1007 disq 0 p ph 48071 shutdown philosophy

Upload: hamada-amer

Post on 01-Jun-2018

227 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/9/2019 1007 DISQ 0 P PH 48071 Shutdown Philosophy

    1/12

     

    Contract

    Number:P1007

    File Reference

    1007-DISQ-0-P-PH-48071 

    Page

    1 of 12

    RWE Dea

    Disouq Field Development

    FEED

    Shutdown Philosophy

    Document number1007-DISQ-0-P-PH-48071-Rev.0 

    0 12.12.11 Issued for Client comment S.Morsi A.Fawzi A.Hamdan RWE

    Rev Date Description Issued By Checked By Approved

    By

    Client

     Approval

  • 8/9/2019 1007 DISQ 0 P PH 48071 Shutdown Philosophy

    2/12

     

    Onspec Engineering Solutions

    Disouq Field Development Project

    Shutdown Philosophy

    Page: 2 of 12

    Changes List

    Rev.Date

    prepared (dd.MM.yyyy)

    Prepared by Description

  • 8/9/2019 1007 DISQ 0 P PH 48071 Shutdown Philosophy

    3/12

     

    Onspec Engineering Solutions

    Disouq Field Development Project

    Shutdown Philosophy

    Page: 3 of 12

    Table of Contents

    1  Introduction ...................................................................................................................... 4 

    1.1 

    Objectives & Scope ...................................................................................................... 5 

    1.2 

     Abbreviations ............................................................................................................... 6 

    2  Safety Shutdown Philosophy and Principles .................................................................... 7 

    2.1.   Application ................................................................................................................... 7 

    2.2. 

    Principles ..................................................................................................................... 7 

    2.3.   Applicable Code ........................................................................................................... 7 

    2.4.  Safety Integrity Level .................................................................................................... 7 

    Logic Hierarchy ................................................................................................................ 8 

    3.1. 

    Shutdown Levels .......................................................................................................... 9 

    4  Process & Utilities Shutdown Events ............................................................................. 11 

    Shut Down Valves design Criteria .................................................................................. 12 

    5.1  ESD valves ................................................................................................................ 12 

    5.2 

    Position Status & Resetting ........................................................................................ 12 

  • 8/9/2019 1007 DISQ 0 P PH 48071 Shutdown Philosophy

    4/12

     

    Onspec Engineering Solutions

    Disouq Field Development Project

    Shutdown Philosophy

    Page: 4 of 12

    1 Introduction 

    RWE Dea Egypt has discovered seven natural gas reserves in the Disouq Concession withinthe onshore Nile Delta, starting in 2008, as shown on the concession map below. Furtherexploration in the concession is ongoing. RWE Dea Egypt is the operator of the Concessionwith EGAS as a partner.

    The objective of this project is to carry out front end engineering design (FEED) services andprepare a scope of work for Engineering, Installation and Construction tenders (procurement willbe undertaken by RWE Dea) to finally install a natural gas trunk line system to be gathered, ledto a central gas treatment plant where the gas shall be treated to achieve sales gas quality and

    send to the gas pipeline infrastructure at the boundaries of the Disouq Concession.The selected development comprises a central gas treatment site near NSG-1x, where the gasis collected, treated by means of Low Temperature Separation utilizing the Joule Thomsoneffect, and compressed for export. Treated gas is exported via a 16” export pipeline directly intothe GASCO NTS pipeline.

    The well fluids from the directly routed wells and the trunk line are fed to a common inletseparator at the central plant. All gases and liquids will be separated and processed on thecentral treatment site into sales gas, stabilized condensate, and free production water.

    Treatment of gas is carried out in two trains, while treatment of condensate is in a single train.

    Three trains of sales gas compression are installed. During FEED investigation shall clarify, if

    the installation of front end booster compressors is more advantageous compared to thisconcept.

    Fuel gas for the gas engine drives is taken from the suction of the sales gas compressors.

  • 8/9/2019 1007 DISQ 0 P PH 48071 Shutdown Philosophy

    5/12

     

    Onspec Engineering Solutions

    Disouq Field Development Project

    Shutdown Philosophy

    Page: 5 of 12

    To allow further increase of the production additional tailings and all necessary equipment likevalves and flanges shall foresee to allow a simple tie in of future treatment trains.

    1.1 Objectives & Scope

    This document defines the safety shutdown philosophy and the basis of design for the SafetySystem for Disouq Gas Plant Facility.

    The principal objectives of the safety system are:

      Ensure personal protection

      Minimization of hazards to the environment

      Plant and equipment protection

    The safety system will provide the safe isolation and depressurization of the total facility orcritical sections of the process and utilities in the event of an emergency condition when thesafety of personnel or equipment is threatened. The safety system is divided into two sub-systems; Fire and Gas detection and protection system (F&G) and Emergency ShutdownSystem (ESD).

    This document primarily defines the Process Shutdown philosophy.

    Protective systems will provide the protection of personnel, environment, and equipment byproviding the safe shutdown of plant and/or process equipment during an event that mayinclude hazards such as loss of containment or fire, a process upset, or when the primarycontrol system fails to keep the process within specified operating limits.

    Shutdown, isolation of process inventories into manageable volumes and depressurizing areused to manage and limit escalation of any event.

    Protective systems will include dedicated process sensors and final elements and will not relyupon functions controlled by the process control system. Except where required by the projectdesign specifications, protective system outputs will be designed as Fail-Action, that is, loss ofoutput signal will cause the associated field device to move to its shutdown state.

    The Shutdown Philosophy includes systems that respond to different types of events. Thesesystems are the Emergency Shutdown System (ESD) that includes fire and gas detection, firesuppression, and emergency depressurizing, Total Plant Shutdown, Process Shutdown, andEquipment Shutdown.

    Electrical protection, including manual emergency switchgear trip, manual emergency generatortrips, and electrical protective relay functions is separate to and independent of the SafetyInstrumented System.

    The Shutdown System for each facility will be a self-contained stand-alone system that is notdependent upon inter-location communications. The Shutdown System will operateindependently of the Plant Control System, but communicate with the Plant Control System fordata to be available at the operator interface.

  • 8/9/2019 1007 DISQ 0 P PH 48071 Shutdown Philosophy

    6/12

     

    Onspec Engineering Solutions

    Disouq Field Development Project

    Shutdown Philosophy

    Page: 6 of 12

    1.2 Abbreviations

    Blowdown valve : BDV

    Central treatment Plant : CTP

    Emergency Shutdown : ESD

    Emergency Shutdown Valve : ESDV

    Fire and Gas : F&G

    General Process Shutdown : GPSD

    Safety Instrumented System : SIS

    Safety Instrumented Function : SIF

    Process Shutdown : PSD

    Safety Integrity Level : SIL

    Safety System : SS

    Unit Shutdown : USD

  • 8/9/2019 1007 DISQ 0 P PH 48071 Shutdown Philosophy

    7/12

     

    Onspec Engineering Solutions

    Disouq Field Development Project

    Shutdown Philosophy

    Page: 7 of 12

    2 Safety Shutdown Philosophy and Principles

    2.1. Application

     A common safety shutdown system is provided for the entire facility. The shutdown hierarchyapplies across all plant areas.

    2.2. Principles

    The overall safety shutdown philosophy is based on the principle of maintaining the facility at anacceptable level of safety for personnel; equipment and the environment whilst initiating thelowest shutdown level possible to allow for efficient re-start.

    The following principles shall apply to the achievement of an acceptable level of safety:

      Personnel safety.

      Protect the environment, plant and equipment

      Prevent escalation and minimize the consequences of a hazardous event.

      Minimize the requirement for manual operations during and after a hazardous event.

      Where appropriate, limit cascaded process trips to allow easier identification of the trip

    cause and make use of operator intervention.

      Provide a system that is simple to implement, test / verify and operate thereby achieving

    high availability.

    2.3. Applicable Code

     API RP 500 Classification of Locations for Electrical Installations

     API RP 520 Recommended practice for sizing, selection and installation of

    pressure relieving (parts I and II).

     API RP 521 Guide for pressure devices in refineries relieving and

    depressurizing systems.

    2.4. Safety Integrity Level

    Safety Instrumented Functions (SIF) within the Protective System will be analyzed to ensurecompliance with the required Safety Integrity Level (SIL) and will be designed to meet the targetSILs of the project.

  • 8/9/2019 1007 DISQ 0 P PH 48071 Shutdown Philosophy

    8/12

     

    Onspec Engineering Solutions

    Disouq Field Development Project

    Shutdown Philosophy

    Page: 8 of 12

    3 Logic Hierarchy

    The shutdown system logic is structured in a hierarchical form ensuring that an orderlyshutdown of systems can be accomplished. The structure includes:

      An Emergency Shutdown System (Level 4) that includes fire or gas detection that initiates

    the site emergency alarm isolates the electrical systems and following either confirmed fire

    or confirmed gas detection in the processing area initiates a Total Plant Shutdown with

    depressurization.

      A General Process Shutdown (Level 3) that isolates the site from external sources of

    hydrocarbons by closing the facility import and export pipeline valves and inter-facility tie

    line valves, isolates large volume inventory, and initiates a process shutdown for train, unit

    or process station shutdown.

      A Process Shutdown (Level 2) stops a whole process train, closes inventory isolation

    valves and initiates Process Equipment Shutdown for the train.

      An Equipment (Unit) Shutdown (Level 1) that stops a single equipment item (process

    component) and closes its inventory isolating valves.

    Figure 1 - Shutdown system logic hierarchy

    Total Plant Shutdown, Process Shutdown, and Equipment Shutdown respond to both manuallyinitiated shutdowns from shutdown hand switches, and automatically initiated shutdown fromprocess sensors.

  • 8/9/2019 1007 DISQ 0 P PH 48071 Shutdown Philosophy

    9/12

     

    Onspec Engineering Solutions

    Disouq Field Development Project

    Shutdown Philosophy

    Page: 9 of 12

    3.1. Shutdown Levels

    The safety shutdown system for the facility is arranged in a hierarchical manner, with each

    shutdown level automatically initiating the level below.

    The shutdown levels are divided into four (4) main groups, ESD, GPSD, PSD and USD asfollows:

    3.1.1 Emergency Shutdown (ESD)

    ESD is a high emergency shutdown which will be initiated under extreme circumstances whennormal operations cannot be resumed in the foreseeable future.

    ESD shutdown will be initiated by the following conditions:

    I. Explosion – identified by operator.

    II. Manual fire call point activation.III. Major plant fire, confirmed fire (by at least two detectors) in more than one fire

    zone at CTP

    The ESD is aimed at isolating hydrocarbon feeds and outlets, reducing hydrocarbon inventoryand limiting ignition sources and will be automatically activate in the following;

      Activate the facility emergency alarm

      Start fire pumps (where installed)

      Activate fire water monitors (where installed)

      Initiate fire suppression (where applicable)

      De-energize electrical systems

      Initiate a Total Plant Shutdown; by closing all SDV’s

      Initiate emergency depressurizing at CTP facilities (except well area).

    Valves activated upon ESD are identified in the C&E Diagram.

    3.1.2 General Process Shutdown (GPSD)

    GPSD shutdowns shall be initiated under emergency conditions due to abnormal processconditions not within the limits of process control system, where it is possible that normal

    operation could be resumed in the foreseeable future. These conditions are process upsetcircumstances.

    Utilities will be kept running as long as possible to enable recovery from the shutdown tripsituation.

    The GPSD will be automatically initiated in the following circumstances;

      Manual activated switch in the control room or remotely in the CTP.

      Shut down of un spared main equipment (such as slug catcher)

      Total power failure.

      Loss of instrument air pressure.  Loss of fuel gas pressure.

      High high level in the flare K.O drum.

  • 8/9/2019 1007 DISQ 0 P PH 48071 Shutdown Philosophy

    10/12

     

    Onspec Engineering Solutions

    Disouq Field Development Project

    Shutdown Philosophy

    Page: 10 of 12

    This level of shutdown will:

      Isolate a site from external hydrocarbon sources by closing the site or facility import and

    export pipeline (S) valves that are located at or near the plant area boundary

      Isolate a site or facility from external hydrocarbon sources by closing valves on inter-

    facility.

      Isolate large volume inventory by closing inventory isolation valves

      Initiate a Process Shutdown

      Initiate Process Equipment Shutdown that is not shutdown by a Process Shutdown

    GPSD comprises the activation of all SDVs only. These are identified in the C&E

    Diagram.

    3.1.3 Process Shutdown (PSD)

    PSD is Lower level shutdowns resulting from abnormal process conditions within a definedprocess system.

    Shutdown is aimed at avoiding escalation to an emergency condition. Only the train with theabnormality is isolated as well as the electrical system connected to it.

    The Process Shutdown provides protection of process units and/or equipment and willshutdown rotating equipment and close equipment shutdown valves. The Process Shutdownminimizes the potential for equipment damage or process excursions.

    A Process Shutdown is initiated by:

      A manually activated switch in the control room, or field

      Automatically by process sensors (pressure, level, temperature)

    A Process Shutdown will:

      Isolate all trains or units by closing the train or unit isolation valves

      Isolate large inventory within trains or units by closing inventory isolation valves

      Initiate Process Equipment Shutdown

    3.1.4 Equipment/Unit Shutdown (USD)

    This level of shutdown is the lowest shutdown level. It results from abnormal process conditionsfor a single equipment/unit only.

    Unit shutdown is initiated by:

      A Process Equipment Shutdown switch in the control room, or process area

      Automatically by process sensors (pressure, level, temperature)

    Unit shutdown will activate the followings:

      Stop/shutdown a single equipment item or rotating equipment.

      Close the process equipment or rotating equipment isolation valves.

      Inventory blow down is initiated manually except for incidents for which blow down is

    automatic.

  • 8/9/2019 1007 DISQ 0 P PH 48071 Shutdown Philosophy

    11/12

     

    Onspec Engineering Solutions

    Disouq Field Development Project

    Shutdown Philosophy

    Page: 11 of 12

    4 Process & Utilities Shutdown Events

    The plant flare systems will be designed to handle the plant capacity of 165 MMSCFD based onblocked outlet case resulting from process upset conditions. The flare header is designed for275 MMSCFD to accommodate future expansion expected.

    The action of GPSD will reduce the quantity of flared hydrocarbon due to process upsetconditions.

    4.1. Abnormal flow 

      Low flow shutdown inputs should be used for centrifugal pumps to prevent cavitation and

    subsequent pump damage from operating at flow rates less than the required minimum

    flow. These are not required where pump minimum flow protection is provided.

    4.2. Abnormal level

      Low low level shutdown inputs are recommended for any vessel where loss of level would

    result in damage to process pumps or significant gas blow-by and overpressure of

    downstream equipment.

    4.3. Abnormal Pressure

    Low pressure shutdown inputs should be considered for:

      Process equipment that is susceptible to damage in the event of low inlet pressure and no

    other adequate protection exists, e.g. compressors.  Fuel/pilot gas pressure to shutdown gas engine.

      High pressure shutdown inputs and alarms should be considered for compressor

    discharge and seal leakage detection systems for pumps.

    4.4. Abnormal Temperature

    High temperature shutdown inputs and alarms are required for:

      Compressor, cooling system, diesel engines and pump lube-oil systems.

      Rotating equipment, bearing temperatures.

    4.5. Abnormal Vibration

    Rotating equipment will be provided with the appropriate vibration protection.

    4.6. Utilities Shutdown

     All utilities shall be shut down only in case of ESD (level 4) except fire fighting system.

     All essential utilities listed below will normally remain in operation.

      Instrument Air

      Fuel gas system

      Fire fighting and deluge systems

      Flare System

      Open drain & closed drain

  • 8/9/2019 1007 DISQ 0 P PH 48071 Shutdown Philosophy

    12/12