QualityAssurancePlan
Constructionworkprocedurefor FOOTINGLOADTEST
CONTENTS
Sl.No. Content
01 Scope
02 Reference(Documents,Drawings,Layouts)
03
OrganizationChart
04 StaffResponsibility
05 Materials
06 Manpower
07
Machine,
Equipment,
Tools
&
Tackles
08 Sequenceofactivities
09 WorkProcedure
10 Weatherlimitations
11 Inspectionplan
12 Testplans
13 MandatorySafetyRequirements
14 Environment,Health&Safety
15 Trainingandeducation
16 Formats&Checklist
-
7/31/2019 4-construction-work-procedure-for-foundation-load-test-13-09-11.pdf
2/41
QualityAssurancePlan
Constructionworkprocedurefor FOOTINGLOADTEST
1. SCOPE:Thepurposeofthefootingloadtestistostudytheloadsettlementbehaviorofthetypeofsoilencountered
atthesiteforshallowfoundationrestingonsoil.
Thetestlocationisasunder:
Corridor
Location
Coordinates NGLinRL(m) Sizeof
Footing
TestDepth R.L.(m)
3m
from
NGL
N E
III BetweenNagoletoUppal 1924902.877 240317.267 480.439 2mx2m 477.439
Thetestconsistsofmeasuringsettlementuptoloadintensityof100t/m.Theloadshallbeappliedinten
equalincrementsonarigidfootingof2mx2mattheabovespecifiedtestlevel.Theloadshallbeappliedby
meansofhydraulicjack;Rockanchorsalongwithstructuralframeshallbeusedasareactionforthejack.
2. REFERENCEDOCUMENTS:3. ORGANISATIONCHART:
`
4. STAFFRESPONSIBILITIES:
Surveyor
QualityControlEngineer
AgencyforRock
Anchors&LoadTest
M/sTech9
Engg.solutionsPvt.Ltd
SafetyEngineer
ConstructionManager
(TapasDas)
Engineer
(B.B.Rai)
Foreman
(IGupta)
AgencyforRock
Anchors&LoadTest
ConstructionManager
Engineer
Foreman
-
7/31/2019 4-construction-work-procedure-for-foundation-load-test-13-09-11.pdf
3/41
QualityAssurancePlan
Constructionworkprocedurefor FOOTINGLOADTEST
MonitorsoptimumutilizationofMachine,equipmentengaged
InvolvesinSafetyandQualityPeptalksregularly.
MonitorstheProgramvs.Progressofhisworkandanalysesworkdifficulties,criticalpathifanyasper
thesetTarget.
Monitorsmandatorysafetyrequirementsforworkmenandworkenvironment.
4.2.ENGINEER:
ReportstotheConstructionManagerfordaytodayactivities.
InteractswiththeLTMRHLRepresentativesandgeneratesRFIsforinspection.
Execute the job thru specialised agency and give the feedback about the progress toConstruction
Manager.
LiaisonwithinternaldepartmentslikePlanningcell,Qualitycontrolcell,Plant&Machinerydepartment,
SafetydepartmentandStoresfor
Ensurestoimplementallmandatorysafetyrequirementswithinhisworklimits.
Responsibleforoptimumutilizationofresources.
Submitshisrequirementsofmaterials&otherresourcesforhisworktotheCONSTRUCTIONMANAGER
wellaheadofschedule.
PrepareshisworkschedulebasedonProjectschedule.
Closely
monitors
to
achieve
the
set
program.
Follows the Inspection, Test plans and submits records to LTMRHL for their reviews and approval
throughEDMS.
4.3.SURVEYOR:
ReportstotheConstructionManager.
MarksthecoordinatesfortherockanchorboreholepositionsandFootingLayout.
Check
invert
Levels
of
test
pit
before
&
after
excavation,
Plain
Cement
Concrete
Top,&
Footing
Top.
4.4.FOREMAN:
ReportstotheSiteEngineerandfollowhisinstruction.
ResponsibleforassemblinganderectionofKentledgeincludingfixingofrockanchors.
Supervise adequately for any safety lapses and ensure the right way of handling of Heavy equipment /
-
7/31/2019 4-construction-work-procedure-for-foundation-load-test-13-09-11.pdf
4/41
QualityAssurancePlan
Constructionworkprocedurefor FOOTINGLOADTEST
ImplementEHSsystemsatsite,Superviseforthesafetylapsesbeforecommencementofwork.
Organizetrainingprogrammesforsafetyawareness.
Coordinateswithsiteadministration,firstaidcenter,doctors&hospitalsduringemergency.
4.7.QUALITYCONTROLENGINEER:
Reportsmaterialengineeraswellasactsasasitequalitycoordinator.
Involvesinregularqualitypeptalks,periodicaldemonstrationsofbestpracticesinwork,
Arranges routine testing for the consumable construction materials like cement grout cubes,
concrete cubes, witness calibration of testing & measuring equipment /tools like pressure
gauges,deflectiongauges.
Checkstherightmaterialusedatrightplace.
5. MATERIALS:Sl.
No
Name Brand/Source Conformsto
QuantityRequired
1 HYSDSteelTMTBars M/sAFPL IS:1786 0.332MT
3 LimePowder Locallyavailable 20kg
2 Concrete1:3:6 Handmixed IS:456 0.400M
3 ConcreteM30Grade BMRReadyMix IS:456 3.800M
4 HTStrandsof12.7mm DPwires ,Ratlam,MP IS:6006 (25Mx10nosx
5 HDPEPipeof16mmID Locallyavailable 175Mtr
6 FixedAnchor Locallyfabricated IS:10270Cl.6.4
7 EpoxyHardenerLapox
K46,EpoxyResinLapox
B47,
ATUL Chemicals,
Valsad,Gujrat
4nosx2.5kg
8 AnchorHead MF1205 IndiaComponents(P) IS:10270, 4nos
9 Wedge RudraMetalIndustries 50nos
10 PVCspacerplateof100mmdiaand6mm
thick)
Locallymade DrawingAnnexureA
10
11 BarBindingwire(22 Locallymanufactured IS:432 10.000kg
12 Shutteroil SWC/SIKA/ IS:4990,AnnxC3 2.000ltr
13
-
7/31/2019 4-construction-work-procedure-for-foundation-load-test-13-09-11.pdf
5/41
QualityAssurancePlan
Constructionworkprocedurefor FOOTINGLOADTEST
6. MANPOWER:Sl.No Catagory Nos.Required Remarks
1 Drillingmachineoperator 1 2 Supervisor 1 3 Rigger 4
4 Tractorcompressoroperator 1
5 HydraulicJackOperator 1 6 Trafficmarshal/Flagmen 2
7 Unskilledworkman 4
8 QualityControlTechnician 1
7. MACHINE,EQUIPMENT,TOOLS&TACKLES:Sl.No TypeofMachine,Tools&
Tackles
Nos.
Required
Calibration Remarks
1 Safetycones 12
2 SafetyBarricadingboard 14
3 Blinkers 10
4 PVCTrafficBarrier 10
5 Barricadingboardfixingnails 60
6 Totalstation 01 Calibrated
7 Levelmeasuringinstrument 01 Calibrated
8HydraulicRockDrilling
Machine
01
9 DewateringPump5hp 01
10 Platecompactor 01
11 Handcompactor 01
12Tyre mountedHydraulic
Crane12MT
01
13Concretepouringchute3m
long
01
14 Tractor Compressor 01
-
7/31/2019 4-construction-work-procedure-for-foundation-load-test-13-09-11.pdf
6/41
QualityAssurancePlan
Constructionworkprocedurefor FOOTINGLOADTEST
Sl.No
Typeof
Machine,
Tools
&
TacklesNos.
RequiredCalibration Remarks
NABL
Accredited
Laboratory.
19 Multistrandstressingjack 01
20
Deflectionmeasuringgauge
(50mmrangewithprecision
of0.01mm)
04 Calibratedfrom
NABL
Accredited
Laboratory.
21
Deflectionmeasuringgauge
(25mmrangewithprecision
of0.01mm)
04 Calibratedfrom
NABL
Accredited
Laboratory.
22 Concrete(needle) Vibrator 01
23 ConcreteVibratorneedle60mmdia
02
24Steel/Plywoodshutters 08SQM
25 Pickaxe 2
26 Spade 2
27 Measuring(steel)tape3m 1
28Plumb 1
29Soundingchainfordepth
measuring(25m)
1
30SteelfabricatedLadderof
2.2mlong.
2
31 Gascuttingset 1
8. Sequenceofwork:Obtainingstatutoryworkpermissions.
EducatingteamaboutConstructionWorkProcedure(CWP).
Marking of test pit coordinate and area of excavation
-
7/31/2019 4-construction-work-procedure-for-foundation-load-test-13-09-11.pdf
7/41
QualityAssurancePlan
Constructionworkprocedurefor FOOTINGLOADTEST
TyingofRebaratthefoundationlocationShutteringofconcretefooting.
Placingofconcrete.
Strippingoutofshutters.
Curingoffootingloadtestconcretestructure.
Settingofanchorframe.
Cementgroutcubetest.
InitialstressingforSlackremovalofstrands.
Calibrationofpressuregauges&deflectiongauges.
FixingofHydraulicjack,pressuregaugeanddeflectiongauges.
Concretecubetesting.
SettingoflevelmeasuringinstrumentandReducedLevelmeasuring.
Loadtesting
Recordingtheobservationsofsettlementagainstpressure/LoadandTime.
Unloadingofpressure.
Dismantling&demobilizationoftestarrangements.
Backfillingoftestpit.
Roadrestoration.
Removalofbarricadingboards,safetyconesetc.
OpeningofBarricadingareatoTraffic.
9. WORKPROCEDURE:9.1TheworkshallbecommencedafterobtainingstatutorypermitsfromtheTrafficpolicedepartment
andGreaterHyderabadMunicipalityCorporation,andotherGovernmentbodies.
9.2Theconstructionteamshallbeeducatedabout theapprovedConstructionWorkProcedure(CWP)
byConstructionmanager.
9.3Asperthecoordinategiveninthetablegiveninsection1.0scope,keepingthecoordinateasthe
centeroffoundation,areaofexcavation(2.5mx2.5m)shallbemarkedbylimepowder.
9.4The footing load test area (12.0m x 8.0m) shall be marked and barricaded with 16nos steel
fabricatedboards (L=2.0m x H=2.4m each). These barricades shall be firmly secured by nailing
downintotheground.Fournosofredblinkinglightsshallbefixedashazardsignalsalongandat
thetopofbarricadingline.Otherroadsafetycautionaryboardsshallbeprovidedfacingtowards
-
7/31/2019 4-construction-work-procedure-for-foundation-load-test-13-09-11.pdf
8/41
QualityAssurancePlan
Constructionworkprocedurefor FOOTINGLOADTEST
shallbeinsertedbyproviding10nosofPVCspacerplatesat1mc/cplacedthroughoutthefixedlength,sothatthestrandsarenotentangledtoeachotherwhileinsertingintothedrilledbore
hole.AnAnchorheadshallbefixedattheendofstrandgroupandaguidebulbshallbemadeat
thecutendbeforeinsertingofstrandsusingEpoxy(mixofHardenerLapoxK46andResinLapox
B47)grout.
9.6AHighDensityPolyEthylene(HDPE)pipeof16mmIDand25minlengthshallbeinsertedthrough
thecenterofthespacerplatesuptothebottomforpouringcementgrouttoanchorthestrands
intherockhole.Allofthestrandsinsidetheboreholeabovethe10mrocksocketingforthefree
length shall be inserted thru individual HDPE Pipes of 16mm ID to keep the strands free from
contactwithmoistureandsoilaround.
9.7Grout shall be prepared by mixing Cement and water uniformly using a mechanical mixer to a
watercement ration of 0.40per bag of cement, water to be added is 20lts) which shall be
pumpedintotheanchorholethroughthecentrallyplacedHDPEpipe.Asuitablepressuregrout
pumpcapabletopumptheabovecementgroutshallbeusedtopourthegrout.6nosormoreof
groutcubesofdimension(100mmx100mmx100mm)shallbecasttoascertaintheageatwhich
aminimum strengthof 30Mpa is achieved.Groutshall be filledupto the fixed length (Bottom
10.0m) portion i.e. up to the rock socketing length. Confirmation of filled depth shall be
measuredbyusingsoundingchain.Thefreelength(11.50mminimumfromthegrouttop)ofthe
anchoriskeptfreetoelongateforstressingeffectduringloadtest.
9.8Dismantling of the concrete median, hard top road surface shall be done by pneumatic
pavementbreakerandtheexcavatedmaterialshallbedisposedoffinasuitabledisposalarea.
9.9Theunderneathlayersshallbeexcavatedmanuallybyusingpickaxeandspade.Excavationshallbe
done up to 3mtr below the existing ground Level. Excavated material shall be kept aside for
backfillingofthetestpit.Thebaseofthetestlocationshallbeleveledandcompactedwiththe
lightdutyplatecompactor.A75mmthickPlainCementConcrete1:3:6shallbeplacedoverthe
excavated,leveled&compactedtothedimensionsgivenasperthedrawinginAnnexureA.
9.10 Abrickmasonry/solidprecastconcreteblockwallofheight150200mmshallbemadearoundthetestpitattheexistingground leveltoprotectthetestareafromsurfacerainwaterentering
in.
9.11 Cutting,bending,andtyingofReinforcementbarsforthefootingshallbecarriedoutasperthe
Bar Bending Schedule. Adequate water tightness of shuttering for the RCC footing shall be
-
7/31/2019 4-construction-work-procedure-for-foundation-load-test-13-09-11.pdf
9/41
QualityAssurancePlan
Constructionworkprocedurefor FOOTINGLOADTEST
achieved ismore than 30N/mm but not before 14days, strandgroups from each rock anchorsshall be stressed one by one using a multi strandjackto remove slackness if any. The required
pressuretoremovetheinitialslacknessshallnotbemorethan0.72MT.
9.13 Asgiveninthedrawing(AnnexureA),thearrangementsofplacing Datumbars,andHydraulic
Jack,fixingof twoset ofdeflectionmeasuringgaugesof 50mm travel(4nos)and 25mmtravel
(4nos)withthedatumbars,settinguppressure/Loadmeasuring gaugeshallbedone. Once
loading commences, readings shall be observed from the 50mm deflection gauges (First set of
dialgauges)forthesettlementoffooting.Afterthedeflection(settlement)reachesabout45mm
travelanothersetofdialgaugesof25mmtravel(Secondsetofdialgauges)shallbesettoitszero
positionandsubsequentreadingsshallbestarted.Inasimilarmannerifthesettlementreaches
20mm(inthesecondsetofdialgauges),againtheprevious50mmgaugesshallbekeptreadyfor
the next settlement reading. The observations in settlement shall be continued until the final
loadof400MTisreached.
9.14 As an additional measure to check elongation of strands comparing with yield of ram ofjack,
four level instruments shall be set with a paint mark on each set strands before loading
started.The survey instrument shall be used to note the change in reduced level on each
increment of loading, immediately and after elapse of 60minutes. This shall provide a relation
betweentheelongationsofstrand;pressureappliedandyieldsoframofjack.
9.15 Concrete cube sample shall be tested at the age of 14days or later to check the compressive
strength of concrete is achieved more than 30Mpa.And once the concrete achieved the
compressivestrength
the
activity
for
the
load
test
shall
be
taken
up.
Initially
minimum
seating
loadof2.80Tshallbeappliedandremovedbeforestartingoftheloadtest.Theloadingpatterns
intermsofpressureshallbecalculatedbasedontheRAMdiameterofjackatsite.Thenfooting
shallbeloadedtoamaximumloadof400MTandthedesignloadintensityof100MT/m.Thisis
done in 10 equal increments. Settlement will be observed for each increment of load after an
intervalof1.00,2.25,4.00,6.25,9.00,16.00and25.00minutesandthereafterathourlyintervals
tothenearestof0.01mm.Eachload incrementshallbekeptfornotlessthan1houroruptoa
time when the rate of settlement is appreciably reduced to a value of 0.02mm/min. the next
incrementofloadthenbeappliedandtheobservationsrepeated.Theloadingshallbecontinuedtoamaximumloadintensityof100MT/msubjectedtothreeconsecutivehoursthroughwhich
no change observed in settlement.Consideringfree length ofstrands as 11.500m, expected
elongationofstrandsshallbeasunder:
LoadappliedinMT Loadingin% Elongationinmm)
40 10 5.98
-
7/31/2019 4-construction-work-procedure-for-foundation-load-test-13-09-11.pdf
10/41
QualityAssurancePlan
Constructionworkprocedurefor FOOTINGLOADTEST
9.16 Reading of dial gauges shall be taken by getting down from existing ground level to the top of
footing level,but outside the footing through the steps made from two opposite barricaded
sides asinthesketchasAnnexureD .Ineachsideoftopoffootingthereisaclearanceof1.2m
inbetweendatumbars.Careshallbetakenthatdatumbarsmustnotbe touchedordisturbed
duringdialgaugereading.
9.17 Upon completion of loading, unloading shall be done in 10 equal decrements. After reaching
theultimateload,thesettlementshallbeobservedforsuchthreehourlyreadingswherethere
is no further settlement (less than 0.02mm/min) is noted or elapse of 24 hours, whichever is
earlier.After eachdecrementof load 15minobservation timeshallbeallowedfor recovery in
settlementandrecorded.
9.18 After completion of test, the testing instruments (Pressure gauge, Deflection gauges) shall be
removed,packedandsealedcarefullyandshallbestoredatQualityControlDepartment.Other
Kentledgearrangementshallbedistressedanddismantledbyusingcraneanddemobilizedfrom
sitebynexttwodays.Strandsfromtheanchorholesshallbecut150mmbelowtheholetopand
the hole shall be filled with crushed rock sand followed by full water saturation and 150 mm
concretecapping.
9.19 BackfillingofthetestpitshallbecarriedoutaspertheConstructionWorkProcedureandthere
by road shall be restored.At last the barrication and road safety Cautionary boards shall be
removedandopenedtotraffic.
10.WEATHERLIMITATIONS:Season RiskAnalysis PreventiveMeasures
Rainy a) Heavy rain may cause flooding
insidethetestpit.
b) Rainingduringtest
a) Test pit barricading wall shall be
checked for any water leakage from
outside.
b) Test pit shall be shaded by covering
with Tarpaulins to avoid any kind of
interruptionintesting.
Winter Settingandstrengthgaininginconcrete
requires sufficient time and may cause
Suitable adjustment shall be done in mix design
of concrete to get required strength in time
-
7/31/2019 4-construction-work-procedure-for-foundation-load-test-13-09-11.pdf
11/41
QualityAssurancePlan
Constructionwork
procedure
for FOOTINGLOADTEST
11.INSPECTIONPLANSl.No. DescriptionofOperation QHP QCP Documentation
1 Layoutoftestpitandanchorholepositions
SketchfootingLoadTestLocation
2 SafetyBarrication
Trafficsafetybarricationplan
3 Drillingofrockanchors
CheckListbeforeHomingofRockAnchors
4 LoweringofStrandsGroutingofrockanchors
Rockanchorgroutingreport
5Excavation &Levelcheckafterexcavation &PCC
ChecklistforPCCforconcretestructures
6Shutteringoffooting,placingandfixingofRebars
BarBendingSchedule
7Concretingoffooting&column
Concretepourcard
8Arrangementofkentledge
9HydraulicJackPerformance
ManufacturersTestCertificate
10 CalibrationofPressureGauge
CalibrationReport,RFI
11CalibrationofDeflectionGauges
CalibrationReport,RFI
12 Loadtestingonfooting Footingloadtestrecord&Footingloadtestreading
12.TESTPLAN:Sl.No. Testtype Codeofpractice Frequencyoftesting Specificationrequirement
1
Cement
Test
IS:4031 One
per
Batch
(Review
of
MTC) AS
per
IS:8112
&
IS:12269
2 ConcreteSlumpTest IS:1199 One /TransitmixerLoad 10025mm
3 ConcreteCubeTest IS:516 ,IS:456 Onesample/5m >30N/mm
4 CementGroutCubetest IS:10270/BSEN:447 Twosamples(6cubes)/day >30N/mm
Note:AllthetestreportsasinTestPlanareavailablewiththeQualityControlEngineer.
-
7/31/2019 4-construction-work-procedure-for-foundation-load-test-13-09-11.pdf
12/41
QualityAssurancePlan
Constructionwork
procedure
for FOOTINGLOADTEST
13.MANDATORYSAFETYREQUIREMENTS:EveryworkmanmustbeengagedafterScreening,Safetyinduction&medicaltest.
EveryworkmanshallbeallowedtoworkwithPersonalProtectiveEquipment(safetyshoes,SafetyHelmet,ReflectiveJackets,handgloves,nose
musk,earplug,safetygoggles).
AreaofworkshallbebarricadedwithBoardswithproperanchoring,boltingandweighttobekeptforstabilityofbarricades.
Whileplanning excavationoftestpit,itisimportanttoplanagainstthefollowing:
Collapseofthesides,
Materialfallingonthepeopleworkingintheexcavation,
Peopleandvehiclesfallingintotheexcavation,
Peoplebeingstuckbyplantandmachinery,
Accesstotheexcavation,
Fumes,Toxicgas Undergroundutilities
Incidentstomembersofthepublic.
Certifiedcrane&vehicleshallonlybedeployedforthejob
Operatorofvalidlicenseshallbepermittedtooperatethecrane.
Properaccessandworkingplatformshouldbeprovidedtoreachtheworkspot.
Safetywarningsignsshallbeplacestoprovideadequatewarning.
Wherenaturallightingisnotadequate,workinglightfittingsorportablehandlampsshallbeprovidedatworkplaceontheconstructionsite.Inthe
workingspotilluminationshallbe110lux.
-
7/31/2019 4-construction-work-procedure-for-foundation-load-test-13-09-11.pdf
13/41
QualityAssurancePlan
Constructionwork
procedure
for FOOTINGLOADTEST
14.ENVIRONMENTALHEALTH&SAFETYRISKASSESSMENT/SUMMARYSHEET
CONTRACTORNAME: RISKASSESSMENTFOR: FoundationLoadTestActivity
OriginatorName(Print): Contract:Signature: Date:
KEY: L=Likelihood S=Severity R=Risk(LikelihoodxSeverity)
RISKRANKING:L=Lowprioritytobeimplemented
whenresourcesallow.
M=Mediumprioritytobescheduledassoon
aspracticable.
H=Highprioritytobeactedon
immediately.
Task/ElementPotential
Hazards
Population
atRiskRiskRating
ControlMeasures/FollowupChecklistRevisedRating
L S R L S R
Setupforsurveyatproposedarea/location/points
Loading/Unloadingofbarricading
boards
FixingofBarricadingboardontheroad
Machineshiftingfromstoretositeby
vehicle
Drilling
HTstrandsfixing
ExcavationWorkforLoadTestarea
BuiltupbeamshiftingfromFabrication
yardtositebycrane&tailor.
Handling& Erectionof Builtupbeam
andHydraulicjack&Plashing
-
7/31/2019 4-construction-work-procedure-for-foundation-load-test-13-09-11.pdf
14/41
QualityAssurancePlan
Constructionwork
procedure
for FOOTING
LOAD
TEST
RISKASSESSMENTFORMSAF20
CONTRACTORNAME: RISKASSESSMENTFOR: FoundationLoadTestActivity
OriginatorName(Print): Contract:
Signature: Date:
KEY: L=Likelihood S=Severity R=Risk(LikelihoodxSeverity)
RISKRANKING:L=Lowprioritytobeimplementedwhen
resourcesallow.
M=Mediumprioritytobescheduled
assoonaspracticable.
H=Highprioritytobeactedon
immediately.
Task/Element PotentialHazardsPopulationat
Risk
RiskRating
ControlMeasures
RevisedRating
L S R L S R
Setupfor
surveyat
proposedarea/
location/points
WorkbelowHTorLTlive
lineElectrocutiondue
toaccidentalcontactof
levelingstaffwithHT/LT
line.
Surveyors/
SurveyAsst./
helpers.
1.Allpersonsshouldbescreenedandinducted.
2.AllpersonsmusthaveallPPEs
3.Beforestartingthework,priortoinspectallareaproperly.
4.AnyOHlinemustbeidentified.
5.Allworkmen&staffmustbeusereflectivejacket
compulsory.
6.Usingoffiber/PVCorwoodenlevelingstaff.
7.Whilerainingnobodyshouldstandorallocatednear/
nearbytheOHlivelines.
-
7/31/2019 4-construction-work-procedure-for-foundation-load-test-13-09-11.pdf
15/41
QualityAssurancePlan
Constructionwork
procedure
for FOOTING
LOAD
TEST
8.RegularToolBoxTalkatsite.
9.Allpersonsmustbeawareaboutthepotentialhazards.
10.Allocatedareahasbeenbarricadedandensuresthe
vehicularmovementswereclearfrom.
Roadaccident Movingofpersonsacrossthe
road.
Surveyors/SurveyAsst./
helpers.
1.Alltrafficprecautionarymeasurehasbeentakenwhile
setuplikesafetycone,barrier,signboardetc.
2.Oneflagmanhasbeendeployedinfront.
3.Whilecrossingoftheroad,flagmenmustbeguidedthe
crew.
4.Ensuringthetrafficmovementwaslow,meantime
maximumcrossingshallbeallowed.
5.Allworkmen&staffmustbeusereflectivejacket
6. Specialtraininghasbeengivenforsurveyteamswhile
induction.
7.Allsurveypersonshavebeenfrequentlysubjectedfor
medicalcheckup.
8.Bealertwhilewalkingoverroadandothertrafficmovement
areas.
Loading/
Unloadingof
barricading
boards
Toppling/Fallingof
materialsfromvehicles.
Helpers
&khalasi
1.Allnecessarycheckingaboutthefitnessofthevehiclestobe
conductedbeforestartingofoperation.
2.Alltheliftingtools&tacklesmustbetestedandcertified,
3.Tagropeshouldbeusedforanyliftingloads.
-
7/31/2019 4-construction-work-procedure-for-foundation-load-test-13-09-11.pdf
16/41
QualityAssurancePlan
Constructionwork
procedure
for FOOTING
LOAD
TEST
4.Nobodyshouldworkundersuspendedloadatany
circumstances.
5.Materialsshallbeproperlysecuredonthevehicle.
6.Thewholehandlingoperationwillbecarriedoutunder
authorized/competentsupervisor.
7.Duringpositioning&placementofloadcareshouldbe
takentoavoidinjuriesduetopressinbetween.
8.Materialsshouldnotbeoverloaded.
9.Correctriggingpracticemustbefollowed.
Fixingof
Barricading
boardonthe
road
Unbalancing/toppling
whileboardfixing
Helpers/
khalasies/
Public.
1.Usingofpropertaglinewhilefixing
Sufficientworkmenshallbeengagedforfixing&shiftingon
theroad.
2.Useofsafetyhelmets,Shoes,FlorescentJacket,andother
relevantPPEsensuredforallworkers.
3.Flagmanmustbedeputedatsitewithfluorescentjacket,
redflag(Day),whistle&redlightbatonfornighttimeswith
otherrelevantPPEs.
4.WorkplaceBarricadesweresecuredbyproperNailingwith
600mmlength&20dia.Alsosecuredby70kgconcreteblock
forstrengtheningtheboards(Counterweight).
5.AllBarricadingboardsconnectedbynutbolt
6.Trafficsafetydevicesshouldbeproperlykeptfrom15mts
bufferzoneandadvancewarningzonewasaligned10mts
-
7/31/2019 4-construction-work-procedure-for-foundation-load-test-13-09-11.pdf
17/41
QualityAssurancePlan
Constructionwork
procedure
for FOOTING
LOAD
TEST
fromapproachtransitionzones.
8.Barricadingboardkeptwithblinkers&monitoringboards
shallbeindicatedbyreflectedtape.
9.Trafficmarshal&vehiclediversionmustbegiven.
10.Allbarricadingboards Shouldbekeptinastraightlinefor
public&vehicleconvenience
Machine
shiftingfrom
storetositeby
vehicle
Duringshifting&
Unloadingatsite
Riggers,
khalasi&
Helpers
1.Vehiclesparkedlowerlevelandauthorizedriggersand
workmenwereengaged.
2.Alltoolsandtackleswerecheckedproperlybeforeengaging
intothetask.
3.Areashouldbeseparatedfrompublicaccessbybarricadingthearea.
DrillingPerson
injured
at
the
timeofdrillhammer,bit
&rodhandling&
changing.
Drillers,Helpers,
Supervisors
1.EnsurethatalltheutilitiesareIsolated/removedfromour
workpoint.
2.Ensurethatallrotatingpartsareproperlyguarded.
3.AllmachinerieswereproperlyinspectedwithP&M&EHS
engineerandconfirmthatallthepartisworkingproperly.
3.EnsurethatthelocationsarefreefromHTutilities.
4.Allplacesofhosepipejointingareashouldbefastened
properly.
5.Useofsafetyhelmets,Shoes,FlorescentJacket,Earplug
(Duetonoisepollution)andotherrelevantPPEsensuredfor
allworkers.
-
7/31/2019 4-construction-work-procedure-for-foundation-load-test-13-09-11.pdf
18/41
QualityAssurancePlan
Constructionwork
procedure
for FOOTING
LOAD
TEST
6.Awakingthedrillingpersonsinperiodicalintervalaboutthe
procedureofjointing&removingthedrillrod.Nobitgrinding
shouldbeallowedinneckedeye.
HTstrands
fixing
DuringplacingtheHT
stand
Supervisor,
Helpers&
Workmen
1.BealertwhileHTstrandsareloadedontoDecoilerwiththe
helpoftheF15crane.
2.UseshoulderpadforshiftingofHTstand
3.Educatetheworkmentocarrythesharpedgedbarsfront
sideupward.
4.Ensuringspaceforworkingarea.
5.Dailyhousekeepingpracticeisadopted.
GroutingDuringhandlingof
materials
Workmen,
Masons,
Helpers
1.MSDSisbriefedtotheworkedwithdosanddonts.
2.Engageexperiencepersononthejob.
3.UseofRubberHandgloves,gumboots,Nosemask&
GogglesduringGroutingwork.
Excavation
WorkforLoad
Testarea
Undergroundutilities
ImproperAccess/egress
Materialsstackingonthe
edgeofexcavation
Collapseofsides,
Materialfallingonthe
peopleworkinginthe
excavation,
Workmen,
Operator
&Helpers
1.FollowExcavationclearancepermitsystem.
2.Ensureadequateillumination,&dangerlighting.
3.Nomaterialsshallbestackedatedgeofthepit.Min1.5m
clearanceshallbegiven.
4.BarricadingwithTape&HardBarricadewithreflective
signage.
5.Accessladdershallbesoplace,thatworkmenisableto
access.
-
7/31/2019 4-construction-work-procedure-for-foundation-load-test-13-09-11.pdf
19/41
QualityAssurancePlan
Constructionwork
procedure
for FOOTING
LOAD
TEST
People,animalsfalling
intotheexcavation,
6.Properslope/Stepcuttingshouldbemaintainedasper
norms.
7.Excavationshouldbemadefromtoptobottomandno
undercutsshouldbemade.
8.Provideadequateemergencyaccesssothatworkmencan
accessitat15mreachoutofexcavation&Allowonly
minimumRequired numberofpersonstoworkatthesame
time
9.Excavatedlooseearthshouldbekeptfromthehalfdepthof
theexcavatedpittoavoidtheoverloadingonthesidewall.
Foundation
CastingDuringhandlingof
concreteWorkmen,
Masons,
Helpers
1.MSDSisbriefedtotheworkedwithdosanddonts.
2.Engageexperiencepersononthejob.
3.UseofRubberHandgloves,gumboots,Nosemask&
GogglesduringGroutingwork.
Builtupbeam
shiftingfromFabricationyard
tositebynew
generation
Hydracrane&
tailor.
Duringshifting&
Unloadingatsite
Riggers,
khalasi&
Helpers
1.Allnecessarycheckingaboutthefitnessofthevehiclestobe
conductedbeforestartingofoperation.
2.Alltheliftingtools&tacklesmustbetestedandcertified,
3.Tagropeshouldbeusedforanyliftingloads.
4.Nobodyshouldworkundersuspendedloadatany
circumstances.
5.Materialsshallbeproperlysecuredonthevehicle.
6.Thewholehandlingoperationwillbecarriedoutunder
authorized/competentsupervisor.
-
7/31/2019 4-construction-work-procedure-for-foundation-load-test-13-09-11.pdf
20/41
QualityAssurancePlan
Constructionwork
procedure
for FOOTING
LOAD
TEST
7.Duringpositioning&placementofloadcareshouldbe
takentoavoidinjuriesduetopressinbetween.
8.Materialsshouldnotbeoverloaded.
9.Correctriggingpracticemustbefollowed.
10.UseofnewgenerationHydracrane&VehicleafterinspectionofSafety&P&M.
Handling&
Erectionof
Builtupbeam
andHydraulic
jack&Plashing
Rough/wronghandling
ofmaterials,fallofmen
&materials,Crash/hit
withobjects,collapse
duetooverload/poor
fabrication,Failureof
liftingtools,tackles&
FailureofHydraulicJack.
Riggers,
Workmen,
Operator&
Helpers
1.Thematerialstransportingwithvehicleshouldbeproperly
tightened.
2.Workmenhandlingthematerialsshouldbewearhand
Gloves.
3.Nomanshouldbestandunderthehangingmaterials.
4.Slings,WireRopes,LiftingTacklesetc.mustbecheckedas
pernormsbeforeuse.
5.RegularToolBoxTalk&adequatesupervisionshouldbe
ensured.
6.Jacksandhydraulicconnectionsshouldbeleakproofand
regularlychecked
by
P&M.The
jack
factor
of
safety
2:1
on
materialyield.Thejackbeingthreadedramwithlocknut,itisa
safe&jerkfreeequipmenti.e.during,theloadingthejackshall
behydraulicallypressurizedandmechanicallylocked.
7.Oilleakagefromjackshouldbeprevented.
8.TrainedOperatorshouldoperatethepressurepump.
9.HydraulicequipmentmusthaveBypassvalve.
-
7/31/2019 4-construction-work-procedure-for-foundation-load-test-13-09-11.pdf
21/41
QualityAssurancePlan
Constructionwork
procedure
for FOOTING
LOAD
TEST
10.Nopersonshouldstandinthelineofjack
11.AllLiftinggearstobeinspectedannuallybythirdParty
competentPerson.
12.Liftinggearstobeinspectedbeforeuse.
13.Properaccesstobeprovidedtothetop.
14.PlyboardtobeplacedonbothsideoftheJack.
15.Anytiltingeffectshallbeguidedbyallfoursupportblocks
attheendofsecondarybeamsduringinitialslackremovalor
loadingactivity.Duringloading,thestrandsofrockanchor
whicharefixedtothecrossbeamswillbeundertensionandit
preventscrossbeamsfromtilting.
-
7/31/2019 4-construction-work-procedure-for-foundation-load-test-13-09-11.pdf
22/41
QualityAssurancePlan
Constructionwork
procedure
for FOOTING
LOAD
TEST
MatrixforRiskAssessment:
SEVERITY
1 2 3 4 5
L
I
K
E
L
I
H
O
O
D
1
2 LOW
3 MEDIUM
4
5
HIGH
-
7/31/2019 4-construction-work-procedure-for-foundation-load-test-13-09-11.pdf
23/41
QualityAssurancePlan
Constructionworkprocedurefor FOOTINGLOADTEST
15.TRAINING&EDUCATION:a. DailysafetypeptalkshallbegivenbyConstructionManagertothestaffandworkmen.
b. Beforecommencementofthework,ConstructionWorkProcedureshallbeexplainedtothe
staffs.
16.FORMATS&CHECKLIST:(Annexed)Sl.
no.
Format/CheckListno. Format/Checklistdescription
Safety System
1 Vehicle&EarthMovingEquipmentInspectionChecklist
2 HouseKeepingInspectionChecklist
3 HydraulicRigInspectionChecklist
4 BarricadingBoardShifting&FixingInspectionChecklist&ClearancePermit
5 CraneInspectionChecklist
6 ExcavationClearancePermit
7 Tools&TacklesInspectionChecklist
8 LiftingPlan
QualitySystem
9 ChecklistBeforeHomingOfRockAnchors
10 RockAnchorGroutingReport
11 ChecklistforPCCforconcretestructures
12 ConcretePourCard
-
7/31/2019 4-construction-work-procedure-for-foundation-load-test-13-09-11.pdf
24/41
QualityAssurancePlan
Constructionworkprocedurefor FOOTINGLOADTEST
VEHICLE&EARTHMOVINGEQUIPMENTINSPECTIONCHECKLIST
NameofProject: Make/Model :
JobNo. : Assetcode(Ifapplicable) :
InspectedBy : Ownedby :
Date :
Sl.No. Points Observation Measures
1 Enginecondition
2 Clutch/ brake/Handbrake
3 HydraulicSystem
4 Guards/Covers/Doors
5 Fastenerlockpins/Keys
6 Horn/Reversehorn/Lights
7 Indicators/WiperBlades
8 Operatorsfitness
9 Tyrepressure/TyreCondition10 ConditionofBatteryandLamps
11 Operatinglevers/steering
12 Gauges&warningdevices
13 Fireextinguisherprovided
14 RearSideMirror
15 SeatBelt
16
TriangularRetroReflectors4nos.
(Frontside02,Rearside02)
17 Chockblocks(min02nos.)
18 DelayStartMechanism
19 ValidityofPUCCertificate
20 ValidityofFitnessCertificate
-
7/31/2019 4-construction-work-procedure-for-foundation-load-test-13-09-11.pdf
25/41
QualityAssurancePlan
Constructionworkprocedurefor FOOTINGLOADTEST
HOUSEKEEPINGINSPECTION
CHECKLIST
NameofProject :
JobNo. :
InspectedBy :
Date :Sl.
No.Points Observation Measures
STRUCTURALFABRICATION
/ERECTION
SITE
1 Walkways,passageskeptclearofmaterials?
2Area & roads kept clear for manoeuvring of cranes and material handling
equipment?
3Scrap, cutpieces, welding electrode stubs, handtools kept tidy in workplace and
disposedsuitably?
4 Scrapbinavailableinadequatenumber?
5Welding cables, power cables routed properly to avoid runover by vehicle or
trippinghazards?
6 Compressedgashosesroutedproperly?
7 Atleast1metreonbothsidesofgantryrailsiskeptclearofmaterial?
8 Floorkeptclearofwater,oilspillage/accumulation?
CIVILWORKAREA
1 Allapproach,aisle,ingress/egresstoandfromworkarea,excavatedpits,ramps,
walkwayskeptclearofdebris,toolsetc?
2 Scaffolding materials (Hbeam, HD tower frames, bracing, clamps) shuttering
boards
etc.
are
stacked
properly
at
site?
3 Stackingofbricks,hollowblocksaredoneinsafemanner?
4 Nailsremovedfromwoodenplanks/timberandnotprotrudingout?
5 Saw dust, wood chips & scrap wood cleared from carpentry shop and disposed
suitably?
6 Debrisfromdemolitionandexcavatedearthclearedfromworkplaceandaccess?
Sl.
No.Points Observation Measures
ELECTRICALINSTALLATIONS&BOOTHS
1 ApproachtoDB,Panels,Switcheskeptclear?
2 Fireextinguishersinstalledatlocationswheretheyareeasilyaccessible?
3 Weldingcablesandpowercablesareroutedseparately?
4 Routingofcablesaredoneproperlytoavoidobstruction&trippinghazards?
5 Floorofelectricalboothskeptdry?
-
7/31/2019 4-construction-work-procedure-for-foundation-load-test-13-09-11.pdf
26/41
QualityAssurancePlan
Constructionworkprocedurefor FOOTINGLOADTEST
Sl.
No.Points Observation Measures
collectiontraystosafeguardagainstaccidentalleakage?
8Storingareaforliftingtools&tackles,ropes,wireropes&PPEisdry,clean&free
ofcorrosivematerial?
9 Easyaccessibilitytoinstalledfireextinguishersensuredinstore?
GENERAL
1 Separatescrapyardallocatedfortheproject?
2Approach to workstations, offices, time offices, stores, P&M are well laid and
demarcated?
3 Roadsarekeptclearofstackedmaterialforfree&safevehicularmovement?
4 Heavymaterialsstackingaretakencareoftopreventslips,collapseandrolling?
5 ForhousekeepingatelevatedworkplacesrefertoIM09A2.
-
7/31/2019 4-construction-work-procedure-for-foundation-load-test-13-09-11.pdf
27/41
QualityAssurancePlan
Constructionworkprocedurefor FOOTINGLOADTEST
HYDRAULICRIG
INSPECTION
CHECKLIST
AreaInspected :
InspectedBy :
Date :
Sl.No. Activities Observation Measures
01 IsRigplacedinalevelledsurface?
02 Tripodshavingproperstrength&goodcondition
03 Aretripodshavingproperbaseplates&stopper?
04IsDshackleengagedintripodshavinggood
condition
05 TripodsshouldbeconnectedwithHTnuts&bolts
06 Conditionoftheropeguideandpulleyintripods
07Laddersareweldedwithpropermaterialsand
spacingshallbemaintained300mm
08 Rotatingpartofthemachinesisguardedproperly.
09Batteryterminalsareenclosedfromwater
compounds.
10 Exhaust&emissionisundercontrol
11 Isanyspillageinmachine/otheraccessories
12 Conditionofwireropeused13 Conditionoftheradiator.
14 IsPUCavailableinrigs?
15 Anyotherrelevantinformation
SignatureofSiteEHSPersonal
-
7/31/2019 4-construction-work-procedure-for-foundation-load-test-13-09-11.pdf
28/41
QualityAssurancePlan
Constructionworkprocedurefor FOOTINGLOADTEST
CONFIRMATORYBOREHOLES&TRAILPITSAREA
BARRICATIONBOARDSHIFTING&FIXINGINSPECTIONCHECKLIST&CLEARANCEPERMIT
Area/Location : Date:_______________
Natureofthejobtobedone:Sl.
No.PointsareChecked Done
Not
Reqd.
1 Workplaceinspectedpriortostartofwork?
2 ScreeningandElearningforallpersonsmustbeensuredbeforecommencementofthejob.
3 Alltheworkershavebeenexplainedsafeworkprocedures?
4Useofsafetyhelmets,Shoes,FlorescentJacket,andotherrelevantPPEsensuredforall
workers.
5 Barricadingboardshiftarrangementsarechecked?
6 Anyobstructioninthebarricadingboard?
7WorkplaceBarricadesweresecuredbyproperNailingwith600mmlength&20dia.Also
securedby70kgconcreteblockforstrengtheningtheboards(Counterweight).
8 AreallBarricadingboardsconnectedbynutbolt?
9 AreallbarricadingboardsShouldbekeptinastraightlineforpublic&vehicleconvenience?
10Areallapproach,access/egresstoandfromworkarea,excavatedpitswalkwayskeptclear
ofloosematerial,flammablematerial,debrisetc.?
11AreTrafficsafetydevicesshouldbeproperlykeptfrom15mtsbufferzoneandadvance
warningzonewasaligned20mtsfromworkingzones?
12Flagmanmustbedeputedatsitewithfluorescentjacket,redflag,whistle&redlightbaton
forday&nighttimeswithotherrelevantPPEs.
13Barricadingboardkeptwithblinkers&monitoringboardsshallbeindicatedbyreflected
tape.
14Areamustbeidentified&securedbyputtingtrafficcones,barriersforshiftingthematerials
safely.
15 Adequateilluminationoughttobeensuredatnightshift.
16 Useofmachineries&VehicleafterinspectionofSafety&P&M.
Note:TheapplicabilityofthispermitforBoreHoles&TrailpitsareaBarricadingboardshifting&fixingworks.Tobefilledinandcertifiedbypersonbeforestartingthejob.Aftercheckingalltheaboveprecautionstheworkcanbecarriedoutintheabovearea.
SignatureofSiteInchargeEngineer SignatureofEHSO/SiteEHSPersonal
-
7/31/2019 4-construction-work-procedure-for-foundation-load-test-13-09-11.pdf
29/41
QualityAssurancePlan
Constructionworkprocedurefor FOOTINGLOADTEST
CRANEINSPECTION
CHECKLIST
NameofProject :
Sl.No. Points Observation Measures
1 HookandHookLatch
2 OverHoistLimitSwitch
3 BoomLimitSwitch
4 BoomAngleindicator
5 BoomLimitcutoffswitch6 Overloadlimitswitch
7 Conditionofboom
8 ConditionofRopes
9 No.ofloadlines
10 Sizeandconditionofthesling
11 Stabilityofcrane
12 SoilCondition
13 SwingBrake&Lock14 PropelBrake&Lock
15 HoistBrake&Lock
16 BoomBrake&Lock
17 SwingAlarm
18 Mainclutch
19 Leakageinhydrauliccylinders
20 Outriggersfullyextendible
21
Tyrepressure
22 ConditionofBatteryandLamps
23 Guardsofmovingandrotatingparts
24 Loadchartprovided
25 Numbers,positionandsizeofpendantropes
26 Reversehorn&Rearviewmirror
27 ValidityofCertificationbycompetentauthority
28 OperatorsFitness
29 FireExtinguisherinoperatorscabin
30 CautionBoards
31 ValidityofPUCcertificate(fortyremounted)
32 ValidityofFitnesscertificate(fortyremounted)
-
7/31/2019 4-construction-work-procedure-for-foundation-load-test-13-09-11.pdf
30/41
QualityAssurancePlan
Constructionworkprocedurefor FOOTINGLOADTEST
EXCAVATIONCLEARANCE
PERMIT
(Inrespectto(i)Existenceofservicelinesandutilities(ii)Intheproximityofexistingstructures,buildings,foundations,installationslikegas,electricalservicestationsetc. (iii)Anyotherconditionswhichmayresultinserioushazardousconsequences.)
Pleasepermitthefollowingexcavationjobaspersketchenclosed:
Detailsofexcavation:Lengthm Width.m Depth.m
Location: Performing Agency:
Permitvalidfrom(Date):to.....ExecutionIncharge
Tel.No.: Name:
Date: Designation: Signature:
Proj/Mfg/Maint/TS/ES
I ELECTRICAL:
1. Detailsofundergroundcablepresentintheareatobeexcavated..
2. Electricalisolationofthefollowingrequired...
Date: Name&Designation: Signature:
IIINSTRUMENTS:
1. Detailsofundergroundcablepresentintheareatobeexcavated....
2. Precautionstobeobservedforsafeexcavationjob...
Date: Name&Designation: Signature:
IIICOMPUTERSERVICES:
1. Detailsofundergroundcablepresentintheareatobeexcavated....
2. Precautiontobeobservedforsafeexcavationjob....
Date: Name&Designation: Signature:
IVENGINEERINGSERVICES:
1.Descriptionofundergroundfacilitiesexistingattheproposedlocation....
2.Precautiontobeobservedforsafeexcavationjob....
Date: Name&Designation: Signature:
V.FIRE&SAFETY:
1. Provide: Crossover....Barricades... Road
Blocks...Shoring....Others..
2. Usefollowingsafetyequipment:GasMasks...Eye Protection..
WoodenHandledTools....Others..
3. Providefollowing:ApproachfortheFire/EmergencyTenders/Roadclosureboards/Other
Precautions...
Date: Name&Designation: Signature:
Remarksifany..
TheAboveMentionJobCanCommence.....
Date: Name&Designation: Signature:
ISSUINGAUTHORITY
-
7/31/2019 4-construction-work-procedure-for-foundation-load-test-13-09-11.pdf
31/41
QualityAssurancePlan
Constructionworkprocedurefor FOOTINGLOADTEST
TOOL&
TACKLES
INSPECTION
CHECKLIST
NameofProject :
JobNo. :
AreaInspected :
InspectedBy :
Date :
SlNo Particulars Observation Measures
LiftingTool&Tackles1 Slings/WireRopes
1.1 Isanydefectonslings/wirerope?
1.2 ConditionofEyeusedinsling/wire
rope?
1.3 Sufficientnumberof Uclampsused
asperdia.1.4 Areanyidentificationcode/markson
theslings/wirerope?
2 D/Bowshackle
2.1 IsSWLidentifiedontheshackle?
2.2 Areanyidentificationcode/markson
theShackles?
2.3 Openingwidthofshacklesareok
2.4 SeatingconditionofShacklepin
2.5 Anydefectsareobservedonthepin?
3 UBolts&EyeBolts
3.1 ConditionofU/Eyeboltused
3.2 Anycracks/wearwerefound
3.3 Tapperofeyeboltisfreefromrust.
3.4 ShapeofU/Eyeboltisregular
4 Hooks&ChainPulleyBlock
4.1 Isanydeformationontheeyeportion?
4.2 Isanycrack/wearwerefound?
4.3 Conditionofhooklatch
Electrical/AutomotiveTool&Tackles1 Spanners&Screwdrivers
1.1 ConditionofSpanners/Screwdrivers
-
7/31/2019 4-construction-work-procedure-for-foundation-load-test-13-09-11.pdf
32/41
QualityAssurancePlan
Constructionworkprocedurefor FOOTINGLOADTEST
3.1 Conditionofthecrimperused3.2 Conditionoftheinsulation
3.3 Conditionofgripers
3.4 Isanycrackonthecrimpers
4 GrindingMachine
4.1 ConditionofGrindingmachine
4.2 Iswheelguardprovidedproperly
4.3 Wheelhavingavalidexpirydate
4.4 Isearthinggivenproperly?4.5 Conditionofthecableconnected
5 DrillingMachine
5.1 ConditionofDrillingmachine
5.2 IsDrillbitfittedproperly
5.3 Useofpropertighteningkey
5.4 Isearthinggivenproperly?
5.5 Conditionofthecableconnected
Testers1 EarthleakageCircuitBreakerTester
1.1 Ispolarityshowingonthemeteris
good
1.2 Accuracyofthemeterisacceptable
1.3 Iscalibrationrequired
2 SurfaceResistanceTester
2.1 Ispolarityshowingonthemeteris
good2.2 Accuracyofthemeterisacceptable
2.3 Iscalibrationrequired
AnyotherrelevantInformation1
2
-
7/31/2019 4-construction-work-procedure-for-foundation-load-test-13-09-11.pdf
33/41
QualityAssurancePlan
Constructionworkprocedurefor FOOTINGLOADTEST
LIFTINGPLAN
Site/location FootingLoadTestbetweenNAGOLEtoUPPAL
Appointed Person carrying out
theAssessment:DateofAssessment:
Descriptionoflift:ErectionofMainBeam&secondarybeams,forFootingloadtestkentledgearrangement.
DetailsofLoads LoadPosition1 LoadPosition2 LoadPosition3
Weight:
Dimensions:
PositionofCofG:
Heightoflift(worstcase
Max.radius(worstcase
Dateoflift:
Timeoflift:
Monetaryvalueofload:
DetailsofCranes 1st 2nd 3rd
Make&model:
Capacity:
Jiblength:
Outriggerspread:Outriggerload:
Max.groundbearing
Counterweight:
Weightofcrane:
GroundConditions(Visualassessment)
Access/Egressforcrane&
transport:
Liftingposition:
LiftingAccessories
Slings(wirerope): Slings(webbing):
Slings(chains): Shackles:
-
7/31/2019 4-construction-work-procedure-for-foundation-load-test-13-09-11.pdf
34/41
CHECKLISTFORINSPECTIONBEFOREHOMINGOFROCKANCHORS
Project :
Client :IndependentEngineer :
Concessionaire :
Contractor :
AnchorIdentification: Date:
Sl.
No:
Description
CheckedNot
ApplicableRemarks
Yes No
1 Depthofdrilledhole
2 Casingpipeinstalled
3 Dia.ofeachAnchor
4 FreeLengthofAnchor
5 FixedLengthofAnchor
6 Burstingrebarspiralprovided
7Epoxycoatoneachanchorfixed/free
Length
8 FreeLengthHDPEPipefixed
9 GroutventfixedatFixedend
10 Safeaccessprovidedtoworkplace
-
7/31/2019 4-construction-work-procedure-for-foundation-load-test-13-09-11.pdf
35/41
ROCKANCHORGROUTINGREPORTFIXEDLENGTH/FREELENGTH
Project :
Client :
IndependentEngineer :
Concessionaire :
Contractor :
AnchorLocation: DateofInspection:
AnchorNumber: CableNo:
DateofAnchorInstallation:
Typeofcement:
Week&YearofCementManufacture:
Admixtureifadded/mixdetails:
W/CRatios:
Temperature: Water:
Equipment:T9DDGP 150 GroutMixer: Groutpump:
HoleDiameter: CableDiameter: CableLength:
VolumeofGrout: Regrouting:
PreGroutingChecks:
FreeofBlockage: Inlet: Yes/No Outlet: Yes/No
LeakageObserved: Vents: Yes/No Yes/No
GroutingRecord:
Cable/AnchorNumber StartTime FinishTime GroutPressure Remarks/Observation
L&T INFRA IC L&TMRHL
-
7/31/2019 4-construction-work-procedure-for-foundation-load-test-13-09-11.pdf
36/41
STRESSINGREPORTProject :
Client :
IndependentEngineer :
Concessionaire :
Contractor :
LOCATION: DATE:
RFINumber GAIdentification:
Cube
strength:
STRESSINGEQUIPMENT
Typeofjack:MONORamareaofJack(sq.cm)
JackSerialnumber:
Hydraulicpump:PumpNumber
StressingRecord:
PressureappliedKg/sq.cm ELONGATIONINSTRESSBARANCHORNUMBERS Remarks
1 2 3 4 5
Loadequivalent tons
000
050
50100
100160
NETELONGATION
FORMAT FOR FOOTING LOAD TEST RECORD
-
7/31/2019 4-construction-work-procedure-for-foundation-load-test-13-09-11.pdf
37/41
FORMATFORFOOTINGLOADTESTRECORD
Project :
Client :
IndependentEngineer :
Concessionaire :Contractor :
LOCATION: Date:
1 Depth/R.L.ofPit:
2 SizeofFooting:
3 Dia.ofeachAnchor
4 SensitivityofDialGauge:
5
a) SensitivityofPressureGauge:
b)
Pressuregauge
calibration
valid
upto
:
c) Pressuregaugenumber:
6a) DiameterofRamofhydraulicjack:
b) Jacktestedagainstloadcell:
7
RelationshipbetweenPressureGaugereadingandLoadonPlate
1Kg/Sq.cmonPressureGauge= (TonnesonFooting)
8 Typeoftest:
9 Typeofstrata:
Remarks:
-
7/31/2019 4-construction-work-procedure-for-foundation-load-test-13-09-11.pdf
38/41
FORMATFORFOOTINGLOADTESTREADINGSProject :
Client :
IndependentEngineer :
Concessionaire
:
Contractor :
FOOTINGLOADTESTLOCATION:
Date
Pressure
Gauge
Reading
Loadin
MT
Time
(Min.)
DialGauge1 DialGauge2 DialGauge3 DialGauge4 Average
Settlement
(mm)
Rate
mm/minRemarks
Reading Settlement Reading Settlement Reading Settlement Reading Settlement
CONCRETEPOURCARD
-
7/31/2019 4-construction-work-procedure-for-foundation-load-test-13-09-11.pdf
39/41
Project :
Client :
IndependentEngineer :
Concessionaire :
Contractor
:
PROJECT : DATE :
AREA : POURNO. :
LOCATION : REF.DRAWING:
MIXGRADE: QUANTITY :
BEFORE
CONCRETING
ACTIVITY DESCRIPTIONCHECKED
YES NO N/A
a) PCCTopLevel
b) Centrelineschecked
REINFORCEMENT
a) Dia&Shape
b)
ExtraReinforcement apartfromDrawingc) ExtraLaps
d) No.ofChairs&Length
e) Binding/welding
f) CovertoReinforcement
g) BatchCertificate&
TestCertificate
FORMWORK
a) centerlines
b) Shuttering line,Level&Plumb
c) Shutteroilapplied
d) Watertightness
e) Concretetoplevel
f) Supportsadequacy
EMBEDEDITEMS
a) BOLTS
c) INSERTS
ETING
CHECK OBSERVATION
RETECHCK
CHECK OBSERVATIONa) Weather
b) CementBatchNo. SUPPORTSTIGHTNESS
c) Mixgrade LEAKAGES
e) Slump TOPCOVER
-
7/31/2019 4-construction-work-procedure-for-foundation-load-test-13-09-11.pdf
40/41
Annexure - A
-
7/31/2019 4-construction-work-procedure-for-foundation-load-test-13-09-11.pdf
41/41
Annexure - D