Pre-Commissioning Checklist
of
SMPS based IPS
REFERENCE: SPECIFICATION NO. RDSO/SPN/165
SIG0101 (Revision 1)
Number of pages 13
RESEARCH, DESIGNS & STANDARDS ORGANISATION
MINISTRY OF RAILWAYS
MANAK NAGAR
LUCKNOW - 226011
![Page 2: 7096827-IPS-Pre-Comm-Check-List](https://reader036.vdocuments.mx/reader036/viewer/2022062512/551e1cab4a795982108b4a17/html5/thumbnails/2.jpg)
Format No. SIG 0101, Ver. 1 Pre-Commissioning Checklist for SMPS Based IPS RDSO/SPN/165/2004
DOCUMENT DATA SHEET
Designation
SIG 0101 (Revision 1)
Title of Document
Pre-Commissioning Checklist of SMPS based IPS
Authors: See Document Control Sheet
Name: Vipul GoelDesignation: Joint Director / Signal
Approved By
Name: Shri G.D.BhatiaDesignation: Sr.Executive Director /Signal, RDSO
Abstract
This document defines the guidelines for Pre-Commissioning Checklist of SMPS based IPS.
2
![Page 3: 7096827-IPS-Pre-Comm-Check-List](https://reader036.vdocuments.mx/reader036/viewer/2022062512/551e1cab4a795982108b4a17/html5/thumbnails/3.jpg)
Format No. SIG 0101, Ver. 1 Pre-Commissioning Checklist for SMPS Based IPS RDSO/SPN/165/2004
Document control Sheet
Designation Organization Function Level
Joint Director/Signal
RDSO Member Prepare
Sr.ED /Signal RDSO - Approval
3
![Page 4: 7096827-IPS-Pre-Comm-Check-List](https://reader036.vdocuments.mx/reader036/viewer/2022062512/551e1cab4a795982108b4a17/html5/thumbnails/4.jpg)
Format No. SIG 0101, Ver. 1 Pre-Commissioning Checklist for SMPS Based IPS RDSO/SPN/165/2004
PRE-COMMISSIONING CHECKLIST FOR SMPS BASED IPS SYSTEM
1. STATION DETAILS
Zonal Railway Number of main signalsDivision Number of shunt signalsStation Name Number of point machinesIPS Make Number of Axle CountersRE/Non RE Number of Track CircuitsNo. of lines / Roads Type of Track Circuit
(AFTC/DC) Power availability hours / day
Number/Type of Indoor relays
DG set rating Number/Type of outdoor relays
Type / capacity of battery (LM/VRLA)
Interlocking ( RRI/SSI)
2. PRE-COMMISSIONING REQUIREMENTS
S.N.
ITEM Specified Value/provision
Measured Value / Observation
Remark (OK/Not OK)
A Ambience of IPS Room
A1 Availability of working space for maintenance.
1 m (min.) from sides and rear. 2 m (min.) in front of the IPS
A2 Provision of flooring to ensure proper cleaning.
Pucca floor/ Ceramic tiles
A3 Provision of forced ventilation
Fresh Air fans with dampers
A4 Arrangement for protection against dust.
(i) Tight closing of doors & windows; use gaskets if necessary.
(ii) Washable dust filters on windows.
(iii) Provision of double door or entry through adjoining room to reduce dust ingress
A5 Provision of Ventilators As per RE Drg. No. RE/Civil/S-129-2001 (Annexure-I).
Signature of Manufacturer's Representative Signature of Railway Supervisor
4
![Page 5: 7096827-IPS-Pre-Comm-Check-List](https://reader036.vdocuments.mx/reader036/viewer/2022062512/551e1cab4a795982108b4a17/html5/thumbnails/5.jpg)
Format No. SIG 0101, Ver. 1 Pre-Commissioning Checklist for SMPS Based IPS RDSO/SPN/165/2004
S.N.
ITEM Specified Value/provision Measured Value / Observation
Remark (OK/Not OK)
B Batteries
B1 Installation of secondary cell as per para 16.6 of SEM Pt.
Installed in separate room / apparatus case.Acid proof flooring and tilesExhaust fanInitial charging as per instruction of battery manufacturerUse of battery grade sulphuric acid conforming to IS: 266. Use of distilled or de-mineralised water conforming to IS: 1069
B2 Storage period of VRLA batteries for IPS
Less than 03 months (If the battery is being stored for more than 3 months, freshening charge should be given once in 3 months as given below. The charging current should be 10% to 20% (max.) of rated capacity:-
Float Charge @ 2.25V/cell for 24 hours Boost Charge - @ 2.30V/cell for 15 hours)
B3 Measured capacity of battery after capacity test on batteries.
Rated AH
B4 Feeder cable from battery to charger120AH200AH 300AH
10 sq.mm copper16 sq.mm copper25 sq.mm copper
B5 Availability of Spare cell in charged condition at site
05 Nos.
C Commercial/AT Supply
C1 Availability of commercial supply (Ref: RB letter No. 2002/SIG/SGF/3 dt. 24.6.03).
More than 6 hours in 24 hours with least fluctuations
(Note: Nominal incoming AC supply shall be 230V, 50Hz single phase AC. The specified AC voltage range for IPS is 150V-270V.)
Signature of Manufacturer's Representative Signature of Railway Supervisor
5
![Page 6: 7096827-IPS-Pre-Comm-Check-List](https://reader036.vdocuments.mx/reader036/viewer/2022062512/551e1cab4a795982108b4a17/html5/thumbnails/6.jpg)
Format No. SIG 0101, Ver. 1 Pre-Commissioning Checklist for SMPS Based IPS RDSO/SPN/165/2004
S.N.
ITEM Specified Value/provision Measured Value / Observation
Remark (OK/Not OK)
C2 Voltage drop in input feeder at full load.
Less than 30 volts
C3 Provision of sources of power supply as per para 16.2 of SEM Pt. II.
RE Area Power supply drawn from AT Up/Dn/ Commercial supply/Genset with auto/ manual changeover facility in the control panel.
On double/multiple line sections, at least one AT is available to ensure power supply in the event of power block.
On single line sections where power supply is drown from a single AT, a DG set of suitable capacity has been provided
In big yards, a DG set of adequate capacity in addition to supply from AT's and local source
Non RE Area Power supply drawn from commercial feeder. In addition two standby diesel generators have been provided
C4 Size of input feeder cable as per TI Directorate's note no. TI/PSI/Project/CLS/01 dt. 04.01.02.(Annexure II)from Auxiliary Transformer (AT ) / Distribution transformer to IPS room for 5 KVA AT10KVA AT50KVA AT
2X25 sq.mm Al2x70 sq.mm Al2x300 sq.mm Al
Signature of Manufacturer's Representative Signature of Railway Supervisor
6
![Page 7: 7096827-IPS-Pre-Comm-Check-List](https://reader036.vdocuments.mx/reader036/viewer/2022062512/551e1cab4a795982108b4a17/html5/thumbnails/7.jpg)
Format No. SIG 0101, Ver. 1 Pre-Commissioning Checklist for SMPS Based IPS RDSO/SPN/165/2004
S.N.
ITEM Specified Value/provision Measured Value / Observation
Remark (OK/Not OK)
C5 Sanctioned Commercial feeder load (KVA)=SGeneral Electrical Lighting load (KVA)=LBalance available for Signalling Load(KVA) = S-L
4 Line Non-RE4 Line RE6 Line Non-RE6 Line RE
7.4 KVA6.25 KVA8.1 KVA7.0 KVA
C6 MCB/ Changeover switch
(Ref: RB letter No. 2004/SIG/SGF/3 dt. 25.3.2004.
63 Amp of Merlin Gerlin (Telemecanique) / Siemens, Schneider or ABB.
D DG Set supplyD1 Provision of adequate
capacity DG set (without AFTC)4 Line Non-RE4 Line RE/6 Line RE6 Line Non-RE
with AFTC in yard
10 KVA10 KVA12.5/15 KVA
At least 25 KVAD2 Checking of DG set at
5KW dummy load: Waveform Voltage Regulation Frequency
Sinusoidal within 3%50Hz ± 5% from no load to full load
D3 Proper termination of earth and neutral.
Good workmanship
E EarthingE1 Earth resistance of
earthing arrangement.Less than 2 Ohm (without adding water prior to measurement) Preferably maintenance free earth.
E2 Extension of earth to equipotential bus bar.
Provided
Signature of Manufacturer's Representative Signature of Railway Supervisor
7
![Page 8: 7096827-IPS-Pre-Comm-Check-List](https://reader036.vdocuments.mx/reader036/viewer/2022062512/551e1cab4a795982108b4a17/html5/thumbnails/8.jpg)
Format No. SIG 0101, Ver. 1 Pre-Commissioning Checklist for SMPS Based IPS RDSO/SPN/165/2004
S.N.
ITEM Specified Value/provision Measured Value / Observation
Remark (OK/Not OK)
E3 Connection of individual equipment to equipotential bus bar: - IPS racks - DG sets -Surge protection devices
with individual copper insulated cable of size
4 Sq.mm4 Sq.mm16 Sq.mm
F Lightning & Surge ProtectionF1 Provision of lightning &
surge arrestors (As per Cl. 3.12 of RDSO/SPN/165/2004 Ver 2)
One set
G. Instruction ManualG1 Instruction Manual
consisting of Layout drgs., Circuit/ System diagram, PCB Layout etc. (Ref: Cl. 7.1 of RDSO/SPN/165/2004 Ver 2)
Two sets
H TrainingH1 Imparting on job training
to SE/SSE/JE and ESM 3 days
3. IPS LOAD DETAILS
N= Number of modules provided in hot standby
S.N.
ITEM Specified Value/provision
Measured Value / Observation
Remark (OK/Not OK)OK Not
OK1. Signalling Equipment load
(KVA)80% of the DG Set capacity provided at station
2. Relay internal 24-32V/5A 5 *(N-2) Amp3. Relay external 24-32V/5A 5 *(N-1) Amp4. Axle counter 24-32V/5A 5 *(N-1) Amp5. Block local 12-28V/5A 5 *(N-1) Amp6. Panel Indication12-28V/5A 5 *(N-1) Amp7. HKT/magneto 12-28V/1A 1 *(N-1) Amp8. Block UP 12-40V/1A 1 *(N-1) Amp9. Block DN 12-40V/1A 1 *(N-1) Amp
8
![Page 9: 7096827-IPS-Pre-Comm-Check-List](https://reader036.vdocuments.mx/reader036/viewer/2022062512/551e1cab4a795982108b4a17/html5/thumbnails/9.jpg)
Format No. SIG 0101, Ver. 1 Pre-Commissioning Checklist for SMPS Based IPS RDSO/SPN/165/2004
Signature of Manufacturer's Representative Signature of Railway Supervisor
S.N ITEM Specified Value/provision
Measured Value / Observation
Remark (OK/Not OK)OK Not
OK10 Block Tele UP 3-6V/0.1A 0.1*(N-1) Amp11 Block Tele DN 3-6V/0.1A 0.1*(N-1) Amp12 Data logger 24-32V/5A 5 *(N-1) Amp13 SSI 24-32V/5A 5 *(N-2) Amp14 Load on each Signal Tx UP 500 VA15 Load on each Signal Tx DN 500 VA16 Load on Inverter
4 Line6 Line
1.5 KVA2.0 KVA
17 Load on Signalling AVR4 Line6 Line
1.5 KVA2.0 KVA
18 Load on Track TxUPDN
500VA500VA
19 Load on Track AVR4 Line6 Line
1.0 KVA1.5 KVA
20 High voltage disconnect 275 V21 Low voltage disconnect 160V22 Battery capacity 300/200AH23 Battery charging current 30/20A =Y24 Total Current drawn from
FRBC at 110 V after one hour of discharge.
20* (N-2) Amp=X
25 Current drawn from FRBC at 110 V when battery is in float condition
X-Y
26 Input feeder current at full load4 Line Non-RE4 Line RE6 Line Non-RE6 Line RE
32 Amp27.2 Amp35 Amp30.2 Amp
27 Input feeder voltage at full load
160 Volts (Minimum)
28 Functioning of dynamic current control
Operational
29 Supply fuse 63 A
9
![Page 10: 7096827-IPS-Pre-Comm-Check-List](https://reader036.vdocuments.mx/reader036/viewer/2022062512/551e1cab4a795982108b4a17/html5/thumbnails/10.jpg)
Format No. SIG 0101, Ver. 1 Pre-Commissioning Checklist for SMPS Based IPS RDSO/SPN/165/2004
Signature of Manufacturer's Representative Signature of Railway Supervisor
S.N ITEM Specified Value/provision
Measured Value / Observation
Remark (OK/Not OK)OK Not
OK30 Working of Status Monitoring
Panel (Para 4.10 of spec.) DOD 50% 60% 70%
Stop DG Set
RED & Audio alarmRED & Audio alarmRED & Audio alarm till DG is started
GREEN & Audio alarm
31 Call S&T due to failure of any module
RED & Audio alarm
32 Changeover inv. 1 to 2 and vice versa
Inverter failure
33 Changeover inv. to CVT and vice versa
Both inverter fail
34 DC-DC Converter for spare cells 2-12V, 5Amp
02 Nos.
35 Temperature compensation Provided for VRLA battery
4. Performance Monitoring of IPS
S.N ITEM Specified Provision
Observation Remark
1 Monthly calculation of MTBF / MTTR and sending it to Zonal Railways for onward transmission to RDSO.
As per Annexure-III
**********************
10
Signature of IPS Manufacturer's Representative NameDesignationDate
Signature of Railway Supervisor NameDesignationDate
![Page 11: 7096827-IPS-Pre-Comm-Check-List](https://reader036.vdocuments.mx/reader036/viewer/2022062512/551e1cab4a795982108b4a17/html5/thumbnails/11.jpg)
Format No. SIG 0101, Ver. 1 Pre-Commissioning Checklist for SMPS Based IPS RDSO/SPN/165/2004
Annexure-II
Telephone : 2451200 Extn. 42394 Tele Fax : 91-0522-2452332E-mail : [email protected]
Government of India - Ministry of RailwaysResearch Designs & Standards Organisation
LUCKNOW - 226011
No.TI/PSI/PROJECT/CLS/01 Dated 04.01.2002
The Chief Electrical Engineer
i) Central Railway, Mumbai CST-400 001. ii) Western Railway, Churchgate, Mumbai-400 020. iii) Eastern Railway, Fairlie Place, Kolkata-700 001. iv) South Eastern Railway, Garden Reach, Kolkata-700 043. v) Northern Railway, Baroda House, New Delhi-110 001. vi) Southern Railway, Park Town, Chennai-600 003. vii) South Central Railway, Rail Nilayam, Secunderabad-500 371. viii) CORE, Nawab Yusuf Road, Civil Lines, Allahabad-211 001.
Sub: The cable sizes between Auxiliary Transformer and Distribution Panel.
The existing cable between auxiliary transformer and distribution panel is of 2x25 Sq.mm Aluminium cable for 5 KVA and 10KVA auxiliary transformers. The problem of excessive voltage drop and failure of fuse / tripping of MCB in distribution panel especially during low OHE voltage have been reported by the Signal Directorate. The cable size has been accordingly reviewed considering the voltage drop as well as energy loss in the cable.
Presently, 10KV ATs are being provided at the end of platforms at the stations for signalling loads. 5KVA ATs are being provided at IBH stations and level crossing gates. The signalling load for ¾ line station in double line section on 10KV AT is about 8.5KVA. The signalling load at IBH and level crossing gate is about 2.0KVA. 50KVA ATs are presently planned for Mumbai area under DC-AC conversion where the requirement of load is higher. The estimated max. signalling load on 50KVA AT is about 40KVA. These 50KVA ATs may be used in future in other areas depending on the requirement of load.
Due to provision of voltage stabilizer, the signalling load is normally of constant VA type i.e. if the voltage decreases the current will increase correspondingly. The input voltage range of the voltage stabilizer is 160-270V. Considering this the optimum cable sizes for different types of ATs are worked out and are given as follows:
AT type Cable sizes5KVA 2 x 25 Sq.mm Aluminium10KVA 2 x 70 Sq.mm Aluminium50KVA 2 x 300 Sq.mm Aluminium
The above cable sizes of 1100V, PVC insulated, PVC sheathed, Al-conductor, Armoured Power cable as per IS: 1554-Part-I are to be provided for the respective type of ATs. The cable lugs and connectors are to be suitably provided. The taps of ATs should be judiciously kept so that the available voltage is maintained in the range of 160-270 V, which is the input voltage range of signalling voltage stabilizer.
(B.P.Singh)
11
![Page 12: 7096827-IPS-Pre-Comm-Check-List](https://reader036.vdocuments.mx/reader036/viewer/2022062512/551e1cab4a795982108b4a17/html5/thumbnails/12.jpg)
Format No. SIG 0101, Ver. 1 Pre-Commissioning Checklist for SMPS Based IPS RDSO/SPN/165/2004
for Director General/TI
Annexure-III
Suggested Format of field MTBF to be submitted by Zonal Railways
Make Total working hours Total number of failures MTBFIPS SMR** Inv.** DC-DC
Conv**IPS* SMR Inv DC-DC
ConvIPS SMR Inv. DC-
DC Conv
AMRBSMC
HBL
Statcon
*IPS failures shall be those failures which have affected the final performance of signalling system i.e failures affecting signals, complete shut down, failure of complete function.
** Total working hours of SMR = number of SMR provided x working hours of IPS system
Total working hours of Inverter = number of Inverters provided x working hours of IPS system
Total working hours of DC-DC Conv = number of DC-DC Conv. Provided x working hours of IPS system
Total working hours MTBF = Number of failures of sub system
Format of field MTTR to be submitted by Zonal Railways
Make Total number of failures Total duration of failures (hours)
MTTR (hours)
AMRBSMCHBL Statcon
12
![Page 13: 7096827-IPS-Pre-Comm-Check-List](https://reader036.vdocuments.mx/reader036/viewer/2022062512/551e1cab4a795982108b4a17/html5/thumbnails/13.jpg)
Format No. SIG 0101, Ver. 1 Pre-Commissioning Checklist for SMPS Based IPS RDSO/SPN/165/2004
13