6 design for deep excavation civil engineering
TRANSCRIPT
-
8/13/2019 6 Design for deep excavation civil engineering
1/121
10.1 Introduction
10.2 Design Methods and Factors of Safety
10.3 Retaining Walls
10.3.1 Soldier Piles
10.3.2 Sheet Piles
10.3.3 Column Piles10.3.4 Diaphragm Walls
Ch10 Design of Retaining Structural Components
-
8/13/2019 6 Design for deep excavation civil engineering
2/121
10.4 Structural components in Braced Excavations10.5 Strut Systems
10.5.1 Horizontal struts
10.5.2 End Braces and Corner Braces10.5.3 Wales
10.5.4 Center Posts
10.6 Structural components in Anchored Excavations
-
8/13/2019 6 Design for deep excavation civil engineering
3/121
10.7 Anchor Systems
10.7.1 Components of Anchors
10.7.2 Analysis of Anchor Load
10.7.3 Arrangement of Anchors
10.7.4 Design of Anchor Heads, Anchor Stands, and Wales
10.7.5 Design of the Free Section
10.7.6 Design of the Fixed Section10.7.7 Preloading
10.7.8 Design of Retaining Walls
10.8 Tests of Anchors
10.8.1 Proving Test
10.8.2 Suitability Test
10.8.3 Acceptance Test
10.9 Summery and General Comments
-
8/13/2019 6 Design for deep excavation civil engineering
4/121
10.2 Design Methods and Factors of Safety
The design methods for reinforced concreteworking stress method and
strength design method
The design methods for steel structuresThe allowable stress method (abbreviated as the ASD method)
and the ultimate strength design method.
For diaphragm walls served as permanent structure, the
allowable stress would be magnified by a factor withoutthe earthquake force considered. Some country building
codes suggest =1.25.
-
8/13/2019 6 Design for deep excavation civil engineering
5/121
To design the sections and dimensions of a retaining
wall, the first thing is to carry out the stress analysis.Three methods can be adopted for the stress analysis of
a retaining wall
Assumed hinge method too simple, only suitable on
shallow excavation
Finite element method too complicated for input and
output, need professional geotechnicalengineering training
Beam on elastic foundation method suitable for any
excavation, simple to input and out put, suitable
for common engineer
10.3 Retaining Walls
-
8/13/2019 6 Design for deep excavation civil engineering
6/121
FIGURE 10.1 Typical bending moment and shear diagrams of a retaining wall by
stress analysis
-60 -30 0 30 60
28
24
20
16
12
8
4
-90 -60 -30 0 30 60 900
Shear (t)Bending moment (t-m)
D
epth
(m)
-
8/13/2019 6 Design for deep excavation civil engineering
7/121
The commonly used types of soldier piles in
excavations are the H steel, I steel and rail piles.
10.3.1 Soldier Piles
-
8/13/2019 6 Design for deep excavation civil engineering
8/121
Take the maximum bending moment (M max ) from the
typical bending moment envelope (Figure 10.1).According to the allowable stress method (ASD method),
we can obtain the section modulus of the soldier piles as
a = allowable stress of the steel
l = short-term magnified factor of the allowable stress, which
can be found from the country building codes
a
MSl
max= (10.1)
-
8/13/2019 6 Design for deep excavation civil engineering
9/121
The sections of sheet piles are various. U-shaped, Z-shaped, and line-shaped
sheet piles are frequently used in some countries, as shown in Figure 3.19.
10.3.2 Sheet Piles
( a )
( b )
( c )
FIGURE 3.19 Sections of steel sheet piles (a) U pile (b) Z pile (c) straight pile
-
8/13/2019 6 Design for deep excavation civil engineering
10/121
The dimensions of a sheet pile are determined on the basis
of the results of the stress analysis. According to the
envelope of bending moments (Figure 10.1), take the
maximum bending momentM max and compute the section
modulus using Eq.10.1, which is then used to find the
dimension of the sheet pile
a
MSl
max= (10.1)
-
8/13/2019 6 Design for deep excavation civil engineering
11/121
Column piles used in excavations include the PIP pile,reinforced concrete pile, and the mixed pile.
Column piles bear the axial load and flexural load
simultaneously. Therefore, their behavior is similar to thatof the reinforced concrete columns.
The thus obtained bending moment and shear envelopes
are then used for the design of reinforced concretecolumns. Please refer to the design chart of reinforced
concrete columns or the ACI code.
10.3.3 Column Piles
-
8/13/2019 6 Design for deep excavation civil engineering
12/121
The design of a diaphragm wall includes specifying the wallthickness and the reinforcements.
The thickness is usually determined according to the results
of the stress analysis, the deformation analysis and the
feasibility of detailing of concrete reinforcements.
According to the experience of excavations, the thickness ofa diaphragm wall can be assumed to be 5 %He (He is the
excavation depth) in the preliminary design.
10.3.4 Diaphragm Walls
-
8/13/2019 6 Design for deep excavation civil engineering
13/121
The deformation of the retaining wall in the central section of
the site is usually assumed to be in the plane strain condition
during analysis. Therefore, the unit width (b =1 m) of the
diaphragm wall is usually used for flexural stress analysis.
The definitions of the designed and nominal bending moments
and shears are as follows
l=
MM
u
LF
u
n
MM=
un
VV=
(10.3)
(10.2)
(10.4)
(10.5)
l=
VVu
LF
-
8/13/2019 6 Design for deep excavation civil engineering
14/121
Mu = bending moment for design
Mn = nominal bending moment (capacity of bending
moment)Vu = shear for design
Vn = nominal shear, also called the capacity of shear
M = bending moment obtained from stress analysis
V = shear obtained from stress analysis
LF= load resistance factor; ACI (2005),LF=1.6; ACI
(2002),LF=1.7 = strength reduction factor; ACI (2005),= 0.9 (bending
moment ), = 0.75 (shear); ACI (2002), = 0.9
(bending moment ), = 0.85 (shear)
-
8/13/2019 6 Design for deep excavation civil engineering
15/121
FIGURE 10.3 Stress in the ultimate state on a section of the reinforced concrete
beam (reinforcements are smaller than those in the balanced state)
d
b
sA
0.003
c
c
a
ysfAT=yfys
nM
f 85.0 abfC c= 85.0
2
ad
2a
-
8/13/2019 6 Design for deep excavation civil engineering
16/121
Suppose the thickness (t) of a reinforced concrete beam is
given. The nominal resistant bending moment of concrete ofthe width of b is
d = distance from extreme compression fiber to centroid of
tension reinforcement
= maximum reinforcement ratio that does not contain
compression reinforcement, max = 0.75 b= compressive strength of concrete
= yielding strength of reinforcements
b = reinforcement ratio producing balanced strain conditions
(1) Vertical main reinforcement
max
yfc
f
2max
max 59.011
bdf
ffM
c
y
yR
= (10.6)
-
8/13/2019 6 Design for deep excavation civil engineering
17/121
The balanced reinforcement ratio can be computed as follows
where the measurement unit of and is ; b1 relates to
the strength of concrete, which is generally under 280 .
High performance concrete has used to construct diaphragm
walls recently. Thus, b1 can also be computed by the followingequation
where the measurement unit of and is ; b1 relates to
the strength of concrete.
2kg/cm2kg/cm
2kg/cm0.85-0.05( )0.65
0.85
70
280 kg/cm2
280 kg/cm
2b1= - 280cf
cf
cf
cf
yf
cf
(10.7)b=
y
b
f 6120 +fy
61200.851
cf
(10.8)
yf
-
8/13/2019 6 Design for deep excavation civil engineering
18/121
When Mu MR , the only item to be designed is tensionreinforcements, which can be computed as follows
Let the strength ratio of the material be
Since
m=0.85 cf
yf
259.0
1 bd
f
ffM
M
c
y
ynu
-
8/13/2019 6 Design for deep excavation civil engineering
19/121
We can then have the reinforcement ratio,
deriving from the above equation
The reinforcement ratio, deriving from the
above equation
As = bd
=
2
211
1
bdf
mM
m y
n (10.9)
(10.10)
-
8/13/2019 6 Design for deep excavation civil engineering
20/121
IfMu MR , it follows that the maximum resistance of
concrete (under the condition that the tension
reinforcement has achieved its yielding strength) is still
smaller than the designed bending moment.
That is to say, the diaphragm wall is to be thickened or
compression reinforcements have to be designed.
-
8/13/2019 6 Design for deep excavation civil engineering
21/121
The design of compression reinforcements can follow the
method of the doubly reinforced beam, which is as follows
Let the ratio of the reinforcement be 1= 0.75 b
As1 = 1bd
T1 = As1fy
Cc = T1 = 0.85 ba
From above, we obtain
a =0.85 b
T1
cf
cf
(10.11)
(10.12)
(10.13)
(10.14)
-
8/13/2019 6 Design for deep excavation civil engineering
22/121
The bending moment provided by the tension
reinforcement is
M2 = Mn - M1
Thus, the area of tension reinforcements corresponding to
M2 is
= distance from extreme compression fiber of the wall to
the centroid of compression reinforcements
M1= T1 ( d )2
a
d
As2
=fy ( d )
M2
d (10.17)
(10.16)
(10.15)
-
8/13/2019 6 Design for deep excavation civil engineering
23/121
The required area of tension reinforcements is
As =As1 + As2
The required area of compressive reinforcements is
=Es fy
Es = Young's modulus of reinforcements
= strain of the compression reinforcements, which
can be computed as follows
c = a / b1 (see Figure 10.3)
=As2fy
= ( ) 0.003c c
d
s
s
s
sf
sA
sf
(10.21)
(10.20)
(10.19)
(10.18)
-
8/13/2019 6 Design for deep excavation civil engineering
24/121
The retaining wall with one dimensional deformation does not need to
be reinforced horizontally. If shrinkage and temperature are to be
considered, horizontal reinforcements will be needed. According to
the ACI code, the reinforcement with shrinkage and temperature
effects is
(2) Horizontal main reinforcement
As = 0.0020 Ag 4200 kg/cm2 0.0018 Ag = 4200 kg/cm2 0.00184200/ Ag 0.0014Ag > 4200 kg/cm2 Ag= thickness of the retaining wall unit width;
The reinforcement for shrinkage and temperature effects (As) has
to be placed evenly on both sides of the wall
yf
yf
yf
yf
(10.22)
-
8/13/2019 6 Design for deep excavation civil engineering
25/121
According to the ACI code, the nominal shear ofconcrete is
Vc is the nominal shear of concrete and is measured by
kg. The unit of is kg/cm2
. b is the unit width and isusually taken to be 100 cm.
When the designed shear (Vu) is smaller thanfVc, it is
theoretically unnecessary to design reinforcement. Inpractice, the shear reinforcement still has to be
designed in order to be able to hang the steel cage into
the trench.
(3) Shear reinforcement
Vc = 0.53 bdcf
cf
(10.23)
-
8/13/2019 6 Design for deep excavation civil engineering
26/121
FIGURE 10.2 Plan, 3D view, side view of a steel cage of diaphragm wall
(1, 2, and 3 represent shear reinforcements)
b
b
A
C
E
F
B
D
A
C
E
F
A C
B D
1
1
1
2 2
2 2
2
3 3
3
3
3
Vertical main renforcement
Plan
Horizontal
reinforcement
Vertical main
reinforcement
Side view3-D
view
Horizontal
reinforcement
Sv
Sv
Sv
Sv
Sv
Sv
Sv
Sv
Sv
Sh
Sh
Sh Sh Sh Sh
Sh Sh Sh
-
8/13/2019 6 Design for deep excavation civil engineering
27/121
Three types of shear reinforcements are used in the steelcage of a retaining wall, main shear reinforcement-type 1,
and two small slant reinforcements-type 2, and 3. As a
result, the nominal shear (capacity of shear) of the
retaining wall per unit width is
Vn = Vc + Vs
where Vs is nominal shear of shear reinforcements
(10.24)
-
8/13/2019 6 Design for deep excavation civil engineering
28/121
Since the horizontal distance between any two shear
reinforcements is identical, the sectional area of the shearreinforcement per unit width (b = 100 cm) is
Av = total sectional area of all shear reinforcements on the
horizontal section per unit width (cm2)
Ab = sectional area of a single shear reinforcement (cm2)
Sh = horizontal distance between shear reinforcements (cm)
Av=100Ab
Sh(10.25)
Th i l h f th t 1
-
8/13/2019 6 Design for deep excavation civil engineering
29/121
The nominal shear of the type 1
Sv =vertical distance between the main shear reinforcements
The nominal shear of the type 2
= angle between the small slant reinforcement and thehorizontal reinforcement
The nominal shear of the type 3
b = angle between the small slant reinforcement and the vertical
reinforcement
The nominal shear offered by all shear reinforcements per unit
width is
Vs1 = Sv
Avfy d
Vs2 = SinSv
Avfy d
Vs3 = Sin bSv
Avfy d
Vs = Vs1 + Vs2 + Vs3
(10.28)
(10.27)
(10.29)
(10.26)
-
8/13/2019 6 Design for deep excavation civil engineering
30/121
Minimum lap splice length and development length of reinforcements
of a diaphragm wall can be designed according to the ACI code, or
they can be determined using Eqs.10.30 and 10.31. The coefficient1.25 is to magnify the lap splice length and development length,
considering the effects of concrete casting in bentonite, which leads to
a smaller bond stress
Development length
Lap splice length
Ab = the sectional area of a single reinforcement; if applied a vertical
reinforcement, c = 1.0to horizontal reinforcement, c = 1.4
(4) Lap splice length and development length
Ld = 1.25cld = 0.075c Abfy
Ld = 1.25cld =0.091c Abfy
cf
cf
(10.30)
(10.31)
-
8/13/2019 6 Design for deep excavation civil engineering
31/121
FIGURE 10.5 Design of reinforcements in a steel cage of the diaphragm wall
(a) profile (b) side view
(a) (b)
Floor slab
Raft foundation
Inside the
excavation zone
Outside the
excavation zone
-
8/13/2019 6 Design for deep excavation civil engineering
32/121
FIGURE 10.6 Components of a strutting retaining system
Soldier pile
Lagging
Horizontal
struts
Wale
Center post
Sheetpile
Jack
Jack
End brace
Corner brace
10.4 Structural components in Braced Excavations
-
8/13/2019 6 Design for deep excavation civil engineering
33/121
FIGURE 10.7 Single strutting system
End brace
waleRetaining wall
Horizontal struts
-
8/13/2019 6 Design for deep excavation civil engineering
34/121
X
Horizontal strutof the higher level
Horizontal strut
of the lower level
Y
U-clip
Center
post
(b)(a)
FIGURE 10.8 Joint of a single strut and a center post (a) 3D view (b) plan view
U clip
Bracket
Horizontalstrut of the
higher level
Horizontal strut of the
lower level
Center post
xe
-
8/13/2019 6 Design for deep excavation civil engineering
35/121
FIGURE 10.8 Joint of a single strut and a center post (c) photo
-
8/13/2019 6 Design for deep excavation civil engineering
36/121
FIGURE 10.9 Double strutting system
End braces
Retaining wall
Horizontal struts
-
8/13/2019 6 Design for deep excavation civil engineering
37/121
Horizontal strut of the higher level
U-clip
Horizontal strut
of the lower
level Center postHorizontal
strut of the
higher level
U-clip
Horizontal strut of the lower level
Center post
(a) (b)
FIGURE 10.10 Joint of a double strut and a center post (a) 3D view (b) plan view
-
8/13/2019 6 Design for deep excavation civil engineering
38/121
FIGURE 10.10 Joint of a double strut and a center post (c) photo
10 5 Strut Systems 10 5 1 H i t l t t
-
8/13/2019 6 Design for deep excavation civil engineering
39/121
10.5 Strut Systems 10.5.1 Horizontal struts
(1) Stress computation
A strut is usually subjected to the axial compressive load as well as
the flexural load. The axial compressive stress can be computed as:
N
Afa =
A = sectional area of the strutN = axial load =N 1 +N2
N1 = strut load induced by excavation, which can be computed
using the beam on elastic foundation method, the finite
element method, or the apparent earth pressure methodN2 = strut load induced by the temperature change = DtEA
= coefficient of thermal expansion of struts; for the steel strut,
= 1.32 10 5 /
Dt = temperature change of struts ()
E = Young's modulus
(10.32)
-
8/13/2019 6 Design for deep excavation civil engineering
40/121
Because the result using DtEA to compute the effect of
temperature change of the strut load,N2, usually comes
out too large, the empirical formula is often used
instead.
The JSA (1988) suggests
N2 = 10 t ~ 15 t orN2 = ( 1.0 t ~ 4.0 t ) Dt, where
Dtis the temperature change () in the air (not thetemperature change of the steel).
-
8/13/2019 6 Design for deep excavation civil engineering
41/121
The flexural stress can be computed as follows
M1 = bending moment produced by the strut weight and the live load;
taking the center post as the simply supported hinge, thenM1 =
wL2
/8w = strut weight + live load 0.5 t/m
L = distance between two adjacent center posts
M2 = bending moment caused by the uplift of the center post; since
struts are constructed level by level during excavation, the
influence ofM2 on the top level would be largest while that on
the lowest level would be largest while that on the lowest level
would be the smallest
S= section modulus
M1 +M2S
fb = (10.33)
(2) Allowable stress
-
8/13/2019 6 Design for deep excavation civil engineering
42/121
The allowable axial compressive stress of a strut can be selected from the tables
and figures offered by the AISC Specification or using the following equation
KL / ry = effective slenderness ratio of the strut on the flexural plane where K can
be taken as 1.0
L = unsupported length of the strut, usually distance between the two adjacent
center posts
ry = radius of gyration of the cross section of the strut in the direction of theweak axis
Cc = critical slenderness ratio =
E= Young's modulus of struts
Fy = yielding stress of struts
l = short-term magnified factor of the allowable stress, which can be found incountr buildin code, l = 1.25.
( ) owab e s ess
KLry
> Cc
KLry
Cc
l
=3
/
8
1/
8
3
3
5
/
2
1
1
c
y
c
y
c
y
a
C
rKL
C
rKL
FC
rKL
Fy
l
= 2
2
23
12
y
a
r
KL
EF
yFE/22
(10.34)
(10.35)
-
8/13/2019 6 Design for deep excavation civil engineering
43/121
The allowable flexural stress (Fb) of a strut can be
derived from the tables and figures offered by the
AISC Specification.
However, the flexural stress (fb) of a strut, during
normal excavation (that is, the uplift of the center post
is not much), is not large. To simplify the design, wecan assumeFb = 0.6Fyl.
(3) E i ti f bi d t
-
8/13/2019 6 Design for deep excavation civil engineering
44/121
According to the AISC Specification, the stress on each section of a strut
should satisfy the following equation
Cm = coefficient of modification = 0.85
1 /(1 fa / = amplification factor= allowable Euler stress = l122E / [23KL / rx2]
KL / rx = effective slenderness ratio on the flexural plane, we can
assumeK= 1.0
rx = ratio of gyration of the strut in the direction of the strong axis
E= Young's modulus of struts
l = short-term magnified factor of the allowable stress, which can be
found in country building codes, we can assume l = 1.25
(3) Examination of combined stresses
+ 1.0fa
Fa 15
faFa
fbFb
faFa
> 15
eF
0.1
1
be
a
bm
a
a
FF
f
fC
F
f
(10.36)
(10.37)
-
8/13/2019 6 Design for deep excavation civil engineering
45/121
10.5.2 End Braces and Corner Braces
FIGURE 10.11 Distance and angle between struts and end braces or corner braces
2
211 1
3
1 2 3 2 4
6
5
p
p
L1 L2
-
8/13/2019 6 Design for deep excavation civil engineering
46/121
The axial force on the end brace is
p = apparent earth pressure or the strut load per unit width
1 2 = spans (see Figure 10.11)
1 = angle between the end brace and the wale
(usually 45)
N =p 12 1 + 2 Sin1 (10.38)
-
8/13/2019 6 Design for deep excavation civil engineering
47/121
The axial force on an corner brace is
3 4 5 6 = the spans
23 = angles between the corner brace and the wale,
45 in most cases
To be conservative, the design load can be assumed to be
the maximum value betweenN1 andN2 .
N1 =p 12 3 + 4 Sin2N2 =p 12
5 + 6
Sin3 (10.40)
(10.39)
-
8/13/2019 6 Design for deep excavation civil engineering
48/121
The function of wales is to transfer the earth pressure
on the retaining wall to the struts.
For analysis, the earth can therefore be assumed toact on the wale directly.
The earth pressure can be obtained from the apparent
earth pressure method or by transforming the strut
load, computed using the finite element method or
beam on elastic foundation method.
10.5.3 Wales
-
8/13/2019 6 Design for deep excavation civil engineering
49/121
The wale is usually acted on by the earth pressure as
well as the axial force from the end brace or corner
brace. That is to say, the wale bears simultaneously
the moment and the axial force and its design falls in
the domain of the beam-column system. With ample
lateral support, the analyses of secondary moment and
buckling for wales can be saved.
-
8/13/2019 6 Design for deep excavation civil engineering
50/121
FIGURE 10.12 Computation of the bending moment of a wale
L
Joint
p
WaleStrut
Earth pressure
Fixed end beam mode
Simplly supported beam modeAnalysis method
considering weak joints
Mmax = pL2
8
1 Mmax pL210
14
L
Mmax = pL212
1
To compute the maximum bending moment and shear of wales the wales can be
-
8/13/2019 6 Design for deep excavation civil engineering
51/121
To compute the maximum bending moment and shear of wales, the wales can be
viewed as simply supported beams with struts as supporting hinges, or viewed as
fixed end beams.
Simply supported beam
Fixed end beam
Mmax = maximum bending moment of the wale
Qmax = maximum shear of the wale
L = distance between struts
p = earth pressure
Mmax = pL281
Qmax = pL2
1
Mmax = pL212
1
Qmax = pL2
1
(10.41a)
(10.41)
(10.42a)
(10.42)
-
8/13/2019 6 Design for deep excavation civil engineering
52/121
Mmax pL210
1
Because the length of a wale is limited, the wales
have to be joined in the field. The strength of the
joint is not fully rigid and the joint could easily
become the weakest part of the structure. Thus,
the joints had better be located at the places
where the stress is smaller.According to the bending moment distribution
diagram of a continuous or a simply supported
beam, if the joint is located at theplaces 1/4 of
the span from the support, the maximum bendingmoment of the wale would be
(10.43)
-
8/13/2019 6 Design for deep excavation civil engineering
53/121
In design practice, if the wale is assumed to be a
simply supported beam, it may not work out as
economical.
If it is designed to be a fixed end beam, it may tend
to be insecure. The more reliable method is to
locate the joint at theplace 1/4 of the span from the
support and compute the maximum bending
moment and shear as follows
Mmax = pL2101
Qmax = pL2
1
(10.44)
(10.44a)
-
8/13/2019 6 Design for deep excavation civil engineering
54/121
When there are no end braces,L is the horizontaldistance between struts.
When there are end braces, the distance between struts
can be reduced properly.
Generally speaking, when 60 ,L = 1 + 2. When
> 60 , less conservative design can be madeL = 1
-
8/13/2019 6 Design for deep excavation civil engineering
55/121
Viewed from the view point of mechanics, the wale is also
subjected to the axial stress.
If sheet piles or soldier piles with end braces are used, the
axial force of the wale can be designed by choosing the
larger one between the following two computing results
or
N = p 12 1 + 2 tan1N = p 5 + 2 6 (10.45)
(10.46)
-
8/13/2019 6 Design for deep excavation civil engineering
56/121
Since the corners of a diaphragm wall have an arching
effect, to determine the axial load of a wale around a
corner of an excavation with diaphragm walls, it is
necessary to use Eq. 10.46.
If sheet piles or soldier piles are used, take the
maximum value among the computed results of Eqs.
10.45 and 10.46.
-
8/13/2019 6 Design for deep excavation civil engineering
57/121
10.5.4 Center Posts
Center post are usually set to
bear the weight of struts, the materials on the struts,
and other extra loading out of the movement of the
retaining system.
Center posts, usually H steels,
(1) installed by striking the piles into soils directly.
(2) embedment into soils by way of pre-boring or
inserted into a cast-in place pile.
-
8/13/2019 6 Design for deep excavation civil engineering
58/121
FIGURE 10.13 Installation of center posts onto cast in-situ piles
Cast-in-place pile
Retaining
wall
Central post
Horizontal strut
-
8/13/2019 6 Design for deep excavation civil engineering
59/121
The design of a center post includes the design of the section and
the embedment depth.
The possible axial loads on each center post are
(1) Weight of the horizontal strut and the live load,P1
wi = strut weight of each level and its live loadL1,L2 = distance between struts
n = number of the levels
p1= wi (L1 +L 2 )n
i=1
FIGURE 10.14 Distribution of strut weight on a center post
L1
L1
L2L2
(10.47)
-
8/13/2019 6 Design for deep excavation civil engineering
60/121
(2) Weight of the center post above the excavation
surface,P2
-
8/13/2019 6 Design for deep excavation civil engineering
61/121
(3) Slant compressive force on the horizontal strut,P3
Suppose the tilt angle of a horizontal strut is , the downward or
upward force on the center post would be
sin)(2 ,,1
3 iyix
n
i
NNP ==
(10.48)
= load on the struts of each level in thex direction
= load on the struts of each level in they direction= tilt angle of the horizontal strut
ixN ,
iy
N,
FIG. 10.15 Action of the axial force of struts on a center post
(a) when the center post settles (b) when the center post heaves
where
1,yN
1,yN
1,yN
1,yN1,xN
1,xN
1,xN
1,xN
2,yN
2,yN
2,yN
2,yN2,xN
2,xN
2,xN
2,xN
(a) (b)
The first level
of struts
The second level
of struts
-
8/13/2019 6 Design for deep excavation civil engineering
62/121
In analysis, the tilt angle of the horizontal strut is
difficult to estimate. According to the data of field
observations of excavations, the tilt angle can beassumed to be sin1/50.
To be conservative in analysis, the center post can be
assumed to be subject to the axial force of the strut and
downward force. Thus, the total load on the center post
would be
(10.49)321 PPPP =
In the double strutting system the moments generated by the weight of
-
8/13/2019 6 Design for deep excavation civil engineering
63/121
In the double strutting system, the moments generated by the weight oftwo struts, which eccentrically act of the center post, can be assumed to
be mutually offset.
Horizontal strut of the higher level
U-clip
Horizontal strut
of the lower
level
Center post Horizontalstrut of the
higher level
U-clip
Horizontal strut of the lower levelCenter post
(a) (b)
FIGURE 10.10 Joint of a double strut and a center post (a) 3D view (b) plan view
-
8/13/2019 6 Design for deep excavation civil engineering
64/121
In the single strutting system, the moment caused by the strut
weight eccentrically acting on the center post can be computed
by the following equation
(10.50)= eccentricity distance
xePPM )( 32xe
FIGURE 10.8 Joint of a single strut and a center post (a) 3D view (b) plan view
X
Horizontal strut
of the higher level
Horizontal strut
of the lower level
Y
U-clip
Center
post
(b)(a)
U clip
Bracket
Horizontal
strut of the
higher level
Horizontal strut of the
lower level
Center post
xe
Buckling length
-
8/13/2019 6 Design for deep excavation civil engineering
65/121
The buckling length of a center post should take the maximum
unsupported length during the process of excavation, floor
construction and dismantling. the buckling length of the center
postL is(10.51)),,,,max( 54321 LLLLLL=
Strut Center post
etaining wall
Excavation bottom
Raft foundationFloor slabs
213,usually LLL
FIGURE 10.16 Unsupported length of center posts
1L
2L
3L
4L5L
-
8/13/2019 6 Design for deep excavation civil engineering
66/121
Because the center post bears, simultaneously, the
axial force and bending moment, it is the beam-
column system that is to be adopted in analysis.Choose a proper section and then use Eq.
10.47~10.51 to examine it.
-
8/13/2019 6 Design for deep excavation civil engineering
67/121
The center post may bear
(1) vertical loads
(2) uplift forces caused by the tilt of the horizontal
strut.
The analysis method is identical with that
for piles though a pile is of circular section.
-
8/13/2019 6 Design for deep excavation civil engineering
68/121
FIGURE 10.17 Area to be adopted for the computation the vertical
bearing capacity of center posts of the H pile
columntheofdepthembedded)(2 =
=
HBA
HBA
s
p
B
H
1t
2t
(1) Vertical bearing capacity
-
8/13/2019 6 Design for deep excavation civil engineering
69/121
(1) Vertical bearing capacity
The ultimate vertical bearing capacity can be expressed as :
(10.52)
= ultimate vertical bearing capacity of the center post
= point load resistance of the center post
= skin frictional resistance of the center post
= unit frictional resistance of the center post
= surface area of the center post
= the unit point resistance per unit area of the center post
= sectional area of the center post
The allowable vertical bearing capacity of the center post is
(10.53)
= allowable vertical bearing capacity
= factor of safety
ppssspu AqAfQQQ ==uQ
pQ
sQ
s
f
sApq
pA
FSQQ
FSQQ psua ==
aQ
FS
-
8/13/2019 6 Design for deep excavation civil engineering
70/121
Under general conditions (low possibility of
earthquake, general excavation, good
geological conditions), the above factor ofsafety can be taken to beFS=2.0.
If considering the possibility of earthquakeor the excavation is of high risk (in soft soils,
for example), the above factor of safety can
be taken to beFS=3.0.
-
8/13/2019 6 Design for deep excavation civil engineering
71/121
In sandy soils, the point resistance of the center
post can be computed as
Driven pile (10.54)
Drilling pile (10.55)
N= the average standard penetration number within the influence
range of the bottom end of the center post.
Generally speaking,Nvalue can be taken as the average value
within the range four times of the center post diameter above the
bottom end of the center post diameter below it.
Nfp
40=
2/mtNfp 15=
2/mt
The frictional resistance of the center post for both the driven and
-
8/13/2019 6 Design for deep excavation civil engineering
72/121
drilling piles is
N= the average standard penetration number within the depth of the center postembedded in the sandy soils
In clayey soils, to be conservative, the value of the center post is
usually assumed to be 0 and the can be computed as follows
= adhesion between the surface of the center post and the surrounding soils
= undrained shear strength of clay
= reduction value of undrained shear strength.
-values relates to the undrained shear strength of the clay, the installation method of
the center post, and its embedment depth. Besides, the cast-in-situ piles embedded in
clayey soils have lower -values because they do not compress the soil during the
construction and are usually installed in boreholes filled with bentonite. Skempton
suggests the -value be between 0.3 and 0.6, 0.45 in most cases.
Nfs 2.0=2/mt
pf
uws scf ==wcus
sf
(10.56)
(10.57)
-
8/13/2019 6 Design for deep excavation civil engineering
73/121
API
0.0 0.2 0.4 0.6 0.8 1.00.0
0.2
0.4
0.6
0.8
1.0
1.2
vu/s
Cast-in-
place pile
FIGURE 4.12 Relation between adhesion and undrained shear strength of clay
(2) Pullout resistance
-
8/13/2019 6 Design for deep excavation civil engineering
74/121
(2) Pullout resistanceThe allowable pulling out resistance of a center post is
(10.58)
= weight of the center post, the influence of groundwater
considered= frictional resistance per unit area of the center post,
which can be estimated using Eq. 10.57 or Eq. 10.58
= surface area of the center post
= factor of safety. As far as the sort-term behavior of a
structure (such as a center post) is concerned,FScan be
assumed to be 3.0
sspa AfFS
WR 1=
pW
sf
sA
FS
10 6 Structural components in Anchored Excavations
-
8/13/2019 6 Design for deep excavation civil engineering
75/121
10.6 Structural components in Anchored Excavations
FIGURE 10.18 Anchored excavation
m2
Anchor head
Anchora
gesection
Potentialfailu
resurfa
ce
Excavation surface
Freesect
ion
10 7 Anchor Systems
-
8/13/2019 6 Design for deep excavation civil engineering
76/121
Anchors are categorized into permanent anchors andtemporary ones. They are applied extensively. The design
of an anchor involves the soil properties, the materials of
the anchor, grouting, and the construction details. The last
is especially crucial in determining the quality of theanchor. Concerning the general rules of the design and
construction of an anchor, please refer to related literature
and specifications referred to in this section.
Anchors in excavations belong to the category of
temporary anchors. This section will only introduce the
anchor system of the retaining wall in excavations.
10.7 Anchor Systems
General rules of anchor
-
8/13/2019 6 Design for deep excavation civil engineering
77/121
General rules of anchor
American Association of Sate Highway and Transportation Officials
(AASHTO) (1992)British Standard Institute (BSI DD81)(1989)
Deutsche Industrie Norm (DIN) (1988)
Federation Internationale de la Precontrainte (FIP) (1982);
Post-Tensioning Institute (PTI) (1980)
Geotechnical Control Office (GCO)(1989)
JSF(1990)
A h i b i ll d f th h
-
8/13/2019 6 Design for deep excavation civil engineering
78/121
An anchor is basically composed of the anchor
head, the free section, and the fixed section.
FIGURE 10.19 Configuration of an anchor
Anchor head
Anchor stand
Retaining wall
Casing
Cement mortar Tendon
)(anchortheofLength L
)(sectionfreef
L
)(sectionfixeda
L
Types of anchor heads
-
8/13/2019 6 Design for deep excavation civil engineering
79/121
FIG. 10.20 Types of anchor heads (a) locked by wedges (b) locked by screw nuts
(c) composite lock (CICHE, 1998)
clips Male awl
Female awl
Screw nut
PC steel bar
Screw nut
Steel strandsteel bar connector
Multiple PC steel strand
(a)
(b) (c)
Anchors can be categorized into the resistance type, the bearing
-
8/13/2019 6 Design for deep excavation civil engineering
80/121
resistance type, and the composite type according to the characteristics of
the bearing force provided by the fixed section.
FIG. 10.21 Types of anchorage body (a) frictional resistance type (b) bearing resistance type
(c) composite resistance type
Tension type
Compression type
Bearing body
Bearing resistance type
Composite (friction + bearing)
resistance type
Frictional resistance type{
-
8/13/2019 6 Design for deep excavation civil engineering
81/121
The horizontal component of the anchor
load can be computed using the half
method or underneath pressure methodof the apparent earth pressure method.
The related analytical method is identical
to that for the braced excavation.
10.7.2 Analysis of Anchor Load
-
8/13/2019 6 Design for deep excavation civil engineering
82/121
FIGURE 10.23 Anchorage force and its horizontal component
(Horizontal component )
(Anchorage force )
-
8/13/2019 6 Design for deep excavation civil engineering
83/121
The anchor load is
(10.59)
where = designed load of the anchor= horizontal component obtained from analysis
= angle between the axis of the anchor and the
horizontal plane
cosPT
w=
wTP
-
8/13/2019 6 Design for deep excavation civil engineering
84/121
In literature and specifications on anchors, group anchor
effects are seldom discussed. The design of anchor is
usually based on a single anchor pattern. Under suchconditions, the minimum distance between anchors has to be
limited so that the group anchor effect will not be produced
or the installation of an anchor may cast a bad influence on
the adjacent anchors. Table 10.3 lists the related
specifications on the minimum distance between anchors.
10.7.3 Arrangement of Anchors
-
8/13/2019 6 Design for deep excavation civil engineering
85/121
TABLE 10.3 Specifications for the minimum distance between the fixed sections
bdNote : refers to the diameter of the anchorage section
or 1.2 m
Larger than 4
Larger than 4
Larger than 6
Larger than 4
For anchors with working load large than 70 tons, the
minimum center-to-center distance of the anchorage
section is 1.0 mFor anchors with working load largerthan 130 tons, the minimum center-to-center distance of
the anchorage section is 1.5 m
DIN(1988)
AASHTO(1992)
or 1.2 mPTI(1989)
, generally 1.5 m to 2.0 m in applicationBSI(1989)
, or not shorter than 1.5 mFIP(1982)
Suggested minimum distanceRule
bd
bd
bd
bd
-
8/13/2019 6 Design for deep excavation civil engineering
86/121
The determination of the vertical distance between
anchors depends on the analytical results of theanchor load. The vertical distance between anchors
is about 2.5~4.5 m and at least 1.0~1.5 m above the
floor slabs. Besides, both FIP (1982)and BSI (1989)require the vertical distance between the fixed
section and underground structure be longer than 3
m. The fixed section has to be 5 m away from theground surface (see Figure 10.24).
The anchorage length must be embedded within the shadow area and
k di h 1 8 f h d f il f
-
8/13/2019 6 Design for deep excavation civil engineering
87/121
FIGURE 10.24 Locations of the anchorage sections in soil (redraw after BSI, 1989)
keep a distance more than 1.8 m from the assumed failure surface
Assumed failure surface
Assumed support
Depth
C B
D
A E
F
G
2/45o
2/45
o
2/45 o
Locations of the anchorage sections
-
8/13/2019 6 Design for deep excavation civil engineering
88/121
FIGURE 10.25 Distance between an anchorage section and the potential failure surface
Assumed failure surface
(potential failure surface)
2 m
b d f
-
8/13/2019 6 Design for deep excavation civil engineering
89/121
FIGURE 10.26 Potential failure surfaces in excavations
Excavation surface
Assumed supports
Wall bottom 2
45
C
a
b d f
e
The installation angle of anchors
-
8/13/2019 6 Design for deep excavation civil engineering
90/121
g
Theoretically, if an anchor is installed with the same direction of
loading, it is able to develop the maximum capacity.
Considering the installation quality, to clear the dregs in the drillingbore of the anchor, the installation angle should not be smaller than 10.
The fixed section should be placed in a bearing layer (such as a
sandy layer, gravelly layer, or rocks) or soils with high strength.
Generally speaking, the deeper the soils, the higher the strength. It ismore suitable to place the fixed section in deeper soil. As a result, an
anchor is usually installed with a certain slope. The steeper the slope,
however, the larger the dragging down force on the retaining wall.
When the installation angle exceeds 45, it becomes dangerous.
That is to say, without going beyond 45, the installation angle
should fall within the range .
4510
10 7 4 Design of Anchor Heads Anchor Stands and
-
8/13/2019 6 Design for deep excavation civil engineering
91/121
The locking device should be tested before using and its
locking capacity should be large enough to make the
tendon bear 80% of the ultimate loading without being
damaged. If the locking device is used with a wedge clip,the locked tendon should not slide too much. The bearing
strength of the bearing plate should be large enough to
resist the maximum pulling force during the process of
preloading and excavation.
10.7.4 Design of Anchor Heads, Anchor Stands, and
Wales
-
8/13/2019 6 Design for deep excavation civil engineering
92/121
The function of an anchor stand is to transfer the load on the wale
or the retaining wall to the anchored soil layer. Anchor stands
can be categorized into reinforced concrete anchor stands and
steel anchor stands. The detailing of reinforcements of the
concrete anchor stand should be carefully designed to meet safety
requirements. Under the working load, the allowable
compressive stress of the concrete anchor stand should be smaller
than 30% of the 28th-day strength of concrete.
-
8/13/2019 6 Design for deep excavation civil engineering
93/121
FIGURE 10.27 Commonly used anchor stands
Steel bond
Steel anchorstandWale
Retaining wall
Anti-erosion
materialsConcrete anchor
stand
Bearing
plate
Steel anchor stand
L1
-
8/13/2019 6 Design for deep excavation civil engineering
94/121
Steel bond
Wale
hor stand
Lower/ upper brackets
Upper wale
Anchor stand
Lower wale
Soldier pile
FIGURE 10.28 Configuration of wales in anchored system
PL1
Pv
Anchor force
L1
L2
The stress of a wale can be examined as follows
-
8/13/2019 6 Design for deep excavation civil engineering
95/121
(1) Stress computation in the direction of strong axis
Viewing the wale between two anchors as a simplysupported beam structure, the maximum bending
moment and shear are(10.60)
(10.61)
where = maximum bending moment in the direction ofstrong axis
= maximum shear in the direction of strong axis
= lateral earth pressure on the wale
= horizontal distance between anchors
2
1max 8
1
pLM
1max2
1pLQ
maxM
maxQ
p
1L
A i h d i f l i h b d i
-
8/13/2019 6 Design for deep excavation civil engineering
96/121
As in the design of a wale in the braced excavation
introduced in Section 10.5.3, if the joint is placed at
the distance of 1/4 of the span from the support, themaximum bending moment can be computed by the
following equation
(10.62)2max
10
1pLM =
The bending stress and shear stress of the wale in the direction of
-
8/13/2019 6 Design for deep excavation civil engineering
97/121
The bending stress and shear stress of the wale in the direction of
the strong axis should satisfy the following criteria:
(10.63)
(10.64)
= section modulus of the member in the direction of thestrong axis
= area of the web of the member
= allowable bending stress of the member=(0.6~0.66)
= allowable shear stress of the member=0.4
= yielding stress of the member
=short-term magnified factor of the allowable stress
axS
M
2/max
awA
Q 2/max
xS
wA
a
ly
Fa
yF
l
lyF
(2) Stress computation in the direction of the weak
-
8/13/2019 6 Design for deep excavation civil engineering
98/121
axis
Viewing the wale between the brackets supporting the anchor as a
beam, the maximum bending moment and shear of the wale are
(10.65)
(10.66)
(10.67)
= maximum bending moment in the direction of weak axis
= maximum shear in the direction of weak axis
= vertical component of the anchorage force at the support
= distance between the brackets supporting the anchor
tan1pLPv=tan4
1
4
1212max LpLLPM v
tan2
1
2
11max pLPQ v=
maxM
maxQ
vP
2L
The bending stress and shear stress of the wale in the direction of the
k i h ld ti f th f ll i diti
-
8/13/2019 6 Design for deep excavation civil engineering
99/121
weak axis should satisfy the following conditions
= section modulus of the member in the direction of weak axis
= area of a single flange of the member
= allowable bending stress of the member=0.75
= allowable shear stress of the member=0.4
= yielding stress of the member= short-term magnified factor of the allowable stress
ayS
M
2/max
afA
Q 2/max
yS
fA
a lyF
a
yFl
lyF
(10.68)
(10.69)
10 7 5 Design of the Free Section
-
8/13/2019 6 Design for deep excavation civil engineering
100/121
The free section is composed of a tendon and a plastic
casing. Three types of tendons are availablesteel bars,steel wires, and strands. The 7-wire strand is common in
many countries, usually available in size of 13 mm(0.5 1n),
15mm (0.6 in) and 18 mm (0.7 in). The ultimate tensile
strength varies from 1570 to 1765 N/mm2
. The allowabletensile force can be computed as follows
(10.70)
where = designed safety factor for the tendon. Table 10.4
lists the commonly used factors of safety.
tuw FPP /=
tF
10.7.5 Design of the Free Section
TABLE 10.4 Factor of safety for single anchor
il f h i
-
8/13/2019 6 Design for deep excavation civil engineering
101/121
ClassificationTensile force
of tendons
( )
Anchoring
force
( )
Bond force of
tendons ( )
Temporary anchors whose working
period is not longer than 6 months and
which dont affect public safety when
failing(2)
1.4 2.0 2.0
Temporary anchors whose workingperiod is not longer than 2 years and
which dont affect public safety,
though having certain influence, when
failing without alert
1.6 2.5 (3) 2.5 (3)
Permanent or temporary anchors which
are highly risky in rusting or which
affect public safety seriously due to
failure(2)
2.0 3.0 (4) 3.0 (3)
tF
aF b
F
-
8/13/2019 6 Design for deep excavation civil engineering
102/121
NOTE:
(1) The table is from CICHE (1998), incorporating specifications
made by BSI (1989) and FIP (1982)
(2) The temporary anchors in this table refer to those whoseworking periods are not longer than 2 years. Otherwise, they
are classified as permanent anchors.
(3) With complete proving test results, the minimum factor of
safety can be 2.0.
(4) If creep of soil is to be encountered, the factor of safety can be
increased to 4.0.
Th b f t d i
-
8/13/2019 6 Design for deep excavation civil engineering
103/121
The number of tendons is
(10.71)
As discussed above, is computed usingEq. 10.59, transforming the horizontal
component, as analyzed using the apparent
earth pressure method, the beam on elastic
foundation method, or the finite elementmethod.
w
w
P
Tn =
wT
-
8/13/2019 6 Design for deep excavation civil engineering
104/121
As Figures 10.24 and 10.25 illustrate, the free section
has to extend beyond the potential failure zone by at
least 2.0 m. If the free section is too short, the
stresses in soils caused by the fixed section will
easily affect the retaining wall. In addition, theanchor behavior will tend to be fragile, any small
displacement possibly bring about large stress, and
threatening the security of the anchor. Therefore, thefree section has to be at least 4.0 m long.
10.7.6 Design of the Fixed Section
-
8/13/2019 6 Design for deep excavation civil engineering
105/121
The fixed section of an anchor should be placed 2.0 m
away from the potential failure zone. The design of a fixed
section includes the bond forces between tendons and
grouts and the anchorage force between the fixed section
and soils.The bond forces between tendons and grout have to be
large enough so that the designed strength of the anchor can
fully develop. Table 10.4 suggests the safety factors
between tendons and grout. As for the allowable bondforces between tendons and cement grout, we can use the
values as suggested by JSF (1990), as shown in Table 10.5.
10.7.6 Design of the Fixed Section
-
8/13/2019 6 Design for deep excavation civil engineering
106/121
TABLE 10.4 Factor of safety for single anchor (CICHE, 1998)
ClassificationTensile forceof tendons
( )
Anchoring force
( )
Bond force of
tendons ( )
Temporary anchors whose working period
is not longer than 6 months and which
dont affect public safety when failing(2)1.4 2.0 2.0
Temporary anchors whose working period
is not longer than 2 years and which dont
affect public safety, though having certain
influence, when failing without alert
1.6 2.5 (3) 2.5 (3)
Permanent or temporary anchors which arehighly risky in rusting or which affect
public safety seriously due to failure(2)2.0 3.0 (4) 3.0 (3)
tF aF bF
-
8/13/2019 6 Design for deep excavation civil engineering
107/121
NOTE:
(1) The table is from CICHE (1998), incorporating specifications
made by BSI (1989) and FIP (1982)
(2) The temporary anchors in this table refer to those whose
working periods are not longer than 2 years. Otherwise, theyare classified as permanent anchors.
(3) With complete proving test results, the minimum factor of
safety can be 2.0.
(4) If creep of soil is to be encountered, the factor of safety can
be increased to 4.0.
TABLE 10 5 All bl b d f f t d i t t (JSF 1990)
-
8/13/2019 6 Design for deep excavation civil engineering
108/121
TABLE 10.5 Allowable bond force of tendons in cement mortar (JSF, 1990)
Designed compressive strength of
cement mortar ( )2cm/kgTypes of tendons
150 180 240 300 >400
Temporary
anchors
Steel wireRound steel bar
Steel strand
Multiple steel
strand
8
8
8
8
10
10
10
10
12
12
12
12
13.5
13.5
13.5
13.5
15
15
15
15
Permanent
anchors
Steel wireRound steel bar
Steel strand
Multiple steel
strand
8
8
8
8
9
9
9
9
10
10
10
10
The anchorage force between the fixed section and soils
-
8/13/2019 6 Design for deep excavation civil engineering
109/121
(1) Friction type of anchor
The ultimate anchorage force, Tu, for a friction type ofanchor can be computed by the following equation
= ultimate anchorage force
= diameter of the fixed section
= length of the fixed section
= average ultimate shear resistance strength per unit area
(also called the frictional strength) between the fixed
section and soils
uT
ultabu LdT
bd
aL
ult
(10.72)
h d i d l d h h i
-
8/13/2019 6 Design for deep excavation civil engineering
110/121
The designed load on the anchor is
(10.73)
where = safety factor of the designed anchorage force; the
commonly used factors of safety are listed in Table 10.4.
a
u
w
F
TT =
aF
-
8/13/2019 6 Design for deep excavation civil engineering
111/121
The strength between the fixed sectionand the surrounding soil, , changes with
the types of soils where the fixed section is
placed, the failure mode of the fixed section,
the grouting pressure, and the installation
method. Many investigators have proposed
some empirical formulas to estimate .
ult
ult
(a) Anchorage in rocks
-
8/13/2019 6 Design for deep excavation civil engineering
112/121
Null pressurized anchors are often used for rocks (see
Figure 10.22). Little john's suggestion (1970) is usually
taken for the ultimate shear resistance strength between
the fixed section and rocks. That is, let be 0.1 qu (forblock rocks) or 0.25 qu (for weathered rocks) where qu is
the axial compressive strength of rock. Anchor choice is
to adopt the suggestions by JSF (1990), as sown in Table10.6.
ult
TABLE 10.6 Ultimate frictional strength of an anchorage body (JSF, 1990)
-
8/13/2019 6 Design for deep excavation civil engineering
113/121
ult )cm/kg( 2
N
Type of soil
Rock
Hard rockSoft rock
Weathered rock
Mudstone
15 ~ 25
10 ~ 15
6 ~ 10
6 ~ 12
Gravel
=10
=20
=30=40
=50
1.0 ~ 2.0
1.7 ~ 2.5
2.5 ~ 3.53.5 ~ 4.5
4.5 ~ 7.0
Gravel
=10
=20
=30
=40
=50
1.0 ~ 1.4
1.8 ~ 2.2
2.3 ~ 2.7
2.9 ~ 3.5
3.0 ~ 4.0
Clay 1.0 c
N
NNNNNNNN
Note :Nis standard penetration test number, c is cohesion, and
is ultimate frictional strength after pressure groutingult
(b) Anchorage in sandy soils
-
8/13/2019 6 Design for deep excavation civil engineering
114/121
The -value of an anchor in sandy soils can be computed as
follows
(10.74)
= the average effective overage effective overburden pressure
above the fixed section= the angle of friction between the fixed section and soils
Because anchors in sandy soils are usually the low
pressure type, the average ultimate shear strength of sandis usually determined on the basis of experience or field
tests.
ult
tanvult v
(c) Anchorage in clayey soils
-
8/13/2019 6 Design for deep excavation civil engineering
115/121
Anchors in clays are usually installed following the null
pressurized grouting method (see Figure 10.22). The ultimate
shear resistance strength of the fixed section in clayey soils can be
expressed as follows
(10.75)
where = undrained shear strength of clay
= reduction factor for undrained shear strength
uult
s =u
s
1.2
-
8/13/2019 6 Design for deep excavation civil engineering
116/121
API
0.0 0.2 0.4 0.6 0.8 1.00.0
0.2
0.4
0.6
0.8
1.0
vu/s
Cast-in-
place pile
FIGURE 4.12 Relation between adhesion and undrained shear strength of clay
-
8/13/2019 6 Design for deep excavation civil engineering
117/121
As Eq. 10.72 shows, the longer the fixed section, the
larger the anchorage force. However, many investigatorshave found that when the length of the fixed section
exceeds some critical value, more lengthening of the
fixed section can hardly increase its anchorage force.
Thus, the length of the fixed section has to be limited. In
principle, the length of the fixed section is best when
between 3.0 and 10.0 m. If out of this range, it is better
to carry out field tests to examine the ultimate anchorageforce. Table 10.7 lists specifications on the minimum and
maximum length of the fixed section.
TABLE 10.7 Specifications for the length of the fixed section (CICHE, 1998)
-
8/13/2019 6 Design for deep excavation civil engineering
118/121
Specifications Minimum suggested distance
FIP (1982) and
BSI (1989)
No shorter than 3 m, except if the proving test
result is satisfactory in fulfilling the design, and
not longer than 10 m, under normal condition
PTI (1980) No shorter than 3 m
JSF (1990) Between 3 ~10 m
GCO (1989) No shorter than 3 m
AASHTO
(1992)In soil, no shorter than 4.6 m; in rock, 3 m
10.7.7 Preloading
-
8/13/2019 6 Design for deep excavation civil engineering
119/121
Locked Preloading or the Locked Load
The anchor installed, it usually needs to be
preloaded and locked, which is called locked
preloading or the locked load.
The locked load is usually a little larger than
the designed load of the anchor because the
slipping of the wedge clips during the process of
locking will cause some loss of the anchorpreload. After locking, the remaining force is
called the effective load.
10.7.7 Preloading
-
8/13/2019 6 Design for deep excavation civil engineering
120/121
10.8 Tests of Anchors
-
8/13/2019 6 Design for deep excavation civil engineering
121/121
Influenced by the process of fabrication, grouting, and
geological conditions, the actual ultimate load of an anchorhas to be examined through field tests. The tests are
classified into many methods in terms of their different
aims, though their common goal is to understand the
deformation behaviors and load capacities of the anchor.
Anchor tests can be distinguished into theproving test, the
suitability test, and the acceptance test.