5deapwaterchallenges _robertobenzanaoec2012
TRANSCRIPT
-
8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012
1/29
1
Risk Management of the First Deepwater
Project in ChinaAsia Offshore Energy ConferenceSeptember 27, 2012
-
8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012
2/29
2
Advisories
Forward-Looking Statements
Certain statements in this presentation are forward-looking statements or information within the meaning of applicable securitieslegislation (collectively “forward-looking statements”). Any statements that express, or involve discussions as to, expectations, beliefs,plans, objectives, assumptions or future events or performance (often, but not always, through the use of words or phrases such as“likely,” “expected,” “will,” “anticipated,” “on our way,” “estimated,” “intend,” “plan,” “projection,” “could,” “vision,” “goals,” “objective,”“target,” “scheduled” and “outlook”) are not historical facts, are forward-looking and may involve estimates and assumptions and are
subject to risks, uncertainties and other factors some of which are beyond the Company’s control and difficult to predict. Accordingly,these factors could cause actual results or outcomes to differ materially from those expressed in the forward-looking statements.
In particular, forward-looking statements in this presentation include, but are not limited to: the Company’s short, medium, and long-termgrowth strategies and opportunities in its upstream, infrastructure and marketing and downstream business segments; estimated risinggas demand in Asia; planned timing of first production at the Company's Asia Pacific properties; expected delivery time of mono-ethyleneglycol unit for Block 29/26; and expected timing for strong cash flow generation at the Company’s Liwan property.
Although the Company believes that the expectations reflected by the forward-looking statements in this presentation are reasonable, theCompany’s forward-looking statements have been based on assumptions and factors concerning future events that may prove to beinaccurate. Those assumptions and factors are based on information currently available to the Company about itself and the businessesin which it operates. In addition, information used in developing forward-looking statements has been acquired from various sourcesincluding third-party consultants, suppliers, regulators and other sources.
-
8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012
3/29
3
Roberto BenzanManager, Corporate Risk Management
+1 (403) [email protected]
Thank you
-
8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012
4/29
Risk Management of the First DeepwaterProject in ChinaAsia Offshore Energy ConferenceSeptember 27, 2012
-
8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012
5/29
55
• Amongst largest Canadianintegrated energy companies
• Balanced growth and dividendproposition
• Strong balance sheet positionedto commercialize a rich portfolio
of growth opportunities• Production ~70% oil bias
• Focused integration to reducevolatility and capture the Heavy
Oil and Oil Sands value chain
Husky Snapshot
-
8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012
6/29
6
Near-term2010 – 2012
Mid-term2013 – 2015
Long-term2016+
Upstream Acquisitions Asia Pacific • Oil Sands Oil Sands • Atlantic Region
Transforming Western Canada and Heavy Oil foundation
Value acceleration
Infrastructure
and Marketing,Downstream
Remove volatility from heavy oil and oil sands by capturing differentials
Strategic Building Blocks
-
8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012
7/29
7
Asia Pacific Energy Requirements:Rising Gas Demand in Asia Creates Opportunity
7
Source: Trizen China Gas Pricing report, Sept. 2011
-
8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012
8/29
8
Asia Pacific Growth Strategy
• Building a material oil and gasbusiness
• Liwan 3-1 and Liuhua 34-2developments expected to be onstream in 2013/14
• Madura Strait and Liuhua 29-1gas field expected to be on streamin 2014/15
• Strong partnership history withCNOOC
8
-
8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012
9/29
9
Background
• Deepwater gas field discovered in June2006 in 1,400m water depth
• Successfully drilled and tested threeappraisal wells
• Satellite discoveries at Liuhua 34-2 andLiuhua 29-1
• First gas production targeted for 2013 /2014
• Three fields under development
Remaining Block 29/26 Area
Relinquishment Area (Sept 30, 2007)
320Km
29/26 29/06Husky
LH34-2-1Discovery Well
LW3-1-2Appraisal Well
LW3-1-4Appraisal Well
LW3-1-1Discovery Well
LW3-1-10Development Well
LH34-3-1Discovery Well
LH29-1-1Discovery Well
LH34-2-2Appraisal Well
LH29-1-2Appraisal Well
LW3-1-3Appraisal Well
LH29-1-3Appraisal
Well
-
8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012
10/29
10
West Manifold
Pipeline End Manifold
Central Platform
Main Flowlines
East Manifold
Liuhua 34-2 FieldSingle well development
Onshore Gas Plant
Block 29/26 Development
Deep Water Facilities(Husky Operated)
Liuhua 29-1 FieldFuture 6-7 well development
Shallow Water and Onshore Facilities(CNOOC Operated)
Liwan 3-1 Field8 well development
MEG Package
-
8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012
11/29
11
0
• West Hercules − continuous
operations 2008-2012
• Drilled 25 wells
• Water Depths: 700 m – 1800 m
• Conducted six Drill Stem Tests
Block 29/26 Drilling & Completions
1,000 days – No LTAs No Environmental Incidents
-
8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012
12/29
12
Liwan Well Architecture Installed in 1,400m Water Depth
6 to 8 slot Well Manifolds
Pipeline End Termination Manifolds
Production Wells
-
8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012
13/29
13
Block 29/26 - Deepwater Development by Husky(Husky 49% W.I.)
Status
• Drilling work
− LW3-1 / LH34-2 wells drilled− 10 lower completions and six upper
completions installed
• Subsea Equipment
− All 10 trees delivered and now installedon subsea wellheads in the fields
• Marine Installation
− Final design / planning ongoing. All
services contracted
• Mono-ethylene Glycol Unit
− Unit to be delivered in September /October 2012
-
8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012
14/29
14
MEG Unit Construction
-
8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012
15/29
15
15
Block 29/26 Development:A Global Project Requiring World-Class Skills
15
Cameron (Subsea) - USAHouston - Manifold Design
and 22 inch connector manufacturing
Cameron (Subsea)- UKSubsea Trees and Connectors
Cameron (Subsea) - GermanySubsea Controls Design and
Manufacture
Saipem - FranceFlowline and Installation Design
Cameron (Process) - SingaporeMEG Project Management
Cameron (Subsea) - MalaysiaProject Management and
Manufacturing
Cameron (Process) - ChinaTianjin – MEG Module Fabrication
Qingdao – MEG module integration
Husky Oil China Ltd
Shenzhen – DW TeamOverall Project Management
Saipem -SingaporeInstallation Project Management
Malaysia:Project Detailed Engineering
CNOOC / COOECTangu – Engineering & Design
Qingdao – Jacket and Topsides FabricationBeijing - Procurement
CNOOCShenzhen – SW Owners Team Project
ManagementGaolan – Gas Plant Construction
China (General) Pipeline / Steel supplyand domestic equipment
Cameron (Subsea)- italySubsea Pipeline Valves
Saipem – NorwayUmbilical Design and Manufacturing
Cameron (Subsea) - AustraliaControl System HPU
Saipem - China
Flowline Pipe Supply
18 sites in 10 countriesare working on Block 29/26
Head Office,Calgary, Canada
-
8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012
16/29
16
• Project substantially progressed and majoractivities de-risked:
− Engineering complete
− Wells drilled and reservoir proven
− Installation progressing as planned and
within budget
− First gas expected late 2013/early 2014
• Attractive returns
− Oil-based pricing
− Strong cash flow generation in 2014
− Revenue split 49% / 51% with CNOOC
− Exploration and Development cost recoveryprioritized
− Competitive tax and royalty rates
16
Topsides fabrication is proceeding on schedule
Jacket complete, sailing to site
Liwan Progress
-
8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012
17/29
17
Shallow Water Development by CNOOC
• Platform among the world’s largest – in top 25
• CNOOC installing
− Central Platform
− 30” pipeline to shore – 260 km
− Onshore gas plant – 800 mmcfd
− All scalable to 1,200 mmcfd
• Separate gas and condensate and LPGs for salescompress gas
− Transport 260 km to onshore gas plant
• MEG System – Hydrate Mitigation
− Pump glycol to subsea trees and manifolds
− Process the glycol offshore for recycle
• Five major projects to deliver:− Jacket− Topsides− Pipeline to Shore− Gas Plant− Panyu – 100% CNOOC project
PDMS 3 D Model Snap Shot
-
8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012
18/29
18
Gaolan Onshore Gas Plant and Energy Hub
-
8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012
19/29
19
Completion of Jacket Load-Out
COMPLETION OF JACKET LOAD-OUT JULY 20 17:00 HOURS
-
8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012
20/29
20
-
8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012
21/29
21
CEP Topside Fabrication
-
8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012
22/29
22
Liability and Insurance Challenges
• First deepwater project:− For China
− For Husky Energy
− Two partners each operating a portion of the project
• Scale and scope of the project:− One of the largest platforms in the world
− One of the largest floatovers
− Diverse geographic construction base
• Contracting and insurance processes− Different timelines
• Strong alignment− Safety
− Environmental stewardship− Partner alignment
• Other challenges:− Weather
− Insurance & financial market environment− Contracting environment
-
8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012
23/29
23
Contracting Strategy
• Minimize interfaces by tendering three EPC contracts
− Subsea Equipment Supply (Husky)
− Deepwater EPCI (Husky)
− MEG Package (for CEP topsides)
• Competitively tendered all three contracts
• All bidders were deepwater industry leaders in the international offshoreconstruction market
• Emphasis on proven deepwater technology
• Contracting with proven deepwater contractors
• Built on experienced leadership and project management team
-
8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012
24/29
24
• Contracts negotiated before insurance program finalised
• Contractor concerns:
− Other Assured Status− QA/QC provisions for contractor
− Defective part buyback endorsement
− Damage to existing property
− Property in Care, Custody and Control− Deductibles
• QA/QC:
− Project has dedicated QA Coordinator in the Husky team managing thesubsea equipment supply contract
− Project has dedicated QA / Welding Engineer in the central project
team
24
Contractual Challenges
-
8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012
25/29
25
• Construction All Risks (CAR) utilising Welcar 2001 policy wording
− All contract works that will constitute the “deep” water element of Liwan
(including the Liuhua 34-2 and 29-1 extensions) in Pearl River Mouth Basin,
South China Sea, the People's Republic of China.
− Policy period: 1 May 2011 to 31 December 2013; but not beyond 31 March 2014
plus 24 months maintenance
− Covered as soon as they become Husky’s risk anywhere in the world, including
while at contractors’ yards and in transit.
− Underwriters: PICC Property and Casualty Insurance Co. Ltd; Ping An Property
and Casualty Insurance Company of China Ltd; China Pacific Property InsuranceCo. Ltd
• Contractor responsible for deductible on a “sliding scale”
• Company responsible for “gap” in deductibles / coverages
25
Deep Water Insurance Coverage
-
8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012
26/29
26
• Husky Corporate Risk Management group in Calgary, Canada, Project Teamin Shekou, JV Partner in Beijing; Insurance Brokers in Calgary, London &Beijing – 7 and 14 hour time differences
• Maintaining strong communications with J.V. Partners; Project team andInsurance Underwriters
• The scale and scope of the insurance program (and premium)
• Interface between the deepwater and shallow water projects; interfacebetween Chinese direct underwriters and European reinsurance underwriters
• Emphasis on complying with local regulations
• Strong focus on Operational Integrity and Loss Prevention
26
Insurance Challenges
-
8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012
27/29
2727
Risk Metrics
Cause Category Risk Count %01 Contractual 47 15.4%06 Project Organisation 42 13.7%02 Equipment and Supply 37 12.1%05 Interfaces (Technical) 36 11.8%12 Partners / Stakeholders 31 10.1%
03 Environmental (Weather) 27 8.8%07 Technology 26 8.5%09 Financial / Economic 20 6.5%10 Country / Government / Political 19 6.2%04 Regulatory 18 5.9%08 HSE 6 2.0%11 Marketing 4 1.3%
Total Distinct Risk Count 306
Risks identified and an effectivemanagement plan establishedand implemented to mitigate
-
8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012
28/29
Roberto BenzanManager, Corporate Risk Management
+1 (403) 298-6261
Thank you
-
8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012
29/29
29
Advisories
Forward-Looking Statements
Certain statements in this presentation are forward-looking statements or information within the meaning of applicable securitieslegislation (collectively “forward-looking statements”). Any statements that express, or involve discussions as to, expectations, beliefs,plans, objectives, assumptions or future events or performance (often, but not always, through the use of words or phrases such as“likely,” “expected,” “will,” “anticipated,” “on our way,” “estimated,” “intend,” “plan,” “projection,” “could,” “vision,” “goals,” “objective,”“target,” “scheduled” and “outlook”) are not historical facts, are forward-looking and may involve estimates and assumptions and aresubject to risks, uncertainties and other factors some of which are beyond the Company’s control and difficult to predict. Accordingly,
these factors could cause actual results or outcomes to differ materially from those expressed in the forward-looking statements.
In particular, forward-looking statements in this presentation include, but are not limited to: the Company’s short, medium, and long-termgrowth strategies and opportunities in its upstream, infrastructure and marketing and downstream business segments; estimated risinggas demand in Asia; planned timing of first production at the Company's Asia Pacific properties; expected delivery time of mono-ethyleneglycol unit for Block 29/26; and expected timing for strong cash flow generation at the Company’s Liwan property.
Although the Company believes that the expectations reflected by the forward-looking statements in this presentation are reasonable, the
Company’s forward-looking statements have been based on assumptions and factors concerning future events that may prove to beinaccurate. Those assumptions and factors are based on information currently available to the Company about itself and the businessesin which it operates. In addition, information used in developing forward-looking statements has been acquired from various sourcesincluding third-party consultants, suppliers, regulators and other sources.