20090714 contracts workshop

27
NEC3 Option C 5 Key Contract Mechanisms Steve Jackson

Upload: mmcbas

Post on 02-Nov-2014

1.082 views

Category:

Business


1 download

DESCRIPTION

5 key contract mechanisms for controlling cost on an Option C contract

TRANSCRIPT

Page 1: 20090714 Contracts Workshop

NEC3 Option C5 Key Contract Mechanisms

Steve Jackson

Page 2: 20090714 Contracts Workshop

5 Key Contract Mechanisms

• Disallowed Costs• Compensation Events and Change Control.• How to manage time• Communications.• Defects.

“A child of five would understand this. Send someone to fetch a child of five.”Groucho Marx

Page 3: 20090714 Contracts Workshop

The Ground Rules

• Clause 10.1... shall each act as stated in this

ContractAND

In a spirit of mutual trust and cooperation

“The secret of life is honesty and fair dealing. If you can fake that, you've got it made.”Groucho Marx

Page 4: 20090714 Contracts Workshop

Contractor’s overriding obligation

11.2(60)

… to do the work necessary to complete the works in accordance with this Contract and all incidental work services and actions which the Contract requires

20 Contractor ..

Advises on the design

Prepares forecasts

Ensures proper integration

To ‘Provide the Works’(He does what it says on the tin)

Page 5: 20090714 Contracts Workshop

Financial ControlFinancial Control

Disallow CostsClause 11.2(23)

Control the Target CostCompensation Events

Clause 60

Make DeductionsClause 55

Page 6: 20090714 Contracts Workshop

Goal or no goal? You are the Russian Linesman

The PM decides – Clause 11.2(23)

You cannot expect the Contractor not to claim the costs

It is your responsibility to allow or disallow

Disallowed Costs

Page 7: 20090714 Contracts Workshop

Disallowable Costs - 1

Page 8: 20090714 Contracts Workshop

Disallowable Costs - 2

Page 9: 20090714 Contracts Workshop

Disallowable Costs - 3

Page 10: 20090714 Contracts Workshop

Disallowable Costs - Summary

• Not ‘Providing the Works’• Any kind of rework (Design or

Construction)• Unnecessary work• Uneconomic work

• Repairing damage

• ‘Other costs’

Clause 11.2(23) is a bit of a jumble – but can be summarised as:

Page 11: 20090714 Contracts Workshop

Record Keeping

Site Records

Accounts Records

You set the agenda

Be demanding

Burden of proof lies with you

Records must be communicated

Feed the system!

Page 12: 20090714 Contracts Workshop

Don’t expect a happy response

Final thought on Disallowed Cost

But remember what Andy Warhol said ….

“Art is anything you can get away with”

The same applies to costs on a NEC Option C contract!!

Page 13: 20090714 Contracts Workshop

Compensation Events

“If anything is certain, it is that change is certain” Philip Crosby

“A Compensation event is like a Cruise Missile – you know its coming but there is f**k all you can do about it” Anon

Page 14: 20090714 Contracts Workshop

The Roots of Compensation Events

• Damages: Hadley v Baxendale [1854]– Liable for all losses in the contemplation of the

parties

• Loss and Expense – JCT Contracts– Contractual remedy for damages– Time dealt with separately

• Compensation Events – NEC– Takes account of time and money

Page 15: 20090714 Contracts Workshop

Clause 16

Early Warnings & Risk Reduction

Clauses 60-65

WhatAssess

Notify

Quote

PM Assessment

Implement

Page 16: 20090714 Contracts Workshop

Compensation Events

• A CE may arise from almost any change in the Works Information– And a few other things besides

• Contractor quotes• PM must assesses if the quote is wrong• State assumptions where necessary

Beware: The Project Manager’s indecision is final! (64.4)

Page 17: 20090714 Contracts Workshop

How to Manage Time

“You may delay, but time will not” Benjamin Franklin

Page 18: 20090714 Contracts Workshop

Time – the basics

Clause 30Start: on the ‘Access Date’Finish: on (or before) the ‘Completion Date’Fulfil the criteria for the ‘Key Dates’ (on or

before)Proceed: Regularly and diligentlyMitigate delay

Page 19: 20090714 Contracts Workshop

Time Management

31 Accepted Programme

32 The Contractor revises the programme – from time to time – New Accepted Programme

63/64 Completion Date is adjusted by Compensation events

Similar to Financial Forecasts

Page 20: 20090714 Contracts Workshop

Communications

“The single biggest problem in communication is the illusion that it has taken place.” George Bernard Shaw

Page 21: 20090714 Contracts Workshop

PM

Contracto

r Emp

Compare with Cl 10.1

Good communication facilitates working together

Page 22: 20090714 Contracts Workshop

13.2communication

is notCommunication

• “This 'telephone' has too many shortcomings to be seriously considered as a means of communication. The device is inherently of no value to us.”Western Union internal memo, 1876

Page 23: 20090714 Contracts Workshop

instruction

record

registerproposal

submission

certificate

direction

order

message

refusal

non-acceptance

acceptancewarning

13.1 CommunicationCopy – Read – Record

Page 24: 20090714 Contracts Workshop

Communication v notification

‘Gee, I’ve never had a pen pal before’

11.2(11) Communication is any form of communication as defined in Clause 13.

Page 25: 20090714 Contracts Workshop

Defects

“In a true zero-defects approach, there are no unimportant items” Phil Crosby

Page 26: 20090714 Contracts Workshop

43 / 44Contractor corrects all Defects

(whether notified or not)

Corrects Defects at a time to suit himself, but without delay to Completion

Employer may accept a Defect – change to cost and time

“The crack’s no fun when it’s in concrete” - Anon

Page 27: 20090714 Contracts Workshop

Thank you!