46064-002: technical and vocational education and training

49
Social Safeguard Monitoring Report Semestral Report July 2018 Cambodia: Technical and Vocational Education and Training Sector Development Project Prepared by Ministry of Labour and Vocational Training for the Royal Government of Cambodia and the Asian Development Bank. This Social Safeguard monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Upload: others

Post on 12-Mar-2022

3 views

Category:

Documents


0 download

TRANSCRIPT

Social Safeguard Monitoring Report

Semestral Report July 2018

Cambodia: Technical and Vocational Education and

Training Sector Development Project

Prepared by Ministry of Labour and Vocational Training for the Royal Government of Cambodia

and the Asian Development Bank.

This Social Safeguard monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

2

NOTE

(i) In this report, "$" refers to US dollars.

Table of content Page

Contents I. Executive Summary ............................................................................................................ 5

II. Project Overview, General safeguard matters ..................................................................... 7

2.1. Project Overview .......................................................................................................... 7

2.2. Project Progress .......................................................................................................... 9

2.3. Safeguard Plans Implementation Arrangements .........................................................13

2.4. Updated EMP Incorporation of Safeguards Requirements into Project Contractual Arrangements ........................................................................................................................14

III. Environmental Performance Monitoring ..........................................................................15

3.1. Status of EMP implementation (Mitigation Measures) .................................................15

3.1.1. Detailed design-construction stage: .....................................................................15

3.1.2. Construction and operations: ...............................................................................15

3.2. Health and Safety .......................................................................................................21

3.3. Environment Effect Monitoring ....................................................................................22

IV. Involuntary Resettlement Performance Monitoring .........................................................23

V. Indigenous People Performance Monitoring .......................................................................23

VI. Compliance with safeguards related project covenants ..................................................33

VII. Public consultation, Information Disclosure, Capability Building .....................................35

7.1. Meetings and consultations .....................................................................................35

7.2. On-job training/capacity building to involved officers, workers and site engineers ...35

VIII. Grievance Redress Mechanism ......................................................................................36

IX. Conclusion .....................................................................................................................36

X. Attachments .......................................................................................................................37

Annex-1: Field visits to public TVET institutions: ....................................................................37

Annex-2: Environmental Monitoring checklists for actual civil works implementations ...........37

Annex-3: Photos of safeguards and IPP activities:.................................................................41

Annex-4: Field report of safeguards orientations to staff and workers on site: .......................43

3

ABBREVIATION RGC Royal Government of Cambodia ADB Asian Development Bank ADF Asian Development Fund AFD Agence Française de Développement AHs Affected Households AM ADB Accountability Mechanism APs Affected People BIT Battambang Institute of Technology CARM ADB Cambodia Resident Mission CBT Competency based training CBTA Competency based training and assessment CDS Community Development Specialist CHSP Community Health and Safety Plan CIEDI Cambodia India Entrepreneurship Development Institute CLAC Commune Land Acquisition Committee COE Centers of Excellence COI Corridor of Impact CQF Cambodian Qualifications Framework CRO Complaint Receiving Officer CW Civil Work DDS Detailed Design Supervision DGTVET Directorate General Technical Vocational Education and Training DLMI Department of Labour Market Industry DMF Design and monitoring framework EA Executing Agency EEO Equal Employment Opportunity EM Ethnic Minorities GAP Gender Action Plan GRM Grievance Redress Mechanism Ha Hectare HHs Households ILU Industrial Liaison Unit IP Indigenous people IPP Indigenous people plan IPPF Indigenous people planning framework IRC Inter-Ministerial Resettlement Committee LARF Land Acquisition and Resettlement Framework M&E Monitoring & Evaluation MEF Ministry of Economy and Finance MIS Management Information System NEA National Employment Agency NGOs Non-governmental organizations NPIA National Poly Technic Institute of Angkor

4

NVIB National Vocational Institute of Battambang OHSP Occupational Health and Safety Plan PAI Project administration instructions PAM Project administration manual PI Polytechnic Institute PIU Project implementation unit PIPP Polytechnic Institute of Pursat Province PIPS Polytechnic Institute of Preah Sihanouk PPI Preah Kosamak Poly Technic Institute RPL/RCC Recognition of Prior Learning/Recognition of Current Competency RPF Resettlement Policy Framework PTC Provincial Training Centre QBS Quality based selection QCBS Quality- and cost based selection RC Reinforced Concrete RP Resettlement Plan RTC Regional Training Centre SBD Standard bidding documents SBP Skill Bridging Program SDR Special Drawing Rights SPS ADB’s Safeguard Policy Statement (June 2009) SSC Sector Skill Council TENA Training Employment Need Assessment TVET Technical Vocational Education and Training TVETSDP Technical Vocational Education and Training Sector Development Project TOR Terms of references VC Vocational Certificate VSTP Voucher Skill Training Program

5

I. EXECUTIVE SUMMARY

1. The Technical and Vocational Education and Training Sector Development Project (TVETSDP) supports the Royal Government of Cambodia’s commitment to the development of high-quality, skilled and capable human resources to meet the immediate and long-term needs of economic growth and socio-economic development. The Project/Program is comprising of four outputs include output-1: increased access to TVET programs (5 sub outputs); output-2: improved quality and relevance of the TVET system (7 sub outputs); output-3: increased involvement of employers in technical and vocational education and training delivery (3 sub outputs); and output-4: strengthened governance and management of TVET delivery (5 sub outputs). 2. To achieve the objectives mentioned above, the buildings, infrastructures, amenities, and facilities within the premises of public TVET institutions are needed to new build and upgrading to serve for the Project/Program. The environmental implication is category B, due to the implementation of civil works, therefore, the environmental safeguard is triggered to cope with the civil work implementations, particularly, the Environmental Management Plan (EMP) in Initial Environmental Examinations (IEE). 3. The Project/Program civil works of building constructions and upgrading included the additional financing of ADF have been made a provision to the 23 public TVET institutions and DGTVET, which are the original ADB financing covers 13 public TVET institutions and additional financing of AFD covers 18 public TVET institutions, both are overlapping each other’s. The following table is delineated the scopes of civil works, status, building types within outputs/sub outputs of the Project/Program. 4. During this semi-annual report, from 1st January to 30th June 2018, there have been four public TVET institutions implementing civil work as well as environmental safeguards’ implementations including: (i) woman’s dormitory building in NPIA/Siem Reap; (ii) woman’s dormitory in Bateay Mean Chey PTC; (iii) new classroom building in BIT have been awarded contract since 27 December 2017 to T.S.K. Construction Co., Ltd and commencement of civil work during mid-January 2018; and (iv)woman’s dormitory and workshop building in Koh Kong PTC has been awarded contract to General Building Construction Co., Ltd (G.B.C.) on 27 December 2017 and started civil work during mid-January 2018. 5. Awarded contractors were orientated/introduced about social and environmental safeguards on 23rd January 2018 at project office in Phnom Penh, the attention was paid to environmental monitoring checklists and environmental management plan (EMP) implementations. The commencement of civil works is taken longer time for piling and method of piling, whether using diesel hummer machines driven or pressing, this is taking long negotiation between the executing agency (EA) and the contractor. The safeguards specialist together with involved officers have scheduled visiting Battambang Institute of Technology (BIT/Battambang) on 9 May 2018, National Polytechnic Institute of Angkor (NPIA/Siem Reap) on 11 May 2018, and Koh Kong Provincial Training Center (PTC) on 9-12 July 2018. The main objective of these visits is to assess the EMP implementations by contractors, environmental monitoring checklist completions, orientating and introducing environmental safeguards, Personal Protective Equipment (PPE) and personal hygiene, provision of adequate drinking water supply and sanitation facilities, implementation of occupational health and safety to all staff and workers at campsites.

6

6. The corrective actions have been made to staff and workers in the campsites including the proper wearing of safety helmets, safety boot/shoes and strictly implementing the EMP particular the pollution from used engine oil needs to proper maintaining, human waste should be in appropriate septic tanks/chambers, littering the solid waste should be in proper rubbish bins. 7. Due to the locations of civil works constructions are far from residents and premises of public TVET institutions are fencing enclosure so far there is no complaint yet from likely affected persons/households for social and environmental safeguards as well as IPP. 8. The activities planned for next reporting period will be dealing with and following up the environmental issues occurring during current civil works implementations and to cope with IPP target indicators set in Project/Program’s outputs/sub outputs. The Project is acceptable and will create positive social impacts to women, indigenous people and the poor by increasing their access to education, thus improving their quality of life.

9. The delays in civil works implementation is lesser implementation of social and environmental aspects this is due to all involved primary stakeholders- (EA, IA, contractors and consultants) have been tried to deal with the civil works to push through in according with proposed schedule. The commencement of civil works for building constructions are pilings which are taken longer times to complete them and the contractors used diesel hummer machines/driven machine and few machines’ operators.

7

II. PROJECT OVERVIEW, GENERAL SAFEGUARD MATTERS

2.1. Project Overview

10. The Technical and Vocational Education and Training Sector Development Project (TVETSDP) was approved by ADB on 26 September 2014 with policy-based loan and project loan of USD30 million and co-financing from AFD with amount of USD 15 million approved by the Board of Director on 17 June 2015. 11. The TVETSDP has been supported the Royal Government of Cambodia (RGC) to address equity and quality issues facing the technical vocational education and training (TVET) system through: (i). Increased access to TVET programs, particularly for women, poor or vulnerable youths, and Indigenous People. (ii). Improved quality and relevance of the TVET system; (iii). Increased Involvement of Employers in TVET Delivery and (iv). Strengthened governance and management of TVET delivery. The Project supports RGC’s commitment to the development of high-quality, skilled and capable human resources to meet the immediate and long-term needs of economic growth and socio-economic development. 12. The civil works of building constructions for workshops, new classrooms, woman’s dormitories, center of excellences and upgrading of existing buildings as well as infrastructure/amenities are providing to the 23 public TVET institutions and DGTVET have been built that are triggered in EMP/IEE implementations. The table below is delineated the civil works of the Project/program that public TVET institutes’ obtaining:

No. Building type in

sub-output Original ADB financing/TVETSDP

Additional financing of AFD/TVETSDP-AF

1

Women's

Dormitory within Sub-output-1.4: Piloting Women’s dormitories

A woman’s dormitory building construction in NPIA: Civil work is ongoing, by commencing on mid-January 2018, scheduling to complete on Q4 2018. The T.S.K. construction Co., Ltd has been awarded contract on 27 Dec 2017 to implement the civil work.

Not yet start a woman’s dormitory building construction in NVIB

2

A woman’s dormitory building construction in Koh Kong PTC: Civil work is ongoing, by commencing on mid-January 2018, scheduling to complete on Q4 2018. The General Building Construction Co., Ltd (G.B.C.) has been awarded contract on 27 Dec 2017 to implement the civil work.

Not yet start a woman’s dormitory building construction in Kratie PTC

3

A woman’s dormitory building construction in Banteay Meanchey PTC: Civil work has been delayed due to the piling methods until end of June 2018. The T.S.K. construction Co., Ltd has been awarded contract on 27 Dec 2017 to implement the civil work.

Not yet start a woman’s dormitory building construction in Kandal PTC

1 New Building.

within Sub output 2.6:

Improving learning environment in TVET facilities.

Not yet start a new building construction in Tboung Khmum PTC

2 Not yet start a new building construction in CIEDI/Phnom Penh

3 Not yet start a new building construction in NPIA/Siem Reap

1 Classroom

Building. within Sub

output 2.6: Improving

A new classroom building construction in BIT: Civil work is ongoing, by commencing on mid-January 2018, scheduling to complete on Q4 2018. The T.S.K.

8

learning environment in TVET facilities.

construction Co., Ltd has been awarded contract on 27 Dec 2017 to implement the civil work.

1

Workshop within Sub output 2.6:

Improving learning environment in TVET facilities.

A workshop building construction in Koh Kong PTC: Civil work is ongoing, by commencing on mid-January 2018, scheduling to complete on Q4 2018. The General Building Construction Co., Ltd (G.B.C.) has been awarded contract on 27 Dec 2017 to implement the civil work.

Not yet start a workshop building construction in NVIB

2

The 9 workshop buildings in 9 public TVET institutions were completed civil works since November 2017, included: -Kampong Speu PTC -Kampong Thom PTC -Kandal PTC -NPIA/Siem Reap -Kampong Cham Polytechnic Institute -Polytechnic Institute of Pursat Province/PIPP -Polytechnic Institute of Preah Sihanouk/PIPS -Banteay Meanchey PTC and -BIT

Not yet start a workshop building construction in Kratie PTC

3 Not yet start a workshop building construction in Prey Veng PTC

4 Not yet start a workshop building construction in Tboung Khmum PTC

5 Not yet start a workshop building construction in Oddar Meanchey PTC

6 Not yet start a workshop building construction in Kep PTC

7 Not yet start a workshop building construction in Kampong Chhnang PTC

8 Not yet start a workshop building construction in Pailin PTC

9 Not yet start a workshop building construction in JVC-Phnom Penh

10

1

Upgrading 18

TVET Institutions.

within Sub output 2.6:

Improving learning environment in TVET facilities.

Not start yet in Kampong Cham Polytechnic Institute

2 Not start yet in Kampong Speu PTC

3 Not start yet in Kampong Thom PTC

4 Not start yet in Kandal PTC

5 Not start yet in NPIA/Siem Reap

6 Not start yet in Koh Kong PTC

7 Not start yet in Polytechnic Institute of Pursat Province/PIPP

8 Not start yet in Polytechnic Institute of Preah Sihanouk/PIPS

9 Not start yet in Banteay Meanchey PTC

10 Not start yet in NVIB/Prey Konkla

11 Not start yet in Kratie PTC

12 Not start yet in Prey Veng PTC

13 Not start yet in Tboung Khmum PTC

14 Not start yet in Oddar Meanchey PTC

15 Not start yet in Kep PTC

16 Not start yet in Kampong Chhnang PTC

17 Not start yet in Pailin PTC

18 Not start yet in JVC-Phnom Penh

1

DGTVET

rehabilitation. within Sub output 2.6:

Improving learning environment in TVET facilities.

Not start yet in DGTVET building- Phnom Penh

9

1 COEs

establishment within Sub output 3.3: Establishment of Centers of Excellence

Not start yet in NPIC- Phnom Penh-renovation

2 Not start yet in PPI-Phnom Penh-renovation

3 Not start yet in BIT- renovation building (Ca)

4 Not start yet in NPIA/Siem Reap Source: Civil work status of TVETSDP consultant team

2.2. Project Progress 13. As mentioned in previous section, the overall TVETSDP’s outputs included (i). Increased access to TVET programs, particularly for women, poor or vulnerable youths, and Indigenous People. (ii). Improved quality and relevance of the TVET system; (iii). Increased Involvement of Employers in TVET Delivery and (iv). Strengthened governance and management of TVET delivery. 14. The TVETSDP Project/program civil works of construction included the additional financing of ADF have been made the provision to the 23 public TVET institutions and DGTVET, and categorization for this Project/program is B, therefore it is triggered to implement the environmental safeguards, the attention has been paid to EMP implementations in IEE including: Construction of three women dormitories and new classroom building with water and sanitation packages in the Provincial Training Centers (PTCs) of Koh Kong, BIT, Banteay Meanchey, and NPIA in Siem Reap under TVETSDP-(current civil works implementations, by commencing during mid-January 2018 and will complete during Q4 2018, the General Building Construction Co., Ltd has been awarded contracted for Koh Kong and T.S.K. construction Co., Ltd has been awarded contract for Banteay Meanchey, BIT/Battambang and NPIA in Siem Reap). 15. Construction of nine workshops with specialized equipment packages in nine public TVET institutions of Banteay Meanchey, Kampong Cham Polytechnic Institute, Kampong Speu, Kampong Thom, Kandal, Koh Kong, Polytechnic Institute of Pursat Province, NPIA and Sihanouk/PIPS under TVETSDP (completed civil works at end of November 2017); and other nine workshop at PTCs of Prey Veng, Tboung Khmum, Kratie, Kep, JVC in Phnom Penh, Kampong Chhnang, NVIB, Pailin, and Oudar Meanchey under TVETSDP-AF (will begin in Q3 2018). 16. New construction of Center of Excellence at NPIA (will start civil work mid-July 2018, Reaksmey Keo Meas construction Co., Ltd has been awarded contract to implement this COE building in NPIA) and renovations of existing buildings for Center of Excellence at BIT (will start civil work in mid-July 2018, the O.S.C. construction Co., Ltd has been awarded contract to implement the civil works), and renovation of existing building at NPIC and PPI (will begin in Q4 2018), all Center of Excellences are under TVETSDP. And new classroom buildings at Tboung Khmum, CIEDI in Phnom Penh, and NPIA/Siem Reap under TVETSDP-AF (will commencement civil works in Q4 2018); and Rehabilitation of the DGTVET building under TVETSDP, (will start in early 2019). 17. There have been four public TVET institutions implementing civil work as well as social and environmental safeguards’ implementations during January to June 2018 included woman’s dormitory building in NPIA/Siem Reap. The T.S.K. Construction Co., Ltd has been awarded contract since 27 December 2017 and commencement of civil work during mid-January 2018, T.S.K. also awarded contract on 27 December 2017 for woman’s dormitory in Banteay Mean Chey PTC, but has been delayed in civil work implementation until early July 2018 due to the

10

matter of piling with rocky ground and new classroom building in BIT on 27 December 2017, by starting civil work on mid-January 2018. Last one is the woman’s dormitory and workshop buildings in Koh Kong PTC, the contract has been awarded to General Building Construction Co., Ltd (G.B.C.) on 27 December 2017 and started civil work in mid-January 2018.

18. The EA has employed engineers as TVETSDP team of consultants to overall management, supervisions and overseeing the quality of building constructions, speed up the works process according to proposed work plan. The awarded contractors have site engineers and site manager to daily implement the civil works. The contractors are also implementing the safeguards aspects-particularly the environmental monitoring checklist and EMP implementations, oversee by TVETSDP engineers team of consultants. The following tables indicated the status of civil work progress and completions:

SUMMARY CIVIL WORKS PROGRESS STATUS AS OF 30 June 2018

ID. Construction type No. Name of institution Status as of 30 June-2018

A Women dormitory

1 Koh Kong PTC

Under construction 2 NPIA (Siem Reap)

3 Banteay Meanchey PTC

4 Kandal PTC

Will start construction on 16 July 2018 5 Kratie PTC

6 NVIB (Battambang)

B New classroom building 1 BIT (Battambang) Under construction

C COE 1 NPIA (Siem Reap)

Construction will start on 9 July 2018 2 BIT (Battambang)

D Workshop building 1 Koh Kong PTC Under construction

E Workshop building (AFD)

1 Pailin PTC

Starts bidding process in July 2018

2 Kampong Chhnang PTC

3 NVIB (Battambang)

4 Prey Veng PTC

5 Kratie PTC

6 Tbong Khmom PTC

F COE 1 PPI (Phnom Penh) Starts bidding process in July 2018

G Workshop building (AFD)

1 JVC

Ongoing designs and bids preparation 2 Kep PTC

3 Oddar Meanchey PTC

H New (classroom) Building

1 Tboung Khmum PTC

Ongoing designs and bids preparation 2 NPIA (Siem Reap)

3 CIEDI (Phnom Penh)

J COE 1 NPIC Ongoing design and bid preparation

K

Upgrading works-1

1 PIPP/Pursat

Ongoing designs and bids preparation

2 Banteay Meanchey PTC

3 NVIB (Battambang)

4 Pailin PTC

Upgrading works-2 1 Kandal

2 Kampong Speu PTC

11

3 Kampong Chhnang PTC

Upgrading works-3

1 Preah Sihanouk/PIPS

2 Koh Kong PTC

3 Kep PTC

Upgrading works-4

1 Kampong Thom PTC

To start sites preliminary survey Q3-18 2 NPIA (Siem Reap)

3 Oddar Meanchey PTC

Upgrading works-5

1 Tboung Khmum PTC

To start sites preliminary survey Q3-18 2 Kratie PTC

3 Prey Veng PTC

4 Kampong Cham PI

Upgrading works-6 1 JVC To start site preliminary survey Q3-18

I Rehabilitation 1 DGTVET Headquarters To start in Q4-18

Source: Civil work status of TVETSDP consultant team

ID. Construction

type

No. Name of institution Status as of 30 June-

2018

Comments

A Workshop

building

1 Kandal PTC Construction

completed

Defect liabilities

inspection in

June-18

2 Kampong Speu PTC

3 Preah Sihanouk/PIPS

B Workshop

building

1 PIPP/Pursat Construction

completed

Defect liabilities

inspection in Oct-

18

2 BIT

3 Banteay Meanchey PTC

C 1 Kampong Cham PI

2 Kampong Thom PTC

3 NPIA (Siem Reap) Source: Civil work status of TVETSDP consultant team

Locations of Public TVET Institutions:

No Project locations Village Commune/Sangkat District /Town Province

01 DGTVET Building Russian Blvd Toek La’ak I Tuol Kouk Phnom Penh 02 Banteay Meanchey PTC Keap Teuk Tla Serey Saophoan Banteay Meanchey 03 Battambang Institute of Technology Romchek 4 Ratanak Battambang Battambang 04 Kampong Cham PTC 7 Kampong Cham Kampong Cham Kampong Cham 05 Kampong Speu PTC Tompoung Kaheng Samraong Tong Kampong Speu 06 Kampong Thom PTC Archar Leak Archar Leak Stueng Saen Kampong Thom 07 Kandal PTC Preak Tnout Takhmao Takhmao Kandal 08 Koh Kong PTC 1 Smachmeanchey Koh Kong Koh Kong 09 PIPP/Pursat Chamkachek Phtesprey Pursat Pursat 10 Siem Reap PTC Chongkoesour Slakrom Siem Reap Siem Reap 11 Polytechnic Institute of Preah Sihanouk 2 3 Preah Sihanouk Preah Sihanouk 12 Prey Veng PTC Lek Mouy (1) Kampong Leav Preveng Preveng 13 Tboung Khmum PTC Nikum Leu Sra Lop Tboung Khmum Tboung Khmum

12

Source: Safeguards field assessment and investigation/dynamic updating

Land Area of the public TVET institutions

Source: Safeguards field assessment and investigation/dynamic updating

Table 1: Project Overview, Snapshot of Project Progress

Project Number: Title:

ADB Loan No. 3166&3167-CAM (SF)&8305-CAM Technical and Vocational Education and Training Sector Development Project (TVETSDP)

Safeguards Category

Environment B

Indigenous Peoples B- beneficial

Involuntary Resettlement

C

Reporting period: 1st January to 30th June 2018

Last report date: 31st December 2017

14 Kratie PTC O’Reusey Pi O’Reusey Kratie Kratie 15 Kep PTC Thmey Preythom Kep Kep 16 National Vocational Institute of

Battambang Andong Pring O’marll Battambang Battambang

17 Pailin PTC O’Tapuk Krom Tul Lvea Pailin Pailin 18 Oudar Meanchey PTC Borey Rathabal Samrong Samrong Odor Meanchey 19 National Poly Technic Institute of

Angkor Prey Kuy Ampil Siem Reap Siem Reap

20 Kampong Chhnang PTC Tulkralagn Kampong Chhnang

Kampong Chhnang

Kampong Chhnang

21 Cambodia-India Entrepreneurship Development Institute (CIEDI)-PP

Chong Thnal Khang Lech

Teuk Thla Sensok Phnom Penh

22 Japan Vocational Center (JVC) Prek Samrong Chroy Changva Chroy Changva Phnom Penh

Public TVET Institutions Land Area, m2 Number of Buildings

Number of Rooms

Banteay Meanchey PTC 7, 408 4 9 Battambang Institute of Technology-BIT 130, 000 8 16 National Vocational Institute of Battambang, office 3, teachers house 6

56,924 9 11

Kampong Cham PTC (existing) 2, 500 2 17 Kampong Cham Polytechnic Institute 7, 000 1 3 Kampong Chhnang 10,718 3 6 Kampong Speu PTC 14, 375 3 11 Kampong Thom PTC 20, 640 6 16 Kandal PTC 36, 000 6 20 Kep 5,680 2 11 Pailin 3000 2 7 Koh Kong PTC 5, 000 3 13 Polytechnic Institute of Pursat Province 9, 360 5 13 Polytechnic Institute of Preah Sihanouk 7,352 4 25 Tboung Khmum PTC 17,084 1 2 Odor Meanchey PTC 4,000 3 13 Kratie PTC 4,669 2 7 Prey Veng PTC 4,085 2 10 NPIA/Siem Reap 20,070 3 8 Japan Vocational Center JVC 15,000 3 15

13

Key sub-project activities since last report:

- Nine workshops buildings in nine public TVET institutions were completed during November 2017. Safeguards documents attached in bidding documents, had approved and implemented, location of workshop buildings in the vacant land of master plans, have no cut of trees.

- Contracts awarded on 27 December 2017 for the construction of three women dormitories in Banteay Meanchey PTC, NPIA-Siem Reap, Koh Kong PTC and workshop buildings are ongoing. The progress of civil works achievements is approximately 25%. Safeguards documents attached in bidding documents, had approved and implementing, location of buildings in the vacant land of master plans, have no cut of trees. The awarded contractors have been orientating/training on safeguards issues on 23 January 2018. The construction of 3 other woman’s dormitories in Kandal, Kratie, and NVIB under AFD funding is expected to start in August 2018 to be completed by Q2 2019. Safeguards documents attached in bidding documents, had approved, and location of buildings in the vacant land of master plans, have no cut of trees. The awarded contractors have orientating/training on safeguards issues on 15 July 2018.

- The center of excellence/construction in NPIA/Siem Reap and center of excellence/auto mechanics in (BIT)/Battambang, the contracts were awarded on 27 June 2018, The awarded contractors have been orientating/training on safeguards issues on 15 July 2018 including EMP and Environmental Monitoring checklist.

- On-job refresher training at construction sites about safeguards matters have been conducted to skilled, unskilled works and site engineers.

Report prepared by: Site engineers and safeguards consultant

2.3. Safeguard Plans Implementation Arrangements 19. As involuntary resettlement is categorized C, and environment is categorized B, the EMP and Environmental Monitoring Checklists are crucial to implement during civil works of building constructions. The awarded contractors or subcontractors have to provide site engineers to supervise the construction site, daily managing and ensure proper and timely implementation of EMP and Environmental Monitoring Checklists. The TVETSDP engineer consultant team is overseeing on the safeguards implementation of contractors/sub-contractors and reporting to PCU/Directorate General of Technical Vocational Education and Training (DGTVET), the corrective action has to be made immediately if found any. There is no external monitoring agency. 20. The DGTVET as implementing agency of Ministry of Labour and Vocational Training (MLVT) is tasked assigning safeguards officer to direct manage and be responsible for (i) inclusion of EMP in bidding documents and other applicable contracts; (ii) implementation of EMP and EMoP during the constructions, operations and maintenance activities in the public TVET institutions; (iii) review and monitoring of the Occupational Health and Safety Plan (OHSP) and

14

Community Health and Safety Plan (CHSP); and (iv)submission of semi-annual monitoring reports to ADB. The following table is delineated the agencies and their responsibilities:

Agency Responsibility

Ministry of Labour and Vocational Training (MLVT)

Executing Agency • Ensure that sufficient funds are available to properly implement

the EMP • Ensure that project implementation complies with the provisions

of the EMP, ADB SPS 2009, applicable environmental policies and guidelines

Directorate General of Technical Vocational Education and Training (DGTVET)

Implementing agency • Responsible for the overall responsibilities for the

implementation of EMP and EMoP and other requirements stated in the IEE.

• Appoint a Safeguards Officer from the Department of TVET Management

Safeguards Officer • The assigned safeguards officer has the following responsibilities: (i) inclusion of EMP in bidding documents and other applicable contracts; (ii) implementation of EMP and EMoP during the construction, operation and maintenance activities in the public TVET institutions; (iii) review and monitoring of the OHSP and CHSP; and (iv)submission of semi-annual monitoring reports to ADB.

Contractor/subcontractors • Provide sufficient funding and human resources for the implementation of EMP

• Ensure proper and timely implementation of the mitigation measure during the construction phase of the project.

• Submit and implement OHS and CHS plans to DGTVET • Implement additional environmental mitigation measures, as

necessary

2.4. Updated EMP Incorporation of Safeguards Requirements into Project Contractual Arrangements

21. Due to the detailed design of building structures are taking times, including the procurement process, the safeguards documents have been produced step-by-step to fulfill and attaching to bidding documents are still waiting for those detailed designs documents completions. The safeguards documents have been updating and included in bidding documents for proceeding of civil works implementation are:

• EMP, English and Khmer version (side by side). • Environmental Monitoring checklist, English and Khmer side by side • Initial environmental examination-IEE (main material in bidding document)) • Due diligence reports- social and resettlement issue • Produced safeguards materials to capacity building for involved TVETSDP staff, included

environmental safeguards, resettlement safeguards, Indigenous peoples safeguards for the Project developments.

• Continued on job training to site engineers and contractor’s engineers about environmental monitoring checklists, EMP and actual implemented at sites. Continued to orientate to workers about PPE and personal hygiene, provision of adequate drinking water supply and sanitation facilities, implementation of occupational health and safety.

15

III. ENVIRONMENTAL PERFORMANCE MONITORING

3.1. Status of EMP implementation (Mitigation Measures)

3.1.1. Detailed design-construction stage:

22. Planning principles and design considerations have to be reviewed and be consistent with the Master Plan of the public TVET institutions: The final technical design of the workshops, woman’s dormitory, new classroom/additional building and rehabilitation activities are taking into consideration the following: (i) followed the suggested guidelines on building school facilities; (ii) construction of sanitation facilities should not be located near source of drinking water (at least 30 meters from the source of drinking water) and consistent with applicable national and international guidelines (i.e. World Health Organization’s Water, Sanitation and Hygiene Standards for Schools in Low-cost Settings); and (iii) follow applicable rules and regulations on structural integrity of building structures.

3.1.2. Construction and operations: 23. During construction stage, the contractors have been responsible for site management including site enclosure/fencing, campsites and pollution from human waste, providing first-aid kits, occupational health and safety plan, safe water for drinking and cooking, reasonable water and sanitation. Contractors implemented the EMPs strictly, oversight by site engineers included monthly environmental monitoring checklist completions.

o Permits or agreement for obtaining the campsite installation and construction waste disposal within institutions’ campus:

24. The awarded contractors usually have informed the public TVET institutions’ director/management in order to introduce about her/his firm to undertake the construction of dorms, new classroom and workshop buildings in the institutions, includes showing the master plan of institution and showing the detailed designs of the buildings, the contractors have requested the institution directors/management to obtain the permission to install the campsite within the institution, rubbish bins have been provided by contractors/firms to dispose the solid waste from kitchen and the construction waste (usually less, just only cement bags and some plastic materials). Most institutions used the system of dumping and burning solid waste within their institutions; few institutions used the system of solid waste collection by municipality/private companies.

The construction of buildings could not generate much of solid waste; the buildings are small, normally it is concrete and masonry works within enclosure of building site or nylon net fencing.

o Management of construction sites: 25. After getting the permission from institutions’ director/management for installation of campsite, the contractor starts installation the common camps and warehouses, making from timbers, woods, planks, bamboo and covering by tarpaulin or similar materials, this is just temporary shelter for construction workers in short period of times. At the same time, if the public TVET institutions did not have the toilet (water and sanitation) immediately the contractor is building the toilet to ensure their construction workers are comfortable. And other sites used the existing toilet within the institutions (requested permission from directors).

16

26. Due to this is just small buildings constructions, the heavy equipment or plants did not use, they used only common vibrators, cement mixtures, while storage for fuel, oil and construction materials are negligible, including the trucks for transportation of construction materials. Workshop building could not generate much of water pollution, it is negligible, and due to sewerage system is connected to municipality sewerage system and in NPIA the construction of dorm building and its campsite did not connect to municipality electricity grid, the awarded contractor used old generator therefore some leakages of used oils and other lubricants are in at campsite, the correction action has taken by instructing to site engineer and site manager to deal with this issue immediately to put in proper place in according with ADB environmental safeguards officers’ recommendations during field mission on 27 June 2017. 27. The contractor is implementing of works at the established time (e.g. work during daytime 06.00 to 18.00, lunch time from 11:30 to 14:00). Installation of necessary construction signs in construction sites includes nylon net fencing surround buildings constructions to prevent children and/or animal enters into the site camp.

o Community and Security

28. The contractor/workers need to be aware of and all sites have been applied the following general rules: (i) No alcohol/drugs on-site; (ii) Prevent excessive noise; (iii) No illegal activities such as, but not limited to gambling, and hunting farm animals in the

area; (iv) Trespassing on private/commercial properties adjoining the site is forbidden; (v) No littering in the public TVET institutions; and (vi) Workers are not allowed to be loitering in the TVET institutions especially when there

are trainings or classes in adjacent buildings.

o Ready construction site:

- Restoration of the area of construction sites and camps when the building construction works are completed.

- Replanting/planting of finished work areas (cut one tree replanting two trees if any). - The completion of nine workshop buildings in nine public TVET institutions of Banteay

Meanchey, BIT/Battambang, Kampong Cham Polytechnic Institute, Kampong Speu, Kampong Thom, Kandal, Pursat Polytechnic Institute, NPIA and Sihanouk/PIPP under TVETSDP end of November 2017 had cleaned to pre-project status and there is no cut of tree because the location for implantation of workshop buildings are in the vacant land of public TVET institutions’ master plan.

17

o Employment (unskilled labors)

Table 2: Compliance with EMP Requirements (Environmental Performance)

EMP Requirements Compliance Status (Yes, No, Partial)

Comment or Reasons for

Non-Compliance

Issues for Further Action

Air pollution:

Generation of dust or particulate matter from on-site excavation , and movement of earth materials

• Water spraying on road surface and work areas, as necessary especially during dry weather- NOT APPLICABLE (N/A)

• Place stockpiled soil in areas shielded from prevailing winds- N/A

AS IT IS SMALL SCALE BUILDING CONSTRUCTION

Emission from movement of heavy equipment and construction vehicles

• Truck carrying sands, soil, stone, and other loose materials should be covered with tarpaulin- N/A

• Vehicles and equipment used during construction must be properly maintained and in good condition to ensure optimal performance. N/A

• All vehicles and equipment used in the construction activities shall have valid certifications indicating compliance to vehicle emission standards- N/A

AS IT IS SMALL SCALE BUILDING CONSTRUCTION

Water pollution:

Run-off or soil erosion from stockpiled construction materials and spoils

• Minimize spoil by balancing cut and fill wherever possible. Spoil shall only be disposed to areas approved by local authorities- N/A

AS IT IS BUILDING CONSTRUCTION- SMALL SCALE

Domestic sewage from construction workers, accidental spillage of oil and other lubricants, wastewater from washing of construction equipment and vehicles and improper disposal of solid wastes.

• Implementation of solid wastes collection, storage and disposal system, with provision for waste segregation. DONE

• Provision on adequate on-site sanitation facilities with septic tanks to prevent untreated sewage from being channeled into the drainage canals, irrigation canals, and river- DONE

• Ensure that no cesspools will be created during construction activities- DONE

• Used oil should be stored at safe place for sale. Prohibit to disposal into the environment such as water course, rice field and other areas not designed and approved. DONE

MINOR ISSUE OF LEANKAGE OF USED OIL FROM GENERATOR AS SITE NO CONNECTION TO ELECTRICITY GRID FROM TOWN.

Strictly implementing this aspect in EMP

Noise and Vibration

Disruption of training/classes in the TVET institutions. Noise pollution to other sensitive receptors: nearby community, schools, hospitals in the project area.

• Planning activities in consultation with the staff and officials of public TVET institutions so that activities with the greatest potential to generate noise and vibration are planned during periods of the day that will result in least disturbance- DONE

• Construction activities will be avoided during nigh time, and religious or cultural events in close proximity to the roadside- DONE

18

• Prohibit workers from generating loud noise (e.g., due to loud talking, when handling materials). DONE

Noise and vibration due to the movement of vehicles along the access road may potentially result to nuisance.

• Impose speed limits on construction vehicles to minimize emissions along areas where sensitive receptors are located (i.e. temples, hospitals, schools, houses)- N/A

• Truck driver and equipment operators shall avoid the use horns unless it is necessary to warn other road users or animals of the vehicle’s approach- N/A

Vibration from the construction activities may cause damage to other structures and buildings in the area

• Identify any buildings at risk (i.e. old buildings in Kandal training center and BIT) from vibration damage and avoiding any pneumatic drills or heavy vehicles in the vicinity. Complete the civil works in these areas as quickly as possible- DONE

Quarry and Borrow Sites

Operation of quarry and borrow sites could cause adverse impacts to surface water quality, elevated dust emission during excavation, soil erosion and siltation of nearby water courses, and potential damage to productive land and ecologically sensitive areas.

• Utilize readily available sources of materials. If contractor procures materials from existing borrow pits and quarries, ensure that these conform to all relevant regulatory requirements. -N/A

• Borrow area and quarry must not be located in culturally and ecologically protected areas. N/A

Generation of Solid Wastes

Improper solid waste management could cause odor and vermin problems, air pollution, risks to health and safety, flow obstruction of nearby watercourses and could negatively impact the landscape

• Construction materials and stockpiles of soils should be covered to reduce material loss. DONE

• Stockpiles, lubricants, fuels, and other materials should be located away from steep slopes and water bodies. DONE

• Domestic solid wastes (i.e. food wastes) should be properly segregated in biodegradable and non-biodegradable for collection and disposal to designated solid waste disposal site. DONE

• Prohibit burning and disposal of solid wastes into canals, rivers, and other watercourses. DONE

• Residual and hazardous wastes such as oils, fuels, and lubricants shall be disposed in disposal sites approved by local authorities. DONE

• Ensure that wastes are not haphazardly dumped within the project site and adjacent areas. DONE

• Kitchen waste should be segregated for use of villagers as animal feeds or fertilizer. N/A

Biological Environment

19

The activities are located on existing TVET institution and there are no protected areas or areas of ecological interest in or around the project site

• If during the project implementation, there will be cutting of trees or removal of vegetation, compensatory plantation for trees lost at a rate of 2 trees for every cut tree will be implemented by the contractors. N/A

• Re-planting trees at the subproject area to compensate for lost trees provide shade and improve the landscape. N/A

Cultural Heritage

Construction activities are within the premises of the Public TVET Institutions which have been developed in time, thus no cultural heritage is expected to be found. However, mitigating measures must be in place for any possible “chance discoveries” made during construction work; with procedure as discussed in Article 37 of the Law on the Protection of Cultural Heritage (NS/RKM/0196/26). The Chance Discovery Procedure will be put in place to include the following

• If any cultural heritage material is encountered, all works at the discovery site should be immediately halted. N/A

• Without delay, the contractor and/or site engineer will inform the PTC Director of the find and report it to local authorities. N/A

• All project workers and staff shall be made aware of the Chance Discovery Procedure. N/A

Traffic

Aside from the generation of noise and dust on hauling routes, the movement of construction vehicles will disrupt normal traffic patterns and expose the local community and the trainees and personnel in the TVET institutions to risk of injury or accidents

• Using locally sourced materials, whenever possible, to minimize transport distances. DONE

• The contractor should closely coordinate with local authorities and with the TVET institutions for traffic management. DONE

• The contractor should ensure that drivers are duly licensed with good track records. DONE

• The contractor should ensure that vehicles and equipment are regularly maintained and in good working conditions. DONE

Damage to infrastructure

Transport of construction materials and other construction activities may cause damage to existing roads, irrigation and drainage canals adjacent to the construction sites. The contractor shall implement the following measures to minimize the

• The contractor shall not allow overloading of trucks used for the transport of materials- DONE

• The contractor will be required to repair damaged infrastructure resulting from the transport of materials and other construction activities. DONE

20

damage to existing infrastructure

Occupational Health and Safety

Construction activities may cause harm and danger to the lives and welfare of workers

• The contractor should prepare occupational health and safety plan (OHSP) which will be part of the contractor’s contract documents. DONE.

• The occupational safety plan should have provisions on (i) providing personal protective equipment (PPE) like hard hats, safety gloves, ear mufflers to all workers; (ii) providing occupational health and safety training to all workers (i.e. first aid measures, prevention of malaria, diarrhea, HIV/AIDS); (iii) documenting safety procedures to be followed for all construction site activities; (iv) maintaining records of accident and the corrective actions implemented; and (v) emergency response plan during fire, earthquake and other incidents- DONE

• Provision of first-aid facilities for the workers. DONE

• Provide adequate portable or permanent

sanitation facilities serving all workers. DONE

• Provide sufficient, safe, and easily

accessible drinking water stations in the project area. DONE

OPERATIONS AND MAINTENANCE

Due to the nature of the trainings and programmes in the TVET system, potential risk to the maintenance of the workshops and dormitories are occupational health and safety of trainees and staff and the proper segregation and disposal of solid wastes.

• Provision of first-aid kit in the workshop area. DONE

• Provision of PPE (i.e. gloves, proper shoes, face mask, safety goggles and other appropriate safety gear) to staff and trainees, as necessary. PARTIALLY

• Establish emergency response procedure and preparedness during fire, earthquake and other incidents. N/A

• Encourage proper waste segregation, collection and disposal. DONE

• Train all trainees on health and safety during works to avoid or minimize risk on health and safety before going to practice at the workshop. DONE

SOME UNSKILLED WORKERS DID NOT WEAR THE HELMET DUE TO HEADHACH, SHOES due to it is not fitted

Have to compulsory to workers to wear

21

Table 3: Issues for Further Action

Issue Required Action Responsibility and

Timing Resolution

Old Issues from Previous Reports

Used oil should be stored at safe place for sale. Prohibit to disposal into the environment such as water course, rice field and other areas not designed and approved.

Informing to site manager to cope with this issue and take action

Immediately take action- implementing EMP strictly

Solved

New Issues from This Report

NONE/SO FAR

3.2. Health and Safety

29. Normally, construction activities may cause harm and danger to the lives and welfare of workers and animals. The awarded contractors have been prepared occupational health and safety plan (OHSP), which is part of the contractor’s contract documents. So far, there is no issue of occupational and community health and safety within the construction campsites. There is no accident involving in injury or death of workers and staff. The occupational safety plan should have provisions on:

(i) Providing personal protective equipment (PPE) like safety helmets/hard hats, safety gloves, ear mufflers to all workers;

(ii) Providing occupational health and safety training to all workers (i.e. first aid measures, prevention of malaria, diarrhea, HIV/AIDS);

(iii) Documenting safety procedures to be followed for all construction site activities; (iv) Maintaining records of accident and the corrective actions implemented; and (v) Emergency response plan during fire, earthquake and other incidents. (vi) Provision of first-aid facilities for the workers. (vii) Provide adequate portable sanitation facilities serving all workers and staff. (viii) Provide sufficient, safe, and easily accessible drinking water stations in the Program

areas.

Table 4: Health and Safety Issues

Issue Required Action Responsibility and

Timing Resolution

Old Issues from Previous Reports

Personal protective equipment: - New classroom building construction in BIT and woman’s dormitory building in NPIA- few workers did not wear the

Site engineers are compulsory to workers to wear/use safety helmets/hard hats, safety gloves, ear mufflers to all workers during implementing of civil works at construction

Awarded contractors and their site engineers taking immediately actions

Solving

22

safety helmets, they feel headache. -Workshop and woman’s dormitory buildings in Koh Kong PTC- Some workers still do not use safety shoes due to if they wear they felt not being comfortable

buildings, starting after field assessment of safeguards’ missions.

New Issues from This Report

NONE- So far

3.3. Environment Effect Monitoring

30. Monitoring plan: Environments, Occupational Health and Safety, and Personal Hygiene need to refresher orientation to new coming workers and staff of awarded contractors and their site engineers, reminding them to regular implementation of EMP, this is compulsory to do so. The awarded contractors have participated in safeguards orientation on 23 January 2018 after signing the contract on 27 December 2017 for three dormitories and workshop buildings in four public TVET institutions receiving civil works. During this semi-annual environmental monitoring report, the safeguards specialist together with involved staff from TVETSDP project has conducted capacity building/orientation at sites to workers and staff working in current civil work implementation of public TVET institutions including BIT on 9 May 2018, NPIA on 11 May 2018, in Koh Kong PTC on 11 July 2018. Workers usually do not want to use Occupational Health and Safety such as safety hard hats/helmets, safety shoe, safety gloves and ear mufflers, and this project has to introduce and be compulsory to worker’s adaptations of using safety helmets/hard hats, safety shoe, safety gloves and ear mufflers. 31. Monitoring activities in the reporting period: The monitoring activities have been conducted depends upon civil works implementations of building constructions in public TVET institutions. During this semi-annual report, the monitoring activities have conducted to all civil work implementations in public TVET institutions, receiving building constructions, including BIT/Battambang, Banteay Mean Chey PTC/no civil works during field visits, NPIA/Siem Reap and Koh Kong PTC. The orientation/training about Environments, Occupational Health and Safety, and Personal Hygiene to skilled and unskilled workers as well as site engineers have been done with total 6 engineers (all males) and 70 workers (26 females) on 9 May 2018 in BIT on 11 May 2018 in NPIA, and on 11 July 2018 in Koh Kong PTC. Transect walking to construction sites and assessment of safeguard issues that may occur deviating from the implementation of EMP and the corrective action has been made with log sheet records to instruct the site engineers to take action immediately after visiting and finding of safeguard issues to sites.

23

Table 5: Environment Effect Monitoring Results in the Reporting Period

Location Parameter

Date

Monitoring value

Relevant government

standard, standard value

NPIA/Siem Reap of dormitory building construction

Used oil leaked from Old generator

27 June 2018

Critical Yes

BIT/Battambang- New classroom building

Personal protective equipment

9 May 2018 Critical Yes

Koh Kong, Workshop and woman’s dorm

Personal protective equipment

11 July 2018 Critical Yes

BMC PTC/woman’s dorm

Not starting yet, during field visit

10 May 2018

32. Assessment. The monitoring results indicated that there is a bit improving to previous results of monitoring, although government also has standards of environment of building constructions. The delay in civil works constructions and the lower costs of awarded contractors as well as the variations of bill of quantity would result in environment/EMP implementations because the concern is how to push and proceeding the civil work goes ahead.

IV. INVOLUNTARY RESETTLEMENT PERFORMANCE MONITORING

33. The resettlement categorization for this Project is C, there is no resettlement plan. The project is not involved in land acquisition or involuntary resettlement as confirmed by the due diligence reports, prepared during June-July 2018. The premises of all public TVET institutions are enclosed by fencing and have titles and/or certificates from Ministry of Land Management, Urban Planning and Construction and local authorities that deem them as state-owned land, designating for buildings and development within their campuses. There are no informal or squatter settlements inside these campuses. There are no non-titled residents or vendors on the properties. The Project will not restrict land use and/or access to legally designated parks and protected areas for the reasons described above. Thorough assessment also indicated that, there is no indigenous people are residing within public TVET institutions’ campuses and its surroundings.

V. INDIGENOUS PEOPLE PERFORMANCE MONITORING

34. ADB classifies Indigenous People (IP) as category B, in terms of benefiting from the Project/Program, this document was uploading onto the ADB website since October 2015, it is not affected entities by implementing the civil work of building construction. The consultant team and especially the Executing Agency (EA) and implementing agency (IA) are fully aware of the IP implementation within out puts/sub-out puts and have to be addressed them, when identified. Every output and sub-output of TVETSDP is qualified with IP targets and/or requirements. Mechanisms to increase IP enrolment in public TVET institutions have been identified by the working group of

24

DGTVET. The outputs and sub-outputs of IPP is paralleled with general Program/project of TVETSDP with particular expertise’s responsibilities. 35. The Executive Agency, Implementing Agency together with consultant team will conduct the more field visits to verify the often stated perception that IP targets are very difficult because of their cultures, traditions, languages and isolation. The social marketing campaign will give special attention to ‘capture’ IP students to study in the various TVET programs including SBP, VSTP, VC, CQF levels. Similarly, the internship program, SSC, COE, CQF level 2 and above courses and so forth have been paid attention to access and benefiting by IPs in the PTCs and RTCs. The following table delineated the progress of IPPs’ target indicators achieved:

Table 6: Summary of Compliance with IPP

Indicators and Targets, Timeframe and Responsibility

Progress to Date - Compliance status Issues and Challenges

Establishment of personnel in PMU: Office of Special Training and Gender/IPs in DGTVET

Public consultation and socialization process: Workshop and refresher workshop about IPP indicators of out puts and sub out puts. Output 1: Increased Access to TVET Programs

Anticipated positive impact: Better access of IPs to TVET programs, and increased awareness about TVET and employment opportunities

Anticipated negative impact: IPs excluded due to limited TVET course offerings and limited employment opportunities in remote regions and failure of social marketing campaigns

1.1 VSC pilot with non-formal TVET courses implemented in the 2 IP majority provinces (Ratanakiri & Mondulkiri). Responsibilities: Counterpart: Chief office of Department of Training Consultant: National VSC & VSTP Implementation Specialist

The VSC guidelines has been approved, and orientation training was conducted in June 2018. The VSC will be piloted in Q3 2018 in 5 RTCs/PTC s plus the PTCs in Ratanakiri and Mondulkiri. Teacher training of RTCs/PTCs involved in the piloting will be conducted in July 2018.

1.2 45 of 900 Cambodian assessed for RPL/RCC are IPs and ethnic minorities. DMF 1a Responsibilities: Counterpart: DSC/DQA Consultant: National Assessment Specialist

NTB has approved RPL/RCC Assessment Policy and Certification Policy. ADB has also issued NOL for CBT package for Assessors Training Program. Assessment and certification to follow after development of assessment tools, training of assessors, and establishment of assessment centers within 2018. IPs and minorities will be among those to be assessed and certified.

1.3 CQF 2-4 stipends pilot and personal coaching pilot implemented in 2 IP provinces, at least 1 of which is an IP

At least 2 provinces (Ratanakiri & Mondulkiri) will be included during piloting of stipend in Q3 2018 and personal coaching in Q4 2018.

25

Indicators and Targets, Timeframe and Responsibility

Progress to Date - Compliance status Issues and Challenges

majority province. (Ratanakiri & Mondulkiri). DMF 1f

1.4.1. IP status included as one of the weighted criteria to qualify for residence in women’s dormitory (in case of a queue) DMF 1c Responsibilities: Counterpart: Chief of OSTG office/DT Consultant: National IPP Specialist

Draft criteria for selection of dormitory residence includes IP status as one of the weighted criteria.

Of the 6 women’s dormitory, only one will be built in an IP province, at the Kratie PTC.

1.4.2. 100% of coaching and counseling materials and trainings include sections on ethnic and cultural sensitivity. DMF 1f Responsibilities: Counterpart: Deputy of OSTG office/DT Consultant: National Public Finance Management Specialist/Business Process Analysis

Not started yet: To follow after construction of women’s dormitories by Q4 2018. Materials to be developed and delivered by selected firm will include sections on ethnic minority (EM) and cultural sensitivity. They will be EM/IP sensitive.

1.4.3 100% of IPs in CQF2-4 eligible for stipends in PTCs and RTCs where stipends are piloted. DMF 1f

The student stipend guidelines provide priority to IP students in PTCs where stipends are to be piloted. Initial list 1,500 students proposed by PTCs/RTCs as recipients for stipend for academic year 2017-2018 has been prepared subject to validation. Disbursement is targeted for August 2018.

1.4.4. Awareness raising workshops and information brochures on stipends and coaching pilots are translated in local language and reflect appropriate cultural patterns and values. DMF 1f Responsibilities: Counterpart: Chief of OSTG office/DT Consultant:RR specialist

Not started yet: Will ensure that the selected firm will consider appropriate cultural patterns and values in its awareness raising workshops and information materials on stipend and coaching. Already included in the ToR. Visual pictures help IP to understand is needed to included.

The translations of information brochures on stipends and coaching pilots from Khmer into local languages may not possible, but will reflect appropriate cultural patterns and values of IPs, visual pictures is needed to included.

26

Indicators and Targets, Timeframe and Responsibility

Progress to Date - Compliance status Issues and Challenges

1.5.1. At least 50 roadshows implemented in IP provinces, of which a minimum of 20 are in IP majority provinces. (Ratanakiri, Mondulkiri) Responsibilities: Counterpart: Vice chief of DLMI/DLMI Consultant: National Social Marketing Special Target: On-going

Conducting Roadshow Standard Operating Procedure (SOP) consultation meeting to three additional RTCs-Kampot Takeo and Svay Rieng and implement 1st official roadshow in Battambang. Marketing Specialist has visited the 2-IP majority provinces and Gender & IP components are included in SOP. The IP provinces and IP major provinces will schedule in Q3&Q4

1.5.2 Social marketing and media campaigns targeting IPs especially developed, emphasizing positive IP role models, especially women and people in under-represented sectors Responsibilities: Counterpart: Vice chief of DLMI/DLMI Consultant: National Social Marketing Special Target: On-going

TOR includes IP/EM. Work plan of social marketing is specified in details the targets as per GAP and IPP. The successful IP students/ trainees, for instance, from Plan NGOs to operate their business in their communities. Therefore the others may follow.

1.5.3. 100% of marketing messages are translated in local language and reflect appropriate cultural patterns and values. Responsibilities: Counterpart: Vice chief of DLMI/DLMI Consultant: National Social Marketing Special Target: On-going

Final draft of 5-year social marketing strategic plan (English and Khmer versions) will be submitted for final review by Technical Units during Q2 2018.

The translations of social marketing strategy plan from Khmer into local languages may not possible, but it has been taken into account to reflect appropriate cultural patterns and values of IPs

1.5.4 Social mobilization and job/income placement pilot implemented in 2 IP majority provinces, at least one of which in an IP majority province

Social mobilization and job/income placement pilot will implement in 2 IP majority provinces in Q3 or Q4 2018.

Output 2: Improved Quality and Relevance of TVET System

Anticipated positive impact: Skills development amongst IPs is recognized in terms of cultural patterns and values

Anticipated negative impact: IPs exposed to limited TVET offerings and employment opportunities

27

Indicators and Targets, Timeframe and Responsibility

Progress to Date - Compliance status Issues and Challenges

2.1.1 Quality assurance system piloted in 2PTCs or RTCs serving IP provinces, at least 1 of which is an IP majority province. (Ratanakiri, Mondulkiri) Responsibilities: Counterpart: Deputy Director of DPS/DPS Consultant: National M&E Specialist

Quality assurance (Q.A.) audit reports indicated amongst 6 PTCs in IPs provinces, there are 2 PTCs have been classified as acceptable level while other 4 PTCs in Ratanakiri, Mondulkiri, Kratie and Preah Vihear/Yalay have not met the 6 criteria of Q.A. indicating that those 6 need further improvement.

2.1.2 Directors and relevant staff from 100% of PTCs and RTCs serving IP provinces attend workshops and seminars on TVET quality assurance system. Responsibilities: Counterpart: Deputy Director of DPS/DPS Consultant: National M&E Specialist

100% directors and relevant staff from 100% of PTCs and RTCs serving in IP provinces attended workshops and seminars on TVET quality assurance system.

2.2.1 At least 1 out of 10 competency assessment centers established in 1RTC or PTC serving an IP majority provinces.

Consultation workshop on criteria for selection of assessment centers was conducted in Kampot RTC during Q2 2018. At least 1 of the selected assessment centers will be in an IP majority provinces in Q3 and/or Q4 2018.

2.2.2 At least 20 out of 200 assessors are from RTCs or PTCs serving IP provinces. DMF 2a

Not yet started: To follow after assessment and certification system become operational (see 1.2. above) Will ensure that at least 20 out of 200 assessors are from RTCs/PTCs serving IP provinces.

2.3.1. 100 out of 800 instructors trained in CBT are from RTCs and PTCs serving the 5 IP provinces. (Ratanakiri, Mondulkiri, Kratie, Stung Treng and Preah Vihear) DMF 2b Responsibilities: Counterpart: QA Consultant: National Master Teacher Trainer

In-Service Training is on-going as per TVET Teacher Training Plan, there have been two phases in the 5-IP provinces which are included: -Phase-I, 55 instructors have trained, Females=11 - Phase-II, 30 instructors have trained, Females=9 (trained second time)

28

Indicators and Targets, Timeframe and Responsibility

Progress to Date - Compliance status Issues and Challenges

2.3.2. 20 instructors selected for return to industry pilot are from RTCs and PTCs serving IP provinces.

RIS guidelines has been approved on 23 Feb 2018 and under process of implementation. Will ensure that at least 20 instructors will come from RTCs/PTCs serving IP provinces during Q3 and/or Q4.

2.4.1. VSTP is rolled-out in all 5 IP provinces (Ratanakiri, Mondulkiri, Kratie, Stung Treng and Preah Vihear) DMF 2d Responsibilities: Counterpart: Chief office of DT/DT Consultant: National VSC & VSTP Implementation Specialist

Phase I started in 14 public and one non-state training institutes including those in IP provinces, as follows: • Ratanakiri=498/F=221 IPs participants • Mondulkiri=379/F=259 IPs participants.

The other provinces will be covered in Phases II and III of VSTP

2.4.2. Size of IP population is included as one of the weighted criteria to identify VSTP communes.

VSTP guidelines includes size of IP population as one of the weighted criteria to identify VSTP communes.

2.4.3. 100% of CDS trained in incorporating ethnically and culturally appropriate perspective in TENA. Responsibilities: Counterpart: Chief office of DT/DT Consultant: National VSC & VSTP Implementation Specialist Target: On-going

28-CDS (2 females) in 8 provinces (Kadal, Kg Speu, Kg Chhnang, Prey Veng, Kg Cham, Tboung Khmum Kratie and Preah Vihear have been trained in May 2018 in conducting TENA survey phase-II including ethnically and culturally appropriate perspective.

2.5.1. Skills bridging program (SBP) is rolled out in all 5 IP provinces. (Ratanakiri, Mondulkiri, Kratie, Stung Treng and Preah Vihear) DMF2f Samrith Vy?Saroeun

SBP has been started in Q1&2 2018 including Stung Treng PTC, an IP province, with 30 participants, Females=18. The rest of four IP provinces will be in Q3 and/or Q4.

2.5.2. Size of IP population is included as one of the weighted criteria to identify SBP communes or training proposal. DMF2f

Yes- included weighted criteria.

29

Indicators and Targets, Timeframe and Responsibility

Progress to Date - Compliance status Issues and Challenges

2.7.1. TVET instructor policies on instructor management and professional development incorporate analysis and measures for IPs and/or IP majority provinces. (Ratanakiri, Mondulkiri)

The TOR and work plan of the TVET HRM firm to be engaged by the project will incorporate analysis and measures for IPs and/or IP majority provinces. The firm will be mobilized in Q3 2018.

2.7.2. 2 out of 10 public TVET institutes for inspection pilot serve IP provinces, at least 1 of which is in an IP majority province. (Ratanakiri, Mondulkiri)

Not started yet: DGTVET will ensure that at least 2 of the majority IP provinces will be included in the piloting for inspection.

Output 3: Increased Involvement of Employers in TVET Delivery

3.1.2. Industry Liaison Units trained to implement and monitor new internship program: -100% of ILUs in PTCs and RTCs serving IP provinces develop networks with ILUs in provinces with large enterprises and a large business community Responsibilities: Counterpart: Deputy of OSTG office/DT Consultant: Team Leader

All ILUs in PTCs/RTCs serving IP provinces will be included in the training scheduled in Q3 2018 to implement and monitor the new internship program.

3.2.1.Establish sector skills councils (SSCs): 4 SSC established and formalized through Memoranda of Agreement: -100% of SSC members attend a workshop with one session on IP needs and support requirements for skill development and employment.

MOU between MLVT and CAMFEBA signed in June 2018 making the establishment and operation of SSCs as PPP in workforce development. The Prakas for the establishment of SSCs initially in 4 priority sectors will be issued in July 2018. An orientation and planning workshop for SSC members to follow in September 2018 including a session on IP needs for skills development.

Seeking ways to establish the permanent body of SSC.

3.2.2. Operating procedures and monitoring and evaluation framework for SSC established: -Operating procedures and M&E framework for SSCs include social inclusion metrics (including ethnic minorities and IPs). (Ratanakiri, Mondulkiri, Preah Vihear, Stung Treng and Kratie) Responsibilities:

Operating procedures and M & E framework for SSCs will include social inclusion metrics including social inclusion and IPs.

Seeking ways to establish the permanent body of SSC

30

Indicators and Targets, Timeframe and Responsibility

Progress to Date - Compliance status Issues and Challenges

Counterpart: DSC/Chief of OSTG office/DT Consultant: Team Leader/Deputy Team Leader/National Gender Specialist

3.2.3. VSC and CQF Levels 2–4 training programs piloted: -15 of 150 participants in pilot of CQF level 1-2 courses in Basic Manufacturing Processes under the Center of Excellence in manufacturing are IPs and other ethnic minorities. (Ratanakiri, Mondulkiri, Kratie, Preah Vihear, and Stung Treng) Responsibilities: Counterpart: DT Consultant: National Competency Based Training & Assessment Learning Materials Specialist

The pilots of VSC for basic manufacturing to follow after development of VSC CBT packages. Only the IP PTCs province of Preah Vihear is under Center of Excellence in Siem Reap cluster. Target number of participants will be considered.

-

3.3.4.Soft skills training module developed to be incorporated into curricula for CQF Levels 1–4: - Soft skills training program are ethnically sensitive and culturally appropriate, and include a module on working in ethnically diverse and inclusive workplace

Soft skills training modules to be developed by a firm for inclusion into curricula for CQF 1-4 will be ethnically sensitive and culturally appropriate. The firm is scheduled to be mobilized in Q3 2018.

Output 4: Project management and support services

4.1 Strengthen RTCs and PTCs to offer CQF levels 2 and above courses

4.1.2. 26 PTCs deliver 286 courses: - At least 50% of PTC and RTCs serving the 5 IP provinces develop ITMD strategies: (Ratanakiri, Mondulkiri, Kratie, Stung Treng and Preah Vihear)

In the process of selecting RTCs and PTCs to engage in income generation activities. ITMD taskforce developed a tool for the selection and they assessed 1 RTC and 7 PTCs during June 2018. Criteria of selection RTCs and PTCs give priority to IPs RTCs and PTCs provinces.

31

Indicators and Targets, Timeframe and Responsibility

Progress to Date - Compliance status Issues and Challenges

4.2.1. Start-up costs for RTCs and PTCs to offer Levels 2–4 courses financed: - At least 50% of the PTCs and RTCs serving the 5 IP provinces receive operational grants for CQF 2-4. Responsibilities: Counterpart: DPS Consultant: Team Leader/Deputy Team Leader

It is noted that 5 IPs provinces did not have CQF level 2-4 for Academic Year 2016-2017. Will be considered in the next round of start-up cost business planning for AY 2017-2018.

3 Cluster Coordinators for Kampot, Takeo and Battambang clusters have been mobilized since May 2018.

4.3. Improve information management systems 4.3.1. - Skills survey, tracer surveys, and TVET MIS modules on students and teachers have questions on ethnicity, cultural patterns and values. Responsibilities: Counterpart: DLMI, Procurement Unit Consultant: National M&E Specialist

Firms that will be contracted to undertake skills surveys and tracer studies will include questions on ethnicity, cultural patterns and values (To be scheduled later).

4.3.4. 100 DGTVET staff, NEA, and staff of Public TVET Institutions, together with RTCs and PTCs, receive training on TVETMIS and LMIS: - Directors and staff from 100% of PTCs and RTCs serving IP provinces trained on integrated TVET MIS and Labor MIS Responsibilities: Counterpart: TVETMIS OFFICE/DLMI Consultant: National Information Technology Specialist

100% of directors and staff from PTCs and RTCs serving in IPs provinces (Ratanakiri, Mondulkiri, Kratie, Stung Treng and Preah Vihear PTCs and Siem Reap&Svayrieng RTCs) trained on integrated TVETMIS and Labor MIS on (24 Nov 2017 at Sokha Hotel Phnom Penh)

Project Implementation

DGTVET, NEA and DLMI staff trained in issues of social inclusion (including inclusion of IPs and ethnic minority cultural patterns and values).

Training of DGTVET, NEA, and DLMI staff on social inclusion scheduled in Q3 2018.

32

Indicators and Targets, Timeframe and Responsibility

Progress to Date - Compliance status Issues and Challenges

(Ratanakiri, Mondulkiri, Kratie, Preah Vihear, and Stung Treng)

Semi-annual IPP progress reports submitted to PCU

• 1st semi-annual progress report on implementation of the IP plan (January-June 2017) submitted to ADB on 1 September 2017, and was uploaded to the ADB website.

• 2nd semi-annual progress report on implementation of IP plan (July-December 2017) was submitted to ADB on 11 January 2018, and it was uploaded to the ADB website

• 3rd semi-annual report on IP implementation will be submitted in 15 July 2018.

Ethnic indicator used in baseline and end line surveys/studies

Baseline survey/study conducted during project design included ethnic indicator; ethnic indicator will likewise be used during end line survey/study.

Mid-term review includes IP review and adjustments

The mid-term review scheduled in February 2019 will include IP review and adjustments.

Role of Office of Special Training and Gender under Department of Training communicated to IPs through targeted communications

The Office of Special Training and Gender uses her existing communication with PTCs and RTCs in order to inform, get advisory, facilitating, coordinating and reporting to each other regarding the IPP&GAP issues.

33

VI. COMPLIANCE WITH SAFEGUARDS RELATED PROJECT COVENANTS

Schedule Para No. Covenant Remarks/Issues

(Status of Compliance)

Schedule 5

para 7

The Borrower shall cause MLVT to ensure that the preparation, design, construction, implementation, operation and decommissioning of the Project and all Project Facilities comply with a) all applicable laws and regulations of the

Borrower relating to environment, health and safety;

b) the Environmental Safeguards; and

all measured and requirements set forth in the IEE, the EMP, and any corrective or preventative actions set forth in a Safeguards Monitoring Report.

Being complied with environment

Schedule 5

para 8

The Borrower shall cause MLVT to ensure that a) all construction under the Project is

carried out within existing TVET facilities on government owned land; and

involuntary resettlement screening for subprojects involving construction is provided to ADB to ensure that the Project does not have any involuntary resettlement impacts, all within the meaning of the SPS.

Being complied with Involuntary Resettlement Safeguards.

Schedule 5

para 9

The Borrower shall cause MLVT to ensure that the preparation, design, construction, implementation and operation of the Project and all Project Facilities comply with a) all applicable laws and regulations of the

Borrower relating to indigenous peoples; b) the Indigenous Peoples Safeguards; and

all measures and requirements set forth in the IPP, and any corrective or preventative actions set forth in a Safeguards Monitoring Report.

Being complied with Indigenous Peoples Safeguards

Schedule 5 para 10 The Borrower shall cause MLVT to make

available necessary budgetary and human resources to fully implement the EMP and the IPP.

Being complied with Safeguards

Schedule 5 para 11

The Borrower shall cause MLVT to ensure that all bidding documents and contracts for Works contain provisions that require contractors to: a) comply with the measures relevant to the

contractor set forth in the IEE, the EMP, and the IPP (to the extent they concern

Being complied with safeguards

34

impacts on affected people during construction), and any corrective or preventative actions set forth in a Safeguards Monitoring Report;

b) make available a budget for all such environmental and social measures;

c) provide the Borrower with a written notice of any unanticipated environmental, resettlement or indigenous peoples risks or impacts that arise during construction, implementation or operation of the Project that were not considered in the IEE, the EMP, and the IPP;

d) adequately record the condition of roads, agricultural land and other infrastructure prior to starting to transport materials and construction; and

e) reinstate pathways, other local infrastructure, and agricultural land to at least their pre-project condition upon the completion of construction.

Schedule 5 para 12

The Borrower shall cause MLVT to do the following: a) submit semi-annual Safeguards

Monitoring Reports to ADB and disclose relevant information from such reports to affected persons promptly upon submission;

b) if any unanticipated environmental and/or social risks and impacts arise during construction, implementation or operation of the Project that were not considered in the IEE, the EMP, and the IPP, promptly inform ADB of the occurrence of such risks or impacts, with detailed description of the event and proposed corrective action plan; and

report any actual or potential breach of compliance with the measures and requirements set forth in the EMP or the IPP promptly after becoming aware of the breach.

Complied with safeguards.

35

VII. PUBLIC CONSULTATION, INFORMATION DISCLOSURE, CAPABILITY BUILDING

7.1. Meetings and consultations 36. Safeguards consultant together with TVETSDP project involved staff frequently conducted field visits to each subproject site before and during construction. During each field visit particular attention was paid to social and environmental issues such EMP implementation, environmental monitoring checklists, regardless resettlement issue during civil work implementation due to it is as category C. The following table is delineated the date of field visits, consultations, on-job capacity building, and summary of safeguards issues:

No Date of meetings and consultations

Public TVET Institutions

Summary of safeguards issues

1 25-28 Feb 2018 Kandal, Tboung Khmum, and Kratie

Conducted site visit, investigation of Dormitories buildings. Updating social and environmental screening checklists, safeguards issues, redress mechanism in public TVET institutions

2 7-12 May 2018 Kampong Chhnang PTC, BIT, NVIB, Pailin, BMC, NPIA

Conducted site visits, updating social and environmental screening checklists, safeguards issues, redress mechanism in public TVET institutions, investigation of renovation building for COE. Orientated/trained about environmental and social safeguards issues to site engineers included skilled and unskilled workers at new classroom building. Understanding social and environmental issues, personal hygiene at site camps.

3 9-12 July 2018 Koh Kong PTC Updating safeguards issues, redress mechanism in public TVET institution. Orientated/trained about environmental and social safeguards issues to site engineers included skilled and unskilled workers at workshop and dorm buildings. Understanding social and environmental issues, personal hygiene at site camp, monitoring social and environmental issues.

4

7.2. On-job training/capacity building to involved officers, workers and site engineers

37. The capacity building or on-job training to involved officers of TVETSDP on site engineers, totally 6 engineers (all males) and 70 workers (26 females) on 9 May 2018 in BIT, on 11 May 2018 in NPIA, and on 11 July 2018 in Koh Kong PTC (please review in annex-4 the fields reports and lists of participants). The contents of the trainings are about Social Safeguard and Environmental Monitoring Checklist, Environments Safeguards, Occupational Health and Safety, and Personal Hygiene, the staff and workers understand about social and environmental safeguards, Occupational Health and Safety, and Personal Hygiene. The staff requested to have refresher training to their new site engineer’s recruitment for woman’s dormitories in NVIB, Kandal and Kratie PTCs and the recruitment of new comer’s engineers are on the process, do not know how long will take, therefore, the safeguards training should be scheduled to those new comers or scheduling for every six months’ periods.

36

VIII. GRIEVANCE REDRESS MECHANISM

38. A grievance redress mechanism has been established in community level, mainly in the public TVET institutions that have been introduced for civil works of building constructions, for instance, BIT/ Battambang, Banteay Mean Chey PTC, NPIA, and Koh Kong PTC had established during September and October 2016 due to they had implemented for civil works of workshop buildings, since then, the safeguards specialist and TVETSDP involved staff have regularly conducted the field visits and reminding/maintaining the mechanism for further and coming building constructions such as new classroom buildings, woman’s dormitories, and COE buildings during October 2017 and May/June 2018. The members of grievance redress mechanism consisted of directors/directress, deputy directors/directress and involved staff, augmenting site engineers and contractors to facilitate and corresponding the complaints from affected person (APs) during the construction phase.

39. The notice boards in public TVET institutions displaced the information in connection with complaints and its procedures, If APs do not have the writing skills or being able to express their grievances verbally, however, APs are encouraged to seek assistance from the nominated local NGOs or other family members. So far, there is no complaint yet regarding social, environmental safeguards and the IPP. The building construction implementations within public TVET institution’s premises and the building constructions are fencing enclosure, they are away from residents and animals, they did not damage and invade social infrastructures, social facilities, and environment at all.

IX. CONCLUSION

40. There is no major issue for the buildings constructions within public TVET institutions during this semi-annual safeguards monitoring report:

o The contractors managed the environmental safeguards issues, however it needs to

further improvement and regular monitoring and oversight by site engineer consultants (employed by EA/DGTVET).

o The negative environmental impact during construction phase is short term and minor. The significant impacts included dust control from civil works implementation, materials transportation, human waste, and solid waste generation from construction campsite, work safety and health, pollution from fuels and used engine oil, for instance, the leakage from old generator in NPIA and this impact is immediately correcting by site engineers, and contractor at site.

o Environmental Management System has been established for the Subprojects and for

each Contract Package. The Contractors and site engineers have cooperated in environmental management plan and monthly environmental monitoring checklist.

o Specific activities to minimize environmental impacts during construction have been done

by the Contractors and overseeing by site engineers.

o The monitoring results showed that the impacts of construction activities to the ambient air, noise, vibration and water are negligible.

37

X. ATTACHMENTS

Annex-1: Field visits to public TVET institutions: No Date PTCs/RTCs/Institutions-Subprojects

1 25-28 Feb 2018 Conducted field visits to project sites of Kandal, Tboung Khmum, and Kratie

2 7-12 May 2018 Conducted field visits to project sites of Kampong Chhnang PTC, BIT/Battambang, NVIB, Pailin PTC, Banteay Meanchey PTC, NPIA/Siem Reap

3 11-14 June 2018 Conducted field visits to Preah Vihear in relation to IPP 4 9-12 July 2018 Conducted field visits to project sites of Koh Kong PTC- capacity

building

Annex-2: Environmental Monitoring checklists for actual civil works implementations

General information Date: summary up to 30 June 2018 30 June 2018

Checklist prepared by: Contractor/Engineer Name of subprogram/output and location of construction site

New building classroom in (BIT)

Name of contractor/subcontractor (if any) T. S. K. Construction Co., Ltd

Permits, agreements Request for obtaining a campsite is in the public TVET institutions’ campus during construction (if any), renting house is N/A

√ Yes No N/A

Request for obtaining an agreement for disposal of construction waste (if any)

√ Yes No N/A

Management of construction sites

Proper location of construction site/camp √ Yes No N/A

Equipment/plants properly licensed and approved by Ministry of the Environment (MOE).

√ Yes No N/A

Availability of proper storage for fuel, oil and construction materials

√ Yes No N/A

Proper maintenance of construction machinery and equipment (prevent leakage of fuel, oil, lubricants, etc.)

√ Yes No N/A

Use reasonable trucks for transportation of construction materials and waste with tarpaulin or similar materials covering

√ Yes No N/A

Clean the surrounding area from dust by water sprinkling in construction zone (when necessary)

√ Yes No N/A

Clean/ wash tires of vehicles before they get to dwellings and/or drive on highways (when necessary)

√ Yes No N/A

Implementation of works at the established time (e.g. work during daytime 06.00 to 18.00)

√ Yes No N/A

Installation of necessary construction signs in construction sites, i.e. Safety FirstR

√ Yes No N/A

Ensure proper sanitary/ hygienic conditions for workers at the construction site/use the existing in campus?

√ Yes No N/A

Community, Health and Safety

Provision of first-aid facilities for the workers

√ Yes No N/A

Provision of personal protective equipment (PPE) (i.e. gloves, proper shoes, face mask, goggles) to staff and trainees, as necessary.

√ Yes No N/A

Workers need to be aware of the following general rules: (i) no alcohol/drugs on-site; (ii) prevent excessive noise; (iii) no

√ Yes No N/A

38

illegal activities such as, but not limited to gambling, and hunting farm animals in the area; (iv) trespassing on private/ commercial properties adjoining the site is forbidden; (v) no littering in the public TVET institutions; and (vi) workers are not allowed to be loitering in the TVET institutions especially when there are trainings or classes in adjacent building

Ready construction site

Restoration of the area of construction sites and camps when the building construction works are completed

√ Yes No N/A

Replanting/planting of finished work areas (cut one tree replanting two trees)

√ Yes No N/A

Employment (Unskilled labor)

1. Equal pay for equal works √ Yes No N/A

2. At least 25% of unskilled worker has to be employed as women.

√ Yes No N/A 4 females/11 total

3. Child labor in site. √ Yes No N/A

Notice: All unskilled female workers are accepted their slightly daily wage less than men due to men workers do harder and heavier works.

General information Date: summary up to 28 June 2018 28 June 2018 Checklist prepared by: Sam Pheakdey- Engineer Name of subprogram/output and location of construction site

Dorm&workshop in Koh Kong PTC

Name of contractor/subcontractor (if any) General BuildingConstruction Co., Ltd

Permits, agreements Request for obtaining a campsite is in the public TVET institutions’ campus during construction (if any), renting house is N/A

√ Yes No N/A

Request for obtaining an agreement for disposal of construction waste (if any)

√ Yes No N/A

Management of construction sites

Proper location of construction site/camp √ Yes No N/A

Equipment/plants properly licensed and approved by Ministry of the Environment (MOE).

√ Yes No N/A

Availability of proper storage for fuel, oil and construction materials

√ Yes No N/A

Proper maintenance of construction machinery and equipment (prevent leakage of fuel, oil, lubricants, etc.)

√ Yes No N/A

Use reasonable trucks for transportation of construction materials and waste with tarpaulin or similar materials covering

√ Yes No N/A

Clean the surrounding area from dust by water sprinkling in construction zone (when necessary)

√ Yes No N/A

Clean/ wash tires of vehicles before they get to dwellings and/or drive on highways (when necessary)

√ Yes No N/A

Implementation of works at the established time (e.g. work during daytime 06.00 to 18.00)

√ Yes No N/A

Installation of necessary construction signs in construction sites, i.e. Safety FirstR

√ Yes No N/A

Ensure proper sanitary/ hygienic conditions for workers at the construction site/use the existing in campus?

√ Yes No N/A

Provision of first-aid facilities for the workers

√ Yes No N/A

39

Community, Health and Safety

Provision of personal protective equipment (PPE) (i.e. gloves, proper shoes, face mask, goggles) to staff and trainees, as necessary.

√ Yes No N/A

Workers need to be aware of the following general rules: (i) no alcohol/drugs on-site; (ii) prevent excessive noise; (iii) no illegal activities such as, but not limited to gambling, and hunting farm animals in the area; (iv) trespassing on private/ commercial properties adjoining the site is forbidden; (v) no littering in the public TVET institutions; and (vi) workers are not allowed to be loitering in the TVET institutions especially when there are trainings or classes in adjacent building

√ Yes No N/A

Ready construction site

Restoration of the area of construction sites and camps when the building construction works are completed

√ Yes No N/A

Replanting/planting of finished work areas (cut one tree replanting two trees)

√ Yes No N/A

Employment (Unskilled labor)

4. Equal pay for equal works √ Yes No N/A

5. At least 25% of unskilled worker has to be employed as women.

√ Yes No N/A 4 females/11 total

6. Child labor in site. √ Yes No N/A

Notice: The daily wage of women unskilled workers is less then men due to men is stronger than women, heavy work than women and women are acceptable for their work.

General information Date: summary up to 30 June 2018 30 June 2018 Checklist prepared by: Contractor/Engineer Name of subprogram/output and location of construction site

Dormitory in NPIA

Name of contractor/subcontractor (if any) T. S. K. Construction Co., Ltd

Permits, agreements Request for obtaining a campsite is in the public TVET institutions’ campus during construction (if any), renting house is N/A

√ Yes No N/A

Request for obtaining an agreement for disposal of construction waste (if any)

√ Yes No N/A

Management of construction sites

Proper location of construction site/camp √ Yes No N/A

Equipment/plants properly licensed and approved by Ministry of the Environment (MOE).

√ Yes No N/A

Availability of proper storage for fuel, oil and construction materials

√ Yes No N/A

Proper maintenance of construction machinery and equipment (prevent leakage of fuel, oil, lubricants, etc.)

√ Yes No N/A

Use reasonable trucks for transportation of construction materials and waste with tarpaulin or similar materials covering

√ Yes No N/A

Clean the surrounding area from dust by water sprinkling in construction zone (when necessary)

√ Yes No N/A

Clean/ wash tires of vehicles before they get to dwellings and/or drive on highways (when necessary)

√ Yes No N/A

Implementation of works at the established time (e.g. work during daytime 06.00 to 18.00)

√ Yes No N/A

Installation of necessary construction signs in construction sites,

√ Yes No N/A

40

i.e. Safety FirstR Ensure proper sanitary/ hygienic conditions for workers at the construction site/use the existing in campus?

√ Yes No N/A

Community, Health and Safety

Provision of first-aid facilities for the workers

√ Yes No N/A

Provision of personal protective equipment (PPE) (i.e. gloves, proper shoes, face mask, goggles) to staff and trainees, as necessary.

√ Yes No N/A

Workers need to be aware of the following general rules: (i) no alcohol/drugs on-site; (ii) prevent excessive noise; (iii) no illegal activities such as, but not limited to gambling, and hunting farm animals in the area; (iv) trespassing on private/ commercial properties adjoining the site is forbidden; (v) no littering in the public TVET institutions; and (vi) workers are not allowed to be loitering in the TVET institutions especially when there are trainings or classes in adjacent building

√ Yes No N/A

Ready construction site

Restoration of the area of construction sites and camps when the building construction works are completed

√ Yes No N/A

Replanting/planting of finished work areas (cut one tree replanting two trees)

√ Yes No N/A

Employment (Unskilled labor)

7. Equal pay for equal works √ Yes No N/A

8. At least 25% of unskilled worker has to be employed as women.

√ Yes No N/A 8 females/20 total

9. Child labor in site. √ Yes No N/A

Notice: All unskilled female workers are accepted their slightly daily wage less than men due to men workers do harder and heavier works.

41

Annex-3: Photos of safeguards and IPP activities:

On-site capacity building to workers engineers in Battambang BIT (9 May 2018)

On-site capacity building to skilled and unskilled workers, engineers in NPIA (11 May18)

First-Aid provision in BIT and onsite toilet for workers in NPIA and below in Koh Kong (9-12 July 2018)

42

IPP indicators refresher training in Preah Vihear PTC (11-14 June 2018), all IP provinces participated

43

Annex-4: Field report of safeguards orientations to staff and workers on site:

Field report for Safeguards Monitoring Assessment and trainings

The safeguards specialist has conducted safeguards monitoring assessment and capacity building-training/orientation about safeguards issues, involving in civil works construction to skilled and unskilled workers, site engineers as well as site managers, currently working at BIT, NPIA and Koh Kong PTC. The field monitoring assessment went down together with involved officers from TVETSDP including procurement officer and engineers, meeting with primary stakeholders of these 3 public TVET Institutions. The attentions have been paid to the implementations of Environmental Management Plan (EMP) and Environmental Monitoring Checklists that has mentioned in Initial Environmental Examination (IEE), the following are concise summary of Safeguards Monitoring Assessment: 1. The construction of new building classroom in BIT and the upgrading of existing building to be COE building is still not staring yet its civil works during the field visits (9 May 2018):

� The building has net fence to prevent any body enter into the new classroom building. � Site camp is located in BIT campus- within enclosure in building construction. � Temporary toilet has been built at the edge of enclosure net- one toilet for all workers. � Provision of first-aid facilities for the workers in construction building. � Provision of personal protective equipment (PPE) (i.e. gloves, proper shoes, helmets.) to

staff and workers. A few workers still do not use the PPE such as helmet due to if they wear the helmet, they feel headache, they like to wear the common cape/hat and the construction just starting construction of foundation during the field visits.

� Safeguards specialist is strongly instructed to site engineer and site manager to be compulsory to their workers to wear PPE.

� Installation of necessary construction signs in construction sites � Implementation of works at the established time. � Conducted training/orientation to site engineer, site manager and workers about EMP

and Environmental Monitoring Checklists that need to collect monthly (at the end of month).

� Orientation about PPE to staff and workers, personal hygiene, cleaned living, cleaned eating and cleaned drinking to workers and staff

� Photos below delineated the safeguards activities:

44

2. The construction of woman’s dormitory building in NPIA, the COE building is still not staring yet its civil works during the field visits (11 May 2018):

� The building has net fence to prevent any body enter into the workshop building. � Site camp is located in NPIA campus- within enclosure in building constructions. � Temporary toilet has been built at the edge of enclosure net- one toilet for all workers. � Provision of first-aid facilities for the workers in construction building. � Provision of personal protective equipment (PPE) (i.e. gloves, proper shoes, helmets.) to

staff and workers. A few workers still do not use the PPE such as helmet due to if they wear the helmet, they feel headache, they like to wear the common cape/hat and the construction just starting construction of foundation during the field visits.

� Safeguards specialist is strongly instructed to site engineer and site manager to be compulsory to their workers to wear PPE.

� Installation of necessary construction signs in construction sites � Implementation of works at the established time. � Conducted training/orientation to site engineer, site manager and workers about EMP

and Environmental Monitoring Checklists that need to collect monthly (at the end of month).

� Orientation about PPE to staff and workers, personal hygiene, cleaned living, cleaned eating and cleaned drinking to workers and staff

� Photos below delineated the safeguards activities:

3. The construction of workshop and woman’s dormitory buildings in Koh Kong PTC (11 July 2018):

� The building has net fence to prevent any body enter into the workshop and dorm buildings.

� Site camp is located in front of Koh Kong PTC campus. � Temporary toilet has been built at the edge of enclosure net- one toilet for all workers. � Provision of first-aid facilities for the workers in construction building. � Provision of personal protective equipment (PPE) (i.e. gloves, proper/safety shoes,

helmets.) to staff and workers. Some workers still do not use safety shoes due to if they wear the shoe they are not comfortable, they like to wear the common shoe and the construction just completing of foundation and column casting during the field visits.

� Safeguards specialist is strongly instructed to site engineer and site manager to be compulsory to their workers to wear PPE.

� Installation of necessary construction signs in construction sites

45

� Implementation of works at the established time. � Conducted training/orientation to site engineer, site manager and workers about EMP

and Environmental Monitoring Checklists that need to collect monthly (at the end of month).

� Orientation about PPE to staff and workers, personal hygiene, cleaned living, cleaned eating and cleaned drinking to workers and staff

� Photos below delineated the safeguards activities:

Schedule and summary of building constructions and safeguards implementations (EMP/IEE)

No Date of meetings and consultations

Public TVET Institutions

Summary of safeguards issues

1 7 May 2018 Travelling Prepared materials/document and travelled to Kampong Chhnang town

2 8 May 2018 Kampong Chhnang PTC

Conducted site visit, site assessment/measurement the master plan and actual building implantation within master plan (engineering work) updating social and environmental screening checklists.

3 9 May 2018 BIT and NVIB Conducted site visit, investigation of renovation building for COE. workshop, and woman’s dorm building. Orientated/trained about environmental and social safeguards issues to site engineers included skilled and unskilled workers at new classroom building. Understanding social and environmental issues, personal hygiene at site camp, and updating social and environmental screening checklists.

4 10 May 2018 Pailin PTC Conducted site visit, site assessment/measurement the master plan and actual building implantation within master plan (engineering work) updating social and environmental screening checklists.

5 11 May 2018 NPIA Conducted site visit, investigation of COE building implantation, and new building classroom. orientated/trained about environmental and social safeguards issues to site engineers included skilled and unskilled workers at new classroom building.

46

Understanding social and environmental issues, personal hygiene at site camp, and updating social and environmental screening checklists.

6 12 May 2018 Travel back to office in Phnom Penh 7 9 July 2018 Traveling Travelled to Koh Kong Town 8 10 July 2018 Koh Kong PTC Conducted site visit, investigation of current

buildings constructions, technical assessment, checking progress versus proposed work plan by contractor. Asked contractor to prepare the work plan again and speed up the civil works.

9 11 July 2018 Koh Kong PTC Orientated/trained about environmental and social safeguards issues to site engineers included skilled and unskilled workers at workshop and dormitory buildings. Understanding social and environmental issues, personal hygiene at site camp, and updating social and environmental issues.

10 12 July 2018 Travelled Travelled back to office i9n Phnom Penh

47

List of participants in BIT trained on safeguards (Date: 9 May 2018) No. Name Position

1. Mr. Min Dy Skilled worker 2. Mr. AN Doung Skilled worker

3. Mr. Phoeun Skilled worker

4. Mr. Nang Skilled worker

5. Mr. Hou Unskilled worker 6. Mr. Tok Unskilled worker

7. Mr. Vanna Unskilled worker

8. Mr. Vatt Unskilled worker

9. Mr. Kouk Unskilled worker

10. Mr. Khmao Unskilled worker

11. Mr. Pheak Unskilled worker

12. Mr. Phorn Unskilled worker

13. Ms. Yapp Unskilled worker

14. Ms. Neang Unskilled worker

15. Ms. Krouch Ya Unskilled worker

16. Ms. SIn Oun Unskilled worker

17. Mr. Tit Toy Skilled workers 18. Mr. Doc Chantha Site engineer 19. Mr. Chhou Vises EA engineer 20.

48

List of participants in NPIA trained on safeguards (Date 11 May 2018) No. Name Position

1. Mr. Dy Vet Skilled worker 2. Mr.Chham Chhouy Skilled worker

3. Mr. Phlong Ya Skilled worker

4. Ms. Nhouch Touch Skilled worker

5. Ms. Doung Khoan Unskilled worker 6. Ms. Preng Prao Unskilled worker

7. Mr. Chheak Chhun Unskilled worker

8. Mr. Doung Oeun Skilled worker

9. Ms.Pao Srey Roth Unskilled worker

10. Ms. Pao Srey Pich Unskilled worker

11. Mr.Noun Ra Skilled worker

12. Mr. Sor San Skilled worker

13. Ms. Yan Chroep Unskilled worker

14. Ms. Ren Srey Ra Unskilled worker

15. Mr.San Kimseang Unskilled worker

16. Mr. Yann Sok Net Unskilled worker

17. Mr. Tum Hoeun Skilled workers 18. Mr. Chea Sok Vorn Unskilled worker

19. Ms. Chhun Sok Kheng Unskilled worker

20. Mr. Moeun Mot Skilled worker 21. Ms. Phin Sophea Unskilled worker

22. Ms. Chhun Srey Neang Unskilled worker

23. Mr. Orn Dit Unskilled worker

24. Ms. Srey Nor Unskilled worker

25. Mr. Orn Oudam Skilled worker 26. Ms. Hout Vannak Unskilled worker

27. Mr. Chuon Chi Unskilled worker

28. Mr. Lamey Unskilled worker 29. Mr. Chhun Oul Firm Manager 30 Mr. Him Chamnan Site Engineer 31 Mr. Chenda EA engineer 32

49

List of participants in Koh Kong PTC trained on safeguards (11 July 2018) No. Name Position

1. Mr. Ouk Oeun Firm Manager 2. Mr. Thy Skilled worker

3. Mr. Chhloanh Unskilled worker

4. Mr. Tha Unskilled worker

5. Mr. Nay Unskilled worker

6. Mr. Net Unskilled worker

7. Mr.Bata Unskilled worker

8. Mr. Manh Unskilled worker

9. Mr. Chamroeun Unskilled worker

10. Ms.Mei Tae Unskilled worker

11. Ms. Net Unskilled worker

12. Ms. Neath Unskilled worker

13. Ms. Mei Oeun Unskilled worker

14. Ms. Ny Unskilled worker

15. Ms. Kong Unskilled worker

16. Mr. Oeun Unskilled worker

17. Ms. Thy Mouy Unskilled worker

18. Ms. Vorn Unskilled worker

19. Ms. Reasmey Unskilled worker

20. Mr. Tit Unskilled worker

21. Mr.Koeur Unskilled worker

22. Mr. Koa Unskilled worker

23. Mr. Kong Unskilled worker

24. Ms. Srey Vorn Unskilled worker

25. Mr. Chan Som Pheakdey Site Engineer 26. Mr. Pen Sarith EA engineer

27.