4k_-_startup_and_commissioningÊÔÔËÐÐ

Upload: naravichandran3662

Post on 05-Apr-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/31/2019 4K_-_Startup_and_Commissioning

    1/17

    PM Workshop

    Start-up & Commissioning

  • 7/31/2019 4K_-_Startup_and_Commissioning

    2/17

    Slides\execution\startup.ppt

    2

    Start-up & Commissioning

    What Is It? Comprehensive Process of Testing and Starting

    Facility & Production Systems

    What Does It Do?

    Demonstrate That the System Can Perform

    A Means for Owners Acceptance

    What Else? Documents Tests (Part of Quality Plan)

  • 7/31/2019 4K_-_Startup_and_Commissioning

    3/17

    Slides\execution\startup.ppt

    3

    Start-up & Commissioning

    Keys to Success Start-up & Commissioning Schedule

    Production Schedule

    Utilities Needed

    Earliest Date System Needed

    Organization

    Start-up Coordinator

    System Teams

  • 7/31/2019 4K_-_Startup_and_Commissioning

    4/17

    Slides\execution\startup.ppt

    4

    Start-up & Commissioning

    Keys to Success (Continued) Documentation

    Project Quality Plan

    Standard Forms

    Written Procedures

    Design Team System Owner

    Material & Utility Needs

    Identify and Validate Availability

  • 7/31/2019 4K_-_Startup_and_Commissioning

    5/17

    Slides\execution\startup.ppt

    5

    Start-up & Commissioning

    Keys to Success (Continued)

    Regular Meetings

    System Team

    Construction Meeting

    System Readiness

    Design Verification

    Past Tests OAT and FAT

    Permits, As Needed

  • 7/31/2019 4K_-_Startup_and_Commissioning

    6/17

    Slides\execution\startup.ppt

    6

    Start-up & Commissioning

    Caution:

    Do Not Start Vendor Systems WithoutManufacturers Representative

  • 7/31/2019 4K_-_Startup_and_Commissioning

    7/17Slides\execution\startup.ppt

    7

    Start-up & Commissioning

    Planning

    Begin Early in Construction

    Review P&IDs and PFDs

    Validate Factory Test/receiving Reports Identify & Calibrate Instrumentation

    Compile Forms for Documentation

    Participate in Construction Meetings

  • 7/31/2019 4K_-_Startup_and_Commissioning

    8/17Slides\execution\startup.ppt

    8

    Start-up & Commissioning

    Scheduling Start-up & Commissioning Develop Schedule

    Integrate Into Construction Schedule

    Must Drive Construction Activities

    Administering & Witnessing

    Walk the System

    Validate Set-points

    Document Tests (Signatures)

  • 7/31/2019 4K_-_Startup_and_Commissioning

    9/17Slides\execution\startup.ppt

    9

    Start-up & Commissioning

    Reporting Status

    System Team Meetings

    Weekly Construction Meetings

    Obtaining & Compiling O & M Manuals

    From Vendors/manufacturers

    From Contractors

    From the Design Team

  • 7/31/2019 4K_-_Startup_and_Commissioning

    10/17Slides\execution\startup.ppt

    10

    Start-up & Commissioning

    Acceptance & Turnover Documents

    Performance Tests

    Signoff and Turnover

    Warranty

  • 7/31/2019 4K_-_Startup_and_Commissioning

    11/17Slides\execution\startup.ppt

    11

    Start-up & Commissioning

    Activities

    Pre-commissioning

    Design Verification

    OAT

    Commissioning

    FAT

    Start-up

  • 7/31/2019 4K_-_Startup_and_Commissioning

    12/17Slides\execution\startup.ppt

    12

    Start-up & Commissioning

    Activities (Continued)

    Acceptance Tests (Performance Tests)

    Document What Needs Fix

    Witness and Signatures

    Turnover (Warranty)

    O & M Manual

    Test Documentation (Option)

    Training (Option)

  • 7/31/2019 4K_-_Startup_and_Commissioning

    13/17Slides\execution\startup.ppt

    13

    Start-up & Commissioning

    Task Often Overlooked

    Failure to Understand Relation to Production Start

    Assigned To Others (I & C)

    Owner Does Not Know How to Start/operate

    Ownership (Designer)

    Original Owner on Another Project/not in Field

  • 7/31/2019 4K_-_Startup_and_Commissioning

    14/17Slides\execution\startup.ppt

    14

    Start-up & Commissioning

    Junior

    Staff

  • 7/31/2019 4K_-_Startup_and_Commissioning

    15/17Slides\execution\startup.ppt

    15

    Start-up & Commissioning

    Construction

    Developdesignsolutionsf

    or

    processdevelopmentdesig

    n

    issues

    STARTUP AND TRAINING

    OPERATOR TRAINING FIELD ENGINEERING SYSTEM TEAM CONSTRUCTION

    Develop Startup plan,

    checklists, procedures, andperformance testing plans

    Respond to RFIs, review

    submittals, observe construction

    Punchlist and FixupPunchlist

    Develop SOPs, and

    Training Manuals with

    Engineering assistance

    Pre-startup ChecklistTrain the Trainer

    Fix Critical Items

    Component Operational Test

    (check PLC function, check component mechanical operation, energize equipment, run

    in manual)Fix Critical Items

    System Operational Test

    (auto operation, set control tuning, begin process testing using product)

    On-the-Job and Classroom

    Training of Equipment

    OperatorsFix Critical Items

    System Performance Acceptance Test

    (system performance demonstration through a range of operating conditions using product where

    possible)

    Training Complete

    System Turnover

    Fix Critical Items

    Full Line Performance Acceptance Test

    Full Line Turnover for

    Production Operation

    Final Inspection Report

    Review Startup Plan and

    SOPs

  • 7/31/2019 4K_-_Startup_and_Commissioning

    16/17Slides\execution\startup.ppt

    16

    Start-up & Commissioning

    VentilationDustCollection

    System

    220-1

    CA

    Electrical

    DRY RUN MATERIAL

    Recycle

    800-1

    Electrical

    Vent Cyclone

    Starch Tank

    110-1Storage

    Truck

    CA

    Elect

    Gain In Wt

    Feeder

    190-1

    Mix Transfer

    Presses

    300-x

    Trimming

    310-x

    4:1 Merge &

    Conveyors

    320-1

    Continued

    Mag Stearate

    Tank 120-1Storage

    Truck

    CA

    Elect Guar Gum

    Tank 130-1StorageTruck CA

    Elect

    Calc. Carb.

    Tank 105-1Truck

    CA

    Elect

    Fiber

    Tank 180-1StorageTruck

    CAElect

    Mixer

    200-1

    Recycle

    900-1

    Hot and Cold

    Water

    CA

    Elect

    CA

    Elect

    CAElect

    CA

    Elect

    CA

    Elect

    CACIP

    Mold

    Bad

    Batch

    CW

    Truck to

    Landfill

    Liquid

    Waste

    LPCLPS

    CWElect

    Liquid

    Waste

    Elect

    Liquid WasteHeat Vent

    VentReject

    VentCWElect

    Vision

    Inspection

    330-1

    CA

    Elect

    Ventilation

    SUPPORTREQUIREMENTS for

    PROCESS STEPS

  • 7/31/2019 4K_-_Startup_and_Commissioning

    17/17Slides\execution\startup ppt

    17

    Start-up & CommissioningCoating

    No.1

    340-1

    CACW

    Coating

    No.2

    360-1

    Airveyor

    380-1

    CAElect

    Stacking

    390-1

    CAElect

    Packaging

    700-1

    CAElect

    Conveyor

    400-1

    CAElect

    Printer /

    Bagger

    600-1

    CAElect

    Heater170-1

    Store

    HVAC

    CIP

    Elect

    Gas

    Drains

    SCADA

    Paraffin Wax

    160-1

    Vinac &

    Benzoflex

    140-1

    Hinge Coat140-1

    Boiler

    Process

    Chiller

    Air

    Compressor

    VOC

    AbatementWarehouse

    Forklift

    Truck

    VOCHeat Exhaust

    Reject (Trash)

    Heat Exhaust

    Reject (Trash)

    Recycle

    N2DIW

    Elect

    CA

    HPCHPSCA

    HPCHPS

    WET RAW MATERIALS

    LPCLPS

    Elect

    CATruck

    ElectCATruck

    ElectCA

    Truck

    Trays

    Trays

    Ink

    Wrapping Film (Rolls)VOCReject

    (Trash)

    PalletsStretch

    Wrap FilmCoding Ink

    TapeBoxes

    Cooling

    Tower

    Permit

    Plant

    City Utility

    City Utility

    City Utility

    Plant

    Plant

    10-13

    IACA

    Elect

    PCW

    PCR

    CWSCWR Elect

    PermitElect

    Coating No.1

    VentHPC

    LPCHPS

    LPS

    CWGasElect

    SUPPORT REQUIREMENTS for

    PROCESS STEPS