Container Transport Management A Case Study – Perth, Western Australia Bob Peters 1. BACKGROUND The containerisation of freight being shipped around the world has grown rapidly for many years. In the case of Perth it has grown rapidly to about 450,000 Twenty Foot Equivalent Units (TEUs) per annum moving through its port of Fremantle. The task continues to grow at about 10% per annum. The port of Fremantle’s container terminal is situated in the heart of the City of Fremantle, a place that is rapidly becoming a very fashionable and desirable place to live. (Demographics changing dramatically. Place being gentrified.) There is capacity within the port for the container terminal to grow until it reaches its capacity of about 1.2 million TEUs per year – in about 10 to15 years. However the transporting of the containers to and from Fremantle has, and still is, very contentious. Its management is a classic conundrum for the transport network operator – how to make the transport task happen in a way that is most acceptable to all parties. (i.e. address the tension at the port-community interface) The essence of the task is to contain heavy vehicle impacts in the face of rapidly rising trade through the Port. This brief paper outlines the approach being adopted in Perth. 2. KEY ISSUES The owners of the containers want them moved between Fremantle and their depots as cheaply and quickly as possible. The quickest and cheapest way of moving them is generally by truck. The roads presently being used are not ideal for the task – somewhat congested, not particularly safe and adjacent to many residential areas. Plans for a new road designed to address these deficiencies became politicised and ended up being scrapped because of perceived community impacts. The rail system serving Fremantle was poor and not competitive because of its low volumes and short journey distances. 3. THE PLAN The network operator (the State road and traffic authority)) has played a major role in formulating a plan that is the best compromise between the competing forces. The master plan has six elements, some of which are particularly important to the network operator: 1. Extend a major highway to take some non-container traffic off present roads; 2. Put more freight on rail; 3. Build inland container terminals; 4. Make better use of existing roads; 5. Plan for a new container terminal in a better location; and 6. Improve existing roads. MAIN ROADS Western Australia V:\Program Files\PIARC\www\documentstore\Australia Container Transport Management - 29 Sep 2004 - Bob Peters.doc

Upload: mujims

Post on 29-Sep-2015

212 views

Category:

Documents


0 download

DESCRIPTION

m

TRANSCRIPT

  • Container Transport Management A Case Study Perth, Western Australia Bob Peters 1. BACKGROUND

    The containerisation of freight being shipped around the world has grown rapidly for many years. In the case of Perth it has grown rapidly to about 450,000 Twenty Foot Equivalent Units (TEUs) per annum moving through its port of Fremantle. The task continues to grow at about 10% per annum. The port of Fremantles container terminal is situated in the heart of the City of Fremantle, a place that is rapidly becoming a very fashionable and desirable place to live. (Demographics changing dramatically. Place being gentrified.) There is capacity within the port for the container terminal to grow until it reaches its capacity of about 1.2 million TEUs per year in about 10 to15 years. However the transporting of the containers to and from Fremantle has, and still is, very contentious. Its management is a classic conundrum for the transport network operator how to make the transport task happen in a way that is most acceptable to all parties. (i.e. address the tension at the port-community interface) The essence of the task is to contain heavy vehicle impacts in the face of rapidly rising trade through the Port. This brief paper outlines the approach being adopted in Perth. 2. KEY ISSUES

    The owners of the containers want them moved between Fremantle and their depots as cheaply and quickly as possible. The quickest and cheapest way of moving them is generally by truck. The roads presently being used are not ideal for the task somewhat congested, not particularly safe and adjacent to many residential areas. Plans for a new road designed to address these deficiencies became politicised and ended up being scrapped because of perceived community impacts. The rail system serving Fremantle was poor and not competitive because of its low volumes and short journey distances. 3. THE PLAN

    The network operator (the State road and traffic authority)) has played a major role in formulating a plan that is the best compromise between the competing forces. The master plan has six elements, some of which are particularly important to the network operator: 1. Extend a major highway to take some non-container traffic off present

    roads; 2. Put more freight on rail; 3. Build inland container terminals; 4. Make better use of existing roads; 5. Plan for a new container terminal in a better location; and 6. Improve existing roads. MAIN ROADS Western Australia V:\Program Files\PIARC\www\documentstore\Australia Container Transport Management - 29 Sep 2004 - Bob Peters.doc

  • Each of these actions will provide marginal benefits, but collectively they will provide major benefits. The master plan acknowledges that the existing container terminals throughput will continue to grow but wants its impact on roads to be kept to a minimum. Without change, demand for road space for trucks carrying containers will also increase by at least 10% per year something that is unacceptable. It is expected that the new approach will keep this impact much smaller. So what will each element of the plan do and achieve? 3.1 Extend Major Highway

    This will divert non-container traffic off the roads carrying container traffic. Much of the existing truck traffic on these roads is movement of freight between key industrial areas. 3.2 More Freight on Rail

    A dedicated rail loop and rail/sea intermodal terminal is being constructed at the container terminal. This will lower the cost of moving containers by rail by reducing handling costs and providing for the use of longer trains. The target is to have 30% of containers moved by rail. Presently the figure is 5%. It needs to be noted that most of the containers are moved between industrial areas in Perth and the container terminal a relatively short journey unsuitable to a competitive rail service. The disadvantage is exacerbated by the fact that the road distance is 25 km, while the rail journey is 45 km. 3.3 Build Inland Container Terminals

    Presently the majority of container storage takes place near the container terminal in Fremantle. This results in the movement of empty containers to and from the port by road that would not need to be hauled on these roads if they were stored in the hinterland close to packing/unpacking functions. The building of inland container terminals will result in more of this activity taking place elsewhere, resulting in less empty containers being transported to and from Fremantle. 3.4 Better Use of Roads

    Australia Container Transport Management - 29 Sep 2004 - Bob Peters.doc Page 2

    By international standards trucks servicing the container terminal are already very large able to carry three TEUs and have a gross mass of up to 88 tonne. Surveys have however shown that up to 30% of the capacity of these trucks is not used. Efforts are being made to better utilise these trucks. In particular, an opportunity exists for container terminal operators at the Port to make use of commercial levers such as their charging policy to encourage less empty truck movements (i.e. full truck in, full truck out) and total utilisation of truck capacity. In addition the network operator is looking into the possibility of permitting slightly larger trucks those able to carry 4 TEUs, as is the case in Mexico and in limited areas at ports around Australia. As well as this the network operator is working with others to see what opportunities there are for trucks to operate at times outside the present dominant envelope of 7am to 7pm Monday to Friday. This will alleviate some road pressure but it does raise issues of truck noise in urban MAIN ROADS Western Australia

  • areas at nighttime. 3.5 Plan for New Container Port

    Within the next 10-15 years, it is likely that the existing port will reach capacity in terms of terminal facilities and community tolerance. An overflow port will be required to handle ongoing growth. As a consequence planning is taking place to build a new container port south of Fremantle in a location that has excellent transport links road, rail and sea. 3.6 Improve Existing Roads

    As truck movements will continue to grow on existing roads albeit more slowly than would otherwise be the case, efforts to make the existing roads more acceptable are being made. These efforts include treatments such as demonstration noise walls, anti skid treatments, the provision of bus bays to improve traffic flow, the provision of better traffic signals to improve safety and improved traffic signal coordination. As by way of example the main road used by the container carrying trucks has 27 sets of traffic signals. It is also the case that it is the only direct link from the major industrial area and the international airport to the Port. The traffic signals are coordinated using the SCATS system, but further refinements are being made to try and improve service levels for the container carrying trucks. VMS is also being considered with the view to providing road users with advice on travel times and optimum travel speeds in order to minimise journey stress and time. In addition major infrastructure changes are being proposed for key intersections converting them from at grade intersections to grade separations. Innovative at grade solutions such as proposed in Mexico (crossing on coming traffic before the intersection) have also been investigated, but dismissed due to their large land area requirements. 4. CONCLUSION

    The network operator has a key role to play in improving transport operations. In many places this largely revolves around car issues but as has been demonstrated it can also involve freight. The successful road network operator needs to be able to engage with freight - as well as people, other transport modes, the community and key stakeholders in developing Wide Network Operation solutions that are the best compromise between competing interests.

    MAIN ROADS Western Australia Australia Container Transport Management - 29 Sep 2004 - Bob Peters.doc

    Page 3

    A Case Study Perth, Western Australia 1. BACKGROUND 2. KEY ISSUES 3. THE PLAN 3.1 Extend Major Highway 3.2 More Freight on Rail 3.3 Build Inland Container Terminals 3.4 Better Use of Roads 3.5 Plan for New Container Port 3.6 Improve Existing Roads 4. CONCLUSION