Page 1: 13 Resource Allocation and Project Crashing

Project Management

Resource Allocation

Page 2: 13 Resource Allocation and Project Crashing

Resource Allocation

• Time allocation is called scheduling• Related to time is allocating other resources• Altering schedules can alter the need for

resources and timing of resource needs• At any given time a firm will have fixed

level of resources• But in Project environment the needs keep

changing

Page 3: 13 Resource Allocation and Project Crashing

Resource Allocation

• Resources include 5 Ms• Example.

– Suppose for project X the need for a particular resource varies between 70 to 120%

– This means this resource will be under utilized for some time and over utilized at some other

– By smoothing the use of resource (by adjusting the project schedule) it may be possible to make efficient use of the resource.

Page 4: 13 Resource Allocation and Project Crashing

This topic covers …….Resource problems.

• Trades offs involved • Allocation to one project and multiple projects• Critical Path method – Crashing a Project• Resource loading and Leveling• Resource Constrained Schedules• Multi project Resource Management• Critical Chain

Page 5: 13 Resource Allocation and Project Crashing

Critical Path Method - Crashing a Project

• CPM includes a way of relating the project schedule to the level of physical resources allocated to the project

• This allows the project manager to trade time for cost, or vice versa

• In CPM, two activity times and two costs are specified, if appropriate for each activity

Chapter 9-1

Page 6: 13 Resource Allocation and Project Crashing

Critical Path Method - Crashing a Project

• The first time/cost combination is called normal, and the second set is referred to as crash

• Normal times are “normal” in the same sense as the ‘m’ time estimate of the three times used in PERT

• Crash times result from an attempt to expedite the activity by the application of additional resources

Chapter 9-2

Page 7: 13 Resource Allocation and Project Crashing

Critical Path Method - Crashing a Project

• Careful planning is critical when attempting to expedite (crash) a project

• Expediting tends to create problems; and the solution to one problem often creates several more problems that require solutions

• Some organizations have more than one level of crashing

Chapter 9-3

Page 8: 13 Resource Allocation and Project Crashing

Critical Path Method - Crashing a Project

• Use of three times may reduce this kind of situation to some extent, but can not totally rule out the same

• Deterministic times are more prone to changes

• Lat minute changes by clients, unforeseen situations make crashing away of life

Page 9: 13 Resource Allocation and Project Crashing

Example

• We need to crash the activities of some project to ensure timely completion

• We have the labor and materials• But we do not have specialized equipment• Our equipment is committed else where• We can not hire it locally• We can hire it from a far off place but it

costs a lot

Page 10: 13 Resource Allocation and Project Crashing

Crashing – Sample Network

1 2

3

4

5

6

73

6

10

11

8

5

6

0

Critical Path = 3 + 6 + 8 + 6 = 23 Time Units

Page 11: 13 Resource Allocation and Project Crashing

Crashing – An Example

Activity Normal Time

Normal Cost

Crash Time

Crash Cost Slope

Max

Crsh Tm

1-2 3 $50 2 $70

2-3 6 $80 4 $160

2-4 10 $60 9 $90

2-5 11 $50 7 $150

3-6 8 $100 6 $160

5-7 5 $40 4 $70

6-7 6 $70 6 $70

Page 12: 13 Resource Allocation and Project Crashing

Cost/Time Slope

• Step1 compute a cost /time slope that can be crashed.

• Slope is defined as • Slope = (Crash cost – Normal cost)/(Crash Time –

Normal time)• Slope is the “Cost Per day of crashing a project”• Slope is negative which means “As time required

for a project or task is reduced, cost is increased”

Page 13: 13 Resource Allocation and Project Crashing

Cost/Time Slope

• In the above activity 6-7 can not be crashed• Calculating the slope this way might give the

impression that activities can be crashed in increments of one day

• But this is not true• Example – An activity could be carried out in

eight days or Four days (No intermediary times are possible)

• The crash has to be four days in this case

Page 14: 13 Resource Allocation and Project Crashing

Crashing – Sample Network

1 2

3

4

5

6

7$50

$80

$100

$70

“Normal” Project Total Cost = $50 + $80 + $100 + $70 + $60 + $50 + $40 = $450

Page 15: 13 Resource Allocation and Project Crashing

Crashing

• First task – Develop a table or graph of cost of the project as a function of the project’s various completion dates

• Starting with the normal schedule, crash selected activities one at a time, to decrease the project duration at the minimum additional cost

Page 16: 13 Resource Allocation and Project Crashing

Crashing

• Two principles– 1. Focus on critical path when trying to shorten

the duration of the project. (with the exception that the resource needed for one activity, not on the critical path is needed for another project)

– 2. when shortening a project duration, select the least expensive way to do it.

• AOA example is easier to illustrate than AON

Page 17: 13 Resource Allocation and Project Crashing

Crashing – An Example

Activity Normal Time

Normal Cost

Crash Time

Crash Cost Slope

Max

Crsh Tm

1-2 3 $50 2 $70 -20 1

2-3 6 $80 4 $160 -40 2

2-4 10 $60 9 $90 -30 1

2-5 11 $50 7 $150 -25 4

3-6 8 $100 6 $160 -30 2

5-7 5 $40 4 $70 -30 1

6-7 6 $70 6 $70 0 0

Page 18: 13 Resource Allocation and Project Crashing

Crashing – Sample Network

1 2

3

4

5

6

7$50

$80

$100

$70

“Normal” Project Total Cost = $50 + $80 + $100 + $70 + $60 + $50 + $40 = $450

Critical Path = 23 Days

3

68

6

$60

$50 $40

10

11 5

Page 19: 13 Resource Allocation and Project Crashing

Crashing – Sample Network

1 2

3

4

5

6

7$70

$80

$160

$70

“Crashed” Project Total Cost = $70+ $80 + $160 + $70 + $60 + $50 + $40 = $530

Critical Path = 23 Days

2

66

6

$60

$50 $40

10

11 5

“Crashed”Path = 20 Days

Page 20: 13 Resource Allocation and Project Crashing

Crashing – Sample Network

1 2

3

4

5

6

7$70

$160

$160

$70

“Crashed” Project Total Cost = $70+ $160 + $160 + $70 + $60 + $50 + $40 = $610

Critical Path = 23 Days

2

46

6

$60

$50 $40

10

11 5

“Crashed”Path = 18 Days

Page 21: 13 Resource Allocation and Project Crashing

Crashing – Sample Network

• Further crashing of CP is not possible as we have used up the complete (maximum) crash time possible.

• Crashing other paths will not shorten the project duration

Page 22: 13 Resource Allocation and Project Crashing

Fast-Tracking

• Another way to expedite a project is known as “fast-tracking”

• It refers to overlapping the design and build phases of a project

• Because design is usually completed before construction starts, overlapping the two activities will result in shortening the project duration

Chapter 9-4

Page 23: 13 Resource Allocation and Project Crashing

The Resource Allocation Problem

• A shortcoming of most scheduling procedures is that they do not address the issues of resource utilization and availability

• Scheduling procedures tend to focus on time rather than physical resources

• Time itself is always a critical resource in project management, one that is unique because it can neither be inventoried nor renewed

Chapter 9-5

Page 24: 13 Resource Allocation and Project Crashing

The Resource Allocation Problem

• Schedules should be evaluated not merely in terms of meeting project milestones, but also in terms of the timing and use of scarce resources

• A fundamental measure of the project manager’s success in project management is the skill with which the trade-offs among performance, time, and cost are managed

Chapter 9-6

Page 25: 13 Resource Allocation and Project Crashing

The Resource Allocation Problem

• The extreme points of the relationship between time use and resource use are these:– Time Limited: The project must be finished by a

certain time, using as few resources as possible. But it is time, not resource usage, that is critical

– Resource Limited:The project must be finished as soon as possible, but without exceeding some specific level of resource usage or some general resource constraint

Chapter 9-7

Page 26: 13 Resource Allocation and Project Crashing

The Resource Allocation Problem

• If all three variables - time, cost, specifications - are fixed, the system is “overdetermined”

• In this case, the project manager has lost all flexibility to perform the trade-offs that are so necessary to the successful completion of projects

• A system-constrained task requires a fixed amount of time and known quantities of resources

Chapter 9-8

Page 27: 13 Resource Allocation and Project Crashing

Resource Loading

• Resource loading describes the amounts of individual resources an existing schedule requires during specific time periods

• The loads (requirements) of each resource type are listed as a function of time period

• Resource loading gives a general understanding of the demands a project or set of projects will make on a firm’s resources

Chapter 9-9

Page 28: 13 Resource Allocation and Project Crashing

Resource Loading

• Is an excellent guide for early, rough project planning

• Because the project action plan is the source of information on activity precedences, durations, and resources requirements, it is the primary input for both the project schedule and its budget

• The action plan links the schedule directly to specific demands for resources

Chapter 9-10

Page 29: 13 Resource Allocation and Project Crashing

Resource Loading

• The PERT/CPM network technique can be modified to generate time-phased resource requirements

• The project manager must be aware of the ebbs and flows of usage for each input resource throughout the life of the project

• It is the project manager’s responsibility to ensure that the required resources, in the required amounts, are available when and where they are needed

Chapter 9-11

Page 30: 13 Resource Allocation and Project Crashing

Resource Leveling

• Resource leveling aims to minimize the period-by-period variations in resource loading by shifting tasks within their slack allowances

• The purpose is to create a smoother distribution of resource usage

• Several advantages include: – Less hands-on management is required

– May be able to use a “just-in-time” inventory policy

Chapter 9-12

Page 31: 13 Resource Allocation and Project Crashing

Resource Leveling

• When resources are leveled, the associated costs also tend to be leveled

• The project manager must be aware of the cash flows associated with the project and of the means of shifting them in ways that are useful to the parent firm

• Resource leveling is a procedure that can be used for almost all projects, whether or not resources are constrained

Chapter 9-13

Page 32: 13 Resource Allocation and Project Crashing

Resource Leveling - Example

Page 33: 13 Resource Allocation and Project Crashing

Constrained Resource Scheduling

• There are two fundamental approaches to constrained allocation problems:– Heuristic Methods– Optimization Models

• Heuristic approaches employ rules of thumb that have been found to work reasonably well in similar situations

• Optimization approaches seek the best solutions but are far more limited in their ability to handle complex situations and large problems

Chapter 9-14

Page 34: 13 Resource Allocation and Project Crashing

Heuristic Methods

• Heuristic approaches to constrained resource scheduling problems are in wide, general use for a number of reasons:– 1. They are the only feasible methods of attacking the

large, nonlinear, complex problems that tend to occur in the real world of project management

– 2. While the schedules that heuristics generate may not be optimal, they are usually quite good- certainly good enough for most purposes

Chapter 9-15

Page 35: 13 Resource Allocation and Project Crashing

Heuristic Methods

• Most heuristic solution methods start with the PERT/CPM schedule and analyze resource usage period by period, resource by resource

• In a period when the available supply of a resource is exceeded, the heuristic examines the tasks in that period and allocates the scarce resource to them sequentially, according to some priority rule

• Technological necessities always take precedence

Chapter 9-16

Page 36: 13 Resource Allocation and Project Crashing

Heuristic Methods

• Common priority rules:– As soon as possible– As late as possible– Shortest task first– Most resources first– Minimum slack first– Most critical followers– Most successors– Arbitrary

Chapter 9-17

Page 37: 13 Resource Allocation and Project Crashing

Heuristic Methods

• Most priority rules are simple adaptations of the heuristics used for the traditional “job shop scheduling” problem of production/operations management

• Most heuristics use a combination of rules: a primary rule, and a secondary rule to break ties

• As the scheduling heuristic operates, one of two events will result:– The routine runs out of activities before it runs out of resources

– The routine runs out of resources before all activities have been scheduled

Chapter 9-18

Page 38: 13 Resource Allocation and Project Crashing

Optimizing Methods

• The methods to find an optimal solution to the constrained resource scheduling problem fall into two categories:

– Mathematical programming

– Enumeration

• Mathematical programming can be thought of as liner programming (LP) for the most part

Chapter 9-19

Page 39: 13 Resource Allocation and Project Crashing

Optimizing Methods

• Linear programming is usually not feasible for reasonably large projects where there may be a dozen resources and thousands of activities

• In the late 1960s and early 1970s, limited enumeration techniques were applied to the constrained resource problem

• Tree search, and branch and bound methods were devised to handle up to five resources and 200 activities

Chapter 9-20

Page 40: 13 Resource Allocation and Project Crashing

Multiproject Scheduling and Resource Allocation

• The most common approach to scheduling and allocating resources to multiple projects is to treat the several projects as if they were each elements of a single large project

• Another way of attacking the problem is to consider all projects as completely independent

• To describe such a system properly, standards are needed by which to measure scheduling effectiveness

Chapter 9-21

Page 41: 13 Resource Allocation and Project Crashing

Multiproject Scheduling and Resource Allocation

• Three important parameters affected by project scheduling

are:

– Schedule slippage

– Resource utilization

– In-process inventory

• The organization (or the project manager) must select the

criterion most appropriate for its situation

Chapter 9-22

Page 42: 13 Resource Allocation and Project Crashing

Multiproject Scheduling and Resource Allocation

• Schedule slippage, often considered the most important of the criteria, is the time past a project’s due date or delivery date when the project is completed

• Resource utilization is of particular concern to industrial firms because of the high cost of making resources available

• The amount of in-process inventory concerns the amount of work waiting to be processed because there is a shortage of some resource

Chapter 9-23

Page 43: 13 Resource Allocation and Project Crashing

Multiproject Scheduling and Resource Allocation

• All criteria cannot be optimized at the same time

• As usual, the project manager will have to make trade-offs among the criteria

• A firm must decide which criterion to evaluate its various scheduling and resource allocation options

Chapter 9-24

Page 44: 13 Resource Allocation and Project Crashing

Mathematical Programming

• Mathematical programming can be used to obtain solutions to certain types of multiproject scheduling problems

• These procedures determine when an activity should be scheduled, given resource constraints

• Mathematical programming, however, is rarely used in project management to handle the multiproject problem (mostly, heuristics are used)

Chapter 9-25

Page 45: 13 Resource Allocation and Project Crashing

Mathematical Programming

• The three most common objectives of mathematical programming are:– 1. Minimum total throughput time (time in the shop) for all

projects

– 2. Minimum total completion time for all projects

– 3. Minimum total lateness or lateness penalty for all projects

• These objectives are most appropriate for ‘job shop’

type solutions to resource constraints

Chapter 9-26

Page 46: 13 Resource Allocation and Project Crashing

Heuristic Techniques

• There are scores of different heuristic-based procedures in existence

• They represent rather simple extensions of well-known approaches to job-shop scheduling:– Resource Scheduling Method

– Minimum late finish time

– Greatest resource demand

– Greatest resource utilization

– Most possible jobs

Chapter 9-27

Page 47: 13 Resource Allocation and Project Crashing

Critical Chain

• Eliyahu M. Goldratt’s “Theory of Constraints”

• Traditional Project Estimation Techniques Ineffective– Time and Resource Constraints Usually Violated– PMs Rely on “Padding” of Schedules and Budgets– Unknown Nature of Event Interaction

• Fear, Uncertainty, Doubt

• Psychological, Organizational, and Physical

Page 48: 13 Resource Allocation and Project Crashing

Critical Chain - Approach• Bottleneck Management

– Activities with Several Predecessors and/or Successors

– Add “Time Buffers” at Bottleneck Events• “Safety Stock” Equivalent in Manufacturing• Just-in-Time with “Just-in-Case”• Statistically-derived “Path Buffers”

– Establish the Critical Chain for Scarce Resources– Prioritization of Resources in Chain Events

• Communication of “Walt” Needs is Critical to Success