Page 1: 20 Year Master Facility Plan - BoardDocs, a Diligent Brand · 2019. 5. 18. · 20 Year Master Facility Plan 22 September 2014. Brief Background •The District began work on this

20 Year Master Facility Plan

22 September 2014

Page 2: 20 Year Master Facility Plan - BoardDocs, a Diligent Brand · 2019. 5. 18. · 20 Year Master Facility Plan 22 September 2014. Brief Background •The District began work on this

Brief Background

• The District began work on this plan with the help of the community, the Facility Committee, BLDD, and Gorski Reifsteck/DLR Group.

• Created potential District facility scenarios and vetted them based on cost, enrollment capacity , and educational adequacy (How well the buildings serve 21st century education).

• The most recent discussion and update on the plan was at a July BOE Meeting.

Page 3: 20 Year Master Facility Plan - BoardDocs, a Diligent Brand · 2019. 5. 18. · 20 Year Master Facility Plan 22 September 2014. Brief Background •The District began work on this

Brief Background

The Board and administration looked most recently at 3 scenarios (1, 8, and 9) – Each scenario had strengths in accomplishing the

District’s goals.

District’s goals:

1. Meeting enrollment capacity

2. Combining building functions in fewer buildings

3. Improving educational adequacy and providing an option to the community for K-8 instruction

Page 4: 20 Year Master Facility Plan - BoardDocs, a Diligent Brand · 2019. 5. 18. · 20 Year Master Facility Plan 22 September 2014. Brief Background •The District began work on this

Scenario 1

• South Side:3 Strands @ 383 Students

• IPA (Kirby): 3 Strands @ 383 Students

• Barkstall: Addition for 3 strand K-8

• Dr. Howard: CLOSE and build 4 strand @ 425 students on new Site

• Franklin: Addition/Renovate @ 675 students

• Jefferson: Addition/Renovate @ 675 students

• Edison: CLOSE and relocate to current Central

• Central: Build on New Site

• Current Central: Move Edison students and Academy.

Page 5: 20 Year Master Facility Plan - BoardDocs, a Diligent Brand · 2019. 5. 18. · 20 Year Master Facility Plan 22 September 2014. Brief Background •The District began work on this

Scenario 8

• South Side: Addition/Renovate for 3 strands• IPA (Kirby): Addition/Renovate for 3 strands• Barkstall: (K-8) Addition for 3 strands @ grades 6-8• Dr. Howard: Close, rebuild on site for 4 strands• Edison: Close, build on new site for 750 students• Jefferson: Addition/Renovation • Franklin: Addition/Renovation• Current Central: Renovate for Career Prep Academy

and demolish 130,000 sq ft.• New Central: New site for 1,700 students• Centennial: Addition/Renovation

Page 6: 20 Year Master Facility Plan - BoardDocs, a Diligent Brand · 2019. 5. 18. · 20 Year Master Facility Plan 22 September 2014. Brief Background •The District began work on this

Scenario 9

• South Side: 4 Strand K-8• Barkstall: (K-8) Addition for 3 strands @ grades 6-8• Dr. Howard: Close and build 4 strand K-8 on new site• Stratton: (K-8) Addition for 3 strands @ grades 6-8• Columbia: Close• Mellon Close• Franklin: Addition and Renovate • Jefferson: Addition and Renovate• Edison: Close• Current Central: Remodel for Mellon, Columbia, Novak, Career

Prep, FIC, and SPED• New Central: New site• Centennial: Addition/Renovate

Page 7: 20 Year Master Facility Plan - BoardDocs, a Diligent Brand · 2019. 5. 18. · 20 Year Master Facility Plan 22 September 2014. Brief Background •The District began work on this

Master Facility Plan

Goal 2: Combining building functions in fewer buildings

Administration and Support Buildings– Retire Columbia Building (FIC) and relocate services to

current Central Building $57,239 (annual savings)– Novak Academy would relocate to current Central

Building $84,165 (annual savings)– Retire Mellon Building and relocate services to current

Central Building $52,813 (annual savings)

Total Annual Savings: $194,217 based on

Page 8: 20 Year Master Facility Plan - BoardDocs, a Diligent Brand · 2019. 5. 18. · 20 Year Master Facility Plan 22 September 2014. Brief Background •The District began work on this

Master Facility Plan

Goal 1: Meeting enrollment capacity

Goal 3: Improving educational adequacy and providing an option to the community for K-8 instruction.

Elementary/MS Buildings

– South Side: Addition/Renovation, increase to 3 strands (383 total seats)

– Retire Dr. Howard and rebuild as a 4 Strand K-8 on a new site (300 seats 6-8 and 383 seats K-5)

Page 9: 20 Year Master Facility Plan - BoardDocs, a Diligent Brand · 2019. 5. 18. · 20 Year Master Facility Plan 22 September 2014. Brief Background •The District began work on this

Master Facility Plan

Goal 1: Meeting enrollment capacityGoal 3: Improving educational adequacy and providing

an option to the community for K-8 instruction.

Elementary/MS Buildings

• IPA: Continue to expand as a 3 strand elementary school for 383 seats

• Jefferson: Addition/Renovation for 675 seats

• Franklin: Addition/Renovation for 675 seats

• Edison: Retire/Build on new site for 750 seats

Page 10: 20 Year Master Facility Plan - BoardDocs, a Diligent Brand · 2019. 5. 18. · 20 Year Master Facility Plan 22 September 2014. Brief Background •The District began work on this

Master Facility Plan

Goal 1: Meeting enrollment capacityGoal 2: Combining building functions in fewer buildings

High Schools– Repurpose Current Central: District Administration,

Novak Academy, Family Information Center, and Curriculum Services

– Central High School: Rebuild on new location for 1,700 seats

– Centennial High School: Renovate/Addition for 1,700 seats

Page 11: 20 Year Master Facility Plan - BoardDocs, a Diligent Brand · 2019. 5. 18. · 20 Year Master Facility Plan 22 September 2014. Brief Background •The District began work on this
Page 12: 20 Year Master Facility Plan - BoardDocs, a Diligent Brand · 2019. 5. 18. · 20 Year Master Facility Plan 22 September 2014. Brief Background •The District began work on this

Facility Improvement Over 20 Years

• Dr. Howard (4 strand K-8): $36,700,000

• South Side (3 strand) Renovation/Addition: $14,500,000

• IPA: (3 Strand) Interior Remodeling: $666,500

• Edison: $27,200,000

• Franklin: $14,500,000

• Jefferson: $11,300,000

• Central High School: $98,000,000

• Centennial High School: $51,000,000Cost estimates provided by BLDD through QLEO analysis for elementary and middle schools except the IPA. IPA based on internal O/M cost estimates. High school costs based on DLR/Gorski estimates.

Page 13: 20 Year Master Facility Plan - BoardDocs, a Diligent Brand · 2019. 5. 18. · 20 Year Master Facility Plan 22 September 2014. Brief Background •The District began work on this

Facility Plan Annual Operating Cost Savings

Building Reductions

– Columbia Building

– Novak Academy

– Mellon Building

$194,217 Annual Savings in Plant Operating Expenses based on 2013 data.

Savings based on District FY 13 operating costs

Page 14: 20 Year Master Facility Plan - BoardDocs, a Diligent Brand · 2019. 5. 18. · 20 Year Master Facility Plan 22 September 2014. Brief Background •The District began work on this

Facility Improvement Over 20 Years

• The plan addresses all three of the district facility goals:

1. Meeting enrollment capacity

2. Combining building functions in fewer buildings

3. Improving educational adequacy and providing an option to the community for K-8 instruction

This facility plan provides direction and flexibility for future boards.

Page 15: 20 Year Master Facility Plan - BoardDocs, a Diligent Brand · 2019. 5. 18. · 20 Year Master Facility Plan 22 September 2014. Brief Background •The District began work on this

Master Facility Plan Total Cost and Funding Options

• $253,866,500 total cost in today’s dollars.

• Referendum for the two high schools.

• Begin to utilize 1% sales tax funds in 2025 for bond issue to cover building projects as seen fit by future Boards of Education.

Page 16: 20 Year Master Facility Plan - BoardDocs, a Diligent Brand · 2019. 5. 18. · 20 Year Master Facility Plan 22 September 2014. Brief Background •The District began work on this

How Does the 10 Year Capital Improvement Plan FIT into this?

• Annually, the District has $1,400,000 to put towards capital improvement projects. The dollars come from three sources:

– 61 FUND -$1,100,000

– 20 FUND- $300,000

• The Operations and Maintenance Staff have identified facility needs, their projected costs, and a 10 year timeline for these improvements.

Page 17: 20 Year Master Facility Plan - BoardDocs, a Diligent Brand · 2019. 5. 18. · 20 Year Master Facility Plan 22 September 2014. Brief Background •The District began work on this

10 Year CIP Overview

• Total Project Expense Over 10 Yrs• $13,082,000• Total 61 Fund $ Over 10 Yrs• $10,250,000• Total 20 Fund $ Over 10 Yrs• $3,000,000• Total Available $ Over 10 Yrs• $13,250,000• Excess $ Available Over 10 Yrs• $168,000• WITHOUT HLS REQUIREMENTS

Page 18: 20 Year Master Facility Plan - BoardDocs, a Diligent Brand · 2019. 5. 18. · 20 Year Master Facility Plan 22 September 2014. Brief Background •The District began work on this

10 Year CIP Overview

2014-15 2015-16 2016-17 2017-18 2018-19 2019-20 2020-21 2021-22 2022-23 2023-24Total Projects'

Expenses by Year $787,124 $1,431,968 $1,595,968 $1,885,968 $1,860,966 $1,175,000 $1,203,500 $1,163,500 $1,103,500 $1,003,500

61 FUND $ Avail $350,000 $1,100,000 $1,100,000 $1,100,000 $1,100,000 $1,100,000 $1,100,000 $1,100,000 $1,100,000 $1,100,000

20 FUND $ Avail $300,000 $300,000 $300,000 $300,000 $300,000 $300,000 $300,000 $300,000 $300,000 $300,000

90 FUND $ Avail $419,124 $200,000 $200,000 $200,000 $200,000

Total Available $ $1,069,124 $1,600,000 $1,600,000 $1,600,000 $1,600,000 $1,400,000 $1,400,000 $1,400,000 $1,400,000 $1,400,000

Over/Under $ $282,000 $168,032 $4,032 ($285,968) ($260,966) $225,000 $196,500 $236,500 $296,500 $396,500

Total Project

Expense Over 10 Yrs $13,210,994Total 61 Fund $ Over

10 Yrs $10,250,000Total 20 Fund $ Over

10 Yrs $3,000,000Total Available $

Over 10 Yrs $14,469,124Excess $ Available

Over 10 Yrs $1,258,130

Page 19: 20 Year Master Facility Plan - BoardDocs, a Diligent Brand · 2019. 5. 18. · 20 Year Master Facility Plan 22 September 2014. Brief Background •The District began work on this

Location Capital Improvements ProjectsProject Costs 2014-15 2015-16 2016-17 2017-18 2018-19 2019-20 2020-21 2021-22 2022-23 2023-24

HLS Yr 1 HLS Yr 2 HLS Yr 3 HLS Yr 4 HLS Yr 5

Scenario 1HLS "A" Items Paid from HLS Fund Balance$419,124 $419,124

HLS "B" Items Paid

from HLS Fund; 20

Fund; 61 Fund $2,889,870 $722,468 $722,468 $722,468 $722,466

Location Capital Improvements ProjectsProject Costs 2014-15 2015-16 2016-17 2017-18 2018-19 2019-20 2020-21 2021-22 2022-23 2023-24IPA Interior Remodeling (casework, paint, furniture, flooring, etc.)$666,500 $137,000 $68,500 $68,500 $68,500 $50,000 $68,500 $68,500 $68,500 $68,500

IPA Additional Keyless Door Access $35,000 $35,000

Mellon Additional Keyless Door Access $35,000 $35,000

Edison Additional Keyless Door Access $35,000 $35,000

Jefferson Additional Keyless Door Access $35,000 $35,000

Southside Additional Keyless Door Access $15,000 $15,000

Centennial Replace interior doors and hardware $0

Centennial Replace A/C plant $0

Centennial Replace all HVAC supply fans - 10 Year Lease Purchase$0

Central Replace hot water heater $26,000 $26,000

Central Replace fire alarm system $380,000 $380,000

Central Replace Boilers $250,000 $250,000

Central Window Replacement $1,750,000 $250,000 $250,000 $250,000 $250,000 $250,000 $250,000 $250,000

Central Exterior Concrete Replacement $50,000 $50,000

Columbia Interior Door and Hardware Replacement$0

District Other Capital Projects $311,500 $180,000 $131,500

Bottenfield Roof Restoration $350,000 $350,000

IPA Roof Restoration $350,000 $350,000

Garden Hills Roof Restoration $350,000 $350,000

Dr. Howard Roof Restoration $350,000 $350,000

Westview Roof Restoration $350,000 $350,000

Edison Roof Restoration $350,000 $350,000

Franklin Roof Restoration $350,000 $350,000

Jefferson Roof Restoration $350,000 $350,000

Centennial Roof Restoration $0

Central Roof Restoration $0

District Asphalt Replacement $600,000 $100,000 $100,000 $100,000 $100,000 $100,000 $100,000

IPA Fire Alarm Replacement $100,000 $100,000

Dr Howard Fire Alarm Replacement $100,000 $100,000

Southside Fire Alarm Replacement $100,000 $100,000

Edison Fire Alarm Replacement $200,000 $200,000

Franklin Fire Alarm Replacement $100,000 $100,000

Jefferson Fire Alarm Replacement $100,000 $100,000

Columbia Fire Alarm Replacement $100,000 $100,000

IPA Phones/Intercom Replacement $175,000 $175,000

Dr Howard Phones/Intercom Replacement $175,000 $175,000

Southside Phones/Intercom Replacement $175,000 $175,000

Stratton Phones/Intercom Replacement $175,000 $175,000

Edison Phones/Intercom Replacement $250,000 $250,000

Franklin Phones/Intercom Replacement $175,000 $175,000

Central Phones/Intercom Replacement $250,000 $250,000

CECC Update BAS System $60,000 $60,000

Stratton Update BAS System $60,000 $60,000

Barkstall Update BAS System $60,000 $60,000

IPA Update BAS System $60,000 $60,000

Dr Howard Update BAS System $60,000 $60,000

Southside Update BAS System $60,000 $60,000

Edison Update BAS System $60,000 $60,000

Central Update BAS System $60,000 $60,000

Columbia Update BAS System $0

Dr Howard Hot water heater replacement $3,000 $3,000

Dr Howard Return pump replacement $7,000 $7,000

Dr Howard Repair interior stairs $18,000 $18,000

Jefferson Phone Replacement $170,000 $170,000

South Side Replace package boiler $60,000 $60,000

Total Project Expense Over 10 Years$13,210,994

2014-15 2015-16 2016-17 2017-18 2018-19 2019-20 2020-21 2021-22 2022-23 2023-24

Total Projects'

Expenses by

Year $787,124 $1,431,968 $1,595,968 $1,885,968 $1,860,966 $1,175,000 $1,203,500 $1,163,500 $1,103,500 $1,003,500

61 FUND $ Avail $350,000 $1,100,000 $1,100,000 $1,100,000 $1,100,000 $1,100,000 $1,100,000 $1,100,000 $1,100,000 $1,100,000

20 FUND $ Avail $300,000 $300,000 $300,000 $300,000 $300,000 $300,000 $300,000 $300,000 $300,000 $300,000

90 FUND $ Avail $419,124 $200,000 $200,000 $200,000 $200,000

Total Available $ $1,069,124 $1,600,000 $1,600,000 $1,600,000 $1,600,000 $1,400,000 $1,400,000 $1,400,000 $1,400,000 $1,400,000

Over/Under $ $282,000 $168,032 $4,032 ($285,968) ($260,966) $225,000 $196,500 $236,500 $296,500 $396,500

10 Year CIP Projects, Costs, Funding, Timeline