on a Spanish high-speed railway line

Spain is a recognised leader in ERTMS The project received grant support from the

TEN-T programme under ERTMS deploymentpriority for the certification process

Both public authority and private partner findthe cooperation under the PPP contractbeneficial

Approach

1. Present the current status of the project andinvestigate its preparation process from thepoint of view of risk-sharing agreements

2. Provide a general overview of ERTMSincluding technical and organisational issues,as well as summarize current status of itsdevelopment in Spain

3. Suggest the ways to transfer best practices toother ERTMS projects based on the gatheredevidence and real life experience

Adaptation to high speed of the 65 km routeand existing facilities between Albacete andAlmansa

Construction of a new high-speed track-bedfor 100 km between Almansa and Alicante

Installation of S&T facilities in the 165 km ofHSL (High Speed Line) double track betweenAlbacete and Alicante, including railwaystations and passing tracks

*Main elements of S&T facilities

Main high-speed line project components

Albacete-Alicante line is one of the most complex routes in Spain

The Global Project: Albacete-Alicante HSL

Source: ADIF

High-speed network development

Infrastructure Stations Superstructure Substructure Signalling and Telecommunications,

main focus of PPP contract* Passenger operators

Freight operators

Capacity allocation and traffic management

Works performed in Albacete-Alicante

Madrid - Castile-La Mancha - Valencia

region - Murcia regionhigh-speed line (HSL)

ERTMS

Signalling system (ETCS)

Rail telecommunication system (GSM-R)

Complementary safety (detection) systems

Integration into the Operational Commandcentre

Interface between infrastructure S&T systemsand the on board rolling stock subsystems(ETCS and GSM-R radio equipment)

Albacete-Alicante165 km section

Project timeline

Project highlights

PPP project addressed the S&T requirements of Albacete-Alicante HSL

The PPP Project profile

Source: ADIF, ALSTOM

Project objective Design and installation of traffic control

systems, fixed and mobile telecoms andsecurity systems in the HSL Albacete-Alicante(165 kms)

Design and installation of S&T systems ofexisting conventional line La Encina-Alicante(69 kms) affected by incompatibility with HSLelectrification system

Maintenance (routine & life cycle) of HSLinstallations only, not those for conventional

The tender was awarded in December 2011 toan SPV consisting of four industrial partners

The duration of the Design, Build, Finance,and Maintain (DBFM) contract is 22 years. TheEIB loan is 17 years, commensurate with theeconomic life of the asset.

Total contract value €271.1 mln ERTMS deployment with total budget €22.2

mln was co-funded through a TEN-T grant

Design 4 months

Execution of works 16 months

System validation and verification of the layout4 months

Construction period 2 years

Maintenance period20 years

A state-owned company that reports to theMinistry of Public Works and Transport

Responsible for:• the administration of railway infrastructure

(tracks, stations, freight terminals, etc)• managing rail traffic• distributing capacity to rail operators• the collection of fees for infrastructure,

station and freight terminal use

ALSTOM is the leader of the winning consortiaalso consisting of EMTE, Isolux Ingenieria, CAF

A global leader in the field of powergeneration, power transmission and railinfrastructure

Leader in the deployment of ERTMS in Europe

Offers a broad spectrum of products andservices from rolling stock to signalling,infrastructure and complete turnkey systems

Other stakeholders

ALSTOM is the leader of the winning consortia – Albali Señalización

Project main counterparties

Source: ADIF, ALSTOM

European Investment Bank: The EIB is the European Union's bank. It provided technical support in structuring the PPP as well as being the main lender to the project.

Centre of research and studies of the Ministry of development: laboratory in Spain performing testing of interoperability between the different components of the ERTMS

European Railway Agency: Agency for the EU that regulates the policy development and the standards and specifications of the European rail system

Notified body: Certifies the Declaration of conformity and suitability of the system

Investment highlights

Project financing

Total Project Costs

44%

16%

12%

10%

8%8%3%

CDC Infra

Fond ICO

ALSTOM

ADIF

EMTE

ISOLUX

CAF

Equity holders

Total: €13.2 mln

Equity of the SPV was predefined at 10% of the total construction phase CAPEX in order to increase guaranteesunder the construction phase. Equity requirements reduced to 5% of CAPEX during maintenance phase

Adif’s 10% equity stake, requirement for bids, made it eligible for representation on the board of directors andpromotes alignment of interests with SPV while maintaining independent decision-making and governance

Financial investors (CDC Infra & Fond ICO) allowed to join industrial equity partners either before BAFO or aftercontract signature, balances equity contribution while keeping industrial competence tied to long term equityperformance

Fond ICO provided a safety buffer in the form of €13 mln subordinated loan

The EIB offered same terms to all bidders, helped ADIF to attract competitive bids. The EIB provided €77.6 mlnloan based on a trilateral agreement with the Spanish Ministry of Public Works and ADIF

Payment mechanism comprised of deferred investment payment and maintenance components. The deferredinvestment payment is not subject to deductions, high quality cash flow drove efficient cost of funds from EIB.

77.6

53.0

13.213.0

EIB loan

Proportion of CAPEX fundedby ADIF during construction

Equity

Subordinated loan from FondICO

Total: € 156.8 mln

ADIF represents the public sector and also has a minority stake in the SPV

Project budget

Contract value in € mlnFinancial modelling aspects

The feasibility study covered the whole lifecycle of the project

A feasibility study was done in order to definetendering amounts according to technicalrequirements

Apart from CAPEX and OPEX budgets, the studiesalso covered availability payment mechanism,discount rates, equity structure, duration of theproject

S&T facilities account for a small share ofconstruction phase costs (around 8%) but becomethe most important cost factor in the maintenancephase (around 30%)

2 years40% of CAPEX

Revenue breakdown of the SPV

60% of CAPEX15 years

20 yearsDebt interest service, O&M costs, replacement, taxes, equity payback and IRR

Tendered Awarded Change

CAPEX* 213.4 132.6 -38%

Construction phase (40%) 85.4 53.0 -38%

Deferred payments (60%) 128.0 79.6 -38%

OPEX 165.3 105.4 -36%

Financial costs 48.5 33.2 -32%Total contract value** 427.2 271.1 -37%

Note: *Capex figures do not include Design and Supervision, Technical Contingencies and SPV costs.**Total contract value includes ERTMS budget. Tendered ERTMS budget was €31.7 mln, while awarded amount was € 22.2 mln

PPP project preparation

Main activities

Project description

Early involvement of EIB facilitated provision of technical assistance, includingdrafting of tender documentation with external legal assistance and review oftechnical specifications. Availability of EIB financing was incorporated into tenderdocuments, creating better transfer of financial value

The objective of the PPP contract was to integrate detailed design, construction andmaintenance phases in order to minimise integration risk between the phases

In March 2010, procurement of legal and financial consultant (Deloitte) signalledfinal documentation preparation phase. The final PPP contract covered design,construction, financing and maintenance of S&T facilities (DBFM)

PPP procurement and resulting project finance structure facilitated access to bankfinancing and reduced the reliance on solely state and corporate resources

The private partner could make independent decisions on the allocation of theproject budget between construction and maintenance phases. Considering the highmaintenance costs of the S&T components, using a life-cycle approach helps toreduce overall costs.

Tender procedures

5 groups prequalified based on 30% financial and 70% technical criteria

The first delivery of economic and technical proposals was followed by a negotiatedprocedure. All consortia had access to EIB financing for financial proposals.

The contract was awarded to a consortia led by ALSTOM Transport based onsubmitted BAFO, assigning equal weight to financial and technical characteristics

Detailed design and 'greenfield' construction of only ERTMS Level 2 led to savingsduring both the construction and maintenance phases

Focus on signalisation attracted technology specialists able to mitigate performancerisks , drove competitive bids without civil construction contingencies

The main interface risks were related to the interface between ERTMS from differentsuppliers in Albacete and managing the transition from ERTMS Level 0, 1, 2 areas(in other sections) to the ERTMS Level 2 area

Main activitiesProject description

Funding/Financing

Construction

Certification and inter-operability

Full responsibility for the certification process lies with the private partner

ADIF through their safety services, approve the safety dossiers and apply to SpanishNSA for the operation authorisation

After the approval tests, the reliability period checks interoperability using trainsequipped with ALSTOM and TALGO-Bombardier technologies

Initial industrial partners participating in the equity of the SPV were joined prior tothe financial close by two public investment funds – Fond ICO and CDC Infra

Fond ICO provided a subordinated debt facility as a contingency buffer

The early involvement of EIB allowed the cost advantage of EIB lending to betransferred to the public sector; EIB long term debt proved to be crucial for thefinancial close

EIB was not exposed to performance risk on deferred CAPEX payments which droveefficient pricing of EIB loan made available to consortia

TEN-T grant of €4.44 mln (50% co-funding of eligible ERTMS costs), representing20% of the total ERTMS investment and 3% of the project's CAPEX.

Public sector considerations

PPP tender preparation

Key dates

27 August 2010Announcement of PPP procurement

5 February 2011Request for proposals (RFP)

15 June 2011Tender delivery

11 October 2011Best and Final Offer (BAFO)

5 December 2011Contract award

The role of advisors

Analysis of previous PPP experience

Risk identification

Drafting of legal clauses

Definition of a financial model

Preparation of a user guide

Two execution strategies were analyzed:1) Public procurement: monthly payments

during the construction phase, mid-termmaintenance period

2) PPP model with long term maintenance

A feasibility study defined tendering amountsaccording to technical requirements

NPV estimated using 5% discount rate

Chose one contract to avoid interface risks

Technology-based PPP kept focus onmaintenance rather than civil construction risk

Coordination of civil and S&T works important

Expected benefits of PPP procurement

Pathfinder project for public sector and EIB

Cost reduction from project re-design andprivate sector involvement

Construction transitions maintenance phasewith low interoperability risk and lower cost

Deferred CAPEX over 15 years

PPP procurement preparation and execution process took two years

25 May 2012Financial Close

Tender procedure took nine months

Private sector considerations

PPP tender process

Procurement phase

5 Feb 2011 - 31 Mar 2011Prequalification:

Legal, administrative, technical and financial28 Apr 2011 – 7/8 Sep

2011Bid & Negotiation Phase:

Negotiated procedure

7/8 Sep 2011 – 11 Oct 2011End Phase:

Invitation and delivery of BAFO

Five consortia bid for the project

Alstom Transport, EMTE, Isolux Ingenieria,CAF

Ansaldo, Inabensa, Telvent

Thales, Cobra, Dimetronic

Siemens, FCC, Indra

Bombardier, EyM instalaciones, Guinovart

The Spanish Minister of public worksannouncement in March 2010 enabled legaland financial consultants to finalisedocumentation prepared in collaboration withthe financial community and transport sector

Pre-qualification evaluated financial capacity(30%) and technical capacity (70%)

Negotiated procedure with 5 groups based oneconomic and technical proposals

The contract was awarded based on BAFOusing 50/50% technical and financial criteria

The combination of construction and long termmaintenance in one contract optimised theallocation of CAPEX and OPEX. Private partnerexpected benefits in costs and to optimisebidding strategy as an alternative to frequenttendering of short term maintenance contracts

The PPP model shifted financing fromcorporate to project finance schemes, lessburden on corporate financial resources,access to attractive EIB loan, ability to bring infinancial investors (CDC Infra and Fond ICO)

TEN-T grant action objective

Equipping 165 km of double-track railway lineAlicante-Albacete with the ETCS level 2, whichwill comply with the baseline version 2.3.0d

TEN-T grant supported the funding of ETCSand certification

TEN-T grant support

The grant covered ERTMS deployment – an important element of the S&T

Project TEN-T grant support

Source: ADIF

Project design and ERTMS L2 real deployment First phase: presentation of a detail project design by the supplier and approval

by ADIF, in accordance with requirements on functionality, interoperability andoperational rules of ERTMS L2

Second phase: installation of all the field elements, software development anddata programming

Subactivity 1

Subactivity 2

Tests, certification, approval and place in service ETCS elements are tested both in lab and on-track to verify the correct

integration of ERTMS L2 with signalling systems (interlockings) andcommunications GSM-R

Subactivity 3

Preparation of awarding documentation and tendering of the contract The procurement performed by the means of a process of public private

partnership (PPP)

Total ERTMS budget €22.20 mil

Total eligible cost €8.88 mil

Total EU contribution (50%) €4.44 mil

Beneficiary ADIF

Overview of the action

1 Contract award

2 Start of project design

3 ADIF Project design official approval

4 CE Conformity Certification

5 Start of ERTMS L2 track deployment

6 50% ERTMS track deployment completion

7 ETCS L2 software completion

8 Completion of GSM-R Network

9 Completion of ERTMS track deployment

10 GSM-R Quality of Service Tests

11 Completion of tests and reports to the ERA

12 EC Conformity declaration of track subsystem

13 Request submission for NSA authorisation

14 NSA authorisation granted

15 Putting into commercial service in L2

TEN-T Action 2011-ES-60002-P

ERTMS deployment action timeline

Feb 2011 Nov 2011 Aug 2012 May 2013 Jun 2014

EU (TEN-T) grant milestones Timeline

Dec 2011

Dec 2011

Mar 2012

Feb 2012

Apr 2012

Dec 2012

Apr 2013

May 2013

Mar 2013

Mar 2013

Nov 2013

Dec 2013

Apr 2014

May 2014

May 2014

Land acquisition

Force majeure

Operator incidents

Early debt termination

Inflation

Geological

Changes in regulations

Project amendments

Financial closing

Refinancing&insurance

Design&Construction

Maintenance costs

Availability

Level of service

Interest rates

Technology

Public partner risks

ADIF was responsible for the expropriationand acquisition of the land needed for theproject execution. The private partner could nothave done it more efficiently. Impact on costs,and construction term was assumed by ADIF.An important risk in civil works, less so for thisaspect of the HSL global project.

The contract will be re-negotiated in such casesof force majeure as:

fires caused by atmospheric electricity natural catastrophic effects wartime damage, looting serious disturbances of public order,

strikes in the SPE, ADIF or RENFE ADIF will be in charge of the recovery of

compensating damages from rail operator inthe case of incidents

In case of early contract finalization ADIFcan choose between taking over of the currentdebt or make an early repayment. ADIFrecognized that debt will not be affected bydeduction or compensation for early finalisation

Risk sharing analysis

Public Private

Risk sharing matrix

The PPP's scope included design, construction, financing and maintenance

Land acquisition

Force majeure

Operator incidents

Early debt termination

Inflation

Geological

Changes in regulations

Project amendments

Financial closing

Refinancing&insurance

Design&Construction

Maintenance costs

Availability

Level of service

Interest rates

Technology

Shared risks

Geological and archaeological risks is theresponsibility of the SPV, a minor risk in thiscase. A more significant risk in the civil workswhich could lead to a contract modification

Cost due to general regulatory changes ispaid by the SPV up to 15% of the awardingcost. The SPV is entitled to a compensation forthe costs generated by specific regulatorychanges

ADIF can authorize public interest projectmodifications up 10% of the awardedcontract. Amounts over 10% may be a causefor contract termination

SPV was responsible for starting the contractexecution in 6 months after the awarding dateregardless of the financial close. ADIF hadthe right to prolong the period and to sharerisk conditions of financial close in exceptionalcases

ADIF shares the risks of insurance costsincreasing by more than 100%

In the case of debt refinancing ADIF isentitled to share 50% of benefits with the SPV

Risk sharing analysis

Public Private

Risk sharing matrix

The PPP's scope included design, construction, financing and maintenance

Land acquisition

Force majeure

Operator incidents

Early debt termination

Inflation

Geological

Changes in regulations

Project amendments

Financial closing

Refinancing&insurance

Design&Construction

Maintenance costs

Availability

Level of service

Interest rates

Technology

Private partner risks

Detailed design, subject to ADIF's approval,was done by the SPV based on the initialproposal provided by ADIF in the tender phase

Deadline risk for project design, as wellas any mistakes from the draftingprocess were also with the SPV

The private partner undertook constructionrisks with the exception of force majeure,geological, archaeological events or reasonsattributable to ADIF

Maintenance cost risk was SPV'sresponsibility except for changes due toregulatory and 'progress clause' upgrades

Availability Risk estimated through definedindicators: Quality, Availability and Reliability

Technical risk and interface risks relatedto the interface between ERTMS from differentsuppliers were addressed by the private side

The scope of this obligation is limited tothe duty to maintain awarded facilitieswith their original features or updatedthem if ADIF authorises them

Risk sharing analysis

Public Private

Risk sharing matrix

The PPP's scope included design, construction, financing and maintenance

Certification and interoperability

The private partner undertook the full responsibility for the certification process, costs included inBAFO

ISA and NOBO requirements to be fulfilled by the private partner

ADIF, through their safety services, approve the safety dossiers and apply to Spanish NSA for theoperation authorisation

After approval tests, reliability and endurance period have been planned to check interoperability withS/100 trains from ALSTOM and S/130 trains from TALGO-Bombardier Technology

Technical components of the project

Construction and certificationTechnical aspects

Signalling – ERTMS Level 2 :

ETCS Radio Block Center, eurobalises, interlockings,

track circuits, point machines, axle counters.

Telecommunication System:

Optical fiber network and copper network,

SDH network // Ethernet network,

CTC // Control desk ERTMS,

Integration in Madrid and Albacete CRC

Civil protection system:

CCTV Devices (Detection and access control),

Detection devices (lateral wind, hot box detectors…)

GSMR: BTS, BSC, Other infrastructure

Accelerated project realization schedulethrough use of DBFM contract

Construction requirements and maintenanceindicators were defined by ADIF standards;technical aspects did not differ from other S&Tcontracts

Installation of ERTMS-2 without backups onHSRL (greenfield construction)

Implementation of modifications of ERTMS-2needed additional tests in an Alstom lab

Train protection systems provided are ASFAand ERTMS Level 1 and Level 2

Integration of the rest of subsystems

Potential improvements

Main lessons

More timely communication with ERA More stable regulatory environment with respect ERTMS Clearer description of technical, legal and financial requirements More pro-active support from the public sector in the process of attracting finance Closer investigation of the project bond strategy for securing long term debt financing Better incorporation of feedback from tendering and construction phases in new PPP contracts Earlier application for EU grants for feasibility studies

Success factors Main challenges

Pro-active role of the public partner (Adif) toinvolve the EIB early in project preparation

Adif technical expertise key to successfulevaluation of bids during PPP procurement

The EU support through the EIB loan atfavourable interest rates, added value of EIBtransferred to public sector

Equity partner (Fond ICO) provided asubordinated loan that served as a buffer andhelped to complement the EIB loan

Scope of risk transfer and alignment ofinterests was optimal for ERTMS project

The lack of available financing fromcommercial banks – very difficult marketconditions

Extra guarantees that private sponsors(mainly the industrial ones) had to provide

Uncertainty about the technological evolutionof GSM-R mobile telecommunications

Risks associated with regulatory changes atthe EU level

Pathfinder project, untested model

Replicability

Replicability

Preparation Phase:

PPP projects that get EIB involved in the preparation phase improve ability to reach financialclose, benefit from ‘signalling effect’ of EIB endorsement and EIB due diligence

The PPP scheme is applicable for superstructure projects (signalling, electrification, substation):

Timing issues drove carve-out of essential traffic control systems into PPP model: ERTMSplus complementary works necessary for ERTMS operations , proved to be ideal toseparate civil works with large capex and high construction risks from the superstructurePPP with its greater focus on opex and maintenance risks.

S&T contract for the infrastructure should be in an advanced development stage andpublic sector needs to coordinate civil works with technology-based PPP contract

Procurement phase: essential to have dedicated public sector team with strong technical expertisefor evaluation and PPP expertise to manage procurement process and PPP contract

Implementation phase: Greenfield status avoided unexpected legacy problems, streamlined theconstruction process and quality of results became dependent on competence of contractor

Operational phase: equity participation of Adif kept long term focus on operational issues, keyaspect of S&T PPP contract success is control of maintenance during operational phase

All public stakeholders can apply for EU support, including CEF grants, CEF financial instruments andEIB loans

TEN-T eligibility provides assurance of stability and commitment of the public sector to the project

Important elements of the case study could be replicated across the EU

Initiation Identification of objectives ADIF proactive EIB involved early

A summary of key points in best practice in PPP procurement of ERTMS

Case study summary

Preparation, Carve out Limited scope: limits

technology/project risks Suitable risk allocation

public/private Focus on Opex

Procurement Prequalification based both

on financial and technicalcapabilities

Expertise available forevaluation of both aspects

Negotiations before BAFO

Implementation & operation

Team approach: all partiesin SPV

Expertise in Execution Objectives met

ANNEX IERTMS

ERTMS is setting single rail traffic management standards across Europe

ERTMS – overview

ERTMS goals Benefits of ERTMS

The European Railway Traffic ManagementSystem (ERTMS) aims at replacing differentnational train control and commandstandards in Europe by a fully interoperablesystem

ERTMS enables the creation of a seamlessEuropean railway system and increasesEuropean railway's competitiveness

ERTMS fosters cross-border cooperationbetween the different stakeholders, includingpassenger carriers, freight transporters andrailway-equipment manufacturers

European level support In 2005 European Commission identified 6

priority ERTMS corridors In 2009 a dedicated European deployment

plan covering more than 25,000 km of raillines was adopted to ensure that EU countriesequip their network with ERTMS by 2020

TEN-T Programme has provided a significantgrant support to be continued under CEF

Interoperability

High levels of safety, punctuality and reliability Better optimisation of the rail lines' capacity Increased speed of cargo delivery and travel More open supply market for equipment Reduced need for ground equipment Lower prices over the long term Improved competitiveness of rail compared

with other modes of transport Greater territorial and economic cohesion Considerable reductions in CO2 emissions due

to modal shift from air and car transport

Geographical interoperability betweencountries – train fitted with ERTMS can run onany other ERTMS-equipped line

Technical interoperability between suppliers –a train fitted by a given supplier will be able torun on trackside infrastructure installed byanother supplier

European Vital Computer (EVC)able to interpret the signals fromthe ETCS trackside elementsinstalled on the track

Onboard

ETCS Eurobalises – specialtransceivers installed at intervalsbetween the rails provide trackinformation to the ETCS systeminstalled in the locomotive

ETCS is a standard system using mass-produced components

ERTMS – technical overview

ERTMS sub-systems ERTMS components

ERTMS operation scheme

GSM-Railway

An international wireless communication standard for railway communication

Used for data and voice transfer between trains and trackside control systems

Trackside A train-based

computer with unified Automatic Train Protection (ATP) system

Prevents the train from exceeding maximum allowed speed at the given part of the track

ETCS European Train Control System

Eurobalises

EVC

Source: International Union of Railways Note: 1 ETCS – European Train Control System

1

Level 1

ERTMS allows for a smooth migration from one level to other level

ERTMS – technical overview

ERTMS levels

Level 2

Designed as an add-on to a conventional line already equipped with lineside signals Ground based beacons – Eurobalises – transmit traffic management information to the train

Does not require lineside signals; however, train position is still carried out on the ground

Balise information is transmitted by radio, which lowers installation and maintenance costs

The Memorandum of Understanding strengthens ERTMS deployment

EC European Commission

Supervises the implementation of ERTMS incases where it is mandatory under Europeanlegislation

Provides financial support for projectsintending to deploy ERTMS, for bothinfrastructure and rolling stock installations

ERA European Railway Agency

Responsible for ETCS and GSM-R regardingspecifications delivery, quality assurance,configuration management and change control

Carries out a biennial report on the progressachieved in the field of interoperability

Prepares report on network safety levels

UNIFE European Rail Industry Association

Result of a merger of 3 associations in 1991

Represents 82 companies responsible for thedesign, manufacture, maintenance andrefurbishment of rail transport systems,subsystems and related equipment in Europe

UNISIG industrial consortium

Founded in 1999, a member of UNIFE Has a task to develop technical specifications

for ERTMS/ETCS in cooperation with the ERA

MoU between EC, ERA and the European rail sector associations

The Memorandum of Understanding (MoU) signed in 2008 forms the basis of the long termcommitment of all stakeholders – the rail industry, infrastructure managers, railway undertakings andEU institutions - to deploy ERTMS along the European railway network

ERTMS – main stakeholders

Note: 1 The Fourth Railway Package articulates that the ERA will be given legal responsibility for issuing vehicle authorisations for placing on the market and for safety certification for Railway Undertakings (RUs)

1

Rail line Albacete – La Encina - Alicante

ERTMS Level 1ERTMS Level 1/2ERTMS Level 2

Overview

Spain is the 1st in Europe and 2nd in theworld, after China, by the length of high-performance lines in operation

€45.1 billion have been invested in high-speedrail network in Spain

ADIF is a pioneer in ERTMS deployment inEurope that identified ERTMS as the signallingsystem of choice since the early 2000s

Spain has world's longest ERTMS network

ERTMS now covers the major part of theSpanish High Speed network

No less than 6 companies are involved inERTMS projects on the Spanish network

User ADIF Supplier Alstom ERTMS Level 2 Order Date 2011 Track length 330 km

Source: ADIF, ERTMS, EUROSTAT Note: 1 ADIF is a Spanish state-owned company managing most of Spain's railway infrastructure, that is the track, signalling and stations; 2 EUROSTAT data for 2011

ERTMS network in Spain

Spain emerges as a worldwide leader in ERTMS deployment

ERTMS – deployment in Spain

Spanish rail network

Total length 14,000 km High-speed network 3,100 km ERTMS network 2,000 km Cities on high-speed network 31 Projected network extension 3,000 km

1

2