2018 tailings and mine waste onference lternative
TRANSCRIPT
| Geotechnical Engineering Centre1
2018 TAILINGS AND MINE WASTE CONFERENCE
ALTERNATIVE APPROACHES TO MANAGEMENT
AND CLOSURE OF TAILINGS STORAGE
FACILITIES
Professor David Williams
Director Geotechnical Engineering Centre
The University of Queensland, Brisbane, Australia
Email: [email protected]
CRICOS Provider No 00025B
| Geotechnical Engineering Centre2
Scope
• Extending Net Present Value approach to tailings
management and closure
• Conventional approach to tailings disposal and storage
• Tailings dam failure rates
• Risk of tailings liquefaction or flow
• Tailings closure and rehabilitation risks and costs
• Alternative approaches to tailings disposal, storage and
rehabilitation
CRICOS Provider No 00025B
| Geotechnical Engineering Centre3
Net Present Value Approach
• NPV, with a high Discount Factor (typically 6 to 10%,
several times inflation rate) is applied to achieve financing
of high cost mining projects
• NPV is extended to tailings disposal, minimising short-
term capital costs, with rehabilitation costs discounted by
same high Discount Factor, which contributes to:
– Increased risk of tailings dam failure
– Initially inexpensive but too small surface facilities storing tailings
slurry delivered by robust and inexpensive centrifugal pumps
– Wet and soft tailings deposits, excessive stored water, and an
ever-increasing stored volume and footprint.
– A blow out in costs, as frequent tailings dam raises are required,
and unintended and cumulative negative impacts
– Difficult and costly rehabilitation, at a time when revenues cease
CRICOS Provider No 00025B
| Geotechnical Engineering Centre4
Constraints Under Which a Surface
TSF Must Operate
• Climatic and topographic setting of TSF
• Dam foundation conditions, and availability and suitability
of borrow materials
• Nature of tailings, particularly presence of clay minerals
• Tailings production rate that must be stored and % solids
at which they are deposited
• Need to manage, store and recycle supernatant
• Need to meet discharge water quality licence conditions
• Need to maximise tailings settled dry density, and hence
minimise wall raising and volume of tailings stored
• Desirability of upstream raising, where appropriate
• Need to rehabilitate TSF on closure
CRICOS Provider No 00025B
| Geotechnical Engineering Centre5
Conventional Approach to Tailings
Disposal and Storage
• Disposal and storage of tailings slurry
• Tailings containment and method of construction and dam
raising varies from region to region:
– Upstream construction is widely employed in South Africa,
Australia and south-west of USA, which share a dry climate
– Downstream construction is employed in wet regions, such as
Canada
– Sand dams, cycloned and/or compacted, are widely employed in
South America, usually raised by centreline method
– Roller compacted concrete dams are employed for high tailings
dams in deep valleys of Andes in South America
• While downstream construction is understandable in wet
climates, choice between upstream construction and sand
dams is not so obvious – “What we’ve always done”
CRICOS Provider No 00025B
| Geotechnical Engineering Centre6
Tailings Continuum (adapted from
Davies and Rice, 2004)
CRICOS Provider No 00025B
By gravity – U/G or In-Pit
| Geotechnical Engineering Centre7
Conventional Approach to Tailings
Disposal and Storage
• A commonly held perception, supported by NPV
approach, is that transporting tailings as a slurry to a
surface dam is most economic
• Discounted cost of rehabilitating resulting TSF is not
considered to be significant
• However, few TSFs have been rehabilitated, due to
difficulty and expense of capping a “slurry-like” (wet and
soft) tailings deposit
• Filtering tailings is perceived to be too expensive due to
capital and operating costs of plant and transport
• Filtered tailings occupy less volume, are relatively easy to
cap, and may be rehabilitated to a high level of future land
use and/or ecological function
CRICOS Provider No 00025B
| Geotechnical Engineering Centre8
Ongoing Tailings Dam Failures
• Average tailings dam failure rate over last 100 years is
1.2% or 2.2/year, >2 orders of magnitude higher than that
for water retention dams of 0.01%
• USA has reported highest number of tailings dam failures
of any country, with 39%,18% located in Europe, 12% in
Chile, and 5% in Philippines
• Most tailings dams that failed were of moderate height – 5
to 20 m high
• Focus is on failures that occur in developed countries
(e.g., Mount Polley in 2014, Cadia in 2018) or that involve
global mining companies (e.g., Samarco in 2015)
• Recent, high profile tailings dam failures are threatening
mining industry’s financial and “social licence to operate”!
CRICOS Provider No 00025B
| Geotechnical Engineering Centre9
Responses to Recent High Profile
Tailings Dam Failures
• Reviews of existing tailings dams by major mining
companies, or when required by Regulators
• More conservative designs, including using lowest bound
parameters – Questioning safety of previous designs, or
feasibility of failure through only lowest strength materials!
• Banning some tailings containment practices, such as
upstream construction in Chile’s seismic environment
• Increased liability of “Engineer of Record”/Design Engineer
• Concern about personal liability/prosecution of senior
executives, driving tailings management
• Increased Security Bonds and Guarantees for TSFs
CRICOS Provider No 00025B
| Geotechnical Engineering Centre10
Responses to Recent High Profile
Tailings Dam Failures
• Responses have not (yet) included a major shift in existing
tailings slurry disposal and containment
• What has occurred is:
– Increased tailings dam monitoring (in real-time), particularly at
failure sites
– Inclusion of buttresses as an “insurance policy”, sometimes forced
by inadequate tailings management and monitoring
– Conditions being imposed on tailings management at new mines
– Filtering of tailings being considered beyond desert sites, possibly
including co-disposal with waste rock
CRICOS Provider No 00025B
| Geotechnical Engineering Centre11
570 mm January 2016 Rainfall-
Induced Tailings Run-Out
CRICOS Provider No 00025B
| Geotechnical Engineering Centre12
Risk of Tailings Liquefaction
• Conditions for liquefaction of tailings:
– Silty sand to fine-grained sandy tailings
– Loose (contractive, brittle) state
– Near-saturated
– Trigger event:
• Earthquake magnitude > 5.5 and peak ground acceleration >
0.13g
• For “static” liquefaction:
– Too rapid a rate of upstream construction
– Too rapid a rate of rise of tailings
– A flooding event, possibly leading to overtopping and
erosion of embankment
• Susceptible tailings can behave in an undrained,
contractive, strain-softening manner, and liquefy or flowCRICOS Provider No 00025B
| Geotechnical Engineering Centre13
Risk of Tailings Liquefaction
• Davies et al. (2002) claimed that tailings impoundments
have demonstrated more static liquefaction events than
any other cause
• Risk of static liquefaction may be higher at sites with low
design earthquakes, such as in Australia
• Tailings potentially susceptible to liquefaction are difficult
to sample and assess
• A precautionary approach is to assume that identified
“loose” tailings will be susceptible to static liquefaction,
and to outlaw upstream construction
• However, well-managed upstream construction can safely
support this method
CRICOS Provider No 00025B
| Geotechnical Engineering Centre14
Tailings Operation, Closure and
Rehabilitation Costs
• Use of NPV and an artificially high Discount Factor result
in:
– Apparent cost savings in tailings management in short-term
– Increasing operational and capital costs over time
– Unintended cumulative detrimental impacts over time
– Ever-increasing closure and rehabilitation risks and costs in long-
term
• To illustrate this, simple NPV analyses are applied to
alternative management and closure approaches for:
– Coal tailings from open pit mining operations
– In relatively flat terrain of Eastern Australian Coalfields
– Mine life of 20 years
– AUD75,000/ha for rehabilitation
CRICOS Provider No 00025B
| Geotechnical Engineering Centre15
Relative Comparison of Tailings
Storage Alternatives
CRICOS Provider No 00025B
High cost
of Dams in
flat terrain
High cost
of RehabHigh cost of
re-handlingHigh CapEx
Balancing
Dam &
Rehab costs
| Geotechnical Engineering Centre16
10% Discount Factor Applied to
Tailings Operations & Rehabilitation
CRICOS Provider No 00025B
A high Discount
Factor makes
(delayed)
rehabilitation
“appear cheap”,
with rehabilitation at
closure “cheapest”,
but this ignores
cumulative
unintended
impacts, Regulators
now favouring
“Progressive
Rehabilitation”, and
ongoing Security
Deposit payments
| Geotechnical Engineering Centre17
2.5% Discount Factor Applied to
Tailings Operations & Rehabilitation
CRICOS Provider No 00025B
A more realistic
Discount Factor of
2.5% indicates
more realistic,
higher
rehabilitation costs
| Geotechnical Engineering Centre18
Tailings Security Deposit
• Queensland and NSW indicative costs for reshaping,
capping/sealing tailings are:
– $170,000/ha for tailings likely to present considerable difficulties
due to reactive and/or soft tailings.
– $108,000/ha for tailings likely to present moderate difficulties due
to reactive and/or soft tailings.
– $81,000/ha for benign and strong tailings.
• To these are added costs for land preparation and
revegetation, and maintenance, giving a total Security
Deposit from $85,300 to $215,000/ha
• Actual cost could be far less, under favourable conditions
• A Bank Guarantee would cost ~1.5 to 3% pa of a high
Security Deposit, possibly continuing in perpetuity
CRICOS Provider No 00025B
| Geotechnical Engineering Centre19
Alternative Approaches to Tailings
Disposal, Storage and Rehabilitation
• Rather than focussing on lowest NPV, manage tailings for
safety and with end game of lease relinquishment
uppermost
• Consider constraints over time, including changes in ore
grade and geochemistry
• This will likely bias tailings management away from slurry
disposal, unless enhanced operation and control is in
place
• If upstream construction is favoured, tailings disposal must
be managed to ensure a low rate of rise, discharge away
from dam, and decant pond/stored runoff stored well away
from dam – Avoid loose, liquefiable tailings and tailings
that cannot readily be rehabilitated
CRICOS Provider No 00025B
| Geotechnical Engineering Centre20
Alternative Approaches to Tailings
Disposal, Storage and Rehabilitation
• Recognise high cost of managing and rehabilitating
tailings slurry
• Develop cost-effective dewatering of tailings addressing:
– Perceived high cost of filtration
– Difficulty in scaling-up filtration for high production rates
– Need to ensure stability, which may include compaction
• Develop cost-effective co-disposal of filtered tailings and
scalped waste rock addressing:
– Required moisture content of tailings
– Scalping (crushing, screening) of waste rock
– Mixing of filtered tailings and scalped waste rock
– Transportation of mixture
– Need for compaction and encapsulation of PAF material
CRICOS Provider No 00025B