7581-pwg-fiq rev0
TRANSCRIPT
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for
Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 1 of 44
Factory Installation Qualification (FIQ)
For the
Purified Water System
(Genesys Purified Water Generation Unit)
For
Deltaflex SDN BHD
At
N.A.Z Medical Supplies SDN, BHD
Author Job Title Name Signature Date
Puretech Process
Systems Ltd
Process
Engineer Lynne Haines
Reviewed By Job Title Name Signature Date
Puretech Process
Systems Ltd
Development
Director John Parks
Approved By Job Title Name Signature Date
Puretech Process
Systems Ltd Project Manager Dean Sanders
The following approvals must be completed prior to commencement of work detailed within this
document. Approval shows acceptance of this document.
Approval Company Job Title Name Signature Date
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for
Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 2 of 44
Revision Status:
Issue Date Description
P1 30 April 2010 Initial issue for internal review
0 13 May 2010 Internal comments incorporated, document issued for Client
review
Revision History
Issue Date Description
P1 30 April 2010 Initial issue for internal review
0 13 May 2010 Internal comments incorporated, document issued for Client
review
This document contains proprietary information belonging to Puretech Process Systems Ltd and shall
be used only for the purpose for which it was supplied. It shall not be copied reproduced or otherwise
used, nor shall such information be furnished in whole or in part to others.
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for
Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 3 of 44
Contents Page No.
1. Identification of Personnel ................................................................................................5
2. Introduction........................................................................................................................6
3. Objectives ...........................................................................................................................7
4. Responsibilities of Puretech ..............................................................................................7
4.1. Responsibilities of Person Executing Qualification ............................................................7
5. Equipment Description......................................................................................................8
5.1. Process Overview.................................................................................................................8
5.2. Materials of Construction ....................................................................................................8
5.3. System Scope .......................................................................................................................8
5.4. Connected Utilities ............................................................................................................10
5.5. Instrumentation ..................................................................................................................10
6. Associated Documentation ..............................................................................................12
6.1. Specifications.....................................................................................................................12
6.2. Maintenance Documentation .............................................................................................12
6.3. Procedures..........................................................................................................................12
6.4. Drawings ............................................................................................................................13
6.5. Engineering Data Book......................................................................................................13
7. Documentation Checks....................................................................................................14
7.1. Principal Components........................................................................................................14
7.2. Pipework and Line Fittings ................................................................................................16
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for
Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 4 of 44
7.3. Instruments.........................................................................................................................19
8. Installation Checks ..........................................................................................................21
8.1. Principal Components........................................................................................................21
8.2. P&ID Check (inc. Inline Items/Instruments) .....................................................................32
8.3. Electrical Checks ...............................................................................................................34
9. Instrument Calibration Certificate Check ....................................................................35
10. Non-Conformance List ....................................................................................................38
11. Results ...............................................................................................................................39
12. Conclusion ........................................................................................................................39
13. Interim Approvals............................................................................................................40
14. Final Approvals................................................................................................................40
15. Further Actions ................................................................................................................41
16. Appendices........................................................................................................................42
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for
Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 5 of 44
1. Identification of Personnel
In the table below enter details of the people involved in the execution of the Factory Installation
Qualification:
Personnel
Signatures Company/
Department Name
Sign Initial Date
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for
Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 6 of 44
2. Introduction
This is the Factory Installation Qualification (FIQ) of the Genesys Purified Water Generation Unit for
installation as part of the Highly Purified Water System for Deltaflex SDN BHD installed at N.A.Z
Medical Supplies SDN BHD.
The purpose of this FIQ is to document the Genesys Purified Water Generation Unit factory tests and to
reduce the scope of the site based Installation (IQ) so that only site specific testing is needed. The FIQ
will provide support to the site IQ activities.
The testing of the Genesys Purified Water Generation Unit will be carried out in 3 sections
Section 1: Factory Installation Qualification tests (FIQ)
Section 2: Factory Acceptance Test Specification (FAT2)
Section 3: Factory Operation Qualification tests (FOQ)
Note: Electrical Panel Testing (FAT1) and Hardware Acceptance Testing (HAT1) will have been
carried out prior the FIQ.
This document should be read in conjunction with the following Genesys Purified Water Generation
Unit documents:-
Genesys Purified Water Generation Unit P&ID ref 7581-X-0002
Genesys Purified Water Generation Unit FDS ref 7581-PWG-FDS
Genesys Purified Water Generation Unit Valve Schedule ref 7581-S-2001
Genesys Purified Water Generation Unit Equipment Schedule ref 7581-S-2002
Genesys Purified Water Generation Unit Instrument Schedule ref 7581-S-2003
Additional Evidence
In the event of testing being executed, where the engineer is required to attach additional sheets to the
test sheet, the following procedure should be followed:
• All additional sheets will have the test document reference and test number written at the
top right hand corner.
• An appendix number is taken from the appendix log (section 16)
• All additional sheets will have the appendix number, the page number and total number
of additional pages.
• All additional sheets will be signed and dated by the engineer.
• All additional sheets will be filed as an appendix, and the appendix log completed.
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for
Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 7 of 44
3. Objectives
The objectives of the Factory Installation Qualification for the Genesys Purified Water Generation Unit
are:-
• To provide documented evidence to demonstrate that all key aspects of installation (that can
be tested in the factory) adhere to client requirements and design intentions.
• To provide a summary of the test results with a conclusion and recommendations where
appropriate.
4. Responsibilities of Puretech
4.1. Responsibilities of Person Executing Qualification
• Ensuring that this document is fully approved and signed prior to starting the FIQ.
• Executing the FIQ in accordance with the Qualification.
• Recording the results of FIQ and any relevant comments in the FIQ document and its
appendices.
• Recording deviations discovered during execution of the Qualification in the non-
conformance section of this document.
Note, a resolution of non-conformances must be made by all parties.
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for
Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 8 of 44
5. Equipment Description
5.1. Process Overview
The Genesys Purified Water Generation Unit is designed to generate 3,000 l/hr purified water which as
a minimum will meet the Highly Purified Water requirements of the European Pharmacopeia (EP).
Parameter Specifiation
Appearance A clear colourless liquid
Conductivity < 1.1 µS/cm at 20°C
Total Organic Carbon < 500 ppb as C
Nitrates < 0.2 ppm
Babterial Endotoxins < 0.25 EU/ml
Total viable count < 10 CFU/100 ml
5.2. Materials of Construction
Wetted materials used on the Genesys Purified Water Generation Unit will be 316 stainless steel. Pre-
RO unit the material will be 316 descaled ID dairy tube, post RO will be pharmaceutical grade 316L
tube with internal finish mechanically polished to 0.5µm Ra. Valves post RO will be 316L
mechanically polished to 0.5µm Ra. Wetted/contact surfaces will be passivated. Valve diaphragm
material and tri-clover seals in contact with the purified water will be PTFE/EPDM (FDA compliant).
Permanent jointing of pipework will be closed head orbitally TIG welded, the number of manual welds
will be minimised. Weld samples, procedures, approvals and weld logs will be provided.
5.3. System Scope
The Genesys Purified Water Generation Unit is fed from a pretreated water supply. The Genesys
Purified Water Generation Unit is sized to feed 3,000l/hr to a Purified Water Storage Tank (TK201
supplied by Deltaflex) for distribution.
The Genesys Purified Water Generation Unit will comprise of a number of purification stages utilising
proprietary water purification equipment, the system will be operated from a central control panel
(CP01). The Genesys Purified Water Generation Unit will automatically fill the Purified Water Storage
Tank (TK201) when demanded and recirculate back to the Genesys Feed Water Storage Tank (TK01)
when the Purified Water Storage Tank is full, via valves V18 and V19 (valves free issued to Deltaflex
for installation) which are controlled by the Genesys, via volt free fill request signals from the
Distribution System.
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for
Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 9 of 44
The Genesys Purified Water Generation Unit comprises of the following main items of equipment:-
5 Micron Particulate Filter FH01
Feed Water Storage Tank TK01
RO Booster Pump PU01
Reverse Osmosis Units ROH01/02 (ROE01-ROE04)
Degasser DG01
Continuous Electro Deioniser CEDIA
Ultra Filtration Units UF01/02
The Genesys Purified Water Generation Unit will have 3 modes of operation, which will be selected via
the HMI on the Genesys Purified Water Generation Unit Control Panel (CP01)
• Normal Operation Mode
• Hot Water Sanitisation Mode
• CIP Mode
o CIP1 (RO Low Pressure Clean Sequence)
o CIP2 (RO High Pressure Clean Sequence)
o CEDI Clean Sequence
The Genesys Purified Water Generation Unit Control System will also interface with the following
panels:-
• PWD System Control Panel (CP201)
A complete description of the main control functions associated with the system is presented in the
following document:-
Genesys Purified Water Generation Unit Functional Design Specification 7581-PWG-FDS.
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for
Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 10 of 44
5.4. Connected Utilities
Utility Parameter Details Use
Pretreated Feed Water
Flowrate: 4,800 l/hr
Pressure: 2-6 barg
PH:6.5 - 9.0
Conductivity:<1000 µS/cm
Total Hardness:<5.0 ppm as CaC03
SDI:<5
Chlorine:<0.1 ppm
Temperature:≤ 20-25°C
Supply to Feed Water Storage
Tank TK01
Power 380V 3ph 50Hz Neutral + Earth, 63Amp Power to Genesys Control Panel
(CP01)
Instrument Air 50 l/min @ 6-7 barg Instrument Air to Genesys
Pneumatic Panel (CP02)
5.5. Instrumentation
In summary the system comprises of the following main instrument items:-
Inst Ref Parameter Monitored Function
PI01 Pre 5 Micron Particulate Filter
FH01 Local Indication
PI02 Post 5 Micron Particulate Filter
FH01 Local Indication
CL01/TT05 ORP (Chlorine)/Temperature Feedwater Chlorine/Temperature
Monitoring, Indication and Alarms
LT01 Feed Water Storage Tank Level Level Control with Indication and
Alarms
CT01/TT01 Feed Water Storage Tank Outlet
Conductivity and Temperature
Conductivity/Temp Monitoring,
Indication and Alarms
PT01 RO Feed Pressure Pressure Monitoring, Indication and
Alarms
CT02/TT02 RO Permeate Conductivity and
Temperature
Conductivity/Temp Monitoring,
Indication and Alarms
FT01 Primary RO Permeate Flowrate Flow Monitoring, Indication and
Alarms
PT03 CEDIA Dilute Feed Pressure Pressure Monitoring, Indication and
Alarms
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for
Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 11 of 44
Inst Ref Parameter Monitored Function
FT04A CEDIA Concentrate Flowrate Flow Monitoring, Indication and
Alarms
PT04A CEDIA Concentrate Feed Pressure Pressure Monitoring, Indication and
Alarms
PI04 CEDIA Concentrate to Drain Pressure Local Indication
PT05 CEDIA Dilute Outlet Pressure Pressure Monitoring, Indication and
Alarms
CT03/TT03 Final Product Quality/Temperature Conductivity/Temp Monitoring,
Indication and Alarms
TT04 Purified Water Return Temperature Temperature Monitoring, Indication
and Alarms
FT06 UF Retentate Flow Flow Monitoring, Indication and
Alarms
PT02 Primary RO Reject Pressure Pressure Monitoring, Indication and
Alarms
FT02 Primary RO Reject Drain Flowrate Flow Monitoring, Indication and
Alarms
FT03 Primary RO Reject to Recycle Flowrate Flow Monitoring, Indication and
Alarms
TT06 Primary RO Reject Drain Temperature Temperature Monitoring, Indication
and Alarms
FR01 Instrument Air Pressure to CP02 Local Indication
FR02 Instrument Air Pressure to Degasser
from CP02 Local Indication
FI01 Instrument Air Flow to Degasser from
CP02 Local Indication
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for
Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 12 of 44
6. Associated Documentation
Confirm that the following documentation is available for the Genesys Purified Water Generation Unit.
6.1. Specifications
Document Title Document Reference Rev Signed Date
Functional Design
Specification
7581-PWG-FDS
Genesys, O&M Manual ref
7581-PWG-O&M Book 1Section )
Genesys Valve
Schedule
7581-S-2001
Genesys, O&M Manual ref
7581-PWG-O&M Book 1Section )
Genesys Equipment
Schedule
7581-S-2002
Genesys, O&M Manual ref
7581-PWG-O&M Book 1Section )
Genesys Instrument
Schedule
7581-S-2003
Genesys, O&M Manual ref
7581-PWG-O&M Book 1Section )
Purified Water
Systems Utility
Schedule
7581-S-1004
Genesys, O&M Manual ref
7581-PWG-O&M Book 1Section )
6.2. Maintenance Documentation
Document Title Document Reference Signed Date
Manufacturer’s Technical
Information
Genesys, O&M Manual ref
7581-PWG-O&M Books 3 & 4
Spare Parts List Genesys, O&M Manual ref
7581-PWG-O&M Book 1
6.3. Procedures
Document Title Document Reference Signed Date
System Operating
Description/Sanitisation Procedure
Genesys, O&M Manual ref
7581-PWG-O&M Book 1
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for
Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 13 of 44
6.4. Drawings
Drawing Title Drawing No. Rev Location Signed Date
P&I D –Genesys Purified
Water Generation Unit 7581-X-0002
Genesys, O&M
Manual ref
7581-PWG-O&M
Book 1
6.5. Engineering Data Book
Document Title Document Reference Signed Date
Engineering Data Book 7581-PWG-EDB
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD
Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 14 of 44
7. Documentation Checks
7.1. Principal Components
The following plant items are included in the documentation checks of this qualification:
Acceptance Criteria: Signing the box confirms all the required documents for a given plant item are compiled in the supporting document file.
Material/Surface
Finish Certs:
Material Conformity Certificates, including seals and gaskets, surface finish certificates (refer to engineering data book section 11)
Test Certs: Test and Performance Certificates including pressure tests, manufacturer’s PED certification (refer to engineering data book section
11)
O&M Manuals: Operational and Maintenance Manuals
Tag
Number Description
Material/
Surface Finish
Certs
Test Certs O&M Manuals Comments Accepted
Yes/No Initial
FH01 5 Micron Particulate
Filter Not Required Not Required Book 3 Section 1.0
TK01 Feed Water Storage
Tank Not Required Water Fill Book 3 Section 2.0
SB01 TK01 Sprayball Not Required Not Required Book 3 Section 2.0
HT01 Feed Water Storage
Tank Heater Not Required Not Required Book 3 Section 3.0
Note 1
PU01 RO Booster Pump Not Required Not Required Book 3 Section 4.0
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD
Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 15 of 44
Tag
Number Description
Material/
Surface Finish
Certs
Test Certs O&M Manuals Comments Accepted
Yes/No Initial
ROH01/
02
Reverse Osmosis
Housings
Material
Certificates only Required Book 3 Section 5.0
ROE01/
04
Reverse Osmosis
Elements
Certificate of
Conformity Not Required Book 3 Section 6.0
DG01 Degasser Certificate of
Conformity
Not
Applicable Book 3 Section 7.0
CEDIA Continuous Electro
Deioniser
Certificate of
Conformity
Not
Available Book 3 Section 8.0
UF01/02 Ultrafilter Units Certificate of
Conformity Required Book 3 Section 9.0
Inspection Report Provided
GS01 Gas Separator Not Required Not Required Book 3 Section 10.0
Notes
1. Pressure test certificate available in the Engineering Data Book Section 11
Tested by: Date: Witnessed by: Date:
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD
Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 16 of 44
7.2. Pipework and Line Fittings
The following pipework and line fittings are included in the documentation checks of this qualification.
Acceptance Criteria: Signing the box confirms that all the required documents for the given pipework and fittings are compiled in the supporting
document file.
Material/Surface
Finish Certs:
Material Conformity Certificates, including seals and gaskets, surface finish certificates (refer to engineering data book section 5)
Valve Material/
Surface Finish
Valve Conformity Certificates, including diaphragms and seals, surface finish certificates (refer to engineering data book - section
12)
Weld Log: Weld Log Sheets, Weld Log Isometrics, Weld Procedures and Welder Approvals (refer to engineering data book sections 1 – 4)
NDT: Boroscopy (refer to engineering data book section 9)
Pressure Test
Certs:
Pressure Test Certificate –Pink copies will be attached as appendix to the FIQ (refer to engineering data book section 7)
Passivation
Certs:
Passivation Certificate (refer to engineering data book section 8)
Line
Terminations
Material/
Surface
Finish Certs
Valve
Material/
Surface
Finish
Weld Log NDT Pressure
Test Cert
Passivation
Cert Comments
Accepted
Yes/No Initial
TP01 to TK01
and TP04
Not
Required
Not
Required
Not
Required
Not
Required Required Required
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD
Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 17 of 44
Line
Terminations
Material/
Surface
Finish Certs
Valve
Material/
Surface
Finish
Weld Log NDT Pressure
Test Cert
Passivation
Cert Comments
Accepted
Yes/No Initial
TK01 to PU01 Not
Required
Not
Required
Not
Required
Not
Required Required Required
PU01 to
ROH01/02
Not
Required
Not
Required
Not
Required
Not
Required Required Required
ROH01/02 to
DG01 Required Required Required Required Required Required
DG01 to CEDIA Required Required Required Required Required Required
CEDIA to
UF01/02 Required Required Required Required Required Required
UF01/02 to TP02 Required Required Required Required Required Required
TP04 to TK01 Required Required Required Required Required Required
ROH01/02 to
TK01, V06 and
Drain
Not
Required
Not
Required
Not
Required
Not
Required Required Required
CEDIA to GS01 Not
Required
Not
Required
Not
Required
Not
Required Required Required
GS01 Vent/Drain
Line
Not
Required
Not
Required
Not
Required
Not
Required
Not
Required
Not
Required
GS01 to TK01 Not
Required
Not
Required
Not
Required
Not
Required Required Required
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD
Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 18 of 44
Line
Terminations
Material/
Surface
Finish Certs
Valve
Material/
Surface
Finish
Weld Log NDT Pressure
Test Cert
Passivation
Cert Comments
Accepted
Yes/No Initial
UF01/02 to TK01 Not
Required
Not
Required
Not
Required
Not
Required Required Required
TK01 Vent Line Not
Required
Not
Required
Not
Required
Not
Required
Not
Required
Not
Required
Drains to TP07 Not
Required
Not
Required
Not
Required
Not
Required
Not
Required
Not
Required
TP07 to Drain
Gulley
Not
Required
Not
Required
Not
Required
Not
Required
Not
Required
Not
Required
By Deltaflex - To be carried out
as part of SAT (7581-PWG-IQ)
Notes
Tested by: Date: Witnessed by: Date:
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD
Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 19 of 44
7.3. Instruments
The following instruments are included in the documentation checks of this qualification. (For calibration refer to section 9 of this document)
Acceptance Criteria: Signing the box confirms that all the required documents, for a given plant item, are compiled in the supporting document
file.
Material Certs : Material Conformity Certificates (refer to engineering data book section 10)
Fill Fluid : Food Grade Fill Fluid (refer to engineering data book section 10)
Tag Number Description Material
Certs Fill Fluid Comments
Accepted
Yes/No Initial
CT02/TT02 RO Permeate
Quality/Temperature Required N/A
FT01 RO Permeate Flowrate Required N/A
PT03 CEDIA Dilute Feed Pressure Required Required
FT04A CEDIA Concentrate Flowrate Required N/A
PT04A CEDIA Concentrate Feed
Pressure Required Required
PT05 CEDIA Dilute Outlet Pressure Required Required
CT03/TT03 Final Product
Quality/Temperature Required N/A
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD
Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 20 of 44
Tag Number Description Material
Certs Fill Fluid Comments
Accepted
Yes/No Initial
TT04 Purified Water Return
Temperature Required N/A
Notes
Tested by: Date: Witnessed by: Date:
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for
Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD
Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 21 of 44
8. Installation Checks
8.1. Principal Components
Inspect the principal components of the equipment to confirm they are as specified in the equipment
data sheet, installed correctly inline with the Manufacturer’s Technical Specification and accurately
documented on the individual checklists.
Tag Number. Principal Component Data Sheet Number Rev. No.
FH01 5 Micron Particulate Filter DS-7581-001
TK01 Feed Water Storage Tank DS-7581-002
HT01 Feed Water Storage Tank Heater DS-7581-003
PU01 RO Booster Pump DS-7581-004
ROH01/02
ROE01/04 Reverse Osmosis Units DS-7581-005 & 006
DG01 Degasser DS-7581-007
CEDIA Continuous Electro Deioniser DS-7581-008
UF01/02 Ultrafilter Units DS-7581-009
GS01 Gas Separator Unit DS-7581-010
CP01 Genesys Control Panel 7581-PWG-FDS
CP02 Genesys Pneumatic Panel Not Applicable
Completed by: Date:
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for
Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD
Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 22 of 44
5 Micron Particulate Filter Checklist FH01
Check List Items Comments Accepted
Yes/No Initial
Check conformation to P&ID 7581-
X-0002 and equipment data sheet ref:
DS-7581-001
Check filter vent and drains are fitted
Check plant tag number is on the
filter housing and is correct and
legible
Check nameplate is present and all
details are correct
Check process inlet and discharge
pipework is correctly connected and
aligned
Check no visual damage
Confirm correct filter element is
installed
Write the serial number in the
comments column
Tested by: Date:
Witnessed by: Date:
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for
Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD
Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 23 of 44
Feed Water Storage Tank TK01 Checklist
Check List Items Comments Accepted
Yes/No Initial
Check conformation to P&ID 7581-
X-0002 and equipment data sheet ref:
DS-7581-002
Check Nameplate is fitted and all
details correct
Check plant tag number is fitted and
is correct and legible
Check no visual damage
Write the serial number in the
comments column
Check sprayball SB01 fitted
Check for cleanliness internally and
externally ie visually inspect to
confirm that all fabrication marks
and dirt etc have been cleaned
off/out.
Tested by: Date:
Witnessed by: Date:
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for
Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD
Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 24 of 44
Tank Heater Checklist HT01
Check List Items Comments Accepted
Yes/No Initial
Check conformation to P&ID 7581-
X-0002 and equipment data sheet ref:
DS-7581-003
Check plant tag number is fitted and
is correct and legible
Check no visual damage
Check Nameplate is fitted and all
details correct
Check heater is installed correctly
onto flange mounting.
Write serial number in comments
Tested by: Date:
Witnessed by: Date:
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for
Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD
Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 25 of 44
RO Booster Pump Checklist PU01
Check List Items Comments Accepted
Yes/No Initial
Check conformation to P&ID 7581-
X-0002 and equipment data sheet ref:
DS-7581-004
Check nameplate is fitted and
contains CE mark and data/rating
information
Check plant tag number is on the
pump and is correct and legible
Check no visual damage
Write the serial number in the
comments column
Check all securing bolts are in place
Check pump can be removed for
maintenance
Check for cleanliness
Tested by: Date:
Witnessed by: Date:
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for
Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD
Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 26 of 44
Reverse Osmosis Units Checklist ROH01-02 (ROE01-04)
Check List Items Comments Accepted
Yes/No Initial
Check conformation to P&ID 7581-
X-0002 and equipment data sheet ref:
DS-7581-005 & 006
Check plant tag number is fitted and
is correct and legible
Check Nameplate is fitted and all
details correct
Check no visual damage
Write the manufacturing numbers in
the comments column
Confirm correct RO membranes are
installed (see sketch below)
Check for ease of
maintenance/removal of membranes
ROE04 Serial:- ROE03 Serial:-
ROE01 Serial:- ROE02 Serial:-
PU01
Tested by: Date:
Witnessed by: Date:
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for
Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD
Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 27 of 44
Degasser Checklist DG01
Check List Items Comments Accepted
Yes/No Initial
Check conformation to P&ID 7581-
X-0002 and equipment data sheet ref:
DS-7581-007
Check plant tag number is fitted and
is correct and legible
Check Identification Nameplate is
present and all details correct
Check no visual damage
Write the serial number in the
comments column
Tested by: Date:
Witnessed by: Date:
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for
Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD
Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 28 of 44
Continuous Electro Deioniser Checklist CEDIA
Check List Items Comments Accepted
Yes/No Initial
Check conformation to P&ID 7581-
X-0002 and equipment data sheet ref:
DS-7581-008
Check plant tag number is fitted and
is correct and legible
Check model reference nameplate
and CE mark is present
Check no visual damage
Write the serial number in the
comments column
Check for ease of maintenance
Check the unit is adequately earthed
Tested by: Date:
Witnessed by: Date:
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for
Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD
Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 29 of 44
Ultra filtration Units Checklist UF01/02
Check List Items Comments Accepted
Yes/No Initial
Check conformation to P&ID 7581-
X-0002 and equipment data sheet ref:
DS-7581-009
Check plant tag numbers are on the
UF and is correct and legible
Check identification stickers are
present and details are correct
Check no visual damage exists
Write the serial numbers in the
comments column
Tested by: Date:
Witnessed by: Date:
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for
Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD
Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 30 of 44
Gas Separator Checklist GS01
Check List Items Comments Accepted
Yes/No Initial
Check conformation to P&ID 7581-
X-0002 and equipment data sheet ref:
DS-7581-010
Check plant tag number is fitted and
is correct and legible
Check no visual damage
Check model reference nameplate is
present and details are correct
Check inlet and discharge pipework
is correctly connected.
Write the identification number in
the comments column
Tested by: Date:
Witnessed by: Date:
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for
Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD
Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 31 of 44
Genesys Control Panel Checklist CP01
Check List Items Comments Accepted
Yes/No Initial
Check conformation to electrical
panel front drawing 7581-PWG-020
Note complete panel checks will be
carried out as part of HATS
Check plant tag number is fitted and
is correct and legible
Check no visual damage
Write installed software version
number in comments
Genesys Pneumatic Panel Checklist CP02
Check List Items Comments Accepted
Yes/No Initial
Check conformation to pneumatic
panel front drawing 7581-PWG-035
Note complete panel checks will be
carried out as part of HATS
Check plant tag number is fitted and
is correct and legible
Check no visual damage
Tested by: Date:
Witnessed by: Date:
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for
Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD
Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 32 of 44
8.2. P&ID Check (inc. Inline Items/Instruments)
The following equipment, instruments, pipework and line fittings are to be checked to provide
assurance of:-
a. Tagging
b. Adequate support
c. Pipework route is correct, see P&ID acceptance criteria below
d. Pipe connections to equipment appear free from stress
e. Materials match specification
f. Pipeline is complete with all blank flanges, restrictor plates, valves, instruments
etc present
g. Notes on P&ID correctly incorporated
h. Valves and instruments installed in correct orientation and no clashes
i. Adequate operating and maintenance access
j. Check deadlegs no longer than 3 times pipe diameter
Use the following P&ID’, Valve, Equipment and Instrument Schedules to check the installation:-
Doc Number Doc Title Rev.
Used Signature Date
7581-X-0002 Genesys Purified Water
Generation Unit P&ID
7581-S-2001 Genesys Valve Schedule
7581-S-2002 Genesys Equipment Schedule
7581-S-2003 Genesys Instrument Schedule
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for
Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD
Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 33 of 44
Acceptance Criteria:-
i. If the installation is satisfactory the lines on the P&ID and items on the Valve, Equipment
and Instrument Schedules will be coloured green.
ii. An incomplete or unsatisfactory part of the installation will be coloured yellow on the
P&ID, Valve, Equipment and Instrument Schedules, and the deficiencies listed in the non
conformance section of this FIQ.
iii. Each person who completes any part of the FIQ will sign and date the appropriate area on
the P&ID, Valve, Equipment and Instrument Schedules
iv. The coloured P&ID, Valve, Equipment and Instrument Schedules will form part of this
installation report and will be attached in the appendices section of this FIQ.
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for
Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD
Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 34 of 44
8.3. Electrical Checks
Electrical testing will be carried out independently (Hardware Acceptance Tests HATS) and does not
form part of this FIQ document.
Checks will be carried out to verify the electrical installation and the HATS document will be provided
which will include the following tests:-
a) Electrical Continuity
b) Electrical Insulation
c) Cable Segregation
d) Earth Bonding and Continuity
e) Tagging
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD
Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 35 of 44
9. Instrument Calibration Certificate Check
Acceptance Criteria: Signing the box confirms that the required calibration certification is compiled in the supporting document file.
Calibration Certs: Calibration Certificates (refer to engineering data book section 10)
Tag No. Instrument Manufacturer Range Serial No. Calibration
Certification Comment
Accepted
Yes/No Initial
PI01 Pre FH01 Pressure Wika 0-7 barg Not Provided
PI02 Post FH01 Pressure Wika 0-7 barg Not Provided
CL01/TT05 ORP (Chlorine) /Temp Endress+
Hauser 0-1500 mV Yes
Note 1
CT01/TT01
Feed Water Tank
Outlet Conductivity
and Temperature
Endress+
Hauser
0-2000µS/cm
and 0-
100degC
Yes
Note 2
PT01 RO Feed Pressure Endress+
Hauser 0 – 40 barg Yes
CT02/TT02
RO Permeate
Conductivity and
Temperature
Endress+
Hauser
0-50µS/cm
and 0-
100degC
Yes
Note 2
FT01 RO Permeate Flowrate Burkert 0 –6000 l/hr Yes Note 3
PT03 CEDIA Dilute Feed
Pressure
Endress+
Hauser 0 – 40 barg Yes
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD
Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 36 of 44
Tag No. Instrument Manufacturer Range Serial No. Calibration
Certification Comment
Accepted
Yes/No Initial
FT04A CEDIA Concentrate
Flowrate Burkert 0 –1000 l/hr Yes
Note 3
PT04A CEDIA Concentrate
pressure
Endress+
Hauser 0 – 40 barg Yes
PT05 CEDIA Dilute Outlet
Pressure
Endress+
Hauser 0 – 40 barg Yes
CT03/TT03 Final Product Quality/
Temperature
Endress+
Hauser
0-10µS/cm
and 0-
100degC
Yes
Note 2
TT04 Purified Water Return
Temperature
Endress+
Hauser 0 – 100 degC Yes
FT06 UF Retentate Flow Burkert 0 –1000 l/hr Note 3
PT02 RO Reject Pressure Endress+
Hauser 0 – 40 barg Yes
FT02 RO Reject Drain
Flowrate Burkert 0 –2000 l/hr Yes
Note 3
FT03 RO Reject to Recycle
Flowrate Burkert 0 –6000 l/hr Yes
Note 3
TT06 RO Reject Drain
Temperature
Endress+
Hauser 0 – 100 degC Yes
PI04 CEDI-A Concentrate to
Drain Wika 0-7 barg Not Provided
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD
Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 37 of 44
Tag No. Instrument Manufacturer Range Serial No. Calibration
Certification Comment
Accepted
Yes/No Initial
FR01
(Pressure
Gauge)
Instrument Air feed to
CP02 Festo 0-7 barg Not Applicable Not Provided
FR02
(Pressure
Gauge)
Instrument Air feed to
Degasser Festo 0-7 barg Not Applicable Not Provided
FI01 Instrument Air Flow to
Degasser
Blue White,
IPS 0.5-4.5SCFM Not Applicable Not Provided
Notes:
1 ORP sensor is supplied with manufacturers certificate. Calibration/ranging of instrument is carried out during commissioning/SAT.
2 Conductivity sensors are supplied with a quality certificate.
3 Flowmeters are supplied with a flow simulation test.
Tested by: Date:
Witnessed by: Date:
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for
Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD
Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 38 of 44
10. Non-Conformance List
On identifying a non-conformance the responsible person will raise a non-conformance report and
record the number below. The non-conformance will then be categorised and a recommended course of
remedial action discussed, agreed and recorded on the NCR (non-conformance report). A copy of the
open NCR will be appended to this Qualification.
Upon completion of the required actions, the responsible person will sign below to confirm that the
non-conformance is now closed. A copy of the closed NCR will be appended to this Qualification.
Categorise each non-conformance as follows:
Fail: A non-conformance which either has a direct effect on product quality or has the
potential to delay validation progress.
Refer: A non-conformance that has little or no GMP impact and will not prevent validation
progress.
Record all non-conformances in the table below, giving a brief description of the non-conformance and
detailing the person responsible for its resolution.
Non Conformance
Report Number
Description
Person
Responsible
Complete
Sign/Date
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for
Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD
Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 39 of 44
11. Results
Summarise below the results of the Factory Installation Qualification including reference to any non-
conformances and their category. Also make reference to any further actions required to complete the
Factory Installation Qualification exercise:
12. Conclusion
Summarise below the conclusion of the Factory Installation Qualification based on the results obtained.
Include a statement regarding the result of the exercise and recommendations for progress of the
validation exercise or further actions where required:
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for
Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD
Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 40 of 44
13. Interim Approvals
All non-conformance “fails” in the non-conformance list have been considered and the corresponding
further actions completed. The Genesys Purified Water Generation Unit is ready for Factory
Operational Qualification.
Interim Approval
Name Title Sign Date
14. Final Approvals
The objectives listed in section 3 for the Genesys Purified Water Generation Unit have been achieved.
All remaining non-conformances have been considered and the corresponding follow up actions
completed. The Factory Installation Qualification is complete.
Final Approval
Name Title Sign Date
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for
Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD
Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 41 of 44
15. Further Actions
Record below any further actions required to complete the validation exercise:
Further
Action No. Description Ref. Section Complete Sign/Date
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for
Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD
Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 42 of 44
16. Appendices
Appendix
No. Description Test Ref No Pages
Confirm
Appended
1 Non Conformance Report Master N/A 1
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for
Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD
Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 43 of 44
Appendix 1
Non Conformance Report
(1 Page)
Factory Installation Qualification
Genesys Purified Water Generation Unit
Highly Purified Water System for
Deltaflex SDN BHD at
N.A.Z Medical Supplies SDN BHD
Date: 13 May 2010 Ref: 7581-PWG-FIQ Rev: 0 Page 44 of 44
Non Conformance Report NCR No. Initial Date
Description of Non-Conformance: Test Reference:
Classification of Non-Conformance: □ Fail □ Refer
Justification:
Action taken (attach extra documentation if needed):
□ No Justification
□ Yes Description
Result (attach extra documentation if needed):
Recommendation (attach extra documentation if needed):
□ The Non-Conformance is accepted □ The Non-Conformance is not accepted
Justification (attach extra documentation if needed):
Approved By: Date: