![Page 1: 2019 Annual Meeting Ashland Superfund Site€¦ · Superfund Project Superfund Program - started 1980 Ashland Superfund Record of Decision (ROD) issued September, 2010. The ROD explained](https://reader033.vdocuments.mx/reader033/viewer/2022043010/5fa0efbe561c3117cd78f58f/html5/thumbnails/1.jpg)
2019
Annual Meeting
Ashland Superfund Site
Brian Hinrichs, Client Team Leader
Foth Infrastructure & Environment
![Page 2: 2019 Annual Meeting Ashland Superfund Site€¦ · Superfund Project Superfund Program - started 1980 Ashland Superfund Record of Decision (ROD) issued September, 2010. The ROD explained](https://reader033.vdocuments.mx/reader033/viewer/2022043010/5fa0efbe561c3117cd78f58f/html5/thumbnails/2.jpg)
Site Location
![Page 3: 2019 Annual Meeting Ashland Superfund Site€¦ · Superfund Project Superfund Program - started 1980 Ashland Superfund Record of Decision (ROD) issued September, 2010. The ROD explained](https://reader033.vdocuments.mx/reader033/viewer/2022043010/5fa0efbe561c3117cd78f58f/html5/thumbnails/3.jpg)
Project Team
Baird.
![Page 4: 2019 Annual Meeting Ashland Superfund Site€¦ · Superfund Project Superfund Program - started 1980 Ashland Superfund Record of Decision (ROD) issued September, 2010. The ROD explained](https://reader033.vdocuments.mx/reader033/viewer/2022043010/5fa0efbe561c3117cd78f58f/html5/thumbnails/4.jpg)
![Page 5: 2019 Annual Meeting Ashland Superfund Site€¦ · Superfund Project Superfund Program - started 1980 Ashland Superfund Record of Decision (ROD) issued September, 2010. The ROD explained](https://reader033.vdocuments.mx/reader033/viewer/2022043010/5fa0efbe561c3117cd78f58f/html5/thumbnails/5.jpg)
Ashland Gas Works History
62 Years of Gas Production
![Page 6: 2019 Annual Meeting Ashland Superfund Site€¦ · Superfund Project Superfund Program - started 1980 Ashland Superfund Record of Decision (ROD) issued September, 2010. The ROD explained](https://reader033.vdocuments.mx/reader033/viewer/2022043010/5fa0efbe561c3117cd78f58f/html5/thumbnails/6.jpg)
Superfund Project
◆ Superfund Program - started 1980
◆Ashland Superfund Record of Decision (ROD) issued September, 2010.
◆The ROD explained which cleanup alternatives to be used at the site.
![Page 7: 2019 Annual Meeting Ashland Superfund Site€¦ · Superfund Project Superfund Program - started 1980 Ashland Superfund Record of Decision (ROD) issued September, 2010. The ROD explained](https://reader033.vdocuments.mx/reader033/viewer/2022043010/5fa0efbe561c3117cd78f58f/html5/thumbnails/7.jpg)
2013-14 2015
On-ShoreSoil Cleanup
Wet DredgePilot Project
Hydraulic Dredge
Sediment Removal
2016 2017 2018
BreakwaterBuild
MechanicalDredge
SedimentRemoval
2010
Record ofDecision
(ROD) Issued
Final Kreher Park Restoration –
Return to Community for Redevelopment
2019
Project Cost
Project Timeline
![Page 8: 2019 Annual Meeting Ashland Superfund Site€¦ · Superfund Project Superfund Program - started 1980 Ashland Superfund Record of Decision (ROD) issued September, 2010. The ROD explained](https://reader033.vdocuments.mx/reader033/viewer/2022043010/5fa0efbe561c3117cd78f58f/html5/thumbnails/8.jpg)
Summary of Work
❖ Design/Build Project
Building Demolitions, Slurry Wall,
Bulkhead Wall,
Soil Excavation, Soil Treatment
Groundwater Extraction
Water Treatment Plant
Contaminated Sediment Cleanup
![Page 9: 2019 Annual Meeting Ashland Superfund Site€¦ · Superfund Project Superfund Program - started 1980 Ashland Superfund Record of Decision (ROD) issued September, 2010. The ROD explained](https://reader033.vdocuments.mx/reader033/viewer/2022043010/5fa0efbe561c3117cd78f58f/html5/thumbnails/9.jpg)
Multi-Year - Two Phases
Phase 1Phase 2
![Page 10: 2019 Annual Meeting Ashland Superfund Site€¦ · Superfund Project Superfund Program - started 1980 Ashland Superfund Record of Decision (ROD) issued September, 2010. The ROD explained](https://reader033.vdocuments.mx/reader033/viewer/2022043010/5fa0efbe561c3117cd78f58f/html5/thumbnails/10.jpg)
Ashland/NSP Lakefront
Superfund Site
Phase 2
Phase 1
![Page 11: 2019 Annual Meeting Ashland Superfund Site€¦ · Superfund Project Superfund Program - started 1980 Ashland Superfund Record of Decision (ROD) issued September, 2010. The ROD explained](https://reader033.vdocuments.mx/reader033/viewer/2022043010/5fa0efbe561c3117cd78f58f/html5/thumbnails/11.jpg)
Phase 1 Source Control
❖Excavation: 90,000 tons
❖Thermal Desorption: 70,000 tons
❖Offsite Disposal: 20,000 tons
❖Met All Soil Cleanup Standards
![Page 12: 2019 Annual Meeting Ashland Superfund Site€¦ · Superfund Project Superfund Program - started 1980 Ashland Superfund Record of Decision (ROD) issued September, 2010. The ROD explained](https://reader033.vdocuments.mx/reader033/viewer/2022043010/5fa0efbe561c3117cd78f58f/html5/thumbnails/12.jpg)
Soil Excavation and
Treatment
![Page 13: 2019 Annual Meeting Ashland Superfund Site€¦ · Superfund Project Superfund Program - started 1980 Ashland Superfund Record of Decision (ROD) issued September, 2010. The ROD explained](https://reader033.vdocuments.mx/reader033/viewer/2022043010/5fa0efbe561c3117cd78f58f/html5/thumbnails/13.jpg)
❖Primary Purpose Wave Barrier for 2016 Pilot Project
Full-Scale Sediment Remedy Benefits
Community Benefits
Phase 2 Breakwater
![Page 14: 2019 Annual Meeting Ashland Superfund Site€¦ · Superfund Project Superfund Program - started 1980 Ashland Superfund Record of Decision (ROD) issued September, 2010. The ROD explained](https://reader033.vdocuments.mx/reader033/viewer/2022043010/5fa0efbe561c3117cd78f58f/html5/thumbnails/14.jpg)
Breakwater Construction
![Page 15: 2019 Annual Meeting Ashland Superfund Site€¦ · Superfund Project Superfund Program - started 1980 Ashland Superfund Record of Decision (ROD) issued September, 2010. The ROD explained](https://reader033.vdocuments.mx/reader033/viewer/2022043010/5fa0efbe561c3117cd78f58f/html5/thumbnails/15.jpg)
![Page 16: 2019 Annual Meeting Ashland Superfund Site€¦ · Superfund Project Superfund Program - started 1980 Ashland Superfund Record of Decision (ROD) issued September, 2010. The ROD explained](https://reader033.vdocuments.mx/reader033/viewer/2022043010/5fa0efbe561c3117cd78f58f/html5/thumbnails/16.jpg)
Phase 2 Pilot Project
![Page 17: 2019 Annual Meeting Ashland Superfund Site€¦ · Superfund Project Superfund Program - started 1980 Ashland Superfund Record of Decision (ROD) issued September, 2010. The ROD explained](https://reader033.vdocuments.mx/reader033/viewer/2022043010/5fa0efbe561c3117cd78f58f/html5/thumbnails/17.jpg)
Pilot Project Work
❖ 40,000 square foot Pilot Study Dredge Area
❖ 8,000 cubic yards Removed
❖ 520 Truckloads to Sub-Title D Landfill
❖ 4 million gallons Water Treated
![Page 18: 2019 Annual Meeting Ashland Superfund Site€¦ · Superfund Project Superfund Program - started 1980 Ashland Superfund Record of Decision (ROD) issued September, 2010. The ROD explained](https://reader033.vdocuments.mx/reader033/viewer/2022043010/5fa0efbe561c3117cd78f58f/html5/thumbnails/18.jpg)
Pilot Project Successful!
Move to Full Scale
Phase 2 Dredging
![Page 19: 2019 Annual Meeting Ashland Superfund Site€¦ · Superfund Project Superfund Program - started 1980 Ashland Superfund Record of Decision (ROD) issued September, 2010. The ROD explained](https://reader033.vdocuments.mx/reader033/viewer/2022043010/5fa0efbe561c3117cd78f58f/html5/thumbnails/19.jpg)
Extensive Monitoring
![Page 20: 2019 Annual Meeting Ashland Superfund Site€¦ · Superfund Project Superfund Program - started 1980 Ashland Superfund Record of Decision (ROD) issued September, 2010. The ROD explained](https://reader033.vdocuments.mx/reader033/viewer/2022043010/5fa0efbe561c3117cd78f58f/html5/thumbnails/20.jpg)
Water Quality Results
• Over 10,000 samples analyzed
• >99.9% meet water quality standards
![Page 21: 2019 Annual Meeting Ashland Superfund Site€¦ · Superfund Project Superfund Program - started 1980 Ashland Superfund Record of Decision (ROD) issued September, 2010. The ROD explained](https://reader033.vdocuments.mx/reader033/viewer/2022043010/5fa0efbe561c3117cd78f58f/html5/thumbnails/21.jpg)
Enhanced Technologies
Multiple Barrier Curtain
System
to contain work area
impacts and protect Lake
Superior
Vapor Phase Odor
Control System
![Page 22: 2019 Annual Meeting Ashland Superfund Site€¦ · Superfund Project Superfund Program - started 1980 Ashland Superfund Record of Decision (ROD) issued September, 2010. The ROD explained](https://reader033.vdocuments.mx/reader033/viewer/2022043010/5fa0efbe561c3117cd78f58f/html5/thumbnails/22.jpg)
Sediment Pre-Project
SWAC = 409 ppm
![Page 23: 2019 Annual Meeting Ashland Superfund Site€¦ · Superfund Project Superfund Program - started 1980 Ashland Superfund Record of Decision (ROD) issued September, 2010. The ROD explained](https://reader033.vdocuments.mx/reader033/viewer/2022043010/5fa0efbe561c3117cd78f58f/html5/thumbnails/23.jpg)
Sediment Post Dredging
Meeting SWAC Performance Standard
![Page 24: 2019 Annual Meeting Ashland Superfund Site€¦ · Superfund Project Superfund Program - started 1980 Ashland Superfund Record of Decision (ROD) issued September, 2010. The ROD explained](https://reader033.vdocuments.mx/reader033/viewer/2022043010/5fa0efbe561c3117cd78f58f/html5/thumbnails/24.jpg)
tPAH Mass Removal
Summary
![Page 25: 2019 Annual Meeting Ashland Superfund Site€¦ · Superfund Project Superfund Program - started 1980 Ashland Superfund Record of Decision (ROD) issued September, 2010. The ROD explained](https://reader033.vdocuments.mx/reader033/viewer/2022043010/5fa0efbe561c3117cd78f58f/html5/thumbnails/25.jpg)
Restorative Layer
![Page 26: 2019 Annual Meeting Ashland Superfund Site€¦ · Superfund Project Superfund Program - started 1980 Ashland Superfund Record of Decision (ROD) issued September, 2010. The ROD explained](https://reader033.vdocuments.mx/reader033/viewer/2022043010/5fa0efbe561c3117cd78f58f/html5/thumbnails/26.jpg)
Ashland Kreher Park
- draft conceptual plan
![Page 27: 2019 Annual Meeting Ashland Superfund Site€¦ · Superfund Project Superfund Program - started 1980 Ashland Superfund Record of Decision (ROD) issued September, 2010. The ROD explained](https://reader033.vdocuments.mx/reader033/viewer/2022043010/5fa0efbe561c3117cd78f58f/html5/thumbnails/27.jpg)