20project audit and closure (2)
DESCRIPTION
Project MangementTRANSCRIPT
2
Closing Processes
To approve and accept the project deliverables, close the contracts and accounts, report the work and save the
information. To review and discuss the final
work, document lessons learned and release the Project Team.
End of the Project.
3
Closing Process Group
Planning
Executing
Controlling
Close Project – finalizing all activities across all of the project management process groups to formally close the project or a project phase.
Contract Closure – completing and settling each contract, including the resolution
of any open items, and closing each contract applicable to the project or a project phase.
4
Project Closure
Conditions for Closure
Normal
Premature
Perpetual
Failed Project
Changed Priority
Close-out Plan: Questions to be Asked
What tasks are required to close the project?
Who will be responsible for these tasks?
When will closure begin and end?
How will the project be delivered?
5
Project Closure Checklist
Project Name: Prepared by: Date: Customer has accepted all project results: Accepted by: 1 2 3 4 5 6
Customer has accepted all other deliverables: Accepted by: 1 2 3 4 5 6
Customer has accepted from delivering organization all other project requirements: Accepted by: 1 Staff evaluations 2 Budget reports 3 Lessons learned 4 Other 5
Explain any exceptions to the above: Documentation for the above has been filed/archived as follows:
Comments or remaining issues:
Checklist submitted by: Name/Title: Signature: Date: Name/Title: Signature: Date:
6
Ending a Contract or Project Ending a contract: Successful completion – goods and services have been delivered in accordance with the
contract specifications. Collective agreement – mutual consent termination of the contract. Breach of contract – one of the parties is not complying with the terms and specifications
of the contract. Work to be done during contract closure: Product verification Financial closure Updating records in the records management system Final contract performance reporting Contract file Procurement audit Formal acceptance and closure
Ending a project: Contract closure occurs first. All contracts should be closed out before the project is closed out. At the end of the contract, the project manager performs a procurement audit for each contract, administratively closes out the contract, and then administratively closes out the project when the whole project is completed.
8
Project Termination Areas
Closeout MtgPlans
Personnel
Organization
PayablesReceivables
Budget Report
Financial
ContractsSupplier CommFinal Payments
Purchasing
Close FacilitiesDispose Equip/Mat'l
Site
Project Closeout
9
Lessons Learned
Keep a knowledge base for future projects:
• What were the successes and failures of the project?
• What could be improved?
• How to save the information for future estimates?
Celebrate the closure of the project!
10
Documenting Lessons Learned
Conduct a review meeting to address four critical questions:
What was done right?
What went wrong?
What improvements can be made in the future?
How, whom, and when to disseminate the knowledge?
Archive the lessons learned in the knowledge database.
11
Purposes of Evaluation - Goals of Project Audit
Four independent dimensions of success:
The project’s efficiency in meeting both the budget and schedule
The most complex, is that of customer impact/satisfaction
Impact on business/direct success i.e. translate the achievement of the
project’s goals into a contribution to the parent organization’s goals
The last dimension, somewhat more difficult and imprecise to ascertain, is
future potential
Chapter 12-2
12
Types of Project Audits
In-process project audits Allow for corrective changes if conditions have changed
and for concentration on project progress and performance.
Postproject audits Take a broader and longer-term view of the project’s role
in the organization and emphasize improving the management of future projects.
13
Project Audit Components
A review of why the project was selected.
A reassessment of the project’s role in the organization’s priorities.
A check on the organizational culture to ensure it facilitates the type of project being implemented.
An assessment of how well the project team is functioning and was it appropriately staffed.
A check on external factors that might change where the project is heading or its importance.
A review of all factors relevant to the project and to managing future projects.
14
Project Audit-during the project
1. Evaluate if the project delivered the expected benefits to all stakeholders.
• Is the project managed well? Is the customer satisfied?
2. Assess what is being done wrong and what contributed to successes.
3. Identify changes to improve the delivery of future tasks/projects.
15
Evaluation – Benefits of Project Audit
A successful project evaluation via audit can help an organization to: Identify problems earlier
Clarify performance, cost, and time relationships
Improve project performance
Locate opportunities for future technological advances
Evaluate the quality of project management
Reduce costs
16
Characteristic of Project Auditor/Evaluator
No direct involvement or direct interest in the project.
First and foremost, the auditor should “tell the truth”
Respect (perceived as impartial and fair) of senior management and other project stakeholders
The auditor must approach the audit in an objective and ethical manner
Must assume responsibility for what is included and excluded from consideration in the report
The auditor/evaluator must maintain political and technical independence during the audit and treat all materials as confidential
Perceived as having the best interests of the organization in making decisions.
Broad-based experience in the organization or industry
17
Project Auditor/Evaluator Responsibilities
Assemble a small team of experienced experts
Familiarize the team with the requirements of the project
Audit the project on site
After the completion, debrief the project’s management
Produce a written report according to a specified format
Distribute the report to the project manager and project team for their response
Follow up to see if the recommendations have been implemented
Chapter 12-17
18
The Project Audit Life Cycle
Like the project itself, the audit has a life cycle composed of an orderly progression of well-defined events:
Project audit initiation
Project baseline definition
Establishing an audit database
Preliminary analysis of the project
Audit report preparation
Project audit termination
19
Data Collection and Analysis
Organization View: Was the organizational culture supportive and correct?
Was senior management’s support adequate?
Did the project accomplish its intended purpose?
Were risks appropriately identified and assessed?
Were the right people and talents assigned?
Have staff been fairly reassigned to new projects?
What does evaluation from contractors suggest?
Were the project start-up and hand-off successful?
Is the customer satisfied?
20
Data Collection and Analysis
Project Team View: Were the project planning and control systems appropriate for this type
of project? Should all similar projects use these systems? Did the project conform to plan for budget and schedule? Were interfaces with stakeholders effective? Have staff been fairly assigned to new projects? Did the team have adequate resources? Were there resource conflicts? Was the team managed well? What does evaluation from contractors suggest?
21
Activities in Closeout Stage
Plan, schedule and monitor completion activities Obtain and approve termination plans
Prepare and co-ordinate termination plans
Plan for reassignment of project team members and assign resources to other projects
Monitor termination activities and complete all contractual agreements
Monitor disposition of all excess material, transfer customer assets etc
22
Factors Influencing Audit Depth and Detail
Organization size
Project importance
Project type
Project risk
Project size
Project problems
23
Project Performance Evaluation: Team
Are standards and goals for measuring performance clear, challenging,
and attainable? Lead to positive consequences?
Are responsibilities and performance standards known by all team
members?
Are team rewards adequate? Management believes teams are important?
Is there a career path for successful project managers?
Does the team have discretionary authority to manage short-term
difficulties?
Is there a high level of trust within the organization culture?
Are there criteria beyond time, cost, and specifications?
25
Project Performance Evaluation: Individual
Responsibility for assessing performance:
Functional and weak matrix organization: The functional
manager may solicit the project manager’s opinion of the
individual’s performance on a specific project.
Balanced matrix organization: The project manager and the
area manager jointly evaluate an individual’s performance.
Strong matrix and projectized organizations: The project
manager is responsible for appraising individual performance.
26
Project Performance Evaluation: Individual
Multirater appraisal or the “360-degree feedback:
Involves soliciting feedback concerning team members’
performance from all the people their work affects.
This includes project managers, area managers, peers,
subordinates, and even customers.
27
Conducting Performance Reviews
Begin by asking the individual to evaluate his or her own performance.
Avoid drawing comparisons with other team members; rather, assess
the individual in terms of established standards and expectations.
Focus criticism on specific behaviors rather than on the individual
personally.
Be consistent and fair in your treatment of all team members.
Treat the review as one point in an ongoing process.
28
Implementing Closedown
1. Getting delivery acceptance from the customer 2. Shutting down resources and releasing to new
uses 3. Reassigning project team members 4. Closing accounts and seeing all bills are paid 5. Evaluating the project team, project team
members, and the project manager
29
How to Terminate a Project
Extinction: Stop the project immediately
Integration: Project results are integrated into the existing organizational units
Addition: Project is institutionalized as a new part of the organization (new product line or new division)
Starvation: Gradually reduce resources so that project dies slowly but surely (it fades out of sight)
31
Project Final Report
History of the project: Usually written by PM
It should address: project performance
administrative performance
organizational structure
confidential assessment of team members
project management techniques
33
33
Results Analysis
Planned / Expected Results
Differences / Deltas from Planned / Expected Results
35
35
Effort Estimate Analysis
Task Est. Hours
Act. Hours
Diff - Hours
Diff - % Explanation of Variance
Project Total
41
(Post) Project Audit
Executive Summary
Introduction
Project Review Project Objectives
Method or approach
Effectiveness of Planning
Effectiveness of project management
Effectiveness of technical solution
Project deliverables Description
Assessment against requirements
42
Project Audit Quality
Standards used Measurement Assessment against requirements
Schedule Delays
Reasons Recovery Method followed
Assessment against plan
Finances Problems
Reasons Recovery Method followed
Assessment against Plan
43
Project Audit
Resource Utilisation
Effectiveness
Problems
Reasons
Recovery Method followed
Lessons Learned
Individual Team-Member Assessment and recommendations
(confidential reports)
Recommendations
44
Checklist
Close-out Plan
Verify Scope Contractual obligations
Administrative obligations
WBS (tasks and deliverables)
Customer acceptance of deliverables
Document and archive files
Document lessons Learned
Reassign Resources
Notify all stake holders for project completion
Celebrate……
45
Reporting Audit Report Content Outline
Classification of project
Project type
Size
Staffing
Technology level
Strategic or support
Analysis of information gathered
Project mission and objectives
Procedures and systems used
Organization resources used
Recommendations
Corrective actions
Lessons learned
Reminders
Appendix
Backup data
Summary booklet
46
Last word…
When one hears of a disastrous slip in project,
imagines that a series of major calamities must
have befallen it. Usually, however, the disaster is
due to termites, not tornadoes…the schedule
slips one day at a time
Frederick P Brooks The Mythical Man-Month Essays
on Software Engineering