Doc Id: Business_Blueprint_PP_1.0
BUSINESS BLUEPRINT
KAY BOUVET ENGINEERING PVT.LTD.
MY SAP ERP IMPLEMENTATION PROJECT
PP MODULE
SANDESH L.BONDE MR.KHANWILKAR
SAP Consultant-PP, B.P.O.ADROIT INFOTECH PVT. LTD. PUNE. K.B.E.P.L.
Date of issue : Issue 1, Template Version : 1.0 Page 1 of 36Reviewed by: Kishor Joshi Approved by : Atul Joshi
Confidentiality Clause: Adroit InfoTech reserves the copyright on all material and ideas in this document. No material should bereproduced in any form (electronic or written), in part or whole without the express consent of Adroit InfoTech. The contents of this
document are strictly confidential and should not be shared with any other company without the prior permission of Adroit InfoTech.
8/2/2019 63917855-KBEPL-PP-BBP
http://slidepdf.com/reader/full/63917855-kbepl-pp-bbp 2/36
Quality ManagementQuality Management SystemSystem
Doc Id: Business_Blueprint_PP_1.0
MODULES TO BE IMPLEMENTED
NO. MODULE
1 PP MODULE
2 QM MODULE
3 SD MODULE
4 FI MODULE
5 MM MODULE
6 CO MODULE
7 PS MODULE
Date of issue : Issue 1, Template Version : 1.0 Page 2 of 36Reviewed by: Kishor Joshi Approved by : Atul Joshi
Confidentiality Clause: Adroit InfoTech reserves the copyright on all material and ideas in this document. No material should bereproduced in any form (electronic or written), in part or whole without the express consent of Adroit InfoTech. The contents of this
document are strictly confidential and should not be shared with any other company without the prior permission of Adroit InfoTech.
8/2/2019 63917855-KBEPL-PP-BBP
http://slidepdf.com/reader/full/63917855-kbepl-pp-bbp 3/36
Quality ManagementQuality Management SystemSystem
Doc Id: Business_Blueprint_PP_1.0
Date of issue : Issue 1, Template Version : 1.0 Page 3 of 36Reviewed by: Kishor Joshi Approved by : Atul Joshi
Confidentiality Clause: Adroit InfoTech reserves the copyright on all material and ideas in this document. No material should bereproduced in any form (electronic or written), in part or whole without the express consent of Adroit InfoTech. The contents of this
document are strictly confidential and should not be shared with any other company without the prior permission of Adroit InfoTech.
CONTENTS
No. TopicPage numbers
Start
1. PURPOSE 04
2 PRE REQUISITIES 04
3 ORGANIZATIONAL STRUCTURE 04
4 MATERIAL MASTER 07
A) BILL OF MATERIAL 09
B) WORK CENTER 11
C) ROUTING 15
5. PRODUCTION PLANNING- DEMAND MANAGEMENT 19
6. PRODUCTION PLANNING -MRP 20
7 MRP CONTROLLER 22
8 CAPACITY PLANNING 22
9 PRODUCTION PLANNING 25
10 PRODUCTION PROCESS EXECUTION 28
11 SAP PROCESS FLOW 31
12 PP STANDARD REPORT 32
13 ANNEXTURE 1 33
14BUSINESS PROCESS OWNER’S ACCEPTANCE SIGNOFF (BBP)
35
8/2/2019 63917855-KBEPL-PP-BBP
http://slidepdf.com/reader/full/63917855-kbepl-pp-bbp 4/36
Quality ManagementQuality Management SystemSystem
Doc Id: Business_Blueprint_PP_1.0
1) PURPOSE:-
This document describes the proposed blue print for SAP Implementation at Kay BouvetEngineering Pvt. Ltd. (KBEPL). It outlines all the business processes associated withinthe scope of implementation. The intent of the document is to define the TO-BE modelfor the process for which an AS-IS study was conducted during the knowledge gatheringphase.The production planning within SAP (PP) would encompass all activities relating toMaterial Requirement Planning (MRP) and processing through production. It would
include master data maintenance and the controlling transactions needed for the same.
The document is a collaborative effort between the implementation team of AdroitInfoTech Pvt.Ltd., Pune and the Core Team of Kay Bouvet Engineering Pvt. Ltd. The
document also represents the agreement of the core team to the proposed processes inindividual modules of the project and also of the deviations, where an agreement needsto be reached on the process change. The blueprint aims to cover all the businessprocesses within the scope of the project and in case there are any processes which arenot covered for lack of clarity, better solution, etc these would be detailed as additions tothe blueprint as and when they are ready.
2) PRE- REQUISITIES:-
MASTER DATA & ORGANIZATIONAL DATA
We are required to have essential master and organizational data to perform the activity,such as the data reflects the organization structure of K.B.E.P.L. and master data thatsuits its operational focus.Following are the lists of data required.
• Organizational Structure
• Material Master
• BOM
•
Work center.*9369*-3
• Routing
3) ORGANIZATIONAL STRUCTURE:-
3.1 AS-IS AT KBEPL
At present no formal organizational structure exists at Kay Bouvet Engineering Pvt.Ltd.
Date of issue : Issue 1, Template Version : 1.0 Page 4 of 36Reviewed by: Kishor Joshi Approved by : Atul Joshi
Confidentiality Clause: Adroit InfoTech reserves the copyright on all material and ideas in this document. No material should bereproduced in any form (electronic or written), in part or whole without the express consent of Adroit InfoTech. The contents of this
document are strictly confidential and should not be shared with any other company without the prior permission of Adroit InfoTech.
8/2/2019 63917855-KBEPL-PP-BBP
http://slidepdf.com/reader/full/63917855-kbepl-pp-bbp 5/36
Quality ManagementQuality Management SystemSystem
Doc Id: Business_Blueprint_PP_1.0
3.2 TO-BE AT KBEPL
B0
COMPANY
A company is an organizational unit in accounting, which represents a business
organization according to the requirement of commercial law in a particular country. Inthe SAP system, consolidation function in financial accounting is based on companies.
COMPANY KAY GROUP
COMPANY NAME KAY BOUVET ENGINEERING PVT.LTD.
Date of issue : Issue 1, Template Version : 1.0 Page 5 of 36Reviewed by: Kishor Joshi Approved by : Atul Joshi
Confidentiality Clause: Adroit InfoTech reserves the copyright on all material and ideas in this document. No material should bereproduced in any form (electronic or written), in part or whole without the express consent of Adroit InfoTech. The contents of this
document are strictly confidential and should not be shared with any other company without the prior permission of Adroit InfoTech.
CLIENT
COMPANY CODE
PRODUCTION PLANT
STORAGE LOCATION
WORK CENTER
EQUIPMENT
KAY GROUP
KBEL
KB01 KB03KB02
SL 01 SL 03SL 02
WC 01 WCWC 02
EQ EQEQ
Capacity
8/2/2019 63917855-KBEPL-PP-BBP
http://slidepdf.com/reader/full/63917855-kbepl-pp-bbp 6/36
Quality ManagementQuality Management SystemSystem
Doc Id: Business_Blueprint_PP_1.0
For Production Planning Module, Plant and Storage Locations are the one’s which arerelevant. Detailed Organization Structure would be covered in more detail in FI (Finance)
Module, MM (Material Management) Module and SD (Sales and Distribution) Module.
COMPANY CODE
• Under the company, there will be 1 Company Code.
• A company code is an organizational unit of external accounting for which a
complete, self contained set of accounting can be created. This includes the entry
of all transactions that must be posted and creation of all items for legal
individual financial statements, such as the balance sheet, profit and lossstatements.
• The company code will be created in the system for KBEPL will be as under.
No. Company Code Name of the Company
1 KBEL Kay Bouvet Engineering Pvt.Ltd.
PLANT
• A plant is an organizational unit which subdivides an enterprise according to
production, procurement, maintenance and material planning.
• It is the place where materials are produced or goods and services are provided.
• A plant s assigned to company.
• A plant also has following in SAP ERP:
An Address
A LanguageA Country Assignment
A Work Day Calendar
• A plant is assigned to company.
• Purchasing
• Organization and sales organizations are assigned to plants.
Date of issue : Issue 1, Template Version : 1.0 Page 6 of 36Reviewed by: Kishor Joshi Approved by : Atul Joshi
Confidentiality Clause: Adroit InfoTech reserves the copyright on all material and ideas in this document. No material should bereproduced in any form (electronic or written), in part or whole without the express consent of Adroit InfoTech. The contents of this
document are strictly confidential and should not be shared with any other company without the prior permission of Adroit InfoTech.
8/2/2019 63917855-KBEPL-PP-BBP
http://slidepdf.com/reader/full/63917855-kbepl-pp-bbp 7/36
Quality ManagementQuality Management SystemSystem
Doc Id: Business_Blueprint_PP_1.0
No. Plant Code Name Of the Plant Code
1 KB01 KBEPL Unit I
2 KB02 KBEPL Unit II
3 KB03 KBEPL Unit III
STORAGE LOCATION
• A location within a plant where inventory is stored.
• In KBEPL following locations are decided for Logistics.
No. Storage Location Type of Storage Location
1 KB11 FINISHED GOOD
2 KB12 SEMI FINISHED GOOD
3 KB13 SALES RETURN, REWORK & SUBCONTRACTING
4 KB14 RAW MATERIAL
5 KB15 GENERAL STORES
6 KB16 SCRAP STORES
4) MATERIAL MASTER:-
Date of issue : Issue 1, Template Version : 1.0 Page 7 of 36Reviewed by: Kishor Joshi Approved by : Atul Joshi
Confidentiality Clause: Adroit InfoTech reserves the copyright on all material and ideas in this document. No material should bereproduced in any form (electronic or written), in part or whole without the express consent of Adroit InfoTech. The contents of this
document are strictly confidential and should not be shared with any other company without the prior permission of Adroit InfoTech.
8/2/2019 63917855-KBEPL-PP-BBP
http://slidepdf.com/reader/full/63917855-kbepl-pp-bbp 8/36
Quality ManagementQuality Management SystemSystem
Doc Id: Business_Blueprint_PP_1.0
• The material maser contains all the information of the material that a company
procures produces, stores and sells.
• The entire production process outlined for KBEPL can be described as follows:
I) Material planning through Customer Schedule.
II) Material Requirement Planning.
III)Production Execution.
IV) Dispatching.
PROCESS FLOW CHART AT KBEPL
VA01 MMBE MD61 MD02NO
OR1
Date of issue : Issue 1, Template Version : 1.0 Page 8 of 36Reviewed by: Kishor Joshi Approved by : Atul Joshi
Confidentiality Clause: Adroit InfoTech reserves the copyright on all material and ideas in this document. No material should bereproduced in any form (electronic or written), in part or whole without the express consent of Adroit InfoTech. The contents of this
document are strictly confidential and should not be shared with any other company without the prior permission of Adroit InfoTech.
ReceivingSales Order
StockAvailability
Planning Raw MaterialAvailability
8/2/2019 63917855-KBEPL-PP-BBP
http://slidepdf.com/reader/full/63917855-kbepl-pp-bbp 9/36
Quality ManagementQuality Management SystemSystem
Doc Id: Business_Blueprint_PP_1.0
NO YES
ME21N
MIGO MB1C
CO01
QA11
MB1
C
VL01N
4 A) BILL OF MATERIAL
AS-IS AT KBEPL
Date of issue : Issue 1, Template Version : 1.0 Page 9 of 36Reviewed by: Kishor Joshi Approved by : Atul Joshi
Confidentiality Clause: Adroit InfoTech reserves the copyright on all material and ideas in this document. No material should bereproduced in any form (electronic or written), in part or whole without the express consent of Adroit InfoTech. The contents of this
document are strictly confidential and should not be shared with any other company without the prior permission of Adroit InfoTech.
Quality Check
Production
Quality Check
Goods Readyfor Dispatch
Procurement
PP
SD
MM
QM
Delivery toSales Order
Issue toProduction
Dept.
8/2/2019 63917855-KBEPL-PP-BBP
http://slidepdf.com/reader/full/63917855-kbepl-pp-bbp 10/36
Quality ManagementQuality Management SystemSystem
Doc Id: Business_Blueprint_PP_1.0
Every component either a finish good or semi-finish goods will have complex BOM.
TO-BE / SAP-PROCESS AT KBEPL
For KBEPL it would be a Multi-Level BOM structure.
4. A.1 SCOPE OF THE DOCUMENT
The Scope of the document is restricted to Creation, Change and Display of Bill of
materials for Finished Materials, Semi finished Materials.
4. A.2 GENERAL EXPLANATION
• BOM is formally structure lists of components that makes of product or assembly.
• The lists would contain object no. of each component, together with the quantity
and unit of measure.
4. A.3 EXPLANATIONS FUNCTIONS AND EVENTS
4. A.3.1 BUSINESS PROCESS DETAILS
BOM’s are used in their different forms in various situations where a finishedproduct is produced from several components parts or materials. The data storedin the Bill of materials serves as basis for production planning activities such as
• In material requirements planning (MRP) Bills of Material are used to
calculate procurement or in-house production quantities for materials.
• In Production orders Bills of material are used for planning the issue of materials.
• During Production order confirmation, the BOM is used to update finished
goods stock of the parent material and back flush actual consumption of
component material.
• Stores personnel use the BOM goods issue of components for in-house or
sub-contracting applications.
• Product costing uses the BOM to calculate the costs of materials required for
a specific product.
Date of issue : Issue 1, Template Version : 1.0 Page 10 of 36Reviewed by: Kishor Joshi Approved by : Atul Joshi
Confidentiality Clause: Adroit InfoTech reserves the copyright on all material and ideas in this document. No material should bereproduced in any form (electronic or written), in part or whole without the express consent of Adroit InfoTech. The contents of this
document are strictly confidential and should not be shared with any other company without the prior permission of Adroit InfoTech.
8/2/2019 63917855-KBEPL-PP-BBP
http://slidepdf.com/reader/full/63917855-kbepl-pp-bbp 11/36
Quality ManagementQuality Management SystemSystem
Doc Id: Business_Blueprint_PP_1.0
4. A.3.2 BOM STRUCTURE
BOM Structures are of two types:-1) Single-Level BOM structure.
2) Multi-Level BOM structure.
BOM Structure for KBEPL:-
• For KBEPL it would be a Multi-Level BOM structure:-
• In KBEPL, BOM is having only one usage, i.e. it would be production BOM.
• Every component either a Finished Good or a Semi Finished Good will have a
BOM.
• BOM will have each component that goes into product and for which productionand planning dept. wants to plan.
Date of issue : Issue 1, Template Version : 1.0 Page 11 of 36Reviewed by: Kishor Joshi Approved by : Atul Joshi
Confidentiality Clause: Adroit InfoTech reserves the copyright on all material and ideas in this document. No material should bereproduced in any form (electronic or written), in part or whole without the express consent of Adroit InfoTech. The contents of this
document are strictly confidential and should not be shared with any other company without the prior permission of Adroit InfoTech.
Item 1 Item 2 Item 3
Child Part
Multi Level BOM
Single-Level BOMSingle-Level BOM
ASSEMBLY
8/2/2019 63917855-KBEPL-PP-BBP
http://slidepdf.com/reader/full/63917855-kbepl-pp-bbp 12/36
Quality ManagementQuality Management SystemSystem
Doc Id: Business_Blueprint_PP_1.0
• MRP will consider stock of raw material while net requirement calculation and MRP
controller decide whether the raw material can procure from outside or to cratepurchase order for the same.
REPORTING CONSIDERATIONS
• CS11 – Explode BOM Level by Level
• CS12 - Explode Multi level BOM
• CS13 – Summarized Bill of Material
LIST OF BUSINESS PROCESS PROCEDURES (BPP)
• CS01 – Create Bill of Material
• CS02 – Change Bill of Material
• CS03 – Display Bill of Material
• CS20 – Mass Changes
•
B) WORK CENTER:-
AS-IS AT KBEPL
Labor and Machines are work centers. Capacity utilization of all machines is 100%
In all Plant shift is for 8.00 Hrs.
TO-BE / SAP-PROCESS AT KBEPL
Accordingly Capacity Category (labor or machine) will be used. Capacity Utilization of
each work center will be used as 100%.
Shift Timings of Work centers to be fixed according to plants (All shifts will be
maintained for each work center).
The creation, Change and Display of Work Centers will be done plant wise.
B.1 GENERAL EXPLANATION
• All machines and labors will be created in SAP as work centers masters.
• These masters will have the capacity availability details in terms of number of shifts, shift sequences, work breaks, and the cost center data.
• Following types of Work Centers would be created:
Date of issue : Issue 1, Template Version : 1.0 Page 12 of 36Reviewed by: Kishor Joshi Approved by : Atul Joshi
Confidentiality Clause: Adroit InfoTech reserves the copyright on all material and ideas in this document. No material should bereproduced in any form (electronic or written), in part or whole without the express consent of Adroit InfoTech. The contents of this
document are strictly confidential and should not be shared with any other company without the prior permission of Adroit InfoTech.
8/2/2019 63917855-KBEPL-PP-BBP
http://slidepdf.com/reader/full/63917855-kbepl-pp-bbp 13/36
Quality ManagementQuality Management SystemSystem
Doc Id: Business_Blueprint_PP_1.0
1.Lathe Machines 9. Welding Machine.
2.Drilling Machines 10.Plasma Cutting Machine
3.Shaping Machines 11.Shearing Machine
4.Boring Machines 12.Hand Cutting Machine
5.Bending Machines 13.Pug Machines
6.Vertical Slotting Machine 14.Oven
7.Milling Machines 15.Profile Cutting Machine
8.Hack Saw Machine 16. Grinders.
DATA IN WORK CENTER WILL BE USE FOR
• Scheduling: - Operation times and formulas entered in the work center, so thatthe duration of an operation con be calculated.
• Costing: - Required costing formulas are entered in the work center, so that the
costs of an operation can be calculated. A work center is also assigned to a costcenter.
THE WORK CENTER WOULD SERVE THE FOLLOWING PURPOSES VIZ.
• To determine which machine or manpower is to be used in an operation.
• To calculate costs and dates for an operation.
• Work center can contain multiple types of capacity categories like Machine, Setupand Labor.
• Standard value key defined in the work centers will identify the parameters to becaptured. The typical standard values are setup time, machine time, labor time
etc. This can be maintained in Minutes etc.
• Work centers will be assigned to a cost center and there will be activity typesdefined in these cost centers. Activity types are evaluated for each cost center
and period with a charge rate that consists of a fixed portion and a variable(work-related) portion. These activity types determine the charge rate with which
costing is to be carried out for internal standard values viz., machine hours, setuptime and labour hours defined in the controlling module.
• The available capacity will be taken from the work centre in which is maintainedshift schedule and shift sequence.
Date of issue : Issue 1, Template Version : 1.0 Page 13 of 36Reviewed by: Kishor Joshi Approved by : Atul Joshi
Confidentiality Clause: Adroit InfoTech reserves the copyright on all material and ideas in this document. No material should bereproduced in any form (electronic or written), in part or whole without the express consent of Adroit InfoTech. The contents of this
document are strictly confidential and should not be shared with any other company without the prior permission of Adroit InfoTech.
8/2/2019 63917855-KBEPL-PP-BBP
http://slidepdf.com/reader/full/63917855-kbepl-pp-bbp 14/36
Quality ManagementQuality Management SystemSystem
Doc Id: Business_Blueprint_PP_1.0
WORK CENTER CODIFICATION
UNIT I
O. MACHINE NAME
(MACHINE SHOP)
CODE NO. MACHINE NAME
(FABRICATION SHOP)
CODE
1. Horizontal Boring Machine,H160
1HBMH160 1. Welding Machine, TIG 01 1WMTIG01
2 Plaino Miller Machine, Heller 1PMHELLR 2 Welding Machine, TIG 02 1WMTIG02
3. Horizontal Boring Machine,Skoda
1HBSKODA 3. Welding Machine, CO2 01 1WMCO201
4. Horizontal Boring Machine,H80
1HBMCH80 4. Welding Machine, CO2 02 1WMCO202
5. Vertical Turret Lathe,VTL 1VTLATHE 5. Plate Bending, Upto 15mm 1PBEND15
6. Radial Drilling Machine,RDM5 1RDMRDM5 6. Shearing Machine,upto5mm 1SHEARM5
7 Radial Drilling Machine,Universal
1RDMUNIV 7 Hand Gas Cutting Machine,1 1HGCUT01
8 Radial Drilling Machine, 1RDRILLM 8 Hand Gas Cutting Machine,2 1HGCUT02
9 Lathe Machine,CL-6QMT 1LM06QMT 9 Hand Gas Cutting Machine,3 1HGCUT03
10 Lathe Machine,CL-7QMT 1LM07QMT 10 Hand Gas Cutting Machine,4 1HGCUT04
11 Shaper Machine 1SHAPERM 11 Hand Gas Cutting Machine,5 1HGCUT05
12 Vertical Sloting Machine,SL-9 1VSMCSL9 12 Hand Gas Cutting Machine,6 1HGCUT06
13 Milling Machine 1MILLING 13 Hand Gas Cutting Machine,7 1HGCUT07
14 Hand Gas Cutting Machine,8 1HGCUT08
15 Hand Gas Cutting Machine,9 1HGCUT09
16 Hand Gas CuttingMachine,10
1HGCUT10
17 Pug Machine,01 1PUGMC01
18 Pug Machine,02 1PUGMC02
19 Pug Machine,03 1PUGMC03
Date of issue : Issue 1, Template Version : 1.0 Page 14 of 36Reviewed by: Kishor Joshi Approved by : Atul Joshi
Confidentiality Clause: Adroit InfoTech reserves the copyright on all material and ideas in this document. No material should bereproduced in any form (electronic or written), in part or whole without the express consent of Adroit InfoTech. The contents of this
document are strictly confidential and should not be shared with any other company without the prior permission of Adroit InfoTech.
8/2/2019 63917855-KBEPL-PP-BBP
http://slidepdf.com/reader/full/63917855-kbepl-pp-bbp 15/36
Quality ManagementQuality Management SystemSystem
Doc Id: Business_Blueprint_PP_1.0
20 Electrodes Drying Oven 1OVEN001
UNIT II
NO. MACHINE NAME(MACHINE SHOP)
CODE NO. MACHINE NAME(FABRICATION SHOP)
CODE
1. Radial DrillMachine,Imported01
2RDRIL01 1. Welding Transformers,1 to 33
2WTRAN01 to2WTRAN33
2 Radial Drill
Machine,Imported02
2RDRIL02 2 Welding Rectifier,01 2WRECT01
3. Stand Drill,01 2SDRIL01 3. Welding Rectifier,02 2WRECT02
4. Magnet Drill,01 2MDRIL01 4. Pug Machines, 1 to 11 2PUGMC01to2PUGMC11
5. Magnet Drill,02 2MDRIL02 5. Hand Grinder (7”), 1 to 14 2HGRI701 to2HGRI714
6. Magnet Drill,03 2MDRIL03 6. Hand Grinder (4”), 1 to 4 2HGRI401 to2HGRI404
7 Hand Drill,01 2HDRIL01 7 Table Grinder 2TBGRI01
8 Hand Drill,02 2HDRIL02 8 Shaft Grinder 2SHGRI01
9 Hydraulic Hack Saw 2HYHSW01 9 Straight Grinder 2STGRI01
10 Hyd. Pipe Bender 2HYPBD01 10 Electrodes Drying Oven 2OVEN002
11 Power Press 2PPRES01 11 Heating Torch,01 2HTORCH1
12 Pipe Cutter 2PCUTT01 12 Heating Torch,02 2HTORCH2
13 Lathe Machine 2LATHEMC 13 Plate Bending Machine 2PBENDMC
14 Sheet Cutter 2SHETCUT1 14
UNIT III
DIVISION I
NO. MACHINE NAME(MACHINE)
CODE NO. MACHINE NAME(FABRICATION)
CODE
1. Lathe Machine,01 3LATHM01 1. Welding Machines, 1 to26
3WELDM01 to3WELDM26
2 Lathe Machine,02 3LATHM02 2 Pug Machines, 1 to 14 3PUGMC01 to3PUGMC14
3. Lathe Machine,03 3LATHM03 3. Profile Cutting Machine 3PROFCM1
4. Lathe Machine,04 3LATHM04 4. Grinders, 1 to 20 3GRIND01 to3GRIND20
5. Lathe Machine,05 3LATHM05 5. Plate Bending & RollingMachine, 32 mm
3PBEND32
6. Lathe Machine,06 3LATHM06 6. Plate Bending & RollingMachine, 80 mm
3PBEND80
Date of issue : Issue 1, Template Version : 1.0 Page 15 of 36Reviewed by: Kishor Joshi Approved by : Atul Joshi
Confidentiality Clause: Adroit InfoTech reserves the copyright on all material and ideas in this document. No material should bereproduced in any form (electronic or written), in part or whole without the express consent of Adroit InfoTech. The contents of this
document are strictly confidential and should not be shared with any other company without the prior permission of Adroit InfoTech.
8/2/2019 63917855-KBEPL-PP-BBP
http://slidepdf.com/reader/full/63917855-kbepl-pp-bbp 16/36
Quality ManagementQuality Management SystemSystem
Doc Id: Business_Blueprint_PP_1.0
7 Lathe Machine,07 3LATHM07 7
8 Shaping Machine,01 3SHAPRE1 8
9 Shaping Machine,02 3SHAPRE2 9
10 Radial Drilling Machine,01 3RDRIL01 10
11 Radial Drilling Machine,02 3RDRIL02 11
12 Radial Drilling Machine,03 3RDRIL03 12
13 Hack Saw Machine 3HACKS01 13
DIVISION II
NO. MACHINE NAME (MACHINE) CODE
1. Radial Drilling Machine ( COLB) 3RDRIL04
2 Radial Drilling Machine (To Be Install) 3RDRIL05
3. Boring Machine ( BFT 180) 3BMFT180
4. Boring Machine ( FB180 To Be Install) 3BMFB180
5. Boring Machine (BFT110 To BE Install) 3BMFT110
6. Vertical Turret Lathe ( To Be Install) 3VTLATHM
7 Milling Machine (Make BHOLE) 3MMBHOLE
8 CNC Gas Cutting Machine ( To Be Install) 3CNCGMC
REPORTING CONSIDERATIONS
• CR08 – Work Center Hierarchy Report
• CR06 – Work Center Assignment to Cost Centers
• CR07 – Work Center Capacities
• CR60 – Work Center information system
LIST OF BUSINESS PROCESS PROCEDURES (BPP)
• CR01 – Creation of Work Center
• CR02 – Change of Work Center
• CR03 – Display of Work Center
• CR21 – Create Work Center Hierarchy
• CR22 – Change Work Center Hierarchy
• CR23 – Display Work Center Hierarchy
• CA85 – Replace
• CA80 – Work Center Where used list
C) ROUTING:-
Date of issue : Issue 1, Template Version : 1.0 Page 16 of 36Reviewed by: Kishor Joshi Approved by : Atul Joshi
Confidentiality Clause: Adroit InfoTech reserves the copyright on all material and ideas in this document. No material should bereproduced in any form (electronic or written), in part or whole without the express consent of Adroit InfoTech. The contents of this
document are strictly confidential and should not be shared with any other company without the prior permission of Adroit InfoTech.
8/2/2019 63917855-KBEPL-PP-BBP
http://slidepdf.com/reader/full/63917855-kbepl-pp-bbp 17/36
Quality ManagementQuality Management SystemSystem
Doc Id: Business_Blueprint_PP_1.0
AS-IS AT KBEPL
For manufacturing one component, various machines are used; multiple work center
assignments are there.
TO-BE / SAP-PROCESS AT KBEPL
While creating the production order user can select the routing by selecting theproduction version which contains that routing number.
C.1 GENERAL EXPLANATION
• A routing is a description of which operations have to be carried out in whichorder to produce a material which can be a Finish Product or a Semi-Finish
Product to be manufactured in-house.• Routing contains information about the work centers where the individual work
steps are carried out.
• Routing also contains the planned times for carrying out the operations (standardvalues).
C.2 ROUTING WOULD ALSO SERVE THE FOLLOWING PURPOSES VIZ.
For work scheduling which uses routing as a basis for operation planning and productioncontrol. The routing thus answers the questions like:
• Where the production is done?• How long it will take?
• What are the materials and tooling required?
• Components required for operation will be attached to operation as per BOM
norms.
• System will automatically group all the routings of a material under a groupnumber and this group number will be internal number generated by the system.
• Operation unit will be maintained in the units on which the output is measured
and monitored and hence it will vary from operation to operation in a routing.
• Any additional information on operation, routing will be maintained at therespective long text area.
Date of issue : Issue 1, Template Version : 1.0 Page 17 of 36Reviewed by: Kishor Joshi Approved by : Atul Joshi
Confidentiality Clause: Adroit InfoTech reserves the copyright on all material and ideas in this document. No material should bereproduced in any form (electronic or written), in part or whole without the express consent of Adroit InfoTech. The contents of this
document are strictly confidential and should not be shared with any other company without the prior permission of Adroit InfoTech.
8/2/2019 63917855-KBEPL-PP-BBP
http://slidepdf.com/reader/full/63917855-kbepl-pp-bbp 18/36
Quality ManagementQuality Management SystemSystem
Doc Id: Business_Blueprint_PP_1.0
• All manufactured items will have routings (detailed routing for discrete
production) created in the system.
REPORTING CONSIDERATIONS
• CA51 – List of Routings for product/plant
• CA60 – Display Changes
• CA80 – Work Center Where Used List
LIST OF BUSINESS PROCESS PROCEDURES (BPP)
•
CA01 – Creation of Routing• CA02 – Change of Routing
• CA03 – Display of Routing
• C223 – Create Production version
C.3 COST CENTER
DEFINITION
A cost center is part of an organization that does not produce direct profit and adds tothe cost of running a company.
Date of issue : Issue 1, Template Version : 1.0 Page 18 of 36Reviewed by: Kishor Joshi Approved by : Atul Joshi
Confidentiality Clause: Adroit InfoTech reserves the copyright on all material and ideas in this document. No material should bereproduced in any form (electronic or written), in part or whole without the express consent of Adroit InfoTech. The contents of this
document are strictly confidential and should not be shared with any other company without the prior permission of Adroit InfoTech.
Cost Center
Price Activity
TypeRouting
CostsFormulas
Work
Formula Std. Value
8/2/2019 63917855-KBEPL-PP-BBP
http://slidepdf.com/reader/full/63917855-kbepl-pp-bbp 19/36
Quality ManagementQuality Management SystemSystem
Doc Id: Business_Blueprint_PP_1.0
EXAMPLE
Formulas
ACTIVITY TYPE
• A unit in a controlling area that classifies the activities performed in a cost center.
• Activity types in production cost centers are machine hours or finished units.
Date of issue : Issue 1, Template Version : 1.0 Page 19 of 36Reviewed by: Kishor Joshi Approved by : Atul Joshi
Confidentiality Clause: Adroit InfoTech reserves the copyright on all material and ideas in this document. No material should bereproduced in any form (electronic or written), in part or whole without the express consent of Adroit InfoTech. The contents of this
document are strictly confidential and should not be shared with any other company without the prior permission of Adroit InfoTech.
Cost Center Production
Price ActivityType
Work Center
Set up time
Op.qty.*Labor r time
Op.qty.*Mach.
time
Routing
100Rs/Hr. RVE
50RS/Hr. LAB
25RS/Hr. MAC
Setu time
Labor time
Mach.time
Costs
SET= 1 Hr.* 100 Rs./Hr.=100 Rs.LAB= 2 pcs.*2 Hr.* 50 Rs./Hr.=200 Rs.MAC=2 Pcs.*3 Hr.*25 Rs./Hr.=150 Rs.
Std. Values
1 Hr
2 Hr
3 Hr
Op.
10
8/2/2019 63917855-KBEPL-PP-BBP
http://slidepdf.com/reader/full/63917855-kbepl-pp-bbp 20/36
Quality ManagementQuality Management SystemSystem
Doc Id: Business_Blueprint_PP_1.0
• Work centers only have an available capacity on working days. In order to
calculate the available capacity, a factory calendar has to be maintained, in whichthe working days are defined.
• You define the work start, work finish and break times for all work centers in a
shift definition.
• In shift sequences, you maintain the sequence of individual shift definitions for allshift sequences.
• The cost center that you want to assign the work center must exist and belong tothe same controlling area as the work center plant.
• At KBEPL we would be defining 3 Activity Types: 1) Machine, 2) Setup, 3) Labour
5) PRODUCTION PLANNING-DEMAND MANAGEMENT:-
5.1 AS-IS AT KBEPL
• Schedule from the customer is on the basis of planning for the Production.
• At times they also receive Customer Order instead of the Schedule; hence theyare using that Customer Order as a reference for production planning.
• Scheduling is done on the basis of customer order which can be monthly /
Quarterly.
• Schedule is then forwarded to the Purchase Dept. who is triggering theProcurement Cycle for Raw material / Semi-finish components / Bought-Out-Parts(BOP) etc. And meanwhile the BOP are received the PPC Department is preparesthe monthly production schedule for each item at FG level for all these
requirements. This gives a day wise item wise schedule for delivery of the FG.• The detailed Monthly production schedule is then circulated to all the concerned
departments in the plant for their necessary action.
• When PPC makes the monthly production plan they manually ensure that the planis as per the capacity of the plant.
• Purchase Dept. also schedules the delivery with the Vendor based on thisschedule received from Customer.
• Raw material and other required components for the production is received at
production to initiate the production activity.
5.2 TO-BE / SAP-PROCESS AT KBEPL
• Production schedules will be created by the system based on the base of PIRinput in the demand management.
• Requirements would be entered in Demand Management. The demandmanagement is the process of entering the requirements of a material that needsto be produced for future sales.
• Customer orders received will be entered in the Sales Module and the datatransfer to Production Planning module is done by the system.
• The requirements will be entered for a finished Product. The system considers therequirements entered in the demand management as the requirement quantities.
Date of issue : Issue 1, Template Version : 1.0 Page 20 of 36Reviewed by: Kishor Joshi Approved by : Atul Joshi
Confidentiality Clause: Adroit InfoTech reserves the copyright on all material and ideas in this document. No material should bereproduced in any form (electronic or written), in part or whole without the express consent of Adroit InfoTech. The contents of this
document are strictly confidential and should not be shared with any other company without the prior permission of Adroit InfoTech.
8/2/2019 63917855-KBEPL-PP-BBP
http://slidepdf.com/reader/full/63917855-kbepl-pp-bbp 21/36
Quality ManagementQuality Management SystemSystem
Doc Id: Business_Blueprint_PP_1.0
• Based on the strategy selected for a material, the system considers other
elements like Sales order, stock etc before arriving at the net quantity that needsto be produced.
• Parameters like Plant, Requirements type (which will be based on the strategy),
For Net requirement planning (LSF), planning period etc. will be made as defaultfor each user who creates the demand.
REPORTING CONSIDERATIONS
• MD63 – Display Independent Requirements
LIST OF BUSINESS PROCESS PROCEDURES (BPP)
• MD61 – Create Independent Requirements
• MD62 – Change Independent Requirements• MD73 – Display Total Requirement
6) PRODUCTION PLANNING-MATERIAL REQUIREMENT PLANNING.
6.1 AS-IS AT KBEPL
• Presently KBEPL is doing the Material Requirement Planning manually.
• They will collect the norms from Quality Management and the same will becirculated to Material management with order quantity and having time to timefollow up with stores people as per planning.\
TO-BE / SAP-PROCESS AT KBEPL
• Planning procedures automatically generate order proposals to purchasing and toproduction. SAP planning procedures can be divided into Material Requirements
Planning.
• The main function of Material Requirements Planning is to give the guarantee of material availability to the shop floor.
• The output of MRP may either be procured or produced.
SOME SALIENT FEATURES OF MRP INCLUDE
• Planned Orders, Schedule lines and Purchase requisitions are generated.• The production or procurement quantity shall be based on the lot sizing
procedure specified for that material in the material master. In order to meetthese requirements, MRP calculates procurement quantities and dates as well asplans the corresponding procurement elements.
• The procurement element in the planning run is the planned order or, for external
procurement, the purchase requisition. Both the procurement elements areinternal planning elements that can be changed, rescheduled or deleted at any
time.
• If a material is produced in-house, the system also calculates the dependentrequirements, that is, the quantity of components required to produce the
finished product or the assembly, by exploding the BOM. If a material shortage
Date of issue : Issue 1, Template Version : 1.0 Page 21 of 36Reviewed by: Kishor Joshi Approved by : Atul Joshi
Confidentiality Clause: Adroit InfoTech reserves the copyright on all material and ideas in this document. No material should bereproduced in any form (electronic or written), in part or whole without the express consent of Adroit InfoTech. The contents of this
document are strictly confidential and should not be shared with any other company without the prior permission of Adroit InfoTech.
8/2/2019 63917855-KBEPL-PP-BBP
http://slidepdf.com/reader/full/63917855-kbepl-pp-bbp 22/36
Quality ManagementQuality Management SystemSystem
Doc Id: Business_Blueprint_PP_1.0
exists, planned orders are created at every BOM level to cover proposedrequirements.
• For external procurement, the system then converts these planned procurement
elements into exact schedule lines set against schedule agreements. Materialsthat are procured externally trigger the purchasing procedure.
• The quantities made available by production or by external procurement areplaced in stock and or managed by inventory management.and are managed by Inventory Management.
CARRYING OUT THE MRP RUN
• MRP shall always be run at multi-level.
• This essentially means that the system explodes the Bill of Material for a material
and generates dependent requirements for assemblies and components.• These components are also planned to cover dependent requirements.
• If the components also have BOMs, the system explodes these BOMs also and
plans the components.
• The system repeats this process until all BOM levels have been exploded.
• While BOM explosion is carried out, the system will check for the status andvalidity of the BOM and shall consider only the specific BOM with active status
and which falls within the defined validity period.
• In specific cases where the dependent material schedule finish date falls laterthan the start date of its higher level material, the system will show exceptionmessages at the MRP list of the dependent material The user shall manuallyreschedule the higher-level material production to suit the schedule of the
dependent material. All materials will be grouped as per the department (as perMRP controller) using the specific material so as to enable each group to viewstock situations of materials relevant to their department. However, MRP shall berun at the material level or Plant level only.
• The systems shall assign number ranges for planned orders at each plant. If
Minimum and Maximum lot size specifies for material in the material master andthe system will create planned order quantities within the above range. In case
where the net requirement exceeds the maximum lot size, the system will createmultiple planned orders.
The possible values which are envisaged to be used in MRP run are:
• Processing key-NETCH
• Create purchase requisition-1,2,3• Delivery schedules-Schedule lines
• Create MRP list-MRP list
• Planning mode-Normal mode
• Scheduling-Lead time scheduling.
The net requirements calculation is carried out in MRP in the planning run after theplanning file check and at plant level. The system checks whether it is possible to coverrequirements with the plant stock and fixed receipts already planned. In the case of a
shortage the system creates a procurement proposal.
Date of issue : Issue 1, Template Version : 1.0 Page 22 of 36Reviewed by: Kishor Joshi Approved by : Atul Joshi
Confidentiality Clause: Adroit InfoTech reserves the copyright on all material and ideas in this document. No material should bereproduced in any form (electronic or written), in part or whole without the express consent of Adroit InfoTech. The contents of this
document are strictly confidential and should not be shared with any other company without the prior permission of Adroit InfoTech.
8/2/2019 63917855-KBEPL-PP-BBP
http://slidepdf.com/reader/full/63917855-kbepl-pp-bbp 23/36
Quality ManagementQuality Management SystemSystem
Doc Id: Business_Blueprint_PP_1.0
LIST OF BUSINESS PROCESS PROCEDURES (BPP)
•
MD01 – Total Planning Run (Plant Level)• MD02 – MRP Run (Single Item Multi Level)
• MD03 - MRP Run (Single Item Single Level)
• MD20 – Create Planning file entry
• MD04 – Display / Stock requirements situation
• MD05 – Display MRP List
• MD16 – Collective display of planned orders
• MD14 – Individual conversion of planned orders
• MD15 – Collective conversion of planned orders
• MDUM – Convert Planned order into Purchase requisitions
List of Transaction Codes related for Long Term Planning:
• MS31 – Create Planning Scenario
• MS32 – Change Planning Scenario
• MS33 – Display Planning Scenario
• MS01 – Total Planning Run (For Long Term Planning)
• MS02 – MRP Run, Single Item Multi Level (For Long Term Planning)
• MS04 – Stock Requirement List (Long Term Planning)
7) MRP CONTROLLER:-
7.1 AS-IS AT KBEPL
• At present the MRP is run by the respective Department, whosoever is in theneed of the material.
7.2 TO-BE / SAP-PROCESS AT KBEPL
We shall be defining an MRP Controller.
• Any material which takes part in Material Requirement Planning will be assigned
to a MRP Controller.
• The Heads of different sections would be the MRP controllers of their respectiveMRP areas.
• The identification of the MRP controllers in the SAP system is through a three digit
numeric code.
• For that purpose, the proposed naming convention of the respective heads will beas follows:
001002003
8) CAPACITY PLANNING:-
Date of issue : Issue 1, Template Version : 1.0 Page 23 of 36Reviewed by: Kishor Joshi Approved by : Atul Joshi
Confidentiality Clause: Adroit InfoTech reserves the copyright on all material and ideas in this document. No material should bereproduced in any form (electronic or written), in part or whole without the express consent of Adroit InfoTech. The contents of this
document are strictly confidential and should not be shared with any other company without the prior permission of Adroit InfoTech.
8/2/2019 63917855-KBEPL-PP-BBP
http://slidepdf.com/reader/full/63917855-kbepl-pp-bbp 24/36
Quality ManagementQuality Management SystemSystem
Doc Id: Business_Blueprint_PP_1.0
AS-IS AT KBEPL
Production in Charge is checking the availability of machines & manpower capacity.Weekly preparation of plan on the basis of monthly plan for each machine, anddisplaying the same. (Fine tuning on daily basis for urgencies)As per production plan, machine load is calculated. Based on this man powerrequirement is generated. If short for the plan, check for overtime to meet the plan.
TO-BE / SAP-PROCESS AT KBEPL
For each planned order/Production order, system will generate the capacity load on that
machine, which can be viewed at any point of time. For checking the manpowercapacity, manpower will be defined as work center of capacity category labor.Accordingly as per the availability of machine, user will convert the planned order intoproduction order, selecting the suitable production version which contains the routingnumber in which that work center is used.
As per the weekly plan, requirements will be given in the system in demandmanagement on weekly basis for a whole month together at the beginning of the month.
And MRP will be run on the basis of this weekly plan once in a month (at the beginningof the month).MRP Will be run on the Plant level.
8.1 PROCESS REQUIREMENT
• Check the Capacity Load on each work center• According to the load on each machine do the Production Planning
• Long term capacity planning to check the available manpower and machines. And
on the basis of this make a decision of either procuring new machine ormanpower
8.2 SCOPE OF THE DOCUMENT
The scope of this document is to check the capacity load on each work center andaccording to the Production planning.
8.3 PROCESS FLOW
8.3.1. GENERAL EXPLANATION
The economic use of resources is an objective for many areas of a company. Thecomponent Capacity Planning (PP-CRP) is available for this purpose.
Capacity planning comprises the following partial components:
CAPACITY EVALUATIONIn the capacity evaluation, available capacity and capacity requirements aredetermined and compared with each other in lists or graphics.
Date of issue : Issue 1, Template Version : 1.0 Page 24 of 36Reviewed by: Kishor Joshi Approved by : Atul Joshi
Confidentiality Clause: Adroit InfoTech reserves the copyright on all material and ideas in this document. No material should bereproduced in any form (electronic or written), in part or whole without the express consent of Adroit InfoTech. The contents of this
document are strictly confidential and should not be shared with any other company without the prior permission of Adroit InfoTech.
8/2/2019 63917855-KBEPL-PP-BBP
http://slidepdf.com/reader/full/63917855-kbepl-pp-bbp 25/36
Quality ManagementQuality Management SystemSystem
Doc Id: Business_Blueprint_PP_1.0
CAPACITY LEVELING
The objectives of capacity leveling are:
• Optimal capacity commitment
• Selection of appropriate resources in most applications, you can use two types of
planning table (graphical and tabular versions) to display the capacity situationand to carry out capacity leveling.
EXPLANATIONS FUNCTIONS AND EVENTS
BUSINESS PROCESS DETAILS
Capacity planning supports planning in all its phases:
• long-term rough-cut planning
• medium-term planning
• short-term detailed planning
8.3.2 PROCESS FLOW
Date of issue : Issue 1, Template Version : 1.0 Page 25 of 36Reviewed by: Kishor Joshi Approved by : Atul Joshi
Confidentiality Clause: Adroit InfoTech reserves the copyright on all material and ideas in this document. No material should bereproduced in any form (electronic or written), in part or whole without the express consent of Adroit InfoTech. The contents of this
document are strictly confidential and should not be shared with any other company without the prior permission of Adroit InfoTech.
Requirements given indemand management
for finished materials
MRP PLANNINGRUN (PLANT LEVEL)
Planned Order createdwith capacity load on
work centermentioned in routing
of that material
Check the total load
on that machine
If load is more on any
work center thanmove the planned
order to other workcenter or change theproduction dates of that planned order
8/2/2019 63917855-KBEPL-PP-BBP
http://slidepdf.com/reader/full/63917855-kbepl-pp-bbp 26/36
Quality ManagementQuality Management SystemSystem
Doc Id: Business_Blueprint_PP_1.0
REPORTING CONSIDERATIONS
• CM01- Work Center Load
• CM02 – Orders• CM50 – Work Center View
•
LIST OF BUSINESS PROCESS PROCEDURES
• CM21 – Planning Table (Graphical)
• CM22 - Planning Table (Tabular)
9) PRODUCTION PLANNING:-
AS-IS AT KBEPL
Production is based on sales order qty.
TO-BE / SAP-PROCESS AT KBEPL
For the machining/fabrication after receiving the material will be reserved for the
processing (as per schedule) through the manual created production order (Work
Order).After that user will book the actual production of that material against thatproduction order.
T-Code: - CO01 /COOIS
9.1 PROCESS REQUIREMENT
Order from on the basis of detailed planning and shop floor execution. All the
intermediates and final product manufacturing will have an order to control its execution.
The document covers details about following for orders all leve
Date of issue : Issue 1, Template Version : 1.0 Page 26 of 36Reviewed by: Kishor Joshi Approved by : Atul Joshi
Confidentiality Clause: Adroit InfoTech reserves the copyright on all material and ideas in this document. No material should bereproduced in any form (electronic or written), in part or whole without the express consent of Adroit InfoTech. The contents of this
document are strictly confidential and should not be shared with any other company without the prior permission of Adroit InfoTech.
8/2/2019 63917855-KBEPL-PP-BBP
http://slidepdf.com/reader/full/63917855-kbepl-pp-bbp 27/36
Quality ManagementQuality Management SystemSystem
Doc Id: Business_Blueprint_PP_1.0
• Order creation(Conversion from planned Order or manual creation)
• Lot Size (Production Planned Quantity)
•
Selection of Order type (Separate Order Types for each Plant)• Selection of production version (Different Production version for different Routing)
• Order Release (Approval for Production Order Execution)
• Inspections lot generation
• Material availability check
Using the order it is expected to control the above said process in shop floor. The Major
expectations from having an order would be
• Scheduling• Capacity requirements analysis
• Material Reservation
• Controlling goods movements
• Booking quantities produced and activities used
• Tracking the cost
9.2 SCOPE OF THE DOCUMENT
The Scope of the document is to create the production orders for Semi finished and
finished products
ORDER TYPES
• Production order with specific order type will be created for each businessprocess, as per requirement. For each Production Plant, separate Order types willbe created. Each Order Types will have the different number range.
• Production Order of forming Material will be created manually. For rework thisalso separate order type will be created to differentiate it with other orders.
Date of issue : Issue 1, Template Version : 1.0 Page 27 of 36Reviewed by: Kishor Joshi Approved by : Atul Joshi
Confidentiality Clause: Adroit InfoTech reserves the copyright on all material and ideas in this document. No material should bereproduced in any form (electronic or written), in part or whole without the express consent of Adroit InfoTech. The contents of this
document are strictly confidential and should not be shared with any other company without the prior permission of Adroit InfoTech.
8/2/2019 63917855-KBEPL-PP-BBP
http://slidepdf.com/reader/full/63917855-kbepl-pp-bbp 28/36
Quality ManagementQuality Management SystemSystem
Doc Id: Business_Blueprint_PP_1.0
9.2.1 PRODUCTION ORDER DESIGN FLOW
No
Yes
Date of issue : Issue 1, Template Version : 1.0 Page 28 of 36Reviewed by: Kishor Joshi Approved by : Atul Joshi
Confidentiality Clause: Adroit InfoTech reserves the copyright on all material and ideas in this document. No material should bereproduced in any form (electronic or written), in part or whole without the express consent of Adroit InfoTech. The contents of this
document are strictly confidential and should not be shared with any other company without the prior permission of Adroit InfoTech.
Production orderfrom R/3 MRP
Planned orderw.r.t.material/Production
Scheduler/Plant
Selection of
Productionversion
If no productionversion (Valid BOM,Routingautomatically copiedto production order)
Availability checkduring production
order creation
Decision for
production order
creation with
missing
parts/capacity
Productionorder creation& Release of orders.
Maintain
production
Maintain Routing
Master Data i.e.Operation time in
each operation,
components.
Maintain Work Center
Master Data.ie.
individual capacity,
capacity utilization,
Factory calendar,
Linkage to cost center.
8/2/2019 63917855-KBEPL-PP-BBP
http://slidepdf.com/reader/full/63917855-kbepl-pp-bbp 29/36
Quality ManagementQuality Management SystemSystem
Doc Id: Business_Blueprint_PP_1.0
REPORTING CONSIDERATIONS
• COOIS – Production Order Information system
• MB25 – Material Reservation list• CO24 – Missing Part list
LIST OF BUSINESS PROCESS PROCEDURES (BPP)
• MD04 - Stock/Requirement list
• CO01 - Production order Creation
• MD04 - Plan order to Production order creation directly.
• CO02 - Production order change
• CO03 - Production order Display
• CO40 – From Planned Order
• CO41 – From Planned Order (collectively)
10) PRODUCTION PROCESS EXECUTION:-
Execution of each production stage is controlled by its orders. The Step involved in
Production order execution are listed below
• Goods issue
• Production Execution start
• Item consumption entry
• Confirmation
• Order settlement
• Technically Completion (TECO)
10.1 SCOPE OF THE DOCUMENT
The scope of this document is of execution of production order for manufacturing of
Semi Finished Good & Finished Good.
Date of issue : Issue 1, Template Version : 1.0 Page 29 of 36Reviewed by: Kishor Joshi Approved by : Atul Joshi
Confidentiality Clause: Adroit InfoTech reserves the copyright on all material and ideas in this document. No material should bereproduced in any form (electronic or written), in part or whole without the express consent of Adroit InfoTech. The contents of this
document are strictly confidential and should not be shared with any other company without the prior permission of Adroit InfoTech.
8/2/2019 63917855-KBEPL-PP-BBP
http://slidepdf.com/reader/full/63917855-kbepl-pp-bbp 30/36
Quality ManagementQuality Management SystemSystem
Doc Id: Business_Blueprint_PP_1.0
10.2 PROCESS FLOW
GENERAL EXPLANATION
A Production order defines which material is to be produced, at which location, at whattime and how much work is required. It also defines which work centers are to be used
and how the order costs are to be settled.
GOODS ISSUE
Before you can start producing a material, all the necessary material components haveto be issued from stock via goods issues. The delivery to stock of the manufacturedmaterial is documented in the system via a goods receipt. Both types of goodsmovement trigger the following transactions in the system:
• A material document is created to record the goods movement.
• The stock quantities of the material are updated.
• The stock values are updated in the material master record and thestock/consumption accounts are updated.
ORDER CONFIRMATION
A confirmation documents the processing status of orders, operations, sub- operationsand Individual capacities. It is an instrument for controlling orders.With a confirmation you specify
• The quantity in an operation that was produced as yield, scrap and the quantity
to be reworked
• How much work was actually done
• Which work center was used for the operation
• Who carried out the operation
Date of issue : Issue 1, Template Version : 1.0 Page 30 of 36Reviewed by: Kishor Joshi Approved by : Atul Joshi
Confidentiality Clause: Adroit InfoTech reserves the copyright on all material and ideas in this document. No material should bereproduced in any form (electronic or written), in part or whole without the express consent of Adroit InfoTech. The contents of this
document are strictly confidential and should not be shared with any other company without the prior permission of Adroit InfoTech.
8/2/2019 63917855-KBEPL-PP-BBP
http://slidepdf.com/reader/full/63917855-kbepl-pp-bbp 31/36
Quality ManagementQuality Management SystemSystem
Doc Id: Business_Blueprint_PP_1.0
After confirmation of production order, following activities takes place in system
• A reduction in the capacity load on the resource
•
An update of the costs, based on the confirmed data• An update of the order vs. production, such as times or order status
• Yield quantity, scrap qty, reason for variance accounting.
• Goods Receipt and Goods Issue
ORDER SETTLEMENT
When a production order is settled, the actual costs incurred for the order are settled toone or more receiver cost-objects (for example, to the account for the materialproduced).
TECHNICALLY COMPLETION OF ORDER
• Technical completion is the completion of a Production order from the logistics
point of view. It is also used when termination of an order is to be done
prematurely, or if the order was not properly executed and want to delete open
requirements of the order (for example, reservations, and capacity
requirements).
• Technically completion of order is necessary from costing point of view. Unless
and until order is technically complete, costing person can’t do the rest of the
costing activities.
Date of issue : Issue 1, Template Version : 1.0 Page 31 of 36Reviewed by: Kishor Joshi Approved by : Atul Joshi
Confidentiality Clause: Adroit InfoTech reserves the copyright on all material and ideas in this document. No material should bereproduced in any form (electronic or written), in part or whole without the express consent of Adroit InfoTech. The contents of this
document are strictly confidential and should not be shared with any other company without the prior permission of Adroit InfoTech.
8/2/2019 63917855-KBEPL-PP-BBP
http://slidepdf.com/reader/full/63917855-kbepl-pp-bbp 32/36
Quality ManagementQuality Management SystemSystem
Doc Id: Business_Blueprint_PP_1.0
• Technical completion of order is possible to do in mass.
11) SAP PROCESS FLOW:-
Logistics General
Production Planning
Master Data
Material
Create Material
Change MaterialDisplay Material
Bill of Material
Create BOM
Change BOM
Display BOM
Work Center
Create Work Center
Change Work Center
Display Work Center
Routing
Create Routing
Change RoutingDisplay Routing
MRP
MRP Run
Total MRP
Single item Multiple Level
MRP List
Stock Requirement List.
Planned Order
Individual conversion to
production order
Collective conversion
production order.Production
Order
Production Order
Create
Change
Release
Order
Confirmation
Production
Confirmation
Partial Confirmation
Date of issue : Issue 1, Template Version : 1.0 Page 32 of 36Reviewed by: Kishor Joshi Approved by : Atul Joshi
Confidentiality Clause: Adroit InfoTech reserves the copyright on all material and ideas in this document. No material should bereproduced in any form (electronic or written), in part or whole without the express consent of Adroit InfoTech. The contents of this
document are strictly confidential and should not be shared with any other company without the prior permission of Adroit InfoTech.
8/2/2019 63917855-KBEPL-PP-BBP
http://slidepdf.com/reader/full/63917855-kbepl-pp-bbp 33/36
Quality ManagementQuality Management SystemSystem
Doc Id: Business_Blueprint_PP_1.0
Final Confirmation
TECO-Completed
.
12) PP STANDARD REPORTS:-
Sr.No. Report Name Report Description T-Code
1 Order Information System The order information system isa tool for shop floor control with
a reporting function forproduction orders and planned
orders.
COOIS
CO28
2 Stock Overview Existing stock overview MMBE
3 Stock / Requirement List Dynamic Listing of current stock MD04
4 Order Progress Report CO46
5 Missing Part Information System Missing Part List Check CO24
6 Material Consumption This report can be used for
analyzing the actual materialusage against plan inmanufacturing process.
MCRE
7 Material List Standard material report MM60
8 BOM Explosion Report on Multi-Level BOM CS12
9 Where-Used List Material Responsible for givinginformation related to Bill of
Materials. Comparison of BOM
between two Materials
CS15
10 Order Information System:
Order View Report
CO26
11 Collective Display of Planned
Orders
MD16
ANNEXURE 1 – PROCESS MAPPING FOR PP
Date of issue : Issue 1, Template Version : 1.0 Page 33 of 36Reviewed by: Kishor Joshi Approved by : Atul Joshi
Confidentiality Clause: Adroit InfoTech reserves the copyright on all material and ideas in this document. No material should bereproduced in any form (electronic or written), in part or whole without the express consent of Adroit InfoTech. The contents of this
document are strictly confidential and should not be shared with any other company without the prior permission of Adroit InfoTech.
8/2/2019 63917855-KBEPL-PP-BBP
http://slidepdf.com/reader/full/63917855-kbepl-pp-bbp 34/36
Quality ManagementQuality Management SystemSystem
Doc Id: Business_Blueprint_PP_1.0
D – Direct fit, W – Work around, N – Not in SAP, C – Customization
ACTIVITY STEP DATA INPUT DATA
OUTPUT
T-CODE
IN SAP
FITN
ESSD/W/N/C
RESPONSIBILITY/
AUTHORIZATION
R
EMA
R K
S
PROCESSING
SYSTEM (SAP,NON-SAP)
Material
Master
Bill of Material
Drawingrequired
Create BOM CS01 D/C MRP Controller SAP
WorkCenter
Codificationrequired
CreateWork Center
CR01 D/C MRP Controller SAP
Routing Set of operations
Create Routing CA01 D/C MRP Controller SAP
DemandManage
ment
Productio
nPlanning
Require
customerorder
includingdrawing.
Production
Schedules willbe created
MD61 D/C MRP Controller SAP
MRP Run MaterialAvailability
(eitherprocured orproduced)
MD02 D/C MRP Controller SAP
CapacityPlanning
Check thecapacityload oneachmachine.
Weeklypreparation of plan on thebasis of monthly plan
for eachmachine
CM01 D/C MRP Controller SAP
Production/Work
ordercreation
Sales order Actualproduction of
that materialagainst thatproductionorder.
CO01 D/C MRP Controller SAP
Production processexecution
Production/Work Order
Goods issue
Item
consumption
entry
Confirmation
CO11MB31
D/C MRP Controller SAP
Date of issue : Issue 1, Template Version : 1.0 Page 34 of 36Reviewed by: Kishor Joshi Approved by : Atul Joshi
Confidentiality Clause: Adroit InfoTech reserves the copyright on all material and ideas in this document. No material should bereproduced in any form (electronic or written), in part or whole without the express consent of Adroit InfoTech. The contents of this
document are strictly confidential and should not be shared with any other company without the prior permission of Adroit InfoTech.
8/2/2019 63917855-KBEPL-PP-BBP
http://slidepdf.com/reader/full/63917855-kbepl-pp-bbp 35/36
Quality ManagementQuality Management SystemSystem
Doc Id: Business_Blueprint_PP_1.0
Order
settlement
TechnicallyCompletion
(TECO)
Date of issue : Issue 1, Template Version : 1.0 Page 35 of 36Reviewed by: Kishor Joshi Approved by : Atul Joshi
Confidentiality Clause: Adroit InfoTech reserves the copyright on all material and ideas in this document. No material should bereproduced in any form (electronic or written), in part or whole without the express consent of Adroit InfoTech. The contents of this
document are strictly confidential and should not be shared with any other company without the prior permission of Adroit InfoTech.
8/2/2019 63917855-KBEPL-PP-BBP
http://slidepdf.com/reader/full/63917855-kbepl-pp-bbp 36/36
Quality ManagementQuality Management SystemSystem
Doc Id: Business_Blueprint_PP_1.0
BUSINESS PROCESS OWNER’S ACCEPTANCE SIGN OFF (BBP)
The Business Blue print (BBP) proposed by Business Process Consultant based on theinformation given by KBEPL representative in the ‘As Is’ workshops conducted. Theproposed solution covers all the existing business requirement of KBEPL developed basedon best practice functionalities supported by SAP. This document will be the base forconfiguring SAP for Production system.
INFORMATION APPROVED BY
Sr.No. Name Designation Date Signature
1 Mr. Uday Gidaveer Production In charge
2 Mr.Sawant Production In charge
3 Mr. Kaushal Production In charge
K.B.E.P.L. MANAGEMENT REPRESENTATIVE
Sr.No. Name Designation Date Signature
1 Mr.P.B.Khanwilkar V.P.
2 Mr.Manish Ojha Project Manager
ADROIT INFOTECH MANAGEMENT REPRESENTATIVE
Sr.No. Name Designation Date Signature
1 Mr.Kishor Joshi Delivery Manager
2 Mr.Ravindranath KC Project Manager
INFORMATION PREPARED AND PROPOSED BY
Sr.No. Name Designation Date Signature
1 Mr.Sandesh Bonde SAP-PP Consultant
Date of issue : Issue 1, Template Version : 1.0 Page 36 of 36