4 retrofitting of bridges

Upload: khelanparmar

Post on 08-Apr-2018

222 views

Category:

Documents


3 download

TRANSCRIPT

  • 8/7/2019 4 Retrofitting of Bridges

    1/19

    Retrofitting of BridgesRetrofitting of Bridges

    Technical paper on

    a Case Study

    By

    Saket P Borgaonkar

  • 8/7/2019 4 Retrofitting of Bridges

    2/19

    Need of RetrofittingN

    eed of Retrofitting Upgrading of seismic coefficients as a result

    of revised seismic zone

    Updating design criteria due to revision ofcode

    Bridges not designed to seismic force

    Bridges that damaged in earthquakes

    Deterioration and aging

  • 8/7/2019 4 Retrofitting of Bridges

    3/19

    WhyN

    ot Demolition and ReconstructionW

    hyN

    ot Demolition and Reconstruction New structure needs large cost.

    New alignment necessitates acquisition of land,

    property.

    Large quantity of material required for reconstructionthat has to be obtained from nature by destroying itand thus a loss of ecological balance.

    New routs add to inconvenience of public and otherliving beings.

    The residual utility of old structure goes to waste.

  • 8/7/2019 4 Retrofitting of Bridges

    4/19

    Methods of Retrofitting

    Methods of Retrofitting

    SuperStructure

    Most common retrofit for superstructures is

    installation of unseating prevention devices

    Sub Structure

    steel jacketing, reinforced concrete

    jacketing, FRP jacketing.

  • 8/7/2019 4 Retrofitting of Bridges

    5/19

    Methods of Retrofitting

    Methods of Retrofitting

    Bearings. Replacing steel bearings by base isolation bearings.

    Bearing seat extension. Provision of stoppers and devices to prevent jumpingof girders.

    Abutment.A unique retrofit for tilt of abutments in the frontdirection is to replace some part of the back-fills withexpanded polystyrene (EPS).

  • 8/7/2019 4 Retrofitting of Bridges

    6/19

    Case StudyCase StudyRetrofitting of the Bridge

    across Vishwaganga River

    between Malkapur & Nandura

  • 8/7/2019 4 Retrofitting of Bridges

    7/19

    Salient Features of the BridgeSalient Features of the BridgeYear of construction 1964

    Carriageway 7.5 m

    Superstructure RCC girder deck system

    Substructure CR masonry

    Foundation open

    No. Of spans 10 spans of 13.72 m,Thickness of deck slab 215 mm

  • 8/7/2019 4 Retrofitting of Bridges

    8/19

    Salient Features of the BridgeSalient Features of the BridgeNumber of girders

    3 main girders at 2.25m c/c with size 300mm

    and 1400mm deep and 450 x 300 mm bottomflange and

    2 cross girders at 4.40 m c /c

    Wearing courseRCC wearing course followed by bituminouswearing course

  • 8/7/2019 4 Retrofitting of Bridges

    9/19

    History

    History

    Repairs were carried out twice in 1994

    and 2001.

    In 1994 mostly cement grouting was

    done which could not have served the

    purpose.

    In 2001, 3 spans were tackled by epoxygrouting, but pot holes to slabs were

    not treated.

  • 8/7/2019 4 Retrofitting of Bridges

    10/19

    Field ObservationsField Observations Considerable holes in deck slab with spalling

    of concrete and virtually no bond between

    concrete and steel. Reinforcement broken atmany places.

    At number of places in bottom bulb of girders,

    concrete had not reached due to congestion ofreinforcement & heavy cracks observed ingirders with porous & spalled concrete. Heavyvibrations observed with vehicle movement.

  • 8/7/2019 4 Retrofitting of Bridges

    11/19

    Field ObservationsField Observations In the bottom surface of cantilever portion,

    steel was corroded thereby cracking & spalling

    of concrete was observed.

    The wearing course was totally damaged withheavy leakages in rainy season thereby further

    damaging deck slab.

    Weep holes provided for draining of rain waterover the bridge had been blocked.

  • 8/7/2019 4 Retrofitting of Bridges

    12/19

    Span wise visual observationsSpan wise visual observationsSPAN MAIN GIRDERS DECK SLAB CANTILEVERS

    Span 1(N) Crack Honey

    Combing

    Mapping Cracks Corroded Reinforcement

    Span 2 MinorHoney

    Combing

    Mapping Cracks Corroded Reinforcement

    Span 3 Cracked Holes Corroded Reinforcement

    Span 4 Cracked Concrete Spalling Corroded Reinforcement

    Span 5 Cracked MinorHoles Repaired but No Bond with Old

    Concrete

    Span 6 Steel Exposed

    Cracked

    Holes Developed Repaired but No Bond with Old

    ConcreteSpan 7 Minor Cracks Severally Damaged Corroded Reinforcement

    Span 8 Slightly Damaged Holes Developed Corroded Reinforcement

    Span 9 Ok Concrete Spalling Corroded Reinforcement

    Span 10 Cracked Concrete Spalling Corroded and Spall

    ing

  • 8/7/2019 4 Retrofitting of Bridges

    13/19

    Non Destructive TestsNon Destructive Tests

    To decide exact strength of existingconcrete ultrasonic testing and

    rebound hammer testing of girders wascarried out.

    Concrete found to be porous with

    pulse velocity from 2.5 to 3.0 km/sec.

    Rebound hammer test indicated

    average strength of about 14.0 N/mm2

    .

  • 8/7/2019 4 Retrofitting of Bridges

    14/19

    Restoration MeasuresRestoration Measures

    The quality of concrete was insufficientin strength to withstand dynamic loads

    resulting from movement of very heavyvehicles. As a matter of fact due to holesin deck slab, cracks in girders a totalretrofitting was necessary to enhancethe life of structure.

    the retrofitting work was divided inseveral activities member wise.

  • 8/7/2019 4 Retrofitting of Bridges

    15/19

    Restoration MeasuresRestoration Measures

    Main and cross Girders

    Girders were strengthenedby injecting low viscous

    epoxy grout (SLV grout).Holes were drilled at 150 mmc/c along the cracks byelectric drill and nipples,then cracks were sealedwith epoxy patchingcompound. After grouting,welded mesh was fixed togirders & entire girders were

    shotcreted.

  • 8/7/2019 4 Retrofitting of Bridges

    16/19

    Restoration MeasuresRestoration Measures

    Deck Slab

    For portion where Reinforcedsteel was broken, loose

    concrete of wearing courseand deck slab was removed.Additional reinforcement waswelded to girder reinforcement.Anticorrosive coating was

    applied to rebar. super fluidmicro concrete was pouredwith 3 days compressivestrength of 250 kg/cm2

  • 8/7/2019 4 Retrofitting of Bridges

    17/19

    Restoration MeasuresRestoration Measures

    Cantilever

    The loose cover concrete wasremoved by chisel. Near

    corroded reinforcement EPCOKP 100 was applied along theexposed concrete surface. Theexposed and corroded steelwas cleaned with wire brush

    and the bars were coated withIPN BR as anticorrosivecoating. The welded meshwas fixed. EPI bond epoxy was

    applied and the surface wasshotcreted 50 mm thick.

  • 8/7/2019 4 Retrofitting of Bridges

    18/19

    Restoration MeasuresRestoration Measures

    Wearing Coat

    The Wearing Coat was removed from half

    portion i.e. one lane up to deck slab. Holeswere drilled @ 1000 c/c and grouted with

    polymer grout. The removed wearing course

    was redone with M 35 with superplisizers,

    micro silica and polypropelene fibers.

    The entire lane was relaid with bituminous

    concrete.

  • 8/7/2019 4 Retrofitting of Bridges

    19/19

    ConclusionConclusion

    The girders, which were cracked severely haveshown improvement through out section ofgirder. Integrity of girder and strain carrying

    capacity has shown significant improvementwith vibrations reduced to great extent.

    The effectiveness of restoration process wasascertained by same NDT techniques.

    The average velocity was 3.75 km/s withimprovement of 25 to 30% and concrete qualitywas good.

    The average compressive strength was 25.0

    N/mm2