9 terrible mistakes and how to fix them
DESCRIPTION
9 Terrible Mistakes and How to Fix Them Using Projected Costs by Bob Mattlin, Founder and Owner of ComputerEase Software, Inc.TRANSCRIPT
Copyright 2008 ComputerEase Software, Inc.All rights reserved.12/4/2008
ComputerEase Software, Inc.6460 Harrison Ave., Suite 200Cincinnati, OH 45247
The text of this publication, or any part thereof, may not be reproduced or transmitted in any form or by any means,electronic or mechanical, including photocopying, recording, storage in an information retrieval system, or otherwise,without the prior written permission of ComputerEase Software, Inc.
Willful violation of this Copyright law of the United States can result in civil damages up to $50,000 (US) perinfringement (17 USC 506; reasonable attorney fees may be awarded (17 USC 505); and copyright infringements canbe a criminal offense. (17 USC506).
All names, products and services mentioned are the trademarks or registered trademarks of the respective vendorsor organizations.
PublisherComputerEase Software
Founder and owner ofComputerEase, Bob Mattlin, camefrom a family background inconstruction and a personalbackground as a CPA for anational accounting firm.
As computer technologies becameincreasingly available in the earlyeighties, Mr. Mattlin had a visionof using this technology to pulltogether his accounting andconstruction-industry knowledgeto improve the way contractorsmanaged their businesses.
Twenty-five years later, he ownsthe industry-leading company inconstruction managementsoftware solutions and continuesworking to improve contractors'business practices.
Construction is a competitiveindustry, and ComputerEaseprovides contractors with theedge they need to stay strongand productive.
Bob Mattlin, CPA A Brief Background
5Contents
5
Table of Contents
Introduction 2
Terrible Mistake #1 4
................................................................................................................................... 4Company profits are misstated and misleading-THEY AREWRONG!!!
................................................................................................................................... 4 Company profits are misstated.
................................................................................................................................... 5EXERCISE #1:
Terrible Mistake #2 7
................................................................................................................................... 7Project managers are under the false assumption that all is welland the job is progressing nicely and making money.
................................................................................................................................... 7 Project managers could be misled in thinking the job is goingalong fine based on actual hours to date.
................................................................................................................................... 8EXERCISE #2
Terrible Mistake #3 10
................................................................................................................................... 10Without projected costs, percent complete analysis isimpossible.
................................................................................................................................... 11Project managers need an early warning system to measure jobstatus before it is too late.
................................................................................................................................... 11EXERCISE #3
Terrible Mistake #4 13
................................................................................................................................... 13The estimator is out of touch with job performance and has noidea where his estimate stands until the job is over.
................................................................................................................................... 14Estimator has to stay involved throughout the job.
................................................................................................................................... 14EXERCISE #4:
Terrible Mistake #5 16................................................................................................................................... 16Job billings are out of sync with job costs.................................................................................................................................... 17Job Billings on the Balance Sheet are incorrect.................................................................................................................................... 17EXERCISE #5:
Terrible Mistake #6 19
................................................................................................................................... 19The contractor’s CPA is required to make large and surprisingadjustments to the year end financial statements.
................................................................................................................................... 20CPAs should not have to make large and surprising adjustmentsat the end of the year.
................................................................................................................................... 20EXERCISE #6:
9 Mistakes6
ComputerEase Software, Inc.
Terrible Mistake #7 23
................................................................................................................................... 23No one knows the job schedule has fallen behind until it’s toolate to make up the lost time.
................................................................................................................................... 24Job schedules are wrong using the cost-to-cost method.
................................................................................................................................... 24EXERCISE #7:
Terrible Mistake #8 26................................................................................................................................... 26Can’t measure unit productivity without projected costs.
................................................................................................................................... 27Cannot compare estimated unit productivity with actual unitproductivity.
................................................................................................................................... 27EXERCISE #8:
Terrible Mistake #9 29
................................................................................................................................... 29Without projected costs, “fade and gain” comparisons are notpossible.
................................................................................................................................... 30Without projected costs, PM’s cannot get a handle on week toweek performance.
................................................................................................................................... 30EXERCISE #9:
How To Fix the Nine Mistakes Using ProjectedCosts 32
................................................................................................................................... 32Cost-to-Cost Method: Don’t use it!!
................................................................................................................................... 33Projected Cost methods used to solve problems brought on bycost-to-cost method
.......................................................................................................................................................... 33Percent Complete Method
.......................................................................................................................................................... 34Estimating the total cost remaining method to complete an item
................................................................................................................................... 34Measuring the “fade” or “gain” in projected cost
................................................................................................................................... 35Using labor hours to calculate percent complete
................................................................................................................................... 36“Stripping” the estimators magical market price
................................................................................................................................... 37Calculating the “fade” or “gain” in the revised estimate usinghours
................................................................................................................................... 37Using Hours to calculate “fade” or “gain” in the revised estimate
Measuring unit productivity is the best way toproject percent complete 39
................................................................................................................................... 39The “fade”/“gain” analysis is a good weekly benchmark whenusing productivity per hour
................................................................................................................................... 40Answers
Reports 42................................................................................................................................... 42Sample - Percent Complete................................................................................................................................... 43Sample - Percent Complete................................................................................................................................... 44Sample - Work In Progress
7Contents
7
................................................................................................................................... 45Sample - Profit Variance
................................................................................................................................... 46Sample - Labor Analysis
................................................................................................................................... 47Sample - Unit Cost Report
................................................................................................................................... 48Sample - Schedule
................................................................................................................................... 49Sample - Unit Productivity Report
Introduction
Introduction 2
9 Terrible Mistakes
Introduction
Most contractors start out with the owner serving as the “project manager” on jobs. The
owner visits the job sites every day and has a keen sense of what is going on. He is
hands-on and can quickly see when things are going wrong. With the owner managing jobs,
they usually come in on time and on budget. But in time, growth brings more and larger jobs
and the owner can no longer keep up with them. The owner finds he needs new tools to
measure job progress.
We will discuss the measuring tools available to owners, estimators and project managers to
assist them in determining accurate job costs before the job is over. The methods discussed
will greatly improve how job costs are reported. Using these methods will forewarn the
construction team of any problems before they get out of hand. The worst thing that can
happen to a contractor is to find out that a job lost money after it was completed. The most
important purpose of using a projected cost system is to prevent this from happening.
The first section of this report starts off with “NINE Terrible Mistakes.” This section discusses
the serious problems caused by not knowing where the job stands at all times. After learning
the problems that come about by not projecting job costs, we discuss ways to prevent them
from happening.
Let’s start with those NINE Terrible Mistakes….
Terrible Mistake #1
Terrible Mistake #1 4
9 Terrible Mistakes
Terrible Mistake #1
Company profits are misstated and misleading-THEY AREWRONG!!!
A construction company has no idea where it stands without an accurate projection of job costs.
The example shown on the next page clearly illustrates that the financial statement cannot be
correct if a revised estimate is not calculated based on remaining costs and actual costs. Work
in progress on the balance sheet is misstated because a true picture is impossible without
projected costs. The illustration shows how using a cost-to-cost method of computing percent
complete can distort the financial statements.
Several problems are highlighted on the next exhibit:
o Profits are misstated
o Estimated tax payments are incorrect
o Cash flow analysis is difficult with the wrong profit
o Bonding companies are given wrong financial statements
Company profits are misstated.
Here is an example of how the cost-to-cost method distorts the financial statements:
ABC Financial Statement
Cost to Cost Projected Cost
Contract $125,000 $125,000
Estimated Cost $100,000 $100,000
Billed Revenue-50% $ 62,500 $ 62,500
Costs to date $ 50,000 $ 50,000
Projected costs to complete $ 50,000 $150,000
Revised Estimate $100,000 $________
Percent Complete 50% 25%
Profit (Loss) $ 12,500 $________
Federal Income Tax Estimate $ 4,000 $________
(40%*$125,000-50,000)
Over(Under) Billed None $________
9 Mistakes5
ComputerEase Software, Inc.
EXERCISE #1:
Calculate the following for the Projected Cost column:
1. Revised Estimate ______________
2. Profit or Loss _______________
3. Tax ________________
4. Over(Under) Billed _________________
Terrible Mistake #2
9 Mistakes7
ComputerEase Software, Inc.
Terrible Mistake #2
Project managers are under the false assumption that all is welland the job is progressing nicely and making money.
The project manager has no idea where he stands on a job without making regular estimates
of projected costs. The estimator has the responsibility to give the PM a break down of the
hours and units he used in his estimate. For example, without an estimate, the PM can’t
know that he used 500 hours to complete 500 square feet when he should have completed
1,000 square feet with that amount of hours. The PM needs to know how many hours he has
used and how many hours he has left to finish the bid item. Without estimated hours he
cannot know where the job stands.
Project managers want to be informed on how well they are doing on their jobs. There are
many studies that prove project managers are very frustrated by not having benchmarks to
measure the performance on their jobs. The PM wants to know desperately where he stands
on a job. Like everyone, he wants recognition for a job well done. Using projected cost
calculations is the only way for him to know the status of his jobs.
Project managers could be misled in thinking the job is goingalong fine based on actual hours to date.
If the estimator provides both units and hours to the PM, a labor analysis report similar to the one
below can be used by the PM to measure job progress.
Actual Hour Method Unit Production Method
Estimated
Hours
Actual
Hours
%
Complete
Remaining
Hours
Estimated
Hours
Estimated
Units
Actual
Hours
Actual
Units
%
Complete
Remaining
Hours
1,000 250 ______ ______ 1,000 2,000 250 200 _______ _______
Terrible Mistake #2 8
9 Terrible Mistakes
EXERCISE #2
Calculate the following:
1. Actual Hour Method % Complete ______________________
2. Actual Hour Method Remaining Hours ______________________
3. Unit Production Method % Complete _______________________
4. Unit Production Method Remaining Hours ______________________
Terrible Mistake #3
Terrible Mistake #3 10
9 Terrible Mistakes
Terrible Mistake #3
Without projected costs, percent complete analysis is impossible.
Without using percent complete calculations, the PM finds out too late that a bid item is in
trouble. If the PM knew he used 50% of the hours but only completed 25% of the work, he
can focus on turning things around early and prevent having to wait until the end of the job to
find out that he lost money.
The cost-to-cost method will not show the PM that a bid item is falling behind. The longer the
work continues off budget, the worse the job losses become. It is very difficult to make up for
the losses on a bid item once they have fallen behind.
A percent complete analysis provides the information needed to produce the work in
progress report. Without a percent complete analysis, the WIP report cannot be produced.
Bonding companies and banks rely more on a construction company’s work in progress
report than any other analysis. The WIP report is used by management as the starting point
of job analysis.
The percent complete report alerts the PM of problems at the bid item level. The WIP report
is used for total job status and is calculated using the individual bid item analysis from the
percent complete report. In accounting terms, the percent complete report is the sub ledger,
or detail work up of the WIP report. Learning which jobs are in trouble from an over all
perspective is one thing, determining which bid items are causing the problems is another. If
the PM doesn’t calculate what expected remaining costs are, the WIP report and the percent
complete report are useless.
9 Mistakes11
ComputerEase Software, Inc.
Project managers need an early warning system to measure jobstatus before it is too late.
Using cost-to-cost, here is a sample job which highlights the distortion:
Work Item %Complete
Contract EstimatedCost
Cost toDate
CostRemaining
RevisedEstimate
EstimatedProfit (Loss)
Projected Profit (Loss)
Excavate 100 12,000 10,000 10,000 0 10,000 2,000 2,000
Form 50 12,000 10,000 5,000 5,000 10,000 2,000 2,000
Pour 25 12,000 10,000 2,500 7,500 10,000 2,000 2,000
WIPReport
58 36,000 30,000 17,500 12,500 30,000 6,000 6,000
If the Percent Complete method is used, the same job looks like this:
Work Item %Complete
Contract EstimatedCost
Cost toDate
CostRemaining
RevisedEstimate
EstimatedProfit (Loss)
Projected Profit (Loss)
Excavate 100 12,000 10,000 10,000 0 10,000 2,000 2,000
Form 33 12,000 10,000 5,000 _______ _______ 2,000 _______
Pour 25 12,000 10,000 2,500 7,500 10,000 2,000 2,000
WIPReport
______ 36,000 30,000 17,500 6,000
EXERCISE #3
Calculate the following if the bid item “Form” is only 33% complete:
1. “Form” Cost Remaining ________________________
2. “Form” Revised Estimate ____________________________
3. “Form” Projected Profit (Loss) ________________________________
4. WIP Report % Complete _________________________
Terrible Mistake #4
9 Mistakes13
ComputerEase Software, Inc.
Terrible Mistake #4
The estimator is out of touch with job performance and has noidea where his estimate stands until the job is over.
The estimator is usually as surprised as anyone when the job he bid runs into trouble. The
estimator’s job requires more than just calculating a bid. He has to keep an eye on the job at all
times to make sure his estimate is being produced with the same methods he used in
developing the bid.
The PM and estimator should be in touch constantly. The PM and estimator must know how
actual costs compare to estimated costs throughout the job’s completion. The estimator can
provide valuable information to the PM as a bid item begins to show a loss. Regular project
meetings should bring the estimator and PM together to discuss problems early in the job,
before it is too late. The estimator should always be involved in calculating projected costs.
Since he bid the work, he is a valuable resource to the PM.
The estimator and PM use two methods to make sure that production in the field is ahead of the
estimate. The first method is comparing the actual unit cost with the estimated unit cost. By
providing the PM with the unit cost used in the estimate, the PM can monitor performance at
any stage of the job by comparing his unit cost of production with the estimated unit cost of
production. This gives the PM an early warning signal very early in the job’s progress. The
second method compares units of production from the field with the units of production used by
the estimator. The PM has valuable information if he knows the estimator used a productivity
rate of say 10 units per hour and compares it to his 12 units per hour. He quickly knows he is
probably doing pretty good. If there are 1000 units in the bid item, the PM knows where he
stands after only 10 are put in place. The PM has to know what his projected unit performance
is at all times.
Terrible Mistake #4 14
9 Terrible Mistakes
Estimator has to stay involved throughout the job.
Estimator is given this progress report based on cost-to-cost.
Work Item EstimatedCost
ActualCost
RemainingCost
% Complete RevisedEstimate
Estimated Unit
ActualUnits
EstimatedUnit Cost
ActualUnitCost
ProjectedUnit Cost
Excavate 10,000 8,750 0 100 8,750 1,000 1,000 10.00 8.75 8.75
Form 10,000 5,000 5,000 50 10,000 2,000 1,000 5.00 5.00 5.00
Estimator is given this progress report based on an updated estimate.
Work Item EstimatedCost
ActualCost
RemainingCost
%Complete
RevisedEstimate
EstimatedUnit
ActualUnits
EstimatedUnit Cost
ActualUnit Cost
ProjectedUnit Cost
Excavate 10,000 8,750 0 100 8,750 1,000 1,000 10.00 8.75 8.75
Form 10,000 5,000 5,000 50 _______ 2,000 1,000 5.00 5.00 _______
EXERCISE #4:
If the PM reports that it will require an additional 75% of the original estimated cost to
complete the bid item “Form”, calculate the following:
1. Projected Unit Cost _________________
2. Revised Estimate ________________________
Terrible Mistake #5
Terrible Mistake #5 16
9 Terrible Mistakes
Terrible Mistake #5
Job billings are out of sync with job costs.
Trouble is ahead if a job becomes overbilled or under billed due to losses. There are few things
worse than finding out late in the job that the money isn’t there to pay for the remaining work.
Billings should progress as much as possible at the same pace as the work. Front end loading
is a good option if the job is running on budget. But if the job is in trouble, front end loading can
only create problems later on in the job. Bonding companies and banks look at billings and job
cost status more than anything else. They want to make sure that future billings will cover
remaining costs. That’s why they demand accurate work in progress reports. Preparing accurate
WIP reports cannot be done without projecting future costs to complete.
The contractor suffers many problems if billings get out of whack with job costs. The problem
can be easily highlighted by an example; if the contract value on a job is $10,000, estimated
cost is $8,000 and actual cost to date is $4,000, billings at 50% complete should be $5,000. But
if the work is only 40% complete and the projected costs are now recalculated to be $10,000 at
completion, then billing $5,000 would create an overbilling situation. In this example if the work
is only 40% complete then billings should only be at 40% or $4,000. There can also be cash
flow problems if a job is under billed. If the job is 50% complete and 50% of the estimated costs
have been incurred, the contractor should be sure that 50% of the contract value is billed.
If the company bills too far ahead of job costs, the excess billings become a liability on the
balance sheet. If the job is under billed, the contractor is not taking advantage of optimum cash
flow. This is key information for banks and bonding agents. A contractor doesn’t want to be
wrong with this calculation. As far as bonding companies and banks are concerned, it is the
single most important number on a contractor’s financial statement.
9 Mistakes17
ComputerEase Software, Inc.
Job Billings on the Balance Sheet are incorrect.
The below report was prepared using the cost-to-cost method.
Work Item Contract Total
Billed
Cost %
Complete
Remaining
Cost
Over
Billed
Under
Billed
Excavate 12,000 12,000 8,750 100 0 0 0
Form 12,000 6,000 5,000 50 5,000 0 0
Pour 12,000 3,000 2,500 25 7,500 0 0
Total Job 36,000 21,000 16,250 12,500 0 0
EXERCISE #5:
Assume the PM reports that, based on his projections, the bid item “Form” is only 40%
complete, calculate:
1. “Form” Remaining cost _____________________
2. “Form” Over(Under) Billed amount _____________________
Terrible Mistake #6
9 Mistakes19
ComputerEase Software, Inc.
Terrible Mistake #6
The contractor’s CPA is required to make large and surprisingadjustments to the year end financial statements.
The percent complete calculation is what drives the values shown on the WIP report. The
percent complete numbers cannot be accurate if projected costs are not used. If the WIP
report is wrong, the CPA has to untangle the errors that were made. The adjustments the
CPA makes directly effects the profit and loss of the company. CPA adjustments would not
be necessary if the PM used projected costs to evaluate their jobs throughout the year. Every
contractor should be able to accurately calculate a WIP report without the use of a CPA. Job
analysis throughout the year is impossible without an accurate WIP report.
The owner is usually disappointed with profits after the CPA is finished adjusting the WIP
report. He cruised along during the year thinking he made more money than he actually did.
Worse yet, the company could have paid too much in estimated federal and state income
taxes based on erroneous profits. Paying taxes when it wasn’t necessary, of course, hurts
cash flow. A well managed contractor should know their projected job costs at all times.
Incorrect financial information is prevented with accurate and timely projected costs. The
bonding company and the bank do not want to be surprised with a CPA’s year end
adjustments.
The controller or accounting personnel in the company must demand an accurate WIP report
from the PM and estimator before he prepares any financial statement. He has to understand
job costs and projected costs and must work hand in hand with the PM in developing future
job costs. Without a job analysis, his financial statements are of little value.
Terrible Mistake #6 20
9 Terrible Mistakes
CPAs should not have to make large and surprising adjustmentsat the end of the year.
Below is an abbreviated WIP report highlighting the problems caused by improper
estimates of percent complete:
Work Item Contract Total
Billed
Cost %
Complete
Remaining
Cost
Revised
Estimate
Projected
Profit
Over
Billed
Under
Billed
Excavate 12,000 12,000 8,750 100 0 8,750 3,250 0 0
Form 12,000 6,000 5,000 50 5,000 10,000 2,000 0 0
Pour 12,000 3,000 2,500 25 7,500 10,000 2,000 0 0
Total Job 36,000 21,000 16,250 12,500 28,750 7,250 0 0
Work
Item
Contract Total
Billed
Cost %
Complete
Remaining
Cost
Revised
Estimate
Projected
Profit
Over
Billed
Under
Billed
Excavat
e
12,000 12,000 8,750 100 0 8,750 3,250 0 0
Form 12,000 6,000 5,000 60 3,333 8,333 ______ _____ _____
Pour 12,000 3,000 2,500 25 7,500 10,000 2,000 0 0
Total
Job
36,000 21,000 16,25
0
10,833 27,083 ______ _____ ______
EXERCISE #6:
The above WIP report is handed to your CPA at the end of the year. After a careful review
with the PM, the CPA determines the bid item “Form” is actually 60% complete based on
projected cost analysis. Calculate the following adjustments:
1. “Form” Over(Under) Billed _______________________________
2. Job Over(Under) Billed ________________________
9 Mistakes21
ComputerEase Software, Inc.
3. Sales Adjustment _____________________
4. Is Under billed shown as an asset or liability on the Balance Sheet?
Terrible Mistake #7
9 Mistakes23
ComputerEase Software, Inc.
Terrible Mistake #7
No one knows the job schedule has fallen behind until it’s too lateto make up the lost time.
The cost-to-cost method of measuring job progress will eventually cause an incorrect job
schedule. If a bid item is on the critical path and assumed to be 50% complete when it is
actually only 25% complete, the schedule will have to be adjusted at some time. It is better to
know of adjustments to the schedule as soon as possible. Customers, bonding agents, bankers
and subcontractors do not want to be surprised by a job falling behind. Job progress reporting
based on a percent complete method will assist in finding early scheduling problems. Any bid
item on the critical path has to be monitored closely and kept current as to percent complete.
During initial job planning, the PM will usually schedule less hours than the estimated hours.
This is his built-in cushion for performance. For example, if the estimator “gave” him 1000 hours
to complete a task, he might initially try and schedule only 800 hours. The PM knows if he can
bring the job in within 800 hours he will make a profit beyond the estimated profit. The 800
hours, not the 1,000 hours becomes his benchmark.
The PM realizes that to hit the 800 hours the job has to run efficiently. There can be no work
stoppages, all subs must show up when needed and finish on time, materials must be delivered
to match manpower on the job and crews must be on the job when needed. Without projecting
job costs, the PM can be surprised by events causing a change in schedule. He needs to know
well ahead of time of any job schedule changes. If he assumes he is 50% complete because he
has used 50% of the hours, his schedule can become unwieldy if in fact he is only 30%
complete.
Terrible Mistake #7 24
9 Terrible Mistakes
Job schedules are wrong using the cost-to-cost method.
The following example demonstrates how cost-to-cost can distort a schedule.
Work
Item
Estimated
Hours
Actual
Hours
%
Complete
Hours
Remaining
Revised
Hours to
Schedule
Excavate 1,000 920 100 0 0
Form 1,000 500 50 500 ______
Pour 1,000 250 25 750 ______
EXERCISE #7:
If “Form” is 70% complete and “Pour” is 10% complete, calculate the Revised Hours to
Schedule:
1. Form _________________________
2. Pour __________________________
Terrible Mistake #8
Terrible Mistake #8 26
9 Terrible Mistakes
Terrible Mistake #8
Can’t measure unit productivity without projected costs.
One of the more important measurements to track job progress is comparing actual unit
production with estimated unit production. Without projected costs, it is impossible to
compare actual unit productivity against estimated unit productivity. The calculation of unit
productivity is easy to make if four things are known:
Estimated hours and estimated units to be complete per hour
Actual hours and actual units put in place.
If the estimate was to complete 500 units in 500 hours and the project manager met this rate
of production, it can be assumed the job is on target. The real advantage of this method is
the PM and the estimator can tell where bid item stands when only 50 units are complete. If
he used 20% of the hours (100) to put 10% (50) of the units in place, he is producing only ½
unit per hour and not the estimated 1 unit per hour.
The estimated units per hour of production must be provided by the estimator. Not only must
he provide the PM with estimated unit costs, but he must show how he came up with those
costs. He has to provide what productivity rate per hour he used to come up with his overall
unit cost. The PM is left in the dark if all he has to measure is unit costs. He knows he must
match the rate of productivity per hour with the estimate. And he needs to know early in the
jobs progress.
By projecting the 100 hours used above to complete the first 50 units, the problem is clearly
highlighted. The PM sees that it will take 900 hours to complete the remaining 90% (450) of
units. Perhaps something can be done in time to recapture some of the losses incurred.
Using the projection is much better than waiting until the end of the job and finding out it took
1000 hours to install 500 units. If the hourly cost rate for the company is $100, that is a
$50,000 loss!
9 Mistakes27
ComputerEase Software, Inc.
Cannot compare estimated unit productivity with actual unitproductivity.
This report was prepared using the cost-to-cost method.
Units Units Work Proj Actual Actual Projected
Work Item Est Compl % % Hours Units Per Hour Units Per Hour
Excavate LS 1000 1000 100 100 200 5.00 5.00
Form SFT 1000 500 50 50 500 1.00 _____
Pour Cu Yds 1000 250 25 25 200 1.25 _____
EXERCISE #8:
Assume that the PM reports that bid item “Form” will require 750 more hours to
complete and “Pour” will require 300 more hours:
What is the Projected Units per Hour?
1. FORM_____________________
2. POUR_____________________
Terrible Mistake #9
9 Mistakes29
ComputerEase Software, Inc.
Terrible Mistake #9
Without projected costs, “fade and gain” comparisons are notpossible.
Fade and gain analysis measures the differences in projected costs from one week to the next. By
comparing the week to week change in projected costs the PM is provided an important trend
analysis as to where his job stands. If estimated projected costs decreased during a week it will
show up as a “gain.” If the PM has to increase his estimate of projected costs, it means he suffered
a “fade.” If for example the PM last week projected job costs to be $115,567, and this week
projected $105,567, he gained $10,000. The gain represents more production with less cost for that
week. Since the job starts off with projected costs equaling the estimated cost, the PM is looking for
week to week gains with hopefully no fade. This is a simple and fast method to compare job
performance from week to week.
The above example calculated the fade/gain for the complete job. The PM needs to take another
step and review the fade/gain on each bid item. The $10,000 gain above will be the net number after
all bid items are taken into consideration. Some bid items will have week to week gains and some
will fade week to week. As an example, the bid item “Form” could have gained (projected cost
decrease) by $20,000, while the bid item “Pour” faded by $10,000 (projected costs increased). The
PM will work diligently to try and get some of the fade back for next weeks reporting.
In analyzing fade and gain changes, PM’s are working more and more with unit productivity
measurements. Comparing actual unit performance against budgeted unit performance is the most
accurate method of projecting job costs. If the PM produced 50% of the items with 60% of the labor
hours for the week, he will have a revised estimated cost of 120% representing a fade in projected
cost for that week of 20%. His goal will be to place the remaining 50% of the units with only 40% of
the original labor budget-thus gaining back the 20% fade and completing the task at 100% of the
original budget. It is easy to see with the fade/gain projected cost analysis, the PM has a better
handle on week to week job performance.
Terrible Mistake #9 30
9 Terrible Mistakes
Without projected costs, PM’s cannot get a handle on week toweek performance.
Cost to cost fade/gain calculation
Week 1 Week 2
Contract amount 12,000 12,000
Estimated cost 10,000 10,000
Actual cost 2,000 5,000
Remaining estimate 8,000 5,000
Projected total cost 10,000 10,000
Job income 2,000 2,000
(Fade)/Gain -0- -0-
Percent Complete fade/gain calculation
Week 1 Week 2
Contract amount 12,000 14,000
Estimated cost 10,000 11,000
Actual cost 2,000 6,000
Remaining estimate 8,000 ?
Projected total cost 10,000 ?
Job income 2,000 ?
(Fade)/Gain -0- ?
EXERCISE #9:
For Week 2, if the task is 40% complete calculate the following:
Remaining estimate ______________
Projected Cost __________________
Job Income ____________________
Job income fade/gain_____________
How To Fix theNine Mistakes
Using ProjectedCosts
How To Fix the Nine Mistakes Using Projected Costs 32
9 Terrible Mistakes
How To Fix the Nine Mistakes Using Projected Costs
Forecasting job costs creates the opportunity to correct job losses before they get out of
hand. Measuring the difference between estimated costs and actual costs cannot be fully
accomplished without estimating projected costs. Estimating future costs on a job gives the
entire construction team an early chance to turn around a work item that is losing money
before the job is complete. Developing methods to forecast job costs are the most important
calculations a contractor can make. Most contractors will use one of five methods to calculate
percent complete and we will discuss these methods in detail:
Cost-to-Cost
Percent Complete
Estimate total cost to complete
Labor hours to complete
Unit Productivity
Cost-to-Cost Method: Don’t use it!!
The cost-to-cost method compares actual costs with estimated costs to develop the percent
complete. For example, if the work item’s estimated cost is $10,000 and $5,000 of cost has
been incurred, it is assumed the job is 50% complete. Actual completion of a work item is not
taken into account with the cost-to-cost method. It is an assumption that costs to date
represent the percent complete when compared to the estimate. There is no consideration
for what projected costs may be. All kinds of things go wrong when this method is used:
· Financial statements are misstated since the WIP report is not correct.
· Cash flow is irregular because billings don’t match costs.
· Losses continue to pile up.
· Bonding agents don’t trust the financial statements. They want to know what cash will
be available to finish the job.
· Owners don’t know where they stand.
· Scheduling becomes difficult if PM is not aware of “future” trouble.
9 Mistakes33
ComputerEase Software, Inc.
The cost-to-cost method produces a WIP report shown below:
Est. Actual Cost % Work % Revised Over/Under
Cost Cost Remaining **Compl Compl Est. Budget
10,000 5,000 5,000 50% 10,000 0
**Calculated by dividing actual cost by estimated cost without reference to projected costs to
complete. Just because we incurred 50% of the estimated cost does not mean we are 50%
complete.
Table 1
Projected Cost methods used to solve problems brought on bycost-to-cost method
Percent Complete Method
The percent complete method corrects the problem caused by the cost-to-cost method. An
additional step is taken by estimating the projected costs needed to complete a work item.
The picture changes drastically if projected costs are calculated based on an estimate that
the work item is only 25% complete. Instead of $5,000 to complete the work item as shown
above, the projected cost method calculates that it will take $15,000 to finish the item. In
other words, it took 50% of the estimated cost to produce 25% of the work. We know if work
continues at the same pace as the first 25%, the item will end up costing $20,000-a projected
over budget of $10,000.
By projecting job costs the WIP report shows a different picture.
Est. Actual Cost % Work % Revised Over/Under
Cost Cost Remaining Compl Compl Est. Budget
10,000 5,000 15,000 25% 20,000 10,000
Compared to the cost-to-cost report which showed a $0 over/under budget, the percent
complete method shows a projected over budget of $10,000.
Table 2
How To Fix the Nine Mistakes Using Projected Costs 34
9 Terrible Mistakes
Another advantage of using the percent complete method is that it detects problems early.
Because the PM caught the problem at the 25% stage, resources can be re-directed to the
problem and perhaps recover some of the projected over budget amount. The revised
projected cost estimate of $20,000 is quite different than the $10,000 calculated with the
cost-to-cost method.
Estimating the total cost remaining method to complete an item
Most contractors would refer to this method as re-estimating the job. This method is
commonly used by contractors that are not able to use estimated labor hours or estimated
units to calculate percent complete. Unlike other methods, the PM has nothing to “hang his
hat” on. He is unable to use labor hours or units to help measure percent complete. He has
to come up with his best estimate of what it will take to complete the bid item. In our example
if the PM estimates that it will take 10,000 to complete the work item the WIP report would
look like this.
Est. Actual Cost Work % Revised Over/Under
Cost Cost Remaining **Compl Est. Budget
10,000 5,000 10,000 33% 15,000 5,000
**Calculated based on the PM’s estimate of costs remaining.
Table 3
Measuring the “fade” or “gain” in projected cost
One way to measure how effectively the PM is projecting job costs is to analyze the “fade” or
“gain” in projected cost every week. This keeps track of the difference in the revised estimate
from week to week. It is normally measured using the WIP report. For example, we will
assume in week one that the original estimate was $10,000 and the PM estimates $5,000 of
remaining costs. He projects he is 50% complete. The revised estimate stays at $10,000
because he is making the budget. Since the first week is on target with the estimate, there is
no fade or gain.
In week two, the PM estimates he has $3,000 remaining in costs to complete the bid item.
His project is projected to be 75% complete. His revised estimate is now $12,000. During
week 2 his revised estimate faded by $2,000 as shown below.
9 Mistakes35
ComputerEase Software, Inc.
Original Actual Remain Revised
Bid Costs Costs % Compl Estimate Fade
$10,000 $10,000
Week One 10,000 5,000 5,000 50% 10,000 -0-
Week Two 10,000 9,000 3,000 75% 12,000 (2000)
Table 4 Calculating fade.
Using labor hours to calculate percent complete
Comparing estimated labor hours against actual labor hours gives the PM a more precise
way to predict future costs. Most labor oriented subcontractors use this method. While it is
better than estimating total costs to complete a work item, it also has it weaknesses. The PM
normally is “tuned in” to labor hours. If the estimator “gives him” 1000 hours to complete a bid
item, he may schedule only 800 hours. He knows if he gets the work done in 800 hours he
has made money-he beat the budget with a margin. It is a simple way for him to keep track of
how well he is doing on the job
.
Example of PM scheduling less than estimated.
Revised
Est hours Schedule hours Actual hours % Hours
1,000 800 400 50% 800
Table 5 Using the PM’s cushion to calculate revised hours.
How To Fix the Nine Mistakes Using Projected Costs 36
9 Terrible Mistakes
“Stripping” the estimators magical market price
The estimator should always give the PM the number of hours he estimated before the job
starts. The estimate is the beginning of job forecasting. Accurate percentage complete
calculations cannot be made without an estimate. Most estimators use a “market price” in
their bid which can be tough to break out the hours.
Let’s take an example of concrete flat work being estimated at $4.00 per sq ft. The $4.00 per
sq ft is the rate the “market” has established for bidding purposes. The estimator is pretty
much locked into this number. He obviously won’t get much work if he uses $6.00 a sq ft
when his competition is bidding it at $4.00 sq ft. Of course, the estimator has to take into
account the type of slab it is and any unusual factors. A slab on the 6th floor will be quoted
differently than a basement slab for example.
The market price of $4.00 per sq ft needs to be broken down for the PM. The all inclusive
estimated unit cost of $4.00 does him little good. His key to making money is managing
labor. He needs to know the hours remaining to complete the bid item. He asks the estimator
to “strip” the estimate of all costs except for labor. It turns out the estimator already made the
labor calculation. In putting his bid together, he wanted to check his market price before
submitting the bid. He estimated it would take 40 hours to complete 1,000 sq ft of slab.
Here is his calculation. Remember, he used the market rate for the estimate and didn’t know
what the labor factor was in the $4.00.
Estimated cost $4,000 ($4 sq ft X 1,000 sq ft)
Less material cost -1,500
Less sub cost -500
Total Labor $2,000 / $50 (labor rate with O.H.) = 40 hours
Table 6 Stripping the estimate to determine labor.
9 Mistakes37
ComputerEase Software, Inc.
Calculating the “fade” or “gain” in the revised estimate usinghours
Let’s assume the PM used 4 hours to complete 100 sq ft of the concrete pour in the first
week and he projects it will take 36 hours to finish the remaining 900 sq ft. Since he did 10%
of the work and used 10% of the hours, his revised estimate is the same as the original
estimate, 40 hours. He is on track.
In week two, the PM runs into some problems and needed 8 hours to pour another 100 sq ft.
He calculates his remaining time to be 30 hours. His revised estimate has changed to 42
hours (adding the 30 hours to the 12 hours he has used).
His revised estimate went from 40 hours to 42 hours. The 42 hours becomes the new basis for thecalculation of the fade
Using Hours to calculate “fade” or “gain” in the revised estimate
Units in Hours Remain Revised
Place Used Hrs Estimate Fade
Original Bid 1,000 sq ft 40 40 40 hrs 0
Week one 100 sq ft 4 36 40 hrs 0
Week two 100 sq ft 8 30 42 hrs -2 hrs
In week three, the PM hopes to reduce his revised estimate below the original estimate.
Table 7 Calculating the “fade” or “gain” in the revised estimate using hours.
Measuring unitproductivity is thebest way to projectpercent complete
9 Mistakes39
ComputerEase Software, Inc.
Measuring unit productivity is the best way to projectpercent complete
Measuring job performance is best derived by calculating how many units per hour were
installed compared to the estimated rate of production. In the above example, the estimator
calculated a production rate of 25 sq ft per hour (1,000 sq ft / 40 hours estimated). This
becomes the project manager’s measure of performance.
Using the unit productivity method to calculate percent complete results in early detection of
the production per hour rate. Measuring unit productivity per hour gives the PM something to
shoot for everyday. Because he knows how many hours were used in that day’s pour, for
example, and how many square feet he poured, he knows the unit productivity at the end of
the day. He learns in the very first pour, the first 100 sq ft, how well he is doing. Best of all,
he is only 10 percent complete. Had this production rate been off, he would have time to
address the problem.
The “fade”/“gain” analysis is a good weekly benchmark whenusing productivity per hour
The “fade”/”gain”calculation in the above example gave the PM a measurement that he could
compare week to week. His first week pour was on target, he poured 100sq ft in 4 hours. His
productivity was 25 sq ft per hour, matching the estimated production per hour.
During the second week, however, he didn’t perform as well. It took him 8 hours to pour the
same 100 sq ft. His production rate for that week fell to only 12.5 sq ft per hour. It is clearly
illustrated that he had a problem and was able to find it very early in the job.
Measuring unit productivity is the best way to project percent complete 40
9 Terrible Mistakes
Answers
Exercise #1: Exercise #7:
1. $200,000 1. 214
2. ($18,750) 2. 2,250
3. $0
4. $31,250 Overbilled. Exercise #8:
1. .8
Exercise #2: 2. 2
1. 25% Exercise #9:
2. $750 1. $9,000
3. 10% 2. $15,000
4. $2,250 3. ($1,000)
4. $3,000 Fade
Exercise #3:
1. $10,000
2. $15,000
3. ($3,000)
4. 50%
Exercise #4:
1. $6.25
2. $12,500
Exercise #5:
1. $7,500
2. $1,200 Overbilled
Exercise #6:
1. $1,200 Under billed
2. $1,200 Under billed
3. $1,200
4. Asset
Reports
Reports 42
9 Terrible Mistakes
Reports
Sample - Percent Complete
9 Mistakes43
ComputerEase Software, Inc.
Sample - Percent Complete
Reports 44
9 Terrible Mistakes
Sample - Work In Progress
9 Mistakes45
ComputerEase Software, Inc.
Sample - Profit Variance
Reports 46
9 Terrible Mistakes
Sample - Labor Analysis
9 Mistakes47
ComputerEase Software, Inc.
Sample - Unit Cost Report
Reports 48
9 Terrible Mistakes
Sample - Schedule
9 Mistakes49
ComputerEase Software, Inc.
Sample - Unit Productivity Report
800.544.2530