6 design for deep excavation civil engineering

Upload: sathya-putra-wijaya

Post on 04-Jun-2018

236 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/13/2019 6 Design for deep excavation civil engineering

    1/121

    10.1 Introduction

    10.2 Design Methods and Factors of Safety

    10.3 Retaining Walls

    10.3.1 Soldier Piles

    10.3.2 Sheet Piles

    10.3.3 Column Piles10.3.4 Diaphragm Walls

    Ch10 Design of Retaining Structural Components

  • 8/13/2019 6 Design for deep excavation civil engineering

    2/121

    10.4 Structural components in Braced Excavations10.5 Strut Systems

    10.5.1 Horizontal struts

    10.5.2 End Braces and Corner Braces10.5.3 Wales

    10.5.4 Center Posts

    10.6 Structural components in Anchored Excavations

  • 8/13/2019 6 Design for deep excavation civil engineering

    3/121

    10.7 Anchor Systems

    10.7.1 Components of Anchors

    10.7.2 Analysis of Anchor Load

    10.7.3 Arrangement of Anchors

    10.7.4 Design of Anchor Heads, Anchor Stands, and Wales

    10.7.5 Design of the Free Section

    10.7.6 Design of the Fixed Section10.7.7 Preloading

    10.7.8 Design of Retaining Walls

    10.8 Tests of Anchors

    10.8.1 Proving Test

    10.8.2 Suitability Test

    10.8.3 Acceptance Test

    10.9 Summery and General Comments

  • 8/13/2019 6 Design for deep excavation civil engineering

    4/121

    10.2 Design Methods and Factors of Safety

    The design methods for reinforced concreteworking stress method and

    strength design method

    The design methods for steel structuresThe allowable stress method (abbreviated as the ASD method)

    and the ultimate strength design method.

    For diaphragm walls served as permanent structure, the

    allowable stress would be magnified by a factor withoutthe earthquake force considered. Some country building

    codes suggest =1.25.

  • 8/13/2019 6 Design for deep excavation civil engineering

    5/121

    To design the sections and dimensions of a retaining

    wall, the first thing is to carry out the stress analysis.Three methods can be adopted for the stress analysis of

    a retaining wall

    Assumed hinge method too simple, only suitable on

    shallow excavation

    Finite element method too complicated for input and

    output, need professional geotechnicalengineering training

    Beam on elastic foundation method suitable for any

    excavation, simple to input and out put, suitable

    for common engineer

    10.3 Retaining Walls

  • 8/13/2019 6 Design for deep excavation civil engineering

    6/121

    FIGURE 10.1 Typical bending moment and shear diagrams of a retaining wall by

    stress analysis

    -60 -30 0 30 60

    28

    24

    20

    16

    12

    8

    4

    -90 -60 -30 0 30 60 900

    Shear (t)Bending moment (t-m)

    D

    epth

    (m)

  • 8/13/2019 6 Design for deep excavation civil engineering

    7/121

    The commonly used types of soldier piles in

    excavations are the H steel, I steel and rail piles.

    10.3.1 Soldier Piles

  • 8/13/2019 6 Design for deep excavation civil engineering

    8/121

    Take the maximum bending moment (M max ) from the

    typical bending moment envelope (Figure 10.1).According to the allowable stress method (ASD method),

    we can obtain the section modulus of the soldier piles as

    a = allowable stress of the steel

    l = short-term magnified factor of the allowable stress, which

    can be found from the country building codes

    a

    MSl

    max= (10.1)

  • 8/13/2019 6 Design for deep excavation civil engineering

    9/121

    The sections of sheet piles are various. U-shaped, Z-shaped, and line-shaped

    sheet piles are frequently used in some countries, as shown in Figure 3.19.

    10.3.2 Sheet Piles

    ( a )

    ( b )

    ( c )

    FIGURE 3.19 Sections of steel sheet piles (a) U pile (b) Z pile (c) straight pile

  • 8/13/2019 6 Design for deep excavation civil engineering

    10/121

    The dimensions of a sheet pile are determined on the basis

    of the results of the stress analysis. According to the

    envelope of bending moments (Figure 10.1), take the

    maximum bending momentM max and compute the section

    modulus using Eq.10.1, which is then used to find the

    dimension of the sheet pile

    a

    MSl

    max= (10.1)

  • 8/13/2019 6 Design for deep excavation civil engineering

    11/121

    Column piles used in excavations include the PIP pile,reinforced concrete pile, and the mixed pile.

    Column piles bear the axial load and flexural load

    simultaneously. Therefore, their behavior is similar to thatof the reinforced concrete columns.

    The thus obtained bending moment and shear envelopes

    are then used for the design of reinforced concretecolumns. Please refer to the design chart of reinforced

    concrete columns or the ACI code.

    10.3.3 Column Piles

  • 8/13/2019 6 Design for deep excavation civil engineering

    12/121

    The design of a diaphragm wall includes specifying the wallthickness and the reinforcements.

    The thickness is usually determined according to the results

    of the stress analysis, the deformation analysis and the

    feasibility of detailing of concrete reinforcements.

    According to the experience of excavations, the thickness ofa diaphragm wall can be assumed to be 5 %He (He is the

    excavation depth) in the preliminary design.

    10.3.4 Diaphragm Walls

  • 8/13/2019 6 Design for deep excavation civil engineering

    13/121

    The deformation of the retaining wall in the central section of

    the site is usually assumed to be in the plane strain condition

    during analysis. Therefore, the unit width (b =1 m) of the

    diaphragm wall is usually used for flexural stress analysis.

    The definitions of the designed and nominal bending moments

    and shears are as follows

    l=

    MM

    u

    LF

    u

    n

    MM=

    un

    VV=

    (10.3)

    (10.2)

    (10.4)

    (10.5)

    l=

    VVu

    LF

  • 8/13/2019 6 Design for deep excavation civil engineering

    14/121

    Mu = bending moment for design

    Mn = nominal bending moment (capacity of bending

    moment)Vu = shear for design

    Vn = nominal shear, also called the capacity of shear

    M = bending moment obtained from stress analysis

    V = shear obtained from stress analysis

    LF= load resistance factor; ACI (2005),LF=1.6; ACI

    (2002),LF=1.7 = strength reduction factor; ACI (2005),= 0.9 (bending

    moment ), = 0.75 (shear); ACI (2002), = 0.9

    (bending moment ), = 0.85 (shear)

  • 8/13/2019 6 Design for deep excavation civil engineering

    15/121

    FIGURE 10.3 Stress in the ultimate state on a section of the reinforced concrete

    beam (reinforcements are smaller than those in the balanced state)

    d

    b

    sA

    0.003

    c

    c

    a

    ysfAT=yfys

    nM

    f 85.0 abfC c= 85.0

    2

    ad

    2a

  • 8/13/2019 6 Design for deep excavation civil engineering

    16/121

    Suppose the thickness (t) of a reinforced concrete beam is

    given. The nominal resistant bending moment of concrete ofthe width of b is

    d = distance from extreme compression fiber to centroid of

    tension reinforcement

    = maximum reinforcement ratio that does not contain

    compression reinforcement, max = 0.75 b= compressive strength of concrete

    = yielding strength of reinforcements

    b = reinforcement ratio producing balanced strain conditions

    (1) Vertical main reinforcement

    max

    yfc

    f

    2max

    max 59.011

    bdf

    ffM

    c

    y

    yR

    = (10.6)

  • 8/13/2019 6 Design for deep excavation civil engineering

    17/121

    The balanced reinforcement ratio can be computed as follows

    where the measurement unit of and is ; b1 relates to

    the strength of concrete, which is generally under 280 .

    High performance concrete has used to construct diaphragm

    walls recently. Thus, b1 can also be computed by the followingequation

    where the measurement unit of and is ; b1 relates to

    the strength of concrete.

    2kg/cm2kg/cm

    2kg/cm0.85-0.05( )0.65

    0.85

    70

    280 kg/cm2

    280 kg/cm

    2b1= - 280cf

    cf

    cf

    cf

    yf

    cf

    (10.7)b=

    y

    b

    f 6120 +fy

    61200.851

    cf

    (10.8)

    yf

  • 8/13/2019 6 Design for deep excavation civil engineering

    18/121

    When Mu MR , the only item to be designed is tensionreinforcements, which can be computed as follows

    Let the strength ratio of the material be

    Since

    m=0.85 cf

    yf

    259.0

    1 bd

    f

    ffM

    M

    c

    y

    ynu

  • 8/13/2019 6 Design for deep excavation civil engineering

    19/121

    We can then have the reinforcement ratio,

    deriving from the above equation

    The reinforcement ratio, deriving from the

    above equation

    As = bd

    =

    2

    211

    1

    bdf

    mM

    m y

    n (10.9)

    (10.10)

  • 8/13/2019 6 Design for deep excavation civil engineering

    20/121

    IfMu MR , it follows that the maximum resistance of

    concrete (under the condition that the tension

    reinforcement has achieved its yielding strength) is still

    smaller than the designed bending moment.

    That is to say, the diaphragm wall is to be thickened or

    compression reinforcements have to be designed.

  • 8/13/2019 6 Design for deep excavation civil engineering

    21/121

    The design of compression reinforcements can follow the

    method of the doubly reinforced beam, which is as follows

    Let the ratio of the reinforcement be 1= 0.75 b

    As1 = 1bd

    T1 = As1fy

    Cc = T1 = 0.85 ba

    From above, we obtain

    a =0.85 b

    T1

    cf

    cf

    (10.11)

    (10.12)

    (10.13)

    (10.14)

  • 8/13/2019 6 Design for deep excavation civil engineering

    22/121

    The bending moment provided by the tension

    reinforcement is

    M2 = Mn - M1

    Thus, the area of tension reinforcements corresponding to

    M2 is

    = distance from extreme compression fiber of the wall to

    the centroid of compression reinforcements

    M1= T1 ( d )2

    a

    d

    As2

    =fy ( d )

    M2

    d (10.17)

    (10.16)

    (10.15)

  • 8/13/2019 6 Design for deep excavation civil engineering

    23/121

    The required area of tension reinforcements is

    As =As1 + As2

    The required area of compressive reinforcements is

    =Es fy

    Es = Young's modulus of reinforcements

    = strain of the compression reinforcements, which

    can be computed as follows

    c = a / b1 (see Figure 10.3)

    =As2fy

    = ( ) 0.003c c

    d

    s

    s

    s

    sf

    sA

    sf

    (10.21)

    (10.20)

    (10.19)

    (10.18)

  • 8/13/2019 6 Design for deep excavation civil engineering

    24/121

    The retaining wall with one dimensional deformation does not need to

    be reinforced horizontally. If shrinkage and temperature are to be

    considered, horizontal reinforcements will be needed. According to

    the ACI code, the reinforcement with shrinkage and temperature

    effects is

    (2) Horizontal main reinforcement

    As = 0.0020 Ag 4200 kg/cm2 0.0018 Ag = 4200 kg/cm2 0.00184200/ Ag 0.0014Ag > 4200 kg/cm2 Ag= thickness of the retaining wall unit width;

    The reinforcement for shrinkage and temperature effects (As) has

    to be placed evenly on both sides of the wall

    yf

    yf

    yf

    yf

    (10.22)

  • 8/13/2019 6 Design for deep excavation civil engineering

    25/121

    According to the ACI code, the nominal shear ofconcrete is

    Vc is the nominal shear of concrete and is measured by

    kg. The unit of is kg/cm2

    . b is the unit width and isusually taken to be 100 cm.

    When the designed shear (Vu) is smaller thanfVc, it is

    theoretically unnecessary to design reinforcement. Inpractice, the shear reinforcement still has to be

    designed in order to be able to hang the steel cage into

    the trench.

    (3) Shear reinforcement

    Vc = 0.53 bdcf

    cf

    (10.23)

  • 8/13/2019 6 Design for deep excavation civil engineering

    26/121

    FIGURE 10.2 Plan, 3D view, side view of a steel cage of diaphragm wall

    (1, 2, and 3 represent shear reinforcements)

    b

    b

    A

    C

    E

    F

    B

    D

    A

    C

    E

    F

    A C

    B D

    1

    1

    1

    2 2

    2 2

    2

    3 3

    3

    3

    3

    Vertical main renforcement

    Plan

    Horizontal

    reinforcement

    Vertical main

    reinforcement

    Side view3-D

    view

    Horizontal

    reinforcement

    Sv

    Sv

    Sv

    Sv

    Sv

    Sv

    Sv

    Sv

    Sv

    Sh

    Sh

    Sh Sh Sh Sh

    Sh Sh Sh

  • 8/13/2019 6 Design for deep excavation civil engineering

    27/121

    Three types of shear reinforcements are used in the steelcage of a retaining wall, main shear reinforcement-type 1,

    and two small slant reinforcements-type 2, and 3. As a

    result, the nominal shear (capacity of shear) of the

    retaining wall per unit width is

    Vn = Vc + Vs

    where Vs is nominal shear of shear reinforcements

    (10.24)

  • 8/13/2019 6 Design for deep excavation civil engineering

    28/121

    Since the horizontal distance between any two shear

    reinforcements is identical, the sectional area of the shearreinforcement per unit width (b = 100 cm) is

    Av = total sectional area of all shear reinforcements on the

    horizontal section per unit width (cm2)

    Ab = sectional area of a single shear reinforcement (cm2)

    Sh = horizontal distance between shear reinforcements (cm)

    Av=100Ab

    Sh(10.25)

    Th i l h f th t 1

  • 8/13/2019 6 Design for deep excavation civil engineering

    29/121

    The nominal shear of the type 1

    Sv =vertical distance between the main shear reinforcements

    The nominal shear of the type 2

    = angle between the small slant reinforcement and thehorizontal reinforcement

    The nominal shear of the type 3

    b = angle between the small slant reinforcement and the vertical

    reinforcement

    The nominal shear offered by all shear reinforcements per unit

    width is

    Vs1 = Sv

    Avfy d

    Vs2 = SinSv

    Avfy d

    Vs3 = Sin bSv

    Avfy d

    Vs = Vs1 + Vs2 + Vs3

    (10.28)

    (10.27)

    (10.29)

    (10.26)

  • 8/13/2019 6 Design for deep excavation civil engineering

    30/121

    Minimum lap splice length and development length of reinforcements

    of a diaphragm wall can be designed according to the ACI code, or

    they can be determined using Eqs.10.30 and 10.31. The coefficient1.25 is to magnify the lap splice length and development length,

    considering the effects of concrete casting in bentonite, which leads to

    a smaller bond stress

    Development length

    Lap splice length

    Ab = the sectional area of a single reinforcement; if applied a vertical

    reinforcement, c = 1.0to horizontal reinforcement, c = 1.4

    (4) Lap splice length and development length

    Ld = 1.25cld = 0.075c Abfy

    Ld = 1.25cld =0.091c Abfy

    cf

    cf

    (10.30)

    (10.31)

  • 8/13/2019 6 Design for deep excavation civil engineering

    31/121

    FIGURE 10.5 Design of reinforcements in a steel cage of the diaphragm wall

    (a) profile (b) side view

    (a) (b)

    Floor slab

    Raft foundation

    Inside the

    excavation zone

    Outside the

    excavation zone

  • 8/13/2019 6 Design for deep excavation civil engineering

    32/121

    FIGURE 10.6 Components of a strutting retaining system

    Soldier pile

    Lagging

    Horizontal

    struts

    Wale

    Center post

    Sheetpile

    Jack

    Jack

    End brace

    Corner brace

    10.4 Structural components in Braced Excavations

  • 8/13/2019 6 Design for deep excavation civil engineering

    33/121

    FIGURE 10.7 Single strutting system

    End brace

    waleRetaining wall

    Horizontal struts

  • 8/13/2019 6 Design for deep excavation civil engineering

    34/121

    X

    Horizontal strutof the higher level

    Horizontal strut

    of the lower level

    Y

    U-clip

    Center

    post

    (b)(a)

    FIGURE 10.8 Joint of a single strut and a center post (a) 3D view (b) plan view

    U clip

    Bracket

    Horizontalstrut of the

    higher level

    Horizontal strut of the

    lower level

    Center post

    xe

  • 8/13/2019 6 Design for deep excavation civil engineering

    35/121

    FIGURE 10.8 Joint of a single strut and a center post (c) photo

  • 8/13/2019 6 Design for deep excavation civil engineering

    36/121

    FIGURE 10.9 Double strutting system

    End braces

    Retaining wall

    Horizontal struts

  • 8/13/2019 6 Design for deep excavation civil engineering

    37/121

    Horizontal strut of the higher level

    U-clip

    Horizontal strut

    of the lower

    level Center postHorizontal

    strut of the

    higher level

    U-clip

    Horizontal strut of the lower level

    Center post

    (a) (b)

    FIGURE 10.10 Joint of a double strut and a center post (a) 3D view (b) plan view

  • 8/13/2019 6 Design for deep excavation civil engineering

    38/121

    FIGURE 10.10 Joint of a double strut and a center post (c) photo

    10 5 Strut Systems 10 5 1 H i t l t t

  • 8/13/2019 6 Design for deep excavation civil engineering

    39/121

    10.5 Strut Systems 10.5.1 Horizontal struts

    (1) Stress computation

    A strut is usually subjected to the axial compressive load as well as

    the flexural load. The axial compressive stress can be computed as:

    N

    Afa =

    A = sectional area of the strutN = axial load =N 1 +N2

    N1 = strut load induced by excavation, which can be computed

    using the beam on elastic foundation method, the finite

    element method, or the apparent earth pressure methodN2 = strut load induced by the temperature change = DtEA

    = coefficient of thermal expansion of struts; for the steel strut,

    = 1.32 10 5 /

    Dt = temperature change of struts ()

    E = Young's modulus

    (10.32)

  • 8/13/2019 6 Design for deep excavation civil engineering

    40/121

    Because the result using DtEA to compute the effect of

    temperature change of the strut load,N2, usually comes

    out too large, the empirical formula is often used

    instead.

    The JSA (1988) suggests

    N2 = 10 t ~ 15 t orN2 = ( 1.0 t ~ 4.0 t ) Dt, where

    Dtis the temperature change () in the air (not thetemperature change of the steel).

  • 8/13/2019 6 Design for deep excavation civil engineering

    41/121

    The flexural stress can be computed as follows

    M1 = bending moment produced by the strut weight and the live load;

    taking the center post as the simply supported hinge, thenM1 =

    wL2

    /8w = strut weight + live load 0.5 t/m

    L = distance between two adjacent center posts

    M2 = bending moment caused by the uplift of the center post; since

    struts are constructed level by level during excavation, the

    influence ofM2 on the top level would be largest while that on

    the lowest level would be largest while that on the lowest level

    would be the smallest

    S= section modulus

    M1 +M2S

    fb = (10.33)

    (2) Allowable stress

  • 8/13/2019 6 Design for deep excavation civil engineering

    42/121

    The allowable axial compressive stress of a strut can be selected from the tables

    and figures offered by the AISC Specification or using the following equation

    KL / ry = effective slenderness ratio of the strut on the flexural plane where K can

    be taken as 1.0

    L = unsupported length of the strut, usually distance between the two adjacent

    center posts

    ry = radius of gyration of the cross section of the strut in the direction of theweak axis

    Cc = critical slenderness ratio =

    E= Young's modulus of struts

    Fy = yielding stress of struts

    l = short-term magnified factor of the allowable stress, which can be found incountr buildin code, l = 1.25.

    ( ) owab e s ess

    KLry

    > Cc

    KLry

    Cc

    l

    =3

    /

    8

    1/

    8

    3

    3

    5

    /

    2

    1

    1

    c

    y

    c

    y

    c

    y

    a

    C

    rKL

    C

    rKL

    FC

    rKL

    Fy

    l

    = 2

    2

    23

    12

    y

    a

    r

    KL

    EF

    yFE/22

    (10.34)

    (10.35)

  • 8/13/2019 6 Design for deep excavation civil engineering

    43/121

    The allowable flexural stress (Fb) of a strut can be

    derived from the tables and figures offered by the

    AISC Specification.

    However, the flexural stress (fb) of a strut, during

    normal excavation (that is, the uplift of the center post

    is not much), is not large. To simplify the design, wecan assumeFb = 0.6Fyl.

    (3) E i ti f bi d t

  • 8/13/2019 6 Design for deep excavation civil engineering

    44/121

    According to the AISC Specification, the stress on each section of a strut

    should satisfy the following equation

    Cm = coefficient of modification = 0.85

    1 /(1 fa / = amplification factor= allowable Euler stress = l122E / [23KL / rx2]

    KL / rx = effective slenderness ratio on the flexural plane, we can

    assumeK= 1.0

    rx = ratio of gyration of the strut in the direction of the strong axis

    E= Young's modulus of struts

    l = short-term magnified factor of the allowable stress, which can be

    found in country building codes, we can assume l = 1.25

    (3) Examination of combined stresses

    + 1.0fa

    Fa 15

    faFa

    fbFb

    faFa

    > 15

    eF

    0.1

    1

    be

    a

    bm

    a

    a

    FF

    f

    fC

    F

    f

    (10.36)

    (10.37)

  • 8/13/2019 6 Design for deep excavation civil engineering

    45/121

    10.5.2 End Braces and Corner Braces

    FIGURE 10.11 Distance and angle between struts and end braces or corner braces

    2

    211 1

    3

    1 2 3 2 4

    6

    5

    p

    p

    L1 L2

  • 8/13/2019 6 Design for deep excavation civil engineering

    46/121

    The axial force on the end brace is

    p = apparent earth pressure or the strut load per unit width

    1 2 = spans (see Figure 10.11)

    1 = angle between the end brace and the wale

    (usually 45)

    N =p 12 1 + 2 Sin1 (10.38)

  • 8/13/2019 6 Design for deep excavation civil engineering

    47/121

    The axial force on an corner brace is

    3 4 5 6 = the spans

    23 = angles between the corner brace and the wale,

    45 in most cases

    To be conservative, the design load can be assumed to be

    the maximum value betweenN1 andN2 .

    N1 =p 12 3 + 4 Sin2N2 =p 12

    5 + 6

    Sin3 (10.40)

    (10.39)

  • 8/13/2019 6 Design for deep excavation civil engineering

    48/121

    The function of wales is to transfer the earth pressure

    on the retaining wall to the struts.

    For analysis, the earth can therefore be assumed toact on the wale directly.

    The earth pressure can be obtained from the apparent

    earth pressure method or by transforming the strut

    load, computed using the finite element method or

    beam on elastic foundation method.

    10.5.3 Wales

  • 8/13/2019 6 Design for deep excavation civil engineering

    49/121

    The wale is usually acted on by the earth pressure as

    well as the axial force from the end brace or corner

    brace. That is to say, the wale bears simultaneously

    the moment and the axial force and its design falls in

    the domain of the beam-column system. With ample

    lateral support, the analyses of secondary moment and

    buckling for wales can be saved.

  • 8/13/2019 6 Design for deep excavation civil engineering

    50/121

    FIGURE 10.12 Computation of the bending moment of a wale

    L

    Joint

    p

    WaleStrut

    Earth pressure

    Fixed end beam mode

    Simplly supported beam modeAnalysis method

    considering weak joints

    Mmax = pL2

    8

    1 Mmax pL210

    14

    L

    Mmax = pL212

    1

    To compute the maximum bending moment and shear of wales the wales can be

  • 8/13/2019 6 Design for deep excavation civil engineering

    51/121

    To compute the maximum bending moment and shear of wales, the wales can be

    viewed as simply supported beams with struts as supporting hinges, or viewed as

    fixed end beams.

    Simply supported beam

    Fixed end beam

    Mmax = maximum bending moment of the wale

    Qmax = maximum shear of the wale

    L = distance between struts

    p = earth pressure

    Mmax = pL281

    Qmax = pL2

    1

    Mmax = pL212

    1

    Qmax = pL2

    1

    (10.41a)

    (10.41)

    (10.42a)

    (10.42)

  • 8/13/2019 6 Design for deep excavation civil engineering

    52/121

    Mmax pL210

    1

    Because the length of a wale is limited, the wales

    have to be joined in the field. The strength of the

    joint is not fully rigid and the joint could easily

    become the weakest part of the structure. Thus,

    the joints had better be located at the places

    where the stress is smaller.According to the bending moment distribution

    diagram of a continuous or a simply supported

    beam, if the joint is located at theplaces 1/4 of

    the span from the support, the maximum bendingmoment of the wale would be

    (10.43)

  • 8/13/2019 6 Design for deep excavation civil engineering

    53/121

    In design practice, if the wale is assumed to be a

    simply supported beam, it may not work out as

    economical.

    If it is designed to be a fixed end beam, it may tend

    to be insecure. The more reliable method is to

    locate the joint at theplace 1/4 of the span from the

    support and compute the maximum bending

    moment and shear as follows

    Mmax = pL2101

    Qmax = pL2

    1

    (10.44)

    (10.44a)

  • 8/13/2019 6 Design for deep excavation civil engineering

    54/121

    When there are no end braces,L is the horizontaldistance between struts.

    When there are end braces, the distance between struts

    can be reduced properly.

    Generally speaking, when 60 ,L = 1 + 2. When

    > 60 , less conservative design can be madeL = 1

  • 8/13/2019 6 Design for deep excavation civil engineering

    55/121

    Viewed from the view point of mechanics, the wale is also

    subjected to the axial stress.

    If sheet piles or soldier piles with end braces are used, the

    axial force of the wale can be designed by choosing the

    larger one between the following two computing results

    or

    N = p 12 1 + 2 tan1N = p 5 + 2 6 (10.45)

    (10.46)

  • 8/13/2019 6 Design for deep excavation civil engineering

    56/121

    Since the corners of a diaphragm wall have an arching

    effect, to determine the axial load of a wale around a

    corner of an excavation with diaphragm walls, it is

    necessary to use Eq. 10.46.

    If sheet piles or soldier piles are used, take the

    maximum value among the computed results of Eqs.

    10.45 and 10.46.

  • 8/13/2019 6 Design for deep excavation civil engineering

    57/121

    10.5.4 Center Posts

    Center post are usually set to

    bear the weight of struts, the materials on the struts,

    and other extra loading out of the movement of the

    retaining system.

    Center posts, usually H steels,

    (1) installed by striking the piles into soils directly.

    (2) embedment into soils by way of pre-boring or

    inserted into a cast-in place pile.

  • 8/13/2019 6 Design for deep excavation civil engineering

    58/121

    FIGURE 10.13 Installation of center posts onto cast in-situ piles

    Cast-in-place pile

    Retaining

    wall

    Central post

    Horizontal strut

  • 8/13/2019 6 Design for deep excavation civil engineering

    59/121

    The design of a center post includes the design of the section and

    the embedment depth.

    The possible axial loads on each center post are

    (1) Weight of the horizontal strut and the live load,P1

    wi = strut weight of each level and its live loadL1,L2 = distance between struts

    n = number of the levels

    p1= wi (L1 +L 2 )n

    i=1

    FIGURE 10.14 Distribution of strut weight on a center post

    L1

    L1

    L2L2

    (10.47)

  • 8/13/2019 6 Design for deep excavation civil engineering

    60/121

    (2) Weight of the center post above the excavation

    surface,P2

  • 8/13/2019 6 Design for deep excavation civil engineering

    61/121

    (3) Slant compressive force on the horizontal strut,P3

    Suppose the tilt angle of a horizontal strut is , the downward or

    upward force on the center post would be

    sin)(2 ,,1

    3 iyix

    n

    i

    NNP ==

    (10.48)

    = load on the struts of each level in thex direction

    = load on the struts of each level in they direction= tilt angle of the horizontal strut

    ixN ,

    iy

    N,

    FIG. 10.15 Action of the axial force of struts on a center post

    (a) when the center post settles (b) when the center post heaves

    where

    1,yN

    1,yN

    1,yN

    1,yN1,xN

    1,xN

    1,xN

    1,xN

    2,yN

    2,yN

    2,yN

    2,yN2,xN

    2,xN

    2,xN

    2,xN

    (a) (b)

    The first level

    of struts

    The second level

    of struts

  • 8/13/2019 6 Design for deep excavation civil engineering

    62/121

    In analysis, the tilt angle of the horizontal strut is

    difficult to estimate. According to the data of field

    observations of excavations, the tilt angle can beassumed to be sin1/50.

    To be conservative in analysis, the center post can be

    assumed to be subject to the axial force of the strut and

    downward force. Thus, the total load on the center post

    would be

    (10.49)321 PPPP =

    In the double strutting system the moments generated by the weight of

  • 8/13/2019 6 Design for deep excavation civil engineering

    63/121

    In the double strutting system, the moments generated by the weight oftwo struts, which eccentrically act of the center post, can be assumed to

    be mutually offset.

    Horizontal strut of the higher level

    U-clip

    Horizontal strut

    of the lower

    level

    Center post Horizontalstrut of the

    higher level

    U-clip

    Horizontal strut of the lower levelCenter post

    (a) (b)

    FIGURE 10.10 Joint of a double strut and a center post (a) 3D view (b) plan view

  • 8/13/2019 6 Design for deep excavation civil engineering

    64/121

    In the single strutting system, the moment caused by the strut

    weight eccentrically acting on the center post can be computed

    by the following equation

    (10.50)= eccentricity distance

    xePPM )( 32xe

    FIGURE 10.8 Joint of a single strut and a center post (a) 3D view (b) plan view

    X

    Horizontal strut

    of the higher level

    Horizontal strut

    of the lower level

    Y

    U-clip

    Center

    post

    (b)(a)

    U clip

    Bracket

    Horizontal

    strut of the

    higher level

    Horizontal strut of the

    lower level

    Center post

    xe

    Buckling length

  • 8/13/2019 6 Design for deep excavation civil engineering

    65/121

    The buckling length of a center post should take the maximum

    unsupported length during the process of excavation, floor

    construction and dismantling. the buckling length of the center

    postL is(10.51)),,,,max( 54321 LLLLLL=

    Strut Center post

    etaining wall

    Excavation bottom

    Raft foundationFloor slabs

    213,usually LLL

    FIGURE 10.16 Unsupported length of center posts

    1L

    2L

    3L

    4L5L

  • 8/13/2019 6 Design for deep excavation civil engineering

    66/121

    Because the center post bears, simultaneously, the

    axial force and bending moment, it is the beam-

    column system that is to be adopted in analysis.Choose a proper section and then use Eq.

    10.47~10.51 to examine it.

  • 8/13/2019 6 Design for deep excavation civil engineering

    67/121

    The center post may bear

    (1) vertical loads

    (2) uplift forces caused by the tilt of the horizontal

    strut.

    The analysis method is identical with that

    for piles though a pile is of circular section.

  • 8/13/2019 6 Design for deep excavation civil engineering

    68/121

    FIGURE 10.17 Area to be adopted for the computation the vertical

    bearing capacity of center posts of the H pile

    columntheofdepthembedded)(2 =

    =

    HBA

    HBA

    s

    p

    B

    H

    1t

    2t

    (1) Vertical bearing capacity

  • 8/13/2019 6 Design for deep excavation civil engineering

    69/121

    (1) Vertical bearing capacity

    The ultimate vertical bearing capacity can be expressed as :

    (10.52)

    = ultimate vertical bearing capacity of the center post

    = point load resistance of the center post

    = skin frictional resistance of the center post

    = unit frictional resistance of the center post

    = surface area of the center post

    = the unit point resistance per unit area of the center post

    = sectional area of the center post

    The allowable vertical bearing capacity of the center post is

    (10.53)

    = allowable vertical bearing capacity

    = factor of safety

    ppssspu AqAfQQQ ==uQ

    pQ

    sQ

    s

    f

    sApq

    pA

    FSQQ

    FSQQ psua ==

    aQ

    FS

  • 8/13/2019 6 Design for deep excavation civil engineering

    70/121

    Under general conditions (low possibility of

    earthquake, general excavation, good

    geological conditions), the above factor ofsafety can be taken to beFS=2.0.

    If considering the possibility of earthquakeor the excavation is of high risk (in soft soils,

    for example), the above factor of safety can

    be taken to beFS=3.0.

  • 8/13/2019 6 Design for deep excavation civil engineering

    71/121

    In sandy soils, the point resistance of the center

    post can be computed as

    Driven pile (10.54)

    Drilling pile (10.55)

    N= the average standard penetration number within the influence

    range of the bottom end of the center post.

    Generally speaking,Nvalue can be taken as the average value

    within the range four times of the center post diameter above the

    bottom end of the center post diameter below it.

    Nfp

    40=

    2/mtNfp 15=

    2/mt

    The frictional resistance of the center post for both the driven and

  • 8/13/2019 6 Design for deep excavation civil engineering

    72/121

    drilling piles is

    N= the average standard penetration number within the depth of the center postembedded in the sandy soils

    In clayey soils, to be conservative, the value of the center post is

    usually assumed to be 0 and the can be computed as follows

    = adhesion between the surface of the center post and the surrounding soils

    = undrained shear strength of clay

    = reduction value of undrained shear strength.

    -values relates to the undrained shear strength of the clay, the installation method of

    the center post, and its embedment depth. Besides, the cast-in-situ piles embedded in

    clayey soils have lower -values because they do not compress the soil during the

    construction and are usually installed in boreholes filled with bentonite. Skempton

    suggests the -value be between 0.3 and 0.6, 0.45 in most cases.

    Nfs 2.0=2/mt

    pf

    uws scf ==wcus

    sf

    (10.56)

    (10.57)

  • 8/13/2019 6 Design for deep excavation civil engineering

    73/121

    API

    0.0 0.2 0.4 0.6 0.8 1.00.0

    0.2

    0.4

    0.6

    0.8

    1.0

    1.2

    vu/s

    Cast-in-

    place pile

    FIGURE 4.12 Relation between adhesion and undrained shear strength of clay

    (2) Pullout resistance

  • 8/13/2019 6 Design for deep excavation civil engineering

    74/121

    (2) Pullout resistanceThe allowable pulling out resistance of a center post is

    (10.58)

    = weight of the center post, the influence of groundwater

    considered= frictional resistance per unit area of the center post,

    which can be estimated using Eq. 10.57 or Eq. 10.58

    = surface area of the center post

    = factor of safety. As far as the sort-term behavior of a

    structure (such as a center post) is concerned,FScan be

    assumed to be 3.0

    sspa AfFS

    WR 1=

    pW

    sf

    sA

    FS

    10 6 Structural components in Anchored Excavations

  • 8/13/2019 6 Design for deep excavation civil engineering

    75/121

    10.6 Structural components in Anchored Excavations

    FIGURE 10.18 Anchored excavation

    m2

    Anchor head

    Anchora

    gesection

    Potentialfailu

    resurfa

    ce

    Excavation surface

    Freesect

    ion

    10 7 Anchor Systems

  • 8/13/2019 6 Design for deep excavation civil engineering

    76/121

    Anchors are categorized into permanent anchors andtemporary ones. They are applied extensively. The design

    of an anchor involves the soil properties, the materials of

    the anchor, grouting, and the construction details. The last

    is especially crucial in determining the quality of theanchor. Concerning the general rules of the design and

    construction of an anchor, please refer to related literature

    and specifications referred to in this section.

    Anchors in excavations belong to the category of

    temporary anchors. This section will only introduce the

    anchor system of the retaining wall in excavations.

    10.7 Anchor Systems

    General rules of anchor

  • 8/13/2019 6 Design for deep excavation civil engineering

    77/121

    General rules of anchor

    American Association of Sate Highway and Transportation Officials

    (AASHTO) (1992)British Standard Institute (BSI DD81)(1989)

    Deutsche Industrie Norm (DIN) (1988)

    Federation Internationale de la Precontrainte (FIP) (1982);

    Post-Tensioning Institute (PTI) (1980)

    Geotechnical Control Office (GCO)(1989)

    JSF(1990)

    A h i b i ll d f th h

  • 8/13/2019 6 Design for deep excavation civil engineering

    78/121

    An anchor is basically composed of the anchor

    head, the free section, and the fixed section.

    FIGURE 10.19 Configuration of an anchor

    Anchor head

    Anchor stand

    Retaining wall

    Casing

    Cement mortar Tendon

    )(anchortheofLength L

    )(sectionfreef

    L

    )(sectionfixeda

    L

    Types of anchor heads

  • 8/13/2019 6 Design for deep excavation civil engineering

    79/121

    FIG. 10.20 Types of anchor heads (a) locked by wedges (b) locked by screw nuts

    (c) composite lock (CICHE, 1998)

    clips Male awl

    Female awl

    Screw nut

    PC steel bar

    Screw nut

    Steel strandsteel bar connector

    Multiple PC steel strand

    (a)

    (b) (c)

    Anchors can be categorized into the resistance type, the bearing

  • 8/13/2019 6 Design for deep excavation civil engineering

    80/121

    resistance type, and the composite type according to the characteristics of

    the bearing force provided by the fixed section.

    FIG. 10.21 Types of anchorage body (a) frictional resistance type (b) bearing resistance type

    (c) composite resistance type

    Tension type

    Compression type

    Bearing body

    Bearing resistance type

    Composite (friction + bearing)

    resistance type

    Frictional resistance type{

  • 8/13/2019 6 Design for deep excavation civil engineering

    81/121

    The horizontal component of the anchor

    load can be computed using the half

    method or underneath pressure methodof the apparent earth pressure method.

    The related analytical method is identical

    to that for the braced excavation.

    10.7.2 Analysis of Anchor Load

  • 8/13/2019 6 Design for deep excavation civil engineering

    82/121

    FIGURE 10.23 Anchorage force and its horizontal component

    (Horizontal component )

    (Anchorage force )

  • 8/13/2019 6 Design for deep excavation civil engineering

    83/121

    The anchor load is

    (10.59)

    where = designed load of the anchor= horizontal component obtained from analysis

    = angle between the axis of the anchor and the

    horizontal plane

    cosPT

    w=

    wTP

  • 8/13/2019 6 Design for deep excavation civil engineering

    84/121

    In literature and specifications on anchors, group anchor

    effects are seldom discussed. The design of anchor is

    usually based on a single anchor pattern. Under suchconditions, the minimum distance between anchors has to be

    limited so that the group anchor effect will not be produced

    or the installation of an anchor may cast a bad influence on

    the adjacent anchors. Table 10.3 lists the related

    specifications on the minimum distance between anchors.

    10.7.3 Arrangement of Anchors

  • 8/13/2019 6 Design for deep excavation civil engineering

    85/121

    TABLE 10.3 Specifications for the minimum distance between the fixed sections

    bdNote : refers to the diameter of the anchorage section

    or 1.2 m

    Larger than 4

    Larger than 4

    Larger than 6

    Larger than 4

    For anchors with working load large than 70 tons, the

    minimum center-to-center distance of the anchorage

    section is 1.0 mFor anchors with working load largerthan 130 tons, the minimum center-to-center distance of

    the anchorage section is 1.5 m

    DIN(1988)

    AASHTO(1992)

    or 1.2 mPTI(1989)

    , generally 1.5 m to 2.0 m in applicationBSI(1989)

    , or not shorter than 1.5 mFIP(1982)

    Suggested minimum distanceRule

    bd

    bd

    bd

    bd

  • 8/13/2019 6 Design for deep excavation civil engineering

    86/121

    The determination of the vertical distance between

    anchors depends on the analytical results of theanchor load. The vertical distance between anchors

    is about 2.5~4.5 m and at least 1.0~1.5 m above the

    floor slabs. Besides, both FIP (1982)and BSI (1989)require the vertical distance between the fixed

    section and underground structure be longer than 3

    m. The fixed section has to be 5 m away from theground surface (see Figure 10.24).

    The anchorage length must be embedded within the shadow area and

    k di h 1 8 f h d f il f

  • 8/13/2019 6 Design for deep excavation civil engineering

    87/121

    FIGURE 10.24 Locations of the anchorage sections in soil (redraw after BSI, 1989)

    keep a distance more than 1.8 m from the assumed failure surface

    Assumed failure surface

    Assumed support

    Depth

    C B

    D

    A E

    F

    G

    2/45o

    2/45

    o

    2/45 o

    Locations of the anchorage sections

  • 8/13/2019 6 Design for deep excavation civil engineering

    88/121

    FIGURE 10.25 Distance between an anchorage section and the potential failure surface

    Assumed failure surface

    (potential failure surface)

    2 m

    b d f

  • 8/13/2019 6 Design for deep excavation civil engineering

    89/121

    FIGURE 10.26 Potential failure surfaces in excavations

    Excavation surface

    Assumed supports

    Wall bottom 2

    45

    C

    a

    b d f

    e

    The installation angle of anchors

  • 8/13/2019 6 Design for deep excavation civil engineering

    90/121

    g

    Theoretically, if an anchor is installed with the same direction of

    loading, it is able to develop the maximum capacity.

    Considering the installation quality, to clear the dregs in the drillingbore of the anchor, the installation angle should not be smaller than 10.

    The fixed section should be placed in a bearing layer (such as a

    sandy layer, gravelly layer, or rocks) or soils with high strength.

    Generally speaking, the deeper the soils, the higher the strength. It ismore suitable to place the fixed section in deeper soil. As a result, an

    anchor is usually installed with a certain slope. The steeper the slope,

    however, the larger the dragging down force on the retaining wall.

    When the installation angle exceeds 45, it becomes dangerous.

    That is to say, without going beyond 45, the installation angle

    should fall within the range .

    4510

    10 7 4 Design of Anchor Heads Anchor Stands and

  • 8/13/2019 6 Design for deep excavation civil engineering

    91/121

    The locking device should be tested before using and its

    locking capacity should be large enough to make the

    tendon bear 80% of the ultimate loading without being

    damaged. If the locking device is used with a wedge clip,the locked tendon should not slide too much. The bearing

    strength of the bearing plate should be large enough to

    resist the maximum pulling force during the process of

    preloading and excavation.

    10.7.4 Design of Anchor Heads, Anchor Stands, and

    Wales

  • 8/13/2019 6 Design for deep excavation civil engineering

    92/121

    The function of an anchor stand is to transfer the load on the wale

    or the retaining wall to the anchored soil layer. Anchor stands

    can be categorized into reinforced concrete anchor stands and

    steel anchor stands. The detailing of reinforcements of the

    concrete anchor stand should be carefully designed to meet safety

    requirements. Under the working load, the allowable

    compressive stress of the concrete anchor stand should be smaller

    than 30% of the 28th-day strength of concrete.

  • 8/13/2019 6 Design for deep excavation civil engineering

    93/121

    FIGURE 10.27 Commonly used anchor stands

    Steel bond

    Steel anchorstandWale

    Retaining wall

    Anti-erosion

    materialsConcrete anchor

    stand

    Bearing

    plate

    Steel anchor stand

    L1

  • 8/13/2019 6 Design for deep excavation civil engineering

    94/121

    Steel bond

    Wale

    hor stand

    Lower/ upper brackets

    Upper wale

    Anchor stand

    Lower wale

    Soldier pile

    FIGURE 10.28 Configuration of wales in anchored system

    PL1

    Pv

    Anchor force

    L1

    L2

    The stress of a wale can be examined as follows

  • 8/13/2019 6 Design for deep excavation civil engineering

    95/121

    (1) Stress computation in the direction of strong axis

    Viewing the wale between two anchors as a simplysupported beam structure, the maximum bending

    moment and shear are(10.60)

    (10.61)

    where = maximum bending moment in the direction ofstrong axis

    = maximum shear in the direction of strong axis

    = lateral earth pressure on the wale

    = horizontal distance between anchors

    2

    1max 8

    1

    pLM

    1max2

    1pLQ

    maxM

    maxQ

    p

    1L

    A i h d i f l i h b d i

  • 8/13/2019 6 Design for deep excavation civil engineering

    96/121

    As in the design of a wale in the braced excavation

    introduced in Section 10.5.3, if the joint is placed at

    the distance of 1/4 of the span from the support, themaximum bending moment can be computed by the

    following equation

    (10.62)2max

    10

    1pLM =

    The bending stress and shear stress of the wale in the direction of

  • 8/13/2019 6 Design for deep excavation civil engineering

    97/121

    The bending stress and shear stress of the wale in the direction of

    the strong axis should satisfy the following criteria:

    (10.63)

    (10.64)

    = section modulus of the member in the direction of thestrong axis

    = area of the web of the member

    = allowable bending stress of the member=(0.6~0.66)

    = allowable shear stress of the member=0.4

    = yielding stress of the member

    =short-term magnified factor of the allowable stress

    axS

    M

    2/max

    awA

    Q 2/max

    xS

    wA

    a

    ly

    Fa

    yF

    l

    lyF

    (2) Stress computation in the direction of the weak

  • 8/13/2019 6 Design for deep excavation civil engineering

    98/121

    axis

    Viewing the wale between the brackets supporting the anchor as a

    beam, the maximum bending moment and shear of the wale are

    (10.65)

    (10.66)

    (10.67)

    = maximum bending moment in the direction of weak axis

    = maximum shear in the direction of weak axis

    = vertical component of the anchorage force at the support

    = distance between the brackets supporting the anchor

    tan1pLPv=tan4

    1

    4

    1212max LpLLPM v

    tan2

    1

    2

    11max pLPQ v=

    maxM

    maxQ

    vP

    2L

    The bending stress and shear stress of the wale in the direction of the

    k i h ld ti f th f ll i diti

  • 8/13/2019 6 Design for deep excavation civil engineering

    99/121

    weak axis should satisfy the following conditions

    = section modulus of the member in the direction of weak axis

    = area of a single flange of the member

    = allowable bending stress of the member=0.75

    = allowable shear stress of the member=0.4

    = yielding stress of the member= short-term magnified factor of the allowable stress

    ayS

    M

    2/max

    afA

    Q 2/max

    yS

    fA

    a lyF

    a

    yFl

    lyF

    (10.68)

    (10.69)

    10 7 5 Design of the Free Section

  • 8/13/2019 6 Design for deep excavation civil engineering

    100/121

    The free section is composed of a tendon and a plastic

    casing. Three types of tendons are availablesteel bars,steel wires, and strands. The 7-wire strand is common in

    many countries, usually available in size of 13 mm(0.5 1n),

    15mm (0.6 in) and 18 mm (0.7 in). The ultimate tensile

    strength varies from 1570 to 1765 N/mm2

    . The allowabletensile force can be computed as follows

    (10.70)

    where = designed safety factor for the tendon. Table 10.4

    lists the commonly used factors of safety.

    tuw FPP /=

    tF

    10.7.5 Design of the Free Section

    TABLE 10.4 Factor of safety for single anchor

    il f h i

  • 8/13/2019 6 Design for deep excavation civil engineering

    101/121

    ClassificationTensile force

    of tendons

    ( )

    Anchoring

    force

    ( )

    Bond force of

    tendons ( )

    Temporary anchors whose working

    period is not longer than 6 months and

    which dont affect public safety when

    failing(2)

    1.4 2.0 2.0

    Temporary anchors whose workingperiod is not longer than 2 years and

    which dont affect public safety,

    though having certain influence, when

    failing without alert

    1.6 2.5 (3) 2.5 (3)

    Permanent or temporary anchors which

    are highly risky in rusting or which

    affect public safety seriously due to

    failure(2)

    2.0 3.0 (4) 3.0 (3)

    tF

    aF b

    F

  • 8/13/2019 6 Design for deep excavation civil engineering

    102/121

    NOTE:

    (1) The table is from CICHE (1998), incorporating specifications

    made by BSI (1989) and FIP (1982)

    (2) The temporary anchors in this table refer to those whoseworking periods are not longer than 2 years. Otherwise, they

    are classified as permanent anchors.

    (3) With complete proving test results, the minimum factor of

    safety can be 2.0.

    (4) If creep of soil is to be encountered, the factor of safety can be

    increased to 4.0.

    Th b f t d i

  • 8/13/2019 6 Design for deep excavation civil engineering

    103/121

    The number of tendons is

    (10.71)

    As discussed above, is computed usingEq. 10.59, transforming the horizontal

    component, as analyzed using the apparent

    earth pressure method, the beam on elastic

    foundation method, or the finite elementmethod.

    w

    w

    P

    Tn =

    wT

  • 8/13/2019 6 Design for deep excavation civil engineering

    104/121

    As Figures 10.24 and 10.25 illustrate, the free section

    has to extend beyond the potential failure zone by at

    least 2.0 m. If the free section is too short, the

    stresses in soils caused by the fixed section will

    easily affect the retaining wall. In addition, theanchor behavior will tend to be fragile, any small

    displacement possibly bring about large stress, and

    threatening the security of the anchor. Therefore, thefree section has to be at least 4.0 m long.

    10.7.6 Design of the Fixed Section

  • 8/13/2019 6 Design for deep excavation civil engineering

    105/121

    The fixed section of an anchor should be placed 2.0 m

    away from the potential failure zone. The design of a fixed

    section includes the bond forces between tendons and

    grouts and the anchorage force between the fixed section

    and soils.The bond forces between tendons and grout have to be

    large enough so that the designed strength of the anchor can

    fully develop. Table 10.4 suggests the safety factors

    between tendons and grout. As for the allowable bondforces between tendons and cement grout, we can use the

    values as suggested by JSF (1990), as shown in Table 10.5.

    10.7.6 Design of the Fixed Section

  • 8/13/2019 6 Design for deep excavation civil engineering

    106/121

    TABLE 10.4 Factor of safety for single anchor (CICHE, 1998)

    ClassificationTensile forceof tendons

    ( )

    Anchoring force

    ( )

    Bond force of

    tendons ( )

    Temporary anchors whose working period

    is not longer than 6 months and which

    dont affect public safety when failing(2)1.4 2.0 2.0

    Temporary anchors whose working period

    is not longer than 2 years and which dont

    affect public safety, though having certain

    influence, when failing without alert

    1.6 2.5 (3) 2.5 (3)

    Permanent or temporary anchors which arehighly risky in rusting or which affect

    public safety seriously due to failure(2)2.0 3.0 (4) 3.0 (3)

    tF aF bF

  • 8/13/2019 6 Design for deep excavation civil engineering

    107/121

    NOTE:

    (1) The table is from CICHE (1998), incorporating specifications

    made by BSI (1989) and FIP (1982)

    (2) The temporary anchors in this table refer to those whose

    working periods are not longer than 2 years. Otherwise, theyare classified as permanent anchors.

    (3) With complete proving test results, the minimum factor of

    safety can be 2.0.

    (4) If creep of soil is to be encountered, the factor of safety can

    be increased to 4.0.

    TABLE 10 5 All bl b d f f t d i t t (JSF 1990)

  • 8/13/2019 6 Design for deep excavation civil engineering

    108/121

    TABLE 10.5 Allowable bond force of tendons in cement mortar (JSF, 1990)

    Designed compressive strength of

    cement mortar ( )2cm/kgTypes of tendons

    150 180 240 300 >400

    Temporary

    anchors

    Steel wireRound steel bar

    Steel strand

    Multiple steel

    strand

    8

    8

    8

    8

    10

    10

    10

    10

    12

    12

    12

    12

    13.5

    13.5

    13.5

    13.5

    15

    15

    15

    15

    Permanent

    anchors

    Steel wireRound steel bar

    Steel strand

    Multiple steel

    strand

    8

    8

    8

    8

    9

    9

    9

    9

    10

    10

    10

    10

    The anchorage force between the fixed section and soils

  • 8/13/2019 6 Design for deep excavation civil engineering

    109/121

    (1) Friction type of anchor

    The ultimate anchorage force, Tu, for a friction type ofanchor can be computed by the following equation

    = ultimate anchorage force

    = diameter of the fixed section

    = length of the fixed section

    = average ultimate shear resistance strength per unit area

    (also called the frictional strength) between the fixed

    section and soils

    uT

    ultabu LdT

    bd

    aL

    ult

    (10.72)

    h d i d l d h h i

  • 8/13/2019 6 Design for deep excavation civil engineering

    110/121

    The designed load on the anchor is

    (10.73)

    where = safety factor of the designed anchorage force; the

    commonly used factors of safety are listed in Table 10.4.

    a

    u

    w

    F

    TT =

    aF

  • 8/13/2019 6 Design for deep excavation civil engineering

    111/121

    The strength between the fixed sectionand the surrounding soil, , changes with

    the types of soils where the fixed section is

    placed, the failure mode of the fixed section,

    the grouting pressure, and the installation

    method. Many investigators have proposed

    some empirical formulas to estimate .

    ult

    ult

    (a) Anchorage in rocks

  • 8/13/2019 6 Design for deep excavation civil engineering

    112/121

    Null pressurized anchors are often used for rocks (see

    Figure 10.22). Little john's suggestion (1970) is usually

    taken for the ultimate shear resistance strength between

    the fixed section and rocks. That is, let be 0.1 qu (forblock rocks) or 0.25 qu (for weathered rocks) where qu is

    the axial compressive strength of rock. Anchor choice is

    to adopt the suggestions by JSF (1990), as sown in Table10.6.

    ult

    TABLE 10.6 Ultimate frictional strength of an anchorage body (JSF, 1990)

  • 8/13/2019 6 Design for deep excavation civil engineering

    113/121

    ult )cm/kg( 2

    N

    Type of soil

    Rock

    Hard rockSoft rock

    Weathered rock

    Mudstone

    15 ~ 25

    10 ~ 15

    6 ~ 10

    6 ~ 12

    Gravel

    =10

    =20

    =30=40

    =50

    1.0 ~ 2.0

    1.7 ~ 2.5

    2.5 ~ 3.53.5 ~ 4.5

    4.5 ~ 7.0

    Gravel

    =10

    =20

    =30

    =40

    =50

    1.0 ~ 1.4

    1.8 ~ 2.2

    2.3 ~ 2.7

    2.9 ~ 3.5

    3.0 ~ 4.0

    Clay 1.0 c

    N

    NNNNNNNN

    Note :Nis standard penetration test number, c is cohesion, and

    is ultimate frictional strength after pressure groutingult

    (b) Anchorage in sandy soils

  • 8/13/2019 6 Design for deep excavation civil engineering

    114/121

    The -value of an anchor in sandy soils can be computed as

    follows

    (10.74)

    = the average effective overage effective overburden pressure

    above the fixed section= the angle of friction between the fixed section and soils

    Because anchors in sandy soils are usually the low

    pressure type, the average ultimate shear strength of sandis usually determined on the basis of experience or field

    tests.

    ult

    tanvult v

    (c) Anchorage in clayey soils

  • 8/13/2019 6 Design for deep excavation civil engineering

    115/121

    Anchors in clays are usually installed following the null

    pressurized grouting method (see Figure 10.22). The ultimate

    shear resistance strength of the fixed section in clayey soils can be

    expressed as follows

    (10.75)

    where = undrained shear strength of clay

    = reduction factor for undrained shear strength

    uult

    s =u

    s

    1.2

  • 8/13/2019 6 Design for deep excavation civil engineering

    116/121

    API

    0.0 0.2 0.4 0.6 0.8 1.00.0

    0.2

    0.4

    0.6

    0.8

    1.0

    vu/s

    Cast-in-

    place pile

    FIGURE 4.12 Relation between adhesion and undrained shear strength of clay

  • 8/13/2019 6 Design for deep excavation civil engineering

    117/121

    As Eq. 10.72 shows, the longer the fixed section, the

    larger the anchorage force. However, many investigatorshave found that when the length of the fixed section

    exceeds some critical value, more lengthening of the

    fixed section can hardly increase its anchorage force.

    Thus, the length of the fixed section has to be limited. In

    principle, the length of the fixed section is best when

    between 3.0 and 10.0 m. If out of this range, it is better

    to carry out field tests to examine the ultimate anchorageforce. Table 10.7 lists specifications on the minimum and

    maximum length of the fixed section.

    TABLE 10.7 Specifications for the length of the fixed section (CICHE, 1998)

  • 8/13/2019 6 Design for deep excavation civil engineering

    118/121

    Specifications Minimum suggested distance

    FIP (1982) and

    BSI (1989)

    No shorter than 3 m, except if the proving test

    result is satisfactory in fulfilling the design, and

    not longer than 10 m, under normal condition

    PTI (1980) No shorter than 3 m

    JSF (1990) Between 3 ~10 m

    GCO (1989) No shorter than 3 m

    AASHTO

    (1992)In soil, no shorter than 4.6 m; in rock, 3 m

    10.7.7 Preloading

  • 8/13/2019 6 Design for deep excavation civil engineering

    119/121

    Locked Preloading or the Locked Load

    The anchor installed, it usually needs to be

    preloaded and locked, which is called locked

    preloading or the locked load.

    The locked load is usually a little larger than

    the designed load of the anchor because the

    slipping of the wedge clips during the process of

    locking will cause some loss of the anchorpreload. After locking, the remaining force is

    called the effective load.

    10.7.7 Preloading

  • 8/13/2019 6 Design for deep excavation civil engineering

    120/121

    10.8 Tests of Anchors

  • 8/13/2019 6 Design for deep excavation civil engineering

    121/121

    Influenced by the process of fabrication, grouting, and

    geological conditions, the actual ultimate load of an anchorhas to be examined through field tests. The tests are

    classified into many methods in terms of their different

    aims, though their common goal is to understand the

    deformation behaviors and load capacities of the anchor.

    Anchor tests can be distinguished into theproving test, the

    suitability test, and the acceptance test.