    3b. LEVELLING

    Errors, Corrections & Contour

    1

  • 7/27/2019 3b. BEC 102 Levelling-Correction & Contour

    2/36

    OUTLINE (Previous chapter:3a)

    Levelling When do we level?

    Definitions/Terminology

    Levelling Instrumentation

    Method of Levelling

    Rules for Levelling

    Levelling Procedures (Two peg test, reducing levels

    using rise and fall method)

    2

  • 7/27/2019 3b. BEC 102 Levelling-Correction & Contour

    3/36

    OUTLINE (Now...)

    Misclosure for Reduce Levels (Rise & Fall) Correction or Adjusting the Misclosure

    Errors in Levelling

    3

  • 7/27/2019 3b. BEC 102 Levelling-Correction & Contour

    4/36

    Levelling procedures & errors

    Two-peg test(Determining for collimation errors)

    4

  • 7/27/2019 3b. BEC 102 Levelling-Correction & Contour

    5/36

    Error on reducing levels (Rise and Fall)

    Back Inter Fore Rise Fall RL Comment

    1.32 50.00 BM A

    2.56 3.98 2.66 47.34 CP 1

    1.25 1.31 48.65 Kerb3.65 2.40 46.25 Post

    3.49 0.67 2.98 49.23 CP 2

    2.58 0.91 50.14 Kerb

    2.64 1.54 1.04 51.18 CP 3

    3.79 1.15 50.03 BM A

    10.01 9.98 6.24 6.21

    (0.03) (0.03) (0.03) 5

  • 7/27/2019 3b. BEC 102 Levelling-Correction & Contour

    6/36

    An acceptable misclose (error)?

    Misclose=the amount by which the measuredheight

    difference (Hmeas) differs from the known height difference

    derived from the RLs of the starting and finishing

    benchmarks (Hknown)

    Smallmisclosures in closed level loops are expected

    because of the accumulation of errors

    If the misclosure is small, it can be adjusted

    If the misclosure is large, the loop (or part of it) must

    be repeated6

  • 7/27/2019 3b. BEC 102 Levelling-Correction & Contour

    7/36

    Adjusting the misclose

    Adjustment is carried out to ensure that themeasured and known RLs of the closing benchmark

    agree

    The misclosure is linearly distributed according to the

    number ofset-ups

    The adjustment per set-up for the previous example

    is (0.03/4)...

    7

  • 7/27/2019 3b. BEC 102 Levelling-Correction & Contour

    8/36

    Adjusting the Errors

    0.03/4

    8

  • 7/27/2019 3b. BEC 102 Levelling-Correction & Contour

    9/36

    Adjusting the misclose

    Measured RL Point Adjustment Adjusted RL

    50.00 BM A

    47.34 CP 1

    48.65 Kerb

    46.25 Post

    49.23 CP 2

    50.14 Kerb

    51.18 CP 3

    50.03 BM A9

  • 7/27/2019 3b. BEC 102 Levelling-Correction & Contour

    10/36

    Adjusting the misclose

    Measured RL Point Adjustment Adjusted RL

    50.00 BM A 0.000 50.000

    47.34 CP 1 0.008 (0.0075) 47.332

    48.65 Kerb

    46.25 Post

    49.23 CP 2

    50.14 Kerb

    51.18 CP 3

    50.03 BM A

    =1*(0.03/4)

    10

  • 7/27/2019 3b. BEC 102 Levelling-Correction & Contour

    11/36

    Adjusting the misclose

    Measured RL Point Adjustment Adjusted RL

    50.00 BM A 0.000 50.000

    47.34 CP 1 0.008 47.332

    48.65 Kerb 0.015 48.635

    46.25 Post 0.015 46.235

    49.23 CP 2 0.015 49.215

    50.14 Kerb

    51.18 CP 3

    50.03 BM A

    =2*(0.03/4)

    11

  • 7/27/2019 3b. BEC 102 Levelling-Correction & Contour

    12/36

    Adjusting the misclose

    Measured RL Point Adjustment Adjusted RL

    50.00 BM A 0.000 50.000

    47.34 CP 1 0.008 47.332

    48.65 Kerb 0.015 48.635

    46.25 Post 0.015 46.235

    49.23 CP 2 0.015 49.215

    50.14 Kerb 0.023 50.117

    51.18 CP 3 0.023 51.157

    50.03 BM A =3*(0.03/4)12

  • 7/27/2019 3b. BEC 102 Levelling-Correction & Contour

    13/36

    Adjusting the misclose

    Measured RL Point Adjustment Adjusted RL

    50.00 BM A 0.000 50.000

    47.34 CP 1 0.008 47.332

    48.65 Kerb 0.015 48.635

    46.25 Post 0.015 46.235

    49.23 CP 2 0.015 49.215

    50.14 Kerb 0.023

    51.18 CP 3 0.023

    50.03 BM A 0.030 50.000

    =4*(0.03/4)

    13

  • 7/27/2019 3b. BEC 102 Levelling-Correction & Contour

    14/36

    Adjusting the misclose

    Measured RL Point Adjustment Adjusted RL

    50.00 BM A 0.000 50.000

    47.34 CP 1 0.008 47.332

    48.65 Kerb 0.015 48.635

    46.25 Post 0.015 46.235

    49.23 CP 2 0.015 49.215

    50.14 Kerb 0.023 50.117

    51.18 CP 3 0.023 51.157

    50.03 BM A 0.030 50.00014

  • 7/27/2019 3b. BEC 102 Levelling-Correction & Contour

    15/36

    Errors in levelling

    Equipment Error Field Error

    Reading and Booking

    15

  • 7/27/2019 3b. BEC 102 Levelling-Correction & Contour

    16/36

    Errors in the Equipment

    Collimation Error - Line of sight not horizontal

    Correctreading

    Actual/observed

    reading

    Two-peg test(Determining for collimation errors)

    16

  • 7/27/2019 3b. BEC 102 Levelling-Correction & Contour

    17/36

    Errors in the Equipment

    Collimation Error - Line of sight not horizontal

    Correct

    reading

    Actual/observed

    reading

    Size of error depends onsight length

    17

  • 7/27/2019 3b. BEC 102 Levelling-Correction & Contour

    18/36

    Errors in the Equipment

    Collimation Error - Line of sight not horizontal

    Keep sight lengths from each instrument position the same

    Check collimation error using Two-Peg Test

    Parallax

    Focus eyepiece on cross-hairs, then focus telescope on staff

    Check prism is not stuck (every reading)

    18

  • 7/27/2019 3b. BEC 102 Levelling-Correction & Contour

    19/36

    Errors in the Equipment

    Staff Errors

    Zero error - base may be worn - doesnt matter as long assame staff is always used

    May not be extended properly

    Tripod Errors

    Must be stable

    19

  • 7/27/2019 3b. BEC 102 Levelling-Correction & Contour

    20/36

    Field Errors

    Staff not vertical

    Use pond bubble on staff

    Rock staff and take minimum reading

    Unstable equipment

    Watch out for soft ground under tripod or staff

    Dont touch (or kick!) tripod

    20

  • 7/27/2019 3b. BEC 102 Levelling-Correction & Contour

    21/36

    Reading and Booking Errors

    Keep sightings short to estimate mm on staff accurately

    Double check all readingsWrite clearly

    WeatherWind causes level to vibrate, heat causes shimmer

    Carry out calculation checks

    21

  • 7/27/2019 3b. BEC 102 Levelling-Correction & Contour

    22/36

    Applications of levelling

    Point heights (relative to a datum) Height differences (independent of datum)

    Longitudinal sections and cross sections

    Data for volume calculations

    Contouring

    Setting out

    22

  • 7/27/2019 3b. BEC 102 Levelling-Correction & Contour

    23/36

    Establishing a new point

    Benchmark

    New point

    RLBM

    Datum

    RLNEW

    23

  • 7/27/2019 3b. BEC 102 Levelling-Correction & Contour

    24/36

    Measuring height differences

    Benchmark

    RLBM

    Datum

    H1

    H2

    H3

    24

  • 7/27/2019 3b. BEC 102 Levelling-Correction & Contour

    25/36

    Profiles and cross-sections

    RLBM

    Benchmark

    Datum25

  • 7/27/2019 3b. BEC 102 Levelling-Correction & Contour

    26/36

    Contour Map

    40m

    50m

    60m

    26

  • 7/27/2019 3b. BEC 102 Levelling-Correction & Contour

    27/36

    What is Contour?

    Imaginary line on the ground joining point of equalaltitude or elevation.

    Contour line shown on maps or plans as a line.

    Contour line mostly used for indicate the elevation

    directly.

    27

  • 7/27/2019 3b. BEC 102 Levelling-Correction & Contour

    28/36

    What is Contour?

    5

    10

    15

    20

    25

    5

    1015

    20 25

    ContourInterval: 5 m

    28

  • 7/27/2019 3b. BEC 102 Levelling-Correction & Contour

    29/36

    USES OF CONTOUR MAP Alignment of a highway or railway line.

    For selecting the most suitable site variousengineering projects.

    Determination of the capacity of the reservoir area.

    Quantities of earth work can be computed byselecting suitable sections.

    Location of various strategic points which are veryimportant in military operations.

    29

    METHODS OF LOCATING

  • 7/27/2019 3b. BEC 102 Levelling-Correction & Contour

    30/36

    METHODS OF LOCATING

    CONTOURS

    DIRECT METHOD

    INDIRECT METHOD

    Squares or Gridding Method

    Radial Method

    30

  • 7/27/2019 3b. BEC 102 Levelling-Correction & Contour

    31/36

    INTERPOLATION OF CONTOURS

    Arithmetical Calculation

    By Graphical Method

    31

  • 7/27/2019 3b. BEC 102 Levelling-Correction & Contour

    32/36

    1.100

    2.9052.510

    A

    B C

    Plotting contours (Arithmetical

    Calculation)

    The RLs for points A, B and C have beendetermined by levelling. We are now

    required to determine the location of thecontours using a 0.5 m contour interval.

    32

  • 7/27/2019 3b. BEC 102 Levelling-Correction & Contour

    33/36

    Plotting contours

    LINE ABHAB = 2.51 - 1.10 = 1.410DAB = 10 m

    1.100

    2.510

    A

    B

    A

    B

    1.41

    10 m

    1.4

    9.93

    For the 2.5 m contour :

    D = 10*(2.5 - 1.1)/1.41 = 9.93

    0.9

    6.38

    For the 2.0 m contour :

    D = 10*(2.0 - 1.1)/1.41 = 6.38

    0.4

    2.84

    For the 1.5 m contour:

    D = 10*(1.5 1.1)/1.41 = 2.84

    33

  • 7/27/2019 3b. BEC 102 Levelling-Correction & Contour

    34/36

    Plotting contours

    LINE BCDH

    BC= 2.905 - 2.510 = 0.395

    DBC = 10 m

    no contours cross this line

    1.100

    2.9052.510

    A

    B C

    34

  • 7/27/2019 3b. BEC 102 Levelling-Correction & Contour

    35/36

    1.100

    2.9052.510

    A

    B C

    Plotting contours

    35