7th study meeting tokyo - holger bietz

Download 7th study meeting Tokyo - Holger Bietz

Post on 01-Dec-2014

556 views

Category:

Technology

2 download

Embed Size (px)

DESCRIPTION

On 16 May 2013, the Global CCS Institute hosted its seventh study meeting in Tokyo. This presentation is by Holger Bietz, the Institute's General Manager, Projects, Financial and Commercial.

TRANSCRIPT

  • 1. THE GLOBAL STATUS OF CCSHOLGER BIETZ General Manager Projects, Financial and Commercial7th Study Meeting Tokyo16 May 2013
  • 2. THE GLOBAL STATUS OF CCS: 2012 Released October 2012. Update released January 2013. Comprehensive coverage on thestate of CCS projects andtechnologies. Challenges and recommendationsfor moving forward.2
  • 3. KEYMESSAGE CCS IS ALREADY CONTRIBUTING,BUT PROGRESS MUST BE ACCELERATED39 operating projects: 6 natural gas processing plants 1 fertiliser plant 1 synthetic natural gas plant 1 hydrogen plant8 projects under construction (Execute): 2 electricity generation plants 2 natural gas processing plants 1 hydrogen plants 1 fertiliser plant 1 ethanol plant 1 oil refining
  • 4. KEYMESSAGEVolume of CO2 potentially stored by large-scale integrated projectsCCS IS ALREADY CONTRIBUTING,BUT PROGRESS MUST BE ACCELERATED4
  • 5. KEYMESSAGE CCS IS ALREADY CONTRIBUTING,BUT PROGRESS MUST BE ACCELERATED5Volume of CO2 potentially stored by large-scale integrated projects
  • 6. KEYMESSAGE STEADY PROGRESS BUTIMPORTANT DEVELOPMENTSLarge-scale integrated projects by asset lifecycle and year6
  • 7. KEYMESSAGEVolume of CO2 potentially stored by primary storage type and region7January 2013 UpdateSTEADY PROGRESS BUTIMPORTANT DEVELOPMENTS
  • 8. KEYMESSAGE8Quest, CanadaTCM, NorwayPlant Barry, USBoundary Dam,CanadaSTEADY PROGRESS BUTIMPORTANT DEVELOPMENTS
  • 9. KEYMESSAGE ACCELERATION OF CCS DEPENDS ONCOLLABORATION AND KNOWLEDGE SHARING CCS faces difficult and time-consumingchallenges. Sharing knowledge gained is critical toaccelerating the deployment of CCS. Collaboration and effort is required to increasethe intensity and scope of knowledge sharingactivities.9
  • 10. PROJECT KNOWLEDGE-SHARING AGREEMENTSINSTITUTE FUNDING STATUSActiveCommencing/under discussionCompleted2. Trailblazer(Tenaska)FEED studies3. Nelson 6(Tenaska/Entergy)Development studies1. RCI(Rotterdam CCS Network)Storage and shipping studies 6. Getica(ISPE)Feasibility Study10. Callide Oxyfuel(OTPL)Transport and CO2 injectionstudies4. Pioneer(TransAlta)FEED studies11. CarbonNet(Victorian Government)Commercial and Planning studies5. Mountaineer(American Electric Power)FEED studies7. ROAD(Maasvlakte CCS)FEED studies &execution planning8 Chiyoda(Chiyoda/Tokyo University)Shuttle shipping study9. South West Hub(Western Australian Government)General reports13. CSIROAmine emissionstudies14. CarbonNet MMV(Victorian Government)MMV scope study15. Loy Yang(Worley Parsons, MHI)Process validation model16. Yanchang CCUS(Shaanxi Yanchang Petroleum)Capture, storage and permit reports10
  • 11. PROJECT KNOWLEDGE-SHARING AGREEMENTSFeasibility/FEED Case Studies StatusProjectCaptureTransport/InfrastructureStorageandMMVFinanceandCommercialPolicy,LegalandRegulationPublicEngagementRiskandEnvironment1Rotterdam CCS NetworkProjectComplete2 Trailblazer Energy Center Complete3 Nelson 6 CCS ProjectComplete4 TransAlta Pioneer In progress5 AEP MountaineerComplete6 Romanian CCS Demo PlantComplete7 ROAD Project In progress8 Chiyoda Project Complete9 South West Hub Project In progress10 Callide Oxy-fuel Project In progress11 CarbonNet Project In progress13 CSIRO Complete14 CarbonNet Project - MMV Complete15 Loy Yang Complete16 Yanchang CCUS Project Commencing
  • 12. PROJECT KNOWLEDGE SHARING AEP mountaineer project (1)KEY ASPECTS OF AEPS MOUNTAINEER PROJECT The project aimed to design, construct, and operate Alstoms chilled ammoniaprocess to capture approximately 90% of the CO2 from a 235 MWe slipstreamfrom the existing 1300 MWe Mountaineer power plant. Around 1.5 million tonnes per annum of CO2 were to be treated, compressed andinjected into suitable deep saline formations for permanent storage approximately2.5 kilometres underground.REPORTS AND OUTCOMESThe knowledge sharing reports delivered to the Institute covered a wide range oftopics including: technical studies, business case, engineering and designconsiderations, integration and storage.In July 2011, AEP announced the project would be put on-hold beyond the front-endengineering design (FEED) phase, due to the current uncertain status of nationalclimate policy and weak economy.12
  • 13. PROJECT KNOWLEDGE SHARING AEP mountaineer project (2)CCS Front End Engineering and Design ReportThe front-end engineering and design package included: a +/- 25% cost estimate (see table below) all information needed Environmental Policy ACT a construction contracting strategy preliminary PFDs and mass and energy balances a deep well drilling program for characterization of subsurface geology at one ofthe CO2 storage sitesSystem (Phases I, II & III) Estimate ($ x million) USDCapture System $665Storage System $160Sub-Total $825Escalation $71Sub-Total $896Risk Based Contingency $103Total Constructed $999Phase IV Operations $66Total Project Cost $1,065AEP has put the project on hold as a lack offederal climate change legislation adverselyimpacting AEPs ability to fund its cost shareof the commercial scale project.
  • 14. PROJECT KNOWLEDGE SHARING ROAD project (Netherlands) (1)14PROJECT DETAILSLocation: Rotterdam, NetherlandsStatus: DefineProponent: Maasvlakte CCS Project C.V., a joint venture of E.ON Beneluxand Electrabel (a subsidiary of GDF Suez Group)Technical aspects Construction of a new E.ON Maasvlakte Power Plant 3 (MPP3), a 1070 MW (gross) coal-and biomass-based power plant. Retrofit of post-combustion capture is being designed on a 250 Mwe unit of the plant,capturing approx 1.1 million tonnes of CO2 per annum. The captured CO2 will be transported through a 26 km pipeline to the P-18-A Platform ofTAQA in the North Sea and injected into depleted gas reservoirs at a depth of 3500 metresunder the sea bed. The project has obtained all necessary permits and concluded all its costing and technicaldesign work FID is expected later this year.
  • 15. PROJECT KNOWLEDGE SHARING ROAD project (Netherlands) (2)15PERMITTING PROCESS REPORT A large number of permits required for all aspects of the CCS chain Obtaining a storage permit was most challenging issue for the project Key issues for the storage permit relate to the: Amount of information requested by the permitting authority Financial Security (funds needed for post-closure activities) Transfer of responsibility and liability
  • 16. PROJECT KNOWLEDGE SHARING Project Pioneer (Canada) (1)16TransAlta announced the cancellation of this project on the 26th of April 2012, on the groundsthat "the revenue from carbon sales and the price of emissions reductions [were] insufficient toallow the project to proceed at this time".KEY ASPECTS OF PROJECT PIONEER The project was built as a retrofit of TransAlta and Capital Power Corporations Keephills 3(K3) coal-based power plant Pioneer would have captured one million tonnes per annum of carbon dioxide (CO2)through post-combustion technology (MHI). The CO2 was to be transported for enhanced oil recovery (EOR) in nearby oil fields as wellas for permanent storage in deep saline formations.REPORTS AND OUTCOMESKnowledge sharing reports cover a wide range of topics including: regulatory, project risk,socio-economic, public opinion, construction execution, commercial structuring, CCSintegration, risk management, and MMV technology issues.
  • 17. PROJECT KNOWLEDGE SHARING Project Pioneer (Canada) (2)17SYSTEMS INTEGRATION WORKSHOP SUMMARY REPORTWhen integrating the capture facility into the host plant the following design features canimprove the efficiency and performance: Integration of utilities Integration of (environmental) monitoring and control systems Optimization of energy/heat recovery and use Waste minim