UNC Modification 429 Customer Settlement Error Claims
Process – Guidance Document
![Page 2: 1 UNC Modification 429 Customer Settlement Error Claims Process – Guidance Document](https://reader036.vdocuments.mx/reader036/viewer/2022080222/56649f4f5503460f94c70b36/html5/thumbnails/2.jpg)
2
• Agenda– Background
– UNC Modification• What it is proposed to cover
• What it is not proposed to cover
– Eligibility Criteria– Treatment
Customer Settlement Error Claims Process
![Page 3: 1 UNC Modification 429 Customer Settlement Error Claims Process – Guidance Document](https://reader036.vdocuments.mx/reader036/viewer/2022080222/56649f4f5503460f94c70b36/html5/thumbnails/3.jpg)
3
• In the decision letter where Ofgem approved the Modification they indicated that the process would benefit from some clarity / development to assist Users in submitting Claim Requests
• A Guidelines document is proposed to provide support to Users on the process, specifically to:– Commentary on the information required– Understanding of the treatment of such Claim Requests by
Transporters
• Guidelines document is not intended to further develop or revisit UNC Modification 429
Background
![Page 4: 1 UNC Modification 429 Customer Settlement Error Claims Process – Guidance Document](https://reader036.vdocuments.mx/reader036/viewer/2022080222/56649f4f5503460f94c70b36/html5/thumbnails/4.jpg)
4
• In order to enact the Guidelines document a UNC Modification has been raised– Guidelines proposed to be governed by UNCC– Within the Guidelines a sample templates is proposed
• Not proposed that this is covered within UNCC
• Proposed that this is held on Extranet – change managed through Xoserve Operational Forum
– Modification will develop the Guidelines
UNC Modification
![Page 5: 1 UNC Modification 429 Customer Settlement Error Claims Process – Guidance Document](https://reader036.vdocuments.mx/reader036/viewer/2022080222/56649f4f5503460f94c70b36/html5/thumbnails/5.jpg)
5
• Guidelines document is not intended to further develop or revisit UNC Modification 429
• Proposed Structure of the Guidelines Document– Initial Assessment by User / Eligibility Criteria– Collation of Data by User / Assessment by the Transporter
Guidelines
![Page 6: 1 UNC Modification 429 Customer Settlement Error Claims Process – Guidance Document](https://reader036.vdocuments.mx/reader036/viewer/2022080222/56649f4f5503460f94c70b36/html5/thumbnails/6.jpg)
6
• Period of Adjustment under UNC Modification 429
Timelines
Y-6 Y-5 Y-4 Y-3 Y-2 Y-1 Y01/04/08 - 31/03/09 01/04/09 - 31/03/10 01/04/10 - 31/03/11 01/04/11 - 31/03/12 01/04/12 - 31/03/13 01/04/13 - 31/03/14 01/04/14 - 31/03/15
Code cut-off*
31/03/2009
Claim submitted within this period could date
back to last day of Y-6, i.e. 31/03/09
* Assuming post-UNC Modification 398 Implementation (1st April 2014)
Example TimelineCustomer Settlement Error Claims Process
Reconciliation PeriodMod 429 Claims Process
Maximum 6yrs 1 day
![Page 7: 1 UNC Modification 429 Customer Settlement Error Claims Process – Guidance Document](https://reader036.vdocuments.mx/reader036/viewer/2022080222/56649f4f5503460f94c70b36/html5/thumbnails/7.jpg)
7
• Eligibility Criteria defined in the Modification
– Materiality of Claim • This value must be a credit or debit exceeding £50,000. • This Claim must relate to an individual User identity (i.e. User Short Code) and the User should be applicable for the whole
Claim period. • This Claim must relate to the period between Code Cut Off Date – 1 day of formula year t-6
– The value of User to Customer invoicing is not relevant in this process. – Demonstrable Customer Claim - User must be able to demonstrate a claim from the customer for the
period and the customer’s assessment of the materiality. • The information provided in support of the Claim must include a statement from the Customer verifying that they have
submitted a claim for the period in question, and the materiality of such claim. • The period of the consumer claim should match that of the User’s Claim. Where the consumer’s claim pre-dates the User’s
Claim, i.e. because the User’s Claim includes the earliest date that such Claims may be made, an assessment of the materiality of the consumer’s claim within the relevant period must be provided.
• The order of magnitude of the User Claim must approximate to that of the consumer claim.– Valid Claim - The claim must be an otherwise valid invoice adjustment request as envisaged in the UNC but
the Code Cut Off Date prevents such invoice challenge being actioned by the Transporters. • The User must provide a written statement accompanying the claim that sets out the nature of the Claim such that the
Transporter is able to assess this on this basis alone and ensure that the type of request would be accepted had this been submitted prior to the Code Cut Off Date.
• If this can not be demonstrated by the User the Claim should not be submitted.
Initial Assessment by User / Eligibility Criteria
![Page 8: 1 UNC Modification 429 Customer Settlement Error Claims Process – Guidance Document](https://reader036.vdocuments.mx/reader036/viewer/2022080222/56649f4f5503460f94c70b36/html5/thumbnails/8.jpg)
8
• Legal Text sets out the data required:– Where a User wishes to make a claim …, the following process shall be followed:– (a) the User shall submit to the Transporter Agency the following information:– (i) detail in relation to the nature and duration of the error resulting in the adjustment, including copies of the invoices between the Transporters
and the User and the User and the consumer (such information to be applicable to the claim, for example at Supply Meter Point level);– (ii) the relevant system files and supporting information (to include workings and methodology);– (iii) the materiality of the claim in terms of volume of gas, including details of the methodology used to calculate such materiality;– (iv) the exact financial impact of the adjustment including energy (by reference to the monthly average of the System Average Prices) for the
period of the claim and transportation costs (with reference to the Transportation Charges prevailing at the time of the claim);– (v[1]) the dates in respect of which the claim will apply in accordance with paragraph 1.3.10– above;– (vi[2]) evidence of the financial impact relating to the Supply Point or group of Supply Points the subject of the claim including written confirmation
that the consumer(s) connected to the Individual Supply Point or group of Supply Points in question agree(s) that:– (a) an adjustment in gas off-taken in the period of time between the Code Cut Off Date and the last Day of Formula Year t-6 should be made;– (b) the materiality of the claim as referred to in paragraph 1.3.11(a)(ii) is correct; and– (c) the dates in relation to which the User’s claim applies are correct; and– (vii[3]) a warranty that no previous claims which are the same in nature and/or are in relation to the same dates as the claim being made by the
User have been made;– (b) the Transporters shall consider the claim and communicate to the User its approval or rejection of such within 90 days of receipt of the claim,
during which time the Transporter Agency shall be entitled to raise queries in relation to the claim and/or to request further information from the User in respect of its claim;
– (c) the Transporters shall be entitled to reject the claim if it is considered that the information provided by the User is so clearly erroneous on its face that it would be unconscionable for the claim to be accepted, in which case the Transporters shall reject the claim and inform the User of the reason(s) for such rejection;
– (d) if the Transporters consider that an amount exceeding £1 million (one million) pounds is to be re-paid to any User, the Transporter Agency shall issue notification of such fact to Users and that the amount determined as payable to the User shall be paid within 2 (two) months of approval of the claim.
• If this can not be demonstrated by the User the Claim should not be submitted.
Collation of Data by User
![Page 9: 1 UNC Modification 429 Customer Settlement Error Claims Process – Guidance Document](https://reader036.vdocuments.mx/reader036/viewer/2022080222/56649f4f5503460f94c70b36/html5/thumbnails/9.jpg)
9
• In assessing the data provided by the User the Transporter Agency were instructed NOT to:– Verify the assessment by the User of the original invoiced energy and
charges position – noting that the Claim may not be at a level that invoices are issued.
– Recalculate the revised and requested energy and transportation adjustment values.
– Assess the Claim adjustment value does not exceed the original invoiced value, is inclusive or exclusive of all invoiced charges or the User’s assessment of this value.
– Undertake any investigation into the veracity of the Claim.– Other than checking that the Supply Meter Point was – for the period of
the Claim - in the ownership of the User raising the Customer Settlement Error Request, verify any of the individual base data items used by the User in their recalculation.
Assessment by the Transporter
![Page 10: 1 UNC Modification 429 Customer Settlement Error Claims Process – Guidance Document](https://reader036.vdocuments.mx/reader036/viewer/2022080222/56649f4f5503460f94c70b36/html5/thumbnails/10.jpg)
10
• Transporter shall assess the data– Transporter shall reject or accept within 90 days– Where Transporter needs further information they shall refer to
User representative– There is no maximum number of referrals– Propose that the 90 days is start / stop clock
Assessment by the Transporter
![Page 11: 1 UNC Modification 429 Customer Settlement Error Claims Process – Guidance Document](https://reader036.vdocuments.mx/reader036/viewer/2022080222/56649f4f5503460f94c70b36/html5/thumbnails/11.jpg)
11
• Example commentary:• (ii) the relevant system files and supporting information (to include workings
and methodology);– Relevant system files and supporting information related to the adjustment
amount– The User must present the information to the Transporter Agency in a format that
the Transporter Agency can use to generate the invoice adjustment.– The format of this file is attached as Appendix A. – Where the User has not provided this format or it is incomplete this shall be
referred back to the User.– The User must provide sufficient information to the Transporter Agency such that
they may provide the Supporting Information to any other User who receives the counter credit or debit through the Neutrality mechanism. The relevant format for this Ad Hoc Invoice Supporting Information is contained within the UK Link Manual.
– Where the User has not provided this format or it is incomplete this shall be referred back to the User.
Assessment by the Transporter
![Page 12: 1 UNC Modification 429 Customer Settlement Error Claims Process – Guidance Document](https://reader036.vdocuments.mx/reader036/viewer/2022080222/56649f4f5503460f94c70b36/html5/thumbnails/12.jpg)
12
• Example template:
Assessment by the Transporter
Shipper Shortcode Shipper Name
Submission Date
Duration of the Customer Settlement Error
WarrantyNo previous claims which are the same in nature and / or are in relation to the same dates as the claim being made by the User have been made, or are in the
process of being made
REASON FOR CLAIM - Nature of the Customer Settlement Error (Including Number of Supply Poins)
Requested Adjustment End DateRequested Adjustment Start Date
CUSTOMER SETTLEMENT ERROR CLAIMS PROCESS
Contact Details of Shipper Personnel
Responsible for Claim. (Shipper to provide Primary
Contact, and up to two Secondary Contacts)
NAME Telephone E-mail
Define Methodology used to calculate the materiality impacts. Methodology used should be aligned with the SUPPORTING DATA provided
Should not be less than the Last Day of Formula Year (T-6)
Should not be greater that the current UNC Code Cut Off Date
ENERGY
Energy (kWh) Energy Charges (£) Transportation Charges (£)Customer Settlement
Error Claim MaterialityIf in excess of £1 million, notification will be issued to all via xxxxx 2 months prior to the invoice date
TRANSPORTATION
Additonal details can be provided in tab 'Additional Information' if required
Anticipated Approval or Rejection Date by (+90 Days from Submission)Transporters shall consider the claim and communicate to the User its approval or rejection of such within 90 days of receipt of the claim
User to complete ALL fields.
Utilising the "Supporting Data" template - User to provide all supporting invoice data including original Supply Point and Meter Point data, original Energy and Transportation charges, original invoice details, revised energy and transportation charges based on the reason for claim submission and the resultant requested adjusted Energy and Transportation charge
values. Please refer to "Customer Settlement Error Claims Process - Guideline Document".
Additonal details can be provided in tab 'Additional Information' if required
![Page 13: 1 UNC Modification 429 Customer Settlement Error Claims Process – Guidance Document](https://reader036.vdocuments.mx/reader036/viewer/2022080222/56649f4f5503460f94c70b36/html5/thumbnails/13.jpg)
13
• Example template:
Assessment by the Transporter
SSC MPRNConfirmation
Reference Number
CONF Start Date
CONF End Date
Adjustment Variance
Period Start Date
Adjustment Variance
Period End Date
COUNT of Days
Original Invoice Number
Charge Type
Supply Point AQ
Supply Point SOQ
Meter Point AQ
LDZExit
ZoneMRF EUC GNT
ABC 12345678 12345678 01/08/09 25/04/10 01/01/10 31/01/10 31 1234567 NNX 5200000 35000 5200000 NT NT2 M 8514 NDMABC 12345678 12345678 01/08/09 25/04/10 01/01/10 31/01/10 31 1234567 CCA 5200000 35000 5200000 NT NT2 M 8514 NDMABC 12345678 12345678 01/08/09 25/04/10 01/01/10 31/01/10 31 1234567 ZCA 5200000 35000 5200000 NT NT2 M 8514 NDMABC 12345678 12345678 01/08/09 25/04/10 01/01/10 31/01/10 31 1234567 NRE 5200000 35000 5200000 NT NT2 M 8514 NDMABC 12345678 12345678 01/08/09 25/04/10 01/01/10 31/01/10 31 1234567 ZRE 5200000 35000 5200000 NT NT2 M 8514 NDMABC 12345678 12345678 01/08/09 25/04/10 01/01/10 31/01/10 31 1234567 GRE 5200000 35000 5200000 NT NT2 M 8514 NDM
![Page 14: 1 UNC Modification 429 Customer Settlement Error Claims Process – Guidance Document](https://reader036.vdocuments.mx/reader036/viewer/2022080222/56649f4f5503460f94c70b36/html5/thumbnails/14.jpg)
14
• Conclude drafting of Guidelines Document
• Circulate to Workgroup considering the UNC Modification
• Develop Guidelines document
• Implement
Next Steps