48325-001: 150 mw burgos wind farm project...initial environmental examination the initial...
TRANSCRIPT
![Page 1: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/1.jpg)
Initial Environmental Examination
The initial environmental examination is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “Terms of Use” section of this website. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Project Number: 48325-001 July 2015
PHI: 150 MW Burgos Wind Farm Project Transmission Line and Jetty
Section 13 – Socio-Economic Assessment Section 14 – Landscape and Visual Impact Assessment Section 15 – Risk Assessment Section 16 – Environmental and Social Management Plan (Part 6 of 14)
Prepared by EDC Burgos Wind Power Corporation for EDC Burgos Wind Power Corporation and the Asian Development Bank.
![Page 2: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/2.jpg)
![Page 3: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/3.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | i
Table of contents
1. Introduction..................................................................................................................................... 1
2. Project Description ......................................................................................................................... 1
3. Assessment Methodology .............................................................................................................. 1
4. Land Use Assessment ................................................................................................................... 1
5. Noise and Vibration Assessment ................................................................................................... 1
6. Biodiversity and Conservation ....................................................................................................... 1
7. Marine Ecology and Seawater Quality ........................................................................................... 1
8. Water and Drainage Assessment .................................................................................................. 1
9. Soil and Groundwater Contamination Assessment ....................................................................... 1
10. Air Quality Assessment .................................................................................................................. 1
11. Heritage and Cultural Assessment ................................................................................................ 1
12. Traffic, Access and Safety Assessment ......................................................................................... 1
13. Socio-Economic Assessment .................................................................................................. 13-1
13.1 Introduction .................................................................................................................... 13-1
13.2 Assessment Methodology .............................................................................................. 13-1
13.3 Stakeholder Engagement .............................................................................................. 13-1
13.4 Existing Conditions ........................................................................................................ 13-6
13.5 Performance of EBWPC during Construction Phase .................................................. 13-18
13.6 Operation Phase Assessment ..................................................................................... 13-21
13.7 Conclusions ................................................................................................................. 13-28
13.8 References ................................................................................................................... 13-29
Table index
Table 13-1 Stakeholder engagement activities conducted by EBWPC ........................................... 13-2
Table 13-2 Major Issues and Concerns raised during the Stakeholder Engagement
Activities ......................................................................................................................... 13-2
Table 13-3 Host barangays .............................................................................................................. 13-6
Table 13-4 Population of Burgos...................................................................................................... 13-7
Table 13-5 Population and Land Area of Pasuquin ......................................................................... 13-9
Table 13-6 Population and Land Area in Bacarra .......................................................................... 13-11
Table 13-7 Population and Land Area of Laoag City ..................................................................... 13-13
Table 13-8 Number of lots affected by the transmission towers .................................................... 13-15
Table 13-9 Actual land use of areas where the transmission towers were built ............................ 13-15
Table 13-10 Percentage of affected land area of the 189 landowners ............................................ 13-16
![Page 4: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/4.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | ii
Table 13-11 Percentage of affected land of the 49 landowners ...................................................... 13-16
Table 13-12 Lots affected by the Transmission Line Project ........................................................... 13-18
Table 13-13 Nature of land rights ..................................................................................................... 13-18
Table 13-14 Safety performance of EBWPC during Construction Phase........................................ 13-19
Table 13-15 Origin of EBWPC Employees during the Construction of the Transmission Line
and Jetty Projects ........................................................................................................ 13-20
Table 13-16 Classification of EBWPC Employees during the Construction of Transmission
Line and Jetty Projects................................................................................................. 13-20
Table 13-17 Height clearance permit secured for the Transmission Towers .................................. 13-22
Table 13-18 Typical US Magnetic Field Levels associated with Transmission Lines ...................... 13-26
Table 13-19 List of Towers Built near Structures ............................................................................. 13-26
Table 13-20 Key impacts and proposed mitigation/enhancement measures .................................. 13-28
Figure index
Figure 13-1 Location of Laoag International Airport relative to the Transmission Line ................... 13-24
Figure 13-2 Electromagnetic Spectrum ........................................................................................... 13-25
![Page 5: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/5.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 13-1
13. Socio-Economic Assessment
13.1 Introduction
The social, economic and health impacts of the Transmission Line and Jetty Projects during the
operation and maintenance phase are discussed in this section. Performance of the projects
during the construction phase is also discussed in this section.
13.2 Assessment Methodology
Methodology used to assess the socio-economic impact of the Transmission Line and Jetty
Projects includes review of secondary information gathered from the different government
agencies, as well as client-provided data.
13.2.1 Desktop Study
An initial assessment of the following documents was subjected to desktop analysis:
� Ecological Profile of Laoag City
� Municipal Health Profile of Burgos
� Municipal Ecological Profile of Burgos
� Municipal Ecological Profile of Pasuquin
� Municipal Profile of Bacarra
� Census of Population and Housing
� Minutes of meeting of stakeholder engagement activities undertaken by EBWPC in 2010
� Report on household survey conducted by EBWPC in September 2014
� Performance report of EBWPC during the construction of transmission line and jetty
projects
13.2.2 Household survey
A household survey was undertaken by EBWPC in February 2015 to determine the socio-
economic condition of the 49 lot owners whose land affected by the Transmission Tower project
is about 10 to 60 percent of their total land area.
13.2.3 Ident ificat ion and Evaluat ion of Impacts and Opt ions for Mit igat ion
Based on the existing baseline socio-economic condition within the identified project affected
areas and review of client-supplied information, potential positive and negative impacts as well
as issues and concerns arising from the operation and maintenance of the project were
identified. Options on preventive and mitigation measures were also formulated to control the
negative effects of the project while enhancement measures were enumerated to improve the
positive impacts.
13.3 Stakeholder Engagement
In 2010, EBWPC conducted various stakeholder engagement activities to inform the host
communities about the transmission line project. Issues and concerns of the community were
also discussed during the consultation activities.
Provided in Table 13-1 are the stakeholder consultation activities conducted by EBWPC while
the summary of issues and concerns raised is presented in Table 13-2. Majority of the
![Page 6: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/6.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 13-2
concerns raised by the community were related to the benefits that will be provided by the
project, health and safety issues, as well as timeframe of project implementation. The issues
and concerns raised during the consultation activities were discussed and addressed in
succeeding sections.
Table 13-1 Stakeholder engagement act ivit ies conducted by EBWPC
Date Venue Title Participants
20 July 2010
Bacarra Municipal Hall
Courtesy Visit to Bacarra Municipal Officials on the 42 km 115 kV Transmission Line Project
Municipal Mayor of Bacarra
21 July 2010
Burgos Central Elementary School
Consultation with Barangay Officials of Burgos, Ilocos Norte on the 42 km 115 kV Transmission Line Project
Burgos Municipal LGU and Barangays Ablan, Bayog, Bobon and Paayas
22 July 2010
Pasuquin Sangguniang Bayan Session Hall
Consultation with Barangay Officials of Pasuquin, Ilocos Norte on the 42 km 115 kV Transmission Line Project
29 Barangay Officials from the impact barangays of Pasuquin, Ilocos Norte
25 July 2010
Barit Elementary School
Consultation Meeting with residents of Barangay Barit on the 42 km 115 kV Transmission Line Project
90 Residents of Barangay Barit, Laoag City
25 July 2010
Vira Elementary School
Consultation Meeting with residents of Barangay Vira on the 42 km 115 kV Transmission Line Project
70 Residents of Barangay Vira, Laoag City
21 July 2010
Laoag City Hall Presentation before the Laoag City Council on the 42 km 115 kV Transmission Line Project
Laoag City Council
16 January 2012
Ilocos Norte Provincial Hall
Consultation with the members of the Ilocos Norte Provincial Council regarding the entire project (e.g. wind farm, substation, transmission line, and jetty)
Ilocos Norte Provincial Council
Table 13-2 Major Issues and Concerns raised during the Stakeholder
Engagement Act ivit ies
Issues and concerns Raised by Stakeholder/Sector
EBWPC Response
Will Bacarra benefit from the project?
Bacarra Municipal Mayor
Energy projects are mandated by law to extend financial benefits to host communities. There is a royalty tax prescribed by the Renewable Energy Law and the Local Government Code, which mandates power producers to allocate 1% of the gross income from the power facility; 40% of which will be given to host LGUs, which will be shared based on the scheme provided in the law.
Preferential employment will be provided to residents where the facilities are to be located
The cost of electricity in Ilocos Norte is still high despite the presence of windmills. Is there a way to reduce the price?
Bacarra Municipal Mayor
Right now, electric power that comes from clean energy sources is expensive. But the cost can be reduced through the so-called Feed-in-Tariff (FIT). This mechanism allows renewable energy (RE) power facilities to
![Page 7: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/7.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 13-3
Issues and concerns Raised by Stakeholder/Sector
EBWPC Response
get viable revenue from operating the RE plants for a certain number of years. The price of power from the RE plant will be diffused as all consumers connected to the grid will share this cost. If we can get a good FiT rate from ERC, we can charge a cheaper price for the electricity that will come from Burgos Wind Power Plan (BWPP).
How about the royalty payment to local government by virtue of local autonomy?
Bacarra Municipal Mayor
As a non-host LGU of the power plant, your royalty and ER 1-94 benefit will come from the share of the Province of Ilocos Norte. You can petition the provincial government for your equitable share.
We’ve been hearing about the project for almost 10 years. We hope that it will materialize because we want our municipality to develop.
Burgos Vice Mayor We apologise for the delay of the project. If we pursued the project earlier, the price of electricity would be too high. At least today we have the Renewable Energy or RE Law to be able to provide cheaper and cleaner source of energy.
Implementation of the project will depend on the result of negotiation with the ERC regarding Feed-in-Tariff (FIT). This negotiation is important since to determine the price of the electricity that comes from the wind farm.
If the negotiation went well, we hope to receive Notice to Proceed this September 2010 so we could start project construction.
What will be the basis of compensation for the landowners?
Barangay Chairman of Bobon and Ablan, Burgos
Land compensation or lease agreement will be based on fair market value.
What benefit can we get from the transmission line project?
Barangay Chairman of Paayas, Burgos
We will make sure that contractors will prioritize local workers.
The municipality and its impact barangays will benefit from the royalty tax prescribed by the Renewable Energy Law and the Local Government Code, which mandates power producers to allocate 1% of the gross income from the power facility; 40% of which will be given to host LGUs, which will be shared based on the scheme provided in the law.
What will EBWPC do to the properties that will be affected by the transmission line route?
Barangay Chairman of San Isidro, Pasuquin
EBWPC can either rent or purchase the land that will be traversed by the transmission line. The compensation will be based on the fair market value of land in Pasuquin.
Expropriation can also be implemented, if necessary.
In any case, just compensation of properties will be provided by EBWPC.
What will EBWPC do to the affected trees and/or plants?
Barangay Chairman of San Isidro, Pasuquin
Crop compensation will be provided to the owners of the trees/plants/crops that will be affected by the project.
![Page 8: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/8.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 13-4
Issues and concerns Raised by Stakeholder/Sector
EBWPC Response
Have you talked to the landowners?
Barangay Chairman of Sulbec, Pasuquin
Yes, negotiation with the landowners is being undertaken by EBWPC Land Negotiation/Right-of-Way Team
What about safety measures? Are transmission lines/towers safe?
Barangay Chairman of Sulongan, Pasuquin
Yes, transmission towers are safe. EBWPC will undergo all the necessary steps and follow safety requirements to make sure that our transmission towers are safe. One of the measures that will be implemented is to erect the towers away from the residential areas.
How can we benefit from the proposed project?
Barangay Chairman of San Isidro, Pasuquin
EBWPC can provide employment to local workers during construction phase. It is EBWPC’s mandate to prioritize locals in employment opportunities. This will eventually provide benefit to the barangay thru ‘multiplier effect’.
There is a royalty tax prescribed by the Renewable Energy Law and the Local Government Code, which mandates power producers to allocate 1% of the gross income from the power facility; 40% of which will be given to host LGUs, which will be shared based on the scheme provided in the law
Are you going to compensate our land if it will be traversed by the project?
Barangay Resident of Barit, Laoag City
Yes. This is mandated in the Philippine Constitution, Bill of Rights Article 3. EBWPC’s Land Negotiation Team are currently negotiating with the land owners regarding this issue
Is there a possibility to reduce price of electricity?
Barangay Resident of Barit, Laoag City
This is possible through the ‘feed-in-tariff’ program.
What will you do to the houses that will be affected by the transmission line?
Barangay Resident of Barit, Laoag City
As much as possible, transmission line will not traverse residential areas to minimize impact. But if this is not possible, just compensation will be provided.
Is it possible for EBWPC to provide 50% discount on electric bill to the residents of Barangay Barit?
Barangay Chairman of Barit, Laoag City
No. EBWPC cannot do anything on the price of electricity because the government sets the price of electricity.
When will you start the project?
Barangay Resident, Barit, Laoag City
We will start the project as soon as we get the FiT rate.
If the transmission tower is located near houses what will happen in case there is accident?
Barangay Chairman of Vira, Laoag City
EBWPC will make sure that accident (i.e. tower collapse) will not happen; we will comply with national and international standard in terms of transmission tower integrity.
We are concerned on high voltage and lighting, how will EBWPC address this issue?
Barangay Resident of Vira, Laoag City
“Lightning arrestor” devices are commonly installed in transmission towers/lines to prevent such events.
What benefit can we expect from the project in terms of employment?
Barangay Resident of Vira, Laoag City
We will advise contractor to prioritize hiring of workers from the host barangay during construction phase.
When will ‘feed-in-tariff’ be approved?
Barangay Secretary of Vira, Laoag City
According to ERC, it will be issued this August 2010.
![Page 9: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/9.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 13-5
Issues and concerns Raised by Stakeholder/Sector
EBWPC Response
Is there competition with North Wind? If there is, can the competition reduce the electricity rate?
Barangay Secretary of Vira, Laoag City
There will be no competition; our project will only produce additional capacity to the grid.
The transmission tower will cross structures or plants; what will EBWPC do with these?
Barangay Resident of Vira, Laoag City
We will provide just compensation to the damaged crops or structures that will be affected by the project.
What is the distance of transmission tower easement/right-of-way?
Barangay Resident of Vira, Laoag City
We will observe 30 m easement.
If this will be pushed thru, what benefits will the constituents get?
Laoag City Council Member
Indirect benefit is that Ilocos Norte will become the wind farm capital of the Philippines; local tourism will be enhanced given Laoag’s strategic position as entry and exit point.
May we know how the 1% of the gross receipts is computed?
Laoag City Council Member
Yes, we will provide the figures.
Other companies have applied for the same permit. May we know if there will be a separate transmission line for every company that will establish wind farm? Are you going to have your own?
Laoag City Council Member
We are going to have our own; there can be an arrangement where other companies may use the TL by paying rent. We will conduct consultation exercises in Barangays Barit and Vira.
I have a relative who has not yet received rental/payment of land; how will you address this issue?
Laoag City Council Member
We have Land Negotiation Team who are in-charge of the negotiations with the land owners.
Will this project be beneficial to the people of Laoag City? They said that it will reduce cost of electricity; can we get assurance from you?
Laoag City Council Member
Feed-in-Tariff will be provided through the Renewable Energy law. The construction of the transmission line is necessary to connect the wind project to the national grid.
What kind of environmental compliance certificate (ECC) was secured for the project?
Laoag City Council Member
We conducted the usual environmental impact assessment (EIA) study and social acceptability processes, which were reviewed by a technical review committee of the DENR. As part of the process, an ECC was secured for the Wind Farm Project several years ago; recently, it was also declared by the DENR that the TL and Jetty projects are not covered by the Philippine EIS System hence Certificate of Non-Coverage (CNC will be issued).
I heard that this 1% of gross proceeds will be shared by the province, city and barangay?
Laoag City Council Member
The distribution is 20-45-35; the share of the LGUs outside of the host municipality will come from the province’s share.
May I know the result of consultation with Barangays Vira and Barit? I suggest you should also conduct a general assembly for the barangays
Association of Barangay Council (ABC) President of Laoag City
There were two consultations conducted—the first is on social acceptability; this time, the purpose is to request for endorsement.
![Page 10: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/10.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 13-6
Issues and concerns Raised by Stakeholder/Sector
EBWPC Response
so that the sentiments of the barangay residents will also be covered.
Did you also consult the young people of Barit?
Association of Barangay Council (ABC) President of Laoag City
The social acceptance was conducted in compliance with the ECC, but the purpose of the presentation now is for endorsement.
Can you provide us copies of the consultation activities as well as information/references for the project to make sure that the project is safe and the residents can benefit from it?
Association of Barangay Council (ABC) President of Laoag City
We will submit to you the project description as well as benefits.
13.4 Exist ing Condit ions
The 115 kV Transmission Line traversed 29 barangays in three municipalities and one city of
the Province of Ilocos Norte. Listed in Table 13-3 are the host barangays and municipalities
that are affected by the proposed Transmission Line. On the other hand, the Jetty Project is
located in Barangay Ablan, Municipality of Burgos, Ilocos Norte.
The socio-economic assessment of the project impact areas are discussed in the succeeding
sections.
Table 13-3 Host barangays
Region Province City/Municipality Barangay Barangay
Region 1 – Ilocos Region
Ilocos Norte Burgos Nagsurot
Poblacion
Saoit
Ablan
Bayog
Bobon
Paayas
Pasuquin Caruan
Carusipan
Davila
Dilavo
Estancia
Nagsanga
Ngabangab
Poblacion 2
Salpad
Batuli (San Isidro)
Sulbec
Sulongan
Susugaen
Tabungao
Bacarra Cabaruan
Cabusligan
Corocor
Pasngal
Pungto
Sangil
Laoag City Barit Vira
13.4.1 Descript ion of Socio-Economic Condit ion in the Municipality of
Burgos
Burgos is a 4th class municipality with a total land area of 12,928 hectares (ha) and a total
population of 9,431 with 2,500 households (Burgos Municipal Profile, 2010). The municipality,
which is about 48 km from Laoag City, is located at the northwestern part of Ilocos Norte.
![Page 11: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/11.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 13-7
Population
Seven of the 11 barangays in Burgos are considered as host barangays (Table 13-4) with an
aggregate population of 6,849. Among the seven host barangays, Poblacion has the highest
number of population followed by Bobon and Ablan.
Based on the Ecological Profile of the Municipality (2010), Burgos has a young age structure
with 36.76 percent of its population with ages less than 15 years old and 21.23 percent are
between the ages 16–25. More than a third of the population (36.67%) belongs to working
group (26–65 years old) while the remaining 5.34 percent are senior citizens (65 and above).
There is no data on age distribution in the host barangays.
Table 13-4 Populat ion of Burgos
Barangay Population Barangay Population
Poblacion* 1,464 Nagsurot* 817
Ablan* 1,272 Paayas* 669
Agaga 570 Pagali 710
Bayog* 685 Saoit* 611
Bobon* 1,331 Tanap 595
Buduan 707 Total 9,431
Note: * host barangays Source: Municipal Ecological Profile of Burgos, 2010
Health and Sanitation
Based on the Ecological Profile (2010), Burgos has one Municipal Health Center and
11 Barangay Health Stations (BHS). The Municipal Health Center is manned by a DOH
representative, one doctor, one nurse, one dentist, four midwives, one sanitary inspector and
one medical technologist. On the other hand, the BHS is managed by 73 Barangay Health
Workers (BHW) and 24 Barangay Nutrition Scholars (BNS).
In 2012, there were 45 mortality cases in the municipality where cancer (all types) and
pneumonia are the leading causes of death. This is followed by cardio-pulmonary arrest and
chronic hypertensive vascular disease. On the other hand, the leading cause of morbidity is
respiratory tract infection (2,407 or 62.85%), followed by tonsillitis (260 or 6.79%) and musculo-
skeletal syndrome (231 or 6.03%) (Municipal Health Office 2012).
Education
The municipality has 10 public elementary schools, one private preparatory school and a public
secondary school located in Poblacion. The teacher to pupil/student ratio and classroom to
pupil/student ratio in the municipality are within the national standard provided by the
Department of Education (DepEd), which is 1:40 and 1:45, respectively.
Peace and Order
The Philippine National Police (PNP), which is composed of 21 personnel, administers the
peace and order situation in Burgos. The police-population ratio in the municipality is 1:449,
which is higher than the standard ratio set by the agency. Police presence is concentrated in
the town center while barangay tanod are dispersed in the rural barangays. Barangay tanods
are responsible for maintaining peace and order at the barangay level.
![Page 12: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/12.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 13-8
Economy
Agriculture and fisheries dominate the local economy of Burgos followed by trading, services
and transportation sector. The rice mills, furniture shops, bakeries and construction sectors
have the smallest contribution to the economy. The fishery subsector is also an important
economic activity in the municipality due to several fishing grounds from inland to near shore
and offshore.
Employment
Burgos has a total labor force of 5,460 or 57.9 percent of its population. Majority of the labor
force in the municipality are engaged in agriculture and fisheries, followed by employment in
government and private institutions, while the least number of workers are engaged in business.
Domestic Water Supply
About 85.9 percent of the households in the municipality have access to improved or safe water
supply; 59.5 percent of which have Level 1 type of water source, 3.24 percent utilises Level II,
while the remaining 37.24 percent has Level III water source.
Electric Power Supply
The Ilocos Norte Electric Cooperative (INEC) provides the electricity requirements of the
municipality. Based on the Ecological Profile (2010), all the 11 barangays of Burgos are already
served by INEC.
Irrigation System
The irrigation system in the municipality includes the Communal Irrigation System (CIS) and
288 individually installed shallow tube wells with water pump. The CIS supplies an aggregate
service area of 1,556 ha of croplands in all the barangays of the municipality. The most
widespread use of shallow tube wells can be found in Barangays Nagsurot, Poblacion, tanap
and Buduan.
13.4.2 Descript ion of Socio-Economic Condit ion in the Municipality of
Pasuquin
Pasuquin is a fourth class municipality in the Province of Ilocos Norte with a total land area of
18,940 ha. It is bounded on the north by the Municipality of Burgos, on the east by the
Cordillera Mountains, on the west by the West Philippine Sea and on the south by the
Municipality of Bacarra.
Population
Based on the data provided by the Philippine Statistics Office (2010) the Municipality of
Pasuquin has a total population of 27,952 (Table 13-5), which gives a population density of 1.47
or 14 persons per 10 ha.
The four urban barangays, namely Poblacion 1, Poblacion 2, Poblacion 3 and Poblacion 4 has
an aggregate population of 5,453 or 19.82 percent of the total population of the municipality.
On the other hand, about 80 percent or 22,499 of the population in the municipality are found in
rural areas.
![Page 13: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/13.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 13-9
Table 13-5 Populat ion and Land Area of Pasuquin
Barangay Population Land area (ha)
Barangay Population Land area (ha)
Batuli (San Isidro)* 391 258.90 Poblacion 2* 1904 269.63
Binsang 841 18,544.35 Poblacion 3 1016 24.50
Nalvo 534 130.47 Poblacion 4 1411 82.00
Caruan* 1,214 281.21 Pragata 509 143.41
Carusikis 790 762.50 Puyupuyan 831 284.32
Carusipan* 461 540.53 Sulongan* 450 393.55
Dadaeman 314 138.59 Salpad* 599 175.71
Darupidip 348 116.62 San Juan 1,442 152.80
Davila* 3,875 162.68 Sta Catalina 933 1,270.19
Dilanis 415 1,107.85 Sta Matilde 429 934.45
Dilavo* 601 338.12 Sapat 32 490.46
Estancia* 938 1,887.17 Sulbec* 775 5,86.78
Naglicuan 1390 139.82 Surong 303 389.41
Nagsanga* 1140 354.88 Susugaen* 1,296 329.29
Ngabangab* 746 126.19 Tabungao* 177 197.07
Pangil 403 84.54 Tadao 322 250.50
Poblacion 1 1122 19.51 Total 27,952 18,940
Note: * host barangays Source: Philippine Statistics Office, 2010
Health and Sanitation
Health care delivery in the municipality is adequate due to the presence of various public and
private health facilities and services. Public facilities in the municipality include one Rural
Health Unit (RHU) located in the town center and five Barangay Health Stations (BHS) situated
in catchment barangays namely Susugaen, Sta Matilde, Sta Catalina, Davila and Poblacion.
The RHU is manned by a doctor, nurse, dentist, two midwives, a population program worker, a
nutrition officer, one medical technologist and two sanitary inspectors while the BHS are
handled by 176 BHW, 46 Barangay Service Point Officer and 66 BNS.
There are also 10 private health clinics in the municipality, five of which are medical clinics,
three are dental clinics, one physical therapy clinic and one laboratory clinic.
Education
Based on the Municipal Profile (2010), Pasuquin has 63 schools, 60 are public and three are
private. Of the 63 schools, 34 are Day Care Centers, 26 are public elementary schools and
three are private institutions.
The Day Care Centers and elementary schools are distributed in the different barangays while
the secondary schools are located in the Poblacion barangays. Eight of the 14 host barangays
have elementary schools, namely San Isidro, Caruan, Davila, Dilavo, Nagsanga, Sulbec and
Tabungao.
![Page 14: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/14.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 13-10
Peace and Order
Peace and order in the municipality is maintained by the Philippine National Police (PNP), which
is composed of 18 personnel. The police-population ratio in 2009 is 1:1550 persons; this ratio is
below the standard ratio of 1:1000. The main police station is located in Barangay Poblacion 1
while a sub-station was established in Barangay Davila.
Paredes Air Station, a military base with about 28 personnel, is also present in the municipality.
The base helps control insurgency in the municipality.
Economy
Agriculture and fisheries dominates the local economy of Pasuquin. This is followed by
manufacturing, mining and quarrying of various minerals such as salt, feldspar, silica and
pebbles. The sector which has the smallest contribution to the local economy includes small-to-
medium sized rice mills, furniture shops, bakeries, salt-making and salt-refinery industries, nipa
palm industries and hollow-blocks making.
Employment
In 2009, the employment rate in the municipality is 93.46 percent, which means that only about
6.54 percent of the labor force is unemployed. Agriculture sector has the highest employment
(73.46%), followed by employment in government and private service (19.80%), fishing (4.35%)
and mining (1.30%).
Electric Power Supply
The electricity requirement of the municipality is provided on a 24-hour basis by the INEC.
Based on the latest report of INEC, all the 33 barangays in the municipality have electric supply.
Domestic Water Supply
The water requirements of the four urban barangays and six rural barangays are being provided
by the Ilocos Norte Water District (INWAD) under the Local Water Facilities Administration
(LWFA).
On the other hand, the five seaside barangays, 10 upland barangays, one military base and four
Agrarian Reform Community (ARC) barangays obtain their water requirements from 21 springs,
which were developed on a Level II status. The rest of the barangays tap underground water
through shallow and deep wells.
Irrigation System
The main source of irrigation in the municipality is the Bacarra River. The main irrigation facility
is the Zanjera Cadaclan Pasayacan CIS, which serves seven barangays in the municipality or
about 350,000 ha of rice lands. Based on the Municipal Profile (2010), the beneficiaries of the
CIS are about 1,750 farmers.
13.4.3 Descript ion of Socio-Economic Condit ion in the Municipality of
Bacarra
Bacarra is a third class municipality with a total land area or 6,550.57 ha. It is about 495 km
from Metro Manila and 15 km from Laoag City. The municipality is bounded on the north by
Pasuquin, on the east by Vintar; on the south by Laoag City; and on the west by the West
Philippine Sea.
![Page 15: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/15.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 13-11
Population
The Municipality of Bacarra has a total population of 31,757 in 2012 (Table 13-6). Barangay
Libtong has the largest population while Barangay San Gabriel has the lowest population.
Considering the land area of the municipality, Burgos has a population density of 4.85 or about
48 persons per 10 ha.
Six of the 43 barangays in the municipality are traversed by the transmission line thus
considered as host barangays. This includes Pungto, Cabusligan, Pasngal, Corocor, Cabaruan
and Sangil.
Table 13-6 Populat ion and Land Area in Bacarra
Barangay Population Land area (ha)
Barangay Population Land area (ha)
Sta. Rita 1,103 52.06 Bani 951 180.73
San Andres I 733 12.18 Paninaan 402 441.38
San Andres II 820 12.86 Macupit 637 195.31
San Simon I 628 20.23 Tubburan 826 325.60
San Simon II 385 4.42 Teppang 709 179.60
San Pedro I 380 5.02 Duripes 992 187.03
San Pedro II 404 11.18 Pungto* 553 146.40
San Agustin I 477 9.09 Cabusligan* 1,040 134.34
San Agustin II 271 7.37 Pasngal* 687 146.71
San Vicente 623 9.48 Cadaratan 1,160 162.82
Sta Filomena I 307 7.95 Calioet-Libong 756 192.93
Sta Filomena II 327 9.03 Corocor* 744 143.85
San Gabriel I 255 5.74 Cabulalaan 751 80.80
San Gabriel II 427 6.96 Cabaruan* 1,442 480.20
San Roque I 498 12.48 Pipias 986 45.76
San Roque II 393 7.54 Natba 503 110.76
Sto Cristo I 438 17.45 Ganagan 735 291.22
Sto Cristo II 460 5.13 Casilian 903 231.37
Nambaran 968 650.28 Sangil* 987 257.84
Tambidao 765 334.19 Pasiocan 1,164 238.31
Pulangi 1,080 436.96 Buyon 1,527 391.13
Libtong 1,552 348.88 Total 31,757 6550.57
Note: * host barangays Source: Municipal Planning and Development Office of Bacarra, 2012
Health and Sanitation
Health services in the municipality are provided through the Rural Health Unit (RHU) and five
BHS, which are distributed in catchment barangays. The RHU has service vehicles and two
ambulances to provide faster medical services in the municipality.
Based on the data provided by the RHU, upper respiratory tract infection (URTI) is the leading
cause of morbidity with a total of 2,523 cases followed by nasopharingitis (2,297).
Education
There are about 29 schools in the municipality, 23 of which are public elementary schools, two
are private elementary schools, three are secondary schools, and one tertiary school. The
teacher-to-pupil ratios in the elementary and secondary levels are 1:20 and 1:35, which
complies with the DepEd national standard.
![Page 16: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/16.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 13-12
Peace and Order
The Philippine National Police in Bacarra is composed of 19 personnel and one non-uniformed
personnel. This gives a police-to-population ratio of 1:671 which is below the national standard
set by PNP, which is 1:1000.
PNP facilities in the municipality includes jail room, administrative room, communication room,
two patrol jeepneys, one motorcycle with sidecar, and a motorcycle.
Economy
Majority of the labor force in the municipality derives their income from various agricultural
activities, which dominates the local economy of Bacarra. Manufacturing is the secondary
sector in the municipality; this includes small/backyard type, family or cooperative-based
industrial activities, such as metallurgy, hollow blocks making, candy and ice cream production,
wood working, garment craft, meat processing and food preservation, goldsmith and ice making.
Commerce and services is the tertiary source of income in the municipality. Commercial entities
in Burgos include groceries, sari-sari stores, pharmacies and merchandisers of agricultural
inputs.
Employment
Of the population of Bacarra, about 70.54 percent or 22,401 are part of labor force; about 58.93
percent or 13,202 of which are employed while 41.30 percent or 9,251 are unemployed.
Electric Power Supply
INEC provides the electric requirement in the entire municipality. Based on the Municipal Profile
(2012), 100 percent of the municipality is already provided with electricity and about 98.69
percent of the households are served by the cooperative.
Domestic Water Supply
Based on the Municipal Profile, the INWAD is serving about 3,708 concessioners in the
municipality. This includes Barangays Cadaratan, Cabusligan, Pungto, Cabulalaan, Buyon,
Pipias, Corocor, Pasiocan, Cabaruan and the 18 Poblacion Barangays. Of the six host
barangays, two are not served by the INWAD. This includes Pasngal and Sangil, where
households obtain water from various sources such as deep well, open dug well and springs.
Irrigation System
About 43 Zanjera Associations serving about 3,000 hectares of agricultural land and
maintaining 32 irrigation canals source water from Bacarra River.
13.4.4 Descript ion of Socio-Economic Condit ion in Laoag City
Laoag City, the capital of the Province of Ilocos Norte, is approximately 488 km from Metro
Manila and 217 km from San Fernando City, the regional capital of Ilocos Region. It is situated
at the west central part of Ilocos Norte bounded on the east by the Municipality of San Nicolas;
in the southwest by the Municipality of Paoay; on the northeast by the Municipality of Vintar; on
the northwest by the Municipality of Bacarra; and on the west by the West Philippine Sea.
Population
Laoag City has a total land area of 12,747.32 ha with a population of 104,904 in 2010 which
gives a population density of 8.22 or eight persons per ha (Table 13-7). The host barangays
traversed by the transmission line are Barit and Vira, with population of 2,117 and 1,226 and
population density of 6.59 and 4.84, respectively.
![Page 17: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/17.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 13-13
Based on the Ecological Profile of Laoag City, females outnumber male with a sex ratio of
100:94 or 100 females for every 94 males. The city has relatively young population where
around 31 percent belong to age group 0–14 years old, 63 percent are 15–64 years old and
only six percent are 65 years old and above.
Table 13-7 Populat ion and Land Area of Laoag City
Barangay Population Land area (ha)
Barangay Population Land area (ha)
Apaya 892 245.90 Nstra. Sra. De Natividad (B)
961 11.50
Araniw 810 93.24 Nstra, Sra. De Soledad
1,478 24.85
Bacsil North 905 355.19 Nstra. Sra. De Visitacion
1,193 19.25
Bacsil South 1,251 545.28 Nstra. Sra. Del Rosario
1,191 15.28
Balacad 1,387 447.25 Pila 1,761 285.45
Balatong 2,638 476.23 Raraburan 1,512 70.48
Barit* 2,117 320.79 Rioeng 1,459 296.80
Bengcag 1,817 217.40 Salet-Bulangon 2,329 451.52
Buttong 2,734 165.21 San Agustin 1,451 10.96
Caaoacan 1,329 49.65 San Andres 1,170 8.03
Cabungaan North 1,719 164.10 San Bernabe (Bernardo)
1,656 100.65
Cabungaan South 1,226 118.72 San Francisco 671 15.98
Calayab 1,889 423.14 San Guillermo 1,143 10.34
Camangaan 920 146.90 San Isidro 1,603 27.06
Casili 862 100.68 San Jacinto 1,040 14.80
Cataban 729 171.37 San Jose 993 11.49
Cavit 1,051 70.96 San Lorenzo 4,391 107.03
Darayday 741 133.05 San Marcelino 1,067 21.29
Dibua South 756 222.82 San Mateo 629 50.40
Dibua North 1,011 166.96 San Matias 2,295 100.31
Gabu Norte East 1,177 10.81 San Miguel 939 24.15
Gabu Norte West 773 101.82 San Pedro 1,261 32.78
Gabu Sur 1,692 110.95 San Pedro 1,716 28.29
La Paz East 1,521 6.12 San Quirino 834 774.96
La Paz West 1,031 117.51 San Vicente 1,025 8.97
La Paz East 1,321 31.53 Santa Angela 783 8.08
La Paz Proper 1,030 39.67 Santa Balbina 1,322 14.46
La Paz Proper 841 10.71 Santa Cayetana 1,094 10.61
Lagui-Sail 2,199 614.67 Santa Joaquina 2,367 74.07
Lataag 848 194.16 Santa Marcela 1,101 23.82
Madiladig 1,489 375.41 Santa Maria 1,260 191.77
Mangato East 917 110.39 Santa Rosa 775 137.57
Mangato West 1,091 101.40 Santo Tomas (A) 1,389 5.58
Nangalisan East 1,509 65.15 Santo Tomas (B) 1,326 103.45
Nangalisan West 706 33.56 Suyo 761 33.07
Nalbo 2,224 100.94 Talingaan 1,485 633.53
Navotas North 808 82.39 Tangid 991 133.18
Navotas South 936 180.35 Vira* 1,226 253.00
![Page 18: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/18.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 13-14
Barangay Population Land area (ha)
Barangay Population Land area (ha)
Nstra. Sra. De Consolacion
979 8.279 Zamboanga 1,259 161.59
Nstra. Sra. De Natividad (A)
1,085 8.40 TOTAL 104,904 12,747.35
Note: * host barangays Source: Laoag City Ecological Profile; Philippine Statistics Office
Health and Sanitation
The health care services in Laoag City is considered adequate due to the presence of several
public and private health facilities and services, which include the Level II-100 bed capacity
Laoag City General Hospital that offers medical, pediatrics, laboratory, x-ray, ultrasound,
dialysis and minor surgery. Another public hospital is the Governor Roque Ablan Sr. Memorial
Hospital (GEAMH) while there are 10 private clinics and hospitals.
The City Health Office employ a total of 419 medical personnel and staff, which can be
considered adequate based on the national standard set by the Department of Health (DOH).
The leading cause of morbidity are diseases of the heart (74) followed by diarrhea (63) while
coronary artery disease (99) and pneumonia (83) are the leading cause of mortality.
Education
Laoag City is the educational center of Ilocos Norte with 33 public elementary schools,
11 private elementary schools, 22 private and 10 public pre-schools, eight private high schools,
five public high schools, three public and five private college and universities. Non-formal
education (NFE) such as literary controlling scheme, poverty alleviation through development
adopt-a-school, barangay operation for livelihood development, community learning approach,
and computer education, are also offered by the Laoag City Schools Division.
The teacher-student and classroom-student ratio for public and private elementary schools are
within the standard provided by the Department of Education (DepEd). However, there is lack
of educational facilities in public high schools with a ratio of 1:90 classroom-student ratio.
Peace and Order
Peace and order in the city is carried out by the Philippine National Police (PNP) in coordination
with the Department of Public Safety (DPS) and the Bureau of Fire Protection. The Police
Station in the city is manned by 70 personnel while the DPS has 16 well trained public safety
members, 15 paramedics, and 30 traffic aides. The police-population ratio is 1:1502, which is
below the national standard.
Economy
Agriculture, fishery, livestock and forestry dominate the local economy of Laoag City. This is
followed by the secondary sector composed of mining and quarrying, manufacturing,
construction and energy generation/distribution while the tertiary sector consists of service
activities such as trade and commerce, real estate, finance, personal and community services,
and transportation and communication.
Employment
Based on the Ecological Profile of the city, the employment rate of Laoag City is 94.23 percent
while labor participation rate is 53.42 percent. Majority (94%) of the labor force are involved in
tertiary sector while the remaining six percent are engaged in agriculture and manufacturing.
![Page 19: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/19.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 13-15
Electric Power Supply
Based on the latest data, all the barangays of Laoag City and 100 percent of the households in
the city are served by the Ilocos Norte Electric Cooperative (INEC).
Domestic Water Supply
The Ilocos Norte Water District (INWAD) supplies domestic water to about 154,516 consumers
in the city. INWAD is under the supervision of the Local Water Utilities Administration.
Irrigation System
The Laoag-Vintar River Irrigation System (Laoag-Vintar RIS) maintained and operated by the
National Irrigation Administration (NIA) Provincial Irrigation Office service an approximate area
of about 2,860 ha of agricultural lands within Laoag City and the Municipalities of Vintar,
Bacarra and Sarrat. The Laoag-Vintar RIS also serves as flood control facility.
13.4.5 Profile of Landow ners
The transmission line project affects about 1,912 lots in 29 barangays. Of the 1,912 lots, the
148 transmission towers were built in 189 lots while the remaining 1723 lots were considered as
sailover lots. As presented in Table 13-8, 182 of the 189 lots are privately owned, three are
public lands and covered by the Forest Land Use Agreement (FLAg), two are owned by
educational institutions (i.e. Davila National High School and Ilocos Norte Agricultural School)
and two lots are under the jurisdiction of the National Power Corporation (NPC).
The actual land use of the 189 lots affected by the transmission tower is presented in Table
13-9. Majority (72.49%) are used for agricultural purposes where the land is cultivated for rice,
onion and garlic. This is followed by forest areas (8.99%). The significance of impact in terms
of transmission tower footprint against the total land area possessed by each lot owner is
presented in Table 13-10. The impact of transmission tower footprint to majority (140) of the lot
owners is less than 10 percent of the total land area they possess while the remaining 49 are
landowners whose affected land ranges from 10 to 60 percent (Table 13-10).
Table 13-8 Number of lots affected by the transmission tow ers
Registered owner Number %
Private land 182 96.30
Public land covered by FLAg 3 1.59
Educational Institution (DNHS, INAC) 2 1.06
National Power Corporation (NPC) 2 1.06
Total 189 100.00
Table 13-9 Actual land use of areas w here the transmission tow ers w ere
built
Actual land use Number %
Agriculture/ Agricultural / Cultivated (use for planting rice, garlic, onion)
137 72.49
Agricultural/ Mountain / Stony 2 1.06
Firewood/ firewood trees/flat/orchard 9 5.29
FLAg 3 1.59
Forest 17 8.99
NGCP 2 1.06
![Page 20: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/20.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 13-16
Actual land use Number %
Pasture land 4 2.12
Riverbank 1 0.53
Stony / forest / firewood trees 12 6.35
Uncultivated land 1 0.53
Total 189 100.00
Table 13-10 Percentage of a ffected land area of the 189 landow ners
Significance of impact Number %lots
0–9 percent 140 74.07
10–49 percent 48 25.40
50–60 percent 1 0.53
Total 189 100.00
Profile of 49 landowners
An impact analysis on landowners was undertaken by EBWPC based on transmission tower
footprint. As a result, a household survey was undertaken in February 2015 to determine the
socio-economic condition of the 49 lot owners (Table 13-11). Of the 49 identified lot owners
with 10 to 60 percent land affected by the transmission towers, 43 or 87 percent participated in
the survey. Most of the respondents came from Bacarra (49%) and Pasuquin (44%). There
were only three respondents from Laoag City and one from Burgos. Only 11 or 26 percent of
those surveyed were the lot owners themselves. In the absence of the lot owners, their
immediate families (e.g. spouse, parents, siblings, and children), who comprised 15 or 34% of
the respondents, participated in the survey. Other relatives (e.g. uncle/auntie, cousin, in-laws)
who were present during the conduct of the survey were also interviewed (14%).
Table 13-11 Percentage of affected land of the 49 landow ners
Affected Area No. of Lot Owners
%
10-15 percent 23 46.94
16-20 percent 14 28.57
21-25 percent 5 10.20
29-37 percent 5 10.20
44 percent 1 2.04
60 percent 1 2.04
Total 49 100.00
Profile of Lot Owners
Respondents were mostly male (58%) and belong to the age-group 51–75 years old (62%).
Eleven or 26 percent are middle-aged (31–50 years old). Four were elderly (76 years old up).
Majority (63%) are heads of their respective families.
Roman Catholic is the dominant religious affiliation (67%) of the respondents while the rest
belong to different religious groups, e.g. Iglesia ni Cristo (4.6%), Aglipayan (16%), Born Again
Christian (4%), and Pentecost (7%). Most of the respondents have are college graduates (38%)
while 11 percent have reached college level. The rest are high school graduates (12%) and
![Page 21: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/21.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 13-17
elementary graduates (7%). About seven percent reached high school level and 14 percent
reached elementary school level.
About 90 percent own their houses which most (84%) of them inherited. Most (72%) of the
houses have one floor with 2 rooms at least (40%), have concrete floors (49%), concrete walls
(78%) and galvanized iron roofs (97%). Appliances commonly found in each house are electric
fan (90%), television (86%), radio (83%), mobile phones (81%), refrigerator (79%), and washing
machine (46%). More than half (58%) own motorcycles while 28 percent own a car.
Socio-Economic
Farming is the main occupation of the 47 percent of the respondents, followed by housekeeping
(14%). Others are employed (8%), or have their own business (8%) while others are working as
teachers (5%), or work as technician/electrician (4.5%). Some are already retired and/or
pensioners (10%). However, only 23% of them disclosed their monthly income ranging from
PHP5,000 (9%), PHP10,000 (2%), PHP20,000 (2%) and more than PHP20,000 (9%).
Respondents are characterized as small land-owners whose farm size is less than 2500 m2 and
93 percent of them claimed that EBWPC’s lease covered almost their entire farm. Rotational
farming is practiced by the respondents where palay is the main crop planted (65%), followed by
corn (39%), garlic (34%) and onion (2%).
Rehabilitation of tower lots was the main concern of 30 percent of the respondents after the
towers were constructed while 25 percent stated that they did not encounter any problem after
the construction of towers. One respondent (2%) claimed to have experienced low production
and another two percent wanted additional payment. However, most of them (34%) chose not
to answer if they encountered any problem after the completion of tower construction.
Many respondents did not see any pressing community problems but some thought that
unemployment, peace and order, environmental degradation, risk from natural disasters, waste
management and low production/income are critical issues. Many of the respondents, however,
viewed these issues as not significant.
Disaster Preparedness
Disasters experienced by most respondents in the past are typhoon (36%) and flash flood
(21%) which fortunately did not cause major damage to their households. About 73 percent of
the families interviewed believe that they are at risk of typhoon (26%), fire (25%) and
earthquake (25%).
Benefits from the Wind Project
Of the 43 respondents, only seven (16%) thought that the Burgos Wind Project/Transmission
Line Project will benefit them by providing a source of electricity or some employment or
livelihood. On the other hand, 37 (86%) of the respondents believe that the project will not bring
any significant benefit. About 81 percent of them, however, did not elaborate their response.
Some (8%) claimed that they want additional payment and that tower lots have to be restored
(5%). One claimed that he did not receive any compensation as a tenant while another believes
that the close distance between the transmission line and houses could pose a problem in the
future.
![Page 22: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/22.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 13-18
13.5 Performance of EBWPC during Construct ion Phase
Displacement of Settlers
The total number of lots traversed by the transmission line is 1912, three of which are public
lands and the remaining 1909 are privately-owned (Table 13-12). The nature of land rights of
the 1909 privately-owned lots is presented in Table 13-13.
Table 13-12 Lots affected by the Transmission Line Project
Type of land Lots Hectares
Public land 3 22.37
Private land 1909 98.56
Total 1912 120.93
Source: Social Safeguard Compliance Audit Report, EBWPC 2014
Table 13-13 Nature of land rights
Nature of land rights Lots Hectares
Forest Land Use Agreement (FLAg) 3 22.37
Contract Easement of Right of Way (CERW) 1014 43.88
Expropriation 562 37.49
Authorizations received from landowners 333 17.19
Total 1912 120.93
Source: Social Safeguard Compliance Audit Report, EBWPC 2014
Displacement of livelihood (i.e. agricultural crops and trees) is the major impact of the
transmission line construction. To mitigate this impact, EBWPC provided crop compensation to
the landowners using the fair market value. Compensation provided during the construction
phase include disturbance of land used as temporary access area, dumping area, or location of
transmission tower and other disturbances such as stringing works. Aside from provision of
disturbance fee or rental for damaged or lost trees or crops, EBWPC, through its contractor,
were also responsible in rebuilding of dike, restoration and rehabilitation activities.
For lands wherein permanent structures were built (e.g. transmission towers and jetty) as well
as sailover areas and right-of-way corridors, lands were legally acquired through Contract of
Easement of Right of Way signed by the owner and EBWPC.
Compensation of land and development activities (e.g. crops, trees, structures) to the
landowners whose affected land is less than 10 percent of the total land area were already paid.
For the 49 landowners whose affected land is more than 10 percent of their total property, on
the other hand, a Livelihood Restoration Plan (LRP) will be developed by EBWPC to address
the impact on their agricultural activities.
Occupational Health and Safety
Safety performance of the Transmission Line and Jetty Projects during construction phase is
summarised in Table 13-14. Safety initiatives implemented by EBWPC during construction to
prevent any incident and/or accident include the following:
� EHS Communication. This includes regular toolbox meeting, project progress meeting,
safety walkthrough, safety induction, safety stand downs, and others.
� EHS Awareness and Promotion. This includes installation of safety signs and posters as
well as updates on safety activities and notifications in EHS Notice Board
![Page 23: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/23.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 13-19
� Emergency Management
� Contractor Safety Management
� Risk Management
� Transport Safety
� Environmental Management
Table 13-14 Safety performance of EBWPC during Construct ion Phase
Incidents Transmission Line Project Jetty Project
Safety induction 397 no available data
Safety passport training 455 no available data
Lost time incident (LTI) 3 no available data
Safety man hours without LTI 760,760 no available data
Near miss 1 no available data
Property damage 1 no available data
Pilferage 1 no available data
Generation of Local Benefits from the Project
During the construction phase, various projects were implemented by EBWPC based on the
Social Development Plan (SDP) that was formulated in partnership with the host communities.
The SDP focused on five key areas including livelihood, health and sanitation, education,
environment, and culture. Enumerated below and detailed in Section 16 (ESMM) are the
projects implemented by EBWPC to provide benefits to the local residents of the impact areas.
In terms of health and sanitation, the following activities were implemented:
� Installation of toilet and hand-washing facilities
� Conduct of medical and dental mission
� Feeding program
Livelihood and educational programs implemented include the following:
� Manpower skills development
� Livelihood skills training
� Employment generation for local youth
� Capability-building for local government unit
Along the environment and culture, the following programs were undertaken:
� Tree planting activities
� Coastal clean-up
� Renovation of cultural and religious facilities
� Support of Municipal Fiesta
Generation of Employment from the Project
As presented in Table 13-15 and Table 13-16, majority of the workers hired by EBWPC and its
contractors during the construction of Transmission Line and Jetty Projects are from the
municipalities of Ilocos Norte, specifically in the project impact areas. Local contractors and
suppliers from the Province of Ilocos Norte were also prioritised by EBWPC. Most of the
workers and contractors from other provinces have the necessary technical capabilities and
![Page 24: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/24.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 13-20
experiences to build the transmission tower and jetty according to national and international
standards.
Employment of local workers provided direct benefit to individuals and households. Moreover,
income generated by the local employees is used to purchase goods and services from the
province, which enhanced the economy of Ilocos Norte. EBWPC and its contractors complied
with the mandate of DOLE National Wages and Productivity Commission as well as mandated
benefits such as SSS, PhilHealth and 13th month pay. In addition, staff house, service vehicle
as well as daily allowances were provided to staff that were from other provinces.
Table 13-15 Origin of EBWPC Employees during the Construct ion of the
Transmission Line and Jetty Projects
City/Municipality Number of employees Percentage
EBWPC staff
City of Laoag 4 7.84
Municipality of Bacarra 2 3.92
Municipality of Banna 1 1.96
Municipality of Burgos 39 76.5
Municipality of Pagudpud 1 1.96
Municipality of Paoay 1 1.96
Municipality of Pasuquin 3 5.88
Total 51 100
Jetty subcontractors
Municipality of Burgos 10 83.33
Municipality of Pagudpud 1 8.33
Metro Manila 1 8.33
Total 12 100
Table 13-16 Classificat ion of EBWPC Employees during the Construct ion of
Transmission Line and Jetty Projects
Classification Number of employees
Percentage
EBWPC staff
Regular 2 3.922
Project-based/Project hire 22 43.14
Contractual subcontractors (i.e. drivers, security guards) 27 52.94
Total 51 100.00
Transmission line subcontractors (First Balfour and its subcontractors)
Regular 15 7.98
Project-based/Project hire 173 92.02
Total 188 100.00
Jetty subcontractors
Contractual 1 8.33
Project-based/project hire 11 91.67
Total 12 100.00
![Page 25: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/25.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 13-21
13.6 Operat ion Phase Assessment
This section summarises the key issues and concerns including the beneficial effects of the
operation and maintenance of the Transmission Line and Jetty Projects. In particular, it
describes the potential changes to, or impacts on, the socio-economic and public health
condition of the people in the project impact areas.
Displacement and disturbance of properties
During the operation and maintenance of the Transmission Line, displacement and disturbance
of properties is insignificant since landowners are allowed to develop the farmlands along the
sail over lands as observed during the site visit. Allowed activities along the sail over area and
transmission line right-of-way include planting of crops up to a maximum height of two meters
and pasture grazing. However, construction of infrastructure is prohibited as well as transfer of
proprietary rights.
EBWPC will also continue on paying the lease or rent of the affected land based on the
conditions stipulated in the lease agreement/contract.
Cultural Resources
The potential impacts of the continuing operation and maintenance activities could include
damage to cultural resources, such as the Kapurpurawan Rock Formation and Palpalokada
Landscape, during vegetation management and other maintenance activities because of
passage of maintenance vehicles along the same access roads leading to these cultural
landscapes. The impact however is minimal and can be mitigated through the implementation
of Traffic Management Plan. Coordination with the local Tourism Council will also be
undertaken during the maintenance activities to prevent adverse impacts on cultural resources.
Occupational and Community Health and Safety
Safety risks identified during the operation and maintenance of the Transmission Line include
electric shock and fire. Electrocution could happen to maintenance workers during repair and
maintenance activities as well as to general public in case of accident. To minimise this impact,
EBWPC and its contractors will implement the Transmission Line Maintenance Manual which
explains safety precautions and maintenance protocols for the operation of transmission line.
The Transmission Line Maintenance Manual includes the following:
� Use of permanent or temporary signs or barriers during operation and maintenance
activities
� Conduct of information education and communication (IEC) activities or coordination with
the local government units (LGU) prior to the conduct of maintenance activities to prevent
public contact with potentially dangerous equipment
Fire risks could occur due to connection of transmission line to vegetation or overloading of
transmission lines. To prevent these risks, EBWPC, through its contractors regularly conduct
vegetation clearing to remove plants along the transmission line right-of-way zone. Further,
implementation of safety precautions in design and operation of the system was undertaken to
avoid overloading of transmission line. Regular monitoring and maintenance are also
undertaken to prevent occurrence of such risks.
Aircraft Navigation Safety
Transmission tower, if located proximate to airport or known flight paths, has the potential to
impact aircraft safety directly through collision or indirectly through radar interference. The
Laoag International Airport is located about 8 km from the nearest towers in Laoag City (Figure
13-1). To prevent aircraft collision impacts, EBWPC conducted consultation with the Civil
![Page 26: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/26.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 13-22
Aviation Authority of the Philippines (CAAP) and secured height clearance permit prior to the
installation of the transmission towers. Presented in Table 13-17 is the list of height clearance
permits secured for the Burgos Transmission Line while copies of said permit are shown in
Appendix T.
Additional measures that can be implemented to ensure aircraft navigation safety is the
installation of aerial marker balls or aircraft warning markers, lights or other attention grabbing
devices (Plate 13-1) on the conductors to improve their visibility.
Table 13-17 Height clearance permit secured for the Transmission Tow ers
No. Date Original tower No. As-built tower No.
Barangay Municipality
I-1028-10 18-Oct-10 TWR A– TWR C BL016– BL018 Saoit Burgos
I-1027-10 18-Oct-10 SP-001–SP015 BL001–BL015 Saoit Burgos
I-1056-10 18-Oct-10 TWR 122–TWR 126 BL141–BL143 Barit Laoag City
I-1055-10 18-Oct-10 TWR 118– TWR 121 BL137–BL138 Vira Laoag City
I-1054-10 18-Oct-10 TWR 110– TWR 117 BL129–BL136 Sangil Bacarra
I-1053-10 18-Oct-10 TWR 105– TWR 109 BL124–BL128 Cabaruan Bacarra
I-1052-10 18-Oct-10 TWR 101– TWR 104 BL120–BL123 Corocor Bacarra
I-1051-10 18-Oct-10 TWR 099– TWR 100 BL118–BL119 Pasngal Bacarra
I-1050-10 18-Oct-10 TWR 097– TWR 098 BL116–BL117 Cabusligan Bacarra
I-1049-10 18-Oct-10 TWR 095– TWR 096 BL114–BL115 Pungto Bacarra
I-1048-10 18-Oct-10 TWR 092– TWR 094 BL111–BL113 Carusipan Bacarra
I-1047-10 18-Oct-10 TWR 089–TWR 091 BL108–BL110 Nangab Pasuquin
I-1046-10 18-Oct-10 TWR 083– TWR 088 BL102–BL107 Batuli (San Isidro)
Pasuquin
I-1045-10 18-Oct-10 TWR 078– TWR 082 BL097–BL101 Pob 2 Pasuquin
I-1044-10 18-Oct-10 TWR 076 to TWR 077
BL095–BL096 Sulbec Pasuquin
I-1043-10 18-Oct-10 TWR 072– TWR 075 BL091–BL 094 Nagsanga Pasuquin
I-1042-10 18-Oct-10 TWR 069– TWR 071 BL088–BL090 Salpad Pasuquin
I-1041-10 18-Oct-10 TWR 066–TWR 068 BL085–BL087 Susugaen Pasuquin
I-1040-10 18-Oct-10 TWR 063–TWR 065 BL082–BL084 Estancia Pasuquin
I-1042-13 18-Oct-10 TWR 059– TWR 062 BL078–BL081 Sulongan Pasuquin
I-1038-10 18-Oct-10 TWR 055– TWR 058 BL074–BL077 Caruan Pasuquin
I-1037-10 18-Oct-10 TWR 050– TWR 054 BL069–BL073 Caruan Pasuquin
I-1042-16 18-Oct-10 TWR 038– TWR 049 BL057–BL068 Dilavo Pasuquin
I-1035-10 18-Oct-10 TWR 031– TWR 037 BL049–BL056 Davila Pasuquin
I-1034-10 18-Oct-10 TWR 025– TWR 030 BL043–BL048 Nagabungan Pasuquin
I-1033-10 18-Oct-10 TWR 020– TWR 024 BL038–BL042 Paayos Burgos
I-1032-10 18-Oct-10 TWR 010– TWR 019 BL028–BL037 Bayog Burgos
I-1031-10 18-Oct-10 TWR 009 BL027 Barat Burgos
I-1030-10 18-Oct-10 TWR 002– TWR 008 BL020–BL026 Der-ap Burgos
I-1029-10 18-Oct-10 TWR 001 BL019 Saoit Burgos
I-0368-11 8-Jul-11 TWR 128 BL148 Barit Laoag City
I-0364-11 8-Jul-11 TWR 124A BL144 Barit Laoag City
I-0365-11 8-Jul-11 TWR 125 BL145 Barit Laoag City
I-0366-11 8-Jul-11 TWR 126 BL146 Barit Laoag City
I-0367-11 8-Jul-11 TWR 127 BL147 Barit Laoag City
![Page 27: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/27.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 13-23
Plate 13-1 Aerial marker ball
Source: (Tranmsission & Distribution, 2013)
![Page 28: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/28.jpg)
!A
Padsan R
iver
Bacarra River
Bura
an
Riv
er
W e s t P h i l i p p i n e
S e a
Bacarra
Bangui
Burgos
Laoag
City
Pagudpud
Pasuquin
Piddig
SanNicolas Sarrat
Vintar
LaoagInternationalAirport
Jetty
235,000
235,000
240,000
240,000
245,000
245,000
250,000
250,000
255,000
255,000
260,000
260,000
265,000
265,000
2,0
15
,00
0
2,0
15
,00
0
2,0
20
,00
0
2,0
20
,00
0
2,0
25
,00
0
2,0
25
,00
0
2,0
30
,00
0
2,0
30
,00
0
2,0
35
,00
0
2,0
35
,00
0
2,0
40
,00
0
2,0
40
,00
0
2,0
45
,00
0
2,0
45
,00
0
2,0
50
,00
0
2,0
50
,00
0
G:\71\12098\GIS\Maps\MXD\BurgosTL&Jetty\Rev 0\7112098_Fig13-1_LaoagAirport_rev0.mxd
LEGEND
0 52.5
Kilometers
Map Projection: Transverse MercatorHorizontal Datum: WGS 1984
Grid: WGS 1984 UTM Zone 51No
© 2016. Whilst every care has been taken to prepare this map, GHD, EDC and NAMRIA make no representations or warranties about its accuracy, reliability, completeness or suitability for any particular purpose and cannot accept liability and responsibility of any kind
(whether in contract, tort or otherwise) for any expenses, losses, damages and/or costs (including indirect or consequential damage) which are or may be incurred by any party as a result of the map being inaccurate, incomplete or unsuitable in any way and for any reason.
EDC Burgos Wind Prower
ESIA for the Transmission Line and Jetty Project
Figure 13-1
Job Number
Revision 0
71-12098
19 Jan 2016
Location of Laoag International Airport relative to the Transmission Line
Date
Data source: EDC - Transmission Towers and Line (2014). NAMRIA - Municipality, Road, River. Created by:jcmatic
11/F Alphaland Southgate Tower, 2258 Chino Roces Avenue corner EDSA, Makati City 1232 Philippines T 63 2 479 5600 F 63 2 479 5601 E [email protected] W www.ghd.com
Paper Size A3
Æ̀ Airport
!A Jetty
!( Transmission Tower
Transmission Line
Waterway
Municipality
![Page 29: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/29.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 13-25
Electric and Magnetic Fields
One of the major concerns on transmission line projects is the generation of electric and
magnetic field (EMF). Electric and magnetic fields intensity is proportional with the line voltage
and electric current.
Electric fields, which are produced wherever there is electricity, are associated with any device
or wire that is connected to a source of electricity; while magnetic fields are created when there
is an electric current (Public Service Commission of Wisconsin). Electric fields, on one hand,
are easily shielded by common objects such as trees, fences and walls; and scientific studies
have found no association between exposure to electric fields and human disease (Public
Service Commission of Wisconsin). Magnetic fields, on the other hand, can pass through most
non-metallic materials and are more difficult to shield; however, magnetic fields become weaker
rapidly with distance from the source.
Magnetic fields generated by electric/transmission lines are in extremely-low-frequency (ELF)
range of the electromagnetic spectrum (Public Service Commission of Wisconsin). Figure
13-2 illustrates the spectrum of signals from different sources (e.g. radio transmission, television
transmission, gamma rays, cosmic rays, etc).
Figure 13-2 Electromagnet ic Spectrum
![Page 30: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/30.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 13-26
Presented in Table 13-18, are typical magnetic fields generated by different types of electric
lines in the United States. Typical ambient magnetic field levels are most often around 1 mG to
3 mG outside the easement (RoW corridor).
Based on today’s researches on electric and magnetic field, there are some guidelines for the
public exposure limitation but no standards limiting exposure. Also, these guidelines are
periodically reviewed and updated. The International Commission on Non-Ionizing Radiation
Protection (ICNIRP) guidelines for EMF Exposure on general public exposure is 2,000 mG
(Table 4 of ICNIRP Guidelines (1 Hz-100 kHz)).
Table 13-18 Typical US Magnet ic Field Levels associated w ith
Transmission Lines
Overhead TL voltages
Usage Typical Magnetic Field Measurement (mG)
Maximum in ROW
Approximate distance from the centreline
50 ft/ 15.24 m
100 ft/ 30.48 m
200 ft/ 60.96 m
300 ft/ 91.44 m
115 kV Average 30 7 2 0.4 0.2
Peak 63 14 4 0.9 0.4
230 kV Average 58 20 7 1.8 0.8
Peak 118 40 15 3.6 1.6
500 kV Average 87 29 13 3.2 1.4
Peak 183 62 27 6.7 3.0
Source: (World Health Organization (WHO), 2007) as cited in (Public Service Commission of Wisconsin)
For the Burgos Transmission Line Project, most towers were built more than 70 m away from
residential area or structures. The above table can be used for comparing expected magnetic
field levels on the Burgos Transmission Line Project. Listed in Table 13-19 and shown in
Appendix U are the transmission towers which were built near structures (approximately 70 m
and below).
Based on Table 13-19, there are seven towers built near structures; these are BL 133, and
BL143 to BL148. The structure near BL133 was compensated and demolished. On the other
hand, compensation or disturbance fee was given to the owner of structure located near the
other six towers. It is also worthy to note that towers BL143 to BL148 are steel poles and were
built within strict horizontal clearance requirements (i.e. in terms of wiring).
Table 13-19 List of Tow ers Built near Structures
Tower No. Barangay Municipality Distance to nearest structure (m)
BL022 Saoit Burgos 70
BL034 Bayog Burgos 55
BL079 Sulongan Pasuquin 65
BL093 Nagsanga Pasuquin 70
BL095 Sulbec Pasuquin 65
BL098 Libeng/ Poblacion Pasuquin 70
BL107 Batuli Pasuquin 37
BL110 Ngabngab Pasuquin 60
BL118 Pasngal Bacarra 30
BL120 Pasngal Bacarra 30
BL130 Sangil Bacarra 50
![Page 31: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/31.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 13-27
Tower No. Barangay Municipality Distance to nearest structure (m)
BL133 Sangil Bacarra 15
BL138 Vira Laoag City 60
BL143 to BL148 Barit Laoag City less than 10 m
In general, magnetic fields are measured at user distance from appliance and refer to (National
Institute of Environmental Health Sciences (NIEHS), 2002) for the measurement found in most
homes.
The studies have found weak association, or no association, between exposure to EMF and the
incidence of some cancers. On one hand, scientists cannot prove that magnetic fields have no
effect and can be safe. On the other hand, science has not been able to prove that magnetic
fields do have an effect. There is a general consensus within the scientific community that
exposure to EMF is not responsible for human disease. The Public Service Commission of
Wisconsin listed result of studies undertaken by various institutions on EMF:
� There is no documented cancer linked to EMF exposure1
� There is a little evidence that magnetic fields cause childhood leukemia, and there is
inadequate evidence that magnetic fields cause other cancers in children 2
� Studies of adults magnetic field exposure from power lines show little evidence of an
association with leukemia, brain tumors, or breast cancer3
� Whole animal exposure studies have not shown evidence that long-term exposure to
EMF causes cancer, and no link has been found to leukemia, brain cancer and breast
cancer4
� For power line magnetic fields below 500 mG, no plausible mechanisms have been
identified by which biological effects can be caused in living systems5
To address the concern of the community regarding electro-magnetic field, EBWPC will conduct
continuous IEC activities explaining scientific studies about EMF.
Socio-economic benefits
Job opportunities during the operation and maintenance of the Transmission Line can provide
direct impact to the host communities. To enhance this benefit, EBPWC will prioritize local
workers in job opportunities and comply with the requirements of the national government in
terms of salary and benefits provided to workers.
The number of required personnel during operation and maintenance is significantly reduced
during the construction phase, which consequently reduces the direct socio-economic impacts
related to jobs. However, the operation and maintenance phase will provide a good opportunity
for technicians, electrician, engineers, and other skilled laborers for a long-term employment.
Further, taxes and revenue paid to the local government will continue. This will enhance the
basic services and infrastructure in the community that will directly benefit the residents.
1 Michael P. Halpin, P.E., Florida Department of Environmental Protection, Transmission Lines–
Electric and Magnetic Fields (EMF), presentation <http://www.dep.state.fl.us/siting/files/application/ppsa/turkey_pt/emf_presentation.pdf>, website accessed April, 10, 2013. 2 National Cancer Institute Factsheet, <http://www.cancer.gov/cancertopics/factsheet/Risk/magnetic-fields>, accessed April, 10,
2013. 3 Ibid
4 Medical College of Wisconsin, 2006.
5 Robert K. Adair, Constraints on Biological Effects of Weak Extremely-Low-Frequency Electromagnetic Fields, Phys Rev A.
January 1991, Vol. 43, Issue 2, pp. 1039-1048
![Page 32: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/32.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 13-28
EBWPC will also implement Social Development Plan as part of its Corporate Social
Responsibility to further enhance the benefits to the host communities.
13.7 Conclusions
The adverse impacts of the transmission line and jetty during the operation and maintenance
phase on the socio-economic condition of the project impact areas are minimal and insignificant
(Table 13-20). Management measures, discussed in the Environmental and Social
Management and Monitoring Plan (ESMP) in Section 16, are now being implemented to prevent
the occurrence of adverse impacts. This includes the following:
� Traffic Management Plan
� Transmission Maintenance Manual
� Social Development Plan
� Information Education and Communication Campaigns
� Occupational Health and Safety Manual
Table 13-20 Key impacts and proposed mit igat ion/enhancement measures
Key impacts Phases Potential significance
Options for prevention/ mitigation or enhancement
Construction Operation TL Jetty
Displacement and disturbance of properties (permanent or temporary loss of productive land)
✁ ✁ High None Compensation of affected crops and land
Restoration and rehabilitation of disturbed areas (e.g. temporary access roads)
Preparation of Livelihood Restoration Plan (LRP) for the 49 households
Occupational and community health and safety
✁ ✁ Low Low Implementation of Occupational Health and Safety (OHS) Plan, Transmission Line Management Manual
Routine vegetation clearing
Regular monitoring and maintenance
Aircraft safety navigation
✁ Low None Consultation with CAAP during design phase
Secured height clearance permit
Installation of aerial marker balls or aircraft warning markers, light or other attention grabbing devices
![Page 33: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/33.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 13-29
Key impacts Phases Potential significance
Options for prevention/ mitigation or enhancement
Construction Operation TL Jetty
Electric and magnetic fields
� High None Most transmission towers were built more than 70 m away
Structures built within the 30 m ROW were compensated and demolished
Compliance with horizontal clearance requirements
Use of steel poles
IEC activities on EMF
Creation of local employment opportunities
� � High High Employment of local workers
Compliance with local labour laws
Wider economic (taxes and revenue) and employment benefits (indirect employment)
� � High High Implementation of Social Development Plan (SDP)
13.8 References
✁ City Planning and Development Office (CPDO). City Ecological Profile. Laoag City:
Local Government Unit.
✁ Micheal P Halpil, P. (n.d.). Florida Department of Environmental Protection, Transmission
Lines - Electric and Magnetic Fields. Retrieved January 14, 2015, from
http://www.dep.state.fl.us/siting/files/application/ppsa/turkey_pt/emf_presentation.pdf
✁ Municipal Health Office. (2012). Municipal Health Profile. Municipality of Burgos: Local
Government Unit.
✁ Municipal Planning and Development Office (MPDO). (2010). Municipal Ecological
Profile. Municipality of Burgos: Local Government Unit.
✁ Municipal Planning and Development Office (MPDO) of Pasuquin and Department of
Interior and Local Government (2010). Municipal Ecological Profile. Municipality of
Pasuquin, Ilocos Norte: Local Government Unit
✁ Municipal Planning and Development Office. (2012). Municipal Profile. Municipality of
Bacarra: Local Government Unit.
✁ National Cancer Institure Factsheet. (n.d.). Retrieved January 14, 2015, from
http://www.cancer.gov/cancertopics/factsheet/Risk/magnetic-fields
✁ National Institute of Environmental Health Sciences (NIEHS). (2002, June). EMF:
Electrical and Magnetic Fields Associated withthe Use of Electric Power. Retrieved
January 14, 2015, from http://www.niehs.nih.gov/health/topics/agents/emf/
✁ Philippine Statistics Office. (2010, May 1). 2010 Census of Population and Housing.
Retrieved
January 7, 2015, from http://census.gov.ph/sites/default/files/attachments/hsd/pressreleas
e/Ilocos.pdf
![Page 34: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/34.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 13-30
� Public Service Commission of Wisconsin. (n.d.). Retrieved January 14, 2015, from
Electric & Magnetic Fields: http://psc.wi.gov/thelibrary/publications/electric/Electric12.pdf
� Transmission and Distribution. (2013). Power Line Markers. Retrieved January 14, 2015
from http://tdworld.com/products/power-line-markers
![Page 35: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/35.jpg)
![Page 36: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/36.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | i
Table of contents
14. Landscape and Visual Impact Assessment ............................................................................. 14-1
14.1 Introduction .................................................................................................................... 14-1
14.2 Methodology .................................................................................................................. 14-1
14.3 Existing Values .............................................................................................................. 14-7
14.4 Impact Assessment ...................................................................................................... 14-30
14.5 Mitigation ...................................................................................................................... 14-47
14.6 Conclusions and Summary of Findings ....................................................................... 14-48
Table index
Table 14-1 Landscape Sensitivity .................................................................................................... 14-3
Table 14-2 Landscape capacity to accommodate change .............................................................. 14-3
Table 14-3 Magnitude of Landscape Impacts / Visual Modification ................................................. 14-5
Table 14-4 Assessment of receptor sensitivity ................................................................................ 14-5
Table 14-5 Duration of impacts ........................................................................................................ 14-6
Table 14-6 Quality of the impact ...................................................................................................... 14-6
Table 14-7 Significance of Impact .................................................................................................... 14-7
Table 14-8 LCU1 – Forested Landscape ....................................................................................... 14-10
Table 14-9 LCU2 – Agricultural/Rural Landscape ......................................................................... 14-13
Table 14-10 LCU3 – Built-up Landscape ......................................................................................... 14-15
Table 14-11 VL1 – Kapurpurawan 4x4 Trail .................................................................................... 14-17
Table 14-12 VL2 – Barangay Ablan House Cluster ......................................................................... 14-18
![Page 37: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/37.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | ii
Table 14-13 VL3 – Cape Bojeador Lighthouse ................................................................................ 14-19
Table 14-14 VL4 – Bayog Elementary School ................................................................................. 14-20
Table 14-15 VL5 – Barangay Davila Salt Vendor Kiosks ................................................................ 14-21
Table 14-16 VL6 – Pasuquin Beach ................................................................................................ 14-22
Table 14-17 VL7 – Barangay Dilavo Field ....................................................................................... 14-23
Table 14-18 VL8 – Barangay Estancia Field ................................................................................... 14-24
Table 14-19 VL9 – Barangay Salpad Field ...................................................................................... 14-25
Table 14-20 VL10 – Barangay Poblacion 2 Field ............................................................................ 14-26
Table 14-21 VL11 – Barangay Carusipan Field ............................................................................... 14-26
Table 14-22 VL12 – Barangay Corocor Field .................................................................................. 14-27
Table 14-23 VL13 – Bacarra River................................................................................................... 14-28
Table 14-24 VL14 – Barangay Salet-Bulangon ............................................................................... 14-29
Table 14-25 VL15 - Jetty .................................................................................................................. 14-30
Table 14-26 LCU1 Impact Assessment ........................................................................................... 14-31
Table 14-27 LCU2 Impact Assessment ........................................................................................... 14-31
Table 14-28 LCU3 Impact Assessment ........................................................................................... 14-32
Table 14-29 VL1 Impact Assessment .............................................................................................. 14-33
Table 14-30 VL2 Impact Assessment .............................................................................................. 14-34
Table 14-31 VL3 Impact Assessment .............................................................................................. 14-35
Table 14-32 VL4 Impact Assessment .............................................................................................. 14-36
Table 14-33 VL5 Impact Assessment .............................................................................................. 14-37
Table 14-34 VL6 Impact Assessment .............................................................................................. 14-38
Table 14-35 VL7 Impact Assessment .............................................................................................. 14-39
Table 14-36 VL8 Impact Assessment .............................................................................................. 14-40
Table 14-37 VL9 Impact Assessment .............................................................................................. 14-41
Table 14-38 VL10 Impact Assessment ............................................................................................ 14-42
Table 14-39 VL11 Impact Assessment ............................................................................................ 14-43
Table 14-40 VL12 Impact Assessment ............................................................................................ 14-44
Table 14-41 VL13 Impact Assessment ............................................................................................ 14-45
Table 14-42 VL14 Impact Assessment ............................................................................................ 14-46
Table 14-43 VL15 Impact Assessment ............................................................................................ 14-47
Table 14-44 Summary of Impacts .................................................................................................... 14-48
![Page 38: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/38.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | iii
Figure index
Figure 14-1 Locations of Landscape Character Units (LCU) ............................................................ 14-8
Figure 14-2 Representative Viewing Locations ............................................................................... 14-16
![Page 39: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/39.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-1
14. Landscape and V isual Impact
Assessment
14.1 Introduction
This section of the ESIA covers the assessment of the landscape and visual impacts/effects of
the constructed transmission line traversing the towns of Burgos, Pasuquin, Bacarra, and Laoag
City as well as the jetty in Barangay Ablan.
For the purpose of this report, the term ‘Landscape’ refers to landscape character, landscape
context, views and prospects, historical landscape and anthropogenic landscapes.
Landscape and Visual Impact Assessment (LVIA) is a combination of two separate but closely
related aspects. The Guidelines for Landscape and Visual Impact Assessment 3rd
Edition
(GLVIA3) describes:
� Landscape Impacts as the effects of the changes in and/or partial or complete loss of
elements, features or aesthetic or perceptual aspects that contribute to the character and
quality of the landscape as well as the addition of new elements or features that will
influence the character and quality of the landscape and alter perceptions; and
� Visual Impacts as the effects of change and development on the views available to
people and their visual amenity.
The central purpose of the LVIA is to identify significant adverse impacts upon landscape and
visual amenity and to propose measures to mitigate or ameliorate such impacts.
The structure of this section is outlined as follows:
� Methodology – process adopted to assess landscape and visual effects and the
limitations and assumptions of this method
� Existing Values – description and evaluation of the baseline landscape and visual
amenity within the visual catchment as well as identification of representative
viewpoints/sensitive receptors
� Impact assessment – assessment of the significance of effects upon landscape and
visual amenity, including:
– GIS viewshed analysis / Zone of Theoretical Visibility
– Description of landscape and visual impacts for each viewpoint and cumulative
impacts
� Mitigation – proposed measures to reduce, remedy or offset negative visual impacts
brought about by the project
� Conclusions and summary of findings
14.2 Methodology
14.2.1 Basis for the Landscape and Visual Impact Assessment
The methodology for the LVIA has been set out to respond to particular project requirements
and constraints including the scale and nature of the project.
This assessment draws on the Guidelines for Landscape and Visual Impact Assessment, Third
Edition, published by the Landscape Institute and Institute of Environmental Management and
Assessment (2013) which is regarded as the international standard for LVIA.
![Page 40: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/40.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-2
14.2.2 Establishment of the Baseline Landscape Characterisat ion
It is proposed that systematic, accurate and comprehensive descriptions of the following
conditions will be included in the assessment. The methodology for the identification of the
existing environment, surrounding landscape character and the identification of the viewing
locations is detailed below.
Defining the Visual Catchment
An indicative visual catchment within which the project may be seen has been defined based on
a worst case scenario based on the investigation corridor. This has been determined through a
desktop study examining aerial photographs and topographic maps where landform and land
cover (screening) were considered in tandem. Also taken into consideration was the potential
maximum visibility for this type of development. For LVIA, the visual catchment becomes the
study area.
This preliminary visual catchment is then used to identify sensitive receptors with views of the
project.
Site Survey
A site survey was undertaken by a Landscape Architect to verify the desktop study findings,
allow characterisation of the landscape, identify sensitive receptors and observe how receptors
might view the landscape. The site visit was conducted in November 2014 during conditions of
good visibility.
During the site survey, the Landscape Architect traversed the study area and viewed the
investigation corridor from publicly accessible viewpoints. At each location a photographic
record of landscape features, key views and receptors was obtained along with coordinates,
bearings, field notes and sketches.
Description of Existing Conditions
The description of existing landscape and visual environment establishes a baseline against
which the project is assessed. The principal document and data sources used have been set
out in the bibliography, referenced within relevant sections of the text.
Defining the Landscape Character Areas
Landscape character considers common landscape types (defined by typical features and
characteristics) and highlights any principal landscape features. A description of the landscape
character differentiates between subjective assessments and objective description and is
provided from both within the study area, and from the wider landscape.
The factors that have been considered in categorising the landscape character areas include
landform, vegetation and intensity and character of land. The categorising was informed through
a review of the information assembled in the desk study and the site survey described in
Section 14.3.1.
Selection of Receptor Viewpoints
Representative publicly accessible viewpoints have been identified in a range of locations and
are identified in section 14.3.2. These have been recorded and photographed. Photographs of
viewpoints within section 14.3.2 represent a range of typical views from that locality to the
project. Viewpoints are selected in order to:
� Represent views of particular landscape and /or visual features of importance.
![Page 41: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/41.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-3
� Represent views from key visual receptors that spend extended amounts of time and
other locations from which fixed or transient views would be possible, but where the time
of stay is shorter. These include residents, road and recreational receptors.
14.2.3 Assessment of Landscape Impacts
Landscape is defined as features (such as vegetation, built elements, topography, etc.) either
within the project boundary or on land adjacent. The features of the landscape are considered
as an integral part of the landscape and visual context that contribute to the overall character of
the environment.
Assessment of changes to the landscape includes identification of:
� The nature of the change, (that is the degree of contrast, or integration) of, any new
features with existing features;
� Context and quality of the views including the extent to which the project would be visible
in the wider landscape (with consideration of the presence of intervening vegetation or
features);
� The scale or degree of change (i.e. obvious / imperceptible with respect to loss or
addition of features); and
� The nature of the impact (adverse or beneficial).
The significance of the landscape character unit is described in Table 14-1. For the purposes of
this assessment, the definition of impacts relate to the relative capacity of the landscape to
accommodate changes to the physical landscape of the type and scale proposed that would
occur as a direct result of the project. These are defined in Table 14-2.
Table 14-1 Landscape Sensit ivity
Landscape Sensitivity Definition
High Landscapes of international designation that are highly valued, particularly near or distinctive and susceptible to small change
Medium Landscape of regional designation that are valued more locally and tolerant of moderate levels of change
Low Landscapes of local designation that are more commonplace and potentially tolerant of noticeable change or are undergoing substantial development, such that their character is one of change.
Table 14-2 Landscape capacity to accommodate change
Landscape capacity Definition
Low capacity The landscape has high sensitivity to the type of development proposed which could have a detrimental effect on the landscape character or value. Mitigation measure unlikely to reduce the impacts of the change.
Medium capacity The landscape has medium sensitivity to the type of development proposed. Any change caused by the proposed development would be unlikely to have a significant adverse effect on the landscape character or value that could not be mitigated against.
![Page 42: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/42.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-4
Landscape capacity Definition
High capacity The landscape would have low sensitivity to this type of development and few constraints imposed by landscape elements. Development of this type is very unlikely to have an adverse effect on the landscape character. Mitigation measures would be effective in neutralising adverse effects and / or may improve the landscape character.
14.2.4 Assessment of Visual Impacts
People are mobile and therefore could potentially experience views of the project from many
different locations. In order to undertake an assessment of visual impacts, a series of key
viewing locations have been selected to represent the points from which the project is to be
viewed by the greatest number of visual receptors and from where the most sensitive visual
receptors are to perceive the project.
Project impacts can be evaluated on the basis of a combination of two factors that inform the
level significance of impact:
� Visual modification, and
� Visual sensitivity.
Both are defined in sections Table 14-3 and Table 14-4 respectively, and their use in identifying
severity of the impacts outlined.
Visual Modification
Visual impacts arise from changes in available views of the landscape that occur as a result of
the project. Visual impact is determined through the subjective assessment of sensitivity of the
visual receptors and the magnitude (scale) of the change in view. Sensitivity is dependent upon
receptors’ location; the importance of their view; their activity; expectations; available view; and
the extent of screening of this view.
Factors that have been considered in assessing the response to changes in the visual amenity
include:
� Interest in the visual environment and their distance/angle of view to the source of the
impact
� The extent of screening/filtering of the view
� Magnitude of change in the view (i.e. loss/addition of features that change the view’s
composition)
� Quality of the impact as detailed in Table 14-6
� Integration of changes within the existing view (form, mass, height, colour and texture)
� Duration of the effect as detailed in Table 14-5
� Effectiveness of the proposed mitigation
![Page 43: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/43.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-5
Table 14-3 Magnitude of Landscape Impacts / V isual Modificat ion
Impact Definition
Large A substantial / obvious change to the landscape due to total loss of, or change to, elements, features or characteristics of the landscape. Would cause a landscape to be permanently changed and its quality diminished.
Moderate Discernible changes in the landscape due to partial loss of, or change to the elements, features or characteristics of the landscape. May be partly mitigated. The change would be out of scale with the landscape, and at odds with the local pattern and landform and would leave an adverse impact on the landscape.
Small Minor loss or alteration to one or more key landscape elements, features, or characteristics, or the introduction of elements that may be visible but may not be uncharacteristic within the existing landscape.
Negligible Almost imperceptible or no change in the view as there is little or no loss of / or change to the elements, features or characteristics of the landscape.
Visual Sensitivity
Visual sensitivity refers to visual receptors and their sensitivity to their visual environment.
Visual sensitivity is defined as the perception of viewers.
For the purposes of this assessment, key visual receptors users of public recreation areas and
all have differing sensitivities to their visual environment. Generally, sensitivity is derived from a
combination of factors including:
� Receptors’ interest in the visual environment (i.e. high, medium or low interest in their
everyday visual environment, and the duration of the effect);
� Receptors’ duration and viewing opportunity (i.e. prolonged, regular viewing
opportunities);
� Number of viewers and their distance / angle of view from the source of the effect, extent
of screening / filtering of the view, where relevant.
For the purposes of this assessment, the terminology set out in Table 14-4 has been used to
describe visual sensitivity.
Table 14-4 Assessment of receptor sensit ivity
Sensitivity Definition
High Occupiers of residential properties with long viewing periods, within close proximity to the proposed development.
Communities that place value upon the landscape and enjoyment of views of their setting.
Receptors that have special interest in the landscape character of the area (e.g. photographers, tourists)
Medium Outdoor workers who have a key focus on their work that may also have intermittent views of the project area.
Viewers at schools, or similar, when outdoor play and recreation areas are located within close proximity but viewing periods are limited.
Occupiers of residential properties with long viewing periods, at a distance from or screened from the project area.
Low Road users in motor vehicles, or on transport routes that are passing through or adjacent to the study area and therefore have short term views.
Viewers indoor at their place of work, schools or similar.
![Page 44: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/44.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-6
Sensitivity Definition
Negligible Viewers from locations where there is screening by vegetation or structures where only occasional screened views are available and viewing times are short.
Road users in motor vehicles, or on transport routes that are passing through/adjacent to the study area and have partially screened views and short viewing times.
14.2.5 Durat ion of Impact
The duration of impact has been defined for the purposes of this assessment as outlined in
Table 14-5.
Table 14-5 Durat ion of impacts
Duration Definition
Temporary Impacts lasting one year or less
Short Term Impacts lasting one to seven years
Medium Term Impacts lasting seven to fifteen years
Long Term Impacts lasting fifteen to sixty years
Permanent Impacts lasting over sixty years
14.2.6 Impact Type
The definition for ‘quality of impact’ as used in this assessment has been outlined in Table 14-6.
Table 14-6 Quality of the impact
Quality Definition
Neutral A neutral impact would neither enhance nor detract from the landscape character or viewpoint.
Positive A positive impact would improve or enhance the landscape character or viewpoint.
Negative A negative impact would reduce or have an adverse effect on the existing landscape character or viewpoint.
14.2.7 Significance of Impact
Only impacts of major or high significance in the context of this assessment have been
considered. These impacts would require further refinement through mitigation or detailed
design.
The definition used to identify significance of impacts for this assessment has been outlined in
Table 14-7.
![Page 45: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/45.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-7
Table 14-7 Significance of Impact
Magnitude of Landscape Impact / Visual Modification
Large Moderate Small Negligible S
ensitiv
ity
High Major Significance
High Significance
Moderate Significance
Minor Significance
Medium High Significance
Moderate Significance
Minor Significance
Not Significant
Low Moderate Significance
Minor Significance
Not Significant Not Significant
Negligible Minor Significance
Not Significant Not Significant Not Significant
14.2.8 Mit igat ion
As the project is already in its operational phase, mitigation measures are limited to reduction
and offsetting of the impacts.
Strategies are described below:
� Reduction – reduction of adverse effects. The significance of adverse impacts is
lessened. Seeks to limit exposure of the sensitive visual receptor. Reduce the visibility of
the project (e.g. by installing barriers between the location(s) of likely receptors and the
source of impact.
� Remedy/Offsetting – Remedy serves to improve adverse conditions by carrying out
further works which seek to restore the environment (e.g. increased planting of
trees/shrubs to offset unavoidable loss of vegetation)
If it is not possible to mitigate an impact, this is described as a residual impact.
14.3 Exist ing Values
The transmission line traverses 29 barangays in the municipalities of Burgos, Pasuquin,
Bacarra, and the City of Laoag, all in the province of Ilocos Norte. These areas are generally
considered rural except Laoag City being reasonably urbanized.
This section gives an overview of the landscape character in the vicinity of the project area as
well as identifies the representative viewing locations/sensitive receptors of impacts.
14.3.1 Landscape Character Units (LCUs)
The study area is divided into landscape character units sharing common landscape features
and visual characteristics. Categorization by LCUs allows for general statements to be made
about landscapes and their sensitivity. However, it should be acknowledged that landscapes
within the study area relatively vary in terms of landforms, land use, vegetation, significant
features and views.
The LCUs recognized in this assessment are:
� LCU1 – Forested Mountains
� LCU2 – Agricultural Lowland
� LCU3 – Built-up Areas
![Page 46: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/46.jpg)
!A
W e s t
P h i l i p p i n e
S e a
Bacarra
BanguiBurgos
Laoag
City
Pasuquin
Piddig
Sarrat
Vintar
Ro
ad
Jetty BanguiWind Fam
230,000
230,000
235,000
235,000
240,000
240,000
245,000
245,000
250,000
250,000
255,000
255,000
260,000
260,000
2,0
15
,00
0
2,0
15
,00
0
2,0
20
,00
0
2,0
20
,00
0
2,0
25
,00
0
2,0
25
,00
0
2,0
30
,00
0
2,0
30
,00
0
2,0
35
,00
0
2,0
35
,00
0
2,0
40
,00
0
2,0
40
,00
0
2,0
45
,00
0
2,0
45
,00
0
2,0
50
,00
0
2,0
50
,00
0
G:\71\12098\GIS\Maps\MXD\BurgosTL&Jetty\Rev 0\7112098_Fig14-1_LVIA.mxd
LEGEND
0 52.5
Kilometers
Map Projection: Transverse MercatorHorizontal Datum: WGS 1984
Grid: WGS 1984 UTM Zone 51No
© 2016. Whilst every care has been taken to prepare this map, GHD, EDC and NAMRIA make no representations or warranties about its accuracy, reliability, completeness or suitability for any particular purpose and cannot accept liability and responsibility of any kind
(whether in contract, tort or otherwise) for any expenses, losses, damages and/or costs (including indirect or consequential damage) which are or may be incurred by any party as a result of the map being inaccurate, incomplete or unsuitable in any way and for any reason.
EDC Burgos Wind Prower
ESIA for the Transmission Line and Jetty Project
Figure 14-1
Job Number
Revision 0
71-12098
19 Jan 2016
Land Character Units (LCUs)
Date
Data source: EDC - Transmission Towers and Line (2014). NAMRIA - Municipality, Road, River. Created by:jcmatic
11/F Alphaland Southgate Tower, 2258 Chino Roces Avenue corner EDSA, Makati City 1232 Philippines T 63 2 479 5600 F 63 2 479 5601 E [email protected] W www.ghd.com
Paper Size A3
!A Jetty Project
Bangui Wind Farm
!( Transmission Tower
Transmission Line
Highway
Road
Barangay
Municipality
Landscape Character Units
LCU1 - Forested landscape
LCU2 - Agricultural/Rural landscape
LCU3 - Built-up landscape
![Page 47: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/47.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-9
LCU1 – Forested Landscape
This LCU, shown in Plate 14-1 and Plate 14-2, generally covers the northern part of the study
area. As shown in Table 14-8, the transmission line traverses this LCU from the town of Burgos
to Pasuquin and some parts of Bacarra. Table 14-8 describes the landscape character in this
LCU.
Plate 14-1 Typical long distance view in Forested Landscape
Plate 14-2 Typical view of Forested Landscape
![Page 48: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/48.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-10
Table 14-8 LCU1 – Forested Landscape
LCU1 – Forested Landscape
Landscape/Visual Element
Description
Location These areas comprise the Barangays of Saoit, Poblacion, Ablan Sarat, Bayog, and Paayas in the town of Burgos as well as Barangays Davila and Dilavo in Pasuquin, Barangay Sangil in Bacarra and Barangay no. 59-B Dibua North and 55-C Vira in Laoag City.
Towers BL-1 to 36, BL-44 to 68 and BL-136 to 140 are located within this LCU.
Landform and significant landscape features
The topography consists of:
Gently sloping hills in the northern and southern section of the LCU (elevation ranging from 20 to 80 m)
Steeply sloping hills in Barangay Bayog, Davila, and Dilavo (elevation reaching up to 200 m)
Gentle undulating low plains with gently to steeply sloping hills to the west of the LCU in Barangay Paayas
A number of cellular sites/towers appear in the landscape.
Cape Bojeador Lighthouse, also known as the Burgos Lighthouse, is a cultural heritage structure. Standing 17 m high, approximately 160 masl, this is the most prominent tower in the vicinity. It is also a frequently visited tourist attraction and is considered a significant feature in this LCU.
This LCU has borrowed views of the Cordillera Central, the highest and largest mountain range in the Philippines.
Vegetation Dense cover of open forest, broad-leaved tree species and woody shrubs with patches of rough grasslands on flatland areas
Water West Philippine Sea
Buraan River in Barangay Ablan
Several ephemeral creeks with riparian zones
Land use Open forest
Sparse rural-residential properties along national road
The Pan-Philippine or Maharlika Highway is the arterial road running the length of this LCU.
LCU2 – Agricultural/Rural Landscape
The Agricultural/Rural Landscape LCU, shown in Plate 14-3, Plate 14-4, Plate 14-5 and Plate
14-6, encompasses the other half of the study area. Table 14-9 describes the landscape
character in this LCU.
![Page 49: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/49.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-11
Plate 14-3 Typical short distance view in Agricultural/Rural Landscape
Plate 14-4 Typical distance view in Agricultural/Rural Landscape
![Page 50: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/50.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-12
Plate 14-5 Typical long distance view in Agricultural/Rural Landscape
Plate 14-6 Typical long distance view in Agricultural/Rural Landscape
![Page 51: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/51.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-13
Table 14-9 LCU2 – Agricultural/Rural Landscape
LCU2 – Agricultural/Rural Landscape
Landscape/Visual Element
Description
Location The areas defined as Agricultural/Rural Landscape are located in the Barangay Bobon in the town of Burgos, Barangays Caruan, Sulongan, Estancia, Susugaen, Salpad, Nagsanga, Nalvo, Sulbec, Pragata, San Juan, Poblacion 1 to 4, Puyupuan, Batuli, Naglicuan, Ngabangab, Binsang and Carusipan in Pasuquin. Also included are the Barangays of Cadaratan, Pungto, Cabusligan, Pasngal, Cabulalaan, Corocor, Cabaruan, Sangil, and Pasiocan in the town of Bacarra.
Towers BL-37 to 43, BL-69 to 135 and BL-141 to 148 are located within this LCU.
Landform and significant landscape features
The topography is generally low and flat paddy fields. These fields are commonly observed on both sides of the road. Crops such as rice, garlic and onions are planted alternately throughout the year.
A number of power poles dotting the highway and occasional cellular sites/towers appear in the landscape.
Bacarra river and its floodplain lie at the center of this LCU. During dry season, a vast section of Bacarra River is dry, permitting low secondary growth trees and shrubs to grow with the river bed.
Medium and long distance views are framed with forested hills and mountains (LCU1).
Vegetation 90% monochromatic cover of arable land
Rough grasslands in Bacarra floodplain
Water West Philippine Sea
Bacarra River
Several ephemeral creeks with riparian zones
Land use Agricultural land/Farmland/Grassland
Sparse rural-residential properties along national road
The Pan-Philippine or Maharlika Highway is the arterial road running the length of this LCU.
LCU3 – Built-up Landscape
This LCU, shown in Plate 14-7 and Plate 14-8, is apportioned to more established residential
communities. One is within the study area while the other two are partly contained by the 2-
kilometer buffer. Table 14-10 describes the landscape character in this LCU.
![Page 52: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/52.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-14
Plate 14-7 Typical short distance view in Built -up Landscape
Plate 14-8 Typical medium distance view in Built -up Landscape
![Page 53: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/53.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-15
Table 14-10 LCU3 – Built -up Landscape
LCU2 – Built-up Landscape
Landscape/Visual Element
Description
Location These areas consist of the Barangays Poblacion 1 to 4 in the town of Pasuquin, southwest of the study area. Bacarra municipal proper is to the east and Laoag City to the south. Both are outside the study area.
Landform and significant landscape features
The topography is generally flat lowland surrounded by LCU2.
Typically, only short and medium distance views are available due to the dense housing characteristic of this LCU.
Vegetation Significant overlay of trees and woody shrubs reaching up to 5 m high.
Water Bacarra River on the southern edge of Bacarra municipal proper
Padsan River on the southern edge of Laoag City
Several ephemeral creeks with riparian zones
Land use Rural-residential properties
The Pan-Philippine or Maharlika Highway is the arterial road running the length of this LCU.
Barangay roads are also present in this LCU.
14.3.2 Sensit ive Receptors
The transmission line being 42 km in length offers a substantial number of locations from which
it may be viewed. At the same time, people are mobile and therefore could potentially
experience different views. Thus, in order to undertake an assessment of visual impacts,
representative viewing locations were selected where the volume of sensitivity of visual
receptors was relatively high.
Likely viewers or receptors include local residents, farmers, tourists visiting towns of Burgos,
Pasuquin, Bacarra and Laoag City, and locals and tourists travelling from Laoag City to Burgos.
Figure 14-2 shows the representative viewing locations (VLs). They are outlined below:
� Viewing Location 1 (VL1) – Kapurpurawan 4x4 Trail
� Viewing Location 2 (VL2) – Barangay Ablan House Cluster
� Viewing Location 3 (VL3) – Cape Bojeador Lighthouse
� Viewing Location 4 (VL4) – Bayog Elementary School
� Viewing Location 5 (VL5) – Barangay Davila Field
� Viewing Location 6 (VL6) – Pasuquin Sexy Beach
� Viewing Location 7 (VL7) – Barangay Dilavo Field
� Viewing Location 8 (VL8) – Barangay Estancia Field
� Viewing Location 9 (VL9) – Barangay Salpad Field
� Viewing Location 10 (VL10) – Barangay Poblacion 2 Field
� Viewing Location 11 (VL11) – Barangay Carusipan Field
� Viewing Location 12 (VL12) – Barangay Corocor Field
� Viewing Location 13 (VL13) – Bacarra River
� Viewing Location 14 (VL14) – Barangay Salet-Bulangon
� Viewing Location 15 (VL15) – Jetty
![Page 54: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/54.jpg)
!A
W e s t
P h i l i p p i n e
S e a
Bacarra
Bangui
Burgos
Carasi
Dumalneg
Laoag
City
Pagudpud
Pasuquin
Piddig
Sarrat
Vintar
Road
Jetty BanguiWind Fam
235,000
235,000
240,000
240,000
245,000
245,000
250,000
250,000
255,000
255,000
260,000
260,000
265,000
265,000
2,0
15
,00
0
2,0
15
,00
0
2,0
20
,00
0
2,0
20
,00
0
2,0
25
,00
0
2,0
25
,00
0
2,0
30
,00
0
2,0
30
,00
0
2,0
35
,00
0
2,0
35
,00
0
2,0
40
,00
0
2,0
40
,00
0
2,0
45
,00
0
2,0
45
,00
0
2,0
50
,00
0
2,0
50
,00
0
G:\71\12098\GIS\Maps\MXD\7112098_EBWPC_TransmissionLine_revA_v2.mxd
LEGEND
0 52.5
Kilometers
Map Projection: Transverse MercatorHorizontal Datum: WGS 1984
Grid: WGS 1984 UTM Zone 51No
© 2016. Whilst every care has been taken to prepare this map, GHD and NAMRIA make no representations or warranties about its accuracy, reliability, completeness or suitability for any particular purpose and cannot accept liability and responsibility of any kind
(whether in contract, tort or otherwise) for any expenses, losses, damages and/or costs (including indirect or consequential damage) which are or may be incurred by any party as a result of the map being inaccurate, incomplete or unsuitable in any way and for any reason.
EDC Burgos Wind Prower
ESIA for the Transmission Line and Jetty Project
Figure 1�✁✂
Job Number
Revision 0
71-12098
19 Jan 2016
Location of 42 km 115 kV TransmissionLine Route and Jetty Projects
Date
Data source: NAMRIA - Municipality, Road, River. Created by:jcmatic
11/F Alphaland Southgate Tower, 2258 Chino Roces Avenue corner EDSA, Makati City 1232 Philippines T 63 2 479 5600 F 63 2 479 5601 E [email protected] W www.ghd.com
Paper Size A3
!A Sampling Site
Burgos Wind Farm
!( Transmission Tower
Transmission Line
Highway
Road
Barangay
Municipality
![Page 55: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/55.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-17
Viewing Location 1: Kapurpurawan 4x4 Trail
View northeast from Kapurpurawan Trail View southwest from Kapurpurawan Trail
Table 14-11 VL1 – Kapurpuraw an 4x4 Trail
Landscape/Visual Element
Description
Location Viewing location is along Kapurpurawan Trail in between Tower BL-16 and 17.
Landform and significant landscape features
Mixed of rolling terrain and gently sloping hills with ridges to the east. It is dissected by the 2-lane concrete access road.
Vegetation Dense cover of woody shrubs reaching up to 5 m high. Roadside foliage is wild non-ornamental grasses common to rural areas.
Water West Philippine Sea located approximately 2 km to the north while Buraan River is 4 km to the south Obscure water channels are present in this area.
Land use and Infrastructure
The Kapurpurawan 4x4 Trail, running 3.52 km in length, serves as the access road of locals and tourists visiting the Kapurpurawan Rock Formation. It is perpendicular to Manila North Road. Entry to Kapurpurawan Trail is Tourism Board-controlled by way of an admission fee. The viewing location is just outside the wind farm site.
Visual context Views range from short to medium in distance due to the presence of dense vegetation cover in some views. Main view is the rolling terrain to the north. Views to the south are restricted on most part of the road. Views are experienced mainly by tourists travelling to Kapurpurawan Rock Formation.
Viewing Location 2: Barangay Ablan House Cluster
View south from Ablan House Cluster
![Page 56: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/56.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-18
Table 14-12 VL2 – Barangay Ablan House Cluster
Landscape/Visual Element
Description
Location The cluster of houses is located approximately 1 km south of the Buraan Bridge. The viewing location is roughly 500 m from the street entrance on Pan-Philippine or Maharlika Highway.
Landform and significant landscape features
Flat topography with prominent hills to the south at an approximate height of 110 masl; residential cluster sited at an approximate height of 8 masl Cellular sites/towers are visible on the ridges.
Vegetation Thickets of secondary growth trees and locally grown dragon fruit in the foreground and middle ground Dense cover of broad-leaved tree species in the background
Water West Philippine Sea and Buraan River located approximately 1 km to the north. Obscure water channels are present in this area.
Land use and Infrastructure
Cluster of 10-15 houses Classified as residential with agricultural land surrounding the house cluster.
Visual context Views range from short to medium distance and are lightly filtered/screened by backyard vegetation. Views are experienced mainly by residents of possibly 2-3 houses in a cluster of 10-15.
![Page 57: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/57.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-19
Viewing Location 3: Cape Bojeador Lighthouse
View east from Cape Bojeador Lighthouse
View southwest of Cape Bojeador Lighthouse
Table 14-13 VL3 – Cape Bojeador Lighthouse
Landscape/Visual Element
Description
Location Cape Bojeador Lighthouse is located approximately 40 km north of Laoag City and 1 km from the access road entrance on Manila North Road. The viewing location is on the pavilion deck of the lighthouse.
Landform and significant landscape features
Steep ridges to the east with elevation reaching up to 130 masl. The viewing location is at an approximate height of 118 masl. Cellular sites/towers are visible on the ridges.
Vegetation Dense cover of open forest, broad-leaved tree species and woody shrubs
Water West Philippine Sea to the west Obscure water channels are present in this area.
Land use and Infrastructure
Tourism-related activities Lighthouse is still operational.
Visual context Open view to the southeast of the verdant hills and towering structures Main view is the West Philippine Sea to the west. Views are experienced largely by tourists taking scenic photos of nature and of themselves.
![Page 58: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/58.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-20
Viewing Location 4: Bayog Elementary School
View east from Bayog Elementary School
Table 14-14 VL4 – Bayog Elementary School
Landscape/Visual Element
Description
Location Bayog Elementary School is situated along the Manila North Road, roughly 1.6 km southwest of Cape Bojeador Lighthouse. The viewing location is located on a field behind the school.
Landform and significant landscape features
Low, terraced topography in the foreground; steep ridges to the east with elevation reaching up to 130 masl. The viewing location is at an approximate height of 23 masl. Cellular sites/towers are visible on the ridges.
Vegetation Cleared open pasture/grazing land in the foreground Thickets of secondary growth trees in the middle ground Dense cover of broad-leaved tree species in the background
Water West Philippine Sea to the west Obscure water channels are present in this area.
Land use and Infrastructure
Agriculture-related activities with majority of the land cleared for grazing
Visual context Views range from medium to long distance. Views are composed of hills and open pasture with a few dwellings around the perimeter. Some residential properties within the vicinity may experience similar views. Views are experienced mainly by residents, school occupants, farmers and road users.
![Page 59: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/59.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-21
Viewing Location 5: Barangay Davila Field
View northeast from field adjacent salt vendors
View east from field adjacent salt vendors
Table 14-15 VL5 – Barangay Davila Salt Vendor Kiosks
Landscape/Visual Element
Description
Location The field along Manila North Road in Barangay Davila is approximately 15 km northwest of Pasuquin municipal proper. The viewing location is adjacent a salt vendor kiosk.
Landform and significant landscape features
Flat topography surrounding salt vendor kiosk/stalls; sloping hills to the northeast. The viewing location is at an approximate height of 32 masl. Cellular sites/towers are very visible in the foreground.
Vegetation Arable land in the foreground Thickets of secondary growth trees in the middle ground Dense cover of broad-leaved tree species in the background
Water West Philippine Sea to the west
Land use and Infrastructure
Agricultural land/Farmland Cellular site/tower in the immediate view
Visual context Views range from short to medium distance. Views are composed of hills, fields with low-growing vegetation and cleared land for pasture/grazing. Small dwellings within the vicinity may experience similar views. Views are experienced by salt vendors and customers, residents, farmers and road users.
![Page 60: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/60.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-22
Viewing Location 6: Pasuquin Sexy Beach
View east from Pasuquin Beach
View east from Pasuquin Beach
Table 14-16 VL6 – Pasuquin Beach
Landscape/Visual Element
Description
Location The beach, located in Barangay Dilavo, is approximately 10.6 km northwest of Pasuquin municipal proper. The viewing location is roughly 150 m west from Manila North Road entrance.
Landform and significant landscape features
Flat terrain with steep ridges to the east with elevation reaching up to 300 masl. The viewing location is at an approximate height of 10 masl. Cordillera Central is located in views to the distant east. Rocky coral beach to the west
Vegetation Cleared levelled land with scattered clumps of secondary growth trees Dense cover of broad-leaved tree species in the background
Water West Philippine Sea to the west Ephemeral creek to the southeast
Land use and Infrastructure
Farmland/Grassland Power poles along national highway
Visual context Views range from short to long distance. Views are composed of cleared sandy land and hills with varying density of vegetation cover. View of the sea especially during sunset causes Pasuquin beaches to be a significant local destination. Views are experienced primarily by road users.
![Page 61: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/61.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-23
Viewing Location 7: Barangay Dilavo Field
View north from Barangay Dilavo field
Table 14-17 VL7 – Barangay Dilavo Field
Landscape/Visual Element
Description
Location The field is approximately 10 km northwest of Pasuquin municipal proper. The viewing location is located in the middle of the field, about 250 m from Manila North Road.
Landform and significant landscape features
Flat terrain within the vicinity rising to high points in the east reaching up to 250 masl. The viewing location has an approximate height of 16 masl. Cordillera Central is located in views to the distant east.
Vegetation Cleared open pasture/grazing land in the foreground Thickets of secondary growth trees in the middle ground Dense cover of broad-leaved tree species in the background
Water West Philippine Sea to the west
Land use and Infrastructure
Farmland/Grassland
Visual context Views range from medium to long distance. Views are composed of fields of open pasture backdropped by the verdant hills. Views are experienced primarily by road users and farmers.
![Page 62: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/62.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-24
Viewing Location 8: Barangay Estancia Field
View northeast from Barangay Estancia field
Table 14-18 VL8 – Barangay Estancia Field
Landscape/Visual Element
Description
Location The field is approximately 6 km northwest of Pasuquin municipal proper. The viewing location is located in the middle of the field, about 200 m from Manila North Road.
Landform and significant landscape features
Flat paddy fields within the vicinity rising to high points in the east reaching up to 400 masl. The viewing location has an approximate height of 8 masl. Cordillera Central is located in views to the distant east.
Vegetation Arable land in the foreground Dense cover of broad-leaved tree species in the background
Water West Philippine Sea to the west Obscure water channels are present in this area.
Land use and Infrastructure
Agricultural land/Farmland/Grassland Sparse rural-residential properties along east perimeter
Visual context Views range from medium to long distance. Views are composed of vast paddy fields with open view of the vegetation-covered hills. Some residential properties within the vicinity, particularly to the east, may experience similar views. Views are experienced primarily by farmers.
![Page 63: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/63.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-25
Viewing Location 9: Barangay Salpad Field
View east from Barangay Salpad internal road
Table 14-19 VL9 – Barangay Salpad Field
Landscape/Visual Element
Description
Location The viewing location is at an internal road in Barangay Salpad, approximately 2.5 km north of Pasuquin municipal proper.
Landform and significant landscape features
Flat paddy fields within the vicinity rising to high points in the east reaching up to 300 masl. The viewing location has an approximate height of 22 masl.
Cordillera Central is located in views to the distant east.
Vegetation Arable land with sparse roadside shrubs
Dense cover of broad-leaved tree species in the background
Water West Philippine Sea to the west
Land use and Infrastructure
Agricultural land/Farmland/Grassland
Sparse rural-residential properties along east perimeter
Gravel road dissecting the paddy fields
Visual context Views range from medium to long distance. Views are composed of vast paddy fields with open view of the vegetation-covered hills.
Views are experienced primarily by farmers and road users.
Viewing Location 10: Barangay Poblacion 2 Field
View northeast from Barangay Poblacion 2 internal road
![Page 64: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/64.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-26
Table 14-20 VL10 – Barangay Poblacion 2 Field
Landscape/Visual Element
Description
Location The viewing location is at the northeastern edge of Poblacion 2, along the internal road, approximately 600 m east of Pasuquin municipal proper. It is situated about 200 m from the last house of the residential area.
Landform and significant landscape features
Flat paddy fields rising gently to the east reaching up to 40 masl. The viewing location is about 18 masl.
Vegetation Arable land with sparse roadside shrubs
Thickets of secondary growth trees in the middle ground
Water Ephemeral creek with riparian zones
Land use and Infrastructure
Residential
Agricultural land/Farmland/Grassland
Gravel road dissecting the paddy fields
Visual context Views range from short to medium distance.
Views from the residences are screened/filtered by dense vegetation.
Views are experienced primarily by farmers.
Viewing Location 11: Barangay Carusipan Field
View west from Barangay Carusipan internal road
Table 14-21 VL11 – Barangay Carusipan Field
Landscape/Visual Element
Description
Location Barangay Carusipan is approximately 4 km south of Pasuquin municipal proper.
The viewing location is along the internal road adjoining a residential property about 900 m east of the Manila North Road.
Landform and significant landscape features
Flat to the west with undulating topography on the eastern side. The viewing location is located approximately at 13 masl.
Vegetation Arable land with an edge of secondary growth trees in the horizon
Water -
Land use and Infrastructure
Residential
Agricultural land/Farmland/Grassland
Concrete road dissecting the paddy fields
![Page 65: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/65.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-27
Landscape/Visual Element
Description
Visual context Views range from medium to long distance. Views are composed of agricultural land and associated activities/infrastructure.
Views are experienced largely by farmers and residents of around 4-5 houses in a cluster of 15-20.
Viewing Location 12: Barangay Corocor Field
View southwest from Corocor internal road View northwest from Barangay Corocor
internal road
Table 14-22 VL12 – Barangay Corocor Field
Landscape/Visual Element
Description
Location Barangay Corocor is roughly 1.6 km west of Bacarra municipal proper.
The viewing location is along the internal road adjoining a residential property about 600 m east of the Manila North Road.
Landform and significant landscape features
Flat paddy fields rising gently to the south reaching up to 60masl. The viewing location has an approximate height of 16 masl.
Vegetation Arable land with clumps of mixed tall shrubs and herbaceous plants
Water Ephemeral creek with riparian zones
Land use and Infrastructure
Residential
Agricultural land/Farmland/Grassland
Concrete road dissecting the paddy fields
Visual context Views range from short to long distance.
Views are composed of agricultural land and associated activities/infrastructure.
View of the nearest tower (BL-121) is about 40 m from the viewing location.
Views are experienced by farmers and residents of around 2-3 houses in a cluster of 30-40.
![Page 66: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/66.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-28
Viewing Location 13: Bacarra River
View north from Bacarra River
View south from Bacarra River
Table 14-23 VL13 – Bacarra River
Landscape/Visual Element
Description
Location Bacarra River spans across at least 9 barangays in Bacarra municipality. It is located in the southern portion of the town and stretches from east to west terminating at the West Philippine Sea.
The viewing location is situated in the river floodplain in Barangay Sangil in the immediate northeast of tower BL-109. Location is not readily accessible by vehicles but is representative of potential views from residents along the river.
Landform and significant landscape features
Predominantly flat floodplain gradually rising up to the east reaching up to 100 masl. The viewing location is at an approximate height of 21 masl.
Vegetation Rough grassland with scattered clumps of mid-height woody shrubs and trees
Water Bacarra River
Land use and Infrastructure
Water body
Embankment to the north periphery of the floodplain
Visual context Views range from medium to long distance and are a mixture of grassland and gravel-covered plain.
Similar views may be experienced by residents of at least 4-5 houses located along the river.
Residential properties within the 500-800 m radius will experience screened/filtered views due to vegetation surrounding the properties.
![Page 67: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/67.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-29
Viewing Location 14: Barangay Salet-Bulangon
View northwest from Barangay Salet-Bulangon
Table 14-24 VL14 – Barangay Salet -Bulangon
Landscape/Visual Element
Description
Location Barangay Salet-Bulangon is located in the northeastern part of Laoag City, the capital of Ilocos Norte.
The viewing location is along the Manila North Road approximately 1.4 km north of Laoag City proper.
Landform and significant landscape features
Flat topography with gently sloping hills to the east and west reaching up to 90 masl. The viewing location has an approximate height of 22 masl.
Vegetation Arable land with sparse roadside shrubs
Water -
Land use and Infrastructure
Agricultural land/Farmland
Manila North Road to the west of the barangay
Power poles along national highway
Visual context Views range from short to medium distance. Views are primarily composed of see-through vegetation along the highway, arable land in the middle ground and dense foliage in the background.
Views are experienced mainly by road users.
Viewing Location 15: Jetty
View west from jetty View east from jetty
![Page 68: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/68.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-30
Table 14-25 VL15 - Jet ty
Landscape/Visual Element
Description
Location The jetty is located approximately 600 m northwest of the Buraan bridge.
The viewing location is along the access road approximately 200 m west of the jetty.
Landform and significant landscape features
Flat rocky coral
The viewing location is approximately 15 masl.
Vegetation Abundant growth of mangrove on the littoral zone with masses of bantigue (famously called as “bonsai”) in the upper region of the splash zone.
Water West Philippine Sea to the west
Land use and Infrastructure
Access road
Visual context Views range from short to medium distance.
Views of the jetty along the Manila North road entrance is filtered/screened by roadside vegetation.
Views are primarily experienced by fishermen, workers and staff using the jetty.
14.4 Impact Assessment
14.4.1 Introduct ion
The landscape and visual impacts of the operation of the transmission line and jetty are
considered within the context of the sensitivity of the surrounding visual environment and the
potential for viewing of the areas that have had changes to their visual outlook. The assessment
of the impacts for this project focuses only on the visibility of the project during the operation
phase.
The key visible components that affect the landscape and visual amenity throughout the
operation phase are the transmission towers. Maintenance access roads also present impacts
predominantly in areas where the towers are situated on top of the hills.
Impacts on selected viewing locations identified in Figure 15-2 and subsequently described on
Section 14.3.2 have been assessed for the operational phase in the following sections. These
locations are taken to represent landscape and visual issues within the study area.
This assessment should be read as a representation of the various effects that are visible at
different publicly accessible locations and not a summary of every landscape and visual impact
associated with the operation of the transmission line and jetty.
14.4.2 Landscape Impact Assessment
Table 14-26 to Table 14-28 identifies the sensitivity of each of the LCUs described above, the
magnitude of impacts on each receptor, and the subsequent significance of impacts on these
landscape receptors. The definitions of the different ratings for magnitude of impact and
significance of impacts are detailed in Table 14-3 and Table 14-7 respectively.
![Page 69: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/69.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-31
Table 14-26 LCU1 Impact Assessment
LCU LCU1 – Forested Landscape
Location and views These areas comprise the Barangays of Saoit, Poblacion, Ablan
Sarat, Bayog, and Paayas in the town of Burgos as well as Barangays
Davila and Dilavo in Pasuquin, Barangay Sangil in Bacarra and
Barangay no. 59-B Dibua North and 55-C Vira in Laoag City.
Visible Elements Transmission towers
Steel Poles
Discussion The landscape elements in these areas are highly valued and are
highly sensitive to change.
The addition of towers in these areas creates a significant disruption
in the landscape character as these towers are considerably massive.
In some locations, towers are located very close to the road while
others are highly visible on the ridges. Also, there are areas where
construction-based cuts and access road to the towers are still evident
in the landscape.
Most of the areas where these towers are located have pre-existing
cellular sites/towers and power poles that are now considered part of
the landscape. Their presence has rendered the landscape receptive
to other elements.
Landscape Sensitivity As these areas are regarded locally, the overall value of this LCU is
considered to be high and has a low capacity to accommodate
change.
Magnitude of Impact It is assessed that the magnitude of impact is small in approximately
80% of this LCU. Moderate impact on the remaining 20%.
Significance of Impact Using the matrix (Table 14-7), the impacts are assessed to be ranging
from moderate to high significance.
Table 14-27 LCU2 Impact Assessment
LCU LCU2 – Agricultural/Rural Landscape
Location and views The areas defined as Agricultural/Rural Landscape are located in the
Barangay of Bobon in the town of Burgos, Barangays Caruan,
Sulongan, Estancia, Susugaen, Salpad, Nagsanga, Nalvo, Sulbec,
Pragata, San Juan, Poblacion 1 to 4, Puyupuan, Batuli, Naglicuan,
Ngabangab, Binsang and Carusipan in Pasuquin. Also included are
the Barangays of Cadaratan, Pungto, Cabusligan, Pasngal,
Cabulalaan, Corocor, Cabaruan, Sangil, and Pasiocan in the town of
Bacarra.
Visible Elements Transmission towers
![Page 70: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/70.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-32
Discussion The landscape elements, particularly the continuity, form and scale of
the vegetation within the area provide important value to the local
character and its sense of place.
The introduction of towers in these areas creates a small
imperceptible disruption in the landscape character. Towers are
predominantly located to the west of the study area where they are set
against the hills rendering them unnoticeable.
Landscape Sensitivity The overall value of this LCU is considered to be medium and has a
low capacity to accommodate change.
Magnitude of Impact It is assessed that the magnitude of impact is moderate.
Significance of Impact Impacts are of moderate significance.
Table 14-28 LCU3 Impact Assessment
LCU LCU2 – Built-up Landscape
Location and views These areas consist of the Barangays Poblacion 1 to 4 in the town of
Pasuquin, southern west of the study area. Bacarra municipal proper
is to the east and Laoag City to the south. Both are outside the study
area.
Visible Elements Transmission towers
Steel poles
Discussion The landscape elements in this LCU are primarily of urban quality. As
such, they are subjected to change.
Towers within these areas are hardly recognizable due to the
presence of cellular sites/towers, power poles and other utility
structures that are now considered part of the landscape. Their
presence has rendered the landscape receptive to other elements.
Landscape Sensitivity It therefore has low value and a medium to high capacity to
accommodate change.
Magnitude of Impact It is assessed that the magnitude of impact is moderate.
Significance of Impact Impacts are of minor significance.
14.4.3 Visual Impact Assessment
Assessment of visual impacts of the project on the identified representative viewing locations
described in section 14.3.2 has been assessed for operational phases of the project. The
impacts are addressed in the following sections. The definitions of the different ratings for
magnitude of impact and significance of impacts are detailed in Table 14-3 and Table 14-7
respectively.
![Page 71: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/71.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-33
Table 14-29 VL1 Impact Assessment
Viewing Location 1 Kapurpurawan 4X4
Trail
LCU LCU1 – Forested
Landscape
Grid Reference E 120° 38’ 13.48”
N 18° 31’ 32.8”
Direction of view Northeast
Southwest
Towers visible 4 nos. towers Distance to nearest tower
< 200 m
Location and views Located along Kapurpurawan Trail in between Tower BL-16 and 17
Views range from short to medium distance. The main view for this VL
is of the rolling terrain to the north.
Visible Elements Transmission towers
Steel Poles
Discussion This is the only road available to visitors of the Kapurpurawan Rock
formation, tourists and road users are the sensitive receptors.
The transmission towers are assessed to have a negative impact as
they reduce the existing landscape character. Impacts are assessed
to be long term but would be reduced over time as these elements
become part of the view.
Receptor Sensitivity &
Magnitude of Visual
Modification
Sensitive receptors are assessed to have low sensitivity due to short
term views but the magnitude of visual modification is deemed to be
large.
Significance of Impact Using the matrix (Table 14-7), the impacts are assessed to be of
moderate significance.
![Page 72: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/72.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-34
Table 14-30 VL2 Impact Assessment
Viewing Location 2 Barangay Ablan
House Cluster
LCU LCU2 –
Agricultural/Rural
Landscape
Grid Reference E 120° 36’ 39.99”
N 18° 31’ 23.8”
Direction of view South
Towers visible 4 nos. towers Distance to nearest
tower
< 200 m
Location and views Located approximately 1 km south of the Buraan Bridge, 500 m from
the street entrance on Manila North Road.
Views range from short to medium distance and are lightly
filtered/screened by backyard vegetation.
Visible Elements Transmission towers
Discussion From this location, some of the towers seem to disappear within the
landscape due to its varying topographical relief and the intervening
vegetation in the foreground.
Receptor Sensitivity &
Magnitude of Visual
Modification
Receptors are residents or occupants of this house cluster in this
barangay. The cluster has about 15 houses. Three of which are
considered to be the primary receptors as they are the ones closest to
the towers. Sensitivity of receptors is high as they have long viewing
periods.
Impact upon the visual amenity of sensitive receptors is moderate
during the operational phase.
Significance of Impact Impacts are of high significance.
![Page 73: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/73.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-35
Table 14-31 VL3 Impact Assessment
Viewing Location 3 Cape Bojeador
Lighthouse
LCU LCU1 – Forested
Landscape
Grid Reference E 120° 35’ 51.7914”
N 18° 30’ 43.524”
Direction of view East
Towers visible 3 nos. towers Distance to nearest
tower
< 400 m
Location and views Located approximately 40 km north of Laoag City and 1 km from the
access road entrance on Manila North Road. Viewing location is on
the pavilion deck of the lighthouse.
Open view to the southeast of the verdant hills and towering
structures. The main view is the West Philippine Sea to the west.
Visible Elements Transmission towers
Discussion Cape Bojeador Lighthouse is frequently visited by tourists and locals
as this is a famous destination in the region. From this location, the
towers are highly visible as they are situated on the ridges.
Construction-based cuts and access road to the towers are still
evident in the landscape.
The transmission towers are assessed to have a negative impact as
they reduce the existing landscape character. Impacts are assessed
to be long term but would be reduced over time as these elements
become part of the view.
Receptor Sensitivity &
Magnitude of Visual
Modification
Tourists are the primary receptors and are assessed to have high
sensitivity as they use this VL for photograph opportunities. The
magnitude of visual impact is moderate.
Significance of Impact Impacts are of high significance.
![Page 74: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/74.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-36
Table 14-32 VL4 Impact Assessment
Viewing Location 4 Bayog Elementary
School
LCU LCU1 – Forested
Landscape
Grid Reference E 120° 35’ 31.056
N 18° 30’ 32.9034”
Direction of view East
Towers visible 2 nos. towers Distance to nearest
tower
< 500 m
Location and views Located along the Manila North Road, roughly 1.6 km southwest of
Cape Bojeador Lighthouse. The viewing location is located in a field
behind the school.
Views range from medium to long distance. Views are composed of
hills and open pasture with a few dwellings around the perimeter.
Visible Elements Transmission towers
Cellular site/towers (by others)
Discussion From this viewing location, the towers are faintly noticeable albeit they
are situated on the ridges.
The transmission towers are assessed to have a negative impact as
they reduce the existing landscape character. Impacts are assessed
to be long term but would be reduced over time as these elements
become part of the view.
Receptor Sensitivity &
Magnitude of Visual
Modification
Sensitive receptors are residents, school occupants, farmers and road
users. All are assessed to have medium visual sensitivity as their
views are mildly affected and the period limited. The magnitude of
visual impact is moderate.
Significance of Impact Impacts are of moderate significance.
![Page 75: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/75.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-37
Table 14-33 VL5 Impact Assessment
Viewing Location 5 Barangay Davila Salt
Vendor Kiosks
LCU LCU1 – Forested
Landscape
Grid Reference E 120° 34’ 50.124”
N 18° 24’ 26.6754”
Direction of view Northeast
East
Towers visible 5 nos. towers Distance to nearest
tower
< 300 m
Location and views The field along Manila North Road in Barangay Davila is
approximately 15 km northwest of Pasuquin municipal proper. The
viewing location is adjacent a salt vendor kiosk.
Views range from short to medium distance. Views are composed of
hills, fields with low-growing vegetation and cleared land for
pasture/grazing.
Visible Elements Transmission towers
Discussion The towers are highly visible from this viewing location. Construction-
based cuts and tower footings are also evident in the landscape.
The transmission towers are assessed to have a negative impact as
they reduce the existing landscape character. Impacts are assessed
to be long term but would be reduced over time as these elements
become part of the view.
Receptor Sensitivity &
Magnitude of Visual
Modification
Sensitive receptors are salt vendors and customers, residents,
farmers and road users. Their viewing periods are short-termed as
they are more focussed on their work (salt vendors and farmers) or on
the purpose of their stop-over (customers). Sensitivity is assessed to
be medium. Magnitude of visual modification is moderate.
Significance of Impact Impacts are of moderate significance.
![Page 76: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/76.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-38
Table 14-34 VL6 Impact Assessment
Viewing Location 6 Pasuquin Sexy
Beach
LCU LCU1 – Forested
Landscape
Grid Reference E 120° 35’ 32.1714”
N 18° 24’ 56.556”
Direction of view East
Towers visible 7 nos. towers Distance to nearest
tower
< 600 m
Location and views The beach, located in Barangay Dilavo, is approximately 10.6 km
northwest of Pasuquin municipal proper. The viewing location is
roughly 150 m west from Manila North Road entrance.
Views range from short to long distance. Views are composed of
cleared sandy land and hills with varying density of vegetation cover.
Visible Elements Transmission towers
Discussion The visual amenity from this viewing location is mildly affected due to
the presence of intervening vegetation in the foreground and middle
ground. At the same time, the utilities in the foreground stretching
from north to south of this viewing location renders an obstructed view
of the towers.
The transmission towers are assessed to have a neutral quality of
impact as they blend with the existing landscape character.
Receptor Sensitivity &
Magnitude of Visual
Modification
Tourists who frequent the beach, fishermen and road users are the
sensitive receptors. However, all have varying sensitivities. Tourists
who have longer viewing period are assessed to have high sensitivity.
Fishermen and road users, on the other hand, have medium and low
sensitivity.
The magnitude of visual impact is small.
Significance of Impact Impacts range from moderate significance to no significance.
![Page 77: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/77.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-39
Table 14-35 VL7 Impact Assessment
Viewing Location 7 Barangay Dilavo
Field
LCU LCU2 –
Agricultural/Rural
Landscape
Grid Reference E 120° 35’ 50.6394”
N 18° 24’ 43.8834”
Direction of view North
Towers visible 5 nos. towers Distance to nearest
tower
< 300 m
Location and views The field is approximately 10 km northwest of Pasuquin municipal
proper. The viewing location is located in the middle of the field,
approximately 250 m from Manila North Road.
Views range from medium to long distance. Views are composed of
fields of open pasture backdropped by the verdant hills.
Visible Elements Transmission towers
Discussion The towers in this viewing location are highly visible as most of them
are situated on rising elevations and there is no intervening vegetation
to buffer the view. Construction-based cuts are also evident in the
landscape.
The transmission towers are assessed to have a negative impact as
they reduce the existing landscape character. Impacts are assessed
to be long term but would be reduced over time as these elements
become part of the view.
Receptor Sensitivity &
Magnitude of Visual
Modification
Sensitive receptors are farmers and road users. Farmers’ views are
intermittent as they are more focussed on their work while road users
who are just passing through have short term views. Sensitivity is
assessed to be medium to low. Magnitude of visual modification is
moderate.
Significance of Impact Impacts are from moderate significance to minor significance.
![Page 78: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/78.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-40
Table 14-36 VL8 Impact Assessment
Viewing Location 8 Barangay Estancia
Field
LCU LCU2 –
Agricultural/Rural
Landscape
Grid Reference E 120° 36’ 4.8954”
N 18° 22’ 45.6594”
Direction of view Northeast
Towers visible 15 nos. towers Distance to nearest
tower
< 300 m
Location and views The field is approximately 6 km northwest of Pasuquin municipal
proper. The viewing location is located in the middle of the field,
approximately 200 m from Manila North Road.
Views range from medium to long distance. Views are composed of
vast paddy fields with open view of the vegetation-covered hills.
Visible Elements Transmission towers
Discussion The visual amenity from this viewing location is fairly altered by the
towers. The openness of the views is now constrained.
The transmission towers are assessed to have a negative impact as
they reduce the existing landscape character. Impacts are assessed
to be long term but would be reduced over time as these elements
become part of the view.
Receptor Sensitivity &
Magnitude of Visual
Modification
Sensitive receptors are farmers and residents. Both are assessed to
have medium sensitivity. Magnitude of visual impact is moderate.
Significance of Impact Impacts are of moderate significance.
![Page 79: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/79.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-41
Table 14-37 VL9 Impact Assessment
Viewing Location 9 Barangay Salpad
Field
LCU LCU2 –
Agricultural/Rural
Landscape
Grid Reference E 120° 36’ 54.288”
N 18° 21’ 19.4034”
Direction of view East
Towers visible 7 nos. towers Distance to nearest
tower
< 100 m
Location and views The viewing location is at an internal road in Barangay Salpad,
approximately 2.5 km north of Pasuquin municipal proper.
Views range from medium to long distance. Views are composed of
vast paddy fields with open view of the vegetation-covered hills.
Visible Elements Transmission towers
Discussion From this viewing location, the towers are highly perceptible as they
are located in the middle of the fields.
The transmission towers are assessed to have a negative impact as
they reduce the existing landscape character. Impacts are assessed
to be long term but would be reduced over time as these elements
become part of the view.
Receptor Sensitivity &
Magnitude of Visual
Modification
Sensitive receptors are farmers and road users. Farmers’ views are
intermittent as they are more focussed on their work while road users
who are just passing through have short term views. Sensitivity is
assessed to be medium to low. Magnitude of visual modification is
moderate.
Significance of Impact Impacts range from moderate significance to minor significance.
![Page 80: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/80.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-42
Table 14-38 VL10 Impact Assessment
Viewing Location 10 Barangay Poblacion
2 Field
LCU LCU3 – Built-up
Landscape
Grid Reference E 120° 37’ 23.556”
N 18° 19’ 59.268”
Direction of view Northeast
Towers visible 3 nos. towers Distance to nearest
tower
< 200 m
Location and views The viewing location is at the northeastern edge of Poblacion 2, along
the internal road, approximately 600 m east of Pasuquin municipal
proper. It is situated about 200 m from the last house of the residential
area.
Views range from short to medium distance.
Visible Elements Transmission towers
Discussion The visual amenity from this viewing location is affected as towers are
highly visible.
The transmission towers are assessed to have a negative impact as
they reduce the existing landscape character. Impacts are assessed
to be long term but would be reduced over time as these elements
become part of the view.
Receptor Sensitivity &
Magnitude of Visual
Modification
Sensitive receptors are farmers and road users. Both are assessed to
have medium and low sensitivity.
However, since this is located within LCU3, it is important to note that
residents are also considered as sensitive receptors. Albeit their
proximity to the project only a few occupiers of residential properties
are affected. They are assessed to have medium sensitivity as their
views are screened by backyard vegetation. The magnitude of visual
impact is moderate.
Significance of Impact Impacts range from moderate significance to minor significance.
![Page 81: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/81.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-43
Table 14-39 VL11 Impact Assessment
Viewing Location 11 Barangay Carusipan
Field
LCU LCU2 –
Agricultural/Rural
Landscape
Grid Reference E 120° 36' 30.276"
N 18° 18' 0.4314"
Direction of view West
Towers visible 4 nos. towers Distance to nearest
tower
< 400 m
Location and views Barangay Carusipan is approximately 4 km south of Pasuquin
municipal proper. The viewing location is along the internal road
adjoining a residential property about 900 m east of the Manila North
Road.
Views range from medium to long distance. Views are composed of
agricultural land and associated activities/infrastructure.
Visible Elements Transmission towers
Discussion The towers in this viewing location are highly visible as they are
located in the middle of the fields.
The transmission towers are assessed to have a negative impact as
they reduce the existing landscape character. Impacts are assessed
to be long term but would be reduced over time as these elements
become part of the view.
Receptor Sensitivity &
Magnitude of Visual
Modification
Sensitive receptors are residents of around 4-5 houses in a cluster of
15-20. Farmers and road users are also considered sensitive
receptors. All have varying sensitivities. Residents who have longer
viewing period are assessed to have high sensitivity. Farmers and
road users, on the other hand, have medium and low sensitivity. The
magnitude of visual impact is moderate.
Significance of Impact Impacts range from high significance to minor significance.
![Page 82: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/82.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-44
Table 14-40 VL12 Impact Assessment
Viewing Location 12 Barangay Corocor
Field
LCU LCU2 –
Agricultural/Rural
Landscape
Grid Reference E 120° 35' 47.5794"
N 18° 16' 23.8434"
Direction of view Northwest
Southwest
Towers visible 5 nos. towers Distance to nearest
tower
< 100 m
Location and views Barangay Corocor is roughly 1.6 km west of Bacarra municipal proper.
The viewing location is along the internal road adjoining a residential
property about 600 m east of the Manila North Road.
Views range from short to long distance. Views are composed of
agricultural land and associated activities/infrastructure.
Visible Elements Transmission towers
Discussion One of the towers from this viewing location is extremely close to the
houses. The visual amenity is substantially affected. Tower footings
are also highly visible.
The transmission towers are assessed to have a negative impact as
they reduce the existing landscape character. Impacts are assessed
to be long term but would be reduced over time as these elements
become part of the view.
Receptor Sensitivity &
Magnitude of Visual
Modification
Sensitive receptors are residents of around 2-3 houses in a cluster of
30-40. Farmers and road users are also considered sensitive
receptors. All have varying sensitivities. Residents who have longer
viewing period are assessed to have high sensitivity. Farmers and
road users, on the other hand, have medium and low sensitivity. The
magnitude of visual impact is large.
Significance of Impact Impacts range from major significance to moderate significance.
![Page 83: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/83.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-45
Table 14-41 VL13 Impact Assessment
Viewing Location 13 Bacarra River LCU LCU2 –
Agricultural/Rural
Landscape
Grid Reference E 120° 35' 29.472"
N 18° 15' 0.1434"
Direction of view North
South
Towers visible 8 nos. towers Distance to nearest
tower
< 400 m
Location and views Bacarra River is located in the southern portion of the town and
stretches from east to west terminating at the West Philippine Sea.
The viewing location is situated in the river floodplain in Barangay
Sangil in the immediate northeast of tower BL-109.
Views range from medium to long distance and are a mixture of
grassland and gravel-covered plain.
Visible Elements Transmission towers
Discussion The alignment of the towers on a flat terrain renders the visual
amenity of the receptors to be disrupted.
The transmission towers are assessed to have a negative impact as
they reduce the existing landscape character. Impacts are assessed
to be long term but would be reduced over time as these elements
become part of the view.
Receptor Sensitivity &
Magnitude of Visual
Modification
Though this viewing location is not readily accessible, the receptors
whose visual amenity is considered are the residents along the river.
They are assessed to have medium sensitivity. They have long
viewing periods but views are generally filtered by vegetation.
Magnitude of visual modification is moderate.
Significance of Impact Impacts are of moderate significance.
![Page 84: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/84.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-46
Table 14-42 VL14 Impact Assessment
Viewing Location 14 Barangay Salet-
Bulangon
LCU LCU3 – Built-up
Landscape
Grid Reference E 120° 36' 13.824"
N 18° 12' 51.4434"
Direction of view Northwest
Towers visible 3 nos. towers Distance to nearest
tower
< 100 m
Location and views Barangay Salet-Bulangon is located in the northeastern part of Laoag
City, the capital city of Ilocos Norte. The viewing location is along the
Manila North Road approximately 1.4 km north of Laoag City proper.
Views range from short to medium distance. Views are primarily
composed of see-through vegetation along the highway, arable land in
the middle ground and dense foliage in the background.
Visible Elements Transmission towers
Discussion The towers seen from this viewing location is nearly imperceptible due
to the presence of intervening vegetation in the foreground and middle
ground. At the same time, the utilities in the foreground stretching
from north to south of this viewing location renders an obstructed view
of the towers.
The transmission towers are assessed to have a neutral quality of
impact as they blend with the existing landscape character.
Receptor Sensitivity &
Magnitude of Visual
Modification
Sensitive receptors are primarily the road users. They are assessed to
have low sensitivity due to the length of their viewing period.
Though this viewing location is located within LCU3 where residents
and city workers are the key receptors, their sensitivity is considered
low as their view of the towers are very limited. Magnitude of visual
impact is small.
Significance of Impact Impacts are not significant.
![Page 85: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/85.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-47
Table 14-43 VL15 Impact Assessment
Viewing Location 14 Jetty LCU LCU1 – Forested
Landscape
Grid Reference E 120° 36’ 46.1"
N 18° 31' 59.7"
Direction of view East
West
Location and views The jetty is located approximately 600 m northwest of the Buraan
bridge. The viewing location is along the access road approximately
200 m west of the jetty.
Views range from short to medium distance. Views of the jetty along
the Manila North road entrance is filtered/screened by roadside
vegetation.
Visible Elements Jetty
Discussion The visual amenity to the jetty area is constrained by roadside
vegetation. At the same time, its distance from readily accessible land
viewpoints does not allow for considerable views.
The jetty is assessed to have a negative impact as it reduces the
existing landscape character. Impacts are assessed to be long term
but would be reduced over time as these elements become part of the
view.
Receptor Sensitivity &
Magnitude of Visual
Modification
Sensitive receptors are primarily fishermen, workers and staff. They
are assessed to have medium sensitivity. Their viewing periods are
short-termed as they are more focussed on their work. Magnitude of
visual impact is moderate.
Significance of Impact Impacts are of moderate significance.
14.5 Mit igat ion
The aim of this section is to identify mitigation measures that will reduce and/or manage
adverse impacts of the operational phase of the project on the landscape character and visual
amenity.
Due to the nature of transmission lines being highly visible, these elements are not easily
screened. Their function dictates that they are located on exposed sites. In this case, it helps
that the towers are located in varying topographical relief and thereby rendering some impacts
to be screened from view.
Operation phase mitigation measures are:
� Revegetation of quarried/excavated areas to reduce significant contrast in the visual
landscape
� Screening of tower footings by planting endemic species in the area
� Coordination with the local government of the concerned barangay and municipality and
provision of assistance in planting and maintenance of trees and other vegetation
screening along the Manila North Road
![Page 86: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/86.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-48
14.6 Conclusions and Summary of Findings
The assessment in this report is based on the maximum impacts of the constructed and now
operational transmission line and jetty.
Key views of the project occur within the 1 km buffer (refer to Figure 14-2). The visual impacts
are described in Section 14.4.3 with corresponding images on Section 14.3.2. These have been
assessed and range from not significant to high significance. There are open views of the
project from numerous stretches of the road. Generally, due to the low nature of the road and
with its intervening planting verge as well as the varying topographical relief, views are filtered in
some locations.
Viewing location 1 (VL1) indicates that the areas within its vicinity experience the maximum
change in views as a result of the towers’ proximity to the road, low nature of intervening
vegetation and sloping hills where the towers are situated.
Viewing locations, where the towers are visible on the ridges and where there is no foreground
vegetation, renders the receptors’ visual amenity to have been affected but significance of
impact is generally moderate.
On viewing locations where towers are located on fields, due to flat topography, the visual
impact ranges from moderate to large.
The project has a reduced impact on viewing locations where the vicinity is a populated area.
This is primarily because of the intervening vegetation.
Due to the region’s favorable location for wind farm projects where the construction of
transmission line is necessary for the conveyance of the power generated by the wind turbines,
the presence of these power –associated elements are not in absolute conflict with the
landscape character.
Landscape is classified into three character units. The impacts of the transmission line and jetty
on the landscape are described in Section 14.4.2. These have been assessed and range from
minor to high significance.
The number of overhead power lines and their strong vertical form dominates the landscape
when viewed from a close distance. However, existing cellular sites/towers and other utility-
related elements render the landscape receptive to other elements.
Table 14-44 Summary of Impacts
LCU Magnitude of Impact Sensitivity Significance of Impact
LCU1 – Forested Landscape
Small to moderate High Moderate to High
LCU2 – Agricultural/Rural Landscape
Moderate Medium Moderate
LCU3 – Built-up Landscape
Moderate Low Minor
VL1: Kapurpurawan 4x4 Trail
Large Low Moderate
VL2: Barangay Ablan House Cluster
Moderate High High
VL3: Cape Bojeador Lighthouse
Moderate High High
VL4: Bayog Elementary School
Moderate Medium Moderate
![Page 87: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/87.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 14-49
LCU Magnitude of Impact Sensitivity Significance of Impact
VL5: Barangay Davila Field
Moderate Medium Moderate
VL6: Pasuquin Beach Small High to Low Moderate to not significant
VL7: Barangay Dilavo Field
Moderate Medium to Low Moderate to minor
VL8: Barangay Estancia Field
Moderate Medium Moderate
VL9: Barangay Salpad Field
Moderate Medium to Low Moderate to minor
VL10: Barangay Poblacion 2 Field
Moderate Medium to Low Moderate to minor
VL11: Barangay Carusipan Field
Moderate High to Low High to minor
VL12: Barangay Corocor Field
Large High to Low Major to moderate
VL13: Bacarra River Moderate Medium Moderate
VL14: Barangay Salet-Bulangon
Small Low Not significant
VL15: Jetty Moderate Medium Moderate
![Page 88: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/88.jpg)
![Page 89: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/89.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/01010/00 | i
Table of contents
1. Introduction................................................................................................................................. 1-0
2. Project Description ..................................................................................................................... 2-0
3. Assessment Methodology .......................................................................................................... 3-0
4. Land Use Assessment ............................................................................................................... 4-0
5. Noise and Vibration Assessment ............................................................................................... 5-0
6. Biodiversity and Conservation ................................................................................................... 6-0
7. Marine Ecology and Seawater Quality ....................................................................................... 7-0
8. Water and Drainage Assessment .............................................................................................. 8-0
9. Soil and Groundwater Contamination Assessment ................................................................... 9-0
10. Air Quality Assessment ............................................................................................................ 10-0
11. Heritage and Cultural Assessment .......................................................................................... 11-0
12. Traffic, Access and Safety Assessment ................................................................................... 12-0
13. Socio-Economic Assessment .................................................................................................. 13-0
14. Landscape and Visual Impact Assessment ............................................................................. 14-0
15. Risk Assessment ...................................................................................................................... 15-1
15.1 Introduction .................................................................................................................... 15-1
15.2 Assessment Methodology .............................................................................................. 15-1
15.3 Risk Assessment Workshop .......................................................................................... 15-7
15.4 Result of the Risk Assessment ...................................................................................... 15-9
15.5 Risk Ranking ................................................................................................................ 15-15
15.6 Management of Risks .................................................................................................. 15-17
Table index
Table 15-1 Estimation of likelihood .................................................................................................. 15-3
Table 15-2 Consequence descriptors .............................................................................................. 15-4
Table 15-3 Risk assessment matrix ................................................................................................. 15-6
Table 15-4 Risk assessment workshop participants ........................................................................ 15-8
Table 15-5 Document review ........................................................................................................... 15-8
Table 15-6 List of issues and risks identified during the operation and maintenance of
Transmission Line and Jetty Projects ............................................................................ 15-9
Table 15-7 Extreme and high risks identified during the operation of Transmission Line
Project .......................................................................................................................... 15-10
Table 15-8 Risks identified during the operation and maintenance of the Burgos
Transmission Line Project ........................................................................................... 15-11
![Page 90: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/90.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/01010/00 | ii
Table 15-9 High risks identified during the operation of Jetty Project............................................ 15-13
Table 15-10 Risks identified during the operation and maintenance of the Burgos Jetty
Project .......................................................................................................................... 15-14
Table 15-11 Risk ranking ................................................................................................................. 15-15
Figure index
Figure 15-1 Risk assessment process .............................................................................................. 15-2
![Page 91: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/91.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/01010/00 | 15-1
15. Risk Assessment
15.1 Introduction
This section presents the risk assessment conducted for the Burgos Transmission Line and
Jetty Projects. Risk assessment was undertaken with the objective of identifying any adverse
impact associated with the operation and maintenance activities of the Transmission Line and
Jetty Projects. Risk management measures or mitigating measures were also identified to
reduce the risk to an acceptable level.
Risk assessment is a process of identifying risk events (hazard/threat, fault/failure/cause and
impacts/consequences); evaluating likelihood (probability and exposure) and consequences of
positive or negative environmental effect that may occur as a result of exposure to the hazards
or threat.
Consistent with the definition of AS/NZS ISO 31000:2009, risk in this document is defined as
“the effect of uncertainty on objectives”. AS/NZS ISO 31000 also provides the following
additional notes to assist in understanding “risk”:
� Risk can be characterised as reference to potential events and consequences, or a
combination of these, and
� Risk is often expressed as a combination of the consequence of an event and the
associated likelihood of occurrence.
15.2 Assessment Methodology
The risk assessment workshop for the Burgos Transmission Line and Jetty Projects was
conducted on 9 January 2015 at GHD office in Makati. The workshop aims to understand the
inherent and potential risk associated with the operation and maintenance of the Transmission
Line and Jetty Projects. The process used during the workshop was consistent with the general
risk management process outlined in the standard AS/NZS 3100:2009 Risk Management
Principles and Guidelines. The following were steps were undertaken during the workshop:
� Identify the risks associated with project related activities during the operation and
maintenance phase of the project.
� Identify the individual and collective risks on the receiving environment associated with
the Transmission Line and Jetty Projects based on recognised standards and review of
related documents from the Client and other secondary sources, in parallel with the
knowledge of GHD staff involved in the operation and maintenance of project facilities
� Provide consistent approach and risk rating system across the various technical study
areas to enable a comparative assessment of risk across all study areas
� Identify residual risks rankings for the specific activities assessed based on existing
mitigation measures in design or standard operation
� Identify risks requiring additional mitigation measures to reduce their residual risk rating to
levels that are acceptable (i.e. tolerable and as low as reasonably practicable – ALARP)
The workshop resulted in the identification of several risks including several “extreme risks”,
such risks require significant resources to ensure that the level or residual risk is reduced to an
acceptable level at all times.
![Page 92: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/92.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/01010/00 | 15-2
15.2.1 Risk Management Process
The Australian and New Zealand AS/NZS ISO 31000:2009 Risk Management Principles and
Guidelines was used as basis in assessing the environmental/ecological risks associated with
the operation and maintenance of the Burgos Transmission Line and Jetty Projects. The risk
assessment flow process prescribed by AS/NZS ISO 31000:2009 and presented in Figure 15-1
was adopted during the risk assessment workshop.
Figure 15-1 Risk assessment process
Source: AS/NXS ISO 31000:2009
15.2.2 Risk Context
Risk assessment undertaken for the Project address the activities associated with the operation
and maintenance of the Transmission Line and Jetty Projects. A detailed description of the
project components are provided in Section 2 (Project Description).
15.2.3 Risk Ident ificat ion
Risk identification is a systematic process of identification of potential sources of risks, areas of
impacts, events and their causes and potential consequences. During the workshop, operation
and maintenance activities were listed and discussions were held between workshop
participants about design, historical events and potential incidents that may occur. The Risk
Assessment Team’s knowledge of these types of incidents was central to the determination of
likelihood.
Once potential risk activity (hazard/threat) is identified, an assessment is undertaken to
determine what aspects of that activity could result in an impact to the following:
� Health and safety
� Environment (land, water, air and biodiversity)
� People (socio-economic, public health and worker’s safety)
![Page 93: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/93.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/01010/00 | 15-3
� Legal
� Reputation
� Visual impact
15.2.4 Risk Analysis
Identified risks are then assessed to their probability of occurrence (likelihood) and the potential
severity of effects (consequence). These quantities can be either simple to measure or have to
be assumed. For risks that have to be analysed based on assumed information, best educated
guesses are applied in the assessment process.
Likelihood (Probability)
Likelihood is a way of expressing knowledge or belief that an event or incident will occur or has
occurred. Table 15-1 was used to estimate the frequency of potential events occurring.
Gross Likelihood
Gross likelihood is the rating of the maximum probability of an event or incident occurring in the
absence of controls in place. This should be an estimate of the frequency the activity takes
place and the inherent failure probability. This assessment is subjective in nature (to an extent).
Where there are no known controls, gross likelihood was applied in assessing base risk levels.
Table 15-1 Est imat ion of likelihood
Level Descriptor Description Measure (example) Probability
5 Almost certain
The event will occur in most circumstances
Once per week >90%
4 Likely The event would occur in recurrent intervals
Once per month 51–90%
3 Possible The event occur on an irregular basis
Once per year 21–50%
2 Rare The event would be an uncommon occurrence and would occur in remote circumstances
Once per 5-10 years
10–20%
1 Unlikely The event may occur in exceptional circumstances. The event is not likely to occur in this location.
Once within 10 years
<10%
Consequence
Consequence is something that is logically or naturally follows from an action or condition.
Hence it is the relationship of a result to its cause or a logical conclusion. The risk assessment
team was tasked to determine the potential consequence (and severity) of the identified risk.
Consequence descriptors, categorised from minor to catastrophic using the definitions in Table
15-2 were used in identifying the consequence of risk for the Burgos Transmission Line and
Jetty Projects.
![Page 94: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/94.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/01010/00 | 15-4
Table 15-2 Consequence descriptors
Category A B C D E
Insignificant Minor Moderate Major Catastrophic
Health and Safety
Low level short-term inconvenience or symptoms. No measurable physical effects. No medical treatment.
Reversible disability/impairment and/or medical treatment injuries requiring hospitalisation.
Moderate irreversible disability or impairment (<30%) to one or more persons.
Single fatality and/or severe irreversible disability or impairment (>30%) to one or more persons.
Short or long term health effects leading to multiple fatalities, or significant irreversible human health effects to >50 persons.
Environmental Effects
No lasting effect. Low-level impacts on biological or physical environment. Limited damage to minimal area of low significance.
Minor effects on biological or physical environment. Minor short-medium term damage to small area of limited significance.
Moderate effects on biological or physical environment (air, water) but not affecting ecosystem function. Moderate short-medium term widespread impacts (e.g. Significant land disturbance).
Serious environmental effects with some impairment of ecosystem function. Relatively widespread medium-long term impacts to the community.
Very serious environmental effects with impairment of ecosystem function. Long term, widespread effects on significant environment (e.g. unique habitat, river systems and community land).
Social and cultural heritage
Low-level social or cultural impacts. Low-level repairable damage to commonplace structures.
Minor medium-term social impacts on local population. Minor damage to structures/items of some significance. Minor infringement of cultural heritage. Mostly repairable.
Ongoing social issues. Permanent damage to structures/items of cultural significance, or infringement of cultural heritage/sacred locations.
Ongoing serious social issues. Significant damage to structures/items of cultural significance, or significant infringement and disregard of cultural heritage.
Very serious widespread social impacts. Irreparable damage to highly valued structures/ items/ locations of cultural significance. Highly offensive infringements of cultural heritage.
Legal Low-level legal issue. On the spot fine. Technical non-compliance. Prosecution unlikely.
Minor legal issues, non-compliances and breaches of regulation. Minor prosecution or litigation possible.
Serious breach of regulation with investigation or report to authority with prosecution and/or moderate fine possible.
Major breach of regulation with potential major fine and/or investigation and prosecution by authority. Major litigation.
Investigation by authority with significant prosecution and fines. Very serious litigation, including class actions.
![Page 95: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/95.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/01010/00 | 15-5
Category A B C D E
Reputation Public concern restricted to local complaints (Barangay Level). Ongoing scrutiny / attention from regulator.
Minor, adverse local public or media attention and complaints (Municipal Level). Significant hardship from regulator. Reputation is adversely affected with a small number of site-focused people.
Attention from media and/or heightened concern by local community (REGIONAL level). Criticism by NGOs. Significant difficulties in gaining approvals. Environmental credentials moderately affected.
Significant adverse national media / public/ NGO attention. Project approval seriously threatened. Environment / management credentials are significantly tarnished.
Serious public or media outcry (international coverage). Damaging NGO campaign. Licence to operate threatened. Reputation severely tarnished. Share price may be affected.
Tourism No effect on tourism activities.
Increase in tourism activities by 10%
Increase in tourism activities by 25%
Increase in tourism activities by 50%
Increase in tourism activities by 100%
Visual Impact No effect on existing visual amenity.
The proposed structures constitute only a minor component in the wider view, which might be missed by the casual observer or receptor. Awareness of the proposed structures will not have a marked effect on the overall quality of the view.
The proposed structures form a visible and recognizable new element within the overall scene and may readily be noticed by the observer or receptor
The proposed structures become the dominant feature of the scene to which other elements become subordinate. They significantly affect and change the overall quality of the landscape
The proposed structures become a dominant feature of the scene to which other elements become subordinate. They permanently affect and change the overall quality of the landscape
![Page 96: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/96.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/01010/00 | 15-6
15.2.5 Risk Evaluat ion
Risk evaluation is undertaken by comparing the estimated levels against the pre-established
criteria. The overall level of risk was determined by combining the likelihood of a risk event and
the consequence. The assigned level of risk takes into account the safeguards or controls that
will be implemented, identified as “mitigation measures” for adverse effects or “enhancement
measures” for positive effects.
Risk Index Matrix
The impact of the risk event is assessed on a scale of A to E, where A and E represent the
minimum and maximum possible impact of an occurrence of risk.
The likelihood or probability of occurrence is likewise assessed on a scale from 1 to 5, where 1
represents a low probability of the risk event actually occurring while 5 represents a 100 percent
probability of occurrence. The overall risk assessment is then Low, Medium, High and
Critical/Extreme.
Table 15-3 Risk assessment matrix
Risk Assessment Matrix
Consequence
Minor Medium Serious Major Catastrophic
A B C D E
Lik
elih
ood
Almost Certain High (H) High (H) Extreme (E) Extreme (E) Extreme (E)
Likely Moderate (M) High (H) High (H) Extreme (E) Extreme (E)
Occasional Low (L) Moderate (M) High (H) Extreme (E) Extreme (E)
Rare Low (L) Low (L) Moderate (M) High (H) Extreme (E)
Unlikely Low (L) Low (L) Moderate (M) High (H) High (H)
Net or Residual Risk
Residual risk is the remaining risk once the controls (mitigation measures) have been put in
place. Additional mitigating or enhancement measures were identified to reduce the level of the
residual risks to an “acceptable” or tolerable level. The acceptability or residual risk considered
the opinion of technical experts as well as standards, industry practice, availability of mitigation
measures and cost-benefit analysis.
Risk Categories
The following risk categories were assessed during the workshop.
� Health and Safety
� Environmental
� Social and cultural heritage
� Legal
� Reputation
� Visual
![Page 97: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/97.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/01010/00 | 15-7
Risk Assessment Worksheets
The Risk Assessment Work Sheets used during the workshop are presented in Table 15-8 and
Table 15-9. The Work Sheets also included what further controls or corrective actions could be
used to ensure mitigation of the original risk is maintained. It also included the assessment of
residual risk.
Control Consideration for the Workshop
For the purpose of the Risk assessment process, the processes and activities in the “base risk
level” were assessed in the “absence” of controls. This was done to determine whether the
existing or planned controls are deemed appropriate to reduce the inherent risk to acceptable
levels.
15.2.6 Risk Treatment
Risk treatment was undertaken by identifying specific cost-effective strategies and action plans.
If the risk level is unacceptable after identifying strategies and action plans, further control and
mitigation measures were identified and then reassessed the residual risk to ensure that the risk
level is acceptable.
Consideration is given to a range of potential mitigation measures that can be implemented and
these are recorded in the risk assessment worksheet along with the resulting treated risk rating.
During the workshop, the study team assessed whether the treated risk can be further mitigated
and that residual risk are acceptable or will require further treatment or mitigation. Proposed
mitigation measures for specific aspects of the Project are described in each of the study
components, specifically in Section 16.
15.2.7 Monitor and Review
It is important that the result of the risk assessment remain relevant or up to date by continuous
monitoring and review. Factors and assumptions used during the workshop may be subject to
change as the Project progresses. As such, new risks will be identified and will be coupled with
new mitigation, if existing mitigation measures are no longer responsive to address the risks.
Updating the risk register (worksheet) may change risk rankings, either positively or negatively.
As new additional information comes along, the risk register was reviewed and revised as
necessary during the development of the ESIA, when additional information became available
through specialist technical reports.
EBWPC is also committed to update the result of the risk assessment and monitor the
effectiveness of mitigation measures. This updating and monitoring will be undertaken through a
combination of continuous monitoring and internal and external audits. The environmental and
social management plan is detailed in Section 16 of this report and will serve as reference for
the frequency and type of monitoring to be undertaken throughout all phases of the Project.
15.3 Risk Assessment Workshop
The result of the risk assessment workshop is presented in the table below. The assessment for
the Burgos Transmission Line and Jetty Projects focused on the operation and maintenance
phases.
15.3.1 Workshop Part icipants
The Project team composed of subject matter experts participated in the workshop (Table 15-4).
![Page 98: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/98.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/01010/00 | 15-8
Table 15-4 Risk assessment w orkshop part icipants
Name Company Position and Specialisation
Mylene Palaypayon-Ana GHD Civil/Environmental Engineer and EIA Specialist
Joel De Jesus GHD Geologist
Pia Madid GHD Senior Environmental Scientist and Terrestrial Flora Specialist
Mitzi Pollisco GHD Principal Scientist and Terrestrial Flora Specialist
Jennifer Patol-Calpo GHD Environmental Scientist and People Specialist
Niko Severino GHD Environmental Scientist and Air & Noise Specialist
Katrina De Guzman GHD Environmental Scientist and Marine Specialist
Mike Edrial GHD Environmental Scientist and Terrestrial Fauna Specialist
Katrina Clemente GHD Landscape Architect and Landscape & Visual Impact Assessment Specialist
Pierre-Jean Pochon GHD Electrical Engineer and Risk Assessment Reviewer
15.3.2 Document Review
Site visits have been conducted prior to the Workshop. Table 15-5 shows the documents
reviewed prior to and during the site visit. These documents formed the basis for workshop
chronology of assessment and supporting documents for decision verification.
Table 15-5 Document review
Document Document Type
Project Description (PD) Report for the 115 kV Burgos-Laoag Transmission Line and Substation Project
Legislative Requirement
Comprehensive Development Management Plan (CDMP) Internal EBWPC Study/ Documentation
Resource Assessment and Biophysical Characterisation of the Reef Area in the Proposed Jetty Area in Burgos, Ilocos Norte
Internal EBWPC Study/ Documentation
Geotechnical Investigation Report Internal EBWPC Study/ Documentation
Project Risk Register Internal EBWPC Study/ Documentation
Study on the Movements of Migratory Birds in Ilocos Norte and the Possible Impact of Windmills and Transmission Line on the Flyways of Migratory Birds
Supporting evidence
Tree Inventory Data Supporting evidence
Site Photographs Supporting evidence
Maps of Project Location Supporting evidence
![Page 99: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/99.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/01010/00 | 15-9
15.4 Result of the Risk Assessment
There are 13 risk events or risk situations identified that may potentially occur during the
operation and maintenance of the Burgos Transmission Line while at least four events were
determined for the Jetty Project (Table 15-6). The identified risks were categorised as threats to
the health and safety of the community and workers, or threat to the environment, public
complaints and possible regulatory or legal disputes which can affect the reputation of EBWPC.
The base risk levels were assessed in terms of their likelihood and the consequence levels
using no controls. Mitigation measures were then recommended to address the specific risk
events or situation to reduce the base risk level. Then again, risks were assessed based on the
present of the mitigation measures to determine if residual risks occur. When residual risks are
still assessed as moderate, high or extreme, additional mitigation measures were
recommended.
Table 15-6 List of issues and risks ident ified during the operat ion and
maintenance of Transmission Line and Jetty Projects
Project ID No. Issues/Risks
Transmission Line
1 Change in visual amenity
2 Loss of biodiversity (fauna)
3 Loss of biodiversity (flora)
4 Reduced air quality
5 Increase in noise levels induces by wind (hissing sound)
6 Increase in noise levels induced by rain (crackling sound)
7 Site issue of workers while doing live work
8 Safety issues of workers while doing non-live work on transmission tower
9 Safety issues of workers and equipment
10 Extreme weather condition (more than 270 kph wind speed)
11 Ground movement
12 Foundation damage from flooding or increase scouring effect
13 Site vegetation/bush fire
Jetty 1 Reduced water quality
2 Reduced air quality
3 Safety issues of workers
4 Extreme weather condition (e.g. storm surge)
15.4.1 Potent ial risks during the operat ion and maintenance of the
Transmission Line
Activities during the operation phase of the transmission line primarily consist of regular
monitoring and routine maintenance, inspection and repair of transmission towers and lines, and
maintenance of vegetation heights.
Risk assessment matrix
During the operation and maintenance phase of the transmission line, the risks identified as
high and extreme are associated with the adverse impact on the health and safety of the
community that has the potential to create legal and reputational risk to EBWPC (Table 15-7).
These include safety issues during maintenance activities that may lead to electric shock,
![Page 100: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/100.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/01010/00 | 15-10
electrocution or cut lines at the insulator points. Extreme weather event and ground movement,
leading to tower collapse, were also identified to produce extreme and high risk.
Table 15-7 Extreme and high risks ident ified during the operat ion of
Transmission Line Project
ID No.
Environmental aspect
Hazard Risk category
Risk rating (pre-control)
Risk rating (post control)
1 Landscape Change in visual amenity
Visual 5 B H 4 A M
3 Biodiversity and conservation
Loss of biodiversity (flora)
Environment 5 B H 5 A H
7a People Safety issue of workers while doing live work
Health and safety
3 E E 1 B L
7b People Safety issue of workers while doing live work
Legal 3 C H 1 C M
7c People Safety issue of workers while doing live work
Reputation 3 D E 1 C M
8a People Safety issue of worker while doing non-live work on transmission tower
Health and safety
3 E E 1 C M
8b People Safety issue of worker while doing non-live work on transmission tower
Legal 3 C H 1 C M
8c People Safety issue of worker while doing non-live work on transmission tower
Reputation 3 D E 1 C M
9a People Safety issue of workers and equipment
Health and safety
2 E E 1 E H
9c People Safety issue of workers and equipment
Reputation 2 D H 1 D H
10a People Extreme weather condition (more than 270 kph wind speed)
Health and safety
2 E E 1 E H
11a People Ground movement Health and safety
2 E E 1 E H
11c People Ground movement Reputation 2 D H 1 D H
13a People Site vegetation/bush fire
Health and safety
2 E E 1 B M
Risk assessment worksheet
Presented in Table 15-8 are risks identified during the operation and maintenance phase of the
Burgos Transmission Line Project. Risk levels, control measures and additional mitigation and
enhancement measures were provided.
![Page 101: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/101.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/01010/00 | 15-11
Table 15-8 Risks ident ified during the operat ion and maintenance of the Burgos Transmission Line Project
Identified risk event Base risk levels Residual risk levels
ID Hazard/ Threat Fault / Failure / Cause
Risk event / Impacts / Consequences
Lik
elih
ood
Health & Safety
Environment
Social & Cultural Heritage
Legal Reputation
Visual Impact
Options for mitigation/ enhancement measures
Lik
elih
ood
Health & Safety
Environment
Social & Cultural Heritage
Legal Reputation
Visual Impact
Additional Mitigation / Enhancement Measures
Consequence
Ris
k
Consequence
Ris
k
Consequence
Ris
k
Consequence
Ris
k
Consequence
Ris
k
Consequence
Ris
k
Consequence
Ris
k
Consequence
Ris
k
Consequence
Ris
k
Consequence
Ris
k
Consequence
Ris
k
Consequence
Ris
k
1 Change in visual amenity
Operation of Transmission Line
Permanent disruption in visual amenity
5 B H Introduction of green buffers (plants) Revegetation of disturbed area
Maintenance of buffer zone
Conduct of IEC to influence perspective of the viewing public/receptors
4 A M
2 Loss of biodiversity (fauna)
Operation of Transmission Line
Species mortality due to collision (e.g. bird-wire collision)
2 B L Installation of deflectors or diverters (BL023 to BL025 along Buraan River)
Regular monitoring by ROW coordinators
1 B L
3 Loss of biodiversity (flora)
Operation of Transmission Line
Permanent restriction for vegetation growth (i.e. 2 m maximum height)
5 B H Implementation of offsets
Introduction of green buffers
Maintenance of vegetation along the Transmission Line twice a year depending on vegetation growth
5 A H Maintenance of buffer zone and offset areas
4 Reduced air quality
Use of access roads for care and maintenance of TL
Dust generation and vehicle emission
3 A L A L Observe speed limit
Vehicle registration and emission compliance
Regular maintenance of vehicles
2 A L A L
5 Increase in noise levels induced by wind (hissing)
Operation of Transmission Line
Nuisance to tourists 1 A L A L Installation of vibration dampers (for more than 150 m distance between towers) to reduce vibration thereby eliminating the wind-induced noise
1 A L A L
6 Increase in noise levels induced by rain (crackling sound)
Operation of Transmission Line
Nuisance and disturbance to nearby community (structure in Barangay Corocor, Bacarra and household near Tower 107 Brgy. Ngabangab, Pasuquin)
1 A L IEC activities
Disturbance compensation, if necessary
1 A L
7 Safety issue of workers while doing live work
Operation and maintenance of Transmission Line
Electric shock and electrocution
3 E E C H D E Built-in measures to prevent electrocution/electric shock are installed
Strict implementation of HSE Plan
Provision of line protection device/equipment which will trip the line and turn-off the power as soon as it touches anything grounded.
1 B L C M C M
8 Safety issue of worker while doing non-live work on transmission tower
Operation of Transmission Line
Electric shock and electrocution
3 E E C H D E Access restriction (anti-climbing feature) and installation of safety signage
Regular IEC activities
Strict implementation of HSE Plan
Proper grounding system
More frequent and regular maintenance activities
1 C M C M C M
![Page 102: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/102.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/01010/00 | 15-12
Identified risk event Base risk levels Residual risk levels
ID Hazard/ Threat Fault / Failure / Cause
Risk event / Impacts / Consequences
Lik
elih
ood
Health & Safety
Environment
Social & Cultural Heritage
Legal Reputation
Visual Impact
Options for mitigation/ enhancement measures
Lik
elih
ood
Health & Safety
Environment
Social & Cultural Heritage
Legal Reputation
Visual Impact
Additional Mitigation / Enhancement Measures
Consequence
Ris
k
Consequence
Ris
k
Consequence
Ris
k
Consequence
Ris
k
Consequence
Ris
k
Consequence
Ris
k
Consequence
Ris
k
Consequence
Ris
k
Consequence
Ris
k
Consequence
Ris
k
Consequence
Ris
k
Consequence
Ris
k
9 Safety issue of workers and equipment
Operation of Transmission Line
Risk of falling objects when there are cut lines at the insulator points
2 E E C M D H Installation and maintenance of vibration dampers (for more than 150 m distance between towers) to reduce possibility of cut lines due to excess vibrations
Conduct of IEC activities for both workers and general public
1 E H C M D H Sustained implementation of IEC activities for both workers and the general public
10 Extreme weather condition (more than 270 kph wind speed)
Operation of Transmission Line
Risk of falling objects when tower and/or wire collapse
2 E E C M Compliance to Philippine Electrical Code/NGCP standard
Regular monitoring and maintenance
1 E H C M Extreme events should be addressed in the Emergency Response and Management Plan (ERMP) of the project
Coordination with the Provincial Disaster Risk Reduction and Management Council of Ilocos Norte
11 Ground movement
Operation of Transmission Line
Risk of falling objects when tower and/or wire collapse
2 E E C M D H Checking of tower stability after seismic event Regular care and maintenance of slope around tower foundation
Regular monitoring and maintenance of tower
1 E H C M D H Extreme events should be addressed in the Emergency Response and Management Plan (ERMP) of the project
Coordination with the Provincial Disaster Risk Reduction and Management Council of Ilocos Norte
12 Foundation damage from flooding or increase scouring effect
Operation of Transmission Line
Safety impact on nearby communities
2 B L B L Regular check of tower foundation
Compliance to structural design standard
1 B L B L
13 Site vegetation/ bush fire
Operation of the Transmission Line
Lighting strike on overhead wire or tower structure during operation
2 E E C M Use of lightning arrestor/rod
Regular maintenance of buffer zone and offset areas
1 B L B L
![Page 103: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/103.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/01010/00 | 15-13
15.4.2 Potent ial risks during the operat ion and maintenance of the Burgos
Jetty
Risk assessment matrix
High risks identified during the operation of the Burgos Jetty project are associated with the
potential adverse impact on health and safety of the workers that may stir public concern and
eventually lead to legal or reputational risk (Table 15-9). Health and safety issues of workers
may occur during unloading activities that may cause legal or reputational risks.
Table 15-9 High risks ident ified during the operat ion of Jet ty Project
ID No.
Environmental aspect
Hazard Risk category
Risk rating (pre-control)
Risk rating (post control)
1 Water quality Reduced water quality
Reputation 2 D H 1 C M
3a People Safety issue on workers
Health and safety
3 C H 1 C M
3b People Safety issue on workers
Legal 3 C H 1 C M
3c People Safety issue on workers
Reputation 3 C H 1 C M
Risk assessment worksheet
Presented in Table 15-10 are risks identified during the operation and maintenance phase of the
Burgos Jetty Project. Risk levels, control measures and additional mitigation and enhancement
measures were provided.
![Page 104: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/104.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/01010/00 | 15-14
Table 15-10 Risks ident ified during the operat ion and maintenance of the Burgos Jetty Project
Identified risk event Base risk levels Residual risk levels
ID Hazard/Threat Fault / Failure / Cause
Risk event / Impacts / Consequences
Lik
elih
ood
Health & Safety
Environment
Social & Cultural Heritage
Legal Reputation
Visual Impact
Options for Mitigation / Enhancement Measures
Lik
elih
ood
Health & Safety
Environment
Social & Cultural Heritage
Legal Reputation
Visual Impact
Additional Mitigation / Enhancement Measures
Consequence
Ris
k
Consequence
Ris
k
Consequence
Ris
k
Consequence
Ris
k
Consequence
Ris
k
Consequence
Ris
k
Consequence
Ris
k
Consequence
Ris
k
Consequence
Ris
k
Consequence
Ris
k
Consequence
Ris
k
Consequence
Ris
k
1 Reduced water quality
Operation of Jetty
Oil spill/leak from vessels
Loss of marine biodiversity
2 B L C M D H
Implementation of HSE protocol Oil spill emergency plan
Monitoring and evaluation of the implementation of HSE protocol
1 B L C M C M
2 Reduced air quality
Operation of Jetty
Dust generation and vehicle emission
3 B M
Observe speed limit
Vehicle registration and emission compliance
Regular maintenance of vehicles
1 B L
3 Safety issue (workers)
Operation of Jetty
Accidents during unloading
3 C H C H C H Strict implementation of HSE Protocol
1 C M C M C M
4 Extreme weather condition (e.g storm surge)
Operation of Jetty
Siltation and impacts on coastal and marine ecology 1 B L
Routine inspection of structural integrity
1 B L
![Page 105: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/105.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/01010/00 | 15-15
15.5 Risk Ranking
Identified risks according to level (i.e. “Extreme” to “Low”) are presented in Table 15-11. It also
shows the Residual Risk Ranking for each identified risk to demonstrate that the Base Risks
were adequately reduced to manageable and acceptable levels.
Table 15-11 Risk ranking
ID No. Environmental aspect
Hazard Risk category Risk rating (pre-control)
Risk rating (post control)
Transmission Line
9a People Safety issue or workers and equipment
Health and safety
2 E E 1 E H
10a People Extreme weather condition (more than 270 kph wind speed)
Health and safety
2 E E 1 E H
13a People Site vegetation/bush fire
Health and safety
2 E E 1 B M
7c People Safety issues of workers while doing live work
Reputation 3 D E 1 C M
8a People Safety issues of worker while doing non-live work on transmission tower
Health and safety
3 E E 1 C M
8c People Safety issues of worker while doing non-live work on transmission tower
Reputation 3 D E 1 C M
11a People Ground movement Health and safety
2 E E 1 B M
7a People Safety issues of workers while doing live work
Health and safety
3 E E 1 B L
9c People Safety issue of workers and equipment
Reputation 2 D H 1 D H
11c People Ground movement Reputation 2 D H 1 D H
3 Biodiversity and conservation
Loss of biodiversity (flora)
Environment 5 B H 5 A H
1 Landscape Change in visual amenity
Visual 5 B H 4 A M
7b People Safety issue of workers while doing live work
Legal 3 C H 1 C M
8b People Safety issue of worker while doing non-live work on transmission tower
Legal 3 C H 1 C M
9b People Safety issue of workers and equipment
Legal 2 C M 1 C M
10b People Extreme weather Legal 2 C M 1 C M
![Page 106: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/106.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/01010/00 | 15-16
ID No. Environmental aspect
Hazard Risk category Risk rating (pre-control)
Risk rating (post control)
condition (more than 270 kph wind speed)
11b People Ground movement Legal 2 C M 1 C M
13b Biodiversity and conservation
Site vegetation/bush fire
Environment 2 C M 1 B L
2 Biodiversity and conservation
Loss of biodiversity (fauna)
Environment 2 B L 1 B L
12a People Foundation damage from flooding or increase scouring effect
Health and safety
2 B L 1 B L
12b People Foundation damage from flooding or increase scouring effect
Legal 2 B L 1 B L
4a Air quality Reduced air quality Health and Safety
3 A L 2 A L
4b Air quality Reduced air quality Environment 3 A L 2 A L
5a Noise Increased in noise levels induced by wind (hissing sound)
Social and cultural heritage
1 A L 1 A L
5b Noise Increased in noise levels induced by rain (crackling sound)
Health and safety
1 A L 1 A L
Jetty
1c Water quality Reduced water quality
Reputation 2 D H 1 C M
3a People Safety issues during unloading activities
Health and safety
3 C H 1 C M
3b People Safety issues during unloading activities
Legal 3 C H 1 C M
3c People Safety issues during unloading activities
Reputation 3 C H 1 C M
2 Air quality Reduced air quality Environment 3 B M 1 B L
1b Water quality Reduced water quality
Legal 2 C M 1 C L
1a Water quality Reduced water quality
Environment 2 B L 1 B L
4 Marine biodiversity
Extreme weather condition leading to siltation and impacts on coastal and marine ecology
Environment 1 B L 1 A L
![Page 107: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/107.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/01010/00 | 15-17
15.6 Management of Risks
Mitigation measures were recommended to address risks, specifically on risks assessed as
“extreme” and “high”. The risks were then assessed based on the presence of control or
mitigation measures.
As shown in Table 15-11, all the eight “extreme” risks were reduced to “high” after the
identification of specific control measures. Risk events after the application of controls are
referred to as residual impacts where the risk rating remains high. Thus, additional mitigating
measures were identified to further reduce the risks.
Base risk events ranked as “extreme” include occupational health and safety issues during the
operation and maintenance activities of the transmission towers. The potential exposure of
workers to unsafe working conditions (i.e. working at heights, working near electricity) remain
“high” even after the application of control because of the severity of consequence should the
risk occur (e.g. electric shock, electrocution, falling object). Adverse effects of extreme weather
condition or ground movement to the public were also identified to cause “extreme” risk event.
Likewise, the risk level remains “high” even after the application of control measures.
Management measures identified to control residual risks include the following:
� Strict implementation of HSE Policies
� Regular maintenance of grounding system
� Maintenance of vibration dampers
� Regular monitoring and maintenance of transmission towers
� Continued implementation of IEC activities for both workers and the general public
![Page 108: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/108.jpg)
![Page 109: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/109.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | i
Table of contents
1. Introduction................................................................................................................................. 1-0
2. Project Description ..................................................................................................................... 2-0
3. Assessment Methodology .......................................................................................................... 3-0
4. Land Use Assessment ............................................................................................................... 4-0
5. Noise and Vibration Assessment ............................................................................................... 5-0
6. Biodiversity and Conservation ................................................................................................... 6-0
7. Marine Ecology and Seawater Quality ....................................................................................... 7-0
8. Water and Drainage Assessment .............................................................................................. 8-0
9. Soil and Groundwater Contamination Assessment ................................................................... 9-0
10. Air Quality Assessment ............................................................................................................ 10-0
11. Heritage and Cultural Assessment .......................................................................................... 11-0
12. Traffic, Access and Safety Assessment ................................................................................... 12-0
13. Socio-Economic Assessment .................................................................................................. 13-0
14. Landscape and Visual Assessment ......................................................................................... 14-0
15. Risk Assessment ...................................................................................................................... 15-0
16. Environmental and Social Management Plan .......................................................................... 16-1
16.1 Management Plan .......................................................................................................... 16-1
16.2 Monitoring Plan .............................................................................................................. 16-1
16.3 Energy and Resource Efficiency Plan ......................................................................... 16-11
16.4 Abandonment Plan ...................................................................................................... 16-11
16.5 Emergency Response Plan ......................................................................................... 16-12
16.6 Waste Management Plan ............................................................................................ 16-15
16.7 Social Development Plan and Performance Report .................................................... 16-17
16.8 Stakeholder Engagement, Consultation, and Disclosure Plan .................................... 16-31
16.9 Land Leasing Process ................................................................................................. 16-31
16.10 Grievance Mechanism ................................................................................................. 16-36
16.11 Occupational Health, Safety and Environmental Guidelines ....................................... 16-39
16.12 Human Rights, Community, Health and Safety, and Security Plan ............................. 16-40
16.13 Transport and Access/Traffic Management Plan ........................................................ 16-41
Table index
Table 16-1 Environmental and Social Management Plan Matrix during Operation and
Maintenance Phase ....................................................................................................... 16-2
Table 16-2 Environmental and Social Monitoring Plan Matrix during the Operation and
Maintenance Phase ....................................................................................................... 16-7
![Page 110: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/110.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | ii
Table 16-3 Members of Compliance Monitoring Team .................................................................... 16-9
Table 16-4 Toilet and hand washing facilities provided to different MDG beneficiary schools
in Ilocos Norte .............................................................................................................. 16-19
Table 16-5 Manpower Skills Development Activities conducted by EBWPC ................................ 16-25
Table 16-6 Livelihood Training carried out by EBWPC ................................................................. 16-27
Table 16-7 IEC Framework Plan .................................................................................................... 16-31
Table 16-8 Sample grievances during pre-construction and construction phase .......................... 16-37
Figure index
Figure 16-1 Compliance Monitoring Team Organization Chart ...................................................... 16-10
Figure 16-2 Emergency Response Team ....................................................................................... 16-12
Figure 16-3 ROW Acquisition Process for No Identified Landowner and Identified
Landowner ................................................................................................................... 16-33
Figure 16-4 ROW Acquisition Process for Easement Contracts ..................................................... 16-34
Figure 16-5 Compensation for structures ........................................................................................ 16-36
Figure 16-6 Burgos Jetty Traffic Management Plan........................................................................ 16-42
![Page 111: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/111.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-1
16. Environmental and Social
Management Plan
The Environmental and Social Management Plan (ESMP) and Monitoring Plan are formulated to
identify the mitigating measures that will be implemented where environmental and social risks
and impacts are identified, particularly during operation phase of the project. In addition, the
management and monitoring plans developed by EBWPC during construction phase of the
project is discussed. Monitoring the efficiency and status of mitigating measures implemented
during construction phase are also included based on relevant environmental indicators.
A compliance monitoring team is identified in the ESMMoP, including their roles and
responsibilities for management and monitoring the environmental and social performance of
the Transmission Line and Jetty Projects for the duration of project operation.
16.1 Management Plan
Management plans were formulated and implemented during the construction of the
Transmission Line and Jetty Projects. These include:
� Traffic Management Plan (Appendix S)
� Emergency Response Plan (Appendix V)
� Waste Management Plan (Appendix W)
� Environment Health and Safety (EHS) Plan (Appendix X)
� Environmental Management Plan (Appendix Y)
� Security Plan (Appendix Z)
On the other hand, the management plans being implemented during the operation and
maintenance activities of the Transmission Line and Jetty Projects are presented in Table 16-1 .
Options for mitigation or enhancement to address the identified impacts were enumerated.
Further, responsible entity, source of cost and financial arrangement were identified.
16.2 Monitoring Plan
The monitoring plan for the Transmission Line and Jetty Projects is formulated and designed to
monitor compliance of EBWPC to environmental standards and ensure effective implementation
of mitigation measures that it has committed to undertake. The monitoring program may be
revised during the project life cycle depending on the extent of activities involved in each of the
project phases.
The environmental and social monitoring plan for the Transmission Line and Jetty Projects is
presented in Table 16-2. The key environmental aspects, the parameters monitored
corresponding to the potential impacts identified, sampling frequency, number of stations
monitored and responsible entity are described in the table.
![Page 112: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/112.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-2
Table 16-1 Environmental and Social Management Plan Matrix during Operat ion and Maintenance Phase
Potential environmental impact Options for prevention/ and enhancement Responsible entity
Cost Guarantee/ Financial arrangements
Land Use
Partial loss of land used for crop production (Conflict in land use)
� Lease agreement between EBWPC and landowner
� Compensation of disturbance fees for temporary disturbance
EBWPC Part of project operation cost
� Lease agreement between EBWPC and landowner
Encroachment in ECA (Ablan-Bayog Marine Sanctuary)
� Participation in the coastal resource management activities of the municipality (e.g. coastal clean-up)
EBWPC Part of project operation cost
� Social Development Program (Reforestation, Watershed Management, Health and/or Environmental Enhancement Fund under ER 1-94)
Noise and Vibration
Increase in ambient noise levels � No significant impact on community � Workers should be provided with PPEs
(e.g. ear plug)
EBWPC Part of project operation cost
� Compliance with DAO 2003-30 � Compliance with DOLE
Occupational Health and Safety Standards
Crackling or humming sound when transmission line gets older
� Regular inspection of transmission lines � Installation of corona rings and/or
application of surface treatments
EBWPC Part of project operation cost
� Compliance with DAO 2003-30 � Compliance with DOLE
Occupational Health and Safety Standards
Increase ambient noise (sizzles, crackles or hissing sounds) during period of high humidity that result in partial discharge of electrical energy called “corona”
� Impact is localised and minimal EBWPC Part of project operation cost
� Compliance with DAO 2003-30 � Compliance with DOLE
Occupational Health and Safety Standards
Vibration of transmission cables during windy conditions
� Installation of vibration dampers to control vibration of overhead conductors
EBWPC Part of project operation cost
� Compliance with DAO 2003-30 � Compliance with DOLE
Occupational Health and Safety Standards
Biodiversity and Conservation
Ecosystem Services
Reduction in biodiversity services � On-site rehabilitation measures Implementation of biodiversity offset
EBWPC Part of project
� Compliance to tree cutting permit and other forest laws
![Page 113: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/113.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-3
Potential environmental impact Options for prevention/ and enhancement Responsible entity
Cost Guarantee/ Financial arrangements
� Monitoring of earth-balled species � Conduct of maintenance activities
operation cost
Terrestrial Flora and Fauna
Loss of species habitat and/or habitat fragmentation
� Ensure that there is minimum clearing of vegetation during maintenance activities
� Re-vegetation of disturbed areas using indigenous species in selected areas
� Retaining and enhancing unaffected vegetation and habitat/ecosystem
EBWPC Part of project operation cost
� Compliance to tree cutting permit and other forest laws
Hindrance to wildlife access � Limit activities to designated area and ROW pathway
� Establish and maintain corridor or buffer zones within the ROW
EBWPC Part of project operation cost
� Compliance to tree cutting permit and other forest laws
Collision and electrocution � Marking of static wires with aviation spheres and installation of flight diverters during downtime period in Site 2 only where transmission line passes through Buraan River
EBWPC Part of project operation cost
� Compliance to standards on operation and maintenance of transmission line
Threat to abundance, frequency and distribution of importance species
� Conduct of IEC to maintenance workers not to engage in activities that exploit the natural resources such as hunting and collection of forest products
� Orientation of workers on wildlife conservation (e.g. not feeding wild animals
� Monitoring of bird collisions or electrocutions along the transmission line
� Put additional wire-marking reflectors if bird collision is evident
EBWPC Part of project operation cost
� Compliance to RA 9147 � Compliance to standards on
operation and maintenance of transmission line
Increase access to critical areas � Rehabilitation of opened areas immediately after construction
� Provision of duty/patrol/roving security officers
� Implementation of commitments on the Special Tree Cutting Permit
EBWPC Part of project operation cost
� Compliance to standards on operation and maintenance of transmission line
� Compliance to Special Tree Cutting Permit
![Page 114: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/114.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-4
Potential environmental impact Options for prevention/ and enhancement Responsible entity
Cost Guarantee/ Financial arrangements
Marine Ecology & Seawater Quality
Impact of jetty operation on plankton, soft-bottom and fish communities
� Impact is localised and minimal EBWPC
Burgos LGU
SDP � Memorandum of Agreement (MOA) with LGU Burgos
Changes in water quality, hydrodynamics and sediment regime
� Impact is localised and minimal
Water and Drainage
Depletion of water resources/ water competition
� No significant impact
Foundation or tower collapse � Regular monitoring and maintenance of tower foundation
� Slope stabilisation � Erosion control
EBWPC
Burgos LGU
Part of project operation cost
� Compliance with the permit provided by the DPWH
Soil and Groundwater Contamination
Accidental release of chemicals (hydrocarbons) onto the surface soil, which may leach into the groundwater
� Regular maintenance of vehicles to ensure that containment is free from defects and likelihood of accidental leaks/spills is reduced
� Implementation of emergency response plan in case of accidental leaks and spills
EBWPC
Contractors
Part of project operation cost
� Compliance with RA 6969
Accidental release of fuel stored in boats/ship that would dock at the jetty into the sea
� Ensure the availability of spill equipment for any accidental spill (e.g. spill booms)
� Ensure that their fuel storage and engines are safe
� Comply with company-prescribed maintenance schedules
EBWPC
Contractors
Part of project operation cost
� Compliance with RA 6969 � Compliance with RA 9295
Air Quality
Vehicle emission, dust generation and re-suspension during maintenance of transmission lines and operation of jetty (delivery of materials/equipment)
� Proper maintenance of inspection and delivery vehicles
� Observe speed limits if driving along dirt roads
� Implementation of Logistics and Travel Plan
EBWPC
Contractors
Part of project operation cost
� Compliance with DAO 2003-30 � Compliance with RA 8749
Heritage and Cultural Resources
Visual impact on local recreation area � Immediate revegetation of quarried and EBWPC Part of � Compliance with DAO 2003-30
![Page 115: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/115.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-5
Potential environmental impact Options for prevention/ and enhancement Responsible entity
Cost Guarantee/ Financial arrangements
excavated areas were undertaken after construction
� Screening of tower footings or foundation by planting vegetation (i.e. below 2 m)
� Addition of roadside vegetation and maintenance of roadside vegetation to limit view of transmission towers from the cultural resources (i.e. permanent road leading to Kapurpurawan Rock Formation)
Contractors project operation cost
� Compliance with tree cutting permit
� Memorandum of Agreement (MOA) with LGUs of Burgos, Pasuquin, Bacarra and Laoag City
Loss of local recreational use � No significant impact
Loss of local religious use � No significant impact
Traffic, Access and Safety
Traffic congestion during operation and maintenance activities (i.e. replacement of tower parts) that may potentially lead to vehicular and/or pedestrian accident
� Coordination with the municipal and barangay LGUs, DPWH and NGCP to inform about the repair and maintenance activities of transmission towers
� Dissemination of information on repair and maintenance to the relevant local media to help inform the public
� Establishment of a temporary traffic control and protective set-up to ensure that destructions and other hindrances are reduced
� Installation of traffic signals (traffic lights, advance warnings signs, pavement markings)
� Implementation of Traffic Management Plan
EBWPC Contractors LGU
Part of project operation cost
� Compliance with DAO 2003-30 � Compliance with RA 4136
Traffic congestion during jetty operation (i.e. material delivery) which may potentially lead to vehicular and/or pedestrian accident
� For oversized materials, contractors should schedule material delivery during lean hours or days
� Permitting and/or compliance on rules particularly on occupational health and safety for the overload/over dimensional goods
EBWPC
Contractors
LGU
Part of project operation cost
� Compliance with DAO 2003-30 � Compliance with RA 4136
![Page 116: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/116.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-6
Potential environmental impact Options for prevention/ and enhancement Responsible entity
Cost Guarantee/ Financial arrangements
� Implementation of Traffic Management Plan
Socio-Economic and Public Health
Displacement and disturbance of properties in areas where transmission towers and jetty were established
� Lease agreement between EBWPC and landowner
✁ Compensation of affected crops and land ✁ Restoration and rehabilitation of disturbed
areas (e.g. temporary access roads) � Preparation of Livelihood Restoration
Plan (LRP) for the 49 households
EBWPC Part of project operation cost
� Lease agreement between EBWPC and landowner
Impacts on workers’ and community health and safety
� Implementation of the Transmission Maintenance Manual and HSE Policy
� Use of permanent and temporary signs or barriers
� Conduct of IEC activities � Coordinate with LGUs
EBWPC
Contractors
Part of project operation cost
� Compliance with DOLE Occupational Health and Safety Standards
Electric and magnetic field � Conduct of IEC about EMF studies to address concern of the community
� Compliance to horizontal clearance requirements
EBWPC Part of project operation cost
Aircraft safety navigation � Coordination with the Civil Aviation Authority of the Philippines (CAAP)
� Installation of aerial marker balls or aircraft warning markers, lights or other attention grabbing devices
EBWPC Part of project operation cost
� Compliance with Height Clearance Permit provided by CAAP
Creation of local employment opportunities
� Prioritize local workers in employment opportunities
� Compliance with local labour laws
EBWPC
Contractors
Part of project operation cost
� Compliance with RA 7160
Wider economic (taxes and revenues) and employment benefits (indirect employment)
� Coordination with LGUs in the implementation of Social Development Plan (SDP)
EBWPC Part of project operation cost
� Compliance with RA 7160 � Memorandum of Agreement
(MOA) with LGUs of Burgos, Pasuquin, Bacarra and Laoag City
![Page 117: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/117.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-7
Potential environmental impact Options for prevention/ and enhancement Responsible entity
Cost Guarantee/ Financial arrangements
Landscape and Visual Impact �
Impact of transmission towers on the landscape character and visual amenity
� Revegetation of quarried/excavated areas to reduce
� Screening of tower footings by planting endemic species in the area
� Coordination with the LGUs and provision of assistance in planting and maintenance of trees and other vegetation screening along the Manila North Road
EBWPC and its contractors
Part of project operation cost
� Compliance with DAO 2003-30
Notes: DAO 2003-30 – IRR for the Philippine Environmental Impact Statement (EIS) System RA 8749 – Philippine Clean Air Act of 1999 RA 4136 – Land Transportation and Traffic Code RA 7160 – Local Government Code of the Philippines RA 9147 – Wildlife Resources Conservation and Protection Act RA 9295 – Domestic Shipping Development Act of 2004
Table 16-2 Environmental and Social Monitoring Plan Matrix during the Operat ion and Maintenance Phase
Key environmental aspects per project phase
Potential impact per environmental sector
Parameter to be monitored
Sampling and measurement plan Lead person
Method Frequency Location
Land – terrestrial flora
Transmission Line – Pruning/removal of vegetation along the ROW
Number and identification of affected trees and its conservation status
Transect Annually Location of critically endangered species (Burgos and Pasuquin)
EBWPC Forester
Established offset area (as a condition in the IFC PS 6)
Monitoring of tree growth indicator parameters
Semi-annual for the first three years
Annually thereafter
Identified offset areas
EBWPC Forester in coordination with DENR
Jetty Area – Potential spread of invasive species (Cassytha filiformis)
Presence of invasive species (Cassytha filiformis)
Visual Jetty area EBWPC Forester to report this issue to the LGU and DENR for their proper
![Page 118: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/118.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-8
Key environmental aspects per project phase
Potential impact per environmental sector
Parameter to be monitored
Sampling and measurement plan Lead person
Method Frequency Location
that can eradicate mangrove and agricultural species
action or includion in their Coastal Resource Management Planning
Land – terrestrial fauna
Collision and electrocution
Incidence of bird mortality due to collision and electrocution
Visual count
Purposive search
Documentation upon encounter by ROW coordinator
Along the Transmission Line ROW
Project PCO or Environmental Officer
ROW Coordinators
EBWPC encourages community to report incidences
Collision and electrocution
Monitoring of incidents involving endangered species i.e. wild ducks (as a condition in the IFC PS 6)
Visual count Semi-annual (2nd
and 4
th quarter of
the year)
Towers BL023 to BL025 along Buraan River
Project PCO or Environmental Officer
People – economic Partial loss of land used for crop production within the ROW
Compensation for opportunity loss based on lease agreement
- Annual Municipalities of Burgos, Pasuquin, Bacarra and Laoag City
EBWPC Land Negotiation Team and Grievance Redress Mechanism Team
Reduced yield of crops
Harvest Survey
Displacement of grazing areas
Size of available grazing areas
Inspection EBWPC CSR Team
![Page 119: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/119.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-9
16.2.1 Organizat ional capacity and competency
Structure and Responsibility
A compliance monitoring team is formed to ensure implementation of the environment and
social management and monitoring plan for EBWPC projects including the Transmission Line
and Jetty. The team has four key members on site, which include the Site Manager, the
Pollution Control Officer (PCO), the Environment Officer, and the Community Relations Officer.
The members all report to the Business Unit Head. Table 16-3 describes the responsibilities of
each member.
Table 16-3 Members of Compliance Monitoring Team
Position Responsibilities
Site Manager Monitor and update the over-all performance of the project
Pollution Control Officer Implement environment management-related programs
Monitor the project’s operation on environment management-related compliance and facilitate necessary actions
Environment Officer Implement forestry and ecosystem conservation-related programs.
Monitor project’s compliance to Forest Management Bureau-related permits and its overall impact to the environment, and implement necessary actions
Community Relations Officer
Implement CSR-related activities and monitor community concerns and feedback on the project and its necessary actions
At EDC, the parent company of EBWPC, various departments were formed to support site-
based employees. These departments, including the Environmental Management Department
(EMD), Watershed Management Department (WMD), Corporate and Social Responsibility
Department (CSRD) and Public Relations Department (PRD), ensure that best practices are
implemented across all sites.
The EMD and WMD guide the PCO and the Environment Officer on ensuring that all
environment-related regulatory standards are complied with. Concerns on air, water, noise, and
waste on-site will be consulted with the EMD. On the other hand, concerns of the Environment
Officer such as on flora, fauna, and reforestation efforts will be discussed with the WMD. The
Community Relations Officer will seek advice from the CSRD on how to better serve the local
communities. The PRD on the other hand will be tapped on crafting the communication plan to
implement the various programs. Figure 16-1 shows the organization chart of the compliance
monitoring team.
![Page 120: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/120.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-10
Figure 16-1 Compliance Monitoring Team Organizat ion Chart
Source: Social Safeguards Compliance Audit Report for Burgos Wind Project, EBWPC September 2014
Training, awareness and competence
Appropriate types and levels of training are provided to EBWPC personnel, especially those
who are involved in the implementation of the Environmental and Social Management Plan
(ESMP). The trainings are commensurate to the nature of work of each personnel and to the
environmental and social risks associated with the project. A training program will be developed
describing the activities and processes that will be conducted throughout the life of the Project.
It includes the following:
Training needs assessment
Appropriate training requirements will be identified to ensure that EBWPC employees are able
to perform their work in compliance with its environmental and social policies and applicable
regulations. Training needs assessment will be undertaken to ensure proper implementation of
the ESMP.
The Human Resource Officer, with the assistance of the department heads, shall periodically
update training needs for all personnel, especially those involved in the implementation of
ESMP. Training needs assessment will include identification of minimum training requirements
as well as evaluation of anticipated responsibilities to fulfil the commitments stated in the plan.
Orientation Program
The orientation program, which is provided to new hires, is designed to orient and integrate the
new employee into his/her new job, work unit and the EBWPC in general. The orientation
program is designed in such a way to emphasize the ESMP which include the health safety and
environmental procedures, emergency response and management, waste management, site
security, vehicle safety, human resource policy, workplace behaviour, labour grievance
mechanism, and external stakeholder engagement.
![Page 121: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/121.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-11
A separate orientation program is also implemented for site visitors prior to entry to the Project
Site. This include adherence to environmental health and safety program of the company.
EBWPC also requires its contractors to comply with the policies and programs concerning the
implementation of ESMP
16.3 Energy and Resource Effic iency Plan
This section outlines the energy resource and efficiency plan of the Burgos Wind Farm
Transmission Line and Jetty Project. Resource efficiency must comply with the IFC
Performance Standard 3 of which objectives are:
� To avoid or minimise adverse impacts on human health or minimising pollution from
project activities;
� To promote a more sustainable use of resources, including energy and water;
� To reduce project-related greenhouse gas emissions.
The Transmission Line Project is routed from across forests, farm lands and private lands. The
components of the line such as towers and its foundations have been designed to meet the site
conditions. To minimise the impact on the environment, the spacing between towers is
sometimes increased to 350 m.
The Transmission Line Project operation activities involve the visual inspection and cleaning of
the insulators. Sometimes the conductor is being repaired and after strong typhoon the tower
may need repair too. Operation and maintenance activities create localised pollution. This
pollution is minimised and it depends on the operation schemes.
The Transmission Line Project does consume very little energy for operation. In fact, the
Transmission Line Project energy consumption is the amount of losses along the conductor
across the entire length of the line. The energy consumption was evaluated when choosing the
conductor size. The large size of the conductor chosen, CONDOR, minimises the energy
consumption compared to a smaller conductor.
The Transmission Line project is exporting power from a renewable energy source. Therefore,
it has the potential to reduce greenhouse gas emissions and other air pollutants. To fabricate
the steel towers, there will be little consumption of greenhouse emissions.
16.4 Abandonment Plan
In the event that a decision is reached to abandon the Burgos Wind Project, the Transmission
Line connecting the Burgos Wind Project to Laoag Substation and Jetty Project will also be
abandoned. The following steps will be taken into consideration during abandonment:
� All excess materials and supplies shall be transported out of the project site. Cradle-to-
grave management of these items should be undertaken in full compliance with the
Philippine regulation on solid waste, toxic substances and hazardous waste.
� Transmission towers, steel poles, aluminum conductors, insulators, and other materials
shall be removed from the site and taken off-site of be turned-over to the LGU, depending
on the agreement or conditions of LGU and national agency concerned.
� Trash materials and other residual solid wastes will be collected, transported, and
disposed to DENR-accredited disposal facilities.
� Recyclable materials shall be collected and donated to the community materials recovery
facility (MRF).
� Waste oil and other hazardous waste shall be transported out of the project for off-site
disposal in accordance with government regulations.
![Page 122: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/122.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-12
� Depending on the agreement with the land owners for rented areas and the DENR for
areas in public lands, rehabilitation or restoration measures will be conducted for the
areas occupied by the transmission towers and jetty.
� Abandonment Plan shall be submitted to the National Grid Corporation of the Philippines
(NGCP) and the Philippine Ports Authority (PPA) for the transmission towers and jetty
projects, respectively. Abandonment Plan will also be submitted to the DENR and
relevant government agencies including the local government units for review prior to
implementation.
� An official abandonment report will be submitted to the DENR-EMB Region 1, NGCP and
PPA.
16.5 Emergency Response Plan
EBWPC is committed to providing a safe and healthful working environment for all its
employees, contractors and various stakeholders while protecting and preserving its assets. To
achieve this objective, EBWPC, through its contractor, developed and implemented an
Emergency Response Plan (ERP) for emergency situations during the operation and
maintenance of the Transmission Line and Jetty Projects (Appendix V). The ERP aims to
minimise the impacts of potential hazardous situations that may occur throughout project
operation. An Emergency Response Team (ERT) was also established to organize and
manage emergency response operations (Figure 16-2).
Figure 16-2 Emergency Response Team
Note: PDRRMC – Provincial Disaster Risk Reduction and Management Council; MDRRMC – Municipal Disaster Risk Reduction and Management Council; BDRRMC – Barangay Disaster Risk Reduction and Management Council
Emergency response procedures will be implemented for the following potential events or
similar events:
� Downed transmission lines or equipment failure
� Fire or explosion
� Sudden loss of power
� Natural disasters (e.g. typhoon, storm surge, tsunami, earthquake)
![Page 123: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/123.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-13
� Personal injury or medical emergency
Provided in the subsequent sections are the rules and safety measures to be implemented
during the operations of the transmission line and jetty projects.
Tower Collapse
Although transmission tower collapses are rare, there are reported instances of collapse due to
various circumstances. The reasons for collapse vary depending on conditions and type of
tower, but may include cyclonic winds and poor or improper maintenance. The transmission
towers were designed to withstand 270 kph, which is the standard set by the National Grid
Corporation of the Philippines (NGCP).
Fire or Explosion
Although the possibility is rare, transmission tower can catch fire. The combination of dense
smoke and hot gases generated by a large fire directly under or near a high voltage
transmission line can create a conductive path that increases the potential for a ‘flashover’1 .
Electrical Safety
The following will be undertaken to maintain electrical safety in transmission lines:
� Only authorized electrical workers may install, commission, inspect, test, maintain, modify
or repair "Fixed" electrical installations.
� Live parts of apparatus and wiring shall be effectively guarded to protect all workers or
objects from coming into contact.
� All personnel using electrical equipment shall first be instructed how to use it safely,
including the dos and don’ts.
� All small tools and temporary electrical equipment will be regularly checked for fitness of
use. Particular attention should be paid to any built in safety functions such as trip
switches.
� Work permit system including “lock out tag out” measures shall be applied to all critical
electrical works.
� Additional safety documentation shall be developed over the course of the construction
period to cover specific electrical hazards as they are identified.
Safety Concerns due to Unauthorized Access
The potential for vandalism or trespassing can cause safety concerns along the transmission
line and jetty projects. Measures intended to reduce personal injury and public hazards include
locked access, warning signs, and postings of 24-hour emergency numbers. Security guards
will be stationed at fixed posts and foot patrols will be provided for all work areas.
Personal Injuries
Minor Injuries
In the event that a minor medical incident during operation and maintenance occurs (e.g. small
cuts, abrasions, etc.), the personnel should:
� Perform first aid, as necessary.
1 Fire and High Voltage Transmission Line Safety. Powerlink Queensland Information Sheet.
https://www.powerlink.com.au/Safety/Documents/Fire_and_High_Voltage_Transmission_Line_Safety.aspx. Retrieved on 01 December 2014
![Page 124: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/124.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-14
� Implement the accident/injury reporting procedure.
Major Injuries
In the event that a major medical emergency occurs, including the need for hospitalisation or
emergency services, personnel should:
� Contact the designated site supervisor.
� Consul the local emergency phone number list and request assistance immediately.
� Perform the first aid/CPR, as needed. Note that this should be done only be a qualified
first-aider.
� Stabilise the injured; decontaminate, and extricate only if the environment of the injured/ill
person is dangerous or unsafe and if the rescuers are appropriately protected from
potential hazards that might be encountered during the rescue.
� When site emergency services personnel arrive, communicate all first aid activities that
have occurred.
� Transfer responsibility to the care of the injured/ill to the local emergency care providers.
� Implement the accident/injury reporting procedure.
Emergency Communication and Protocol
EBWPC will establish appropriate lines of emergency communications to handle emergencies
on site outlining such item as direct access to emergency services at the site. This includes the
following:
� Establishment of site Emergency Response Team that will be able to handle fire, medical,
environmental spills, bomb threats and other emergencies. Drills will be conducted
regularly.
� Provision of site clinic manned by registered project nurse and trained first aiders.
� Coordination with local hospital and signing a Memorandum of Agreement (MOA) to
provide emergency medical services when required.
� Coordination with other governmental agencies such as the police, coastguard, LGU and
other government agencies as may be necessary.
� All workers working on, or visiting the site will be made aware of the procedure during the
safety induction.
� Communication lines will be established with the workers and emergency contact
services will be provided to the workers and posted on strategic location in the work site.
Project Evacuation
It is not expected that evacuation procedures will be implemented. Nevertheless, in the event of
adverse weather conditions, damage to facilities from fire or other catastrophic event, or other
unforeseen conditions, personnel will be evacuated from the project area. EBWPC coordinated
with the Disaster Risk Management and Monitoring Council (DRMMC) in the Municipalities of
Burgos, Bacarra, and Pasuquin and the City of Laoag. An evacuation plan and the standard
procedures was also developed by EBWPC for the transmission line and jetty projects.
![Page 125: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/125.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-15
16.6 Waste Management Plan
Operation and maintenance of the Transmission Line and Jetty Projects will not produce
significant quantities of wastes for disposal. The wastes that will be produced are incidental to
the operations and are related to maintenance activities (e.g. used oil from vehicles/equipment,
and replaced wires and other transmission tower parts).
Spills from used oil and other potentially hazardous materials can be prevented from causing
adverse environmental impact by adhering to good management practices.
The applicable management measures to minimise waste generation and prevent spills are
detailed in the sections below.
16.6.1 Waste Minimizat ion
In waste management hierarchy, source reduction is the most effective means of minimizing
waste generation. Source reduction means being able to use materials that would generate
less or no waste at all. EBWPC is committed to reduce its waste generation and promote reuse
and recycling of wastes. During operation, hazardous products will be substituted by less
hazardous products where equivalent performance can be assured. In addition, procurement
procedures will recognise the need to minimise waste packaging in the purchase of supplies.
EBWPC will comply with the requirements stated in RA 6969 (Toxic Substances and Hazardous
and Nuclear Wastes Control Act of 1990) and its implementing rules and regulations in the
handling, storage and disposal of hazardous products. Recyclable products will be given
preference than non-recyclable products.
Standard work methods will be implemented, as applicable, to minimise wastes by:
� Using the complete contents of containers
� Using materials to the fullest extent possible
� Using the oldest supplies first to avoid expiry
� Ordering supplies in bulk containers, where practical
� Using non-hazardous substitutes
� Safely reusing containers and packaging materials
� Keeping incompatible wastes separated to avoid cross contamination
� Avoiding spoilage by adequately storing supplies
16.6.2 Waste Disposal
Wastes will be generated in small quantities consistent with routine maintenance. These
wastes will be initially stored in a designated area and later removed from the site premises for
proper disposal. EBWPC will coordinate with the LGU of Burgos, Pasuquin, Bacarra and Laoag
for proper disposal of nonhazardous wastes, while a DENR-accredited hazardous waste hauler
will be commissioned by EBWBC for proper disposal of hazardous wastes from the project site.
Hazardous waste management is discussed in more detail in the next section.
16.6.3 Hazardous Materials and Spill Prevent ion
A variety of potentially hazardous materials were used or stored during construction and
maintenance activities for the proposed wind farm project. Potentially hazardous materials
routinely used include petroleum fuel and oils for the vehicle and equipment. The major
concern regarding the use of these substances is their uncontrolled release to the environment
![Page 126: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/126.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-16
through accidental spillage, and subsequent adverse effects on terrestrial and aquatic habitat
and species, soil, groundwater quality, and human health and safety.
Proper storage and materials handling are important to prevent adverse effects to the
environment from accidental spillage, and to prevent unsafe conditions. Diligent operational
procedures will be implemented as part of the Company’s standard operating procedures to
avoid accidental losses. Likewise, good management procedures to prevent accidental spills
will be observed in the wind farm project.
The following protection measures are intended to minimise the potential for any spills on soil,
vegetation, surface water, and groundwater.
Storage and disposal of Petroleum Fuel, Oil, and Lubricant (POL)
� Diesel fuel and gasoline were stored on site in limited quantities and were stored within a
bunded compound with sufficient capacity to contain any spillages. Fuel drums were
stored upright on a deck with drip trays for the collection of spilled substances.
� Fuel drums were provided with sealable covers to prevent spillages. The drums were
closed at all times, except when undertaking refuelling.
� Fire extinguishers and spill kits were located near POL storage areas
� POL storage areas were identified by signs, and “No Smoking” signs were displayed at all
POL storage sites and refuelling areas. Smoking is not permitted within 50 m of any POL
storage area.
� Waste POLs were stored in covered steel drums/containers. The containers were
provided with drip trays for the collection of spilled substances. Waste solvents were
stored separately.
� All used oil and petroleum products were removed from the premises upon accumulation
of a sufficient volume and disposed of in an acceptable manner in accordance with
government regulations and requirements.
� Greasy or oil rags or materials subject to spontaneous combustion were deposited, and
kept in an appropriate receptacle. This material was removed from the work site on a
regular basis and disposed of in accordance with government regulations and
requirements.
Equipment fuelling
� Only equipment that are not easily transported were refuelled on site. Service vehicles
were refuelled at a commercial fuelling station.
� Where possible, vehicle maintenance was performed offsite, at a nearby commercial
fuelling station, in order to minimise the amount of lubricants and oils stored on site.
� When refuelling equipment, operators implemented the following:
– Use designated fuelling locations.
– Use drip trays.
– Use leak free containers and reinforced rip and puncture proof hoses and nozzles.
– Be in attendance for the duration of the procedure.
– ✁eal all storage container outlets, except the outlet currently in use.
– Fuelling and servicing of equipment shall be done at least 100 m from a water body.
![Page 127: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/127.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-17
16.7 Social Development Plan and Performance Report
A social development plan (SDP) was developed by EBWPC in compliance to its commitment to
support community development as embodied in its Corporate Social Responsibility (CSR)
Program. SDP was developed to organise programs, management strategies and social
measures to address social issues associated with the projects. The SDP was prepared in
partnership with the host communities and focuses on five key areas, which include livelihood,
health and sanitation, education, environment, and culture.
On the first quarter of 2013, the Memorandum of Agreement (MOA) on EBWPC CSR Program
for the Province of Ilocos Norte was signed by representatives from EBWPC and the Provincial
Government. CSR projects identified in the MOA include health and sanitation, manpower
development and livelihood, which will be implemented for the next three years.
16.7.1 Social Development Plan
EBWPC CSR Program aims to contribute in improving the socio-economic condition of host
communities through interventions in education, health, livelihood, and environment. In line with
its objective of providing quality education and gainful employment for the youth, EBWPC will
implement a dual-strategy on education. One is to upgrade school facilities particularly health
and sanitation facilities, having been identified as lacking or needing of improvement in most
public schools; and second, to provide manpower training to local youths to enhance their
opportunity to gain employment.
Livelihood support shall be undertaken in the form of skills training to build the youth and
women’s capacities to engage in entrepreneurial activities, thereby increase their income. The
three project components are all provided in the MOA between EBWPC and the Provincial
Government of locos Norte that specifies the CSR projects to be implemented by EBWPC over
the next three years starting 2013.
Meanwhile, the “BINHI: Tree for the Future Project”, among EBWPC’s newest environment-
related undertaking, will be introduced to students, teachers, local officials and other community
members to create awareness on the need to “rescue and secure” the country’s endangered
and premium tree species. Planting and growing of these special tree species will be done in
school grounds and public parks in the Municipality of Burgos, with the hope of establishing
“mother trees” that would later on produce seeds that will be used in future forestation activities.
This will also be an avenue to engage the Department of Environment and Natural Resources
(DENR0 and relevant agencies.
Installation of Sanitation Facilities in Public Schools
As provided in the MOA with the Provincial Government of Ilocos Norte (PGIN) and with the
Laoag City Government that was signed during the first quarter of 2013, EBWPC will install
Toilet and Hand-washing Facilities in select public schools in host municipal LGUs namely
Burgos, Pasuquin, Bacarra and Laoag City. Schools found in areas with high poverty incidence
will be given priority in identifying school-beneficiaries. Most of these schools have multi-grade
classes and are found in interior or relatively remote communities. In the next three years,
EBWPC will install 35 toilet and hand-washing stations in its host-LGUs.
Health and Sanitation
For its health program, EBWPC aims to improve access to water supply and sanitation services.
EBWPC will conduct studies to assess water resources and water demand in selected
communities. These studies will also identify appropriate water supply and sanitation
technologies that can be implemented in the communities.
![Page 128: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/128.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-18
Adopt-A-School for K-12 Program
Starting mid-2015, EBWPC will explore programs that will contribute in upgrading the learning
systems of public secondary schools in order to keep up with the challenges of the K-12
program. Initially, it has identified two public secondary schools needing of support in terms of
learning modules development, tools and equipment and teacher’s training.
Livelihood Skills Training
Livelihood skills trainings will be conducted to build the capacities of the local communities to
undertake service-oriented or income-generating activities independent of the project. A total of
750 participants are targeted to undergo livelihood skills training in a period of three years. The
program as agreed between EBWPC and PGIN and the Laoag City Government will be
implemented over a three-year period.
EBWPC shall identify target communities and assess/determine their needs. The course or
topic of training to be provided shall depend on the needs identified per target community. This
activity shall be coordinated with government agencies or offices such as the Department of
Labor and Employment (DOLE) and the City/Municipal Social Welfare and Development Office
(C/MSWDO) to assist in identifying and designing training courses and inviting local trainers
from the Department of Trade and Industry (DTI) and the Technical Education and Skills
Development Authority (TESDA).
Environment
As part of the “Binhi Tree for the Future” project with the objective objective of planting future
mother trees of endangered premium species in host school grounds and parks, a tree planting
activity shall be conducted at selected school grounds in the Municipality of Burgos.
In each school, a simple ceremony with teachers, students and LGU shall be held to include an
introduction of EBWPC and its “Binhi Program”, followed by the tree planting activity proper.
Students shall be informed that the project not only ends in tree planting, but focuses on their
role to nurture the seedlings until these become mother trees for future seed
sourcing/harvesting, and further proliferation to help secure the vanishing species.
Socio-Cultural
EBWPC will continue to support community events that will enhance or maintain good
relationship with them and/or promote socio-cultural values. Under this program, EBWPC
provides support to activities designed to improve delivery of services by the local government
units and to annual social events by the host-communities.
16.7.2 SDP Performance Report
Health and Sanitation
Toilet and hand washing facilities
Installation of toilet and hand-washing facilities will be provided to indigent public schools that
were classified as Millennium Development Goal (MDG) schools. As provided in the MOA, 55
and 12 schools in the Province of Ilocos Norte and Laoag City, respectively, will benefit for the
next three years.
EBWPC coordinated with the Provincial MDC Council to identify recipients of the project and in
17 April 2013, Certificates of Entitlement were distributed to 12 recipients of sanitation facilities
in Laoag City (Plate 16-1). In coordination with the Department of Education (DepEd) Provincial
Office and Laoag City Division, an ocular inspection was conducted to determine the specific
type of facilities needed by the schools.
![Page 129: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/129.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-19
Plate 16-1 Distribut ion of Cert ificate of Ent it lement to the 12 recipient-
schools in Laoag City
Source: EBWPC
As of June 2014, toilets and hand-washing facilities were constructed in 12 public elementary
schools in Laoag City. As shown in Table 16-4, seven schools were installed with two-seater
detached toilet facilities with hand-washing stations, two schools were installed with one-seater
attached toilet and detached hand-washing stations, and two schools requested repair of their
existing two-seater detached toilets. Meanwhile, Vira Elementary School requested for a
replacement of its water pump as lack of it renders its newly-installed 10-faucet hand-washing
station and existing toilet facilities unutilised.
Table 16-4 Toilet and hand w ashing facilit ies provided to different MDG
beneficiary schools in I locos Norte
School Location Sanitation facility Sanitation facilities
Buttong Elementary School
Barangay Buttong, Laoag City
Two-seater detached toilet with hand-washing
Darayday Elementary School
Barangay Darayday, Laoag City
Two-seater detached toilet with hand-washing
![Page 130: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/130.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-20
School Location Sanitation facility Sanitation facilities
Gabu Elementary School
Barangay Gabu Norte, Laoag City
Two-seater detached toilet with hand-washing
Caaoacan Elementary School
Barangay Caaoacan, Laoag City
Two-seater detached toilet with hand-washing
Eulalio F. Siazon Memorial Elementary School
Barangay La Paz Proper, Laoag City
Two-seater detached toilet with hand-washing
San Mateo Elementary School
Barangay San Mateo, Laoag City
Two-seater detached toilet with hand-washing
Don Galicano Rafales Elementary School
Barangay 59-A Dibua South, Laoag City
Two-seater detached with hand washing
Suyo Elementary School
Barangay 30-A Suyo, Laoag City
One-seater attached toilet and detached hand washing
Picture not available
Cabeza Elementary School
Barangay Cabungaan, Laoag City
One-seater attached toilet and detached hand washing
Picture not available
![Page 131: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/131.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-21
School Location Sanitation facility Sanitation facilities
Salet Elementary School
Barangay 55-B Salet, Laoag City
Repair of two-seater toilet and detached hand washing
Lagui Sail Elementary School
Barangay 54-A Lagui, Laoag City
Repair of two-seater toilet and detached hand washing
Picture not available
Vira Elementary School
Barangay 55-C Vira, Laoag City
Electric water pump Picture not available
Source: EBWPC
Medical and Dental Mission
In celebration of Burgos Town Fiesta, EBWPC spearheaded the Medical and Dental Mission on
February 2014. Services provided during the Medical and Dental Mission were minor surgeries
such as cyst removal and circumcision. Likewise, medicines amounting to PHP 95,965 were
distributed for free to the patients. Medical personnel involved in the activity include six dentists,
two doctors, five surgeons, three dental aides and 14 nurse assistants.
A total of 428 patients availed of free medical consultations and medicines while 71 patients
availed dental services. For minor surgery, 20 boys underwent circumcision while 12 adults
underwent cyst removal operation.
![Page 132: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/132.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-22
Plate 16-2 Medical and dental mission in the Municipality of Burgos
Feeding Program
In celebration of Nutrition Month, EBWPC facilitated feeding program of nine severely-wasted
high school students in Burgos Agro-Industrial School (BAIS) (Plate 16-3). The feeding
program aimed to provide healthy snacks as food supplement for the underweight or
malnourished students.
Plate 16-3 Recipients of the Feeding Program in BAIS
![Page 133: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/133.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-23
Manpower Skills Development
Carpentry and Masonry
In 2013, EBWPC launched manpower skills training on carpentry, masonry, and shielded metal
arc welding (SMAW) to upgrade the skills of the local youth and enhance their opportunity for
employment. The first manpower skills training was attended by 50 participants for the
Carpentry and Masonry National Certification (NC) II (Plate 16-4), 16 of which came from
Barangay Davila, Pasuquin, and the rest were from the different host-barangays in the
Municipality of Burgos. The training lasted for 26 days from 24 June to 30 July 2013.
The Technical Education and Skills Development Authority–Marcos Agro-Industrial School
(TESDA-MAIS) was tapped as the training provider while Burgos Agro-Industrial School (BAIS)
for the manpower skills training. As an output of the training, a two-seater toilet was constructed
at the training’s venue (Plate 16-5). Aside from toilet construction, the trainees were assigned
to different working stations for better and effective learning process.
As of November 2013, 24 graduates of the training were employed as laborers to First Balfour,
EBWPCs contractor for the construction and installation of Transmission Line and Jetty
Projects.
Plate 16-4 Graduates of the Carpentry and Masonry NC I I
Source: EBWPC
![Page 134: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/134.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-24
Plate 16-5 Part icipants of skills t raining during construct ion of 2-seater
toilet
Source: EBWPC
Shielded Metal Arc Welding
In September 2013, SMAW NC II was conducted at the TESDA–Bangui Institute of Technology
(BIT) with 25 participants from the Municipalities of Burgos and Pasuquin (Plate 16-6). In
November 2013, at least five graduates from this training were working for First Balfour.
EBWPC continuously monitors its graduates employed in its sub-contractors.
The second batch of SMAW NC II Training was conducted in June 2014 with 25 participants
from Laoag City (Plate 16-7). Participants were identified with the help of the City Social
Welfare and Development Office (CSWDO).
Plate 16-6 Part icipants of SMAW NC I I Training – Batch 1
Source: EBWPC
Plate 16-7 Part icipants of SMAW NC I I Training – Batch 2
Source: EBWPC
![Page 135: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/135.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-25
Electrical Installation and Maintenance
In November 2013, the Electrical Installation and Maintenance (EIM) NC II training was
conducted at the Ilocos Norte College of Arts and Trade (INCAT) in Laoag City, which was
joined by 40 participants from the Municipalities of Burgos, Pasuquin, and Bacarra and the City
of Laoag. The training was completed in March 2014.
Plate 16-8 Part icipants of Electrical Installat ion and Maintenance
Source: EBWPC
As of June 2014, the total of 140 local residents who have been trained on various manpower
skills by TESDA with the support of EBWPC (Table 16-5).
Table 16-5 Manpow er Skills Development Act ivit ies conducted by EBWPC
Training Number of participants Total
Burgos Pasuquin Bacarra/laoag
Carpentry NC II 15 10 0 25
Masonry NC II 19 6 0 25
SMAW NC II 16 9 0 25
EIM NC II 17 18 5 40
SMAW NC II 0 0 25 25
Total 67 43 30 140
Source: EBWPC
Livelihood Support Program
Livelihood Skills Training
Livelihood skills training program was conducted for the residents of host communities in the
Municipalities of Burgos, Pasuquin, Bacarra and the City of Laoag as provided in the signed
MOA.
As part of EBWPCs livelihood support program, it supported 80 barangays of Laoag City by
providing training materials to technology demonstration sessions provided by the City Social
Welfare and Development Office (CSWDO), which ran from April to May 2013. The
demonstration sessions included candy-making, basket/handicraft-making, soap-making, t-shirt
designing and candle-making (Plate 16-9).
Two communities requested for one-day livelihood training programs. This included
Longganisa-Making training and Dragon Cactus Soap-Making held on 13 July and 14 August,
respectively, both in 2013. The Longganisa-Making was attended by 25 participants in
Barangay 51-A Nangalisan while Dragon Cactus Soap-Making was attended by 19 participants.
![Page 136: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/136.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-26
TESDA provided the resource persons while EBWPC provided the training materials and
assessment fees of the participants.
Plate 16-9 Part icipants of Livelihood Skills Training
Source: EBWPC
EBWPC spearheaded the conduct of training on Basic Silk-Screen Printing (Plate 16-10) in the
Municipalities of Burgos and Pasuquin, on April 2–4 and May 20–22, respectively, with 30
participants in each municipality. Participants were chosen from indigent households. At the
end of the training, the Municipal Social Welfare and Development Office assisted in accessing
start-up kit amounting to PHP 10,000.00 to selected groups of participants.
![Page 137: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/137.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-27
Plate 16-10 Training on Basic Silk-Screen Print ing in the Municipalit ies of
Burgos and Pasuquin
Source: EBWPC
Other livelihood trainings carried out by EBWPC with the assistance from the City Social
Welfare and Development Office (CSWDO) are presented in Table 16-6. CSWDO mobilised
the support of TESDA by providing the resource persons while EBWPC provided training
materials and assessment fees.
Table 16-6 Livelihood Training carried out by EBWPC
Date Venue Training Number of participants
Photo
May to June 2014
Barangay Madiladig, Laoag City
30-day Training on Motorcycle/Small-Engine Repair
13
May to June 2014
Barangay Madiladig, Laoag City
30-day Training on Dressmaking
13
9–13 June 2014
Barangay Vira, Laoag City
5-day Training on Manicure/Pedicure with NC II
28
Employment Generation for Local Youths
In April 2013, EBWPC sponsored a Job Fair (Plate 16-11) in partnership with the Department of
Labor and Employment (DOLE) and the Provincial and City Public Employment and Services
![Page 138: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/138.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-28
Office (P/CESO). About 29 employers/agencies participated the event, 25 of which are local
agencies while four are overseas employers. Of the 626 registered applicants, 55 were hired on
the spot.
Plate 16-11 Part icipants during Job Fair
Source: EBWPC
Capability-Building
EBWPC partnered with the Ateneo School of Government (ASOG) to implement Capability-
Building Program (Plate 16-12) for the officials and personnel of the Burgos LGU. Capability-
Building Seminar is being conducted by EBWPC in line with its objective of providing
appropriate intervention to strengthen the municipality to be able to cope with the development
opportunities. Further, the seminar aims to contribute to the improvement of systems and
processes in the LGU for a more effective delivery of development programs to the community.
Plate 16-12 Capability-Building Program in Burgos, I locos Norte
Source: EBWPC
Environment
In July 2013, EBWPC through its BINHI Project spearheaded a tree planting activity in
partnership with the Municipal Government of Burgos and the Burgos Agro-Industrial School
(BAIS), where the activity was held. The BINHI Project is at the core of EDC’s environment
sustainability thrust which involves planting of endangered species of plants in educational
institutions. For this activity, about 10 of the 40 tree species planted at the grounds of BAIS are
endangered species. The activity was participated by teachers and students of BAIS.
In celebration of the Environment Month in June 2014, EBWPC joined the Kapurpurawan Eco-
Fun Walk organized by the Barangay Poblacion Council in the Municipality of Burgos. The
activity was highlighted by a coastal clean-up drive along the Kapurpurawan Beach in Burgos
(Plate 16-13).
![Page 139: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/139.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-29
Plate 16-13 Clean-up Drive along Kapurpuraw an Beach
Source: EBWPC
External Assistance
In 2013, EBWPC supported the renovation of the St. John Sahagun Parish Church in the
Municipality of Burgos by providing the flooring construction requirements (Plate 16-14).
Towards the end of 2013, EBWPC supported gift-giving activities for indigent communities in the
Municipality of Burgos. A total of 100 gift packs were donated to the Burgos LGU and Barangay
Poblacion.
Plate 16-14 St . John Sahagun before renovat ion
Source: EBWPC
![Page 140: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/140.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-30
Plate 16-15 St . John Sahagun after renovat ion
Source: EBWPC
In 2014, EBWPC continued to support social events in the Municipality of Burgos, both at the
barangay and municipal level. During the fiesta celebration in Barangays Bobon, Pagali, Saoit,
Ablan and Paayas, EBWPC extended financial assistance. Likewise, EBWPC, together with its
contractors for the Burgos Wind Project, sponsored several events in the celebration of the ‘First
Pul-oy Festival of Burgos 27 February 2014. Events sponsored included Duathlon Sport Event,
Kite-flying competition, Concert and Fashion Show, and Medical Mission (Plate 16-16).
Plate 16-16 First Pul-oy Fest ival
Source: EBWPC
During the Provincial Fiesta in May 2014, EBWPC sponsored the La Milagrosa Procesion and
Sagala as well as the Music and Arts Festival. It also supported the Earth Day Celebration in 22
April 2014 by participating in the Fun Walk organized by the Provincial Environment and Natural
Resources Office (PENRO).
In March 2014, EBWPC sponsored the Annual Council Jamboree of the Boy Scouts of the
Philippines (BSP) Ilocos Norte-Laoag City Council. In April 2014, financial assistance was also
extended to 18 employees of Laoag City and Bangui Municipality Regional Trial Court (RTC) for
their participation to different conventions. Likewise, EBWPC provided sponsorship of the
Congress and Seminar-Workshop by the Philippine League of Secretaries to the Sangguniang,
Inc. (PLEASES) Ilocos Norte Chapter held on 5–8 March 2014.
![Page 141: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/141.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-31
16.8 Stakeholder Engagement, Consultat ion, and Disclosure Plan
An information, education and communication (IEC) campaign framework plan was formulated
with the following objectives:
� To gain public acceptance of the Burgos Wind Project, including the Transmission Line
and Jetty Projects
� To provide the public with balanced information and assist them in understanding the
solutions or measures related to the impacts of the project
� To gather feedback from the communities on their issues related to the project and their
ideas of alternatives or preferred solution to the problem
Presented in Table 16-7 is the IEC framework plan, which will be implemented during the
operation and maintenance phase of the projects.
Table 16-7 IEC Framew ork Plan
Target Sector Content/Topics Strategy/Method
Lot owners in TL areas
� Project description & status
� Land acquisition process
� Actual impacts & measures
� Grievance mechanism
� CSR projects
� Use of multi-media
� Group/ Cluster meetings
� Posters, flyers, and newsletters
Community residents
� Project description & status
� Actual impacts & measures
� Grievance mechanism
� Use of multi-media
� Group/ Cluster meetings
� Posters, flyers, and newsletters
LGU Officials � Project description & status
� Actual impacts & measures
� Reinstatement/ rehabilitation plan
� Grievance Mechanism
� CSR projects
� Council session/ meetings
� Consultations
� Newsletter
16.9 Land Leasing Process
The land leasing process conducted by EBWPC for the Transmission Line and Jetty Project are
detailed in this section.
Research and Mapping
Initially, the master list of lots and profile of landowners were prepared based on the map, tax
map control roll, tax declaration, technical description and cadastral maps gathered from the
Municipal Assessor’s Office, Registry of Deeds and the Bureau of Lands. Lot areas to be used
as lateral access and working area needed in the construction were planned and initial
inventory of affected trees and structures were conducted.
Development of Pricing Mix
Pricing mix was developed based on the data obtained from commercial banks, municipal
assessor values, Bureau of Internal Revenue (BIR) zonal values, fair market values, and, if
available, from realtors. EBWPC Land Negotiation Team decided on using the BIR zonal
values as initial offer to the landowners. All payments made for the easement or lease contracts
for the rights-of-way (ROW) were paid covering a period of 25 years.
![Page 142: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/142.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-32
Land Acquisition Strategy
For the transmission line and jetty projects, securing easement rights over affected private lands
was preferred over acquiring title because of the following reasons:
� Higher cost of purchasing the lots compared to leasing the property
� Less socially acceptable in the community perspective because of massive acquisition
� Limitations on the ownership of agricultural land in terms of total land holdings
For lands wherein permanent structures were constructed (e.g. transmission towers and jetty),
lands were legally acquired through the expropriation powers of the Department of Energy
(DOE). Expropriation for mere possession (and not ownership) addresses the following
concerns:
� Defective easement contracts
� Time factor regarding Department of Agrarian Reform (DAR) conversion
In 2010, the initial strategy was to offer easement contracts before proceeding with exploration.
However, securing land owners’ land ownership documents to allow EBWPC to enter into
easement contract and converting the agricultural lands took significant time. The strategy
changed in early 2011 as construction needed to immediately start. Expropriation automatically
converted agricultural land to industrial area, which shortened the needed lead time.
For the transmission line sail over lands, negotiations towards entering into easement contracts
continued to be offered to all land owners. All cases of expropriated sail over lands were due to
defective documentation. There are no cases of expropriation due to unreasonable counter
offer of landowners.
Negotiation Process
Four types of negotiation process were undertaken for the transmission line and jetty projects.
These processes are discussed below.
No Identified Landowner
In cases where lots do not have registered landowners, an expropriation case was filed by the
Office of the Solicitor General (OSG) in the Regional Trial Court (RTC) against “John Doe”
(Figure 16-3). To allow owners who have legal interest to assert to be heard; the RTC issued
an Order of Publication requiring the publication of notices of the expropriation case. Based on
the order, the expropriation case indicating the description of the lot subject to expropriation was
published in a newspaper of general circulation.
If no claimant appears to prove his ownership over the subject lot within 30 days, the OSG filed
a motion for issuance of writ of possession (WOP). The payment for the claimant, in a form if
check in the name of “John Doe”, was also submitted to the RTC. OSG later submits a case for
resolution and a request for an issuance of order of expropriation (OE). A process of this nature
was done until the finality of judgment is issued to close the expropriation case and allow the
registration of the expropriation with the Registry of Deeds.
For those cases wherein a claim was made, land documentation of the claimant was reviewed.
Once confirmed valid, the expropriation case were amended and the check previously issued
are revised for payment to the legal claimant. The expropriation case proceeded unless the
claimant agrees to enter into a lease contract.
![Page 143: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/143.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-33
Identified Landowner
The Land Negotiation Team initiated negotiations over lots with identified landowners by serving
letters from the EBWPC (Figure 16-4). The letter explained the project and stating its interest to
lease the lots for the project. In cases where the land owner were not able to provide
documents proving ownership of the affected lot, a second letter from the DOE was served
informing the land owner that an expropriation case may be instituted if the land documents
were not made available.
The challenge is this phase is that all legal landowners should acknowledge the letters. If the
person indicated in the land title is deceased, all legal heirs should be identified and notified.
For the transmission line and jetty projects, EBWPC has committed to helping the landowners
correspond to all of their relatives. Even after WOPs has been issued, EBWPC continue to help
landowners process their land documentation.
Easement Contracts
For lots with sufficient documentation, an initial offer based on BIR zonal value was offered to
the landowners. Some of the landowners issued a counter offer to EBWPC if they were not
amenable to the first offer. A negotiation was done until both parties agree (Figure 16-5).
In the event that renegotiation has extended beyond reasonable period, the protocol is to file for
expropriation. However, no case of this nature has occurred for the transmission line and jetty
land acquisition process.
EBWPC compensated the landowner based on the agreed amount and have the land owner
sign the Contract of Easement of Right of Way (CERW). The CERWs were then registered with
the Registry of Deeds.
Figure 16-3 ROW Acquisit ion Process for No Ident ified Landow ner and
Ident ified Landow ner
Source: EBWPC
![Page 144: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/144.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-34
Figure 16-4 ROW Acquisit ion Process for Easement Contracts
Source: EBWPC
Expropriation to Lease
The OSG filed an expropriation case at the RTC. During the hearing, the payment, which was
based on BIR zonal value, was made available. After the order for the issuance of WOP has
been granted by the RTC, EBWPC facilitated the payment to the landowner where they sign an
acceptance letter to acknowledge receipt of compensation.
The signed acceptance letters were submitted to the court and were issued as basis for the
request for the issuance of an OE. A copy of the OE was served by the Sheriff of the Court to
the landowner and secured an acknowledgement of receipt thereof. If 60 days has passed and
no acknowledgement has been received, a hearing for the Judgment of Expropriation
proceeded. A process of the same nature as the OE was done before the hearing for the
Finality of Judgment is conducted.
Once the Finality of Judgment is issued, the Land Negotiation Team can already register this at
the Registry of Deeds.
Special Cases
Special cases of land negotiation were conducted by EBWPC for the following land areas:
Memorandum of Agreement (MOA) with the Department of Education (DepEd)
Three lots were secured through MOA with the DepEd. Two of the said lots are currently being
occupied by the Davila National High School (DNHS), while the remaining lot is within the
jurisdiction of the Ilocos Norte Agricultural College (INAC).
In both cases, EBWPC has secured the consent of the Parent-Teachers’ Association prior to
securing the MOA. Since DepEd is a government agency, the said lots cannot be subjected to
![Page 145: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/145.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-35
expropriation. Thus, EBWPC entered into agreements with the DepEd to be granted right-of-
way.
Co-Location Agreement with the National Grid Corporation of the Philippines (NGCP)
Two lots, which are currently occupied by the NGCP, were secured through an agreement.
NGCP is a concessionaire of the transmission network–a government entity statutorily
responsible for managing and operating the transmission network in the Philippines pursuant to
Section 21 of the Electric Power Industry and Reform Act (EPIRA).
Authorization Letters
In the interest of starting construction, a number of landowners were requested to sign an
authorization letter granting EBWPC right-of-way. Land negotiation process is still ongoing for
some landowners because of the following reasons:
� Expropriation case is still pending in the court
� Landowner previously requested that land be subjected to a CERW instead of
expropriation. The landowner has committed to providing the necessary land
documentation.
� The landowners has just recently provided the required documents and payments are still
being processed.
Compensation for Trees, Crops and Structures
Separate payments were made to landowners for the trees, crops and structures that may be
affected (Figure 16-5). EBWPC intervenes in settling payments for affected trees and structures
along the transmission line towers and jetty. However, it is the obligation of the contractors to
settle those affected by lateral access or temporary access roads leading to the transmission
towers.
Only trees that were completely felled were compensated. Compensation was also made for
loss crops during construction. In addition, landowners are compensated for structural
damages that need to be renovated and structures that cannot be expanded.
Pricing of trees were based on DENR regulations while price of structures were based on tax
declaration and assessment provided by the contractor. As for loss crops and disturbance,
values were based on the prevailing market rates and volume of produce that would have been
harvested by the land owner. Moreover, the contractors restore damages to existing road and
public structures that were damaged during construction.
![Page 146: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/146.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-36
Figure 16-5 Compensat ion for structures
Source: EBWPC
16.10 Grievance Mechanism
The grievance mechanism, which will be implemented by EBWPC is presented in this section.
This process will be used during the operation and maintenance of the transmission line and
jetty projects. Grievances received during the pre-construction and construction phases are
also presented in this section.
Grievances received during Pre-Construction and Construction Phase
In the absence of a formal grievance redress mechanism, issues or grievances raised by
community in the past were addressed or resolved as these come. Prior to 2010, issues or
complaints by stakeholders including the community residents and local officials were raised to
EBWPC’s Officer-in-Charge (OIC). Since 2010, the Land Negotiation Team has been handling
all issues pertaining to land acquisition. Issues or grievances were mainly on the land
acquisition price and the acquisition process.
Prior to the start of construction in 2013 and up to present, several issues or complaints were
received by the EBWPC, albeit undocumented, as presented in Table 16-8.
![Page 147: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/147.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-37
Table 16-8 Sample grievances during pre-construct ion and construct ion
phase
Complainant Nature of complaint/grievance How it was resolved
Lot owners Reasonable land acquisition prices Negotiation by the Land Team
Lot owners Cut trees not properly turned-over to the lot owners
Watershed Management Division (WMD) made sure that cut trees were turned-over to the lot owners by coordinating with the contractor
Community residents
Noise caused by drilling and excavation works at night-time
This complaint was not raised by the people directly to EBWPC
Dust caused by the construction activities
Frequent watering of ground surface to control dust
Disposal of wastewater by the contractor at the construction site affecting the drainage of nearby houses
The contractor constructed drainage as demanded by the residents
Potential flooding caused by siltation in the drainage canal
Contractor re-excavated the drainage canal and removed the soil and other aggregates from the drainage water to avoid flooding, as demanded by the residents
Grievance Redress Mechanism
EBWPC views that effective grievance mechanism is an important part of its corporate social
responsibility to respect human rights. This is embodied in one of the core values of EBWPC
which highlights that each person should be treated with respect regardless of individual
differences. As EBWPC commits to building community relations where trust is an integral
component, it designed a grievance mechanism that aims to offer communities an effective
avenue for expressing concerns, achieve fair solutions, and promote a mutually constructive
relationship as the local people and the company find effective solutions together.
Receive and Register a Complaint
In receiving and registering complaint or grievance, EBWPC will provide multiple channels
where people can express or communicate their concerns. The following staff shall be
designated to receive and register complaints:
� Community Partner/Corporate Social Responsibility (CSR) Team
� Forester/Watershed Management Department (WMD) Team
� Land Team
� Security Officer
� Safety Officer
� Right-of-Way (ROW) Patrol
Complainant/s can forward their complaints or grievances to EBWPC in the form of a letter or by
filling-out the prescribed company grievance registration form. They can also call or email any
of the designated staff directly. Those designated to accept complaints, whether written or oral,
shall record them on the grievance log form which is forwarded to the Community Partner, who
will act as the Grievance Officer for further action. Once a complaint is received by the
Grievance Officer, it should be recorded in the complaints log or data system.
![Page 148: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/148.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-38
When a complaint or grievance is received directly by any of the designated staff, he/she shall
discuss the complainants’ situation personally to gain first-hand understanding of the situation,
and explore possible approaches for resolution. It is important during this first step to be
sensitive to the way in which the complainant experiences the issue; as such an understanding
may be important to achieving a successful outcome in a quick and timely manner.
Acknowledge
Upon registration, complainants will receive a timely acknowledgement that their case is
registered. Acknowledgement shall be communicated in an open and proper manner, such as a
letter, telephone call or a copy of the grievance form. The acknowledgement will include
information about the next steps in the process, time frame in which a response can be
expected to be in place and contact details of the grievance officer or complaint coordinator,
who is responsible in handling the case. This may be done at the time the grievance is received
or subsequently after.
Assess the Grievance
Once logged, the grievance team will conduct a rapid assessment to verify the nature of the
grievance. During the assessment, the team gathers information about the complaint and key
issues and concerns and helps determine whether and how the complaint will be resolved. To
gather information about the complaint, the following will be done:
� Identify parties involved
� Clarify issues and concerns raised by the complaint
� Gather views of the stakeholders, including those of the company (the person or
company unit associated with the problem shall be informed that a complaint has been
filed and the grievance team will collect information about the complaint from their
perspective)
� Determine initial options that parties have considered and explore various approaches for
settlement
� The team shall classify the complaint in terms of its seriousness or severity (high,
medium, or low) according to specific criteria. The level of severity will determine who
needs to be informed, who will manage the case (complaint coordinator) and whether the
senior management has to be advised. The complaint coordinator shall be responsible
for overseeing a particular grievance.
Grievances classified as low may be handled by the designated field personnel whereas
grievances ranked as high may have to be handled by the senior management. Issues that are
of low severity from the point of view of the complainant and the company will be resolved
immediately through a fast track process. In principle, EBWPC has bias towards resolving
grievances on-the-spot, if such can be resolved informally and rapidly. Whether the resolution
process is fast-track or requires a period of time, the EBWPC will employ a strategy that
engages the complainant in the assessment and in determining resolution or settlement options.
Formulate a Response
Once the assessment is complete, EBWPC will provide a response or feedback to the
complainant. The company response may suggest an approach on how to settle the issues, or
it may also offer a preliminary settlement or proposal. The response may be presented or
discussed to the complainant through a meeting with the complaint coordinator, manager or
personnel of the relevant company unit, and the complainant. The site manager may participate
in feedback, depending upon the seriousness of the complaint. If a direct meeting is not
possible, a neutral third party may be considered to serve as facilitator.
![Page 149: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/149.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-39
The complainant may accept the proposition, offer an alternative for further discussion, or reject
it or consider another dispute resolution process. If the case is complex and a resolution time
frame cannot be met, EBWPC shall provide an interim response—an oral or written
communication—that informs the person of the delay, explains the reasons, and offers a revised
date for next steps.
Consider recourse or appeal
If the complaints are not resolved on the initial attempts, the grievance mechanism incorporates
an appeals provision. This covers exceptional cases and will be required infrequently. Several
recourse options are described below:
� Elevate the issue to a review committee composed of senior managers to consider
whether additional reasonable actions are adequate
� Elevate the issue to a review committee consisting of company and community
representatives or other stakeholders to consider whether additional reasonable actions
are appropriate
� Propose the use of an independent mediator agreed upon by both the company and the
complainant to facilitate further dialogue
� Involve a trusted, independent external party to assess the grievance and propose an
impartial resolution
� Establish a standing appeals committee jointly with the community. The committee should
consist of individuals who enjoy credibility with affected communities and are viewed as
impartial by both sides
Should the appeals process fail to lead to a mutually acceptable resolution, the complainant
should remain free to pursue other avenues of remedy. The final agreement will be specific,
time bound and agreed upon by both parties. If not self-executing, it will include a monitoring
plan. If the complaint is found to be unsubstantiated, the grievance officer will explain the
reasons and may indicate other possible avenues of remedy.
Follow up and close out
Once a resolution has been agreed or a decision is made to close out, the final stage is to
implement the resolution, monitor outcomes and close out the grievance. Monitoring will
address problems that arise during implementation. In some cases, adjustments may be
necessary to ensure that root causes of complaints are rectified and outcomes are consistent
with the spirit of the original agreement.
Closing out the grievance occurs after the implementation of an agreed resolution has been
verified. Parties may be requested to provide feedback about their level of satisfaction with the
grievance handling process and the outcome.
Even when an agreement is not reached, it is important to close the case, document the results,
and request the parties’ evaluation of the process and its outcome.
Throughout the process, EBWPC will adopt a system that will effectively track and monitor
grievances in line with its commitment to promote timely and fair resolution of grievances. By
doing so, the concerned parties (complainant and relevant company personnel) are constantly
informed about the status of the case and the progress being made toward resolution.
16.11 Occupat ional Health, Safety and Environmental Guidelines
Health Safety and Environmental (HSE) Guidelines was prepared by EBWPC for the Burgos
Wind Project, which include the Transmission Line and Jetty Projects. The guidelines define the
![Page 150: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/150.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-40
practical steps that can be used by Contractors to identify and control significant risks to health,
safety and environment on EBWPC sites.
The plan includes coordination and information dissemination activities between EBWPC and its
contractors and the workers in general. Procedures in controlling risks and complying with the
terms and conditions of permit to work are also detailed in the plan. The detailed HSE
Guidelines for the Burgos Wind Project is presented in Appendix X.
Moreover, First Balfour, the main contractor of EBWPC during the operation and maintenance
of the Transmission Line and Jetty Projects, prepared a Transmission Maintenance Manual
(Appendix AA). The manual aims to serve as the guidelines for implementing works for
transmission lines, serve as a ready training/work reference for transmission linemen, and serve
as a planning guide for maintenance-related activities. The manual is issued to cover the
general administration and technical applications for the maintenance of the 115kV
Transmission Lines, its steel towers and steel poles of varying voltage levels and number of
circuits. Specifically, the manual contains guidelines from which the detailed step-by-step
procedures can be developed based on the actual situation. Moreover, the Transmission
Maintenance Manual provides Environmental Protection Procedures as well as Occupational
Health and Safety Procedures.
16.12 Human Rights, Community, Health and Safety, and Security
Plan
EBWPC is committed to the observance of human rights, and recognises, respects, and
protects human and workplace rights. The Human Rights, Community Health and Safety Plan of
EBWPC is in compliance with the Universal Declaration of Human Rights and the Philippine
Human Rights laws such as to the Presidential Decree 442 (Labor Code of the Philippines),
Article III of the 1987 Philippine Constitution, RA 9710 (Magna Carta of Women), RA 9231 (Anti
Child Labor Law), RA 7876 (Senior Citizens Center Act of the Philippines), RA 7277 (Magna
Carta for Disabled Persons) and other relevant rules and regulations.
All EBWPC personnel and its contractors and consultants shall adhere to the general principles
and policy to accept, recognise, respect and uphold the human rights of the people, domestic or
foreign.
Equality
EBWPC shall uphold the idea of equality for all, regardless of gender, race or belief in
economic, political, religion and social aspect. This includes non-discrimination in employment
and provision of training of women and persons with disability as long as they are qualified for
the position. Further, EBWPC will not tolerate abusive use of power resulting to various
anomalies and suppression of workers’ and community’s rights.
Freedom
EBWPC shall observe freedom from all forms of discrimination and harassment, inside and
outside the workplace. This means that company’s executive officers will listen to the voice of
everyone in the company, contractors, sub-consultants, host communities, and other
stakeholders with due respect and appreciation of their ideologies and beliefs.
Community Responsibility
EBWPC, through its Corporate Social Responsibility (CSR) is committed to promote social and
environmental prosperity through the implementation of projects and programs in partnership
with the stakeholders. Different projects and programs being implemented to provide benefits to
the community are detailed in Section 15.6. This include projects and programs of EBWPC that
![Page 151: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/151.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-41
are benefitting the vulnerable members of the community such as women, children and youth,
senior citizens, persons with disabilities and resource users.
Assistance to victims of natural calamities and disasters in the host communities shall also be
undertaken. Moreover, EBWPC will help in the protection and conservation of the Ilocano
culture.
Training and Monitoring
EBWPC will ensure the implementation and performance of its human rights policy by providing
training and seminar to its staff, especially those who are engaged in community and
stakeholder consultation. Monitoring and evaluation of human rights situations in the project
areas will also be undertaken. This will be conducted in parallel to the grievance redress
mechanism of EBWPC.
16.13 Transport and Access/Traffic Management Plan
A Traffic Management Plan (TMP) was prepared and implemented by EBWPC’s contractors for
the construction of the transmission towers and jetty projects to ensure safe, efficient and
unhampered road access of both road users and pedestrians through and around the areas that
were affected by the project (Appendix P)
The TMP applied to access roads leading to and from all project activity areas; roads utilised for
personnel; materials and equipment operation and transport; and access roads for construction.
The following guidelines were implemented during the construction phase and are being
implemented during the operation and maintenance phase.
� Protection to the public
� Worker safety
� Temporary traffic control
� Maintenance of warning signs
Traffic management implemented for the Jetty Project is shown in Figure 16-6.
![Page 152: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/152.jpg)
GHD | Report for EDC Burgos Wind Power Corporation - EDC Transmission Line and Jetty Projects, 71/12098 | 16-42
Figure 16-6 Burgos Jetty Traffic Management Plan
Source: First Balfour
![Page 153: 48325-001: 150 MW Burgos Wind Farm Project...Initial Environmental Examination The initial environmental examination is a document of the borrower. The views expressed herein do not](https://reader033.vdocuments.mx/reader033/viewer/2022052016/602ec33612076076c34935e0/html5/thumbnails/153.jpg)
Appendices
Appendices
Appendix A – Certificate of Non-Overlap (CNO)
Appendix B – Construction of Burgos Jetty: Method Statement
Appendix C – Permits: Burgos Jetty Project
Appendix D – Permits: Burgos Transmission Line Project
Appendix E – Certificate of Non-Coverage (CNC): Burgos Transmission Line
Appendix F – Certificate of Non-Coverage: Burgos Jetty
Appendix G – Certificate of Calibration
Appendix H – Results of Noise Level Measurements
Appendix I – Tables for Terrestrial Flora
Appendix J – Tables for Terrestrial Fauna
Appendix K – DENR Memorandum Circular No. 2005-005
Appendic L – DENR Administrative Order No. 2007-01
Appendix M – IUCN Red List Categories
Appendix N – Estimates of coral cover and other benthic lifeforms in reef sites in the vicinity of Burgos Jetty
Appendix O – Abundance and biomass of fish families on the reefs fronting the Burgos Jetty
Appendix P – List of associated fish species in the reefs fronting the Burgos Jetty
Appendix Q – Meteorological and Operating Data
Appendix R – Analytical Data
Appendix S – Traffic Management Plan
Appendix T – Height Clearance Permit
Appendix U – Transmission Towers built near Structures
Appendix V – Emergency Response Plan
Appendix W – Waste Management Plan
Appendix X – Environmental Health and Safety Plan for Burgos Project
Appendix Y – Environmental Management Plan
Appendix Z – Security Plan
Appendix AA – Transmission Line Maintenance Manual