13_as_7

Upload: ujjal-regmi

Post on 04-Jun-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/13/2019 13_as_7

    1/4

    CONSTRUCTION CONTRACTS (AS-7)

    A. Types of Construction Contract: Construction contracts are of two types:

    a. Fie! price contracts -In this case of contract, contractor agrees for fixed price of thecontract or fixed rate/unit. However, in some cases the contract price is subject to

    escalation.

    ". Cost-p#us contract -In these contracts, contractor is reimbursed the cost fixed percentage ofprofit.

    $. Ca#cu#atin% t&e profit or #oss of a construction contract: rofit or loss onconstruction contract is Contract revenue ! Contract Cost.

    C. Contract re'enue: Contract revenue includes/ excludes the following:

    A!!Inc#u!es:

    a. "evenue/price agreed as per Contract.

    ". "evenue arising due to escalation clause.

    c. #hen a fixed price contract involves a fixed price per unit of output, contract revenueincreases as the number of units is increased.

    !. $ariations, Claims % Incentive payments.

    ess*c#u!es:

    a. enalties arising from delays caused by the contractor in the completion of the contract.

    ". $ariations.

    *. A 'ariation is an instruction by the customer for a change in the wor& to beperformed. It may lead to an increase/decrease in contract revenue. $ariations are consideredonly when:

    a. 'here is a certainty of collection (it is probable that the customer will accept) the variation%

    ". 'here is a certainty of measurement.

    F. A c#ai+ is an amount that the contractor see&s to collect from the customer asreimbursement for costs not included in the contract price. *xamples are customer causeddelays. Claims are considered only when:

    a. 'here is a certainty of collection %

    ". 'here is a certainty of measurement.

    ,. Incenti'e pay+entsare additional amounts payable to the contractor if specifiedperformance standards are met or exceeded. *x. an incentive payment to the contractor for

    early completion of the contract. 'hese are considered only when:a. 'here is a certainty of collection %

    ". 'here is a certainty of measurement.

    . ercenta%e of co+p#etion +et&o! (C/):+s per + -, the contract revenue willbe recognised with reference to '+* 0 C12*'I3 at the reporting date. 'his is calledC/.

    I. 0eter+ination of sta%e of co+p#etion:

    a. Cost to Cost +et&o!: 'he percentage of completion would be estimated by comparingtotal cost incurred to date with total cost expected for the entire contract:

    ercentage of Completion 4 Cost to dateCost incurred 5 *stimated cost to complete

    Current period revenue from Contract 4 Contract price 6 ercentage of completion 7"evenue previously recognised.

    Accounting Standards___________________________________________ 1

    MASTER MINDS

    6 899

  • 8/13/2019 13_as_7

    2/4

    ". Tec&nica# sur'ey +et&o!:

    *.%.:+ construction contract of a two floor building for "s. 8; la&hs (with a ;9 margin)

    0i'isions ofcontract

    Tec&nica#Co+p#etion

    Cost toco+p#ete

    0oundation

  • 8/13/2019 13_as_7

    3/4

    articu#ars 9ears

    1st n! ;r!

    Initial contract revenue"evenue increase due to escalation in =nd

    yearClaim from contracteeIncentive paymentsenalties

    8999!!!!!!!!!!!!

    8999=99!!!!!!;9

    8999!!!

    8998;9!!!

    So#.: Calculation of contract revenue:

    articu#ars 9ears

    1st n! ;r!

    Initial contract valueIncrease in revenue due toescalationClaimsIncentiveenaltiesContract "evenue

    8999!!!!!!!!!!!!

    8999

    8999=99!!!!!!

    (;9)88;9

    8999

    =998998;9(;9)8>99

    Q.2. 1HI' 2'A. has underta&en bridge construction contract to be constructed in < years. Initialcontract revenue "s.B99 crores. Initial contract cost "s.99 crores.

    articu#ars 9ears

    1st n! ;r!

    *stimated contract costIncrease in contract revenue*stimated additional increase costContract cost incurred upto

    9;!!!!!!

    8D8

    !!!=98;

    ;>

    !!!!!!!!!

    =9

    +t the end of =ndyear cost incurred includes "s.89 crores, for material stored at the sites to beused in ! 89)rofit9ear III:"evenue (B=96899)*xpensesrofit

    898D88B

    D>>;->-9

    B=9=9899

    !!!!!!!!!

    898D88B

    D>>;->-9

    898D88B

    >D>>8DEincl. 89crores mat)

    =9

    B99=9

    B=9=9

    =9

    Accounting Standards___________________________________________ 3

    MASTER MINDS

  • 8/13/2019 13_as_7

    4/4

    tage of completion =9(8D8/9;6 899)

    -9(;>!89/=9

    6 899F

    899(=9/=96 899)

    Q.3. + firm of contractors obtained a contract for construction of bridges across river Grishna.'he following details are available for the year ended . It estimated construction cost initially at "s.-9 crores. Contract was estimated to becompleted in three years. However, when starting the wor& it was found that there were roc&sunderground at construction site and cost shall increase by "s.