5deapwaterchallenges _robertobenzanaoec2012

Upload: yuth-yuthdanai

Post on 06-Jul-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012

    1/29

    1

    Risk Management of the First Deepwater

    Project in ChinaAsia Offshore Energy ConferenceSeptember 27, 2012

  • 8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012

    2/29

    2

    Advisories

    Forward-Looking Statements

    Certain statements in this presentation are forward-looking statements or information within the meaning of applicable securitieslegislation (collectively “forward-looking statements”). Any statements that express, or involve discussions as to, expectations, beliefs,plans, objectives, assumptions or future events or performance (often, but not always, through the use of words or phrases such as“likely,” “expected,” “will,” “anticipated,” “on our way,” “estimated,” “intend,” “plan,” “projection,” “could,” “vision,” “goals,” “objective,”“target,” “scheduled” and “outlook”) are not historical facts, are forward-looking and may involve estimates and assumptions and are

    subject to risks, uncertainties and other factors some of which are beyond the Company’s control and difficult to predict. Accordingly,these factors could cause actual results or outcomes to differ materially from those expressed in the forward-looking statements.

    In particular, forward-looking statements in this presentation include, but are not limited to: the Company’s short, medium, and long-termgrowth strategies and opportunities in its upstream, infrastructure and marketing and downstream business segments; estimated risinggas demand in Asia; planned timing of first production at the Company's Asia Pacific properties; expected delivery time of mono-ethyleneglycol unit for Block 29/26; and expected timing for strong cash flow generation at the Company’s Liwan property.

    Although the Company believes that the expectations reflected by the forward-looking statements in this presentation are reasonable, theCompany’s forward-looking statements have been based on assumptions and factors concerning future events that may prove to beinaccurate. Those assumptions and factors are based on information currently available to the Company about itself and the businessesin which it operates. In addition, information used in developing forward-looking statements has been acquired from various sourcesincluding third-party consultants, suppliers, regulators and other sources.

  • 8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012

    3/29

    3

    Roberto BenzanManager, Corporate Risk Management

    +1 (403) [email protected]

    Thank you

  • 8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012

    4/29

    Risk Management of the First DeepwaterProject in ChinaAsia Offshore Energy ConferenceSeptember 27, 2012

  • 8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012

    5/29

    55

    • Amongst largest Canadianintegrated energy companies

    • Balanced growth and dividendproposition

    • Strong balance sheet positionedto commercialize a rich portfolio

    of growth opportunities• Production ~70% oil bias

    • Focused integration to reducevolatility and capture the Heavy

    Oil and Oil Sands value chain

    Husky Snapshot

  • 8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012

    6/29

    6

    Near-term2010 – 2012 

    Mid-term2013 – 2015 

    Long-term2016+ 

    Upstream Acquisitions Asia Pacific • Oil Sands Oil Sands • Atlantic Region

    Transforming Western Canada and Heavy Oil foundation

    Value acceleration

    Infrastructure

    and Marketing,Downstream

    Remove volatility from heavy oil and oil sands by capturing differentials

    Strategic Building Blocks

  • 8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012

    7/29

    7

    Asia Pacific Energy Requirements:Rising Gas Demand in Asia Creates Opportunity

    7

    Source: Trizen China Gas Pricing report, Sept. 2011

  • 8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012

    8/29

    8

    Asia Pacific Growth Strategy

    • Building a material oil and gasbusiness

    • Liwan 3-1 and Liuhua 34-2developments expected to be onstream in 2013/14

    • Madura Strait and Liuhua 29-1gas field expected to be on streamin 2014/15

    • Strong partnership history withCNOOC

    8

  • 8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012

    9/29

    9

    Background

    • Deepwater gas field discovered in June2006 in 1,400m water depth

    • Successfully drilled and tested threeappraisal wells

    • Satellite discoveries at Liuhua 34-2 andLiuhua 29-1

    • First gas production targeted for 2013 /2014

    • Three fields under development

    Remaining Block 29/26 Area

    Relinquishment Area (Sept 30, 2007)

    320Km

    29/26 29/06Husky

    LH34-2-1Discovery Well

    LW3-1-2Appraisal Well

    LW3-1-4Appraisal Well

    LW3-1-1Discovery Well

    LW3-1-10Development Well

    LH34-3-1Discovery Well

    LH29-1-1Discovery Well

    LH34-2-2Appraisal Well

    LH29-1-2Appraisal Well

    LW3-1-3Appraisal Well

    LH29-1-3Appraisal

    Well

  • 8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012

    10/29

    10

    West Manifold

    Pipeline End Manifold

    Central Platform

    Main Flowlines

    East Manifold

    Liuhua 34-2 FieldSingle well development

    Onshore Gas Plant

    Block 29/26 Development

    Deep Water Facilities(Husky Operated)

    Liuhua 29-1 FieldFuture 6-7 well development

    Shallow Water and Onshore Facilities(CNOOC Operated)

    Liwan 3-1 Field8 well development

    MEG Package

  • 8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012

    11/29

    11

    0

    • West Hercules − continuous

    operations 2008-2012

    • Drilled 25 wells

    • Water Depths: 700 m – 1800 m

    • Conducted six Drill Stem Tests

    Block 29/26 Drilling & Completions

    1,000 days – No LTAs No Environmental Incidents 

  • 8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012

    12/29

    12

    Liwan Well Architecture Installed in 1,400m Water Depth

    6 to 8 slot Well Manifolds

    Pipeline End Termination Manifolds

    Production Wells

  • 8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012

    13/29

    13

    Block 29/26 - Deepwater Development by Husky(Husky 49% W.I.)

    Status

    • Drilling work

    − LW3-1 / LH34-2 wells drilled− 10 lower completions and six upper

    completions installed

    • Subsea Equipment

    − All 10 trees delivered and now installedon subsea wellheads in the fields

    • Marine Installation

    − Final design / planning ongoing. All

    services contracted

    • Mono-ethylene Glycol Unit

    − Unit to be delivered in September /October 2012

  • 8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012

    14/29

    14

    MEG Unit Construction

  • 8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012

    15/29

    15

    15

    Block 29/26 Development:A Global Project Requiring World-Class Skills

    15

    Cameron (Subsea) - USAHouston - Manifold Design

    and 22 inch connector manufacturing

    Cameron (Subsea)- UKSubsea Trees and Connectors

    Cameron (Subsea) - GermanySubsea Controls Design and

    Manufacture

    Saipem - FranceFlowline and Installation Design

    Cameron (Process) - SingaporeMEG Project Management

    Cameron (Subsea) - MalaysiaProject Management and

    Manufacturing

    Cameron (Process) - ChinaTianjin – MEG Module Fabrication

    Qingdao – MEG module integration

    Husky Oil China Ltd

    Shenzhen – DW TeamOverall Project Management

    Saipem -SingaporeInstallation Project Management

    Malaysia:Project Detailed Engineering

    CNOOC / COOECTangu – Engineering & Design

    Qingdao – Jacket and Topsides FabricationBeijing - Procurement

    CNOOCShenzhen – SW Owners Team Project

    ManagementGaolan – Gas Plant Construction

    China (General) Pipeline / Steel supplyand domestic equipment

    Cameron (Subsea)- italySubsea Pipeline Valves

    Saipem – NorwayUmbilical Design and Manufacturing

    Cameron (Subsea) - AustraliaControl System HPU

    Saipem - China

    Flowline Pipe Supply

    18 sites in 10 countriesare working on Block 29/26

    Head Office,Calgary, Canada

  • 8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012

    16/29

    16

    • Project substantially progressed and majoractivities de-risked:

    − Engineering complete

    − Wells drilled and reservoir proven

    − Installation progressing as planned and

    within budget

    − First gas expected late 2013/early 2014

    • Attractive returns

    − Oil-based pricing

    − Strong cash flow generation in 2014

    − Revenue split 49% / 51% with CNOOC

    − Exploration and Development cost recoveryprioritized

    − Competitive tax and royalty rates

    16

    Topsides fabrication is proceeding on schedule

    Jacket complete, sailing to site

    Liwan Progress

  • 8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012

    17/29

    17

    Shallow Water Development by CNOOC

    • Platform among the world’s largest – in top 25

    • CNOOC installing

    − Central Platform

    − 30” pipeline to shore – 260 km

    − Onshore gas plant – 800 mmcfd

    − All scalable to 1,200 mmcfd

    • Separate gas and condensate and LPGs for salescompress gas

    − Transport 260 km to onshore gas plant

    • MEG System – Hydrate Mitigation

    − Pump glycol to subsea trees and manifolds

    − Process the glycol offshore for recycle

    • Five major projects to deliver:− Jacket− Topsides− Pipeline to Shore− Gas Plant− Panyu – 100% CNOOC project

    PDMS 3 D Model Snap Shot

  • 8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012

    18/29

    18

    Gaolan Onshore Gas Plant and Energy Hub

  • 8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012

    19/29

    19

    Completion of Jacket Load-Out

    COMPLETION OF JACKET LOAD-OUT JULY 20 17:00 HOURS

  • 8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012

    20/29

    20

  • 8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012

    21/29

    21

    CEP Topside Fabrication

  • 8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012

    22/29

    22

    Liability and Insurance Challenges

    • First deepwater project:− For China

    − For Husky Energy

    − Two partners each operating a portion of the project

    • Scale and scope of the project:− One of the largest platforms in the world

    − One of the largest floatovers

    − Diverse geographic construction base

    • Contracting and insurance processes− Different timelines

    • Strong alignment− Safety

    − Environmental stewardship− Partner alignment

    • Other challenges:− Weather

    − Insurance & financial market environment− Contracting environment

  • 8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012

    23/29

    23

    Contracting Strategy

    • Minimize interfaces by tendering three EPC contracts

    − Subsea Equipment Supply (Husky)

    − Deepwater EPCI (Husky)

    − MEG Package (for CEP topsides)

    • Competitively tendered all three contracts

    • All bidders were deepwater industry leaders in the international offshoreconstruction market

    • Emphasis on proven deepwater technology

    • Contracting with proven deepwater contractors

    • Built on experienced leadership and project management team

  • 8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012

    24/29

    24

    • Contracts negotiated before insurance program finalised

    • Contractor concerns:

    − Other Assured Status− QA/QC provisions for contractor

    − Defective part buyback endorsement

    − Damage to existing property

    − Property in Care, Custody and Control− Deductibles

    • QA/QC:

    − Project has dedicated QA Coordinator in the Husky team managing thesubsea equipment supply contract

    − Project has dedicated QA / Welding Engineer in the central project

    team

    24

    Contractual Challenges

  • 8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012

    25/29

    25

    • Construction All Risks (CAR) utilising Welcar 2001 policy wording

    − All contract works that will constitute the “deep” water element of Liwan

    (including the Liuhua 34-2 and 29-1 extensions) in Pearl River Mouth Basin,

    South China Sea, the People's Republic of China.

    − Policy period: 1 May 2011 to 31 December 2013; but not beyond 31 March 2014

    plus 24 months maintenance

    − Covered as soon as they become Husky’s risk anywhere in the world, including

    while at contractors’ yards and in transit.

    − Underwriters: PICC Property and Casualty Insurance Co. Ltd; Ping An Property

    and Casualty Insurance Company of China Ltd; China Pacific Property InsuranceCo. Ltd

    • Contractor responsible for deductible on a “sliding scale”

    • Company responsible for “gap” in deductibles / coverages

    25

    Deep Water Insurance Coverage

  • 8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012

    26/29

    26

    • Husky Corporate Risk Management group in Calgary, Canada, Project Teamin Shekou, JV Partner in Beijing; Insurance Brokers in Calgary, London &Beijing – 7 and 14 hour time differences

    • Maintaining strong communications with J.V. Partners; Project team andInsurance Underwriters

    • The scale and scope of the insurance program (and premium)

    • Interface between the deepwater and shallow water projects; interfacebetween Chinese direct underwriters and European reinsurance underwriters

    • Emphasis on complying with local regulations

    • Strong focus on Operational Integrity and Loss Prevention

    26

    Insurance Challenges

  • 8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012

    27/29

    2727

    Risk Metrics

    Cause Category Risk Count %01 Contractual 47 15.4%06 Project Organisation 42 13.7%02 Equipment and Supply 37 12.1%05 Interfaces (Technical) 36 11.8%12 Partners / Stakeholders 31 10.1%

    03 Environmental (Weather) 27 8.8%07 Technology 26 8.5%09 Financial / Economic 20 6.5%10 Country / Government / Political 19 6.2%04 Regulatory 18 5.9%08 HSE 6 2.0%11 Marketing 4 1.3%

    Total Distinct Risk Count 306

    Risks identified and an effectivemanagement plan establishedand implemented to mitigate

  • 8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012

    28/29

    Roberto BenzanManager, Corporate Risk Management

    +1 (403) 298-6261

    [email protected]

    Thank you

  • 8/17/2019 5DeapwaterChallenges _RobertoBenzanAOEC2012

    29/29

    29

    Advisories

    Forward-Looking Statements

    Certain statements in this presentation are forward-looking statements or information within the meaning of applicable securitieslegislation (collectively “forward-looking statements”). Any statements that express, or involve discussions as to, expectations, beliefs,plans, objectives, assumptions or future events or performance (often, but not always, through the use of words or phrases such as“likely,” “expected,” “will,” “anticipated,” “on our way,” “estimated,” “intend,” “plan,” “projection,” “could,” “vision,” “goals,” “objective,”“target,” “scheduled” and “outlook”) are not historical facts, are forward-looking and may involve estimates and assumptions and aresubject to risks, uncertainties and other factors some of which are beyond the Company’s control and difficult to predict. Accordingly,

    these factors could cause actual results or outcomes to differ materially from those expressed in the forward-looking statements.

    In particular, forward-looking statements in this presentation include, but are not limited to: the Company’s short, medium, and long-termgrowth strategies and opportunities in its upstream, infrastructure and marketing and downstream business segments; estimated risinggas demand in Asia; planned timing of first production at the Company's Asia Pacific properties; expected delivery time of mono-ethyleneglycol unit for Block 29/26; and expected timing for strong cash flow generation at the Company’s Liwan property.

    Although the Company believes that the expectations reflected by the forward-looking statements in this presentation are reasonable, the

    Company’s forward-looking statements have been based on assumptions and factors concerning future events that may prove to beinaccurate. Those assumptions and factors are based on information currently available to the Company about itself and the businessesin which it operates. In addition, information used in developing forward-looking statements has been acquired from various sourcesincluding third-party consultants, suppliers, regulators and other sources.