HIGH VOLTAGE 6,6 KV MOTORS MEGGER TEST PROCEDURE PAGE 1 of 3
IT IS EXTREMELY IMPORTANT OF FOLLOWING CORRECT PROCEDURES WHILE
WORKING WITH HIGH VOLTAGE. AN ERROR WOULD MOST PROBABLY BE FATAL
WORKING ON A HIGH VOLTAGE SWITCHBOARD. LIKE ALL THE OTHER WORKS WITH
HIGH VOLTAGE, TWO PERSONS ARE ALWAYS REQUIRED, WITH AT LEAST ONE
ELECTRICIAN WITH A HIGH VOLTAGE TRAINING COURSE.
1. BEFORE MEGGER TEST OF AN HV MOTOR IS CONTACTED, SWITCH FROM ABB TERMINAL
REMOTE CONTROL TO LOCAL [L LED TO BE ON] TO PREVENT REMOTE OPERATION.
2. PULL OUT THE CONTACTOR IN TEST POSITION: TO DO IT SIMULTANEOUSLY TURN
COUNTER-CLOCKWISE TO UN-LATCH AND PULL OUT THE TRUCK
TO WITHDRAWN POSITION, ON ABB TERMINAL SHOWS [TEST POS] PICTURE 1.
3. ROTATE THE DOOR KNOB HORIZONTALLY TO MAKE THE EARTH SWITCH TO BE ENGAGED
WITH THE GROUND, NOT NECESSARY TO OPEN THE DOOR PICTURE 2.
![Page 2: 2d Hv Motors Megger Test Procedure 3](https://reader030.vdocuments.mx/reader030/viewer/2022013111/55cf9d28550346d033ac79e7/html5/thumbnails/2.jpg)
PAGE 2 of 3
4. LOCK THE GROUND INTERLOCK KEY ON THE BREAKER, REMOVE THE KEY FROM THE SLOT
AND KEEP IT INSIDE YOUR POCKET PICTURE 3.
5. REMOVE CONNECTION BOX COVER OF THE MOTOR TO BE TESTED. REMEMBER AS A RULE
HIGH VOLTAGE EQUIPMENT SHOULD BE CONSIDERED ALIVE UNTIL TO
ESTABLISH VISIBLE EARTH OF THE WORK PLACE. DO A VOLTAGE TEST WITH
THE HIGH VOLTAGE TESTER. REMEMBER TO DO A FUNCTION TEST OF THE
TESTER BOTH TIMES BEFORE AND AFTER THE ACTUAL TEST.
CONNECT MEGGER TESTER TERMINALS ONE ON THE SHIP’S METALLIC STRUCTURE
AND THE OTHER TO ONE PHASE L1 PICTURE 4.
6. GO BACK TO MAIN SWITCHBOARD AND DO THE ABOVE STEPS REVERSELY. INSERT THE KEY
AND UN-LOCK, TURN THE DOOR KNOB TO ORIGINAL POSITION [VERTICALLY] AND FINALLY
PUSH BACK THE TRUCK IN NORMAL POSITION.
MOTOR WILL BE UN-GROUNDED AND PHASE IS READY FOR MEGGER TESTING PICTURE 5.
![Page 3: 2d Hv Motors Megger Test Procedure 3](https://reader030.vdocuments.mx/reader030/viewer/2022013111/55cf9d28550346d033ac79e7/html5/thumbnails/3.jpg)
PAGE 3 of 3
7. REMEMBER AS A RULE AFTER DISCONNECTION OF THE EARTH APPARATUS THE
CONNECTIONS SHOULD BE NOW CONSIDERED “ALIVE” SINCE THEY ARE NO LONGER
GROUNDED. KEEP A SAFE DISTANCE FROM THOSE TERMINALS AS A PRECAUTION.
TAKE MEGGER TEST READING FROM THE CONNECTED PHASE L1 ONLY PICTURE 6.
8. REPEAT STEPS FROM [3 – 8] TO MEGGER TEST THE SECOND PHASE L2 AND SO ON.
IMPORTANT REMARKS:
THE FOLLOWING LISTED MOTORS MEGGER TEST PROCEDURE IS SAME AND SHOULD BE
CARRY ON STEP BY STEP AS DESCRIBED ABOVE STEPS [1-8].
1. NO 1 BALLAST PUMP MOTOR
2. NO 2 BALLAST PUMP MOTOR
3. NO 3 BALLAST PUMP MOTOR
4. NO 1 HD CARGO COMPRESSOR MOTOR
5. NO 2 HD CARGO COMPRESSOR MOTOR
THE FOLLOWING TWO MOTORS HAVE THREE BREAKERS AND MEGGER TEST
PROCEDURE SHOULD BE DONE IN THE SAME WAY AS ABOVE. INSTEAD OF ONE ALL THREE
BREAKERS MAIN, BY PASS AND STAR TO BE GROUNDED AND UN-GROUNDED BEFORE
INSULATION READING IS TAKEN.
1. BOW THRUSTER MOTOR
2. SPRAY PUMP MOTOR
THIS IS NOT AN OFFICIAL DOCUMENT THEREFORE EVALUATE ACCORDING
TO YOUR KNOWLEDGE AND EXPERIENCE. IF IT IS NECESSARY TO TAKE MORE
PRECAUTIONS THEN DO IT……………………………………………………………..
………………………NEVER GET CLOSE TO HIGH VOLTAGE………………………
.
CHIEF ENGINEER
GEORGE VRETAKOS