47254-003: dhaka water supply network improvement project

66
Semi-Annual Environmental Monitoring Report Project number: 47254-003 Period: July - December 2018 Submission Date: April 2019 BAN: Dhaka Water Supply Network Improvement Project PART A Prepared by the Dhaka Water Supply and Sewerage Authority, Government of Bangladesh for the Asian Development Bank. This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to t he “terms of use” section of this website. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Upload: others

Post on 10-Feb-2022

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 47254-003: Dhaka Water Supply Network Improvement Project

Semi-Annual Environmental Monitoring Report

Project number: 47254-003

Period: July - December 2018

Submission Date: April 2019

BAN: Dhaka Water Supply Network Improvement Project – PART A

Prepared by the Dhaka Water Supply and Sewerage Authority, Government of Bangladesh for the Asian Development Bank. This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section of this website.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Page 2: 47254-003: Dhaka Water Supply Network Improvement Project

Semi-Annual Environmental Monitoring Report Project number: 47254-003 Period: July - December 2018 Submission Date: April 2019

BAN: Dhaka Water Supply Network Improvement Project

Prepared by the Dhaka Water Supply and Sewerage Authority, Government of Bangladesh for the Asian Development Bank.

This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section of this website.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Page 3: 47254-003: Dhaka Water Supply Network Improvement Project

DHAKA WATER SUPPLY NETWORK IMPROVEMENT PROJECT (DWSNIP) (ADB Loan No. 3397-BAN)

PROJECT MANAGEMENT UNIT

2nd

SEMI ANNUAL ENVIRONMENT MONITORING REPORT

(Period July to December 2018)

April 2019

Dhaka Water Supply and Sewerage Authority

Page 4: 47254-003: Dhaka Water Supply Network Improvement Project

Page | iii

Table of Contents

ABBREVIATIONS ....................................................................................................... v

I. INTRODUCTION .................................................................................................. 1

A. Background ......................................................................................................... 1

B. Purpose of the Report ........................................................................................ 1

C. Environmental Categorization ........................................................................... 1

D. Project Safeguards Team ................................................................................... 4

E. Overall project and subproject progress and status ....................................... 5

II. COMPLIANCE STATUS ...................................................................................... 9

A. Compliance status with National/Local statutory environmental requirements with Environmental Statutory Clearance ........................................................... 9

B. Compliance of Safeguard Loan Covenants ...................................................... 9

C. Safeguards Implementation Arrangements .................................................... 13

III. COMPLIANCE STATUS WITH THE OF ENVIRONMENTAL MANAGEMENT AND MONITORING PLAN ................................................................................. 15

A. Preparation of Safeguards Documents ........................................................... 15

B. EMP Compliance Status ................................................................................... 17

IV. ENVIRONMENTAL MONITORING AND EVALUATION .................................... 17

V. MAJOR PROJECT ISSUES AND PROBLEMS: ENVIRONMENTAL CONTEXT ........................................................................................................................... 19

VI. CONSULTATIONS AND DISCLOSURES CONDUCTED .................................. 19

VII. GRIEVANCE REDRESS .................................................................................... 19

VIII. ISSUES AND ACTION PLAN ............................................................................. 22

IX. SAFEGUARDS TRAININGS .............................................................................. 23

APPENDIX 1: APPROVED TOR FROM DoE ........................................................... 24

APPENDIX –2A: Batch & DMA wise Status of Design and Implementation – ICB 2.8 (July to December, 2018) ............................................................................ 28

APPENDIX –2B: Batch & DMA wise Status of Design and Implementation – ICB 2.11 (July to December, 2018) .......................................................................... 29

APPENDIX 3A: ROAD CUTTING PERMISSION-ICB 2.11 ....................................... 31

APPENDIX 3B: ROAD CUTTING PERMISSION-ICB 2.8 ......................................... 36

APPENDIX –4: Environmental Mitigation Measures Action Plan (ICB 2.11- First Batch) ................................................................................................................ 38

APPENDIX –5: FORMAT FOR COMPLIANCE OF IMPLEMENTATION OF EMP.... 78

Page 5: 47254-003: Dhaka Water Supply Network Improvement Project

Page | iv

Appendix 6: Monthly Environmental Monitoring Report - Format ........................ 82

APPENDIX - 7 : PERFORMANCE FACT SHEET FOR EMP IMPLEMENTATION OF DWSNIP PROJECT (PACKAGE-WISE) ........................................................... 88

APPENDIX - 8: PUBLIC CONSULTATION ON ENVIRONMENTAL ISSUES DURING CONSTRUCTION/ IMPLEMENTATION .............................................. 89

APPENDIX - 9: RECORDS OF TRAININGS CONDUCTED DURING REPORTING PERIOD.............................................................................................................. 90

APPENDIX: 10 SAMPLE GRIEVANCE REGISTRATION FORM ............................. 94

APPENDIX: 11 GRIEVANCE REDRESS FORM (BANGLA VERSION) ................... 95

APPENDIX: 12 OFFICE NOTIFICATION TO FORM GRC ........................................ 97

APPENDIX: 13 ADB Environmental and Social Safeguards Implementation and Monitoring Workshop ....................................................................................... 99

Page 6: 47254-003: Dhaka Water Supply Network Improvement Project

Page | v

ABBREVIATIONS

ADB – Asian Development Bank

CPP - China Petroleum Pipeline Engineering Company Ltd.;

CAP - Corrective Action Plan

DWASA - Dhaka Water Supply and Sewerage Authority DWSNIP - Dhaka Water Supply Network Improvement Project DMA - District Metering Area DMS - Design Management and Supervision Consultants DoE - Department of Environment DTW - Deep Tubewell DDR - Due Diligence Report ECC - Environmental Clearance Certificate

EMP - Environmental Management Plan EIA - Environmental Impact Assessment GoB - Government of Bangladesh GRC - Grievance Redress Committee GRM - Grievance Redress Mechanism ICB - International Competitive Bidding IEE - Initial Environmental Examination O& M - Operation and Maintenance PMU – Project Management Unit PCU - Project Coordination Unit PM - Project Manager RP - Resettlement Plan SCC - Site Clearance Certificate SPM - Suspended Particulate Matter SPS - Safeguard Policy Statement SEMR - Semi Annual Environmental Monitoring Report SEP - Site Environmental Plan SEMP - Site Specific Environmental Management Plan SIU - Safeguard Implementation Unit TDS - Total Dissolved Solids TMP - Traffic Management Plan TSS - Total Suspended Solids

US$ - US Dollar

Page 7: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 1

I. INTRODUCTION

A. Background

1. Dhaka Water Supply Network Improvement Project (DWSNIP) has been initiated by Dhaka Water Supply and Sewerage Authority (DWASA) in improving the water supply distribution network in various zones of Dhaka City. The estimated cost of the Project is US$ 408 millionThe Government of the People’s Republic of Bangladesh (GOB) has obtained a loan of US$ 275 million from the Asian Development Bank (ADB Loan: 3397-BAN) and the balance US$133 million equivalent would be financed by the GOB. 2. The Project will implement 70 DMAs in which about 1668 km pipe lines will be rehabilitated including about 156,163 service connections.

3. The Project has five (5) contract packages and the implementation of each package will approximately take 17 to 36 months with the expectation to complete by the year 2021. 4. The objectives of the Project are:

• To reduce NRW and achieve 24 x 7 water supplies in DMA’s identified under current project, left over DMA’s from DWSSDP.

• To provide new or regular connections to low income communities.

5. Summary of the Construction packages are depicted in Table 1 and the project area of each packages are shown in Figure 1.

B. Purpose of the Report

6. This report is the semi- annual environment monitoring report (SEMR) covering period July to December 2018 to describe the present compliance status and implementation of the mitigation measures, monitoring and reporting as per EMP of the approved draft IEE.

C. Environmental Categorization

According to ADB Safeguard Policy Statement, 2009

7. Sub projects under Five Packages (ICB 2.8, ICB 2.9, ICB 2.10, ICB 2.11 and ICB 2.12) under DWSNIP has been classified by ADB as environmental assessment category B (some negative impacts but less significant than category A) and the impacts of subprojects were assessed through Initial Environmental Examination (IEE), prepared according to ADB Safeguard Policy (SPS 2009).

Page 8: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 2

Figure 1: Project Area

Page 9: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 3

Table 1: Summary of Construction Works of Five Packages under DWSNIP (upto 31st December 2018)

Package

No.

MODS

Zone DMA Nos.

Design

Pipeline

Km

Service

Connections

Nos.

Deep

Tubewell

Nos.

Contract

Amount

(US$ in

Million)

Construction

Duration

days

Name of

Contractor Remarks

ICB 2.8 9 13 457 39297 10

46.84

1000 CPP Awarded

ICB 2.9 2 15 253 19,604 10 24.57 510 CFMCC Awarded

ICB 2.10 1 19 341 39,128 10 - 750 - Bid evaluation

in process

ICB 2.11 3,4,10 16 453 41,990 10 53.89 1000 Navana &

Pratibha JV Awarded

ICB 2.12 7 7 164 16144 10 - 540 -

Preparation of

bidding

documents

are in process

for 7 DMA

Total Civil

Works 70 1668 156163 50

Source: DMS Consultants

Page 10: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN

Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 4

According to National Laws and Regulations

8. As per Schedule 1 of ECA, 1995 all packages under DWSNIP is likely to be classified as red category (serial number 64 under ECR) which require both IEE and EIA for getting SCC and ECC from the DoE prior to commencement of the subproject. During meeting with Director, Environmental Clearance, DoE which was held on October 28, 2018 at DoE office, The Department of Environment provided exemption from Site Clearance considering high priority of the project and approved TOR for conducting EIA in favour of DWSNIP (see Appendix 1). DWASA with the assistance of the consultant teams, will develop the necessary EIA and ensure the ECC is obtained prior to award of civil works contract.

D. Project Safeguards Team

9. Environmental, Resettlement and Gender Officer of PMU has been designated for overseeing implementation of safeguards under the project. Environmental Specialist of DMS

has been mobilized for implementation of EMPs compliance. Resettlement and Gender Specialist has not yet mobilized during reporting period.

Safeguards Team

Name Designation/Office Email Address Contact Number

PMU

1. Jenny Chakma Executive Engineer (Environmental Expert in charge)

[email protected] +8801553266545

2. Sharmin Haque Amir

Executive Engineer (Resettlement Expert in charge)

[email protected] +880171502568

3. Sazia Afrin Executive Engineer (Gender Expert in charge)

[email protected] +8801716332483

PCUs

1. Md. Riaz Uddin Executive Engineer MODS Zone-9- (ICB 2.8)

[email protected] +8801819208902

2. Md. Firoz Alom Executive Engineer

MODS Zone-2 (ICB 2.9)

[email protected] +8801819229415

3. Md. Al Amin Executive Engineer

MODS Zone-1 (ICB 2.10)

+8801819229419

4. Md. Shah Alam , Executive Engineer MODS Zone-3 (ICB 2.11)

[email protected] +8801819229418

5. Md. Mazid Executive Engineer MODS Zone-4 (ICB 2.11)

[email protected] +8801819229417

6. Md. Ashraful Habib, Choudury

Executive Engineer MODS Zone-10 (ICB 2.11)

+880181714495

7. Md. Abid Hossain Executive Engineer MODS Zone-7 (ICB 2.12)

[email protected] +8801763051234

Page 11: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN

Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 5

DMS Consultants

1. Abu Nahid Munir Uddin

Environmental Specialist, DWSNIP

[email protected] +8801715452920

2. Md. Emdadul Haque Bhuiyan

Resettlement Specialist, DWSNIP

[email protected] +8801715005682

10. The Environmental Inspector of DMS will be mobilized after commencement of construction works who assist Environmental Specialist of DMS for EMP implementation and regular monitoring of mitigation measures during implementation

E. Overall project and subproject progress and status

11. DWSNIP civil works is divided into five contracts (packages): ICB 2.8 covering 13 DMAs, ICB 2.9 covering 15 DMAs, ICB 2.10 covering 19 DMAs, ICB 2.11 covering 16 DMAs, and ICB 2.12 covering 7 DMAs. 12. Till 31st December 2018, construction contract agreement has been signed for three (3) packages under DWSNIP. Among 5 packages, ICB 2.8 signed contract for zone 9 on 9th May, ICB 2.9 signed contract for zone 2 on 22nd November and ICB 2.11 signed contract for zone 3, 4 and 10 on 4th April 2018. Table 2 shows various subproject progress and status. Construction activities have not been commenced yet.

Detail progress of works under batch and DMA wise for ICB 2.8 and ICB 2.11 are attached in Appendix 2A and Appendix 2B respectively.

Page 12: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 6

Table 2: Description of Subprojects (Package-wise) and Status of Implementation (preliminary, detailed design, ongoing construction, completed and /or O& M stage) under DWSNIP (1 July ~ 31 Dec. 2018)

Package Number

Components/ List of Works

Status of Implementation Contract Status On going Construction

Preliminary Design

Detailed Design

Ongoing Construction

Construction Completed

O&M Under bidding Contract Awarded

% of Progress

Expected Completion Date

ICB 2.8 (Zone 9)

Rehabilitation of Distribution Network for non-revenue water reduction (including procurement of equipment/plant, and construction of DTW pump station) with O&M support DMA No.- 13 nos. Pipeline- 457 km Service connections- 39,221 nos.

√ Under process for 1st batch 04 DMAs (906, 907, 904 & 903) tentative date: 30th March,2019

Yet to be started tentative start date: 31st March,2019

Not Applicable

Not Applicable

Bidding Finalized

China Petroleum Pipeline Engineering Company Ltd.; (CPP) - has been awarded on May 9, 2018 and effective date fixed for implementation on 20.09.2018 Kick off meeting held on 11.09.18

No Physical Progress (0%)

15.07.2022

ICB 2.9 (Zone 2)

Rehabilitation of Distribution Network for non-revenue water reduction (including procurement of equipment/plant, and construction of DTW pump station) with O&M support DMA No.- 15 nos. Pipeline- 253 km Service connections- 19,604 nos.

√ Not yet started

Not yet started Tentative start date: July 1, 2019

Not Applicable

Not Applicable

Bidding Finalized

China First Metallurgical Group Co. Ltd.; (CFMCC) - has been awarded on November 22, 2018.

Not Applicable

Date will be finalized after approval of Program of Performance by DMS

Page 13: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 7

Package Number

Components/ List of Works

Status of Implementation Contract Status On going Construction

Preliminary Design

Detailed Design

Ongoing Construction

Construction Completed

O&M Under bidding Contract Awarded

% of Progress

Expected Completion Date

ICB 2.10 (Zone 1)

Rehabilitation of Distribution Network for non-revenue water reduction (including procurement of equipment/plant, and construction of DTW pump station) with O&M support DMA No.- 19 nos. Pipeline-341km Service connections- 32,725 nos.

√ Not Applicable

Not Applicable

Not Applicable

Not Applicable

Financial Evaluation Stage

Not Applicable Not Applicable

Not Applicable

ICB 2.11 (Zone 3,4,10)

Rehabilitati on of Distribution Network for nonrevenue water reduction (including procurement of equipment/plant, and construction of DTW pump station) with O&M support DMA No.- 16 nos. Pipeline- 453 km Service Connections- 41,971 nos.

√ Comments on Draft Detailed Design of DMA 320 was made on 27-12-18

To be commenced after approval of detailed design of DMAs Tentative start date: March 31, 2019

Not Applicable

Not Applicable

Bidding Finalized

Navana- Prathiba JV has been awarded on 4th April, 2018 and effective date for implementation on 21.06.2018 PMU/DMS conducted kick-off meeting with Contractor on 27 June 2018

No Physical Progress (0%)

16.04.2022

ICB 2.12 (Zone 7)

Rehabilitation of Distribution Network for non-revenue water

√ Bidding yet to be floated

To be commenced after approval of detailed

Not Applicable

Not Applicable

Bidding documents approved by ADB for 07 DMAs.

Not Applicable Not Applicable

Not Applicable

Page 14: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 8

Package Number

Components/ List of Works

Status of Implementation Contract Status On going Construction

Preliminary Design

Detailed Design

Ongoing Construction

Construction Completed

O&M Under bidding Contract Awarded

% of Progress

Expected Completion Date

reduction (including procurement of equipment/plant, and construction of DTW pump station) with O&M support DMA No. – 07 nos. Pipeline -(164 km) Service Connections- 16,144 nos.

design of DMAs

SBD prepared and sent to ADB on 20 November 2018 for approval.

Page 15: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 9

II. COMPLIANCE STATUS

A. Compliance status with National/Local statutory environmental requirements with Environmental Statutory Clearance

1. During meeting with Director, Environmental Clearance, DoE which was held on October 28, 2018 at DoE office, The Department of Environment provided exemption from Site Clearance considering high priority of the project and approved TOR on November 5, 2018 for conducting EIA in favour of DWSNIP (see Appendix 1). During reporting period, DWASA has started preparation of EIA report with assistance from DMS Consultants. After completion of EIA report. DWASA will submit EIA report to DoE for getting ECC prior to award of civil works contract.

2. During reporting period, respective contractors of ICB 2.8 – Zone 9 and ICB 2.11 –Zone (3,4 and 10) obtained road cutting permission from DNCC for trial pits (See Appendix 3). Removal of trees along the rehabilitation sites are considered subject to planting of native species in the same area after completion of civil work. Therefore, trees might be removed in some places to allow for appropriate workmanship but in that cases the current construction safety standards are to be maintained properly. The required clearances from relevant authorities will be obtained by the Contractors.

3. If utilities are to be shifted, then necessary permission will be required from DESA/DESCO, T&T by civil works contracts. During reporting period, ICB 2.11 confirmed that utilities may not required to shift during updating their IEE report for first batch (DMA 307, 311, 320 and 408).

B. Compliance of Safeguard Loan Covenants

4. The status of compliance of ADB’s major Loan Covenants related to environmental Safeguard is shown below:

Serial no. as per

loan agreement Program Specific Covenants Status / Issues

Procurement of Goods, Works and Consulting Services

Schedule 4 Item 7 Conditions for Issuance of Notice to Commence Works

DWASA shall not issue a notice to commence Works under:

(a) any Works contracts which

involves environmental

impacts until: Department of

Environment has granted the

approval of the IEE (including

approval of separate

environmental impact

Under Compliance

(a) DWASA has applied for

Environmental Clearance to

Department of Environment. The

Department of Environment

provided exemption from Site

Clearance considering high

priority of the project and

approved TOR for conducting

EIA. DWASA will submit EIA

report to DoE for getting ECC prior

Page 16: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 10

Serial no. as per

loan agreement Program Specific Covenants Status / Issues

assessment required to be

prepared under Bangladesh

law);

(b) Incorporated the relevant

provisions from the EMP into

the Works contract

to award of civil works.

(b) Incorporated EMP into the Civil works contract for ICB 2.8, ICB 2.9, ICB 2.10 and ICB 2.11

Safeguards Environment

Schedule 5 Item 5 The Borrower shall ensure or cause the DWASA to ensure that the preparation, design, construction, implementation, operation and decommissioning of the Project, and all projects’ facilities comply with (i) all applicable laws and regulations of the Borrower and the State relating to environment, health, and safety; (ii) the Environmental Safeguards; (iii) all measures and requirements set forth in the IEE, the EMP, and any corrective or preventative actions set forth in a Safeguards Monitoring Report.

Under compliance Document is prepared/or under preparation by complying all relevant National Laws, Safeguard Policy Statement (SPS 2009) of ADB for all five packages. The drafts of initial environmental examinations (IEEs) with related environmental management plans for five different contract packages (ICB 2.08, ICB 2.09, ICB 2.10, ICB 2.11 and ICB 2.12) have already been prepared and disclosed on the DWASA and ADB websites. IEE will be updated and revised in case of any change of scope and location. All measures and requirements as prescribed in IEE/EIA and EMP will be considered during implementation. Corrective or preventive action plans will be reflected in Environment Monitoring Report and project implementation authority (DWASA) will be taken care with assistance from DMS Consultants..

Human and Financial Resources to Implement Safeguards Requirements

Schedule 5 Item 9 The Borrower shall make available, or cause the DWASA to make available, all necessary budgetary and human resources to fully implement the EMP required.

Complied Budgetary provisions have been included in EMP of Packages ICB 2.8, ICB 2.9 and ICB 2.11 under DWSNIP. Environment, Resettlement and Gender Officer of Program Management Unit is in place Human resource (project consultant, i.e Environmental Specialist of DMS) for implementation of EMPs is in place for regular compliance.

Safeguards - Related Provisions in Bidding Documents and Works Contracts

Schedule 5 Item

10

The Borrower shall ensure, or cause the DW ASA to ensure, that all bidding documents and contracts for Works contain provisions that require contractors to:

( a) comply with the measures and requirements relevant to the contractor set forth in the IEE,

Under compliance

( a) Draft approved IEE, EMP for ICB 2.8, ICB 2.9 and ICB 2.11 is attached in Bidding documents. This process will be followed for all the

Page 17: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 11

Serial no. as per

loan agreement Program Specific Covenants Status / Issues

the EMP, the final RP (to the extent they concern impacts on affected people during construction), and any corrective or preventative actions set out in a Safeguards Monitoring Report;

(b) make available a budget for all such environmental measures; (c ) provide the Borrower with a written notice of any unanticipated environmental risks or impacts that arise during construction, implementation or operation of the Project that were not considered in the IEE, the EMP; (d) adequately record the condition of roads, agricultural land and other infrastructure prior to starting to transport materials and construction; and (e) reinstate pathways, other local infrastructure, and agricultural land to at least their pre-project condition upon the completion of construction.

packages within DWSNIP. In case of any change of scope, revised IEEs, EMPs will be prepared and corrective measures will be disclosed to contractor and same will be reflected in the “Environment Monitoring Report”.

) (b) Draft IEE indicates ind icat ive

budgetary provisions for implementation of EMP

(c) With the development of sub project and implementation, in case of additional impacts/risks due to change in scope/area, that will be reflected in the revised IEEs, EMPs and Environment Monitoring Report and accordingly project Executing Agency (DWASA) will inform the Construction Contractor (each Package) for taking relevant corrective measures.

(d) Haul roads will be marked properly (by avoiding residences and agricultural land) before commencement of transportation of materials.

(e) Pathways, land which are likely to be affected for a short period during implementation of the sub project will be restored by concerned construction contractor before acceptance of the work. Restoration status will be reflected in post construction monitoring report

Safeguards Monitoring and Reporting

Schedule 5 Item

11

The Borrower shall cause the D W A S A to do the following: (a) submit semi-annual Safeguards Monitoring Reports to ADB and disclose relevant information from such reports to affected persons promptly upon submission;

Under compliance

(a) Generally Environmental Monitoring Report is to be prepared after starting of implementation of the project but as per action plan of ADB, 2nd semi-annual Environmental Monitoring Report is prepared upto December 2018, , which mainly cover loan covenant part, monitoring format, status of method of statement for EMP

Page 18: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 12

Serial no. as per

loan agreement Program Specific Covenants Status / Issues

(b) if any unanticipated environmental and/or social risks and impacts arise during construction, implementation or operation of the Project that were not considered in the IEEs, the EMPs, promptly inform ADB of the occurrence of such risks or impacts, with detailed description of the event and proposed corrective action plan; and

(c) report any actual or potential breach of compliance with the measures and requirements set forth in the EMPs, promptly after becoming aware of the breach.

implementation.

) (b) With the development of project and implementation, in case of additional impacts/risks due to change in scope/area, will be reflected in revised IEEs, EMPs and accordingly Executing Agency (DWASA) will inform the ADB along with corrective action plan which will be reflected in the Monitoring Report.

(c) in case of any breach of compliance with the measures and requirements set forth in the EMP; DW ASA will promptly inform ADB and suitable corrective action plan will be planned.

Prohibited List of Investments

Schedule 5 Item

12

The Borrower shall ensure that no proceeds of the Loan are used to finance any activity included in the list of prohibited investment activities provided in Appendix 5 of the SPS.

Complied

All Packages under DWSNIP, there is

no violation of prohibited investment

activities as per ADB SPS (2009)

Appendix 5.

Labor Standards Health and Safety

Schedule 5 Item

13

The Borrower shall ensure that

core labor standards and the

Borrower’s applicable laws

and regulations are compiled

with during project

implementation. The borrower

shall include specific

provisions in the bidding

documents and contracts

financed by ADB under the

Project requiring that the

contractors, among other

things: (a) comply with the

Borrower's applicable labor

law and regulations and

incorporate applicable

Complied in document and to be complied during implementation Provision are included (as per EMP & BID document) to carry out HIV/AIDS awareness programs for construction contractor, application of all relevant labour laws for health and safety including child labour law and engagement of local labours (preferably from economically backward group) covering women labours. In case of any breach of provision, necessary corrective measures as per contract clauses shall be taken. All activities including awareness

Page 19: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 13

Serial no. as per

loan agreement Program Specific Covenants Status / Issues

workplace occupational safety

norms; (b) do not use child

labor; (c) do not discriminate

workers in respect of

employment and occupation;

(d) do not use forced labor;

(e) allow freedom of

association and effectively

recognize the right to

collective bargaining; and (f)

disseminate, or engage

appropriate service providers

to disseminate, information

on the risks of sexually

transmitted diseases,

including HIV/AIDS, to the

employees of contractors

engaged under the Project

and to members of the local

communities surrounding the

Project area, particularly

women. The Borrower shall

strictly monitor compliance

with the requirements set forth

above and provide ADB with

regular reports

program will be reflected in “Monitoring Report”.

C. Safeguards Implementation Arrangements

5. The PMU will have a Safeguard Implementation Unit (SIU) staffed with three officers - 1 Environmental Officer, 1 Social Officer, and 1 Gender Officer - at executive engineer level. The SIU will be assisted by relevant safeguard specialists in the DMS teams to implement safeguards.

6. The responsibilities of the Environmental Officer of SIU will ensure that (i) environmental safeguard issues are addressed; (ii) EMP/approved SEP is implemented; (iii) physical and non-physical activities under the subproject are monitored; and (iv) monitoring reports are prepared on time and submitted to ADB.

7. PMU will be supported by the Design Management and Supervision Consultants (DMS). An Environment Specialist will be engaged to ensure: (i) EMP/ approved SEP is implemented; (ii) surveys and measurements are undertaken; (iii) inspections and observations throughout the construction period are recorded to ensure that safeguards and mitigation measures are provided as intended; and (iv) statutory clearances and permits from government agencies/other entities are obtained prior to start of civil works.

8. During this reporting period, PMU and DMS Environmental Specialist has already

Page 20: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 14

been mobilized.

9. The Contractor will be required to:

(i) Submit Site environmental plan (SEP) covering proposed sites / locations for

construction work camps, storage areas, hauling roads, lay down areas, disposal areas

for solid and hazardous wastes

(ii) Comply with all applicable legislation, is conversant with the requirements of the EMP/

approved SEP;

(iii) Brief his staff, employees, and laborer about the requirements of the EMP/ approved

SEP;

(iv) Ensure any sub-contractors/ suppliers who are utilized within the context of the

contract comply with the environmental requirements of the EMP/ approved SEP.

The Contractor will be held responsible for non-compliance on their behalf;

(v) Supply method statements for all activities requiring special attention as specified

and/or requested by the DMS Environment Specialist during the duration of the

Contract;

(vi) Provide environmental awareness training to staff, employees, and laborers;

(vii) Bear the costs of any damages/compensation resulting from non-adherence to the

EMP/ approved SEP or written site instructions;

(viii) Conduct all activities in a manner that minimizes disturbance to directly affected

residents and the public in general, and foreseeable impacts on the environment.

(ix) Ensure that the PMU Environment Officer are timely informed of any foreseeable activities that will require input from the DMS Environment Specialist.

10. ICB 2.8 Contractor has already appointed Environment Specialist, Health and Safety Officer and Resettlement Specialist for implementation of EMP during works implementation. The details are follows:

Name Designation Contact no.

Nowrine Kaiser Environmental Officer +8801779542168

Tashrif Hossain Health, Safety Officer (HSO) +8801683505869

Md. Mizanur Rahman Milon Resettlement Specialist +8801622179631

11. Contractor of ICB 2.11 will appoint Environment, Health and Safety Officer before starting of construction works. Mr. Shyamal Kumar Ghosh, Quality Manager (email: [email protected];cell no. +8801711228753) is now in charge as nodal person for environmental safeguards. -add in the SEMR

12. Reporting Arrangement. Contractor of each package will monitor safeguard implementation daily basis, while DMS Consultants review safeguard implementation weekly. After review they advise contractor for corrective measures. Monthly report summarizing observation, compliance and corrective measures to be prepared by Environmental Officer of Contractor on monthly basis. Quarterly monitoring report will be

Page 21: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 15

prepared by the DMS Consultants on performance of contractors on EMP implementation. Then reports are forwarded to PMU from DMS for their observation and record. Based on monthly and quarterly reports and site observations, PMU through the support from DMS Consultants will review and consolidated the semi annual environment monitoring report for onward submission to ADB.

III. COMPLIANCE STATUS WITH THE OF ENVIRONMENTAL MANAGEMENT AND MONITORING PLAN

A. Preparation of Safeguards Documents

13. During this reporting period, DMS Consultants mobilized the Environmental Specialist to undertake environmental monitoring activities as outlined in the TOR. The activities carried out by the Environmental Specialist are summarized below:

Method of Statement for Updating EMP-

14. ICB 2.8 and ICB 2.11 contractors submitted method of statement for implementing site specific EMP. The Environmental Specialist reviewed the documents and suggested to incorporate the following aspects in the revised method of statement of EMP:

➢ Describe contractor’s own Environmental policy for implementation of EMP ➢ Provide methodology for necessary road cutting and excavation plan ➢ Mention necessary steps for security of the sites ➢ Submit traffic management plan ➢ Contractor’s supervision and management arrangements for the work; ➢ Utility Management and Contingency Plan, ➢ Describe PPE to be used on site ➢ Safety measures taken for the workers and the public.

15. During reporting period, both the contractors are requested to incorporate all comments made by DMS Consultants in their revised method of statement and resubmit for approval.

Updating IEE Report for ICB 2.8 and ICB 2.11

16. According to contractual obligations, Section 6, Article 2.14.1, the Contractor will update IEE Report for each DMA during detail design stage. During recent visit of ADB mission, it was decided by Safeguards Specialists of ADB that each contractor will update IEE report including site specific EMP for each batch wise.

17. As per contract, DMS Consultants will assist both PMU and contractor for updating IEE. During this reporting period, DMS consultants assisted contractor ICB 2.11 for updating IEE report for first batch (DMA No. 307, 311, 320 and 408). For updating IEE report, DMS consultants asked to ICB 2.11 to submit following information:

➢ Profile of DMA (Where DMA area is located, Thana and Ward no.; boundary, Roads,

name where pipe line will be laid down, Population, Household, cultural and

archeological site (mosque, mazar, school, college, temple and so on) major water

bodies (Canal, Lake etc.)

Page 22: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 16

➢ Provide necessary site layout map for each DMA showing exact location of the

contractor’s activities, site office, labor camps, material storage area, waste disposal point, toilet facilities etc.

➢ Provide detail contact of designated Environmental Officer, Health and Safety Officer

and Resettlement Officer

➢ Number of workers (skilled and unskilled);

➢ Details of plant, equipment and machinery, vehicles;

➢ Work duration (total, and activity-wise, for example for pipe laying, from excavation to

road resurfacing/testing);

➢ PPE (helmet, gloves, boots) details for each type of activities;

➢ Details of materials at each site (type and quantity);

➢ Construction waste/debris generated (details and quantity);

➢ Detail the sequence of work process (step-by-step) including specific details of each

work;

18. After getting above information from ICB 2.11, DMS consultants prepared and submitted updating IEE report of First batch to ADB through PMU on December 19 for their review and approval.

Revising IEE Report for ICB 2.12

19. The Initial Environmental Examination (IEE) for ICB 2.12 was prepared earlier (January 2016) considering 19 DMAs. During preparation of the report those 19 DMAs had not been demarcated by hydraulic area. Now ICB 2.12 implies for 7 DMAs and location of those DMAs has been selected. So, DMS consultants feel to revise some portions of those reports (mainly project description chapter) highlighting updated information and location of 7 DMAs. Other chapters in those reports would remain same. Before tendering process, revise IEE will be completed and included in the tender documents. After detail design of ICB 2.12, revised IEE will update subsequently.

20. During this reporting period, DMS consultants prepared revised IEE report and submitted to ADB through PMU for review and approval. ADB made the following major comments on revise IEE report of ICB 2.12.

• Pollution prevention and abatement

• EHS guidelines

• Submit environmental monitoring plan

• EMP budget

• Guidance on handling asbestos pipes

• EHS supervisor mobilization 8ICB The following Table shows the status of various

safeguard documents prepared by contractor/DMA consultants during this reporting

period.

21. DMS Consultants incorporated all comments from ADB environmental safeguard specialist on revised draft IEE Report of ICB 2.12 and submitted to ADB through PMU for approval.

Page 23: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 17

B. EMP Compliance Status

22. Field activities under ICB 2.8, ICB 2.9 and ICB 2.11 has not been started yet. During reporting period, site specific EMP including updating of IEE under first batch of ICB 2.11 has been prepared and submitted to ADB for approval. On the other hand, updating IEE including SEMP is ongoing of first batch under ICB 2.8. Site specific EMPs are generally revised semi annually as per progress of construction works. Appendix 4 shows Site Specific EMP for ICB 2.11 under first batch. 23. The compliance monitoring status for implementation of mitigation measures against impacts on air, water, soil environment, social and safety aspects is enclosed in Appendix 5. Summary compliance status of EMP application and actions/ corrective measures is presented in Table 3 below.

Table 3: Summary Compliance status of Environment Management and Monitoring Plan

Name of Package

EMP being Implemented

(Yes / No)

Overall Status of EMP Implementation

(Excellent/Satisfactory/ Partially Satisfactory/

Compliance/Below Satisfactory

Actions Proposed or continued/Additional Corrective Measures

Required (31st December 2018)

ICB 2.8 No - No activity at site

ICB 2.9 No - No activity at site

ICB 2.11 No - No activity at site

IV. ENVIRONMENTAL MONITORING AND EVALUATION

24. Site specific EMPs will be the basis for monitoring works. Prior to commencement of any civil work, the contractor will submit a compliance report to DMSC ensuring that all identified pre-construction environmental impact mitigation measures as detailed in the EMP will be undertaken. DMSC will review the report and thereafter PMU will allow commencement of civil works. The format of the monthly environmental monitoring report along with Sample Environmental Site Inspection Report and Sample Checklist for Construction safety are attached as Appendix 6. 25. For effective monitoring, selected environmental parameters have been identified as indicators which will be qualitatively and quantitatively measured and compared over a period of time in order to assess/ensure the compliance of EMP. The environmental performance indicators are physical, biological and social characteristics identified as most important in affecting the environment at critical locations all along the subproject locations. The parameters identified as performance indicators are:

o Air, noise and water quality

o Compliance to EMP

o Compliance to local/state/national environmental regulations

Page 24: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 18

26. During implementation process, performance monitoring fact sheet will be maintained against each possible environmental impact and will be attached with the monitoring report. Appendix 7 shows the Performance Fact Sheet for implementation of EMP at pre-construction and construction stage. 27. Before commencement of construction works, ambient air quality, noise level and water quality will be carried out by each contracts Packages which is considered as baseline data.

28. Base line air, noise and water quality monitoring will be carried out at respective DMA areas as per monitoring plan of updating IEE report. Result format of ambient air quality, noise level and water quality data are presented in Table 4. Table 5 and Table 6 respectively.

Table 4: Result Format Base line Ambient Air Quality Monitoring Data at DMA sites

DMA No. Date of Testing

Site Location

Parameters (Monitoring Results) PM10 PM2.5 SO2 NO2

Standard as per ADB Safeguard Policy Statement (µg/m3)

50 (24-h)

25 (24-h)

20 (24-h)

100-Commercial and mixed area 80-Residential and Rural area 30-Sensitive area

Table 5: Result Format Base line Noise Level Monitoring Data at DMA sites

DMA No. Date of Testing

Site Location

Noise Level in Leq dB(A) Day Time Night Time

Standard as per ADB Safeguard Policy Statement (µg/m3)

70- Commercial area 55- Mixed area 50-Residential 45-Silent Zone

60- Commercial area

45- Mixed area 40- Residential 35- Silent Zone

Table 6: Result Format Base line Water Quality Monitoring Data at DMA sites

DMA No.

Date of Testing

Site Location

Parameters PH Iron

mg/l Arsenic mg/l

Manganese mg/l

Chloride mg/l

BOD5

mg/l COD mg/l

Total Coliform mg/l

Page 25: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 19

Standard as per ADB Safeguard Policy Statement

6.5-8.5

0.3-1

0.01 0.1 150-600 4.0 must not be detectable in any 100 ml sample

V. MAJOR PROJECT ISSUES AND PROBLEMS: ENVIRONMENTAL CONTEXT

29. Construction activities for Contract Packages ICB 2.8, ICB 2.9 and ICB 2.11 have not been commenced yet. Till date, no major issues and problems have been encountered with, at each DMA locations.

VI. CONSULTATIONS AND DISCLOSURES CONDUCTED 30. Consultation and disclosure will be a continuous process throughout DWSNIP implementation (ICB 2.8, ICB 2.9, ICB2.11) involving public consultations and focus group discussions. Within the reporting period, no “during work” consultation and disclosures conducted at DMA locations since no physical work is started. Now the Civil works contractor has updated IEE report for ICB 2.11 under first batch (DMA 307, 311, 320 & 408) and submitted to ADB for approval. During reporting period, no local level consultation meetings were conducted for updating IEE due to general election in Bangladesh. Those consultation meetings will be conducted during January 2019. 31. Pubic consultation during construction/ implementation phase will be planned as per the requirement. Appendix 8 shows the blank consultation format for recording.

32. Orientation training program has been arranged for contractors, supervisors by DMSC’s Environmental Specialist on safety and environment. Minutes of the meeting is attached in Appendix 9.

33. There are series of informal discussions with DMSC engineering design team and PMU, PMU mainly on understanding current situation and optimum design to be adopted in order to attain the objectives of taking up the work items.

VII. GRIEVANCE REDRESS

34. A common grievance redress mechanism (GRM) has been established for social, environmental or any other subproject related grievances.

35. PMU will maintain a Complaint Cell headed by a designated Grievance Officer at its office. The Grievance Registration/Suggestion Form (Appendix 10 and Appendix 11) will be available at the Complaints Cell and in Zonal Offices and will also be downloadable from the DWASA website (link to DWASA website : https://dwasa.org.bd/dwsnip/).

Page 26: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 20

36. Grievances/ suggestions of affected persons can be dropped in suggestion boxes or conveyed through phone or mail. Affected Persons will also be able to register grievances – social, environmental or other, personally at Complaint Cell of head quarter (PMU Level) and Zonal offices (PCU Level) of DWASA. The Grievance Officer and designated official at the Zonal will be able to correctly interpret/record verbal grievances of non-literate persons and those received over telephone. The Complaint Cell will also serve as Public Information Centers, where, apart from grievance registration, information on the Project, subprojects, social and environmental safeguards can be provided.

37. The Grievance Officer will resolve simple issues and in case of complicated issues, consult/seek the assistance of the Environment/Social Officer of the PMU. Grievances not redressed through this process within one month of registration will be brought to the notice of the Project Director, DWSNIP.

38. Periodic community meetings with affected communities to understand their concerns and help them through the process of grievance redress (including translation from local dialect/language, recording and registering grievances of non-literate affected persons and explaining the process of grievance redress) will be conducted if required.

39. Grievance Redress Committee (GRC): GR committee set up notification has been done both for PMU and PCU level on 19.12.2018. The GRC committee are shown below:

GRC at PMU Level:

1. Project Director- DWSNIP - Convener 2. Deputy Project Director - Joint

Convener 3. Safeguard Focal Person(Concerned Executive Engineer) - Member 4. Environmental Expert, DMS, DWSNIP - Member 5. Resettlement Expert, DMS, DWSNIP - Member 6. Team Leader, Resettlement (NGO SAMAHAR) - Member 7. Affected Person (APs)/Representative (if applicable) - Invited

Specially-

GRC at PCU Level:

1. Executive Engineer (Concerned MODS Zone) - Convener 2. Safeguard Focal Person(AE/SDE, (Concerned MODS Zine) - Member 3. Team Leader, Resettlement (NGO SAMAHAR) - Member 4. Resettlement Officer of Concerned

Civil Works Contractor - Member 5. Ward Councilor/Female Ward Councilor

(Concerned City Corporation) - Member 6. Affected Person (APs - Invited Specially-

40. The office notification is attached in Appendix 12 (English version)

41. Grievances received and responses provided will be documented and reported back

Page 27: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 21

to the affected persons. The number of grievances recorded and resolved and the outcomes will be displayed/disclosed in the offices of the different Zonal office of DWASA and web. Project-affected people can also send their grievances directly to ADB through the Bangladesh Resident Mission and/or to ADB’s Accountability Mechanism.

42. To resolve all project related grievances and complaints a common social and environmental grievance redress mechanism will be in place. Common and simple grievances will be sorted out at project site level by the Contractor’s Resettlement Supervisor, supervision staff of PMU and project NGO within 7 days. More serious complaints will be sent to the safeguard officer at the PMU to be resolved in 14 days. Any unresolved grievances will be forwarded to GRC to be resolved within 21 days. Despite the project GRM, an aggrieved person shall have access to the country's legal system at any stage.

Figure 2: Flow Chart of GRM Process

Page 28: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 22

43. Consultation Arrangements. This will include group meetings and discussions with affected persons, to be announced in advance and conducted at the time of day agreed on with affected persons and conducted to address general/common grievances; and if required with the Environment/Resettlement Specialist of PMU/DMSC for one-to-one consultations. Non-literate affected persons/ vulnerable affected persons will be assisted to understand the grievance redress process, to register complaints and with follow-up actions at different stages in the process.

44. Record-Keeping. Records will be kept by PMU/PCU Office/Contractors’ site office of all grievances received including contact details of complainant, date the complaint was received, nature of grievance, agreed corrective actions and the date these were in effect, and final outcome.

45. The number of grievances recorded and resolved and the outcomes will be displayed/disclosed in the offices of the different MODS zone of DWASA and web. The phone number where grievances are to be recorded will be prominently displayed at the construction sites. 46. Periodic Review and Documentation of Lessons Learned. PMU will periodically review the functioning of the GRM and effectiveness of the mechanism, especially on the Project’s ability to prevent and address grievances.

47. All costs involved in resolving the complaints (meetings, consultations, communication and reporting / information dissemination) will be borne by PMU.

VIII. ISSUES AND ACTION PLAN

48. Experience from ADB-funded urban projects show complex social, economic, legal, institutional, and management issues in urban development – largely derived from realities of urban life in developing countries like Bangladesh. Urban projects typically consist of a variety of infrastructure such as roads, water, wastewater, solid waste, and slum improvement/upgrading activities. It is important to mention in this context that the final detailed engineering design in each sub project of DWSNIP will be prepared keeping in mind to avoid or minimize social and environmental impact as far as possible. However, since all the developments foreseen are city centric, it is difficult to avoid any impact whatsoever in densely populated towns or cities.

49. With the development of project under DWSNIP the action plan will be considered for timely and satisfactory environmental compliance. Sample suggestion & action plan format is shown in Table 7. Since major physical works under Package ICB 2.8, ICB 2.9 and ICB 2.11 not yet n started, action plan will be developed with the progress of the project.

Page 29: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 23

Table 7: Suggestion & Action plan considered for satisfactory Environmental Compliance

SI No. Issue Suggestion and

Recommendation Action to be

taken by Time Frame

1 Implementation of EMP

2 Health and Safety 3 Base line and

during construction – generation of air, noise and water quality data

4 Restoration of the construction area

5 Social relationship and public safety

IX. SAFEGUARDS TRAININGS

50. The Mission conducted a one-day training on environmental and social safeguards on 4 November 2018 and attended by PMU, consultants and contractors. The topics discussed ADB safeguards requirements including overview of ADB SPS, safeguards documents, and monitoring. The training helped the Mission, PMU, consultants and contractors to have a common understanding of next steps to be taken under the project. The PMU Environmental Officer and DMSC Environment Experts are expected to conduct safeguards induction to contractors upon mobilization, strictly monitor SEMP implementation particularly on workers health and safety, identify training needs and deliver safeguards training for project stakeholders. Capacity building on these topics will continue to be supported by ADB. The workshop minutes is attached in Appendix 13.

Page 30: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 24

APPENDIX 1: APPROVED TOR FROM DoE

Page 31: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 25

Page 32: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 26

Page 33: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 27

Page 34: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 28

APPENDIX –2A: Batch & DMA wise Status of Design and Implementation – ICB 2.8 (July to December, 2018)

Sl.

No. Name of Activities

Batch 1 Batch 2

DMA 903 DMA 904 DMA 906 DMA 907 DMA 905 DMA 908 DMA 913 DMA 912

1 Survey

Survey 75 %

comments

not given

Survey 75 %

comments

given

Survey 75 %

comments given

Survey 75 %

comments

given

survey in

progress,

45 %

survey in

progress,

30 %

survey in

progress,

10 %

Survey not yet

started

2 Model Design not

submitted

not

submitted

comments given

on draft model

not

submitted

not submitted not submitted not submitted not submitted

3 Detail Design not started not started not started not started not started not started not started not started

4 Joint Verification Survey Not done Not done done Not done Not Done Not Done Not Done Not done

5 Method of Statement Out of 10 Method Statements, 08 have been approved. Review on 02 Method Statements (Alleviation plan & Env. Management

Plan ) are in progress.

6 Road Cutting Permission

Trial pit

permission

got

Trial pit

permission

got

Trial pit

permission got

Trial pit

permission

got

not submitted

proposal for

pit permission

not submitted

proposal for

pit permission

not submitted

proposal for

pit permission

not submitted

proposal for pit

permission

7 Materials Mobilization &

Testing

PE pipe, fitting (1st batch, 1st consign.) & PE fittings (2nd cosign)

arrived at Ctg. port on 24.12.18 & 27.12. 18 respectively.

After arrival of PE pipe & fitting of 1st batch at site, CPP will process

for procurement of pipes, fittings & plants for 2nd batch DMAs

Sl.

No. Name of Activities

Batch 3

DMA 915 DMA 911 DMA 902 DMA 901 DMA 914

1 Survey Survey not yet

started

Survey not yet

started

Survey not yet

started

Survey not yet

started

Survey not yet

started

2 Model Design not yet started not yet started not yet started not yet started not yet started

3 Detail Design not yet started not yet started not yet started not yet started not yet started

Page 35: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 29

APPENDIX –2B: Batch & DMA wise Status of Design and Implementation – ICB 2.11 (July to December, 2018)

Sl.

No. Name of Activity

Batch 1 Batch 2

DMA 408 DMA 307 DMA 311 DMA 320 DMA 301 DMA 306 DMA 305 DMA 312

1 Survey Approved Approved Approved Approved Approved 75 %, final

report submit

55 %, report

not submitted

55 %, report

not submit

2 Model Design

comment given

on final model

comment

given on draft

model

comment not

given on final

model

Approved Final

Model

Draft Model

not submitted

Draft Model

not submitted

Draft Model

not submitted

Draft Model

not submit

3 Detail Design

Detail design

not submitted

Detail design

not submitted

Detail design

not submitted

comment made

on draft Detail

Design

Detail design

not submitted

Detail design

not submitted

Detail design

not submitted

Detail design

not submit

4 Joint Verification

Survey

Completed Completed not carried

out

Completed Completed Completed not carried

out

Completed

5 Method of

Statement

Out of total 10 Method “tate e ts, 0 ha e ee app o ed DM“ e ept fo E i o e tal Ma age e t Pla

6 Road Cutting

Permission

Trial pit

permission got

Trial pit

permission

got

Trial pit

permission

got

Trial pit

permission got

Trial pit

permission

got

permission

not get

permission

not get

permission

not get

7

Materials

Mobilization &

Testing

HDPE pipes & fittings (1st consign.) - shipment done on 22 -12- 18;

not arrived at Ctg. Port; HC Fittings (1st consign.)- LC opened on 4-12-

18. Shipment not yet made.

After arrival of PE pipe & fitting of 1st batch at site, NP JV will

process for procurement of pipes, fittings & plants for 2nd batch

DMAs

4 Joint Verification Survey Not Done Not Done Not Done Not Done Not Done

5 Method of Statement Out of 10 Method Statements, 08 have been approved. Review on 02 Method Statements

(Alleviation plan & Env. Management Plan) are in progress.

6 Road Cutting Permission Not Done Not Done Not Done Not Done Not Done

7 Materials Mobilization &

Testing

CPP will process for procurement of pipes, fittings & plants for 3rd batch

DMAs soon. Not Done

Page 36: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 30

Contd. APPENDIX 2B

Sl.

No. Name of Activity

Batch 3 Batch 4

DMA 1011 DMA 1001 DMA 313 DMA 1010 DMA 1009 DMA 409 DMA 1005 DMA 303

1 Survey

34.8 %, report

not submitted

55 %, report

not submitted

55 %, report

not submitted

48 %, report

not submitted

55 %, report

not submitted

48 %, report

not submitted

55 %, report

not submitted

75%,

comment

not made on

draft report

2 Model Design

Draft Model

not submitted

Draft Model

not submitted

Draft Model

not submitted

Draft Model

not submitted

Draft Model

not submitted

Draft Model

not submitted

Draft Model

not submitted

Draft Model

not

submitted

3 Detail Design Detail design

not submitted

Detail design

not submitted

Detail design

not submitted

Detail design

not submitted

Detail design

not submitted

Detail design

not submitted

Detail design

not submitted

Detail design

not submit

4 Joint Verification

Survey

not carried out not carried out not carried out not carried out not carried out not carried out not carried out not carried

out

5 Method of Statement Out of total Method “tate e ts, 0 ha e ee app o ed DM“ e ept fo E i o e tal Ma age e t Pla

6 Road Cutting

Permission

permission not

get

permission not

get

permission not

get

permission not

get

permission not

get

permission not

get

permission not

get

permission

not get

7 Materials Mobilization

& Testing

NP JV will process for procurement of pipes, fittings & plants for 3rd

batch DMAs soon.

NP JV will process for procurement of pipes, fittings & plants for

4th batch DMAs accordingly

Page 37: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN

Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 31

APPENDIX 3A: ROAD CUTTING PERMISSION-ICB 2.11

Page 38: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN

Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 32

Page 39: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN

Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 33

Page 40: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN

Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 34

Appendix 3A Contd.

Dhaka Water Supply Network Improvement Project (DWSNIP)

Design, Management & Supervision Consultant (DMS)

DWASA Bhaban, Dhaka

Following conditions are to be strictly fulfilled by the Road Cutting Agency

1. Sign Board is to be erected mentioning name of the Executing Agency, brief objective of the

excavation works, expression of sorrow for temporary inconvenience of the people, total

length of the excavation works and completion date of the works prior to commencement of

excavation at work site.

2. Deputy Commissioner (Traffic) of the relevant area and Officer-in-charge of the local Police

Station should be informed prior to commencement of excavation work.

3. Surrounding of the excavated work site should be protected by the designated tape and signal

light is to be installed.

4. Adequate light and Signal lights are to be arranged during excavation at night. Red light at

night time and yellow light at day time must be arranged. Necessary step is to be taken for

safe movement of the pedestrian and vehicles.

5. Adequate water should be sprinkled regularly on the restored surface of the road to avoid

dust causing inconvenience to movement of the people during excavation work and until

handing over site to Dhaka North City Corporation (DNCC)

6. Smooth arrangement for movement of the people and vehicles should be ensured by using

MS Sheet of required thickness during Cross Cutting of the road.

7. Modern equipment and technology should be used for early completion of the excavation

work.

8. Construction materials or goods should not be stored at excavation site which may create

problem for movement of the people and vehicles. Presence of field level Engineers and other

active Officers/workers of the Agency should be ensured at excavation site.

9. Excavated earth, rubbish etc. should be removed within 24 hours failure to which

transportation cost will be deducted from the security money as per condition of contract.

10. Excavated trench should be backfilled by sand with mechanical compaction just after the

completion of excavation work.

11. After completion of excavation work, the road surface is to be restored for suitably movement

of the vehicles by constructing brick soling and herring bone bond on top of the backfilled

trench.

Page 41: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN

Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 35

12. The road should be well maintained for movement of the transport and vehicles until handing

over to DNCC.

13. Road cutting Agency will take the responsibilities of the damaged service lines (if any) of other

Agencies and will be liable for activation of the damaged lines through emergency repair.

14. The Agency will also be liable for payment of compensation bill at a fixed rate provided by the

other Agencies during excavation work.

15. If additional bill for excavation work is determined based on joint measurement after the

work, then extra money/bill has to be deposited accordingly.

16. The agency must be liable to agree with the instant work withheld or dismissal of any approval

by the DNCC without showing any reason for the public interest.

17. The vehicles moving portion of the road pavement should be ensured not to covered or

damaged by the excavated soil or rubbish.

18. Dhaka WASA will have to bear the compensation cost for excavation of road during

construction of service lines at different households

Executive Engineer (civil)

Zone -5 (Kawran Bazar)

Dhaka North City

Corporation

Page 42: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN

Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 36

APPENDIX 3B: ROAD CUTTING PERMISSION-ICB 2.8

Page 43: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN

Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 37

English Version- Road Cutting Permission

Executive Engineer (civil)

Zone -1 (Uttara)

Dhaka North City

Corporation

Page 44: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 38

APPENDIX –4: Environmental Mitigation Measures Action Plan (ICB 2.11- First Batch)

Activity Mitigation Measures Responsible for Parameter to Monitor Frequency of

Monitoring

Location Remarks

Implementatio

n

Monitoring

Planning and Design Phase

Co t a to ’s Responsibility

• Be familiar with the present traffic congestion of Dhaka city, rules and regulation of Dhaka City Corporations (DNCC/DSCC) for preparation of road cutting plans before execution of works;

• Arrange for temporary water supply to every household as and when their water supply is disconnected or disrupted;

• Protect all underground and over ground utility services viz. telephone, electricity, gas, sewer, drainage, etc. from damage during execution of the contract. Necessary compensation to be paid to the respective organization(s) as per their prevailing rules and regulations.

Contractor DMS/PCU/PMU • Road cutting plan

• Arrangement for

temporary water

supply

• Disruption to utilities

As required in the

program of

performance

N/A • The

Contractor

have

conducted

survey to

identify the

type and exact

location of the

buried water

lines and also

other utility

services by

GPR Survey

and excavating

trial pit.

• The

Contractor has

already

completed all

types of

mentioned

surveys for

first batch

Page 45: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 39

Activity Mitigation Measures Responsible for Parameter to Monitor Frequency of

Monitoring

Location Remarks

Implementatio

n

Monitoring

• The following surveys must be completed prior to start of detailed design:

o Existing service connection survey

o Road surveys o Initial status

photography o Existing utilities

survey (tracing and/or excavation of trial pits

Pipe

replacement

rehabilitation,

and network

extension

• Existing AC pipes, where intact, shall be left in-situ and not disturbed. Where the AC pipe is damaged and where there is a risk of asbestos particles becoming airborne, the contractor shall follow all necessary procedures, guidelines and laws as laid out locally or by this EMP to contain and remove hazardous material.

• The network expansion into different residential / industrial areas will be through

Contractor DMS/PCU/PMU • Residual design life

and proposed

method of repair

• Inventory of AC pipes

As required in the

program of

performance

Each

DMA

sites

During survey,

about 766 m of

300 mm dia. for

DMA 307 and

about 989 m of

450 mm dia. for

DMA 320 AC

pipes has

identified.

DMS

Consultants

have developed

a guideline for

handling and

disposal of

Asbestos for

Page 46: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 40

Activity Mitigation Measures Responsible for Parameter to Monitor Frequency of

Monitoring

Location Remarks

Implementatio

n

Monitoring

trenchless or conventional trenching methods whereby the pipelines will be laid with a minimum cover depth of 1.0 metres.

guidance to be

applied in any

instances that

AC pipes are

found, to ensure

that appropriate

action is

taken(Appendix

7-IEE Report)

Working hours

and times

• All work in major roads and on minor roads that are heavily used by traffic will only be permitted at night between 7:00 pm and 7:00 am.

• All the minor roads and alley with less traffic may be considered for both day and night working provided alternative passageway can be maintained.

Contractor DMS/PCU/PMU Work hours As required in the

program of

performance

Each

DMA

sites

Road Crossing • Trenchless Technology method or open trench method are recommended for road crossings. In case of narrow streets, open trench method are recommended for road crossing to minimize the

Contractor DMS/PCU/PMU Construction method

statement

Construction

method of

statement

Each

DMA

sites

Page 47: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 41

Activity Mitigation Measures Responsible for Parameter to Monitor Frequency of

Monitoring

Location Remarks

Implementatio

n

Monitoring

traffic.

• Use Horizontal Directional Drilling (HDD) method after making sure that no other utilities are in the way of drilling equipment.

Road Cutting • Unnecessary road cutting should be avoided.

• The contractor has to take all necessary safeguards to avoid accidents at site, prevent loss/damage to all existing utilities like pipelines, telephone/gas/electric cables, poles etc. and any government or private property during the contract period.

• The contractor will apply for the road cutting permission to the road owning agency and shall give full effort and cost of road restoration and collect the road cutting permission for required days.

Contractors for

preparation of

road cutting

plan,

application for

permission,

and payment

for pavement

restoration

DMS/PMU

DNCC for

issuance and

monitoring of

pavement

compaction

• Road category along

pipe alignments

• Budget allocation for

pavement restoration

• Road Cutting Plan

• Road cutting

permission from

DNCC

Prior to start of

works (trial pit and

layour of pipes)

Each

DMA

sites

Contractor

obtained Road

Cutting and

traffic police

permission for

construction

trial pit

(Appendix 13-

IEE Report)

Page 48: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 42

Activity Mitigation Measures Responsible for Parameter to Monitor Frequency of

Monitoring

Location Remarks

Implementatio

n

Monitoring

Therefore the road cutting plans must be prepared by the contractor.

• No temporary or permanent works must proceed before the design and drawings are approved by the Project Manager and road cutting permission obtained from DNCC by Contractor.

• The contractor shall prepare a traffic management scheme (road closure program or diversions) and incorporate detail of traffic diversions and pedestrian routes, all traffic signs (for the regulation and for information) and road markings shall be ensured prior to start of road cutting.

Road Excavation • All excavations shall be done to the minimum dimension as required for safety and working facility

Contractors for

preparation of

road cutting

plan,

application for

DMS/PMU

DNCC for

issuance and

monitoring of

• Road category along

pipe alignments

• Budget allocation for

pavement restoration

Prior to start of

works (trial pit and

layour of pipes)

Each

DMA

sites

Page 49: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 43

Activity Mitigation Measures Responsible for Parameter to Monitor Frequency of

Monitoring

Location Remarks

Implementatio

n

Monitoring

• The excavation must be carried out in the most expeditious and efficient manner.

• The excavation shall be executed in such manner, that the contractor does not damage or interfere with existing services or structures. If damage or interference is so caused the contractor shall make arrangements with the supply and/or building owner to execute the repairs at the contractor’s own cost.

• All trench and pit excavations and other work shall be carried out keeping minimum sufferings for the traffic and within the limits of any existing road area shall be completed as rapidly as possible and, in the case of roads capable of carrying two or more lanes of traffic, not more than one half of the width of the

permission,

and payment

for pavement

restoration

pavement

compaction

• Road Cutting Plan

• Road cutting

permission from

DNCC

Page 50: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 44

Activity Mitigation Measures Responsible for Parameter to Monitor Frequency of

Monitoring

Location Remarks

Implementatio

n

Monitoring

carriage way shall be obstructed at any one time. In single lane roads, the contractor shall programme his work in such a manner that the minimum inconvenience is caused to those persons who have reasonable grounds for using the road.

• Road drains and channels shall be kept free from obstruction at all time.

• In case of excavation in

VIP and other large

roads, the trenches

and pits may need to

be covered by steel

plates to allow traffic

to pass during non

working periods. The

contractor must liaise

with the DNCC and the

responsible police to

familiarize themselves

and adhere to such

rules. All costs

involved to adhere to

Page 51: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 45

Activity Mitigation Measures Responsible for Parameter to Monitor Frequency of

Monitoring

Location Remarks

Implementatio

n

Monitoring

such rules shall be

borne by the

contractor.

• Pits and trenches not

backfilled at end of a

night shift, the

excavation must be

covered with steel

plates and in alleys

with wooden plates.

• It is preferable that

trench excavation

along roads be located

in footpaths or verges

adjacent to the road

rather than in the

carriage way itself.

Trench excavation

shall wherever

practicable be carried

out in such a way that

every part of the

excavation is at least

0.5m clear of existing

edges of the carriage

way.

• Where trench

excavation or any

other part of the works

obstructs any footpath

Page 52: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 46

Activity Mitigation Measures Responsible for Parameter to Monitor Frequency of

Monitoring

Location Remarks

Implementatio

n

Monitoring

or right- of-way, the

contractor shall

provide, at his own

cost, a temporary

footpath around the

obstruction to the

satisfaction of the

Project Manager.

• The contractor shall have

particular regard to the

safety of pedestrian,

livestock, and shall ensure

that all open excavation,

access routes and steep or

loose slopes arising from

the contractor's operations

are adequately fenced and

protected.

Trenchless pipe

installation

• Pipes shall be

installed by the

horizontal

directional drilling

(HDD) methods

where required.

Should survey

information indicate

that the method is

not feasible the

contractor shall

inform the Project

Manager and gain

prior approval for

an alternative

method or for

Contractor DMS/PMU • Program of

Performance

• Pipe Bursting Plan

• Plan for locating,

exposing and

reconnecting service

connections

• Proposed pit size and

location

• Temporary water

supply plan

• Plan for consumer

notification

As required in the

program of

performance

Each

DMA

sites

Page 53: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 47

Activity Mitigation Measures Responsible for Parameter to Monitor Frequency of

Monitoring

Location Remarks

Implementatio

n

Monitoring

open trench

method.

• Excavation

material

shall be

removed

from the

conduit as

the work

progresses.

No

accumulati

on of

excavated

material

within the

conduit will

be

permitted. • The contractor shall

provide sediment

and erosion control

measures in

accordance with

local environmental

legislation.

• The contractor

shall take all

necessary

precautions to

minimize the

damage to the

• Traffic Management

Plan

Page 54: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 48

Activity Mitigation Measures Responsible for Parameter to Monitor Frequency of

Monitoring

Location Remarks

Implementatio

n

Monitoring

adjacent

properties.

• The contractor shall

be responsible for

cleanup and

restoration

• Pits excavated to permit connection of bored pipe shall be backfilled, and disturbed areas shall be restored to their original state or better. Sections of sidewalks, curbs, and gutters or other permanent improvements damaged during HDD operations shall be repaired or replaced at the contractor’s expense.

Preparation of

catalogues,

installation and

O&M manuals

• The contractor shall supply catalogues and installation manuals for each type of pipes to DWASA at the time of submission the Operation and Maintenance manuals.

• All catalogues and manuals shall be printed in the English language

Contractor PMU/DMS Program of

Performance

Completion of civil

works and

decommissioning

N/A Mentioned in

bidding

documents

(Article 2.10.9-

Section 6.22-

E plo e ’s Requirements

Page 55: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 49

Activity Mitigation Measures Responsible for Parameter to Monitor Frequency of

Monitoring

Location Remarks

Implementatio

n

Monitoring

or accompanied by an English translation.

Prior to construction phase

Resettlement

Plan • Update Resettlement

Plan according to detailed design and submit to PMU/ADB for approval

• Implement updated RP approved by ADB

• No civil works will begin until all compensation to affected persons is paid

Resettlement

NGO with

assistance

from

contractor and

DMS

PMU/ADB • According to ADB SPS

2009- Involuntary

Resettlement

• Number of affected

person

• Compensation to

affected persons

• Number and type of

information

dissemination

activities

• Complaint from

stakeholders

After updating RP

for first batch,

before

commencement of

civil works

Each

DMA site

Updated RP for

first batch and

approved by

ADB

Preparation of

final IEE/EMP • Update IEE/site specific

environmental management plan (SEMP) based on detailed design

• Submit to ADB for approval and disclosure

• Contractor will

update with

the assistance

from DMS

PMU submit to

ADB

PMU • Detailed design

• ADB SPS 2009-

Environment and

contractual obligation

of Section 6 and

Section 8

• Site specific EMP

After completion of

detailed design and

prior to commence

of civil works

4 DMA

under

first

batch

Updated

IEE/EMP and

submitted to

ADB

Safeguards • The Contractor shall Contractor DMS- Hiring and actual work As work progresses N/A EHS Supervisor

Page 56: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 50

Activity Mitigation Measures Responsible for Parameter to Monitor Frequency of

Monitoring

Location Remarks

Implementatio

n

Monitoring

Supervisors appoint one EHS supervisor and one Resettlement Supervisor who will be responsible for assisting contractor in updating IEE/Site specific EMP; assisting NGO for updating RP, coordinating with DMS Environmental and Resettlement Specialist; community liaison, consultation with interested/affected parties, reporting and grievance redress on a day to day basis ; Timely submission monthly of monitoring reports including documentary evidence on EMP implementation such as photographs.

Environmental

Specialist and

Resettlement

specialist

will appoint

before

commencement

of civil works.

Consents,

permits,

clearances, No

objection

certificate

(NOCs) etc.

• Obtain all

necessary consents,

permits, clearance,

NOCs, etc. prior to

award of civil

works.

• Ensure that

all necessary

approvals

Contractor PMU(Environmen

tal Expert) and

DMS

(Environmental

Specialist)

All applicable permits

and approvals

Prior to

commencement of

civil works and as

necessary

Each

DMA

site,

Contract

o ’s office

Contractor

obtained Road

Cutting and

traffic police

permission for

construction

trial pit

(Appendix 14-

IEE Report)

Page 57: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 51

Activity Mitigation Measures Responsible for Parameter to Monitor Frequency of

Monitoring

Location Remarks

Implementatio

n

Monitoring

for construction to

be obtained

by contractor are

in place before

start of

construction

• Acknowledge in

writing and provide

report on

compliance all

obtained consents,

permits, clearance,

NOCs, etc.

• Include in detailed

design drawings

and documents all

conditions and

provisions if

necessary

• A copy of the

updated IEE/site

specific EMP

(SEMP) must be

kept on-site and

disclosed in DWASA

and ADB website

Page 58: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 52

Activity Mitigation Measures Responsible for Parameter to Monitor Frequency of

Monitoring

Location Remarks

Implementatio

n

Monitoring

Environmental

Monitoring

report

• Submit to ADB semi

annual

environmental

monitoring report

Contractor

with the

assistance

from DMS to

prepare

PMU submit to

ADB

PMU EMP

Contract provisions

Semi Annual N/A

Education of site

staff on general

and

environmental

conduct

• Ensure that all site

personnel have a

basic level of

environmental

awareness training.

• Staff operating

equipment (such as

excavators, loaders,

etc.) shall be

adequately trained

and sensitized to

any potential

hazards associated

with their task.

• No operator shall

be permitted to

operate critical

items of mechanical

equipment without

having been trained

by the contractor.

• All employees must

Contractor PMU and DMS Records of training Prior to start of

civil works and

every new

employee

N/A

Page 59: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 53

Activity Mitigation Measures Responsible for Parameter to Monitor Frequency of

Monitoring

Location Remarks

Implementatio

n

Monitoring

undergo safety

training.

Identification of

disposal sites

• The contractor shall

identify and request

PMU for approval of

disposal sites for pipes

to be replaced,

spoils/wastes and

other construction

related wastes

Contractor DMS/PMU Approved disposal sites As work progress As

identified

The Contractor yet to be provided the probable disposal point in site environmental plan for each DMA (Appendix 6-IEE Report) due to construction be not started yet. The contractor will remove surplus soil from the working site by truck and will dump to the NAVANA land development area and other selected places.

Establishing

equipment lay-

• Choice of location for

equipment lay- down

Contractor DMS/PMU Approval of location

and facilities

Prior to moving

onto site and

As

identified

Page 60: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 54

Activity Mitigation Measures Responsible for Parameter to Monitor Frequency of

Monitoring

Location Remarks

Implementatio

n

Monitoring

down and

storage area

and storage areas

must take into

account prevailing

winds, distances to

adjacent land uses,

general on – site

topography and water

erosion potential of

the soil. Impervious

surfaces must be

provided where

necessary

during site set-up

Sources of

materials

• Procure construction

materials from

recognize vendors

according to

specifications and

obtain approval from

DMS/PMU

Contractor DMS/PMU Bid documents As work progress As

Identified

Construction stage

Safety, security

and protection

of the

environment

• Take all necessary

precautions against

pollution or

interference with the

supply or obstruction

of the flow of, surface

or underground

water. These

Contractor DMS/PCU/PMU/

DoE

• ECC Provisions

• Program of

Performance

• Waste

Management Plan

• Complaints from

Community

• As required in

the Program of

Performance

• As work

progress

Project

influence

area of 4

DMAs

Page 61: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 55

Activity Mitigation Measures Responsible for Parameter to Monitor Frequency of

Monitoring

Location Remarks

Implementatio

n

Monitoring

precautions shall

include but not be

limited to physical

measures such as

earth bunds of

adequate capacity

around fuel, oil and

solvent storage tanks

and stores, oil and

grease traps in

drainage systems from

workshops, vehicle

and plant washing

facilities and service

and fuelling areas and

kitchens

• Establish sanitary solid

and liquid waste

disposal system

• Should any pollution

arise, clean up the

affected area

immediately at his

own cost and to the

satisfaction of the

Project Manager, and

pay full compensation

to any affected

parties.

Protection of • Every effort shall be Contractor DMA, PCU, PMU • ECC Provisions As work progress Project

Page 62: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 56

Activity Mitigation Measures Responsible for Parameter to Monitor Frequency of

Monitoring

Location Remarks

Implementatio

n

Monitoring

waterways made to ensure

that any

chemicals or

hazardous

substances do not

contaminate the

soil or water on

site

• Care must be taken

to ensure that

runoff from

vehicle or plant

washing does not

enter the

surface/ground

water.

• All concrete mixing

must take place

on a designated

impermeable

surface.

• No vehicles

transporting

concrete to the

site may be

washed on-site.

• No vehicles

transporting,

placing, or

• Complaints from

Community

influence

area of 4

DMAs

Page 63: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 57

Activity Mitigation Measures Responsible for Parameter to Monitor Frequency of

Monitoring

Location Remarks

Implementatio

n

Monitoring

compacting

asphalt or any

other bituminous

product may be

washed on-site.

• All substances

required for

vehicle

maintenance and

repair must be

stored in sealed

containers until

they can be

disposed of

removed from the

site.

Setting up of

Construction

Camp1

• Choice of site for the

o t a to ’s a p requires the Project

Manager permission

and must take into

account location of

local residents,

businesses and

existing land uses,

including flood zones

Contractor DMS,PCU, PMU Approval of Site layout

Plan and facilities

Prior to start of

civil works

As work progress

As

Identified

Presently

contractor

decide to

accommodate

labour camps at

their central

storage area at

Panchora More

Nagri

(Purbachal),

1 Careful planning of the construction camp can ensure that time and costs associated with environmental management and rehabilitation are reduced.

Page 64: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 58

Activity Mitigation Measures Responsible for Parameter to Monitor Frequency of

Monitoring

Location Remarks

Implementatio

n

Monitoring

and slip / unstable

zones. A site plan must

be submitted to the

Project Manager for

approval.

• If the Contractor

chooses to locate the

camp site on private

land, he must get prior

permission from both

the DMSC

Environment

Specialist and the

landowner.

• The contractor shall

make adequate

provision for

temporary toilets for

the use of their

employees during the

construction phase.

Such facilities, which

shall comply with

local authority

regulations, shall be

maintained in a clean

and hygienic

condition. Their use

shall be strictly

enforced.

Gazipur. Two

working sheds

are shown in

layout map of

central

store/ware

house

(Appendix 9-IEE

Report)

Page 65: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 59

Activity Mitigation Measures Responsible for Parameter to Monitor Frequency of

Monitoring

Location Remarks

Implementatio

n

Monitoring

• Bins shall have liner

bags for efficient

control and safe

disposal of waste

Handling of

surface water,

flooding event,

heavy downpour

etc.2

• Protect the working

area including pits,

trenches, materials,

machineries and

equipment from any

damage due to

inundation by

downpour.

• Ensure not to make

any congestion in the

open drains or natural

or artificial channels

by any of his activity.

• Take necessary

measure to bring the

site to the condition

prevailing before the

downpour without

delay. Necessary

measure has to be

taken so that storm

Contractor DMS, PCU,PMU • Program of

Performance

• Biweekly 6 weeks

running plan

• On site record book

As work progress Project

influence

area of 4

DMAs

2 Water logging problem exists during downpours and monsoon. Portions of roads may be flooded for prolonged periods after heavy downpours. The existing drainage

facilities of Dhaka are insufficient. Only about 30% of the it ’s populatio is o e ted to the se e age s ste . Dispose of aste ater through surface drains, or in low-

lying areas, natural drains, or water bodies that find their way to storm sewers. During monsoon period with medium to heavy downpour the roads are inundated for 1-6

hours.

Page 66: 47254-003: Dhaka Water Supply Network Improvement Project

DWSNIP- ADB Loan- 3397-BAN Semi Annual Environmental Monitoring Report – Jan-Jun 2018

Page | 60

Activity Mitigation Measures Responsible for Parameter to Monitor Frequency of

Monitoring

Location Remarks

Implementatio

n

Monitoring

water does not get

into the newly

installed pipelines.

• Be particular in

keeping updated

weather forecast and

maintain a record

book at site in which

weather condition is

recorded.

Handling of

Excavated

materials

• The Contractor can

process the

excavated materials

at the disposal site

and use these as

selected backfill

materials

• Hauling vehicles

must always be

present at the

excavation site

Contractor DMS, PCU, PMU • Program of

Performance

• Biweekly 6 weeks

running plan

• On site record book

• Complaints from

stakeholders

Prior to start of

civil works

As work progress

Each

DMA

site,

disposal

site

Minimization of

public

disturbance

• Restrict his work to

the sites allocated

to him, and keep

the sites accessible

for inspection by

competent

authority at any

time.

Contractor DMS, PCU, PMU • Program of

Performance

• Inventory of

utilities, signs and

barriers

• Access to paths,

steps, crossings or

drives for all

• Prior to start of

civil works (per

pipe section)

• During pipe

laying/bursting

• As work

progress

Each

DMA

sites