Page 1: 1.040 Project Management - MIT OpenCourseWare...• SECTION B : ARC CONSTRUCTION, TURKEY DO IT FASTER! In April 2003, the second item became: Deliver 389 km of paved road by December

MIT OpenCourseWarehttp://ocw.mit.edu

1.040 Project Management Spring 2009

For information about citing these materials or our Terms of Use, visit: http://ocw.mit.edu/terms.

Page 2: 1.040 Project Management - MIT OpenCourseWare...• SECTION B : ARC CONSTRUCTION, TURKEY DO IT FASTER! In April 2003, the second item became: Deliver 389 km of paved road by December

Moavenzadeh Institute of Technology

20 February 2009 The Louis Berger Group

WORKING THE GLOBE:

Improving the Built Environment

Page 3: 1.040 Project Management - MIT OpenCourseWare...• SECTION B : ARC CONSTRUCTION, TURKEY DO IT FASTER! In April 2003, the second item became: Deliver 389 km of paved road by December

THREE STORIES:

� Cutting Edge Urban Planning: Abu Dhabi

� Multicultural Joint Venturing: Qatar

� Post-conflict Reconstruction: Afghanistan

Page 4: 1.040 Project Management - MIT OpenCourseWare...• SECTION B : ARC CONSTRUCTION, TURKEY DO IT FASTER! In April 2003, the second item became: Deliver 389 km of paved road by December

BUT FIRST

� Context, and � Why I think

THE GRASS IS GREENER…

Page 5: 1.040 Project Management - MIT OpenCourseWare...• SECTION B : ARC CONSTRUCTION, TURKEY DO IT FASTER! In April 2003, the second item became: Deliver 389 km of paved road by December

An estimated $1 trillion in 1975

An estimated $4 trillion in 2000

Global Construction Market

Page 6: 1.040 Project Management - MIT OpenCourseWare...• SECTION B : ARC CONSTRUCTION, TURKEY DO IT FASTER! In April 2003, the second item became: Deliver 389 km of paved road by December

?

The US Construction Market as a

Percentage of the World Market

0

10

20

30

40

50

1975 2000 2025

USA’s Market Share

Page 7: 1.040 Project Management - MIT OpenCourseWare...• SECTION B : ARC CONSTRUCTION, TURKEY DO IT FASTER! In April 2003, the second item became: Deliver 389 km of paved road by December

And what will we do with the money at home?

� Changing windows and adding insulation to homes

� Action on long deferred maintenance of vital infrastructure

� A few wind farms, PV fields and ethanol

� Slow movement towards mass transit and still no high speed rail

Page 8: 1.040 Project Management - MIT OpenCourseWare...• SECTION B : ARC CONSTRUCTION, TURKEY DO IT FASTER! In April 2003, the second item became: Deliver 389 km of paved road by December

While the world speeds forward:

� Maglev � 572 kph JR test track � Shanghai already in revenue service

� Cutting edge cities like Masdar: � Carbon neutral, zero waste � An MIT project

Page 9: 1.040 Project Management - MIT OpenCourseWare...• SECTION B : ARC CONSTRUCTION, TURKEY DO IT FASTER! In April 2003, the second item became: Deliver 389 km of paved road by December

BERGER’S ROLE

� Design Competitions � Overall � MIST � HQ

� Program Manager for HQ Building � BIM � Being there

Page 10: 1.040 Project Management - MIT OpenCourseWare...• SECTION B : ARC CONSTRUCTION, TURKEY DO IT FASTER! In April 2003, the second item became: Deliver 389 km of paved road by December

QATAR PROGRAM MANAGEMENT

� Barwa’s Problem � Scope of Services � Organic Growth too slow � JV structuring � Conflict of Interest

Page 11: 1.040 Project Management - MIT OpenCourseWare...• SECTION B : ARC CONSTRUCTION, TURKEY DO IT FASTER! In April 2003, the second item became: Deliver 389 km of paved road by December

Assisting with Post-conflict Reconstruction

� 25 countries emerging from extended periods of civil strife in addition to Afghanistan and Iraq, including Angola, Bosnia, Cambodia, Croatia, El Salvador, Eritrea, Ethiopia, Ghana, Honduras, Iraq, Kosovo, Macedonia, Mozambique, Nicaragua, Nigeria, Philippines, Romania, Rwanda, Sierra Leone, Timor, Uganda and the Democratic Republic of Congo.

Page 12: 1.040 Project Management - MIT OpenCourseWare...• SECTION B : ARC CONSTRUCTION, TURKEY DO IT FASTER! In April 2003, the second item became: Deliver 389 km of paved road by December

Many Masters >conflicting priorities

� Government � Funding Agencies � The People

� Schedule � Cost � Capacity Building

Page 13: 1.040 Project Management - MIT OpenCourseWare...• SECTION B : ARC CONSTRUCTION, TURKEY DO IT FASTER! In April 2003, the second item became: Deliver 389 km of paved road by December

Old Rules --- New Realities

� Communications � Security � Financing Operating Costs � Violence

Page 14: 1.040 Project Management - MIT OpenCourseWare...• SECTION B : ARC CONSTRUCTION, TURKEY DO IT FASTER! In April 2003, the second item became: Deliver 389 km of paved road by December

Case Study

� Afghanistan and the REFS project

Page 15: 1.040 Project Management - MIT OpenCourseWare...• SECTION B : ARC CONSTRUCTION, TURKEY DO IT FASTER! In April 2003, the second item became: Deliver 389 km of paved road by December

THE TREE: PROJECT OBJECTIVES

The purpose of REFS is to promote economic recovery and political stability by:

� Repairing selected infrastructure needed tolower transportation costs

� Roadway & Bridge Reconstruction(389 KM)

� Improving the provision of water and sanitation services

� Increasing access to education, health, andlocal governmental facilities

� Restoring electrical transmission and distribution systems

� Repairing/re-constructing irrigation systems, dams/diversions and canals critical to the re-activation of the agricultural sector

� Providing employment opportunities tothousands of Afghans through project designs that maximize the use of manual labor to the extent possible

� Mentoring Afghan professional staff andnascent Afghan private sector companies to the greatest extent possible

Page 16: 1.040 Project Management - MIT OpenCourseWare...• SECTION B : ARC CONSTRUCTION, TURKEY DO IT FASTER! In April 2003, the second item became: Deliver 389 km of paved road by December

Time Frame

� Berger to begin construction of Section B by the end of 2002

� Deliver 49 km of paved highway (km 43 – 92) by December 2003

Page 17: 1.040 Project Management - MIT OpenCourseWare...• SECTION B : ARC CONSTRUCTION, TURKEY DO IT FASTER! In April 2003, the second item became: Deliver 389 km of paved road by December

Project Participants on Kabul-Kandahar Road Project

� Interim Government of Afghanistan ¾ Ministry of Public Works

� USAID � Contractor: Louis Berger Group, Inc.

USA

¾ Construction subcontractor: • SECTION B : ARC CONSTRUCTION, TURKEY

Page 18: 1.040 Project Management - MIT OpenCourseWare...• SECTION B : ARC CONSTRUCTION, TURKEY DO IT FASTER! In April 2003, the second item became: Deliver 389 km of paved road by December

DO IT FASTER!

� In April 2003, the second item became: Deliver 389 km of paved road by December 2003

Page 19: 1.040 Project Management - MIT OpenCourseWare...• SECTION B : ARC CONSTRUCTION, TURKEY DO IT FASTER! In April 2003, the second item became: Deliver 389 km of paved road by December

UNIQUE ASPECTS

� Time Frame

Page 20: 1.040 Project Management - MIT OpenCourseWare...• SECTION B : ARC CONSTRUCTION, TURKEY DO IT FASTER! In April 2003, the second item became: Deliver 389 km of paved road by December

Project Participants on Kabul-Kandahar Road Project

� Interim Government of Afghanistan ¾ Ministry of Public Works

� USAID � Contractor: Louis Berger Group, Inc.

USA

¾ Construction subcontractors: • SECTION B : ARC CONSTRUCTION, TURKEY • SECTION C : MENSEL CONSTRUCTION, TURKEY • SECTION D : KOLIN NATFER CONSTRUCTION, TURKEY • SECTION E : BSC & C&C CONSTRUCTION, INDIA • SECTION F : GULSAN/ CUKOROVA CONSTRUCTION, TURKEY • ACLU ( AFGHAN CONSTRUCTION & LOGISTIC UNIT)

• SECTION J: TAISEI JV/JICA FUNDING (out of our control)

Page 21: 1.040 Project Management - MIT OpenCourseWare...• SECTION B : ARC CONSTRUCTION, TURKEY DO IT FASTER! In April 2003, the second item became: Deliver 389 km of paved road by December

Mobilization and Transportation

� Equipment Mobilization

� Ground Transportation

� Air Transportation

Page 22: 1.040 Project Management - MIT OpenCourseWare...• SECTION B : ARC CONSTRUCTION, TURKEY DO IT FASTER! In April 2003, the second item became: Deliver 389 km of paved road by December

UNIQUE ASPECTS

� Time Frame � Contracting System

Page 23: 1.040 Project Management - MIT OpenCourseWare...• SECTION B : ARC CONSTRUCTION, TURKEY DO IT FASTER! In April 2003, the second item became: Deliver 389 km of paved road by December

Contracting Method

� Unit rate contract (bid-design-build)

� Adjustable rates for materials � Rates for security related stoppages

� Scope adjustment for performance

Page 24: 1.040 Project Management - MIT OpenCourseWare...• SECTION B : ARC CONSTRUCTION, TURKEY DO IT FASTER! In April 2003, the second item became: Deliver 389 km of paved road by December

UNIQUE ASPECTS

� Time Frame � Contracting System � Pavement Design Solution

Page 25: 1.040 Project Management - MIT OpenCourseWare...• SECTION B : ARC CONSTRUCTION, TURKEY DO IT FASTER! In April 2003, the second item became: Deliver 389 km of paved road by December

Highway Grading

� Surveying � Embankment and Earthwork � Compaction and Testing � Culvert Extensions � Inspections QC/QA

Page 26: 1.040 Project Management - MIT OpenCourseWare...• SECTION B : ARC CONSTRUCTION, TURKEY DO IT FASTER! In April 2003, the second item became: Deliver 389 km of paved road by December

ATB Production and Application

Asphalt Treated Base Course (ATB)

� Screened Aggregate Production

� Chemcrete Modifier Binder � Application and Inspection � Sampling and Testing

Page 27: 1.040 Project Management - MIT OpenCourseWare...• SECTION B : ARC CONSTRUCTION, TURKEY DO IT FASTER! In April 2003, the second item became: Deliver 389 km of paved road by December

Roadway Paving

Page 28: 1.040 Project Management - MIT OpenCourseWare...• SECTION B : ARC CONSTRUCTION, TURKEY DO IT FASTER! In April 2003, the second item became: Deliver 389 km of paved road by December

Roadway Paving

� Asphalt Mix Design � Asphalt Plant Production � Application, Rolling and

Compaction � Inspections and Quality

Control � Sampling and Testing

Page 29: 1.040 Project Management - MIT OpenCourseWare...• SECTION B : ARC CONSTRUCTION, TURKEY DO IT FASTER! In April 2003, the second item became: Deliver 389 km of paved road by December

Bridge Construction

� Bridge reconstruction �

6 collapsed bridges Soil Investigations Demolition

� Design (safety improvements) ¾ Deck width ¾ Guardrails ¾ Earthquake loads

¾ Bridge Approaches

Schedule

Page 30: 1.040 Project Management - MIT OpenCourseWare...• SECTION B : ARC CONSTRUCTION, TURKEY DO IT FASTER! In April 2003, the second item became: Deliver 389 km of paved road by December

Bridge Repairs Minor Damage Repairs and Safety Improvements

� Structural Repairs

� Guardrail Replacement

� Pedestrian Walkways

� Bridge Approaches

� Bridge Deck Overlay

Page 31: 1.040 Project Management - MIT OpenCourseWare...• SECTION B : ARC CONSTRUCTION, TURKEY DO IT FASTER! In April 2003, the second item became: Deliver 389 km of paved road by December

Causeways Repairs � Assess Damages � Design remedies � Repairs ¾ Extended Culverts ¾ Replace Concrete

Panels¾ Repair Expansion

Joints¾ Deck overlay

Page 32: 1.040 Project Management - MIT OpenCourseWare...• SECTION B : ARC CONSTRUCTION, TURKEY DO IT FASTER! In April 2003, the second item became: Deliver 389 km of paved road by December

UNIQUE ASPECTS

� Time Frame � Contracting System � Pavement Design Solution � De-mining and Security

Page 33: 1.040 Project Management - MIT OpenCourseWare...• SECTION B : ARC CONSTRUCTION, TURKEY DO IT FASTER! In April 2003, the second item became: Deliver 389 km of paved road by December

Demining

Page 34: 1.040 Project Management - MIT OpenCourseWare...• SECTION B : ARC CONSTRUCTION, TURKEY DO IT FASTER! In April 2003, the second item became: Deliver 389 km of paved road by December

Demining � Coordination

¾ UNMACA United Nations Mine Action Center for Afghanistan

¾ LBG, Demining Coordinator

¾ Subcontractors Coordinators

� Schedule ~ Sections B thru F

� Assessments ~ MEDDS system achieves 400% throughput increase

� Demining ¾ Destruction of unexploded ordinances

� Clearance Certificates

Page 35: 1.040 Project Management - MIT OpenCourseWare...• SECTION B : ARC CONSTRUCTION, TURKEY DO IT FASTER! In April 2003, the second item became: Deliver 389 km of paved road by December

Security

� Private Security Forces

� Local Security � Highway Security

Forces � Afghanistan

Ministry of Interior Forces

� United States Military

Page 36: 1.040 Project Management - MIT OpenCourseWare...• SECTION B : ARC CONSTRUCTION, TURKEY DO IT FASTER! In April 2003, the second item became: Deliver 389 km of paved road by December

16 December 2003

Page 37: 1.040 Project Management - MIT OpenCourseWare...• SECTION B : ARC CONSTRUCTION, TURKEY DO IT FASTER! In April 2003, the second item became: Deliver 389 km of paved road by December

Benefits: Economic and Other� Restore Afghan

National Unity � Reduce travel time and

fuel consumption � Reduce mechanical

failures � Connect economic

market places � Revitalize rural

communities � Create business

development opportunities

EWC

Page 38: 1.040 Project Management - MIT OpenCourseWare...• SECTION B : ARC CONSTRUCTION, TURKEY DO IT FASTER! In April 2003, the second item became: Deliver 389 km of paved road by December

Benefit Cost Analysis

� Cost / kilometer $515,700� Kabul-Doshi (WB) $342,800� VOC Savings about $300,000/km/yr� Excluded time savings (19 > 5 hrs)� Faster Delivery meant:� Higher Construction Cost: $173,000/km � VOC Savings: $375,000/km (15 months) � Net economic benefit: $78 million

� Schooling, health access, agricultural markets

Page 39: 1.040 Project Management - MIT OpenCourseWare...• SECTION B : ARC CONSTRUCTION, TURKEY DO IT FASTER! In April 2003, the second item became: Deliver 389 km of paved road by December

What will you do after graduation?

Fredric S Berger, P.E.

The Louis Berger

Group, Inc

www.bergerafghanistan.com

Page 40: 1.040 Project Management - MIT OpenCourseWare...• SECTION B : ARC CONSTRUCTION, TURKEY DO IT FASTER! In April 2003, the second item became: Deliver 389 km of paved road by December

on time solutions, by design