18-oct-151 tanzania electric supply company limited tanzania electricity power projects and...

22
Mar 30, 2022 1 TANZANIA ELECTRIC SUPPLY COMPANY LIMITED Tanzania Electricity Power Projects and Available Opportunities PRESENTATION TO TEXTILE DEVELOPMENT UNIT ( TEXTILE INDUSTRY LEADERS TANZANIA) NEW AFRICA HOTEL - DAR ES SALAAM, TANZANIA By Managing Director- TANESCO Eng. Felchesmi J. Mramba

Upload: laurel-newton

Post on 01-Jan-2016

240 views

Category:

Documents


0 download

TRANSCRIPT

Apr 20, 2023 1

TANZANIA ELECTRIC SUPPLY COMPANY LIMITED

Tanzania Electricity Power Projects and Available

OpportunitiesPRESENTATION TO TEXTILE

DEVELOPMENT UNIT ( TEXTILE INDUSTRY LEADERS TANZANIA)

NEW AFRICA HOTEL - DAR ES SALAAM, TANZANIA

ByManaging Director- TANESCO

Eng. Felchesmi J. Mramba

Apr 20, 2023 2

Contents

1. Introduction2. Background and History of TANESCO3. Current Status4. Ongoing and Upcoming Projects5. Current Projects.6. Conclusion

Apr 20, 2023 3

1. Introduction

Apr 20, 2023 4

1. Introduction (…)

Area: 945, 203 km2 Tanzania is in East Africa; has a population of

45 million people (NBS census 2012). Population growth 3% GDP USD33.23 billion in 2013 (World Bank) Customer base 1,409, 966 (as at 31/12/2014) Access to electricity 36% Connectivity: 27% (as at 31/12/2014) Maximum Demand: 934.62MW ( as at

December 2014)

Apr 20, 2023 5

Introduction (…)Future Power Demand 2015 – 2025 (PSMP 2012)

2015 2020 2025

NATIONAL DEMAND 935 3,423 4,574

SOUTHERN POWER POOL (MOZAMBIQUE & ZAMBIA)

100 100

EAST AFRICA POWER POOL (RWANDA & BURUNDI)

50 50

ETHIOPIA Import Import

TOTAL 935 3,573 4,724

Apr 20, 2023 6

Introduction…

S/NO ENERGY RESOURCE POTENTIAL DEVELOPED TO POWER

1 Gas 55Tcf 441MW

2 Hydro: Various sites 4.7GW 562MW

3 Geothermal: 58 sites 5,000MW None

4 Coal 1.9 billion tons None

5 Uranium Oxide 24,550 tons None

6 Wind: 7 sites Average wind speed 5 – 8m/s None

7 Biomass: wood fuel and agricultural waste

500MW 35MW

8 Solar: Several sites Average daily solar insolation 4.6/kWh/m2

About 4MW

9 Tidal Under study None

Available Energy Sources

Apr 20, 2023 7

2. Background and History of TANESCO

A vertically integrated Parastatal organization under the Ministry of Energy and Minerals

Established in 1964 Incorporated under the Companies Ordinance

Cap 212 (now Company Act) Directed by the Board of Directors The Ministry of Energy and Minerals (MEM) is

responsible for policy formulation and overall sector supervision.

Apr 20, 2023 8

2. Background and History of TANESCO

The Energy and Water Utilities Regulatory Authority (EWURA) is the sector regulator.

TANESCO Core business are Generation, Transmission and Distribution of electricity

Sales electricity to the mainland and bulk power supply to the Island of Zanzibar.

Apr 20, 2023 9

Current Status (…)

Power Generation Mix The installed capacity in the

main grid is 1226.24MW. Hydro: 561.84 MW (46%) and Thermal: 664.4 MW (54%).

Capacity of thermal plants (Gas: 441MW: Fuel Oil: 223.4 MW)

Off-grid stations total capacity is 73.77 MW

Highest grid system demand is 934.62 MW recorded in December 2014 .

Apr 20, 2023 10

Current Status (…).

Transmission System :

Transmission network comprises of

2,732 km of 220kV lines;

1,555.79 km of 132 kV lines; and

578.7 km of 66 kV lines, totalling

4,866.85km by the end of

December 2014.

Distribution System :

Total distribution network (MV lines) is 20,704 km, constituting 15,176 km of 33kV line, 5,528km of 11kV lines; and 40,094 km of low voltage (400 and 230V) lines.

Apr 20, 2023 11

4. Ongoing and Upcoming Projects

Kinyerezi I Under Construction

Apr 20, 2023 12

Ongoing and Upcoming Projects…

S/NO PROJECT DESCRPTION SOURCE OF FUNDING

PROJECT COST

STATUS COMPLETION DATE

1 Kinyerezi I - 150MW gas fired power plant

GoT USD 183m Construction 90% completed

SEPTEMBER 2015

2 Kinyerezi II – 240MW gas fired power plant

GoT - 15%JBIC – 85%Contractor: Sumitomo Corporation

USD 344million

GoT is soliciting funds for financing the 15% of the contract value of the project

2017

3 Kinyerezi III – 600MW gas fired power plant

China Power Investment (CPI)

USD 401million

JV Company formed and feasibility study is under review

TBA

4 Kinyerezi IV – 330MW gas fired power plant

Poly Technology Inc. of China

USD 400million.

Preliminary feasibility study is under review

TBA

5 Somanga Fungu 320MW Gas Fired Power Plant

Kilwa Energy - IPP

USD 365.6 Million

Investor working with banks to achieve financial closure

2017

Apr 20, 2023 13

Ongoing and Upcoming Projects…S/NO PROJECT DESCRPTION SOURCE OF

FUNDINGPROJECT COST

STATUS COMPLETION DATE

6 GeoWind 50MW Wind Power Plant at Singida

Exim Bank of China

USD 136 Million

Discussion to conclude financial closure is in progress

2017

7 150MW Solar PV in Shinyanga Not yet secured USD 185million

Under System review and equipment design

2019

8 400MW gas fired power plant at Mtwara with Symbion (T)

Symbion USD 396.577million

Feasibility study is under review

2019

9 87MW hydropower plant to be developed at Kakono in Kagera Region

Not yet secured Estimated cost USD 379.4million

Feasibility Study completed Solicitation of financing in progress

2019

10 44.8MW hydropower plant to be developed at Malagarasi river in Kigoma

Not yet secured Estimated cost: USD 149.5million

Feasibility Study completedSolicitation of financing in progress

2020

Apr 20, 2023 14

Ongoing and Upcoming Projects…

S/NO PROJECT DESCRPTION SOURCE OF FUNDING

PROJECT COST

STATUS COMPLETION DATE

11 400kV Iringa – Shinyanga transmission project (Backbone)

IDA, AfDB, JICA, EIB and Korea EDCF

USD 470 Million

Construction 20% completed

June 2016

12 400kV North East Grid Dar – Chalinze – Tanga - Arusha

GoT - 15%Exim Bank of China – 85 %

USD 692.7million

GoT is soliciting funds for financing the 15% of the contract value of the project

2017

13 200kV Makambako – Songea transmission line

SIDA & GoT USD 111.43million

Distribution component 5% completed

2017

14 400kV North West Grid Phase 1: Mbeya - Sumbawanga

Financing not firmed

USD 259.2million

Contract for upgrading the feasibility study from 220kV to 400kV by SWECO Signed

2018

15 400 kV Singida-Arusha transmission line

AfDB, JICA USD 258.82 million

Valuation of properties for compensation has started

2018

Apr 20, 2023 15

Ongoing and Upcoming Projects…

S/NO PROJECT DESCRPTION SOURCE OF FUNDING

PROJECT COST

STATUS COMPLETION DATE

16 400 kV Chalinze-Dodoma transmission line

Financing not firmed

Estimated USD 175 million

Procurement of Consultant for feasibility study is in progress

2018

17 220 kV Bulyanhulu-Geita transmission line

Arab Bank for Economic Development in Africa (BADEA), OFID & GoT

USD 30million Contract signing with Consultant for project supervision completed

2017

18 220kV T/L Geita – Nyakanazi transmission line

KfW, AFD, EU & GoT

Euro 29million & TZS 5billion

Contract signing with Consultant for project supervision is underway

2017

19 Improving the reliability of Electric power supply in the city of Dar es Salaam

Finish EUR. 21.8million

Construction 70% completed

October, 2015

Apr 20, 2023 16

Ongoing and Upcoming Projects…

S/NO PROJECT DESCRPTION SOURCE OF FUNDING

PROJECT COST

STATUS COMPLETION DATE

20 Tanzania Energy Development and Access Expansion Project (TEDAP) - Transmission

IDA USD 34,252,345.78

Construction 70% completed

March, 2016

21 Tanzania Energy Development and Access Expansion Project (TEDAP) - Distribution

IDA USD 43,543,460.07

Construction 60% completed

June, 2016

22 Electricity V AfDB & GoT USD 51.25million

Construction 85% completed

October, 2015

Apr 20, 2023 17

Ongoing and Upcoming Projects.

S/NO PROJECT DESCRPTION SOURCE OF FUNDING

PROJECT COST

STATUS COMPLETION DATE

23 New 132kV Kilimanjaro – Arusha Transmission Line and Rehabilitation of Kiyungi Substation.

Korean Export-Import Bank through EDCF

USD 20,176,384

Construction 85% completed

December, 2015

24 Rehabilitation of Hale Hydro Plant 21MW

Co-financed by SIDA (60% grant) and GoT (40% commercial loan)

SEK 197 Million

The contract for the technical consultant has been signed

2019

25 Rehabilitation and Upgrade of Grid Network.

AFD EUR. 53.0M Procurement of Consultant for supervision of the project is underway

2017

26 Project for Reinforcement of Power Distribution in Dar es salaam Region

JICA Japanese Yen 4.41 Billion equivalent to USD 38 Million

Contract signing with Consultant for project supervision is underway

2017

Apr 20, 2023 18

Future Grid Map by 2035

Apr 20, 2023 19

ZAMBIA – TANZANIA – KENYA (ZTK) TRANSMISSION LINE

Apr 20, 2023 20

5 .CURRENT PROJECTS FUNDED BY KOREAN’S

S/No. PROJECT DESCRIPTION SOURCE OF FUNDING

PROJECT COST STATUS COMPLETION DATE

1. Power transmission line expansion project between Kilimanjaro and Arusha

Korea Exim Bank – EDCF fund (also supported by World Bank, JICA, AfDB)

USD 25 Million On-going March, 2016

2. Power transmission line expansion project between Iringa and Sinyanga

Korea Exim Bank – EDCF fund (also supported by World Bank, AfDB, JICA, EIB)

USD 36 Million On-going TBA

Apr 20, 2023 21

6. Conclusion

The current situation shows that there is intensive

investment in generation, transmission and

distribution of Power in Tanzania which will stabilise

Power availability in the Country.

The Government of Tanzania still invites potential

investors to invest in Electric Power Generation,

Transmission, and Distribution to curb the future

demands.

Apr 20, 2023 22

THANK YOU