1. title of the cooperation project, relevant project · pdf filetitle of the cooperation...
TRANSCRIPT
Summary of Preliminary Study Result for Grant Aid Project
Date: 2008/02/12
1. Title of the Cooperation Project, Relevant Project Report The Project for Construction of Bridges in the Province of Nusa Tenggara Barat (Phase 2)
Project Activity: Reconstruction of 16Brideges and 1 Culvert on the provincial road
2. Categorization and its reason Category B
Reasons
a) The degree of impacts resulting from the project is not significant on the social and
natural environmental areas due to the small scale reconstruction of bridges and culverts
required on the existing provincial road. The Indonesian EIA law prescripts that full
scale EIA is not required for bridges not longer than 500 meters. However, an IEE
level (UKL+UPL) report, and an approval procedure by the provincial environmental
management agency (BAPEDALDA-NTB), are both required before construction
stage.
b) With regard to social matters, permanent and temporary land acquisition must be caused
by reconstruction structures at the BR34 and BR35. Although the Indonesian
government [Ministry of Public Works (PU)] has an appropriate law as well as
procedures for compensation, the Japan’s Government should monitor a negotiation
between land owners and the plan proponent (Ministry of Public Works). Furthermore,
the Indonesian procedure does not include any system of public involvement. Hence
the proponent in cooperation with the JICA Study Team should hold a stakeholder
meeting for consensus building in the basic design from the view of JICA’s
environmental and social consideration guidelines.
c) With regard to natural environment issues, no sensitive or protected areas are located in
the project site.
3. Outline of the Location (Maps, Environmental and Social Condition, Problems and so on) Project site is located in the Sumbawa Island as follows.
Figure-1 Project Location
Figure-2 Detailed Project Location Map
<Summary of project site is as follows> - Project area is located in West Sumbawa and Sumbawa district.
-Total population in the project site is approximately 25,000.(see following table)
Table-1 Population of Project Site Name of District Name of Village Population Household Remarks
Secongkang Bawah 1,369 236 - Sekongkang Atas 2,552 421 - Tongo 1,380 317 - Ari Kangkung 980 280 Including independent transmigrated village Tatar 734 209 Including independent transmigrated village
West Sumbawa/ Sekongkang
Talonanga 1,269 253 Current Transmigrated village: Tongo II SP2 Planned Transmigrated village: Batu Nampar
Lunyuk Rea 1,638 647 - Lunyuk Ode 1,197 292 - Jamu 1,237 315 Including independent transmigrated village Pada Suka 3,697 915 Planned Transmigrated village:Lamar Suaka Maju 3,155 723 Including independent transmigrated village Perung 2,384 740 Including independent transmigrated village
Sumbawa/ Lunyuk
Emang Lestari 3,137 922 Including independent transmigrated village Total 24,729 6,270 -
Source:Lunyuk/Sekongkang government 2006(BPS)
Mountainous Area (except transmigrated Area) Flat Area
0-45km Section 45-60km Sec.
4. Legal Framework of Environmental and Social Considerations (Law, Projects subject to EIA, Procedures, Information Disclosure and Stakeholder Participation)
a) Relevant Law for EIA / Environmental Permission
Name of Law:
-Law No. 23 of 1997 Environmental Management
-Government Regulation No. 27 of 1999 on Environmental Impact Assessment
- Decree of State Ministry for the Environment No. 17 of 2001 on Types of Business and/or
Activity Plans that are required to be completed with the Environmental Impact Assessment
- Decree of State Ministry for the Environment No.11 of 2006 on Types of Business and/or
Activity Plans that are Required to be Completed with the Environmental Impact
Assessment
b) Criteria of the full scale EIA and IEE
Table -2 Criteria for a full scale of EIA/ IEE
Laws Category
Decree of state Ministry of Env. No.11/2006
Decree of state Ministry of Public Works No.17/2003
Requirement of full scale EIA Bridge Length>=500m -
Requirement of IEE level
UKL+UPL
Propose from proponent to authority (NTB-BAPEDALDA)
Major Town (50,000-500,000) :Bridge Length>=60m
Medium Town(20,000-2000,000):Bridge Length>=20m
According to the environmental management agency (NTB-BAPEDALDA), EIA category
issues will be screened generally based on the proposal report from the proponent. However,
the person in charge of the EIA section NTB-BAPEDALDA commented that only an IEE
level report (UKL+UPL) will be required. This is because the degree of impact resulting
from the project must be limited, and it will not be significant for social and natural
environment issues.
An IEE level (UKL+UPL) procedure is shown in the figure below.
Figure-2 Procedures of Environmental Permission (UKL+UPL)
5. Outline of Relevant Agency and Institution which implement Project, EIA and so on Proponent of this project is the Ministry of Public Works (PU).
The organization chart of PU is as follows.
Figure-3 Organization Chart of PU (Ministry of Public Works) *Note) PU has EIA section under the planning section ( )
On the other hand, the environmental organization whose permission for this project is
required is the NTB provincial environmental management agency (NTB-BAPEDALDA).
This is so because the project site is located in more than two districts, West Sumbawa and
Sumbawa.
Figure-4 Section in charge of Environmental Permission
6. Outline of the Project, Analysis of Alternatives (Proposed Project, Comparative Examination of Alternatives, Selected Project on the basis of the Preliminary Study)
a)Outline of the Project
Reconstruction of 16 bridges and 1 culvert (see Table-4: Target Bridges and Culverts)
b)Analysis of Alternatives
Basically, the alternative-1 will be adopted from the view of social and natural
considerations (exception made of BR34 and BR35).
Table-3 Analysis of Alternatives Physical
Alternatives Impact to the Social area Impact to the
Natural area Impact to the Pollution
Remarks
Without Project (Option Zero)
It is impossible to cross rivers in the project site as no structures are available. Most of villagers will not be able to take emergency medical services. Logistics without transportation will be formulated by the self-sufficient community.
No impact resulting from the project
No impact resulting from the project
-
Physical Alternatives
Impact to the Social area Impact to the Natural area
Impact to the Pollution
Remarks
With Project Alternatuve-1 Reconstruction of the BR. and Culvert at the same location
Land acquisition must be avoided
Small impact resulting from the project due to the same alignment of access road.
Turbidity water will be caused by the construction activity (cutting land/drilling) during construction stage
Disadvantage on the cost and time because current sound causeways will not be used as diversion means
With Project Alternative-2 (Reconstruction at the up/down stream)
Permanent / temporary land acquisition will be caused at some points.
A certain level of deforest will be caused by changing alignment of access road.
Turbidity water will be caused by the construction activity (cutting land/drilling) during construction stage
Advantage on the cost and time because current sound causeways will be used as diversion
Table-4 List of Target Bridges and Culverts
St
ruct
ure
Type
Brid
geLe
ngth
(m)
BR
-1A
ir K
eruh
ⅠSe
kong
kang
30G
abio
nB
ridge
30JA
PAN
BR
-2A
ir K
eruh
ⅡSe
kong
kang
30G
abio
nB
ridge
30JA
PAN
BR
-3N
egen
e ⅠSe
kong
kang
25G
abio
n (D
amag
ed)
Brid
ge30
JAPA
ND
etou
r at U
pstre
am R
iver
Bed
BR
-4N
egen
e Ⅱ
Seko
ngka
ng10
Gab
ion
Box
Cul
vert
-IN
DO
NES
IAB
R-5
Tata
r ⅠSe
kong
kang
100
--
0IN
DO
NES
IAA
lignm
ent I
mpr
ovem
ent o
f Cut
Stre
tch
(Ste
ep G
BR
-6Ta
tar Ⅱ
Seko
ngka
ng15
--
0M
issin
gB
R-7
Tata
r ⅢSe
kong
kang
15Ro
ck P
lacing
Box
Cul
vert
-IN
DO
NES
IAB
R-8
Tata
r Lok
aSe
kong
kang
60G
abio
nB
ridge
50JA
PAN
BR
-9Ta
tar B
odo
Seko
ngka
ng25
Gab
ion
Brid
ge25
JAPA
NB
R-1
0La
bihe
ⅠSe
kong
kang
20G
abio
nB
ox C
ulve
rt-
JAPA
NB
R-1
1La
bihe
ⅡSe
kong
kang
20G
abio
n (D
amag
ed)
Brid
ge20
JAPA
ND
etou
r at U
pstre
am R
iver
Bed
BR
-12
Labi
he Ⅲ
Seko
ngka
ng20
Gab
ion
Brid
ge25
JAPA
NB
R-1
3M
one Ⅰ
Seko
ngka
ng20
--
0M
issin
gB
R-1
4M
one Ⅱ
Seko
ngka
ng15
--
0M
issin
gB
R-1
5M
one Ⅲ
Seko
ngka
ng10
--
0M
issin
gB
R-1
6Te
lona
ng Ⅰ
Seko
ngka
ng30
-B
ridge
30JA
PAN
Cro
ssin
g at
Sha
llow
Wat
er S
tream
BR
-17
Telo
nang
ⅡSe
kong
kang
15W
oode
n B
ridge
(Dam
aged
)B
ridge
10IN
DO
NES
IAB
ridge
Nam
e : B
atu
Nam
par,
Rem
aini
ng o
f Bot
BR
-18
Telo
nang
ⅢSe
kong
kang
10W
oode
n B
ridge
(Dam
aged
)B
ridge
10IN
DO
NES
IAD
ecay
of W
oode
n Pa
rts, D
etou
r at D
owns
tream
BR
-19
Sepa
ngLu
nyuk
40C
oncr
ete
Cau
se W
ayB
ridge
35JA
PAN
Exist
ing
Stru
ctur
e C
ompl
etio
n in
200
7 B
R-2
0Bo
nton
gLu
nyuk
20W
oode
n B
ridge
(Dam
aged
)B
ridge
20JA
PAN
Col
laps
e of
Old
Brid
ge, D
etou
r at U
pstre
am R
ivB
R-2
1Bo
n Ja
tiLu
nyuk
10W
oode
n B
ridge
(Dam
aged
)B
ridge
10IN
DO
NES
IAC
olla
pse
of O
ld B
ridge
, Det
our a
t Ups
tream
Riv
BR
-22
Blen
gkon
Luny
uk20
--
0M
issin
gB
R-2
3Te
bil
Luny
uk20
-B
ridge
20JA
PAN
Cro
ssin
g at
Sha
llow
Wat
er S
tream
BR
-24
Mom
il ⅠLu
nyuk
10-
Box
Cul
vert
-IN
DO
NES
IAB
ridge
Nam
e : G
rant
aB
R-2
5M
omil Ⅱ
Luny
uk30
RC
Brid
ge (N
ew)
--
L=10
m, W
=7.5
m, S
uper
stru
ctur
e: 6
- I B
eam
s ,
BR
-26
Krik
itLu
nyuk
15U
nder
Con
stru
ctio
n-
-IN
DO
NES
IAL=
10m
. Com
plet
ion
of A
butm
ents
, BR
-25
loca
tB
R-2
7La
mar
Luny
uk40
Con
cret
e C
ause
Way
Brid
ge40
JAPA
NEx
istin
g St
ruct
ure
Com
plet
ion
in 2
007
BR
-28
Aik
mad
Luny
uk15
-B
ox C
ulve
rt-
IND
ON
ESIA
BR
-29
Lian
g Ba
gikLu
nyuk
20C
oncr
ete
Cau
se W
ayB
ridge
20JA
PAN
Exist
ing
Stru
ctur
e C
ompl
etio
n in
200
7 B
R-3
0Pe
tain
ILu
nyuk
15C
oncr
ete
Cau
se W
ayB
ridge
20JA
PAN
Exist
ing
Stru
ctur
e C
ompl
etio
n in
200
7 B
R-3
1Pe
tain
IILu
nyuk
15C
oncr
ete
Cau
se W
ayB
ridge
15IN
DO
NES
IAEx
istin
g St
ruct
ure
Com
plet
ion
in 2
007
BR
-32
Peta
in III
Luny
uk20
--
0M
issin
gB
R-3
3M
olon
gLu
nyuk
15-
-0
Miss
ing
BR
-34
Eman
gLu
nyuk
30C
oncr
ete
Cau
se W
ayB
ridge
30JA
PAN
Exist
ing
Stru
ctur
e C
ompl
etio
n in
200
7 B
R-3
5K
albir
Luny
uk20
Con
cret
e C
ause
Way
Brid
ge20
JAPA
NEx
istin
g St
ruct
ure
Com
plet
ion
in 2
007
Nos
. of B
ridge
: 35
T
otal
Brid
ge L
engt
h : 8
25m
Nos
. of B
ridge
: 20
T
otal
Brid
ge L
engt
h : 4
90m
Nos
. of B
ridge
(≧20
m) :
21
Tot
al B
ridge
Len
gth
: 640
mN
os. o
f Brid
ge (≧
20m
) : 1
7 T
otal
Brid
ge L
engt
h : 4
45m
xt
JAPA
N/
IND
ON
ESIA
m
Res
ult o
f Rec
onna
issan
ce b
y JI
CA
Pre
limin
ary
Stud
y Te
amB
ridge
List
Req
uest
ed b
y In
done
sia
Rec
omm
enda
tion
Brid
geN
o.B
ridge
Loc
atio
n(S
ub-D
istr
ict)
Estim
ated
Leng
th o
fB
ridge
(m)
radi
ent o
f Cut
ting
Slop
e)
h A
butm
ents
, Det
our a
t Dow
nstre
am R
iver
Bed
er B
eder
Bed
Abu
tmen
t: R
Ced
nea
r Lun
yuk
than
BR
-26
arks
Re
ure
Stru
cist
ing
EB
ridge
Nam
e
7. Adverse Environmental and Social Impacts (Results of Scoping and Environmental and Social Considerations Studies)
Scoping matrix for the project is as follows.
Significant adverse impacts are not predicted on the social, natural and pollution areas.
Although some items will have certain degree of affection, they will be of small scale and
can be minimized by some appropriate mitigation measures.
Table-5 Scoping Matrix The Project for Construction of Bridges in the Province of
Nusa Tenggara Barat (Phase 2)
Planning Phase
Construction Phase
Post Construction
Likely Impacts
Com
preh
ensi
ve R
atin
g
Ove
rall
Rat
ing
Land
acq
uisi
tion
Cha
nge
of L
and
use
plan
, Con
trol o
f va
rious
act
iviti
es b
y re
gula
tions
for t
he
cons
truct
ion
Rec
lam
atio
n of
Wet
land
, etc
.
Def
ores
tatio
n A
ltera
tion
to g
roun
d by
cut
land
, fill
ing,
dr
illin
g, tu
nnel
, etc
. O
pera
tion
of C
onst
ruct
ion
Equ
ipm
ent
and
Vehi
cles
Con
stru
ctio
n of
Roa
ds, t
ollg
ates
, pa
rkin
g lo
ts, A
cces
s ro
ads
for b
ridge
s an
d ot
her r
elat
ed fa
cilit
ies
Traf
fic R
estri
ctio
n in
con
stru
ctio
n ar
ea
Influ
x of
con
stru
ctio
n w
orke
rs,
cons
truct
ion
of b
ase
cam
p
Incr
ease
of T
hrou
gh T
raffi
c
App
eara
nce/
Occ
upan
cy o
f Roa
ds a
nd
rela
ted
build
ing
stru
ctur
es
Incr
easi
ng in
flux
of s
ettle
rs
1 Resettlement B B
2 Local economy such as employment and livelihood, etc.
3 Land use and utilization of local resources B B B B B B B
4 Social institutions such as social infrastructure and local decision-making institutions
5 Existing social infrastructures and services
6 The poor, indigenous and ethnic people
7 Misdistribution of benefit and damage
8 Cultural heritage
9 Local conflict of interests C C
10 Water Usage or Water Rights and Rights of Common B B
11 Sanitation B
12 Hazards (Risk) Infectious diseases such as HIV/AIDS B B B B
Soc
ial E
nviro
nmen
t
13 Accidents B B B B 14 Topography and Geographical features
15 Soil Erosion
16 Groundwater
17 Hydrological Situation
18 Coastal Zone
19 Flora, Fauna and Biodiversity B B B
20 Meteorology Nat
ural
Env
ironm
ent
21 Landscape
No.
22 Global Warming B B B B
23 Air Pollution
24 Water Pollution B B B B
25 Soil Contamination
26 Waste B B B B B B
27 Noise and Vibration B B B B
28 Ground Subsidence
29 Offensive Odor
Pol
lutio
n
30 Bottom sediment
Rating: A: Serious impact is expected. B: Some impact is expected. C: Extent of impact is unknown (Examination is needed. Impacts may become clear as study progresses.) No Mark: Few impacts are expected. IEE/EIA is not necessary.
8. Mitigation and Monitoring for Key Impacts Mitigation measures and methodology of monitoring for key items are as follows.
Table-6 Mitigation Measures and Monitoring Methodology
No Target Items Selected from
JICA’s Guidelines Items to be inspected in the site
(BD and DD stage) Mitigation Measures
1 Involuntary Resettlement - Land owners for land acquisition/lease land
-Implementation of public consultation in the Basic Design -Participation of UKL+UPL evaluation committee (representative of the Regency)
2 Land use and utilization of local resources
- Land owners for land acquisition / lease land (farming land)
- Law based procedure should be taken
3 Existing social infrastructures and services -
- Adoption of alternative alignment in case of displacement
4 Local conflict of interests -
-Implementation of public consultation in the Basic Design -Participation of UKL+UPL evaluation committee(representative of the Regency)
5 Water Usage or Water Rights and Rights of Common
- Approach water using places near bridge
- Well points, spring water near bridge
- Adoption of easy-approach design of protection embankment to the river
- Adoption of alternative alignment in case of displacement
6 Hazards (Risk) Infectious diseases such as HIV/AIDS
- - Education for village people and construction workers
Social
7 Accidents - - Traffic safety campaign
Natural
8 Flora, Fauna and Biodiversity -
- Minimization of felling trees in the construction site -Implementation of law based procedures for cutting trees
9 Water Pollution - Measurement or observation of water quality
-Selection of construction methodology to avoid pollution - Monitoring of complaint procedures
10 Waste - Proper disposal of waste (oil from construction equipment and waste from base camp)
Pollution
11 Noise and Vibration - -Fixed construction time/date (in respect of residential area, religion considerations, praying time)
9. Consultation (state who has been contacted about the Project, means of contacting them, date when they were contacted and so on) No public consultation, or stakeholder meeting, has been held in this project based on
JICA’s guidelines and Indonesian laws at the moment. Furthermore, the Indonesian EIA
law prescripts that a public involvement process and information disclosure is applied in
case of full scale EIA (AMDAL), not IEE level (UKL+UPL).
Therefore, the JICA Preparatory Study Team recommended the holding of a stakeholder
meeting in the basic design; and the Indonesian Government agreed with this
recommendation basically. (See Figure-2 Procedures of Environmental Permission (UKL+UPL))
The JICA B/D study team should observe the above stakeholder meeting and report it in the
basic design stage.
10. Social Acceptability in case of involving Involuntary Resettlement and Land Acquisition According to a rough planning for reconstruction structures, temporary land acquisition at
BR35, and permanent land acquisition, must be caused without resettlement.
The proponent (PU) will contact owners after preparation of the draft basic design, and law
-based process will be carried out for negotiation and compensation.
A family member of land owners commented: “We will agree to construct all structures and
follow government instructions, if they will be taking appropriate process and compensate
reasonable costs for land acquisition and displaced some properties.”
Table-7 Location of Land Acquisition and Compensation
BR Num. BR. Name
Area of Land Acquisition
Current Land-use Public Compensation Fee
BR-34 Emang Less than 1ha (approximately 2,000m2)
Compound of private house
14,000Rps./㎡×2,000= 28 million Rps.
BR-35 Kalbir Less than 1ha Paddy field Negotiation-based between landowner and proponent