1b nelson james

33
Mass Concrete Thermal Control Ahmad Abu-Hawash, Iowa DOT James Nelson, Iowa DOT John Gajda, CTL Group 2009 Mid-Continent Transportation Research Symposium August 20, 2009 Case Study: I-80 over the Missouri River Bridge Construction

Upload: hari-amudhan

Post on 22-Feb-2015

39 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: 1B Nelson James

Mass Concrete Thermal Control

Ahmad Abu-Hawash, Iowa DOTJames Nelson, Iowa DOTJohn Gajda, CTL Group

2009 Mid-Continent Transportation Research Symposium

August 20, 2009

Case Study: I-80 over the Missouri River Bridge Construction

Page 2: 1B Nelson James

August 20, 20092009 Mid-Continent Transportation Research SymposiumPage 2

What is Mass Concrete?

• ACI: “any volume of concrete with dimensions large enough to require that measures be taken to cope with generation of heat from hydration of the cement and attendant volume change to minimize cracking”

Page 3: 1B Nelson James

August 20, 20092009 Mid-Continent Transportation Research SymposiumPage 3

Factors Affecting Mass Concrete• Concrete mix design: components• Environmental condition:

– Ambient temperature– Concrete mix temperature– Differential temperature

• Structural design: steel reinforcement• Application: bridge elements• Least dimension: 3’, 4’, or 5’?

Page 4: 1B Nelson James

August 20, 20092009 Mid-Continent Transportation Research SymposiumPage 4

Mass Concrete Hydration• Significant heat is generated in the first few

days after placement• Expected to reach maximum temperature

within 1 to 3 days after placement• Heat is trapped and can not escape quickly

resulting in:– Significant temperature difference: interior of

concrete is much hotter than its surface (>35°F)• Thermal Cracking

– Concrete mix getting too hot (>160°F)• Delayed Ettringite Formation (DEF)

Page 5: 1B Nelson James

August 20, 20092009 Mid-Continent Transportation Research SymposiumPage 5

Thermal Cracking• Thermal cracking develops when the tensile stress

exceeds the tensile strength of concrete: – Random map cracks in large foundation– A series of vertical cracks in walls (widest near the base)– Uniformly spaced cracks in beams (perpendicular to the

longest dimension)• Mostly, a durability issue: easy pathways for air and

water• In some severe cases, it may affect the structural

capacity

Page 6: 1B Nelson James

August 20, 20092009 Mid-Continent Transportation Research SymposiumPage 6

Delayed Ettringite Formation (DEF)

• Development of unstable hydration• Long-term effect that may not show for

months or years after construction• Can cause significant cracking

Page 7: 1B Nelson James

August 20, 20092009 Mid-Continent Transportation Research SymposiumPage 7

Thermal Control

• Objective: Eliminate thermal cracking by controlling temperature differential and mix temperature (prior to, during and after concrete placement)

• Control measures should be evaluated for costs vs. benefits

Page 8: 1B Nelson James

August 20, 20092009 Mid-Continent Transportation Research SymposiumPage 8

Thermal Control Measures

• Optimal concrete mix design• Insulation• Concrete cooling before placement• Concrete cooling after placement• Use of smaller placements

Page 9: 1B Nelson James

August 20, 20092009 Mid-Continent Transportation Research SymposiumPage 9

Optimal Concrete Mix Design

• Use low-heat cement such as Type II• Use Class F fly ash and/or slag as a substitute

for a portion of the cement• Use low water-to-cementitious materials ratio• Minimize the amount of cementitious

materials in the mix• Use Larger and better graded aggregates• Limestone aggregates are better suited for

mass concrete

Page 10: 1B Nelson James

August 20, 20092009 Mid-Continent Transportation Research SymposiumPage 10

Insulation

• To control temperature differential: core vs. surface

• Has no significant effect on maximum concrete temperature for placements of 5’ or greater

• Typical R-value recommended: 2 to 4 hr.ft².°F/Btu

Page 11: 1B Nelson James

August 20, 20092009 Mid-Continent Transportation Research SymposiumPage 11

Concrete Cooling before Placement

• Each 1°F of precooling is expected to reduce the concrete temperature (after placement) by about the same amount

• Chilled water: about 5°F (100% subs.) temperature reduction

• Chipped or shaved ice: about 15°F to 20°F (75% subs.) temperature reduction

• Liquid nitrogen (LN2): as low as 35°F reduction. Very effective but the most expensive option

Page 12: 1B Nelson James

August 20, 20092009 Mid-Continent Transportation Research SymposiumPage 12

Concrete Cooling after Placement

• Cooling pipes: – Non-corrosive piping embedded prior to

concrete placementРUniformly distributed: typically 1ӯ pipes

@ 2’ to 4’ on center– Removes heat from placed concrete by

circulating cool water from a nearby source

Page 13: 1B Nelson James

August 20, 20092009 Mid-Continent Transportation Research SymposiumPage 13

Smaller Placements

• Multiple lifts• Result in schedule delays and increased

cost due to additional effort for multiple thermal control, and horizontal joint preparation

Page 14: 1B Nelson James

August 20, 20092009 Mid-Continent Transportation Research SymposiumPage 14

Case Study: I-80 over Missouri River

Page 15: 1B Nelson James

August 20, 20092009 Mid-Continent Transportation Research SymposiumPage 15

Iowa Mass Concrete Specifications• Special Provision for Mass Concrete – Control of

Heat of Hydration– Mix design

• Cement: Type II, IP, or IS – min. 560 lbs• Slag and Class F fly ash substitution• Maximum water to cementitious ratio = 0.45

– Thermal Control Plan (per 207.4R-05 ACI)• Concrete temperature at placement: 40°F-70°F• Max. Concrete temperature after placement: 160°F• Temperature differential: 35°F• Temperature sensing and recording

Page 16: 1B Nelson James

August 20, 20092009 Mid-Continent Transportation Research SymposiumPage 16

I-80 over Missouri River Thermal Control Plan

• Value engineering proposal by Jensen Construction to modify project specifications

• Proposed a thermal control plan based on thermal modeling by CTL

Page 17: 1B Nelson James

August 20, 20092009 Mid-Continent Transportation Research SymposiumPage 17

Thermal Control Plan

• Concrete Mix• Maximum Concrete Temperature • Temperature Difference Limit• Cooling System• Insulation• Temperature Monitoring & Reporting

Page 18: 1B Nelson James

August 20, 20092009 Mid-Continent Transportation Research SymposiumPage 18

Concrete Mix

• As developed by the supplier per project specifications– Type IP-F Cement: 420 lbs– Slag: 207 lbs– W/C ratio: 0.42– Class V sand-gravel: 1586 lbs– Limestone: 1322 lbs– Air content: 6.5%

Page 19: 1B Nelson James

August 20, 20092009 Mid-Continent Transportation Research SymposiumPage 19

Maximum Concrete Temperature

• Initial concrete temperature based on several-truck rolling average: maximum of 85°F instead of 70°F

• Concrete temperature after placement: maximum of 160°F as per specifications

Page 20: 1B Nelson James

August 20, 20092009 Mid-Continent Transportation Research SymposiumPage 20

Temperature Difference Limit

• A compromise between the constant limit and the performance-based limit

• Included a variable factor of safety• More conservative in the early age but

less conservative at the design strength• Calculated specifically for the project

mix design

Page 21: 1B Nelson James

August 20, 20092009 Mid-Continent Transportation Research SymposiumPage 21

Temperature Difference Graph

Page 22: 1B Nelson James

August 20, 20092009 Mid-Continent Transportation Research SymposiumPage 22

Cooling System

• Cooling piping system layout was developed for each component (footing, stem, cap,…)

• River water was continuously circulated through the cooling pipes until the insulation is removed

• Flow rate must be sufficiently high so that the water does not heat by more than 2°F to 3°F

Page 23: 1B Nelson James

August 20, 20092009 Mid-Continent Transportation Research SymposiumPage 23

Typical Cooling System - Footing

Page 24: 1B Nelson James

August 20, 20092009 Mid-Continent Transportation Research SymposiumPage 24

Typical Cooling System - Stem

Page 25: 1B Nelson James

August 20, 20092009 Mid-Continent Transportation Research SymposiumPage 25

Insulation

• Used on top surfaces, over side forms and to cover protruding reinforcing steel

• R-values in accordance with the Thermal Control Plan

• To remain in place throughout the monitoring period but may be temporarily removed to prepare for additional placements

Page 26: 1B Nelson James

August 20, 20092009 Mid-Continent Transportation Research SymposiumPage 26

Typical Insulation Blanket

Page 27: 1B Nelson James

August 20, 20092009 Mid-Continent Transportation Research SymposiumPage 27

Temperature Monitoring & Reporting

• To measure and report concrete temperatures at critical locations (center, surface,…)

• Two temperature sensors (a primary and backup) at each location

• Data is recorded on an hourly basis• Report of temperature data (max. and

differential) is issued

Page 28: 1B Nelson James

August 20, 20092009 Mid-Continent Transportation Research SymposiumPage 28

Typical Temperature Sensors

Page 29: 1B Nelson James

August 20, 20092009 Mid-Continent Transportation Research SymposiumPage 29

Typical Thermal Control Graph

0

10

20

30

40

50

60

70

80

90

100

110

120

130

140

150

160

170

0 50 100 150 200 250 300 350

Hours

Tem

pera

ture

or T

empe

ratu

re D

iffer

ence

, °F

Air Temperature,Center Temperature,Top Surface Temperature,Corner Temperature,Side Surface Temperature,Measured Temperature Difference, °F TCP1b Temperature Difference Limit, °F

TCP1b Footing #: Pier 7 Column final temps

Time/Date of Hour 0 :

Page 30: 1B Nelson James

August 20, 20092009 Mid-Continent Transportation Research SymposiumPage 30

Thermal Control Plan Elements

Pier Size Date CastCooling Pipes Size Date Cast

Cooling Pipes

Least Dim. Date Cast

Cooling Pipes

Least Dim. Date Cast

Cooling Pipes

1 43' x 12' x 4'-6 10/20/2008 No 39' x 4' x 7' 12/4/2008 No 4' 12/4/2008 No 4' 1/23/2009 No2 43' x 15' x 5' 11/19/2008 No 38' x 5' x 19' 1/9/2009 No 5' 2/18/2009 No 5' 3/20/2009 No3 43' x 27' x 7'-3 10/30/2008 No 38' x 6' x 16' 11/21/2008 No 6' 1/23/2009 No 6' 2/25/2009 No4 43' x 15' x 5' 11/4/2008 No 38' x 5' x 18' 12/10/2008 No 5' 3/5/2009 No 5' 3/20/2009 No5 43' x 19' x 6'-6 2/3/2009 No 38' x 5' x 20' 2/17/2009 No 5' 3/31/2009 No 5' 5/5/2009 No6 46' x 18' x 5'-9 11/4/2008 No 38' x 8'-4 x 37' 11/19/2008 Yes 8'-4 1/6/2009 No 8'-4 1/22/2009 No7 43' x 25'-6 x 9' 8/5/2008 Yes 38' x 7' x 35' 9/3/2008 Yes 7' 10/15/2008 Yes 7' 10/30/2008 No8 77' x 39'-7 x 10'-6 12/30/2008 Yes 46' x 9' x 41' 2/12/2009 Yes 9' 4/3/2009 No 9' 4/17/2009 Yes9 77' x 39'-7 x 10'-6 6/11/2009 Yes 46' x 9' x 34' 6/30/2009 Yes 9' 8/14/2009 Yes 9'

10 43' x 19' x 5'-3 3/5/2009 No 38' x 8'-4 x 7' 3/13/2009 No 8'-4 5/21/2009 No 8'-4 6/4/2009 Yes11 43' x 17' x 5'-9 1/20/2009 No 38' x 5' x 5' 1/28/2009 No 5' 2/20/2009 No 5' 3/6/2009 No

Footing Stem Columns Cap

Page 31: 1B Nelson James

August 20, 20092009 Mid-Continent Transportation Research SymposiumPage 31

Completion of Thermal Control

• Hottest portion of concrete has reached and begun to cool from its maximum temperature

• Concrete has reached and begun to cool from its maximum temperature difference

• At least 3 days has elapsed• Difference between the hottest portion of

concrete and the average air temperature is < current difference limit

Page 32: 1B Nelson James

August 20, 20092009 Mid-Continent Transportation Research SymposiumPage 32

Summary

• The implementation of the Thermal Control Plan saved money and kept the project on schedule

• No thermal cracking in concrete was reported

Page 33: 1B Nelson James

August 20, 20092009 Mid-Continent Transportation Research SymposiumPage 33

References

• Iowa DOT Standard Specifications and Special Provisions

• Engineering Mass Concrete Structures, November 2006 – PCA by J. Gajda and E. Alsamsam

• ACI 207.4R-05• I-80 over Missouri River

Thermal Control Plan by CTL