2021 Capital Improvements Plan
Topics
• Introduction• Plan Highlights• Financial Summary• Capital Projects Summary• Financing • Next Steps
Introduction to Draft CIP
Plan is required by commission policy ID ATT-2:
Plan Highlights
1. Increase in annual expenditures2. More projects funded by cash reserves3. Decrease in connection charge revenue4. Proposing to increase annual cash
transfer from operating fund 5. No increase in debt transfer rate from
2020 CIP
Annual Expenditures
$36
$20
$15
$9 $8
$23$25
$41
$19
$29 $30
$19
$27
$0
$10
$20
$30
$40
$50
2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026
Mill
ions
Actual Expenditures Budgeted or Proposed Expenditures
Number of Projects in CIP
0
5
10
15
20
25
30
35
40
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021
Importance of cash reserves
1. Fund construction in progress until loan disbursements received from Clean Water Fund
2. Unplanned expenses or projects3. Fund small or ineligible projects4. Lessen reliance on debt
District FundsConnection
charges (6%)
Direct transfer
(4%)
Clean Water Fund loan (90%)
Operating Fund Capital
Fund
Interest (<1%)
Debt ServiceFundService
charges
$2.4 M
< $0.1 M
$33.6 M
Cash spending in 2021
Project 2021 Spending
Metrogro Applicators & Equipment $0.9 M
CMMS Replacement $1.3 M
Pump Station 17 Relief Force Main – Phase 1 $2.8 M
Total $5.0 M
Connection Charge Projection
$0.0
$1.0
$2.0
$3.0
$4.0
$5.0
$6.020
05
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
Mill
ions
Historical Connection Charges 2020 Budget Projection
2021 CIP Projection
Transfer from Operating Fund to Capital Fund
Year
2020 Capital Budget (Actuals through
2019)
Proposed 2021 Capital
Improvements Plan Difference 2016 $0
2017 172,000
2018 0
2019 1,200,000
2020 915,000
2021 961,000 $1,486,000 $525,000
2022 1,009,000 2,001,000 992,000
2023 1,059,000 2,506,000 1,447,000
2024 1,112,000 3,021,000 1,909,000
2025 1,168,000 3,542,000 2,374,000
2026 1,226,000 4,040,000 2,814,000
2021-2026 Total $6,535,000 $16,596,000 $10,061,000
End-of-Year Capital Reserves
$0
$2
$4
$6
$8
$10
$12
$14
$16
2020 2021 2022 2023 2024 2025 2026
End
of Y
ear C
ash
Bala
nce
Mill
ions
Base Alt 1 Alt 2 Minimum Balance
Total Six-Year Expenditures (2021-2026)
2020 CIP = $151.2M 2021 CIP = $164.8M
NSWWTP , 53%
Interceptors , 30%
Pump Stations,
15%
Capital Expenses ,
2%
NSWWTP , 39%
Interceptors , 37%
Pump Stations,
23%
Capital Expenses ,
1%
Liquid Processing Improvements –Phase 1 • Total Project Budget: $16.8M• 2021 Spending: $7.7M• Estimated Construction
Amount: $13.5M• Currently under construction• Contractor: CD Smith• Estimated Completion:
Spring 2021
Resource Recovery Facility
• Total Project Budget: $899,000• 2021 Spending: $309,000• Study in 2020 by Black &
Veatch/MSA
Metrogro Applicators
• Total Project Budget: $4.1 M• 2021 Spending: $896,000• Four planned purchases from
2021 to 2024
Operations Building First Floor Remodel
• Total Project Budget: $2.4M
• 2021 Spending: $1.5M• Bid in summer 2020• Estimated Completion:
Fall 2021
Interceptor Projects
NSVI Improvements, $4.8M (2020-2021)
NEI – Truax Lining, $6.0M (2022)
Capacity or relocationConditionNew growthRedundancy
Project driver
WI – Shorewood Relief, $14.6M (2021-2023)
PS 6 to PS 10 Connector, $7.1M (2024) NEI Joint Grouting ($0.3 M (2021)
NEI – Waunakee Ext, $7.1M (2023-2024)
Northeast Interceptor Lining, $2.1M (2023)
LBMC – Phase 5, $4.3M (2024)
NSVI Capacity Relief (Phase 1), $13.2M (2027)
NSVI Improvements –McKee Road to Dunn’s Marsh
• Total Project Budget: $4.8M• 2021 Spending: $4.4M• Bid in fall 2020• Estimated Completion: Fall/winter
2021
Dunn’s Marsh
McKee Rd
Capital City TrailBa
dger
Sta
te T
rail
Interceptor to be replaced
Existing Interceptor
Manhole
West Interceptor (Shorewood Relief)
• Total Project Budget: $14.6M• 2021 Spending: $7.1M• To be built in three phases from
2021 to 2023
Pump Station 6 to Pump Station 10 Connector
• Total Project Budget: $7.1M• Coordinate with City of Madison street reconstruction project• 2024 construction
Pump Station & Force Main Projects
Pump Station 14 Rehab, $5.9M (2020-21)
PS 17 FM Relief – Ph 1, $3.2M (2020-21)PS 17 FM Relief – Ph 2, $4.3M (2023)PS 17 Rehab, $5.2M (2023)
CapacityCondition
Project driver
Pump Station 13 Rehab, $6.1M (2020-21)
PS 4 Rehab, $5.3M (2022-2023)
Grass Lake Dike Stabilization, $0.9M (2021)
PS 16 FM Rehab, $1.7M (2023)
Pump Station 13 & Pump Station 14 Rehabilitation• Total Project Budget:
$12.0 M• 2021 Spending: $10.8 M• Estimated Construction
Amount: $10.1 M• Bid August 2020• Estimated Completion: Fall
2021
PS 17 Projects
ProjectTotal
BudgetConst.Year
PS 17 FM-Ph 1 $3.3 M 2021
PS 17 Rehab $5.2 M 2023
PS 17 FM-Ph 2 $4.3 M 2023
Lower Badger Mill Creek Interceptor
$4.3 M 2024
Badger Mill Creek Phosphorus Compliance
• Total Project Budget: $1.5 M• 2021 Spending: $206,000• Status report: 2021• Prelim compliance plan: 2022• Final compliance plan: 2023• Final plans & specs: 2025• Achieve compliance: 2028
Debt Service
-2000000
0
2000000
4000000
6000000
8000000
10000000
12000000
14000000
$0
$5,000,000
$10,000,000
$15,000,000
$20,000,000
$25,000,000
$30,000,000
$35,000,000
$40,000,000
$45,000,000
$50,000,000
1997 1999 2001 2003 2005 2007 2009 2011 2013 2015 2017 2019 2021 2023 2025 2027
Debt
Ser
vice
Fun
d
Debt
Ser
vice
Use of Stabilization
Historical Debt Service Requirement
Projected Debt Service Requirement - 2021 CIP
Historical Debt Service from Service Charges
Potential Debt Service from Service Charges - 2021 CIP
EOY Debt Reserve Balance
Service Charge Impacts
Year
Operating Fund Support for the Capital Program (From Service
Charges)Increase Over Prior
Year
Implied Percentage Increase in Service
Charge Revenue Over Prior Year
2016 $12,909,000 $1,066,000 4%
2017 13,856,000 947,000 3%
2018 14,505,000 649,000 2%
2019 16,358,000 1,853,000 5%
2020 16,755,000 397,000 1%
2021 18,038,000 1,283,000 3%
2022 19,298,000 1,260,000 3%
2023 20,582,000 1,283,000 3%
2024 21,910,000 1,328,000 3%
2025 24,667,000 1,371,000 3%
2026 $24,667,371 $1,386,000 3%
Summary/Alternatives
• Increased spending in 2021• Uncertain revenue streams due to COVID-19
pandemic• Proposing increased transfers from operating
fund to mitigate uncertainty• Alternatives
– Reduce debt transfer rate for 2021– Reduce amount of direct transfer from operating
fund
Next Steps
• 2021 Draft CIP and business cases available on District websitehttp://www.madsewer.org/Planning/Budget-Finance
• Acceptance of 2021 Draft CIP at July 16 meeting
• Comments/questions:• Todd Gebert – [email protected]• Bill Walker – [email protected]
Questions?
Thank you!
2020 Connection Charge Revenue
$2.8
$1.7
0.0
0.5
1.0
1.5
2.0
2.5
3.0
Jan Feb Mar Apr May June July Aug Sep Oct Nov Dec
Mill
ions
202020195-Year Average2020 Budget Target2020 Revised Budget Target
District FundsConnection
charges (7%)
Direct transfer
(2%)
Clean Water Fund loan (91%)
Operating Fund Capital
Fund
Interest (<1%)
Debt ServiceFundService
charges
Interceptor Construction by Decade
0.52.3 1.2
5.7
27.624.3
3.3
10.28.4
5.11.60.8
1.2
0.8
1.4
0.4
1.0
0
5
10
15
20
25
30
35
1910 1920 1930 1940 1950 1960 1970 1980 1990 2000 2010
Mile
s of I
nter
cept
or In
stal
led
Lined Interceptors - 7.2 miles
Unlined Interceptors -88.8 miles
Cash Reserves
$-
$5
$10
$15
$20
$25
$30
$35
$40
$45
2018 2019 2020 2021 2022 2023 2024 2025
Mill
ions
Contribution from Operating Fund Connection charges Loan RevenueExpenditures EOY Cash Balance Cash balance minimum
Introduction to Draft CIP
• Plan is required by commission policy ID ATT-2• Six-year planning window• Provides estimates of actual and future cash
flows and debt service• Draft CIP presented in early summer• Capital Budget approved in fall• Actual spending only authorized for budget
year
Lagoon Dikes Improvements
• Total Project Budget: $2.1M• 2021 Spending: $299,000• Study/design: 2020-2021• Repairs: 2022-2024
Grass Lake Dike Stabilization
• Total Project Budget: $864,000
• 2021 Spending: $659,000• Bid late 2020• Estimated Completion:
Fall 2021