7th street and arizona avenue wqarf site community advisory board meeting february...
TRANSCRIPT
7th Street and Arizona Avenue WQARF SiteCommunity Advisory Board Meeting
February 27, 2018
7th Street and Arizona Avenue WQARF Site Project Update: 4th
Quarter 2017 Groundwater Monitoring, Early Response Action & Goals for Fiscal Year 2018
WQARF PROCESS OVERVIEW
4th Quarter 2017 Groundwater Monitoring
Groundwater Elevation -Perched Aquifer Measured water levels
from 43 monitoring wells (MWs)
Light non-aqueous phase liquid (LNAPL) observed in 10 MWs (~0.01 to 7.43 feet [ft] thick)
General flow to northwest
PERCHED AQUIFER
4th Quarter 2017 Groundwater Monitoring
Groundwater Elevation–Regional Aquifer Measured water levels
from 4 MWs. General flow to northwest
REGIONAL AQUIFER
4th Quarter 2017 Groundwater Monitoring
Water Quality Sampled 32 wells
– 20 Perched MWs w/o LNAPL– 8 Perched MWs w LNAPL– 4 Regional MWs
Perched w/o LNAPL: Tetrachloroethene (PCE) in groundwater in 7 MWs from 2.2 to 1,300 micrograms per liter (ug/l)
Perched w/ LNAPL: PCE in LNAPL in 2 MWs from 64,000 to 81,000 ug/l
Regional: PCE in groundwater in 1 MW 0.74 to 7.3 ug/l
PERCHED AQUIFER
4th Quarter 2017 Groundwater Monitoring
PERCHED AQUIFER
Water Quality PCE plume smaller in size
since 2013 Highest PCE dissolved in
LNAPL (64,000 to 81,000 ug/l)
Next highest under 847 N. Stone Ave (1,300 ug/L)
PCE in regional aquifer at 7AZR-3 from 0.74 to 7.3 ug/l
Early Response Action – Soil Vapor Extraction (SVE)
Soil Vapor Extraction (SVE) System Construction Installed 4 triple nested wells Completed ~200 ft. of trenching
and lateral well connection to SVE system
Sited, plumbed and powered blower/motor package
Sited and plumbed 2 granular activated carbon vessels
Early Response Action - SVE wells being drilled (low-clearance rig)
Early Response Action – Completed SVE wells
Early Response Action – Trenching for well connection to system
Early Response Action – Trenching for well connection to system
Early Response Action – SVE well manifold
Early Response Action – Blower/motor package
Early Response Action – Granular activated carbon
Early Response Action – Completed system
Looking SE
Looking NE
Early Response Action - SVE operation
Operation Summary System startup on Dec 5th, 2017 Approximately 832 lbs. of PCE cleaned up as of Feb 21, 2018
0
100
200
300
400
500
600
700
800
900
Cumulative PCE Mass Removed (lbs)
Cum
ulat
ive
PCE
(lbs)
Date
Remaining Goals For Fiscal Year 2018
Continue SVE operation Install one regional and one perched aquifer monitoring
well down gradient of 847 N. Stone Ave source
Early Response Action - SVE operation
QUESTIONS?
Park – Euclid WQARF SiteCommunity Advisory Board MeetingFebruary 27, 2018
Feasibility Study Update
• Draft Feasibility Study Report submitted on April 28, 2016
• No comments received during 30-day public commentperiod
• Comments from ADEQ received on December 15, 2016and February 27, 2017
• Final Feasibility Study Report submitted on October 18,2017
• Final Approval from ADEQ received on November 14,2017
Park – Euclid Status Update Page 2
Site Conceptual Model
Park – Euclid Status Update Page 3
Feasibility Study Proposed Remedy
• Upper Vadose Zone: Monitored Natural Attenuation untilYear 15
• Perched Aquifer: Monitored Natural Attenuation for 30years
• Lower Vadose Zone: Continuous soil vapor extraction for 5years with expanded monitoring until Year 25
• Regional Aquifer: Pumping with a single extraction well at50 gallons per minute with granular activated carbontreatment prior to reinjecting to the RA for 30 years,followed by monitoring until Year 35.
Park – Euclid Status Update Page 4
Site Conditions Update
Park – Euclid Status Update Page 5
Perched Aquifer Diesel Product
Park – Euclid Status Update Page 6
Site Conditions Update (continued)
Perched Aquifer Vinyl Chloride in Groundwater
Park – Euclid Status Update Page 7
Site Conditions Update (continued)
Regional Aquifer PCE in Groundwater
Park – Euclid Status Update Page 8
Remedial Design Refinement
Perched Aquifer - Five new monitoring wells for plumerefinement and downgradient extent
Remedial Design Refinement (continued)
Park – Euclid Status Update Page 9
Lower Vadose Zone – Four vapor monitoring well clusters to evaluatevertical and horizontal extent and for SVE system performance monitoring
Park – Euclid Status Update Page 10
Remedial Design Refinement (continued)
Regional Aquifer – Three monitoring wells for deep plume extent
Lower Vadose Zone Early Response Action
Park – Euclid Status Update Page 11
Lower Vadose Zone Early Response Action (continued)
Park – Euclid Status Update Page 12
– PCE concentrations in extracted vapor decreased throughout operation– Gasoline range Fuel Hydrocarbons increased/remained stable
Lower Vadose Zone Early Response Action (continued)
• Rationale for Restarting the SVE System now– Groundwater elevations increasing and may saturate contaminated
intervals making it more difficult and expensive to clean up later– PCE concentrations were still declining at shutdown– Rebounding PCE and TCE concentrations in vapor extraction well– Increasing dissolved PCE and TCE in groundwater during rebound
monitoring
• Change vapor treatment from GAC to Catalytic Oxidizer
• Operate as ERA for up to 3 years.
Park – Euclid Status Update Page 13
Proposed Remedial Action Plan
Park – Euclid Status Update Page 14
• PRAP development to begin after remedial designrefinement
• PRAP document to include– Boundaries of the site subject to remedial action– Results of remedial investigation and feasibility study– The proposed remedy and its estimated costs– How remediation goals and selection factors in § 49-282.06 have
been considered
• As part of the PRAP, a 60 percent design of the remedywill be completed to support the cost estimate.
Major Task Schedule
• Access Agreements (11/15/17 – 3/14/18)
• Remedial Design Refinement (2/1/18 - 8/1/18)
• Prepare and Issue PRAP (6/21/18 – 1/30/19)
• Catalytic Oxidizer Design and Permitting (2/15/18 – 9/22/18)
• CatOx Equipment Procurement and Installation (9/24/18 - 12/14/18)
• SVE/CatOx Operation, Maintenance, and Monitoring (12/14/18 –12/27/19)
• Long Term Monitoring (ongoing semi-annual/annual monitoring andreporting)
Park – Euclid Status Update Page 15
www.aecom.com
Stone Avenue and Grant Road WQARF Site
February 27, 2018 CAB MeetingWilliam Ellett, Associate Hydrogeologist/Project Manager
Stone and Grant WQARF Site Location
Nash Elementary
Site History
Former dry cleaner operated from 1946 to mid 1970’s.
Automotive Paint Specialists took over the building in mid 1070’s.
Building is currently occupied by Finishmaster, Inc.
Leaking Underground Storage Tank (LUST) gasoline release on north side of Grant Rd.
The City of Tucson completed a Phase I Environmental Assessment and sub-slab soil-gas sampling in 2014.
Site History continued
Site History continued
Site History continued
ADEQ completed Preliminary Investigation in February 2016.
Proposed for WQARF listing in May 2016.
Listed on WQARF Registry in January 2017.
Began Early Response Action (ERA) in April 2017 with Geosyntec Consultants.
Completed Community Involvement Plan and began Remedial Investigation in August 2017 with Clear Creek Associates.
ERA Shallow Soil-Gas Survey
ERA Angled Soil-gas Profile and SVE Well
ERA/SVE System Layout
Completed SVE System
SVE System Mass Removal
Remedial Investigation – Regional GW Wells
SG-2
SG-1
SG-4
SG-3
Drilling a Monitoring Well at Stone & Grant
Surface Completion for New Well
Shallow Soil-Gas Survey at Former Home Laundry and Dry Cleaning
Northwest of Finishmasters in Grant-Stone shopping center.
Investigated to see if there was an additional source of contamination for the Stone and Grant WQARF site.
Collected four shallow soil-gas samples outside former dry cleaner suite.
Results indicated a possible vapor intrusion issue for TCE and PCE.
Indoor air samples were taken that showed no TCE and PCE only slightly above residential screening level.
Plan to take indoor samples again in June to show any seasonal variation.
Site looks like it is separate from Stone and Grant Site, so it is now a new Preliminary Investigation site.
Future Plans
Conduct a thorough evaluation of data from the LUST site and all data collected so far for the Remedial Investigation by March 31.
Collect soil-gas data from shallow GW wells.
Collect any other data needed to fill data gaps.
Write draft Remedial Investigation by June 30 if possible.
Proceed to Feasibility Study.