4.1 miller bros qualifications - p3 virginia...duct and manhole installation . medium and high...

82
4.1 Miller Bros Qualifications Page 208 REQUEST FOR INFORMATION RESPONSES

Upload: others

Post on 16-May-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

4.1 Miller Bros Qualifications

Page 208REQUEST FOR INFORMATION RESPONSES

Page 2: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

Renewable Qualifications Statement

February 20, 2015

This electronic message is intended to be viewed only by the individual or entity to whom it is addressed. It may contain information that is

privileged, confidential and exempt from disclosure under applicable law. Any dissemination, distribution or copy of this communication is

strictly prohibited without our prior permission. If the reader of this message is not the intended recipient, or employee or agent responsible

for delivering the message to the intended recipient, or if you have received this communication in error, please notify us immediately by

return email and delete the original message and any copies of it from your computer system. Miller Bros at 301 Alan Wood Road,

Conshohocken, Pennsylvania 19428.

Page 209REQUEST FOR INFORMATION RESPONSES

Page 3: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

Electric Utility On-Call Emergency/Disaster Response Aerial and Underground Construction

Duct and Manhole Installation Medium and High Voltage

Transmission and Distribution Installations up to 500kV

Substation and Switchyard OPGW, ADSS, ACSR

Transit Services Fiber Optic Installation

Catenary Column & Cable Installation Rail Relay and Switching

Railway Signalization Caisson Installation

Traction Power Bonding

Heavy & Highway Traffic Signal Construction & Maintenance

Intelligent Traffic Systems Highway Lighting

Horizontal Directional Drilling (HDD) Vertical Coring & Conventional Bores

Commercial Interior & Exterior Power Distribution

Fire Alarm/ Security/ Data/ BAU SCADA/Smart Grid Lighting Solutions

Generators, UPS’s, VFD’s Operations & Maintenance

TEGG Infrared Testing

Power System Studies Arc Flash Hazard Analysis Preventive Maintenance

Breaker Testing Upgrade, Reconditioning

& Retrofit Projects 24/7 Technical Support

Renewable Energy Solar, Wind, Co-Gen, CHP Full Project Development

Complete Project Financing Full EPC

Operations & Maintenance Monitoring & Data Collection

Natural Gas Utility Main and Service Installation and Repairs

Low Pressure to High Pressure Riser Replacement and Meter Sets

Integrity/Corrosion Inspections & Repairs Horizontal Directional Drilling (HDD)

Vacuum Excavation Operator Qualifications(OQ):NGA, ITS & MEA

Telecommunications Underground and Aerial Installations

ADSS and OPGW Inside and Outside Plant Construction

Fusion Splicing & Testing Duct and Manhole Installation

3/2/2015 1

24/7 EMERGENCY SERVICE

Page 210REQUEST FOR INFORMATION RESPONSES

Page 4: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

Table of Contents

Company Overview Table of Contents General Information Financial, Insurance, Safety & Bonding Information Key Personnel Resumes Project Management Plan Solar Project Experience Equipment Appendix A: Health & Safety Documentation Appendix B: Quality Management Plan Appendix C: Solar Project Case Studies Appendix D: NJ Licenses & Certificates Appendix E: Insurance

Page 211REQUEST FOR INFORMATION RESPONSES

Page 5: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

General Information 

 

Facilities 

Physical Address:    301 Alan Wood Road, Conshohocken, PA 19428 Main Telephone Number:  610‐832‐1000 Main Fax Number:    610‐832‐1005 Website:      www.millerbros.us    Corporate Information 

 General  Date Company Originated:  1937 Date of Incorporation:    1989 State of Incorporation:    Pennsylvania  Management  Harry B. Miller III    President and Chief Executive Officer Michael T. Miller    Executive Vice President Gerard deLisser     Vice President, Project Development Douglas Stoneback    Vice President, Operations  

 

Regional Offices 

Pennsylvania 

Physical Address:    301 Alan Wood Road, Conshohocken, PA 19428 Main Telephone Number:  610‐832‐1000 Main Fax Number:    610‐832‐1005  

 

Page 212REQUEST FOR INFORMATION RESPONSES

Page 6: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

Corporate Financial, Insurance and Bonding Information 

Financial Statement 

 A statement of Miller Bros financial condition including our latest year end audited financial statements can be provided upon request.  Insurance, Health & Safety 

 Insurance Agency  Agent:      The Safeguard Group, Inc.       100 Granite Drive, Suite 205, Media, PA 19063 Contact:    Apurva Upadhyay, CRIS Phone:      973‐921‐8201 Policies:  General Liability, Workman’s Compensation, Automobile, Umbrella Liability, 

Inland Marine  Insurance Coverage  General Liability:  $1,000,000.00 Each Occurrence Automotive:  $1,000,000.00 Each Occurrence Umbrella:  $10,000,000.00 Each Occurrence Inland Marine:  $2,341,208 Blanket  Experience Modification Rates  2014    .684 2013    .808 2012    1.06 2011    .985 2010    .985  Corporate Safety Programs  Comprehensive written safety and hazardous communications programs are currently in place, which address all of the procedures relative to the electrical construction industry. A copy of the safety manual is available upon request along with additional other safety statistics.  Bonding Information  Bonding Company:    Willis of Massachusetts, Inc.         185 Asylum Street, 25th Floor, Hartford, CT 06103 Contact:      Danielle M. Bechard, Senior Client Manager Phone:        860‐241‐4438 Bonding Capacity:    $100,000,000+ 

Page 213REQUEST FOR INFORMATION RESPONSES

Page 7: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

Home Office Key Personnel – The Miller Bros. Team 

 Corporate Operations    Harry B. Miller III         President           Michael T. Miller         Vice President  

Gerard deLisser      Vice President, Project Development 

                 Douglas Stoneback         Vice President, Operations          Scott Rhea         Vice President, Utility Services          Steve Johnson         Director, Utility Services          Rick Rizzardi         Director, Gas Services                Estimating & Project Mgmt   John Irving         Chief Estimator & Senior Project Manager                                  Joe Marrone         Estimator & Senior Project Manager                  Matthew Williams         Senior Project Manager          Tyson Mandell         Project Manager          Anthony Barbetto          Project Engineer  Asset Mgmt. / O&M    Ryan Hoffman         Director of Asset Management           Financial Operations    Danielle Mazza, CPA, CGMA         Controller  Health & Safety     Lisa Rancitelli         Health & Safety Director 

Page 214REQUEST FOR INFORMATION RESPONSES

Page 8: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

Safety Plans 

Miller Brothers is dedicated to maintaining the safety and health of our employees. Our company has an OSHA  compliant  internal  safety  program  and  staff members  dedicated  to maintaining  the  plan  and training of new staff. Miller Bothers has qualified and successfully worked under numerous federal and corporate  safety  programs  and  requirements.  This  historical  concern  for  the  well  being  of  our employees results in a strong company emphasis on health and safety in all aspects of the construction business.  The  nature  of  the  electrical  construction  industry  requires  strict  attention  to  construction safety  protocols.  We  are  committed  to  meeting  the  stringent  health  and  safety  controls  that  are necessary to protect the health of workers and the public. Our health and safety program is designed to address both the risks of heavy civil construction and electrical  installation. Successful  implementation of our health and safety program on complex projects has been a significant part of the Miller Brothers experience.  The  Project  Manager  always  retains  overall  responsibility  for  the  projects  safety performance. His foremost concern is protecting the safety and health of both the on‐site workers and the public at large, while executing site activities in strict accordance with the approved safety program, project  plans  and  regulatory  requirements.  Through  aggressive  management  oversight,  the  Project Manager and the Superintendant properly coordinate with our Safety & Health Manager to implement the most current Miller Brothers safety program procedures and  the approved Site Safety and Health Plan (SSHP).  Cost Controls 

Cost control  is a constant focus for Miller Brothers project team.  It begins with the estimating process and  continues with  project  execution  and  closeout.  Throughout  this  process,  our  Project Managers utilize a variety of tools to keep focused on controlling and managing cost. Our belief is that efficiencies are  found  and  errors  are  avoided  through  regular  detailed  analysis  of  productions, man‐hour  costs, material  costs, equipment  costs and  subcontractor  costs  in addition  to assessing  risk. Miller Brothers executes  the same stringent  level of cost control and procedures  for  fixed price projects as we do  for cost reimbursable projects. For us, each of our procedures makes good business sense and we  follow them  because  they  provide  for  tight  project management  control  and  cost  effective  results  on  all projects. Cost  control begins during  the project planning  stage  in our estimating process with a  clear definition of  the project  scope  and performance  activities,  specific  task  analysis,  time,  crew  size  and composition  and  equipment.  Miller  Brothers  estimating  methodology  uses  build‐up,  bottoms‐up approach  to  cost estimating,  identifying and  reviewing  specific activities and  then  incorporation each into a cost estimate. Our system allows us to efficiently execute our preferred estimating methods by enabling  the  separation  and  segregation of pricing  for  each work  activity,  as well  as  summarizing or “rolling  up”  categories  for  total  estimate  cost  calculations.  The  granularity  that  comes  with  this approach helps ensure that once operations begin, there are no significant cost swings. Miller Bothers identifies major subcontractor activities early on in the bid process and develops comprehensive scopes of  work  as  the  basis  for  soliciting  subcontractor  quotes.  We  solicit  multiple  quotes  for  materials, subcontracts and equipment  rentals with  the  support of our Procurement Manager. We  require  firm written quotes  indicating prices, quantities,  availability  and delivery  constraints  as well  as  terms  and conditions.  The  Project  Management  Team  reviews  the  cost  proposal.  We  also  evaluate  value engineering  opportunities  and  alternatives  that  offer  cost  savings  and  incorporate  them  into  the proposal as deemed appropriate.      

Page 215REQUEST FOR INFORMATION RESPONSES

Page 9: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

Cost Tracking 

Our Superintendant and Foreman review actual productions daily at the end of the shift to make real‐time adjustments preceding continued operations  to ensure  the project meets budgeted productions. Weekly operations meetings huddles provide our project  staff an opportunity  to  review  the  resource utilization and rental reports, in addition to commitments and purchasing. Productivity and cost per unit of production are tracked against budget for both self‐performed and subcontracted tasks. Balancing resources is an essential element of our approach to effectively control costs, both direct and indirect on our projects and as a company.  It  is also a major  influence on all of our areas of operation (continuity  of  personnel,  process/procedure  familiarity  and  client  knowledge).  Accurate  manpower projections,  timely  acquisition  of  materials  and  services  and  proper  scheduling/  deployment  of equipment and subcontractors are critical to successful performance and effective cost control.  Change Management 

To effectively and efficiently manage change orders and additional scope  items and to ensure that the client  is aware of  costs as work  is occurring, our Project Manager  coordinates  closely with  the  client about each item not only prior to work beginning but during the entire design and construction process to minimize change orders as a result of additional work. Our primary objective  is  to deliver a quality project safely, on‐time and within budget. We  recognize  the value of continuously sharing up‐to‐date information to avoid errors, quality concerns or  interferences on the project. Miller Brothers manages multidirectional  communication between  the  engineers,  subcontractors  and  clients  in  the  event  that Request  For  Information  (RFI)  responses  provided  result  in  a  change  of  price  or  schedule.  Similarly, Miller Brothers manages  the change order process  to  limit  impact  to Miller Brothers and  the owner’s budget as well as any detrimental  impact  to  the project schedule. To do so, our Project Manager has constant communication within the project team and keeps detailed knowledge of the scope of work for each subcontractor.  

    

Page 216REQUEST FOR INFORMATION RESPONSES

Page 10: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

 Schedules 

Miller Brothers has established standard planning and scheduling methodologies and procedures  that we utilize during the estimating process, upon award (during job start up), and throughout the projects duration. We use several  industry standard systems and  tolls  in the planning process.  In addition, our project  delivery  team  extensively  uses  internal  manuals,  procedures,  forms  and  checklists.  Miller Brothers  offers  our  clients  a  thoroughly  coordinated  approach  to  integrate  planning,  design development,  permitting,  procurement,  construction,  inspections  and  commissioning.  Our  plans  are driven by the major milestones and critical paths shown in our project schedule. We sequence activities in parallel to fast‐track the project schedule in order to meet the required completion date. This process is the same for all design/build projects. The on‐time execution of this project of this project is reliant on full  client  involvement,  including  early,  rapid  and  continuous  participation  for  design  reviews  and approvals as well as efficient permitting  from  local authorities. The  final stages of  the project  require careful and diligent coordination of multiple calendars in order to obtain required inspections and utility interconnection. The most critical client coordination points are as follows: 

Fast tracked design development process so we can quickly produce 100% design documents. 

Regular involvement and support during the construction process to avoid delays. 

Communication and coordination during inspections, utility interconnection, commissioning and project close‐out. 

With  this  level of  client  support, Miller Brothers will deliver a  successful,  safe project  that meets  the required completion date on schedule and within budget.  Quality Management System 

Miller Brothers defines “quality” as meeting standards, requirements and expectations of both internal and  external  customers.  The QMS  provides  the  structure  to  achieve  the  quality management  goals necessary  to obtain world‐class  standards of performance  and quality  in  all  areas of operations. The purpose of the QMS is to ensure the quality of products and services provided to customers. The QMS is a  framework  that  provides  structures  for  organizational  level  and  project‐specific  quality  planning, implementation and performance assessment. The QMS consists of the following components:  

Corporate Position on Quality – Describes the corporate policy on quality. 

Quality Assurance Program Plan  (QAPP) – Defines the elements of the QMS and the roles and responsibilities  of  the  corporate  and  quality  control  organizations.  Provides  details  for implementation of each element of  the QWS. The QAPP  is  the basis  for program‐focused and project‐focused Quality Control Project Plans (QCPs). 

Quality Control Project Plans (QCPs)‐Detailed QA/QC documents designed for specific programs or individual projects. Requirements are tailored to particular contracts, customer expectations, specific scopes of services and site conditions. 

Quality  Control Manual  (QCM)‐  Document  specifying  who  shall  apply  what  procedures  and when to a specific product, process and/ or service. 

Standard Operating Practices (SOP’s) – Company‐adopted QA procedures and repetitive process operations referenced by the QAPP and contained in the quality control manual. 

    

Page 217REQUEST FOR INFORMATION RESPONSES

Page 11: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

 Quality Assurance 

Quality assurance involves our system of activities and procedures that ensures that a process, product or service meets the needs and expectations of the customer. QA is an integral part of the QMS. The organizational and project‐specific quality elements of the QMS are used to define QA practices. 

Quality  elements  at  the  organizational  level  regulate  activities  that  support  common  or standardized functions such as employee qualifications and training, document control, billing, cost reporting and material procurement.  

Quality elements at  the project  level address  the definition and  implementation of  customer requirements to produce the desired type and quality of product service. 

 Some specific examples of organizational quality elements in the QMS are:  

QAPP and quality procedures implementing the plan. 

The QAM who oversees, assesses and maintains the quality system. 

Management  assessments  which  provide  feedback  to  corporate  management  on  the effectiveness of the QMS. 

Independent review of design prior to release to customers. 

The use of SOPs to provide standardization of repetitive activities. 

Procurement policies and standard procedures used to achieve necessary and sufficient quality standards in procurement of items and services subcontracts. 

Document  control  procedures  to  that  guide  the  use  of  correct  versions  of  reviewed  and distributed documents in addition to the proper disposition of quality documents. 

Quality improvement processes to improve service, process and product quality. 

Computer hardware and software control to verify that appropriate results are obtained.  Some specific examples of project‐level quality elements in the QMS are:  

Project planning  for all projects,  regardless of  size: planning based on  contract  requirements, the use of customer communications, work plans and project instructions. 

Preparation and  implementation of construction QC Plans with procedures that specify how to carry out activities and define inspection to ensure equality. 

QCP’s that document the data collection planning process, describe specific procedures for data collection. 

Quality assessments and audits used as follow‐up. 

Document and design reviews by qualified technical personnel and senior reviewers to reduce errors and ensure consistency. 

Technical assessments for the technical adequacy of items, activities and documents.’ 

Quality  implementation  of work  processes  (i.e.  follow  only  planned,  reviewed  and  approved procedures.) 

Generation  of QC  records  stating  quality  results  achieved  or  providing  evidence  of  activities performed.  

     

Page 218REQUEST FOR INFORMATION RESPONSES

Page 12: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

The quality program  is applicable  to all Miller Brothers projects. The quality elements and procedures are applied to specific activities being performed to the appropriate degree based on the importance of each activity in achieving technical and quality objectives. This is a graded approach to quality designed to achieve the following:  

Uncompromised adherence to project safety and safe work practices. 

Conformance and compliance with contract requirements. 

Use of necessary and documented methods to obtain reported data. 

Reported data are valid and of known quality. 

Reported observations, analyses are accurate and within known limits. 

Designed facilities will meet design objectives and function satisfactorily. 

Controls in place to perform work safely with protection of project personnel in compliance with applicable federal and state health and safety rules. 

Maintenance of appropriate project records.  Quality Assurance Plan 

The QAPP describes the QMS describes the QMS.  It  is applicable  to all Miller Brothers operations and provides direction  to all administrative and  technical areas. The QAPP  takes precedence over  internal policy matters and all other quality related documents.  Quality Control Project Plans 

Contracts  or  large  programs  sometimes  require  quality  elements  that  are more  specific  than Miller Brothers QAPP. To address these elements, program‐specific QCP’s will be prepared and implemented. The requirements documented in a QCP take precedence over the QAPP for the program. The QCP’s will be tailored to meet the specific needs of the program to which they apply.     

 Construction Quality Control Plan 

The Construction Quality Control Plan (CQCP) is developed to ensure the following: 

To  achieve  a  quality  product  on  time  and  in compliance with the terms of the contract. 

To  establish  and  utilize  a  construction  quality program  of  the  scope  and  character  necessary  to achieve  the  quality  of  construction  outlined  in  the contract. 

To  produce  and maintain  acceptable  records  of  its quality control activities. 

The  CQCP  defines  the  QMS  for  a  construction  project  as dictated by customer requirements. The QMS consists of the plans, procedures and organization necessary to construct the facility  in  accordance  with  the  contract  and  design specifications.  The  CQCP  covers  all  construction  operations, both  on‐site  and  off‐site  as  well  as  work  performed  by subcontractors, fabricators, suppliers and purchasing agents. 

Page 219REQUEST FOR INFORMATION RESPONSES

Page 13: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

The CQCP  is used to verify that the construction activities are performed  in a timely manner, reliable, meet their intended purpose and are of the specified quality. The CQCP includes the processes used to verify construction quality  in  the work processes, materials of construction and construction  services. Components of a CQCP include: 

QC organization, including lines of authority and communication. 

Qualifications of QC personnel. 

Definable feature of work (DFW) 

Procedures for scheduling and managing submittals. 

Surveillance 

Inspection 

Acceptance of testing procedures. 

Testing methods. 

Documentation procedures. Implementation of the CQCP is the responsibility of all personnel providing services for the construction. The Construction Quality Systems Manager (CQSM) verifies he implementation of a CQCP.  Three‐Phase Quality Control Process 

Each phase of the control process presents the programmatic requirements for ensuring that the work is completed in a coordinated and efficient manner with the highest level of integrity and quality.  The Preparatory Phase is executed prior to initiating a DWF. The CQSM will conduct a preparatory phase meeting to ensure that all necessary pre‐construction activities have been completed including: 

Permit requirements and approvals 

Notifications 

Submittal Approvals 

Materials Management 

Specifications and drawings review  

The preparatory Phase also establishes equipment and manpower requirements and defines personnel roles and responsibilities. Safety and health requirements are also  identified and discussed during  the Preparatory Phase of quality control. The Internal Phase of the quality control process ensures that the requirements and methods identified during the Preparatory Phase are implemented appropriately. This phase establishes the minimum quality requirements, workmanship and methods for execution of the DFW  or  task.  It  is  implemented  during  the DFW  inception  prior  to  significant work  completion.  The Follow‐Up Phase of the quality control process  is completed during the DFW execution to ensure that the minimum quality requirements established during the Initial Phase are being met. This phase covers all work completed from the end of the initial Phase through the completion of the DFW. The Follow‐Up Phase includes all required testing and inspections.   Meetings and Inspections 

QC meetings  and  inspections will  be  conducted  and  documented  to  ensure  that  the QC  process  is working. This phased system of quality control will be implemented for each DFW as previously defined or  as  defined  by  the  CQCO  or  CQSM. All  inspections will  be  documented  and  attached  to  the Daily Quality Control Report (DQCR).     

Page 220REQUEST FOR INFORMATION RESPONSES

Page 14: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

Craft Worker Statement 

Miller  Brothers  employs  full‐time  craft  workers  from  all  trades.  Our  workforce  of  trained  and experienced  line workers,  electricians,  laborers,  equipment  operators, mechanical workers  and  iron workers means that we can successfully handle any task related to the project in‐house.  Our workforce is dedicated to delivering the highest quality product for our valued clients and customers.  Submittals and Documentation 

The  CQSM  will  be  responsible  for  review  and  management  of  all  submittals  prior  to  transmittal. Submittals will be  reviewed  to ensure  that  they are accurate and  completed  in  conformance with all applicable specifications. Items identified for “Client Approval” in the project contract specifications will be submitted  to  the appropriate client  reviewers  in  the quantities specified  in  the contract. Copies of data for  items  listed as “For  Information Only”  in the specifications will be submitted  in the quantities specified in the contract.  Submittals  requiring  client  approval will  be  stamped  and  dated  by  the  approving  agency. Once  the submittal has been reviewed and coded, the appropriate actions will be taken based on the reviewers comments, approval or re‐submittal requirements. A submittal register will be maintained will  for  the project  duration  by  the  CQSM  and will  be  revised weekly  to  update  submittal  status.  The  updated register will  be maintained  on‐site  (accessible  to  all  project  personnel)  and  an  updated  copy will  be provided weekly to the client.  Field Logbooks and Daily Record Keeping 

The  CQSM will maintain  a  daily  field  CQC  logbook  of  construction  activities.  The  intent  of  the  CQC logbook is to consolidate field notations for all construction quality control related project activities and will be the core document used to generate the DQCR’s. The logbook will be used as the primary source to document used to generate the DQCR’s. The logbook will be used as the primary source to document quality control information and CQC research.  Construction Daily Quality Control Reports 

Miller Brothers will maintain daily  records and submit daily  reports on all construction quality control activities. The reports will be factual records containing all construction related numerical data (i.e. test results) and quality control  logs. The construction DCQR will contain the daily record of  inspections for all work accomplished subsequent to previous day’s work. The DCQR will consolidate and summarize all reports and logs for the day and copies of these documents will be attached to the DCQR.   Deficiency Management 

This  section  describes  the procedures  for  controlling  items  that  are noncompliant with  the  specified design  requirements. A  tracking  system  (i.e.  electronic  spreadsheet) will  be  implemented  to  identify such nonconforming items and monitor them through resolution by corrective action. Deficiencies may be  identified  during  all  of  the  three‐phases  of  the  quality  control  process.  Defects  and  deficiencies identified will be documented  in  the DQCR. Once  identified, defects and deficiencies will be added  to the  tracking  system  and  will  be monitored  closely  until  the  appropriate  corrective  action  (re‐work, repair,  replacement  or  acceptance0  is  completed.  The  client  will  be  informed  of  all  identified deficiencies  the  prescribed  corrective  action(s)  and  the  status  of  the  corrective  action  through completion. Once  the corrective action(s)  for an  identified  item has been completed,  the  item will be closed‐out  by  removing  it  from  the  active  corrective  action  request  log  and  finalizing  the  non‐conformance report. Stop work authority can be used whenever continued work will either compromise 

Page 221REQUEST FOR INFORMATION RESPONSES

Page 15: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

the quality of the project or jeopardize the health and safety of the workers. All stop work actions must be documented  including  identification of the person(s)  involved, persons notified of the action, tasks being performed and  the deficient act or material that  justifies the stop work action. Work related  to the  deficiency will  not  be  allowed  to  continue  until  the  appropriately  prescribed  actions  have  been implemented and documented.  Field Work Variances 

All variances from the contract specifications or drawings will be documented. This report will  identify the variance, proposed change, technical  justification, cost and schedule  impact  (to be determined by the PM as applicable). All  field work variance  reports must be  reviewed, approved and  signed by  the client prior to implementation.   Punch List 

Punch‐lists are a tool for identifying remaining items to be addressed and are associated with a DFW or a specific work tasks. A project construction punch  list will be generated by the CQSM  for each major portion of work. These punch  lists will  identify all outstanding  items to be completed prior to approval and release of final payment. Construction punch lists will identify the item to be addressed, the date of notice,  the  individual  identifying  the  problem,  the  person  responsible  for  addressing  the  item,  the method by which the item is addressed and the date the item is addressed and accepted by.  Testing 

All  tests  and  inspections will  be  performed  in  accordance with  the  procedures  contained within  the project  contract  documents.  The  QCSM  will  be  responsible  for  the  tracking,  verification  and documentation of all contract documents. The QCSM will be  responsible  for  the  tracking, verification and documentation of all test and inspection activities and data. The contractor will perform specified or required  tests  to  verify  that  control measures  are  adequate  to  provide  a  product  that  conforms  to contract requirements.  Project Closeout Procedures 

Project  Closeout  Procedures  are  established  to  identify  the  requirements  for  the  final  project acceptance and ensure that Miller Brothers and  its subcontractors and vendors have satisfactorily met all obligations as defined in the contract documents and all changes or modifications as identified in the project documentation.  Final Inspection 

Once  all  items  on  the  punch  list  are  addressed  to  the  client’s  satisfaction,  a  final  inspection will  be conducted. The final  inspection will ensure that all outstanding  items,  including noted deficiencies and punch list items have been corrected and/ or addressed.  Pre‐Operation and Sequence Verification 

POSV, as appropriate, will be completed prior to system start up. All operating systems will be “tagged‐out” until the POSV is completed under witness by the CQSM and the client. All system components will be tested for proper placement and/or operation prior to start‐up. Upon completion of the POSV, the responsible  technician  or  engineer  and  the  CQSM  will  prepare  and  sign  a  POSV  checklist  (system specific)  that  identifies  each  tested  component  and  the  date  and  time  of  POSV.  Additionally,  the technician  or  engineer  and  the  CQSM will  initial  each  component  as  having witnessed  their  proper operation. 

Page 222REQUEST FOR INFORMATION RESPONSES

Page 16: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

System Start‐Up 

Upon  completion  of  the  POSV  process,  the  system  will  be  approved  for  start‐up.  Final  system adjustments will be made during  the  start‐up process  to ensure  that  all  components  are  functioning within the specified range(s) of operation.  Communication during Construction 

To efficiently execute construction work, an effective communications network must be established to resolve nonconference  issues  that may  arise. Open  lines of  communication  are essential  to maintain strong working  relationships and provide a quality‐constructed  facility. To  facilitate communication, a set of forms is used to document many of the projects activities. Forms currently available and useful to a project are presented  in appropriate SOPs. Additional communication  forms and documentation are developed as deemed necessary on a project‐specific basis.  Construction Reports 

The  following  construction  reports  or  others  as  identified  in  a  project  specification  are  issued  to communicate progress of the progress of the project to the customer: 

Analytical data reports 

Daily quality controls reports 

Quality control summary reports 

Records arising from the disposal of potentially hazardous construction waste  Quality Assurance & Acceptance Testing 

Miller Brothers will conduct a  full System Quality Control Audit upon completion of system assembly. This  QC  Audit  will  include  a  full  site  visit  and  inspection  upon  completion  of  the  project  by  our designated Engineering team auditor.  

 

Page 223REQUEST FOR INFORMATION RESPONSES

Page 17: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

Recent Solar Projects

Toys R’ Us, Inc., Rooftop Array, Flanders, New Jersey 5.4MW Constellation Energy, John Gummel, Project Manager, 215.390.2048

Interconnection, Substation, AC/DC Wiring, Testing & Commissioning. Q4 2011

Benjamin Moore Paints, Inc., Ground Array, Flanders, New Jersey 1.9MW

Constellation Energy, John Gummel, Project Manager, 215.390.2048 Interconnection, Substation, AC/DC Wiring, Testing & Commissioning.

Q4 2010

Hess Corporation, Ground Tracker Array, Woodbridge, New Jersey 1.1MW Sunpower Corporation, Eric Dietl, Senior Project Manager, 609.964.8900

Installation of Ground Mount Tracker System, Interconnection, Substation, AC/DC Wiring, Testing & Commissioning.

Q1 2012

Arthur Ashe Youth Tennis Center, Rooftop Array, Philadelphia, Pennsylvania 330kW Arthur Ashe Tennis Center 215.487.3477

Interconnection, Substation, AC/DC Wiring, Testing & Commissioning. Q3 2011

Vineland Solar Plant, Ground Array, Vineland, New Jersey 6.5MW

Constellation Energy, John Gummel, Project Manager, 215.390.2048 High Voltage Installation, AC/DC Terminations & Final Commissioning.

Q2 2011

Maryland Port Authority Cruise Terminal, Rooftop Array Baltimore, Maryland 750kW Pepco Holdings, Inc

Q4 2011

Frenchtown I, Ground Array, Frenchtown, New Jersey 3.5MW RMT Energy, 608.831.4444

High Voltage Installation, Re-commissioning, Final Commissioning. Q2 2011

Page 224REQUEST FOR INFORMATION RESPONSES

Page 18: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

Recent Solar Projects

Frenchtown II, Ground Array, Frenchtown, New Jersey 3.5MW RMT Energy, 608.831.4444

High Voltage Installation, Re-commissioning, Final Commissioning. Q2 2011

Flemington Solar, Flemington, New Jersey 9MW

RMT Energy, 608.831.4444 High Voltage Installation, Re-commissioning, Final Commissioning.

Q2 2011

Lebanon Solar, Ground Array, Lebanon, New Jersey 2.3MW High Voltage Installation, Re-commissioning, Final Commissioning.

RMT Energy, 608.831.4444 Q2 2011

Citizens Energy, Devens, Massachusetts 3MW

Toshiba Corporation, John Gummel, Project Manager 866.810.9758 Installation of Ground Mount System, Interconnection, High Voltage, AC/DC Wiring, Testing,

Commissioning Q3 2012

Mountain Creek, KDC Development Corporation, Ground Mount Arrays 7MW

Interconnection, High Voltage, AC/DC Wiring, Testing, Commissioning Sebastian M. Marano, SVP Engineering 908.212.3625

Q3 2013

ImClone, KDC Development Corporation, Ground Mount Arrays 10MW Interconnection, High Voltage, AC/DC Wiring, Testing, Commissioning

Sebastian M. Marano, SVP Engineering 908.212.3625 Q3 2013

Page 225REQUEST FOR INFORMATION RESPONSES

Page 19: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

Recent Solar Projects

Chelmsford Public Schools, Roof Arrays, Chelmsford, MA 2.3MW Johnson Controls Inc., Purchasing, 781-224-5525

Full EPC, in construction Q3 2014

Pittsgrove Solar Project, South Jersey Industries, Ground Mount Array 2.3MW

S.J.I., Inc. 609-568-9028, Full EPC Q4 2013

Newark International Airport, Borrego Solar, Roof Mount Array 600kW

Borrego Operations (888) 898-6273 Complete mechanical and electrical construction

Q1 2014

Brickyard Solar Project, South Jersey Industries, Ground Mount Array 2.3MW S.J.I., Inc. 609-568-9028 Full EPC, in construction

Q4 2014

J&J Mc Neil, Conergy, Ground Mount Array 500kW Conergy Projects Group 888-396-6611

Complete mechanical and electrical construction Q3 2014

Holland Solar Project, South Jersey Industries, Ground Mount Array 3.4MW

S.J.I., Inc. 609-568-9028 Full EPC, in construction

Q4 2014

Frankford Solar Project, South Jersey Industries, Ground Mount Array 10 MW

S.J.I., Inc. 609-568-9028 Full EPC, in construction

Q4 2014

Ogdensburg Solar Project, NYSERDA, Ground Array 2.7 MW

NYSERDA 518-862-1090 Full EPC, in construction

Q2 2015

Page 226REQUEST FOR INFORMATION RESPONSES

Page 20: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

NextEra Energy Resources, Acquisitions, LLC 700 Universe Boulevard Juno Beach, FL 33408 www.NextEraEnergyResources.com

Request for Information Solar Energy Development Project Presented to Virginia Public - Private Partnerships March 13, 2015

Page 227REQUEST FOR INFORMATION RESPONSES

Page 21: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

VIRGINIA PUBLIC-PRIVATE PARTNERSHIPS REQUEST FOR INFORMATION - SOLAR ENERGY DEVELOPMENT PROJECT March 13, 2015

The contents of this document are non-binding. Page | 2

General Information

1. What relevant qualifications and experience does the respondent have in developing and delivering large (>100kW) solar energy projects?

Company Overview

NextEra Energy Resources, LLC (NextEra) is one of the largest wholesale generators of clean power in the U.S. Our parent company, NextEra Energy, Inc. (NYSE: NEE), is a publicly traded Fortune 200 company with approximately $74 billion in total assets that has been in business since 1925. In 2014, NextEra Energy, Inc. recorded consolidated revenues of approximately $17 billion, and as of year-end, owned 44,900 MW of generating capacity in operation. Additionally, NextEra Energy, Inc. employs nearly 14,000 employees in 26 states and Canada.

As an unregulated, competitive energy business, NextEra’s primary business objective is the development, construction and operation of power plants. The company has been generating clean energy for more than 25 years and is the largest generator of wind and solar power in North America, with more than 11,000 MW of wind and 1,200 MW of solar commercially operating in its portfolio. Of the 19,500 MW of generating assets we own in operation, approximately 95% are generating electricity from clean or renewable sources.

Solar Experience

NextEra has greater than 1,000 MW of solar operating, in construction, or in development with a PPA across the United States. The following is a list of NextEra’s currently operating utility-scale solar facilities:

Facility Location Size Description NextEra Role

Genesis Solar Blythe, California 250 MW Solar thermal generation facilities commenced commercial operation in April 2014. PG&E is the energy buyer.

Construct, own and operate

Desert Sunlight Riverside County, CA

550 MW Photovoltaic generation facilities commenced commercial operation in 2013 and 2014. SCE and PG&E are the energy buyers.

Managing partner and 50% owner

Solar Electric Generating Station (SEGS)

Kramer Junction and Harper Lake, California

310 MW SEGS is currently the largest solar project in the United States, using solar thermal technology. Commercial operation dates for the different units range from 1986 to 1990 and SCE is the energy buyer.

Own and operate

Paradise Solar West Deptford, New Jersey

5 MW Photovoltaic solar generation in facility commenced operation in 2010 and the energy is sold into the PJM market.

Construct, own and operate

Page 228REQUEST FOR INFORMATION RESPONSES

Page 22: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

VIRGINIA PUBLIC-PRIVATE PARTNERSHIPS REQUEST FOR INFORMATION - SOLAR ENERGY DEVELOPMENT PROJECT March 13, 2015

The contents of this document are non-binding. Page | 3

Facility Location Size Description NextEra Role

Hatch Solar Hatch, New Mexico

5 MW Concentrating photovoltaic solar generation facility commenced commercial operation in 2011 and El Paso Electric is the energy buyer.

Construct, own and operate

St. Clair Solar Lambton County, Ontario, Canada

40 MW Photovoltaic solar generation of two projects of 20 MW each. Commenced commercial operation in February 2012 and Ontario Power Authority is the energy buyer

Construct, own and operate

Mountain View Solar

North Las Vegas, Nevada

20 MW Photovoltaic solar generation facility commenced commercial operation in January 2014. NV Energy is the energy buyer.

Construct, own and operate

Planta Termosolar I & II

Madrigalejo, Caceres, Spain

100 MW Solar thermal generation including 7 hours molten salt storage. Commenced commercial operation in 2013

Construct, own and operate

The following is a list of solar facilities either under construction or contracted and scheduled to begin construction soon:

250 MW of photovoltaic generation near Blythe, California. Facility scheduled to commence commercial operation in 2016 (McCoy Solar). Southern California Edison is the energy buyer. NextEra will construct, own and operate.

27 MW of photovoltaic generation in Adelanto, California. Facility scheduled to commence commercial operation in 2015. Southern California Edison is the energy buyer. NextEra will construct, own and operate.

20 MW of photovoltaic generation in Shafter, California. Facility scheduled to commence commercial operation in 2015. Pacific Gas & Electric is the energy buyer. NextEra will construct, own and operate.

Distributed Generation Business

We are an energy company that builds and operates large, complex projects, with the flexibility to execute smaller, distributed projects as well. NextEra’s Distributed Generation (DG) business is a premier provider of solar power solutions serving commercial, institutional, utility, and public power customers across the country.

The DG business has transacted on more than 105 MW of distributed scale (below 20 MW in capacity) solar projects across eight states in the past several years. The projects below have been executed with a variety of customers (PPA off-takers), including public and private schools and universities, municipalities, commercial entities, investor-owned utilities, municipal utilities, and electric cooperatives.

Page 229REQUEST FOR INFORMATION RESPONSES

Page 23: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

VIRGINIA PUBLIC-PRIVATE PARTNERSHIPS REQUEST FOR INFORMATION - SOLAR ENERGY DEVELOPMENT PROJECT March 13, 2015

The contents of this document are non-binding. Page | 4

Project Date Installed

Size (MW)

Loca- tion Type Operational NextEra’s Role

Ancillae Assumption Academy 2012 0.1 PA Roof Yes Development and

Financing Bald Eagle Area Middle/High School 2012 0.5 PA Roof Yes Development and

Financing

Bellefonte High School 2012 0.5 PA Roof Yes Development and Financing

Bevans Point 2014 2.6 OR Ground Yes Development and Financing

Big Y (Multiple Stores) 2011- 2012 3.1 MA Ground/Roof Yes Development and

Financing

BMW USA 2014 1.2 NJ Roof Yes Development , Financing Long term owner and operator

Calverton 2015 4 NY Ground No Acquisition

Campbell Soup 2012 2.2 CA Ground Yes Development and Financing

Central Regional School District 2011 1.5 NJ Ground Yes Development and

Financing

City of Yuma 2014 1.2 AZ Ground/ Carport Yes Development and

Financing

Crane School District 2012-2013 2.5 AZ Ground/ Carport Yes Development and

Financing

DEEM 2014 0.6 IN Roof No Development and Financing

Delaware Valley Friends School 2012 0.1 PA Roof Yes Development and

Financing

Eastman Companies 2012 500 NJ Roof Yes Development and Financing

Gettysburg College 2012 0.4 PA Roof Yes Development and Financing

Grinnell Enterprises 2012 0.8 NJ Ground Yes Development and Financing

Grocer’s Supply 2014 1.0 IN Roof No Development and Financing

Heywood Hospital 2015 1.0 MA Carport No Development , Financing Long term owner and operator

Houghton College 2014 2.6 NY Ground Yes Development and Financing

Livingstone Associates 2013 0.5 NJ Roof and Ground Yes Development and

Financing Marion Walker Elementary School 2012 0.1 PA Roof Yes Development and

Financing Middle Township School District (Mult. Sites) 2012 1.5 NJ Roof Yes Development and

Financing Monmouth County (Mult. Sites) 2012 1.6 NJ Ground/

Carport Yes Development and Financing

Moravian Academy 2012 1.3 PA Ground Yes Development and Financing

Oneida County 2015 5.2 NY Ground No Development, Financing, Long-

Page 230REQUEST FOR INFORMATION RESPONSES

Page 24: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

VIRGINIA PUBLIC-PRIVATE PARTNERSHIPS REQUEST FOR INFORMATION - SOLAR ENERGY DEVELOPMENT PROJECT March 13, 2015

The contents of this document are non-binding. Page | 5

Project Date Installed

Size (MW)

Loca- tion Type Operational NextEra’s Role

Term owner and operator

Outback Solar 2012 5.7 OR Ground Yes Development and Financing

Pleasant Gap Elementary School 2012 0.05 PA Roof Yes Development and

Financing Sacramento Municipal Utility District – Boessow

2011 3.7 CA Ground Yes Financing

Sacramento Municipal Utility District – Bruceville

2011 21.9 CA Ground Yes Financing

Sacramento Municipal Utility District – Kost 2011 3.7 CA Ground Yes Financing

Sacramento Municipal Utility District - Point Pleasant

2011 1.2 CA Ground Yes Financing

Springside Academy 2012 0.1 PA Roof Yes Development and Financing

Stockton Unified School District 2014 6.6 CA Carport Yes Development and

Financing The School at Church Farm 2012 1.0 PA Ground Yes Development and

Financing

Tompkins Cortland Community College 2015 2.6 NY Ground No

Development , Financing, Long term owner and operator

Town of Prescott Valley (Multiple Sites) 2013 1.5 AZ Ground Yes Development and

Financing Union Beach Memorial Elementary School 2012 0.5 NJ Parking/Roof Yes Development and

Financing

U. of Maryland Medical 2013 3.8 MD Ground Yes Development and Financing

Wingate Elementary School 2012 0.3 PA Roof Yes Development and

Financing

2. What specific experience does the respondent have in third-party financing of solar energy projects completed or underway on publicly-owned property, especially ROW property? Please provide contact information for the public agencies for which these projects were developed.

We have constructed many ground and carport structures on public, government-owned property and, in some cases, school district property that is publicly owned. Some examples are below:

Monmouth County, NJ – Human Services Project Size: Type: Contact Information:

500 kW Carport 300 Kozloski Rd. Freehold, NJ

Page 231REQUEST FOR INFORMATION RESPONSES

Page 25: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

VIRGINIA PUBLIC-PRIVATE PARTNERSHIPS REQUEST FOR INFORMATION - SOLAR ENERGY DEVELOPMENT PROJECT March 13, 2015

The contents of this document are non-binding. Page | 6

Monmouth County, NJ – Agricultural Services Project Size: Type: Contact Information:

1.1 MW Carport 4000 Kozloski Rd. Freehold, NJ

Monmouth County, NJ – County Courthouse Project Size: Type: Contact Information:

175 kW Carport 71 Monument Rd. Freehold, NJ

Central Regional School District, NJ – Middle School Project Size: Type: Contact Information:

500 kW Ground mount 509 Forest Hills Parkway, Bayville NJ Kevin O’Shea 732.269.1100 ext. 207 [email protected]

Central Regional School District, NJ – High School Project Size: Type: Contact Information:

1 MW Ground mount 509 Forest Hills Parkway, Bayville NJ Kevin O’Shea 732.269.1100 ext. 207 [email protected]

Union Beach, NJ – Memorial Elementary School Project Size: Type: Contact Information:

500 kW Carport 221 Morningside Ave., Union Beach, NJ

Town of Prescott Valley – Sewage Treatment Facilities Project Size: Type: Contact Information of Reference:

1.5 MW Ground-mount Kimberly Moon Town of Prescott Valley (928) 759-3100 [email protected]

City of Yuma Project Size: Type: Contact Information of Reference:

1.2 MW Ground-mount Brian Webb City of Yuma, Sustainability Coordinator (585) 567-9315

Page 232REQUEST FOR INFORMATION RESPONSES

Page 26: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

VIRGINIA PUBLIC-PRIVATE PARTNERSHIPS REQUEST FOR INFORMATION - SOLAR ENERGY DEVELOPMENT PROJECT March 13, 2015

The contents of this document are non-binding. Page | 7

3. Are there any particular concerns with any of the information that has been provided in this RFI? Please explain those concerns and provide proposed solutions or mitigations to address those concerns.

The idea of installing a lot of distributed solar on park and rides, small government buildings and alongside a freeway may be a cost issue. Nextera Energy has significant experience installing rooftop, ground mounts and carport structures around the country. It has been our experience that it is difficult to install the smaller systems cost effectively, and therefore the PPA rates would be higher than the existing costs of power. One way to mitigate that risk is to develop bigger projects or include additional incentives via legislation in VA to allow for these smaller projects to be included in the development efforts. Another way to mitigate the risk is to consolidate many smaller projects in a given geographical area into a single large portfolio. In this way they can be treated as one project with many locations.

4. Do you foresee state or federal legislative issues that would hinder the feasibility of the Project? If so, then what are they and how could they be resolved?

Solar energy projects that achieve commercial operation by Dec. 31, 2016 will receive the 30% Investment Tax Credit (ITC) on eligible installed cost and this value is passed through to the customer in our pricing. NextEra’s current view is that the ITC will be reduced from 30% to 10% after 2016 when the current law expires. We believe future equipment prices will continue to trend downward but will not make up for this 20% difference in installed cost in the near future. This creates a window of opportunity to take advantage of the higher ITC and capture the long-term, fixed price, peak coincident, hedge value of solar against power and fuel price volatility.

Project Structure and Development

Delivery Method

5. What delivery methods are available for this Project? What are the advantages of each delivery method? What are the disadvantages of each delivery method? Which delivery method does the respondent prefer and why?

Nextera Energy has more than 44,000 MW of electrical generating facilities around the US. Many of these systems are tied directly to the utility grid and others are connected behind the meter, reducing the load of an existing facility. The advantages and disadvantages of each of these methods vary depending on a given State’s interconnection and net-metering rules.

As a general rule of thumb, the most cost -effective delivery method is to interconnect behind the meter and offset an existing load, as there typically is not going to be an interconnection cost from the utility. Behind-the-meter projects are often smaller in size than remote projects; therefore installation costs are typically higher, which ultimately increases the solar power rate. Often, we recommend looking for a piece of land upon which to install a ground-mounted solar array in close proximity to a current load that we can offset with a behind-the-meter interconnection.

Page 233REQUEST FOR INFORMATION RESPONSES

Page 27: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

VIRGINIA PUBLIC-PRIVATE PARTNERSHIPS REQUEST FOR INFORMATION - SOLAR ENERGY DEVELOPMENT PROJECT March 13, 2015

The contents of this document are non-binding. Page | 8

The next consideration is offsetting of the power rates. With the existing net-metering rules, most sites will be able to offset the entire kwh rate structure if interconnected behind the meter. This would include the delivery, supply and applicable taxes and surcharges, since the site would be supplying the power themselves on site, rather than taking it from the utility. Offsetting the on-site power can make a deal more affordable than if it were off-site. In some situations, off-site power would be at a lower rate but would only offset the supply portion of the utility bill.

There is a delicate balance when it comes to installing solar power and offsetting the current cost of electricity. NextEra Energy is very well positioned to assist customers with the evaluation of these various options. NextEra Energy also is one of the few solar companies that can provide wholesale power and retail power sales.

6. What are the key success factors facilitating and barriers impeding success that would make delivering a solar energy project more or less likely in Virginia?

As we mentioned in question 5 above, there are several success factors and barriers when it comes to installing a solar facility. As one of the largest providers of renewable energy in the U.S.; we are familiar with these factors and have implemented the necessary strategies for success. Please review a summary of the success factors and barriers below:

Success factors:

Ease of Site Control - land vs. rooftops

In general, site control is imperative, and having limited costs for a land or roof lease will make the economics of the transaction work and the power costs more beneficial to the power purchaser.

If we are using land for a ground-mount system, we would like to understand who owns the land, what easements and site leases are required, costs of the site, property tax requirements, and term of the use permit and site lease.

If we are using rooftops, we would need to know the age of the roof, type of structural support below the surface of the roof, size of the roof, usable space and electrical service in the building.

Interconnection Capabilities & Cost - A low cost of interconnection or no interconnection cost would help the economics of the transaction.

Cost of current power - The higher cost of power can be offset to increase savings.

Installation price vs buying wholesale/retail power - The cost of the installation may vary based on the type of installation. Roof, carport systems, or ground mounts will have different economics based on the technology selected and the installation methodology.

Barriers:

Page 234REQUEST FOR INFORMATION RESPONSES

Page 28: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

VIRGINIA PUBLIC-PRIVATE PARTNERSHIPS REQUEST FOR INFORMATION - SOLAR ENERGY DEVELOPMENT PROJECT March 13, 2015

The contents of this document are non-binding. Page | 9

Lack of state incentives – Some states will introduce local incentives in an effort to drive solar energy installations. However, a small number of states have done actually done this, and in many cases the cost to purchase utility power is lower than the cost of buying solar energy. A lack of incentives may limit the amount of installations that will be economical.

Site restraints - The sites need to be evaluated for feasibility and economics of a solar installation. Old rooftops, heavily wooded ground mounts, and certain carport systems may be difficult to install in a cost-effective manner.

7. What are the advantages and disadvantages of one large singular site versus multiple sites packaged together into one project?

In order to provide the most economical solution our typical structure applies to systems larger them 1MW. Based on current net metering laws, system sizes are limited to 500 kw. It would be most beneficial to aggregate several 500 kw systems to achieve the most cost-effective PPA rate.

Project Site

8. If multiple sites were packaged together, then what are the possible packaging options? What are the advantages and disadvantages of each option? Which option does your firm prefer? Some possible packaging options may include:

Total project capacity as single award - This option would be NextEra’s preference. However, it may be a disadvantage to some organizations to get one award depending on the services offered.

Bidding blocks (e.g., with each respondent proposing a minimum of 1MW) - This packaging option would work as well. If Nextera Energy was awarded only 1MW at a time, this may not be the most aggressive pricing offered to the power purchaser.

Allow bidders to “cherry pick” the list - This option would be fine if the goal is to find the lowest cost PPA. The IPP could eliminate the more expensive installations.

Quote each facility/site separately - Quoting each site separately would cost more than having a bundled cost. This is the most difficult and time consuming and would be our least preferred methodology.

Group into blocks by system types and sizes, by building types & sizes, by financing mechanism, by geography, etc. - This would be fine as well, assuming that the sizes were 1MW minimum system sizes.

Include a minimum system size (e.g., 100 kW or 250kW) - The minimum size for any one site should be 200kw and total aggregate of at least 1MW

9. Based upon the information provided in this RFI, what type of site defined by location, size and other relevant characteristics presents the best opportunity for placement of a solar energy project in Virginia and why?

Page 235REQUEST FOR INFORMATION RESPONSES

Page 29: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

VIRGINIA PUBLIC-PRIVATE PARTNERSHIPS REQUEST FOR INFORMATION - SOLAR ENERGY DEVELOPMENT PROJECT March 13, 2015

The contents of this document are non-binding. Page | 10

While sites would need to be reviewed, the most effective proposal would utilize two or more ground mounted solar arrays averaging 500 kw or greater in size.

10. What type of site offers the best opportunity for replication on other sites in Virginia? What are the advantages and disadvantages of this type of site?

In order to replicate the above mentioned system parameters, it would be beneficial to review 2-3 acre plots of flat cleared land. The benefits to a cleared and graded location can be seen through cost savings that would allow NextEra to offer the most cost-effective solution via a PPA.

11. How should sites be pre-qualified for bid without the time and expense of detailed engineering at each site? What site assessment tools or qualifiers should be utilized?

While engineering site screenings are necessary, NextEra utilizes several tools to pre-qualify locations based on a checklist of items. These tools include the employment of satellite imagery software, topographic charting software, and weather pattern mapping software. These items used in combination allow us to efficiently identify any red flags.

12. What information would a private developer require in order to facilitate project development?

In order move forward with the project, NextEra would conduct a Critical Issues Analysis (CIA) to identify the following:

Site location with respect to surrounding features Topographic information including slope of site Soils and geology Ecoregion and vegetative communities Special status plants and plant species of concern Special status wildlife and wildlife species of concern, including avian species

and bats Wetlands and other jurisdictional waters Floodplains Archaeological, cultural and historical resources Project constraints, including state land/parks, conservation easements,

wildlife management areas, critical habitat, airports, highways etc. Project land use and zoning Noise (state or local regulations) Visual (state or local regulations) Federal, state and/or local permits that will be required

Page 236REQUEST FOR INFORMATION RESPONSES

Page 30: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

VIRGINIA PUBLIC-PRIVATE PARTNERSHIPS REQUEST FOR INFORMATION - SOLAR ENERGY DEVELOPMENT PROJECT March 13, 2015

The contents of this document are non-binding. Page | 11

Commercial and Financial Structure

13. Based upon the delivery methods identified above, who would own the assets, equipment and capital plant in each delivery method? What are the essential terms of the contract for these delivery methods, including the optimal concession period?

NextEra will form a dedicated project LLC, which will become sole and exclusive owner of the Project assets. NextEra reserves the right to pursue tax, lending, and other financing strategies which may amend the ownership structure after commercial operation. It is NextEra’s goal to own these solar assets long term.

14. What financing structure is the most feasible and would provide the best value for Virginia?

There are multiple ways to finance solar systems. The three most typical financing solutions are:

i. Standard Power Purchase Agreement (PPA) - A third party operating companies owns and maintains the system and sells power to VA.

ii. Cash purchase where the system is owed by VA.

iii. Operating Lease- where the bank owns the system and leases the system back to VA.

The best option for VA is to use a PPA structure, since they are not able to take advantage of the ITC. We would recommend that VA also look at combining a solar PPA with either a wholesale power purchase agreement or retail power purchase agreement depending on the solar system parameters and the usage metrics provided.

15. Do you anticipate public or utility (other than adopted tariffs) funding or incentives being available for the Project? If so, then what would be the anticipated source of these funds or incentives and how do they add value to the Project?

In structuring a PPA, NextEra would be able to utilize the ITC, which would pass the savings on to VA. This would reduce the CAPEX by 30%, therefore delivery of power will be reduced. We are not aware of any local incentives that will be used for this project. If there is any local incentive that VA would provide, it would be valuable to outline these in the RPF so each of the respondents can prepare the PPA terms and be on a level playing field.

16. Is a solar energy project installation and operation possible without a public subsidy, and if not, what specific subsidies would be required, from whom and why?

In the case of large ground mounts, the ITC is the only required incentive to maintain the pricing structure offered in a PPA. In the case of smaller rooftop and carport systems, a local incentive may be required to drive the cost of the PPA down below existing tariffs in Virginia.

Page 237REQUEST FOR INFORMATION RESPONSES

Page 31: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

VIRGINIA PUBLIC-PRIVATE PARTNERSHIPS REQUEST FOR INFORMATION - SOLAR ENERGY DEVELOPMENT PROJECT March 13, 2015

The contents of this document are non-binding. Page | 12

17. What threshold financial arrangements would be necessary or other critical factors resolved to successfully complete the Project? Please outline in order of relative importance.

The power purchaser must: be willing to make a 15- to 25-year commitment to buy the solar energy; be willing to give the system owner site control for the duration of the PPA; agree to buy all the power produced by the solar system.

Project Schedule and Solicitation

Schedule

18. What major steps are needed from Notice of Award for the Project to full operation of the Project? What are the approximate elapsed times associated with these identified steps? What are the key decision points in the process (including go/no go decisions) and why?

Environmental Studies, Geotechnical Engineering, Surveys, Site Plan Preparation (3-5 weeks)

Land Use / Planning (2-16 weeks, depending on locations) Design Phase (Electrical, Structural, Civil, Racking (4 weeks) Permitting (4 weeks) Construction Start Procurement Milestones (modules, racking, inverters) Construction Phase (10-18 weeks, depending on system size and location) Interconnection Tie In / Mechanical Completion Start Up and Testing (2 weeks) COD (Provisional Acceptance) Final Acceptance

19. What are the critical path items for the procurement for this Project and why?

NextEra enjoys relationships with all of the top global suppliers and we are typically in a major procurement phase for one or more projects at any given time. Combined with NextEra’s balance sheet financing and performance leadership in the renewable energy space, NextEra is in position to design, procure and construct the project to the highest standards. Only nationally known and experienced companies are used in all of NextEra’s power plants.

With the continuing changes in module technology (efficiencies), racking, and inverter technologies, the timing of a selected supplier depends on when the power plant is to be constructed.

Modules With pricing for mono and poly crystalline 72 cell modules changing rapidly, the current selection may not be the best selection 6-9

Page 238REQUEST FOR INFORMATION RESPONSES

Page 32: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

VIRGINIA PUBLIC-PRIVATE PARTNERSHIPS REQUEST FOR INFORMATION - SOLAR ENERGY DEVELOPMENT PROJECT March 13, 2015

The contents of this document are non-binding. Page | 13

months from now. A full re-evaluation of suppliers will take place once firm construction dates are established. Efficiencies and cost are key considerations, but only nationally established suppliers will be considered.

Inverters Due to ongoing changes with string and micro inverter technologies, an evaluation of the current pricing and technology will take place once firm construction dates are established. An example of these changes is that one year ago central inverters were the only economically viable choice. With the development of the cost and efficiencies of string inventers, smaller ground-mount systems (under 1 MW) are now becoming economically viable.

Racking systems Currently, AET is the racking system of choice, but once a firm construction date is known, the system will be re-evaluated.

20. The currently available federal incentives require an expedited time frame due to expiration December 31, 2016. Does this constraint pose a threat to utilizing these incentives for the Project?

Yes, we would need to have a decision and complete NTP by the end of 2015 to hold the pricing offered.

Solicitation

21. Looking ahead, would the respondent be interested in submitting a committed proposal for the development of the Project? Are there any particular concerns that may prevent the respondent from engaging in the project development? How might those concerns be resolved?

NextEra Energy is considered a top developer in the industry and has invested millions of dollars in the pre-development efforts of multiple megawatts of solar projects throughout the country. We typically do not consider a need for a binding bid or bid bond to be included in an RFP response. We would however, be willing to provide a commitment to the development of the project, if we know the project economics are strong and mutual terms can be agreed upon.

22. What are the key elements of a RFQ for a solar energy project? Please provide references to other RFQs that have effectively elicited innovative proposals for solar energy projects on publicly-owned property and resulted in successfully completed projects.

The key elements of an RFQ are as follows:

An overview describing the highlights of the responses and summarizing how the responding firm will meet the goals of the Virginia Public-Private Partnerships.

Page 239REQUEST FOR INFORMATION RESPONSES

Page 33: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

VIRGINIA PUBLIC-PRIVATE PARTNERSHIPS REQUEST FOR INFORMATION - SOLAR ENERGY DEVELOPMENT PROJECT March 13, 2015

The contents of this document are non-binding. Page | 14

Project Development Experience, i.e., total number of megawatts of PV the firm has constructed and types of customers the firm has worked with in the past (for example, residential, commercial nonprofit, or government).

Project Financing Experience, creditworthiness, demonstration of capital available to fund the proposed project

Operations and Maintenance experience, including a description of monitoring systems

Experience taking advantage of rebates and incentives Experience of key personnel Evidence of insurance References and project examples

23. What is the minimum amount of time that your firm requires for developing and submitting a Statement of Qualifications (“SOQ”) for the Project after issuance of a potential RFQ?

NextEra Energy has a proposal writing team that can prepare and deliver an SOQ response in five business days.

24. What are the key elements of a RFP for a solar energy project? Please provide references to other RFPs that have effectively elicited innovative proposals for solar energy projects on publicly-owned property and resulted in successfully completed projects.

The key elements of an RFP are as follows:

Method to Accomplish Scope of Work -- an outline of both the technical and administrative approach to accomplishing the Scope of Work.

System Equipment -- detailed information on the system equipment to be used Basic System Design – including layouts depicting the solar installation at the

site(s) proposed for the project. Project Plans, Milestones, Schedule of Work and Completion Dates – provide

detailed project plans, listing major milestones and anticipated completion dates.

System Monitoring and Performance Plan -- include a detailed plan for ongoing monitoring of system performance.

Operations and Maintenance Plan -- provide a plan for ongoing operations and maintenance requirements, either directly or through contract with another party that will handle these responsibilities.

Financial Capability -- demonstrate capacity to cover design, engineering and installation costs, administrative or other costs associated with development, and any costs associated with recurring responsibilities, such as operations and maintenance.

Page 240REQUEST FOR INFORMATION RESPONSES

Page 34: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

VIRGINIA PUBLIC-PRIVATE PARTNERSHIPS REQUEST FOR INFORMATION - SOLAR ENERGY DEVELOPMENT PROJECT March 13, 2015

The contents of this document are non-binding. Page | 15

Pricing-- total “all-in” pricing for the proposed system and the power generated by the system.

Project Staffing, including biographies for primary staff to be assigned to the project. Include subcontractor staff if an EPC partner is used.

References -- at least three (3) references demonstrating past performance, including contact person, address, telephone, and subject of work performed.

Minimum Qualifications - demonstrate past experience in satisfactorily designing, constructing, owning, operating and maintaining PV solar system configurations similar in type and scale to the project described in the RFP.

25. What is the minimum amount of time required by the respondent for developing and submitting a committed detailed proposal for the Project after issuance of a potential RFP?

Four weeks is sufficient time for NextEra to prepare a thorough proposal involving up to 20 sites. We would need additional time to prepare engineering layouts and pricing for projects involving more than 20 sites.

Additional Considerations

26. Please provide any comments on other creative project scope ideas, procurement options, technical considerations, etc. that VAP3 should take into account.

NextEra is confident that it will exceed our customers’ expectations in delivering a renewable energy solution. We are one of the only organizations in this space that has the unique ability to provide more than a solar solution. Through our individual business units we are prepared to meet your renewable goals whether through onsite/offsite solar, wind, ESCO services, and wholesale and retail power supply.

27. What are the top risks for successful delivery of this Project and why? What potential impact could the identified risks have? What potential mitigation strategies could be employed to decrease the identified risks?

Environmental – We engage the top environmental companies to evaluate the risks for the project.

Permitting – We have extensive experience researching and evaluating the permitting risks. In lieu of our own staff, we sometime hire local civil engineering firms to work with local and state officials since they have the professional relationships with many of the key personnel.

Engineering, Procurement, and Construction – In most cases we procure the major equipment directly because of our leverage with large-scale utility project procurement. Our extensive evaluation of our third-party EPCs’ credit worthiness, experience, years in business, etc., gives us confidence that the construction cycle will be managed to agreed-upon timelines.

Page 241REQUEST FOR INFORMATION RESPONSES

Page 35: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

VIRGINIA PUBLIC-PRIVATE PARTNERSHIPS REQUEST FOR INFORMATION - SOLAR ENERGY DEVELOPMENT PROJECT March 13, 2015

The contents of this document are non-binding. Page | 16

28. In the respondent’s experience, what type of public benefit and economic development could a large solar energy project (>100kW) foster in terms of new businesses and job creation?

We have seen some levels of economic development incentives to help generate funds to make projects more economically feasible. However, these usually take a long time to put in place and with the ITC pending expiration; we would not recommend this action. Governor McAuliffe recently endorsed legislation creating a 400MW solar goal for the state by 2020, and also in the works is passage of legislation to create a Virginia Solar Development Authority. While details of this legislation are still pending, they do have the potential to positively impact business and job creation in Virginia.

As an example, since breaking ground on a 500 MW NextEra project in Riverside County, California, the project employed an average of 440 construction workers who logged more than 3.6 million man-hours of work. In addition, more than 40 California businesses contributed to the project through services ranging from materials, equipment, utilities, labor, housing, and food and beverage.

29. What challenges related to communication with local officials, communities and business does the respondent foresee and what strategies are suggested to be employed to maintain open and transparent relationships?

We do not foresee much challenge for a project of this type as the current sentiment tends to be pro-solar. We find that most local officials, communities and businesses understand the economic and environmental benefits of such a project.

With that said, NextEra has extensive experience with public outreach and we pride ourselves on our ability to develop relationships in the communities in which we conduct business. In some cases, it has been important to build working relationships with legislative and regulatory bodies to ensure all questions and concerns were addressed in a prompt manner. We have held open houses and public meetings to provide residents and officials the opportunity to learn about a project, view the renderings and voice any concerns. When needed, ongoing public outreach can take the form of a newsletter to stakeholders, updating them on the status of project development.

30. Other than the answers already provided, what information would help the respondent make the business decision to engage in the development of the Project?

The following information would help in the decision to engage in development of the project: An understanding of the current load Current tariff and avoided costs Expected duration of PPA term Whether the Power Purchaser is a wholesale buyer of power or a retail buyer

of energy Whether there is an SREC or solar obligation

Page 242REQUEST FOR INFORMATION RESPONSES

Page 36: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

CONFIDENTIAL

Response to Request for Information Regarding

Solar Energy Development Projects

March 13, 2015

Submitted to

Virginia Office of Public-Private Partnerships Alexandra Lauzon [email protected] www.ProjectNavigator.com | www.PVNavigator.com | www.SafetyMoment.org

VIRGINIA PUBLIC-PRIVATE PARTNERSHIPS

Submitted by

Project Navigator, Ltd. 1 Pointe Drive, Suite 320 Brea, CA 92821 714.388.1800

Page 243REQUEST FOR INFORMATION RESPONSES

Page 37: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

March 13, 2015 Response to Request for Information Regarding Solar Energy Development Projects

PREFACE FIGURE A

Summary of Project Navigator, Ltd.’s Proposed Developments

Who

• A development team anchored by Project Navigator, Ltd. (PNL) as

the project integrator.

• PNL specializes in developing small scale distributed solar facilities

on landfill and brownfield sites.

• Permitting and environmental tasks to be performed by PNL.

What

• A PV solar development located on top of closed

landfill and brownfield sites

• Fixed-tilt, rack-mounted, self-ballasting.

• Occupies acres of otherwise unusable land.

• Racks are specifically designed for landfill/brownfield installations.

• No long-term cap damage.

When

• All permitting and design completed within 18 months after lease

agreement is signed.

How

• PNL to perform a feasibility study on the project at no cost to the

Landfill owner.

• If project is determined feasible, PVN and the landfill owner enter

into a Land Lease and/or Power Purchase Agreement which

includes ability to use the land for 20-25 years.

• Project will be financed via a combination of debt and equity.

• PNL has excellent fund raising track record with major East and

West Coast renewable energy funds.

• System economics will meet favorable IRR criterion.

Develop a 2 to 12 MW photovoltaic solar array from approximately 700 to 4,000 fixed tilt, rack mounted arrays.

Page 244REQUEST FOR INFORMATION RESPONSES

Page 38: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

Response to Request for Information

Regarding Solar Energy Development

Projects

March 13, 2015

Submitted to

Virginia Office of Public-Private Partnerships Alexandra Lauzon [email protected]

Submitted by

Project Navigator, Ltd.

1 Pointe Drive, Suite 320 Brea, CA 92821 T 714.388.1800 F 714.388.1839

www.PVNavigator.com

www.ProjectNavigator.com

www.SafetyMoment.org

Page 245REQUEST FOR INFORMATION RESPONSES

Page 39: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

Response to Request for Information Regarding Solar Energy Development Projects March 13, 2015

iii

Table of Contents

Company Information ............................................................................... 1

Experience ................................................................................................ 2

Qualifications ............................................................................................ 4

Project Approach ...................................................................................... 5

Schedule .................................................................................................... 7

References ................................................................................................ 7

Conclusions .............................................................................................. 7

List of Figures

PREFACE FIGURE A

Summary of Project Navigator, Ltd.’s Proposed Developments

FIGURE 1 Project Navigator, Ltd.’s Landfill and Superfund Experience: Major Projects FIGURE 2 Project Navigator, Ltd. is Expert in Implementing Resource Recovery Projects at Closed

Landfills FIGURE 3 Project Navigator, Ltd. Is Developing a Nationwide Portfolio of Solar PV on Landfills

Projects FIGURE 4 Possible Layout of PV Solar Units on a Landfill Site FIGURE 5 Landfill Based, Solar Power Systems Must be Designed and Operated to Not Interfere

with the Primary Functions of the Landfill FIGURE 6 Project Navigator, Ltd.'s Landfill Solar Systems are Compatible with the Design

Functionalities of the Landfill FIGURE 7 Project Navigator, Ltd.’s Use of the Rack Mounted, Self-Ballasting Arrays Will Simplify

and Speed Up Construction

FIGURE 8 Solar Array Specifically Designed for Use at Landfills and Brownfields

Page 246REQUEST FOR INFORMATION RESPONSES

Page 40: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

Response to Request for Information Regarding Solar Energy Development Projects March 13, 2015

iv

FIGURE 9 PVN Uses a Fixed-Tilt, Racked, Solar Array Specifically Designed for Use at Landfills

and Brownfields List of Tables

TABLE 1 PNL & PVN’s Solar on Landfill Experience: Project Details and Client References

TABLE 2 Sample Landfill Solar Project Schedule

List of Appendices

APPENDIX A Resumes

Page 247REQUEST FOR INFORMATION RESPONSES

Page 41: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

Response to Request for Information Regarding Solar Energy Development Projects March 13, 2015

1

Company Information

Project Navigator, Ltd., via our solar power development subsidiary PVNavigator, LLC, submits this response to the Virginia Office of Public-Private Partnerships (VAP3) request for information titled “Solar Energy Development Project”. Our project approach and niche area of development, in summary, can be found in Preface Figure A.

Project Navigator, Ltd. (PNL) (see: www.PVNavigator.com and www.ProjectNavigator.com) is a Brea, California-based, with offices located in Houston, TX and Ossining, NY, leading, privately held certified small business, with an annual average gross revenue over the past three years of $4MM, engineering firm that has specialty expertise in managing landfill closures, and then subsequently developing solar projects on the closed waste prisms. A map showing projects where PNL is currently working on Landfill and Superfund sites is shown in Figure 1. Since 1997, PNL has developed an extensive track record of designing and implementing innovative solutions for clients at complex landfill closures, nationwide. Currently, many of these projects now include the placement of PV solar racking systems on the landfills’ caps for power generation. PNL’s engineers and scientists formulate and implement green, sustainable site remediation and OM&M strategies on how to maximize the long-term value of landfills which are in their O&M phases. In the past, landfills were considered a local liability; however, with an attitude change in their long-term management, the perceived liability can be shifted to become an asset. Our most prominent application of landfill site reuse is in the solar power arena, where PNL’s wholly owned subsidiary, PVNavigator, LLC (PVN) develops MW-scale PV installations on closed landfill sites. This is PVN’s sole business focus, wherein the landfill skills of PNL and the solar power capabilities of PVN, are combined and leveraged.

Technically, our power and landfill geotechnical engineers have combined decades of experience in the design and permitting, specifically, of landfill-located PV installations. Our systems are all “above grade,” and are sized and engineered to not impact the required environmental performance of the landfill cap (viz; no cap penetration and storm water management equivalence.) We have day-to-day experience of managing all aspects of the offtaker utility feasibility and interconnect process.

Experience-wise our Team has been consulting and developing, landfill-cap-located, utility scale, PV installations for about 5 years. At present we have more than 30 MW of PV on landfill system capacity, at projects in California and New Jersey undergoing design and permitting. We provide solar consulting expertise to municipalities and major corporations such as Chevron, Coeur D’Alene Mines and Union Pacific Rail Road. We have completed working under a grant from the California Energy Commission to pilot a PV system on a landfill cap in Los Angeles, and developed design guidance.

Financial Capabilities are excellent. Our Team is backed by the financial resources of several private equity funds that specialize in the ownership of long term renewable energy assets such as solar facilities.

PNL’s and PVN’s combined skills in landfill solar power development and landfill sites closure and maintenance operations make our partnership unique in this business area. Our preferred locations for the development of solar facilities would be on top of closed capped landfill or brownfield sites. This is

Page 248REQUEST FOR INFORMATION RESPONSES

Page 42: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

Response to Request for Information Regarding Solar Energy Development Projects March 13, 2015

2

PVN’s specialty and niche area of the business space. By putting the solar facility on top of a closed capped landfill, turns a piece of otherwise unusable land into a productive use. An illustration of the landfill “uplift” service areas where PNL works is shown in Figure 2.

Experience

Project Navigator, Ltd. has extensive experience in all phases of landfill design and remediation, as well as 10’s of man-years of experience in the redevelopment of landfills as PV solar power installations. Some of PNL’s landfill projects, which include solar siting initiatives, are shown in Figure 3 and Table 1. PNL and PVN’s relevant solar development and landfill remediation projects, which integrate the placement of solar power on landfills or brownfield sites include:

Milliken Landfill, San Bernardino County, CA – PNL was selected in 2010 by the County of San Bernardino to Design, Finance, Construct, and Operate a 3MW solar facility located at the Milliken Sanitary Landfill in Ontario, CA. PVN has secured an interconnect agreement with the local utility and also secured a long term Power Purchase Agreement and is currently in the process of selecting an EPC contractor for the construction of the project. The project commercial online date is expected to be December 2015.

Owens Corning Landfill, Gloucester, New Jersey – PNL was selected by Gloucester Township to Design, Finance, Construct, and Operate a 3MW facility at the former Owens Corning Landfill. Approximately 25% of the power produced from the plant will be sold to a nearby Elementary school via a power purchase agreement. PVN has entered into an Option to Lease agreement with the Township, secured a favorable interconnect agreement with PSE&G, a wholesale market participation agreement with PJM, secured post closure approval by NJDEP and subsection (t) approval by NJBPU, and is currently negotiating a long term SREC contract with PSE&G. The project commercial online date is expected to also be December 2015.

Fort Irwin National Training Center, California – PVN has won a contract from the U.S. Army to assess the viability of using solar power to run remote electrical equipment at Fort Irwin, California. Fort Irwin is a major training area for the U.S. Military, and is located in the Mojave Desert in San Bernardino County. Facilities currently powered by generators, in training and containment areas, will be reviewed. The first phase of work includes the preparation of a work plan, site visits, modeling computations and recommendations.

California Energy Commission (CEC), Sacramento, CA – PNL was selected by the CEC to pilot a highly instrumented, rack mounted, PV installation, test system on a closed Los Angeles, former Superfund site, hazardous waste landfill. The work lasted for 18 months. The program’s objective was to ultimately understand any impacts a PV facility could have on a closed landfill’s cover system, and define design criteria. The work was consistent with California’s goal of promoting the development of distributed renewable power systems on otherwise unusable land, thereby preserving green-space. The final report can be found at the following link: http://www.pvnavigator.com/downloads/2014-03-11-PIER-CA-Landfill-Based-Solar-Projects-CEC-500-10-061-Final-Report.pdf

Page 249REQUEST FOR INFORMATION RESPONSES

Page 43: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

Response to Request for Information Regarding Solar Energy Development Projects March 13, 2015

3

Chevron Corporation, San Ramon, CA – PNL has performed a range of solar power development assignments for Chevron and its operating companies. Some include:

Prepared a design for a planned solar panel array at Chevron’s former chemical plant in Richmond, California. The facility is planned to generate about 8MW and cover approximately 70 acres.

Screened and ranked more than 500 US-located surplus Chevron properties for their ability to host solar power installations.

Developed PV system designs and offtake plans for PV installations at two overseas operating facilities.

Coeur D’Alene Mines, Rochester, NV – PNL is performing an engineering evaluation of the potential of covering the mines heap leach piles with a novel PV laminate cap which would eliminate infiltration (a BLM requirement) while simultaneously generating power for the mine’s operations.

Mojave Sun Power, LLC, Cambridge, MA – PNL performed numerous solar facilities siting analyses, subsequently delivering a 4,000 acre land parcel to the client to be used for the Hualapai Valley Solar plant in Mohave County, Arizona. Mojave Sun Power is a privately financed solar power developer. The proposed 340-megawatt solar plant would create 1,500 construction jobs and more than 100 permanent jobs. The project would bring in about $4 million in property taxes, $30 million in construction income and more than $5.5 million in personal income to the county. The plant could be in operation by late 2016 and last for about 30 years. PNL represented Mohave Sun Power in land purchase negotiations and due diligence with the seller. PNL assisted Mohave Sun Power in permitting meetings with local, state, and federal regulators.

Ascon Landfill Site (Huntington Beach, CA) – is a closed 38 acre former oil field waste landfill site. The site still requires final closure. PNL is working for the Responsible Parties and DTSC to design the final remedial solution and development configuration. One facet of both the interim and long-term solutions is the inclusion of a small 1 MW sized PV solar facility. PNL has performed a conceptual design and cash flow calculations. Project financing is being pursued.

BKK Class I Landfill (West Covina, CA) – PNL is currently managing the final closure project on the Class I landfill for the BKK Responsible Parties. The project is about to embark on an EE/CA remedy selection work phase.

A long-term “renewable alternative” which PNL has proposed to the City of West Covina is the development of a solar into the cap system to generate power to run onsite systems. The solar system could be optimized so that its power generation works in tandem with the existing landfill gas to power system. At time of writing, PNL has learned of the City’s general acceptance of PNL’s proposed plan to develop an 8 MW solar facility on the landfill’s 50-acre top deck.

Waste Disposal, Inc. (Santa Fe Springs, CA) – is a 40-acre landfill Superfund site contaminated with metals, PAHs and VOCs. PNL designed and managed the cap construction about 4 years ago and is presently responsible for managing the site’s operations, maintenance and monitoring including gas venting and groundwater extraction systems. PNL has recently designed a, 4MW, 25 acre solar array for placement on the cap. Negotiations are presently ongoing with the site

Page 250REQUEST FOR INFORMATION RESPONSES

Page 44: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

Response to Request for Information Regarding Solar Energy Development Projects March 13, 2015

4

landowners for a lease arrangement, and the City of Santa Fe Springs, U.S. EPA and the Responsible Parties regarding deal structure.

Operating Industries Inc. Landfill Site (Monterey Park, CA) – is a 190-acre landfill site generating 6 million cubic feet/ day of methane and 20,000 gal/day of leachate; from 1997 to 2007 PNL managed all aspects of the site closure for the Responsible Parties. The $120MM work effort included the construction of a cap and gas collection system. PNL is presently working on two separate solar initiatives at OII. In 2008 PNL developed and installed a solar-powered WiFi system used to monitor waste subsurface temperatures. The system also acts as a backbone for wireless cameras and other remote monitoring systems. (e.g. settlement). Today PNL is evaluating the feasibility of financing and placing a 20-acre PV solar system on the landfill’s top deck. The system would use SunPods arrays and generate up to 4MW, which makes the project economically viable over a 10 year timeframe when power sales to SCE and the onsite systems are combined. PNL and partners are in negotiations to secure project financing.

Landfills at other locations in the U.S. where PNL is presently working and investigating

the installation of solar power systems include:

Malone Superfund Site (Texas City, Texas) – 150 acre petroleum waste and chemical reclamation disposal facility; PNL conducted project management for remedial investigation and feasibility study. Site remedy is contemplated to include limited redevelopment as environmental reserve. PNL is assessing the placement of a 1MW solar facility which would deliver green power to adjacent refineries.

PAB Oil and Chemical Service, Inc – 9.4 acres of oil field waste disposal area; PNL responsible for operation and maintenance, groundwater sampling, capping and site perimeter maintenance. PNL is assessing the sites long-term use as a solar facility. The site’s land can be delivered into the project at zero cost which makes the economics favorable. Power would be sold to the adjacent oil fields for running the oil well pump motors.

Tex Tin Superfund Site, Texas City, Texas – 130 acre former smelter facility. From 2000 to present PNL managed the remediation of soils, slag, groundwater impacted with acid, metals and radioactive materials in 7 ponds using a variety of remedial measures such as soil stabilization, acid water treatment, pond closure, cap and cover of impacted soils and installation of evapo-transpiration systems. PNL in association with an equity partner acquired the site in 2005. Presently the partnership has prepared designs for a 40 acre PV solar facility. Power would be sold directly to the adjacent BP refinery.

Specific client references can be found in Table 1.

Qualifications

Specific project personnel include: Ian A. Webster, Sc.D. (PNL)

Ian Webster, Sc.D., is the President of Project Navigator, Ltd. Ian had a 15-year career in major projects development with Unocal Corporation before founding PNL in 1997. He will participate in overall project

Page 251REQUEST FOR INFORMATION RESPONSES

Page 45: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

Response to Request for Information Regarding Solar Energy Development Projects March 13, 2015

5

strategy development and in meetings with the VAP3 as requested. He will also assure that the appropriate PNL resources are dedicated to the project in a cost-effective manner, conduct technical reviews at key junctures, assist as needed in the coordination between PNL, and communicate with the VAP3 to assure that the VAP3’s expectations are being satisfied. Ian has 30 years of project development experience. Ian will also be key in devising a project financial structure which maximizes returns for all stakeholders.

Robert Potter, B.S. (PVN)

As the Project Manager (PM), Robert Potter, will be the primary point of contact with the VAP3 and will manage all aspects of the project work and coordinate between PNL, PVN, Utilities, and the VAP3. Robert has an extensive and unique background of Science, Politics, Mathematics and Real Estate. Robert is intimately involved in all PNL and PVN solar projects, and coordinates the company’s solar development initiatives. Robert was responsible for the siting, acquisition, permitting, and securing interconnect agreements and power purchase agreements for both the Milliken and Owens Corning Landfill Projects. Robert was also responsible for the siting, acquisition, and permitting of the 340-megawatt Hualapai Valley Solar Project for Mohave Sun Power. Robert is currently working with Brightfields Development in securing financing and a PPA for the development of a solar project on a Los Angeles brownfield site. His expertise in working with utilities and landowners for the development of solar projects will be a key asset to the success and implementation of the landfill solar project initiative.

Halil Kavak, Ph.D. (PNL)

Halil is PNL’s surveying and GIS Database manager. GIS capabilities will be used in the layout and design of the solar field footprint so as not to interfere with any existing roads or landfill closure components. Halil will also analyze (as required, once we have a better understanding of the closure engineering specifications and subsequent operating performance of the site’s closure) landfill settlement data. Halil will perform geotechnical calculations to advise on the best positioning for the solar system. Halil has over 20 years of experience.

Detailed resumes can be found in Appendix A.

Project Approach

The construction and operation of a photovoltaic generation system on a closed landfill presents certain unique challenges. However the integrated skills of our multi-talented solar/landfill team will cost-effectively deliver a proposed feasibility study and system design, which could then be translated into a working system within eighteen months. This is done at no cost to the landfill owner. PVN as the developer will bear all costs for the feasibility, permitting, design and construction of the solar facility and in turn pay the landfill owner a lease payment for the use of the landfill. A project schedule indicating major project milestones and durations can be found in Table 2. Technical issues such as landfill settlement, long-term waste prism geotechnical stability, and landfill cap load-bearing requirements will be taken into account during the feasibility, siting, sizing and design of the proposed PV systems. PVN's project integrator leadership role will include formulating and coordinating all aspects of the design and installation of the solar electric generation system. We will insure that the system does not interfere (or more importantly, compromise) with the overall environmental functions of the existing cover system

Page 252REQUEST FOR INFORMATION RESPONSES

Page 46: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

Response to Request for Information Regarding Solar Energy Development Projects March 13, 2015

6

(i.e. especially eliminating waste exposure, eliminating storm water infiltration and managing water runoff.) . During detailed design PNL will also use surveying, GIS and other programs to: 1) develop a solar panel installation footprint that maximizes and further optimizes the usable top deck space of the landfill and 2) prepare artists renderings and other compelling visuals that will assist all stakeholders (citizens, planners, regulators, agencies, public meetings, etc.) to conceptualize the proposed development. Figures 4 to 7 conceptually show aspects of a solar on landfill system, highlighting design issues which are specific to the development of a solar on landfill project. Figures 5 and 6 show how the design will address and manage any Department of Environmental Protection potential concerns regarding cap integrity and storm water flow. At this preliminary stage we are proposing to use a racking system (Figure 8). The PV units are self-ballasting (i.e. no tie downs.) The rack systems, on large, adjustable spread-footings, will be configured to impart a load of less than 300 pounds per square foot. The system will be designed to not penetrate

the cap. Our system will use polycrystalline solar modules, which are connected to SMA inverters. Another positive feature of the self-ballasted racking system from a landfill owner’s perspective is that the modules are assembled off the cap, and then simply driven and lowered into position. As shown in Figure

6, this has the advantages of not having large construction crews work on the cap, (which could result in cap damage), and drives a faster onsite installation schedule versus mounting on shallow piers. The end state vision of a 20-year lifespan, PV solar farm located on a landfill is depicted in Figure 4. We believe that our Team provides unique synergies and capabilities – financial, solar-developmental and landfill-environmental – that are crucial to the successful implementation of solar on landfill projects. Our capabilities would seem to be unmatched by any other single developer in the current PV development business-space. We are quite confident in our ability to deliver this vision to the VAP3. To maximize the educational benefits of any solar project, PVN installs a web based reporting system. A public website would give access to the system’s solar performance, display the landfill owner as being instrumental in driving the project’s vision, and demonstrate stewardship of the environment. System parameters that are remotely monitored around the clock on a 15-minute interval basis include:

Inverter kW output Inverter kWh output Inverter fault codes Global irradiation Direct Normal irradiation Wind Speed Wind direction PV reference cell temperature Ambient temperature Perimeter security violations

PVN will be the overall manager of the project (a.k.a. “project integrator,” using the terminology of the solar power delivery business) and will oversee all activities.

Page 253REQUEST FOR INFORMATION RESPONSES

Page 47: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

Response to Request for Information Regarding Solar Energy Development Projects March 13, 2015

7

Schedule A sample project schedule can be found on Table 2. Please note that once an option to lease or MOU is signed, a typical project can be up and running within 18 months.

References Detailed project description of three current projects and contact information of references can be found on Table 1.

Conclusions

1. A Project Navigator, Ltd. led and managed team has an interest to evaluate the feasibility, permit, finance, design/build, then own and operate solar PV facilities located on top of closed landfill or brownfield sites located throughout the state of Virginia with a lifespan of 20 to 25 years. (PNL’s solar experience is shown in Figure 3.)

2. At time of writing, our proposal is for the VAP3 or VDMME to allow PNL to conduct a feasibility study of landfill or brownfield sites (including mine tailings) at no cost and then if proven feasible, enter into a 20 year Power Purchase and/or lease agreement with an option to extend for five years and in return receive access and lease rights to the land, and for the Team to own the project. The Team is however flexible. If this response leads to a formal proposal and is

successful and leads to negotiations, we can also describe a sliding scale of business

arrangements where there can be low-medium-high ownership involvement.

3. PNL commonly works with local sub-contractor in order for municipalities and utility clients to help meet their M/WBE goals. PNL will use local M/WBE for permitting assistance, environmental document review, and construction as necessary.

4. General project schedule forecasting has been performed at this proposal stage. We believe the project could be permitted and operational (weather and policy permitting and in conformance with landfill construction season) within 18 months after a lease arrangement is signed.

Page 254REQUEST FOR INFORMATION RESPONSES

Page 48: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

FIGURES

Page 255REQUEST FOR INFORMATION RESPONSES

Page 49: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

March 13, 2015 Response to Request for Information Regarding Solar Energy Development Projects

FIGURE 1

Project Navigator, Ltd.’s Landfill and Superfund Experience: Major Projects Patrick Bayou Superfund Site

Deer Park, TX • PNL is the project coordinator for a multi-

party PRP Group. • Initial efforts were to assist in AOC/SOW

negotiations for the RI/FS and in selecting the RI/FS contractor.

• PNL provides oversight of the RI/FS and various specialty sediment, hydrodynamic, and risk evaluation contractors for the project.

• PNL is the primary interface with EPA, TCEQ and other stakeholders.

• The project utilizes Adaptive Management Strategies to rapidly respond to new information on site conditions.

Ascon Landfill Site

Huntington Beach, CA • PNL serves as group project coordinator. • Complex remedy selection process with DTSC. • Perform group administration and technical

management services; responsible for all project submittals.

• Manage consulting resources and all field programs.

• Managed multi-million dollar Emergency Action. • Instituted a “safety-first working atmosphere”.

Malone Superfund Site

Texas City, TX • PNL is the project coordinator and is currently

managing all aspects of the RI/FS at this complex site.

• In particular we are overseeing the collection of appropriate data to perform a focused risk assessment. Our responsibilities also include the management of all associated workplans.

Cox Road Landfill Site Liberty County, TX • PNL is working to coordinate closure of the

site under the State Voluntary Cleanup Program (VCP) and move the project forward to closure.

• PNL plans and manages all site assessment work.

• The approach is to build consensus with the State and Responsible Parties for site closure using the risk-based Texas Risk Reduction Protocol.

Newark Bay Study Area

Newark, New Jersey PNA is the Group Coordinator for some major industrial parties.

• PNA is currently performing a data analysis and geospatial plotting of key COPCs to assess the nature and extent of contamination.

• Extensive GIS analysis. • We are also responsible for

budget control and Group fund management.

Confidential Site

Hawaii • PNL is working to create an

allocation methodology that fairly and accurately assigns environmental liability while maintaining a high level of legal defensibility.

• Initial efforts include data analysis, review of work products and project visualizations.

Purity Oil Sales

Fresno, CA • PNL acts as the project

coordinator and Engineer in Responsible Charge for both Operable Units, including the Remedial Action conducted from 2006 through 2008.

• Responsible for control of all site documents.

• PNL performs field oversight of the Remedial Action.

• Field oversight includes review of construction and quality control activities, and H&S for all site contractors.

Waste Disposal, Inc.

Santa Fe Springs, CA • PNL has been the project coordinator since 1997

through entire remedial closure process. • Turn-key PRP group coordination services. • PNL strategies avoided expensive excavation

remedies. • Excellent safety record.

Operating Industries, Inc.

Monterey Park, CA • PNL staffed lead site management

position from 1997 to 2000, and 2005 to 2006.

• Supervised all aspects of $100MM CD3 landfill closure work.

• Cap and gas collection system design and construction.

• Developed a landfill construction to O&M compliance strategy.

McColl Superfund Site

Fullerton, CA • Participate in complex EPA negotiations. • Managed complex cap and cut off wall closure. • PNL staff member helped manage design. • Community relations assistance. • Site now in reuse as part of golf course.

SEMOU

South El

Monte, CA • Assessed

remediation costs for PRP group.

Rialto Site

Rialto, CA • PNL was hired to provide expert advice to an

individual property owner on how to minimize liability.

BKK Landfill Site

West Covina, CA • PNL is working on all the sites technical

issues including landfill gas control, cap maintenance, compliance and

managing City relationships.

Cal Compact

Landfill Site

Carson, CA • Ian Webster was Bingham’s

landfill dynamics and degradation expert.

• Report capitalized on PNL’s expertise in landfill science, and remediation.

• Use of PNL graphical and visualization capabilities.

Cranbury Brickyard

New Jersey • PNA is retained by the

successor of the former owner of a facility that produced munitions for the United States during WWII and the Korean War.

• Our role is to monitor site activities to help ensure that clean up goals are achieved and that our client’s liability is ultimately eliminated.

MAR Services Oilfield Site

Cankton, LA • Devised a risk-based remedy for PRPs. • Worked diligently with DNR to limit

remediation to 3 feet depth for salts and most metals.

• $10MM+ in cost savings and reduced the project schedule by 24 months.

• Managed design and construction.

PAB Oil & Chemical

Abbeville, LA • PNL was the project coordinator at this former

CERCLA oilfield waste facility. • Successfully challenged EPA’s initial ROD remedy

resulting in an “ESD remedy change”. • Managed all design and construction activities.

Tex Tin Superfund Site

Texas City, TX • PNL is the project coordinator.

PNL developed a fast-track, streamlined Design/Build approach that saved $10MM and reduced the project schedule by 5 months.

• Worked to build excellent relationship with City and EPA.

• Tailored an area by area remedy, where solution matched long-term development goals.

Omega Superfund Site

Whittier, CA • PNL staff member was the project

coordinator for drum removal action. • Currently PNL is project coordinator for a

PRP group who has characterized the off site groundwater plume.

Confidential Site New Jersey • PNA is working on behalf of the former owner

of this CERCLA site to develop a credible and defensible allocation of remedial costs between our client and subsequent users of the site.

• Extensive fingerprinting analysis of NAPL impacts.

Chapin Road Landfill

Montebello, CA • Phase II Brownfields

Environmental Site Assessment and Analysis.

Hookston Station

Pleasant Hill, CA • PNL provides administrative

oversight on this water board-ordered remediation site.

• PNL manages the remediation bank account, reviews project invoices, coordinates group meetings, monitors for compliance with the Order, provides technical peer review, and distributes project funds.

Sherwin Williams

Facility

Emeryville, CA • Compliance reporting to

RWQCB, Oakland • PNL assessed paint

manufacturing facility compliance issues for Sherwin-Williams, and worked on cleanup plan formulation.

San Diego Sediment Site

San Diego, CA • PNL is providing web-based technical support

services for the PRP Group response to RWQCB Clean Up and Abatement Order.

• PNL has created a secure third-party website and searchable record index.

Page 256REQUEST FOR INFORMATION RESPONSES

Page 50: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

March 13, 2015 Response to Request for Information Regarding Solar Energy Development Projects

FIGURE 2

Project Navigator, Ltd. is Expert in Implementing Resource Recovery Projects

at Closed Landfills

Page 257REQUEST FOR INFORMATION RESPONSES

Page 51: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

March 13, 2015 Response to Request for Information Regarding Solar Energy Development Projects

FIGURE 3

Project Navigator, Ltd. Is Developing a Nationwide Portfolio of Solar PV on Landfills

Projects

11 10

10. Buena Vista Landfill: 1MW 11. Delaware City: 4MW 12. Ocean Township: 10MW 13. Owens Corning Landfill 3MW

East Coast

1

2

3 4 5 6 8

7

CA

NV

OR

AZ

ID 1. Avon Refinery: 10 MW 2. Purity Landfill: 1MW 3. OII Landfill: 4MW 4. BKK Landfill: 10MW 5. WDI Landfill: 4MW 6. Big Bear Landfill: 2MW 7. Gemcor Site (Chevron Landfill): 10MW 8. Milliken Landfill: 3MW 9. Barstow Landfill: 10MW

West Coast

MA

VT NH

NY

CT

RI

NJ

PA

DE MD

OII Landfill: 4MW

BKK Landfill: 10MW

Avon Refinery: 10MW

Buena Vista Landfill: 1MW

12 13

9

Page 258REQUEST FOR INFORMATION RESPONSES

Page 52: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

March 13, 2015 Response to Request for Information Regarding Solar Energy Development Projects

FIGURE 4

Possible Layout of PV Solar Units on a Landfill Site

Before

CONCEPTUAL PLAN

Installation of 700 to 4,000

solar units (each unit is 10’x20’)

Enough for a 2 to 12 MW

(AC) Facility (each unit can generate 3.0 kW)

Solar Power Plan

Page 259REQUEST FOR INFORMATION RESPONSES

Page 53: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

March 13, 2015 Response to Request for Information Regarding Solar Energy Development Projects

FIGURE 5

Landfill Based, Solar Power Systems Must be Designed and Operated to Not

Interfere with the Primary Functions of the Landfill

The solar facilities’ components are designed to be compatible and integrated with the landfill’s gas, leachate and stormwater management systems.

LEGEND 1. Security Systems 2. Supervision Systems 3. Solar Panels 4. DC Junction Boxes 5. LV DC Protection 6. DC/AC Inverter 7. LV AC Protection 8. Metering Systems 9. LV/MV Substation

Page 260REQUEST FOR INFORMATION RESPONSES

Page 54: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

March 13, 2015 Response to Request for Information Regarding Solar Energy Development Projects

PNL Team’s design considerations

include eliminating cap penetration,

continued functionality of the cap,

storm water management, wind

design and insuring protectiveness

during an earthquake event.

Design of PV Array will take into

consideration:

1. Settlement

• Total • Differential

2. Panel placement on cap

• Spread footings • Anchors

3. Continued performance of

vegetative cap

• Infiltration minimization • Vegetative growth

4. Stormwater management

• No standing water • Runoff management

5. Other

Settlement monument

Electrical lines in above-ground, lightweight, flexible steel conduit

2

1

3

4

Vegetative cover

Drainage swale

SunPods solar array with adjustable

footing

Pre-cast concrete footing SunPods adjustable footing Ballasted racking

Types of footings for rigid glass solar panels

Swale cross-section

design

Landfill ET cap designs

FIGURE 6

Project Navigator, Ltd.'s Landfill Solar Systems are Compatible

with the Design Functionalities of the Landfill

Page 261REQUEST FOR INFORMATION RESPONSES

Page 55: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

March 13, 2015 Response to Request for Information Regarding Solar Energy Development Projects

Conventional Ground-Mounted Installation

Self Ballasted Racking Installation

Time: 1 to 2 weeks

Time: 1 to 2 hours

Connect Deliver

Grade Dig Form Concrete Posts Barrier

Gravel Racking Modules Wiring Test Connect

FIGURE 7

Project Navigator, Ltd.’s Use of the Rack Mounted, Self Ballasting Arrays Will

Simplify and Speed Up Construction

Page 262REQUEST FOR INFORMATION RESPONSES

Page 56: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

March 13, 2015 Response to Request for Information Regarding Solar Energy Development Projects

FIGURE 8

Solar Array Specifically Designed for

Use at Landfills and Brownfields

Features of Landfill PV Solar

Unit

3.0 kW per array

(as shown) Arrives prefabricated

• Minimal onsite assembly 20 ft X 10 ft arrays

Weighs 3,100 lbs, supported on a

self leveling support system

• Eliminates landfill cap penetration

• Systems load on the landfill is less than 300 lbs./ft2

10 Gauge steel frame

Rated to 120+ mph wind speed

Ready to connect

Minimal maintenance

Page 263REQUEST FOR INFORMATION RESPONSES

Page 57: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

March 13, 2015 Response to Request for Information Regarding Solar Energy Development Projects

FIGURE 9

PVN Uses a Fixed-Tilt, Racked, Solar Array Specifically Designed for Use at

Landfills and Brownfields

Conceptual array on a closed landfill site.

Page 264REQUEST FOR INFORMATION RESPONSES

Page 58: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

TABLES

Page 265REQUEST FOR INFORMATION RESPONSES

Page 59: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

March 13, 2015 Response to Request for Information Regarding Solar Energy Development Projects

TABLE 1

PNL & PVN’s Solar on Landfill Experience:

Project Details and Client References

PNL’s Landfill Closure and O&M Experience Regarding the Future Siting of PV Solar on Landfills

Project

Ft. Irwin Nat’l Training Center

Ft. Irwin, CA

Milliken Landfill

Ontario, CA

79-acre landfill

Owens Corning Landfill

Gloucester, NJ

12-Acre Top Deck

California Energy Commission

Sacramento, CA

Solar on Landfill Research Grant

Description

In 2010 PNL won a contract from the

U.S. Army to assess the viability of

using solar power to run remote

electrical equipment at Fort Irwin,

California. Fort Irwin is a major training

area for the U.S. Military, and is located

in the Mojave Desert in San Bernardino

County. Facilities currently powered by

generators, in training and containment

areas, will be reviewed. The first phase

of work includes the preparation of a

work plan, site visits, modeling

computations and recommendations.

PNL was selected in 2010 by the County of San Bernardino to Design, Finance, Construct, and Operate a 3MW solar facility located at the Milliken Sanitary Landfill in Ontario, CA. PVN has secured an interconnect agreement with the local utility and also secured a long term Power Purchase Agreement and is currently in the process of selecting an EPC contractor for the construction of the project. The project commercial online date is expected to be December 2015.

PNL was selected by Gloucester Township to Design, Finance, Construct, and Operate a 3MW facility at the former Owens Corning Landfill. Approximately 25% of the power produced from the plant will be sold to a nearby Elementary school via a power purchase agreement. PVN has entered into an Option to Lease agreement with the Township, secured a favorable interconnect agreement with PSE&G, a wholesale market participation agreement with PJM, secured post closure approval by NJDEP and subsection (t) approval by NJBPU, and is currently negotiating a long term SREC contract with PSE&G. The project commercial online date is expected to also be December 2015.

PNL was selected by the CEC to pilot a highly instrumented, rack mounted, PV installation, test system on a closed Los Angeles, former Superfund site, hazardous waste landfill. The work lasted for 18 months. The program’s objective was to ultimately understand any impacts a PV facility could have on a closed landfill’s cover system, and define design criteria. The work was consistent with California’s goal of promoting the development of distributed renewable power systems on otherwise unusable land, thereby preserving green-space. The final report can be found at the following link: http://www.pvnavigator.com/downloads/2014-03-11-PIER-CA-Landfill-Based-Solar-Projects-CEC-500-10-061-Final-Report.pdf

Reference

Mark Burns

Directorate of Public Works

(760) 380-3737

Fred Cole

County of San Bernardino Solid Waste

Management

(909) 382-3239

Matthew Stanger

Blue Sky Power

(856) 479-9095

Marla Mueller

California Energy Commission

(916) 327-1716

Page 266REQUEST FOR INFORMATION RESPONSES

Page 60: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

March 13, 2015 Response to Request for Information Regarding Solar Energy Development Projects

TABLE 2

Sample Solar Project Schedule

Page 267REQUEST FOR INFORMATION RESPONSES

Page 61: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

APPENDIX A

RESUMES

Page 268REQUEST FOR INFORMATION RESPONSES

Page 62: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

Page 269REQUEST FOR INFORMATION RESPONSES

Page 63: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

Page 270REQUEST FOR INFORMATION RESPONSES

Page 64: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

Page 271REQUEST FOR INFORMATION RESPONSES

Page 65: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

 March 13, 2015  Virginia Office of Public‐Private Partnerships 600 E. Main Street, Suite 2120 Richmond, VA 23219  

Prospect Solar, LLC www.prospectsolar.com 

Nextility www.nextility.com 

Attn:  Alexandra Lauzon   Re:  Virginia Public‐Private Partnerships 

Request for Information – Solar Energy Development Project  Dear Ms. Lauzon:  Prospect Solar and Nextility would like to thank you for the opportunity to provide input toward the eventual success of this extremely important project toward the securement of Virginia’s energy future.  Prospect Solar is a solar EPC contractor operating in Northern Virginia and the District of Columbia and Nextility is a financing partner located in the District of Columbia.  Prospect Solar is also a sister company to Prospect Waterproofing, the DC metropolitan area’s premier commercial roofing contractor.  The following is our narrative answering the questions posed in the above referenced RFI.  If after your review you would like to speak with our team directly to discuss options that should be employed to give this project the best opportunity for success, please feel free to contact Jon Hillis with Prospect Solar or Mike Healy with Nextility.  1. What relevant qualifications and experience does the respondent have  in developing and delivering  large 

(>100kW) solar energy projects? While Prospect Solar has installed the largest commercial solar generation facilities in Loudoun (42 kW) and Fairfax Counties (56 kW) and we are also considered as one of the premier residential installers in Northern Virginia and the District of Columbia, to date we have not installed any projects over 100 kW.  It should be noted  that as of  the end of 2014  there were only seven net metered projects  located  in Virginia that were over 100 kW and four of these were installed by contractors not located in or actively doing business in Virginia.  We do have a number of projects under contract that are over 100 kW but are not yet complete.   Nextility has over 5 years of experience  in small and medium sized commercial solar  including over 250 solar water heating systems and has deployed over $30 million on small and medium sized solar projects throughout the United States.  Nextility Solar PV projects range from 17kW ‐ 250kW in nameplate size.  Nextility employs over 40 people in the District of Columbia and has offices in California and San Juan Puerto Rico.   Nextility has worked with several major universities  including American University,  and George Washington University  along with  Affordable  Housing  Authorities, Non‐Profits.    Currently  Nextility  has  solar  systems  operating  in  Hawaii,  California,  Maryland, Washington ‐ DC, Pennsylvania, and Delaware.  

2. What  specific  experience  does  the  respondent  have  in  third‐party  financing  of  solar  energy  projects completed  or  underway  on  publicly‐owned  property,  especially  ROW  property?  Please  provide  contact information for the public agencies for which these projects were developed. In partnership with Nextility  Inc., Prospect Solar would work exclusively with Nextility  Inc. as a  third‐party financier.   Nextility’s first institutional investor was Washington Gas (now known as WGL) which gave it an initial commitment of $30 million for solar project financing.  Projects are under construction 

Page 272REQUEST FOR INFORMATION RESPONSES

Page 66: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

March 13, 2015 Virginia Office of Public‐Private Partnerships Request for Information – Solar Energy Development Project Page 2 of 8  

Prospect Solar, LLC www.prospectsolar.com 

Nextility www.nextility.com 

in Massachusetts, New York, and Puerto Rico.   Nextility has experience working with over 50 different installation companies and in 25 different jurisdictions.      

3. Are there any particular concerns with any of the  information that has been provided  in this RFI? Please explain those concerns and provide proposed solutions or mitigations to address those concerns. Please see Attachment A – Comments to the High Level Screening Recommendation for the Solar Energy Development Project.  

4. Do you foresee state or federal legislative issues that would hinder the feasibility of the Project? If so, then what are they and how could they be resolved? As  a  Power  Purchased  Agreement  financial model  would most  likely  be  required  to monetize  the available federal tax incentives, an expansion of the existing PPA pilot program, or a codification of the Act that created the pilot with an  increase of the 50 MW cap, may be required to achieve the energy production  stated  in  Figure  7  of  the  High  Level  Screening  Recommendation  for  the  Solar  Energy Development Project.  

5. What delivery methods are available for this Project? What are the advantages of each delivery method? What are the disadvantages of each delivery method? Which delivery method does the respondent prefer and why? Nextility  can offer  two  types of  financing methods.   Nextility offers  a proprietary Price‐Index‐Energy (PIE) offering and can also offer a long term power purchase agreement.  Both options would be owned, managed,  maintained,  insured,  monitored,  and  financed  by  Nextility.    PIE  offers  a  unique  PPA agreement  that guarantees a  fixed % discount  to  the end users  rate  for  the  term of  the contract.    It allows  the energy users  solar  rate  to  fluctuate with  their current energy  rates.    If electricity  rates go down,  the consumer  is not stuck with a solar  rate  that  is higher  than market energy  rates.   They are always guaranteed to save money.  A standard Power Purchase agreement can lock in rates for the long term and hedge against energy  inflation  in a more predictable manner to the user.   At the end of the contract, the end user can opt to buy the system from Nextility or extend the contract length.  Nextility does  have  the  flexibility  to  enter  into  a  lease  agreement,  but  the  former  options  are much more standard in the marketplace.  

6. What are the key success factors facilitating and barriers  impeding success that would make delivering a solar energy project more or less likely in Virginia? The  legality of PPAs would need  to be expanded  to all utility service  territories and  the program cap would need to be substantially increased.  A viable and predictable SREC market would be required to attract tax equity investors if it is anticipated that SREC sales will be used to finance the installation of projects.   Other  options would  be  utility  sponsored  feed  in  tariffs  or  performance  based  incentives.  Since it is likely that we will also want to take advantage of net energy metering, systems sizes would be limited  to  500  kW  (or  1 MW  assuming  recent  legislation  is  signed  into  law)  and  other  restrictions associated with the net energy metering code and associated rules and regulations established by the State  Corporation  Commission.   Municipal  aggregate  net metering  would  also  allow  the  state  and municipalities to aggregate meters and  install  larger systems and offset  loads from several meters but such legislation has not been successful in the General Assembly. 

Page 273REQUEST FOR INFORMATION RESPONSES

Page 67: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

March 13, 2015 Virginia Office of Public‐Private Partnerships Request for Information – Solar Energy Development Project Page 3 of 8  

Prospect Solar, LLC www.prospectsolar.com 

Nextility www.nextility.com 

 7. What  are  the  advantages  and  disadvantages  of  one  large  singular  site  versus multiple  sites  packaged 

together into one project? Economies of scale will always reduce costs  for a  larger project compared to multiple projects.   O&M costs will  also be  substantially  reduced.    Smaller  sites  and  rooftop  arrays may be more desirable  in suburban or urban locations where real estate is a premium and rooftop space is limited.   

8. If multiple  sites were packaged  together,  then what are  the possible packaging options? What are  the advantages  and  disadvantages  of  each  option?  Which  option  does  your  firm  prefer?  Some  possible packaging options may include:  ● Total project capacity as single award  ● Bidding blocks (e.g., with each respondent proposing a minimum of 1MW)  ● Allow bidders to “cherry pick” the list  ● Quote each facility/site separately  ● Group  into blocks by  system  types and  sizes, by building  types &  sizes, by  financing mechanism, by 

geography, etc.  ● Include a minimum system size (e.g., 100 kW or 250kW)  We  would  recommend  packaging  options  that  group  projects  or  blocks  according  to  geographic location, size, and type of installation.  This will cater directly to the solar EPC firms performing the work as opposed  to  the  financing companies.   We would not suggest award  the entire package as a single award,  individual projects, or packaging options grouped by  financing mechanism as each respondent will likely be able to provide pricing for a variety of mechanisms through their financing partners.  Here is a suggested grouping which does not take into account geographic location:  • Ground mount arrays < 250 kW • Ground mount arrays between 250 kW and 1 MW • Ground mount arrays over 1 MW • Parking canopy arrays < 250 kW • Parking canopy arrays between 250 kW and 1 MW • Parking canopy arrays over 1 MW • Rooftop arrays < 250 kW • Rooftop arrays between 250 kW and 1 MW • Rooftop arrays over 1 MW  

9. Based  upon  the  information  provided  in  this  RFI, what  type  of  site  defined  by  location,  size  and  other relevant characteristics presents  the best opportunity  for placement of a solar energy project  in Virginia and why? Without performing a thorough review of the almost 1,400 sites provided in the RFI we would provide a general statement that smaller systems could be  installed on rooftops to create proximity to  load and larger ground mounted systems could be installed on acreage that is not likely to be developed on for 30 years.  While parking canopies do provide other benefits these systems typically come at a premium installation price and should not be seen as the  immediate opportunity.   Open, unshaded, nearly new roofs are the ideal candidates that serve as low hanging fruit and best value. 

Page 274REQUEST FOR INFORMATION RESPONSES

Page 68: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

March 13, 2015 Virginia Office of Public‐Private Partnerships Request for Information – Solar Energy Development Project Page 4 of 8  

Prospect Solar, LLC www.prospectsolar.com 

Nextility www.nextility.com 

 • Location –  Ideally  large scale solar generation  facilities would be  located near existing natural gas 

generation  facilities  or  near  a  load  with  a  profile  similar  in  size  and  peak  time  to  that  of  the generation facility. 

• Size – To capitalize on economies of scale we would recommend system sizes of at least 100 kW and up to 5 MW. 

• Type of  Installation – Ground mounted  installations are  typically  the most cost effective methods for  systems  greater  than  250  kW  in  size  provided  the  cost  of  the  real  estate  is  not  prohibitive.  Systems  less  than  250  kW  in  size  should  be  roof mounted,  either with  penetrating  or  ballasted racking systems, depending on roof considerations. 

 10. What  type  of  site  offers  the  best  opportunity  for  replication  on  other  sites  in  Virginia? What  are  the 

advantages and disadvantages of this type of site? There are many variables to consider when determining an optimum scenario for a site for solar arrays.  A  1 MW  ground mounted  array with  proximity  to  a  similar  load may  be  optimal  in  a  rural  setting whereas  a  250  kW  rooftop  installation may  be more  appropriate  for  a  suburban  or  urban  location.  Larger  ground mounted  arrays  require more  real  estate  and  conditions  of  existing  roof  need  to  be considered for rooftop installation.  

11. How  should  sites be pre‐qualified  for bid without  the  time and expense of detailed engineering at each site? What site assessment tools or qualifiers should be utilized? Given the volume and complexity of possible sites we would recommend that these be assessed by an authority with expertise in solar development to qualify each site for location, installation method and size.  An experienced NABCEP certified technical sales engineer could be contracted for much less than an  engineer.    The  NABCEP  certified  TSE  could  be  consulted  to  determine  the  likelihood  of  specific buildings being suitable.  Typically, available satellite data can provide the level of information needed for this analysis.  To supplement this for specific sites we would recommend Pictometry which provides various types and increased levels of imagery for assessing sites.  

12. What information would a private developer require in order to facilitate project development?  A private developer would require project  location, project size or  load to be offset, financing method preferred  (PPA  assumed),  ownership  of  SRECs  and/or  proposed  purchase  agreement  for  SRECs,  and revenue to be paid through Land Lease Agreement (if any). 

 13. Based upon the delivery methods identified above, who would own the assets, equipment and capital plant 

in  each  delivery  method?  What  are  the  essential  terms  of  the  contract  for  these  delivery  methods, including the optimal concession period? See response to question 5 above.  

14. What financing structure is the most feasible and would provide the best value for Virginia? We would recommend the Price‐Index‐Energy (PIE) offering described in response to question 5 above.  

Page 275REQUEST FOR INFORMATION RESPONSES

Page 69: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

March 13, 2015 Virginia Office of Public‐Private Partnerships Request for Information – Solar Energy Development Project Page 5 of 8  

Prospect Solar, LLC www.prospectsolar.com 

Nextility www.nextility.com 

15. Do you anticipate public or utility (other than adopted tariffs) funding or incentives being available for the Project? If so, then what would be the anticipated source of these funds or incentives and how do they add value to the Project? We would suggest some sort of requirement to comply with newly stated public interests that creates an SREC market in Virginia.  See response to question 16 below.  

16. Is  a  solar  energy  project  installation  and  operation  possible without  a  public  subsidy,  and  if  not, what specific subsidies would be required, from whom and why? If the state  is to own the  facility and all the energy and non‐energy attributes produced  (SRECs) then installation and operation would not require any other public subsidy as the state would purchase, own, and maintain the asset.  If the project is to be developed, owned, and operated by a third party in order to monetize all possible  federal  tax  incentives  then  the state would  likely need  to purchase  the non‐energy  attributes  (SRECs)  in  addition  to  the  energy  produced  in  order  to  secure  project  financing.   However, we would not consider this a public subsidy since there  is a value associated with SRECs as this mechanism provides  compliance with a  stated public  interest and  there  is  inherent value  in  the non‐energy attributes of solar.   Other methods as mentioned above could be utility sponsored feed  in tariffs or performance based incentives to comply with newly stated public interests.  

17. What  threshold  financial  arrangements  would  be  necessary  or  other  critical  factors  resolved  to successfully complete the Project? Please outline in order of relative importance. ● Allowance  of  power  purchased  agreements  with  a  program  cap  of  250 MW  within  all  service 

territories.  Project could commence with current limitation to Dominion service territory with a cap of  50 MW  but  this  would  need  to  be  addressed.    This  is  required  to monetize  all  federal  tax incentives. 

● Requirement for state agency to purchase SRECs or utility to provide feed  in tariff or performance based incentive program.  This will bring tax equity investment to Virginia to develop projects. 

 18. What major steps are needed from Notice of Award for the Project to full operation of the Project? What 

are the approximate elapsed times associated with these identified steps? What are the key decision points in the process (including go/no go decisions) and why? Since there are no specific parameters provided for the project size other than the proposed 193 million kWh per year capacity  installed at the Park and Ride sites we will assume multiple  large scale ground mounted arrays (1 MW to 5 MW) will be incorporated into the project.  Since these sized arrays involve the most  planning,  design,  permitting,  and  site work  requirements  we  will  evaluate  based  on  the timeline  for  such  a  project.    These  projects  can  take  2  years  from  initial  site  selection  process  to completion,  but  with  sites  identified,  expedited  procurement,  design,  and  permitting  it  could  be possible  to have a number of  these projects  completed by  the end of 2016.   Rooftop arrays are  less involved  and  can be operational  in  four  to  six months  from NOA.    The below  timeline  assumes  the following  steps  have  been  completed:  Site  identification,  lease  negotiation,  preliminary  engineering, feasibility  study  submitted  to  PJM,  impact  study  submitted  to  PJM,  and  issuance  of  a  certificate  of public convenience and necessity (CPCN) if required.  This is very simplified and is a listing of the critical path  activities  only  and  does  not  include  activities  falling  under  categories  such  as  preconstruction activities, general conditions, and logistics since these run concurrent with the activities listed below. 

Page 276REQUEST FOR INFORMATION RESPONSES

Page 70: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

March 13, 2015 Virginia Office of Public‐Private Partnerships Request for Information – Solar Energy Development Project Page 6 of 8  

Prospect Solar, LLC www.prospectsolar.com 

Nextility www.nextility.com 

 Major Schedule Components and Estimated Durations • Design/Permitting ‐ 150 days • Equipment Procurement ‐ 60 days • Site Work and Construction ‐ 60 days  

19. What are the critical path items for the procurement for this Project and why? Major critical path activities are 100% design completion, permitting, and equipment procurement.  

20. The currently available federal incentives require an expedited time frame due to expiration December 31, 2016. Does this constraint pose a threat to utilizing these incentives for the Project? With  an  assumed  project  size  to  meet  the  power  generation  as  per  Figure  7  this  will  require  an expedited procurement schedule  for  facilities  to be operational prior to  the December 31, 2016 date.  We would suggest that the Solar Energy Development Authority would be utilized for this purpose once this is established.  

21. Looking  ahead,  would  the  respondent  be  interested  in  submitting  a  committed  proposal  for  the development  of  the  Project?  Are  there  any  particular  concerns  that may  prevent  the  respondent  from engaging in the project development? How might those concerns be resolved? Yes,  we  intend  to  submit  a  proposal.    Our  concerns  and  proposed  resolutions  regarding  project financing  are  related  in  response  to  question  17.   Our  concerns  and  proposed  resolutions  regarding information provided  in an RFP are related  in responses to questions 9‐12, and 24.   Additionally, care should  be  taken  to  not  include  bidder  requirements  that  would  exclude  Virginia contractors/developers.  There should be a stated preference for Virginia firms to comply with recently passed legislation.  

22. What are the key elements of an RFQ for a solar energy project? Please provide references to other RFQs that have effectively elicited innovative proposals for solar energy projects on publicly‐owned property and resulted in successfully completed projects. RFQ is assumed to mean “Request for Qualifications”. • Mission Statement • Company Profile • Key Personnel and Resumes • Scope and Geography of Operations • Experience • Quality Control and Safety Plan Specifics • Business Partners • References  

23. What is the minimum amount of time that your firm requires for developing and submitting a Statement of Qualifications (“SOQ”) for the Project after issuance of a potential RFQ? This could be provided in two weeks.  

Page 277REQUEST FOR INFORMATION RESPONSES

Page 71: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

March 13, 2015 Virginia Office of Public‐Private Partnerships Request for Information – Solar Energy Development Project Page 7 of 8  

Prospect Solar, LLC www.prospectsolar.com 

Nextility www.nextility.com 

 24. What are  the key elements of a RFP  for a solar energy project? Please provide  references  to other RFPs 

that have effectively elicited innovative proposals for solar energy projects on publicly‐owned property and resulted in successfully completed projects. RFP should allow for creative financing mechanisms and development of specific sites to performance based criteria. • Executive Summary of RFP • Scope of Work to be Provided • Award Criteria • Required Organization of Response • Bidding Procedures • Attachments 

o Site Information o Pricing and Estimated Energy Production o Qualifications o Project Team o Disclosures o Exception and Qualifications 

References to other RFPs The District of Columbia Department of General Services DCAM‐14‐CS‐0123 Army Corps of Engineers Renewable Energy MATOC  

25. What  is  the  minimum  amount  of  time  required  by  the  respondent  for  developing  and  submitting  a committed detailed proposal for the Project after issuance of a potential RFP? This could be provided in six weeks.  

26. Please  provide  any  comments  on  other  creative  project  scope  ideas,  procurement  options,  technical considerations, etc. that VAP3 should take into account. ● Development of community solar projects through willing utilities. ● Inclusion of properties managed by other state agencies.  

27. What are  the  top  risks  for  successful delivery of  this Project and why? What potential  impact could  the identified  risks have? What potential mitigation strategies could be employed  to decrease  the  identified risks? Delivery  of  operational  facilities  after  December  31,  2016  would  increase  required  PPA  rate substantially with the current scheduled reduction of the federal ITC.  Expedited procurement schedule managed by the Solar Energy Development Authority is recommended.  

28. In the respondent’s experience, what type of public benefit and economic development could a large solar energy project (>100kW) foster in terms of new businesses and job creation? 1 MW of solar installed will employ the equivalent of approximately 15 workers for one year and create approximately $2.5 million  in business revenue.   We would estimate that this project,  if completed  in the scope required to meet the energy production goals  in Figure 7 by the end of 2016, would create 

Page 278REQUEST FOR INFORMATION RESPONSES

Page 72: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

March 13, 2015 Virginia Office of Public‐Private Partnerships Request for Information – Solar Energy Development Project Page 8 of 8  

Prospect Solar, LLC www.prospectsolar.com 

Nextility www.nextility.com 

1000 new jobs in the solar industry in Virginia and 30 to 50 new businesses, provided the procurement is managed  to  develop  businesses  located  in  Virginia.    Furthermore,  it  should  be  assumed  that  the energy savings captured by organizations powered by solar will lead to further job creation within their respective industries and workers in the solar field that are working locally will also spend money locally creating additional demand for goods and services.  Job creation should also lessen the burden on local government unemployment programs and subsidies.  

29. What  challenges  related  to  communication  with  local  officials,  communities  and  business  does  the respondent foresee and what strategies are suggested to be employed to maintain open and transparent relationships? It  is  likely  that  there  will  be  a  portion  of  the  public  that  will  protest  the  use  of  public  funds  for renewable energy generation.   It may be wise to anticipate this and quickly react with public  listening sessions to answer concerns.  

30. Other than the answers already provided, what information would help the respondent make the business decision to engage in the development of the Project? Together  with  Nextility,  we  believe  that  solar  is  not  only  a  way  to  engage  in  good  corporate environmental  stewardship,  but  it  is  a  path  towards  creating  jobs;  spurring  economic  development within  communities;  hedging  against  future  energy  increases;  educating  our  youth  about  energy independence; and creating value  for business and property owners.   The price of solar has dropped dramatically  in  the past  few years  to a point where we are seeing a bottom.   While other states and regions have helped drive down the costs with their own respective solar subsidies, Virginia sits on an opportunity to make a big impression while spending less money than other states and regions before it.   We would  also  encourage  that  respondents work with  qualified  solar  developers  and  installers versus adding  layers of General Contracting  firms  that add minimal value  in order  to maintain  lower pricing for the end users of the solar energy.   

 Sincerely,                Sincerely, Prospect Solar, LLC              Nextility 

            Mike Healy

Jon F. Hillis                Mike Healy Vice President                Market Development & Policy 

                

Page 279REQUEST FOR INFORMATION RESPONSES

Page 73: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

 

Prospect Solar, LLC www.prospectsolar.com 

Nextility www.nextility.com 

            

Attachment A Comments to the High Level Screening Recommendation for the 

Solar Energy Development Project 

Page 280REQUEST FOR INFORMATION RESPONSES

Page 74: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

Summary of Comments on Comments to High Level Project Screening.pdfThis page contains no comments

Page 281REQUEST FOR INFORMATION RESPONSES

Page 75: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

This page contains no comments

Page 282REQUEST FOR INFORMATION RESPONSES

Page 76: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

Page: 3Author: hillisj Subject: Sticky Note Date: 3/12/2015 2:23:22 PM These are not "models" but are specific financial arrangements that could individually be incorporated into different models. Author: hillisj Subject: Sticky Note Date: 3/12/2015 11:39:42 AM These states all have a mandatory RPS which creates a market and associated quantifiable value for the SREC revenue. Author: hillisj Subject: Sticky Note Date: 3/12/2015 11:40:29 AM A project of this small size would not realize cost savings through economies of scale. Author: hillisj Subject: Sticky Note Date: 3/12/2015 11:42:33 AM VDOT has no requirement to offset its carbon footprint so purchasing these RECs would be done voluntarily and would probably not be allowed unless there was a requirement created. Author: hillisj Subject: Sticky Note Date: 3/12/2015 11:45:40 AM It should be noted that parking canopy installations can add 25% to 40% to project costs compared to a standard ground mounted array, potentially offsetting much of the federal ITC and accelerated depreciation benefits.

Page 283REQUEST FOR INFORMATION RESPONSES

Page 77: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

Page: 4

Author: hillisj Subject: Sticky Note Date: 3/12/2015 11:54:05 AM A solar parking canopy installation is a not a requirement for the installation of charging stations. Author: hillisj Subject: Sticky Note Date: 3/12/2015 11:56:10 AM There is nor viable SREC market in Virginia that will create any substantial revenue from their sale.

Page 284REQUEST FOR INFORMATION RESPONSES

Page 78: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

Page: 5

Author: hillisj Subject: Sticky Note Date: 3/12/2015 11:57:28 AM This suggests developing these projects through the Solar Energy Development Authority. Author: hillisj Subject: Sticky Note Date: 3/12/2015 12:10:10 PM To generate the production at the Park and Ride sites as stated in Figure 7, a total of approximately 150 MW of solar generating capacity would need to be installed. If the installation of these facilities is completed prior to the end of 2016, given the current schedule reduction of the ITC from 30% to 10%, a saving of approximately $100 million could be achieved.

Page 285REQUEST FOR INFORMATION RESPONSES

Page 79: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

Page: 6

Author: hillisj Subject: Sticky Note Date: 3/12/2015 2:08:35 PM New legislation states that the construction or purchase by an investor owned incumbent utility of up to 500 MWs of solar is in the public interest. Also allowed are power purchased agreements between the utility and private investors prior to purchasing the generation facility. Additionally, the utility may propose a rate adjustment clause based on a market index in lieu of a cost of service model for such facility. Further, the Solar Development Authority (not yet signed into law by the Governor) shall assist investor-owned utilities in the planned deployment of at least 400 megawatts of solar energy projects in the Commonwealth by 2020.

Page 286REQUEST FOR INFORMATION RESPONSES

Page 80: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

Page: 7

Author: hillisj Subject: Sticky Note Date: 3/12/2015 2:14:48 PM While this may be the case this does not preclude Dominion, or any other investor owned utility, from allowing third party PPAs. Regardless, an expansion of the pilot, or a codification of the Act that created the pilot with an increase of the 50 MW cap, would be required to achieve the energy production stated in Figure 7.

Page 287REQUEST FOR INFORMATION RESPONSES

Page 81: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

Page: 8

Author: hillisj Subject: Sticky Note Date: 3/12/2015 3:11:09 PM In light of new legislation it is possible that funding could be provided through a utility performance based incentive program or feed in tariff. Also possible is an SREC market driven by a separate public load requirement to assist in meeting the stated 400 MW goal in the Governor's Executive Directive 3. The public agency (VDOT) could purchase SRECs from the developer to satisfy an established carbon offset requirement.

Page 288REQUEST FOR INFORMATION RESPONSES

Page 82: 4.1 Miller Bros Qualifications - P3 Virginia...Duct and Manhole Installation . Medium and High Voltage . Transmission and Distribution . Installations up to 500kV . Substation and

Page: 9

Author: hillisj Subject: Sticky Note Date: 3/12/2015 2:21:55 PM It is doubtful that the value of these RECs generated in Virginia with a voluntary RPS would attract the investment required.

Page 289REQUEST FOR INFORMATION RESPONSES