3 drilled shafts for slope stabilization geohazards-2010 final

60
Slope Stabilization using Drilled Shafts: Design and Long-Term Monitoring Jamal Nusairat, Ph.D., P.E. E.L. Robinson Engineering of Ohio Co. & Izzaldin Almohd, Ph.D., P.E. Huesker Synthetic GmbH 8/4/2010

Upload: sahsimpson

Post on 07-Mar-2015

102 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

Slope Stabilization using Drilled Shafts: Design and

Long-Term Monitoring

Jamal Nusairat, Ph.D., P.E.E.L. Robinson Engineering of Ohio Co.

&Izzaldin Almohd, Ph.D., P.E.

Huesker Synthetic GmbH

8/4/2010

Page 2: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

Presentation Outlines

IntroductionGeotechnical Analysis Structural Design Instrumentation & Long-Term Monitoring Summary and Conclusions

Page 3: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

Introduction

1. Slope remediation using drilled shafts

2. Single row of drilled shafts Inexpensive

Various techniques and equipments

Has been successfully used

Simple to design

Page 4: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

Geotechnical Elementso Geometryo FS improvemento Shaft forceo Soil Arching

Page 5: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

Analysis Methodology

Define Geometry Define Stratigraphy and Material Properties Initial Slope Stability Analysis (no stabilization)

Determine the need and location of stabilization Elements

Assume Shafts diameter, length, and spacing Verify/modify assumed shaft parameters

Verify Shaft Structural adequacy (Lateral Analysis)

Page 6: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

Stability Analysis: Limiting Equilibrium(Method of Slices)

W

Potential Slip Surface

in

Slice i - 1Slice iSlice i + 1 Pile

Vi-2Vi-1Vi-1ViVi? ??

Hi-2

HiHi-1

WW

Ni-1

Si-1/FSSi/FS

NiNi+1

Si+1/FS

Page 7: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

Soil Arching

Direction of Moving Soil

S

S

S

Arching Load

1

3

2

Arching MechanismLiang and Zeng (2002)

ODOT Research Report: Drilled Shaft Foundations for Noise Barrier Walls and Slope Stabilization (2002)

Page 8: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

UA Slope Program to

Design Landslides using Drilled Shafts

Page 9: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

Initial Slope Stability

Page 10: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

Slope Stability W/ Drilled Shafts

Page 11: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final
Page 12: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final
Page 13: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

1.00

1.20

1.40

1.60

1.80

2.00

2.20

2.40

2.60

2.80

3.00

0 10 20 30 40 50 60 70 80 90 100 110 120Offset (ft)

Safe

ty F

acto

r

0

50

100

150

200

250

300

350

400

Shaf

t For

ce (K

ip)

FS; S/D = 2FS; S/D = 3Shaft Force (Kip); S/D = 2Shaft Force (Kip); S/D = 3

Page 14: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

Lateral Analysis Results Assumed Shaft diameter, Reinforcement, and

concrete strength. Defined loads from Slope Stability Analysis (UA

Slope, FEM…) Run Lateral Analysis (L-Pile, COM624, FB-Multi

Pier, FEM… )

Results Deflection Moment Shear verify/modify section

Page 15: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

Perform Lateral AnalysisVerify assumed diameter, spacing, and

length of shaft

Page 16: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

Moment Shear

Page 17: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

Z

Slip Surface

Lateral Deflection

Design Shear = 1.69×Vmax

Design Moment = 1.69×Mmax

D

NetShaftF

2 NetShaft

uFPZ

Structural Design of Drilled Shaft

Page 18: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

39’ 02”

#6@12 in

#6@12 in

#6@12 in

X X

D = 60 in

3 in cover

#6@12 in

36#11

X - X

Page 19: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

Field Instrumentation and Monitoring

JEF-152-1.3

WAS-7-47.9

MRG-376-1.1

HAM-275-7.02

Page 20: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

Projects Design Summary

Site D(ft)

S/D(ft/ft)

Lp(ft)

Lr(ft)

Fshaft(kips)

# of

Shafts

Offset(ft)

JEF-152-1.30 3.5 2 45 20 100 42 40

WAS-7-47.90 4 2, 3 40 10 200 128 90

MRG-376-1.1 4 2 40 18 165 23 20

HAM-275-7.02 4 2 55 15 165 54 180

Page 21: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

JEFF – 152-1.3

Page 22: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

56+00 57+00 55+00

40 ft

Lateral Load Test Shafts

The two instrumented drilled shafts (#20 & #21

S.R. 152

3. 5 ft-Diameter Drilled Shafts

42 Drilled Shafts; S/D = 2 on centers

Work Limits

PZ-1

INC#4 Sliding Zone Limits

PZ-2

PZ-3

INC#3 Shaft #1

Shaft #42

250 ft

CL S. R. 152

TOR

Offset = 40 ft PZ: Piezometers INC: Inclinometer

PZ-1 (20 ft)

PZ-2 (22 ft)

PZ-3 (23 ft)

INC#3

INC#4

INC#1 & #2

25 ft

20 ft

A single row of 42 Drilled Shafts:

(D = 3. 5 ft; S/D = 2 on centers)

Water Table Existing Slip Surface

160 ft

Instrumentation Plans/Slope Section

Page 23: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

Instrumentation/Shafts

Page 24: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

JEF-152-1.30Shaft Properties

D (ft) Reinforc. Moment capacity (k-f)

Loadkips

Max Deflection (in)

3.5 26 #11 2,824 102 3.2

Max. Deflection: LPILE AnalysisLoad : UA Slope Analysis

Page 25: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

Drilled Shafts DeflectionSH#20 SH#21

Page 26: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

Moments in Shaft #20 and Shaft #21 Moment in SH#20 Moment in SH#21

Max. Moment Observed = 950 ft-kipsNominal Moment Capacity = 2,824 ft-kips

A factor of 2.97

Page 27: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

WAS – 7-47.9

Page 28: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

Shaft Properties

D (ft) Reinforc. Moment capacity (k-f)

Loadkips

Max Deflection (in)

4.0 32 #14 4,918 63 2.6

Max. Deflection: LPILE AnalysisLoad : UA Slope Analysis

Page 29: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

Soil MovementUp-Slope Down-SlopeIn-between

Page 30: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

Drilled Shafts DeflectionSH#53 SH#54

Page 31: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

Moments in Shaft #20 and Shaft #21 Moment in SH#53 Moment in SH#54

Max. Moment Observed = 225 ft-kipsNominal Moment Capacity = 4,918 ft-kips

The factor is very high

Page 32: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

HAM-275-7.02

Page 33: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

HAM-275-7.02

Page 34: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

HAM-275-7.02

Page 35: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

HAM-275-7.02

Page 36: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

HAM-275-7.02

Page 37: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

HAM-275-7.02

Page 38: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

ERI-60-0227 over Vermillion River

Page 39: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

ERI-60-0227 over Vermillion River

Page 40: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

PIER 1PIER 3 PIER 4

RIVER

PIER 2

VERMILION

RIVER

ELEVATION

PLAN

203' 254' 254' 230' 190'

60 Overmilion River

ERI-60-0227 over Vermillion River

Page 41: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

ERI-60-0227 over Vermillion River

Page 42: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

Section Through Drilled

STEEL CASING

INCLINOMETER TUBE

18-HP12x5310-HP12x53

12'-0" DIAMETERDRILLED SHAFT

18 BARS

(TYPICAL)

ERI-60-0227 over Vermillion River

Page 43: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

ERI-60-0227 over Vermillion River

Page 44: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

ERI-60-0227 over Vermillion River

Page 45: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

ERI-60-0227 over Vermillion River

Page 46: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

ERI-60-0227 over Vermillion River

Page 47: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

ERI-60-0227 over Vermillion River

Page 48: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

The deflection at the top of drilled shaft pier #2

Deflection, in-1.2-1.0-0.8-0.6-0.4-0.20.0

The

num

ber o

f ten

sion

ed a

ncho

rs

0

1

2

3

4

5

6

7

8

FEMMeas.

ERI-60-0227 over Vermillion River

Page 49: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

ERI-60-0227 over Vermillion River

Page 50: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

ERI-60-0227 over Vermillion River

Page 51: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

ERI-60-0227 over Vermillion River

Page 52: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

CUY-90-15.24

Page 53: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

Site Condition Prior to Construction

CUY-90-15.24

Page 54: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

St bilit E l ti d Sli f

F.S.=1.25

F.S.=1.1

CUY-90-15.24

Page 55: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

CUY-90-15.24

Page 56: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

CUY-90-15.24

Page 57: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

CUY-90-15.24

Page 58: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final
Page 59: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

Summary and Conclusions The use of drilled shafts to stabilize slopes

demonstrated to be an effective method

The design process is an optimization of the drilled shaft size, spacing, location along the slip plane, and length

The factor of safety was enhanced in all the cases

The calculated shaft deflection is always more than the field measured deflection

Page 60: 3 Drilled Shafts for Slope Stabilization GeoHazards-2010 Final

Thank You

QUESTIONS?