13_as_7
TRANSCRIPT
-
8/13/2019 13_as_7
1/4
CONSTRUCTION CONTRACTS (AS-7)
A. Types of Construction Contract: Construction contracts are of two types:
a. Fie! price contracts -In this case of contract, contractor agrees for fixed price of thecontract or fixed rate/unit. However, in some cases the contract price is subject to
escalation.
". Cost-p#us contract -In these contracts, contractor is reimbursed the cost fixed percentage ofprofit.
$. Ca#cu#atin% t&e profit or #oss of a construction contract: rofit or loss onconstruction contract is Contract revenue ! Contract Cost.
C. Contract re'enue: Contract revenue includes/ excludes the following:
A!!Inc#u!es:
a. "evenue/price agreed as per Contract.
". "evenue arising due to escalation clause.
c. #hen a fixed price contract involves a fixed price per unit of output, contract revenueincreases as the number of units is increased.
!. $ariations, Claims % Incentive payments.
ess*c#u!es:
a. enalties arising from delays caused by the contractor in the completion of the contract.
". $ariations.
*. A 'ariation is an instruction by the customer for a change in the wor& to beperformed. It may lead to an increase/decrease in contract revenue. $ariations are consideredonly when:
a. 'here is a certainty of collection (it is probable that the customer will accept) the variation%
". 'here is a certainty of measurement.
F. A c#ai+ is an amount that the contractor see&s to collect from the customer asreimbursement for costs not included in the contract price. *xamples are customer causeddelays. Claims are considered only when:
a. 'here is a certainty of collection %
". 'here is a certainty of measurement.
,. Incenti'e pay+entsare additional amounts payable to the contractor if specifiedperformance standards are met or exceeded. *x. an incentive payment to the contractor for
early completion of the contract. 'hese are considered only when:a. 'here is a certainty of collection %
". 'here is a certainty of measurement.
. ercenta%e of co+p#etion +et&o! (C/):+s per + -, the contract revenue willbe recognised with reference to '+* 0 C12*'I3 at the reporting date. 'his is calledC/.
I. 0eter+ination of sta%e of co+p#etion:
a. Cost to Cost +et&o!: 'he percentage of completion would be estimated by comparingtotal cost incurred to date with total cost expected for the entire contract:
ercentage of Completion 4 Cost to dateCost incurred 5 *stimated cost to complete
Current period revenue from Contract 4 Contract price 6 ercentage of completion 7"evenue previously recognised.
Accounting Standards___________________________________________ 1
MASTER MINDS
6 899
-
8/13/2019 13_as_7
2/4
". Tec&nica# sur'ey +et&o!:
*.%.:+ construction contract of a two floor building for "s. 8; la&hs (with a ;9 margin)
0i'isions ofcontract
Tec&nica#Co+p#etion
Cost toco+p#ete
0oundation
-
8/13/2019 13_as_7
3/4
articu#ars 9ears
1st n! ;r!
Initial contract revenue"evenue increase due to escalation in =nd
yearClaim from contracteeIncentive paymentsenalties
8999!!!!!!!!!!!!
8999=99!!!!!!;9
8999!!!
8998;9!!!
So#.: Calculation of contract revenue:
articu#ars 9ears
1st n! ;r!
Initial contract valueIncrease in revenue due toescalationClaimsIncentiveenaltiesContract "evenue
8999!!!!!!!!!!!!
8999
8999=99!!!!!!
(;9)88;9
8999
=998998;9(;9)8>99
Q.2. 1HI' 2'A. has underta&en bridge construction contract to be constructed in < years. Initialcontract revenue "s.B99 crores. Initial contract cost "s.99 crores.
articu#ars 9ears
1st n! ;r!
*stimated contract costIncrease in contract revenue*stimated additional increase costContract cost incurred upto
9;!!!!!!
8D8
!!!=98;
;>
!!!!!!!!!
=9
+t the end of =ndyear cost incurred includes "s.89 crores, for material stored at the sites to beused in ! 89)rofit9ear III:"evenue (B=96899)*xpensesrofit
898D88B
D>>;->-9
B=9=9899
!!!!!!!!!
898D88B
D>>;->-9
898D88B
>D>>8DEincl. 89crores mat)
=9
B99=9
B=9=9
=9
Accounting Standards___________________________________________ 3
MASTER MINDS
-
8/13/2019 13_as_7
4/4
tage of completion =9(8D8/9;6 899)
-9(;>!89/=9
6 899F
899(=9/=96 899)
Q.3. + firm of contractors obtained a contract for construction of bridges across river Grishna.'he following details are available for the year ended . It estimated construction cost initially at "s.-9 crores. Contract was estimated to becompleted in three years. However, when starting the wor& it was found that there were roc&sunderground at construction site and cost shall increase by "s.