1. purpose of report 2. recommendation(s)committees.aberdeencity.gov.uk/documents/s3235/update on...

8
ABERDEEN CITY COUNCIL COMMITTEE HOUSING & ENVIROMENT DATE 19 th NOVEMBER 2009 DIRECTOR PETE LEONARD TITLE OF REPORT UPDATE ON THE COUNCIL NEW BUILD PROGRAMME 1. PURPOSE OF REPORT This report provides an update on the key technical elements of the delivery programme and the tender process to date for the development of the three new build council housing sites at Rorie Hall, Byron Park and Hayton Road. 2. RECOMMENDATION(S) It is recommended that the Committee: Note the update and ratify the completed actions to date regarding the progress of the new build council housing sites at Rorie Hall, Byron Park and Hayton Road. To instruct officers to report back in January 2010 at the Housing & Environment Committee on the outcome of the tender process. 3. FINANCIAL IMPLICATIONS Within the Housing Business Plan, monies have been committed for the New Build Programme over the next three financial years (2010 – 2013) for circa £13.5 million. This money will be complimented by the “Kick Start” Scottish Government funding which has been awarded to Aberdeen City Council for sum of £2.1 million. 4. SERVICE & COMMUNITY IMPACT Our Single Outcome Agreement that was produced in response to the Concordat that was agreed between the Scottish Government and local authorities in March 2008 and highlights the local outcomes for housing as follows: To increase the number of new build affordable houses; To meet the targets for the SHQS for social housing; To increase the number of new built houses across all tenures; To meet the 2012 Homelessness targets set by the Scottish Government; and The delivery of the council new build programme is ka key objective of the administration as identified in the VDLF;

Upload: trinhmien

Post on 14-May-2018

215 views

Category:

Documents


2 download

TRANSCRIPT

ABERDEEN CITY COUNCIL

COMMITTEE HOUSING & ENVIROMENT DATE 19th NOVEMBER 2009 DIRECTOR PETE LEONARD TITLE OF REPORT UPDATE ON THE COUNCIL NEW BUILD

PROGRAMME

1. PURPOSE OF REPORT This report provides an update on the key technical elements of the delivery programme and the tender process to date for the development of the three new build council housing sites at Rorie Hall, Byron Park and Hayton Road. 2. RECOMMENDATION(S)

It is recommended that the Committee:

• Note the update and ratify the completed actions to date regarding the

progress of the new build council housing sites at Rorie Hall, Byron Park and Hayton Road.

• To instruct officers to report back in January 2010 at the Housing & Environment Committee on the outcome of the tender process.

3. FINANCIAL IMPLICATIONS Within the Housing Business Plan, monies have been committed for the New Build Programme over the next three financial years (2010 – 2013) for circa £13.5 million. This money will be complimented by the “Kick Start” Scottish Government funding which has been awarded to Aberdeen City Council for sum of £2.1 million.

4. SERVICE & COMMUNITY IMPACT Our Single Outcome Agreement that was produced in response to the Concordat that was agreed between the Scottish Government and local authorities in March 2008 and highlights the local outcomes for housing as follows:

• To increase the number of new build affordable houses; • To meet the targets for the SHQS for social housing; • To increase the number of new built houses across all tenures; • To meet the 2012 Homelessness targets set by the Scottish Government;

and The delivery of the council new build programme is ka key objective of the administration as identified in the VDLF;

• To increase the provision of sheltered housing for communities across the City.

• Work with Registered Social Landlords to develop affordable housing including 2000 new affordable houses.

OTHER IMPLICATIONS 1. Legal –. The tendering process has fully complied with OJEU regulations

and has been ratified by our Legal colleagues in Corporate Governance. 2. Resources – A fully resourced, multi-disciplinary design team is key to the

successful delivery of this project. Robinson Low Francis (construction and property consultants) have been appointed to act as the employer’s agent ensuring contractor(s) meet the contract specifications set out by Aberdeen City Council.

3. Personnel – none arising directly from this report.

4. Property – The addition of new build council houses will help ease pressure on our housing waiting list whilst providing good quality and sustainable homes for the citizen’s of Aberdeen.

5. Equipment – none arising from this report.

6. Sustainability and Environment – Building homes that are eco friendly will

have a positive impact on the environment and add to the sustainability of our communities.

7. Health and Safety – Appointed contractor(s) will be fully compliant with all

H&S specifications of a “Build & Design” contract.

8. Risk Management – All management of risk will be monitored and mitigated in accordance with the ability to meet risk policy and programme objectives. All risks identified will be responded to by evaluating a range of options for treating risks and preparing and implementing a risk management plan.

5 Delivery Update

5.1 Design briefs for the three sites are now complete. The Design and Build briefs set out the house types, room sizes, guidance on design and quality of build and structural and building services systems. The design brief will also set out the planning policies that must be adhered to ensure that the designs are within the requirements for permitted development (a process for ensuring that the design briefs and the subsequent detailed tender submissions are within permitted development has been agreed with the Planning and Infrastructure Service).

5.2 The procurement of the new build council housing takes the form of a design and build tender, as above. Each site will be tendered separately, following the process set out in the Official Journal of the European Union

(OJEU) regulations. The first stage was in May 09 when an OJUE pre-qualification notice was issued. This allowed contractors interested in tendering for the detailed design and build contract to submit details of their capabilities to undertake the requirements of the brief.

5.3 The pre-qualification period ended in July, eight contractors were short listed as a result of this process and were issued with an invitation to tender on October 9th. Tenders are due to be returned on the 8th December, followed by a tender evaluation and interview process for all qualifying contractors. The selected contractor(s) will be reported a special Housing and Environmental Committee in January 2010 followed by formal appointment of contractor(s). The awarded contractor(s) will start on site March 2010.

5.5 Each site has followed a rigorous programme of works to date from site assembly to formal design layout. Please see attached Programme Plan for the sites in appendix i. The details of the three sites are set out below with design layouts attached in appendix ii.

5.5.1 Hayton Road – a mix of up to 30 units, comprising of 2 and 3 bed properties (12 houses & 18 flats)

Demolition of the existing properties is now complete which followed the backfilling of the foundations at the end of September. No ground condition issues have been raised in the initial site survey work. Site is ready for handover to contractor in January.2010.

5.5.2 Byron Park – a mix of up to 28 units, comprising of 3 bed flats and 3 bed Houses (16 houses & 12 flats).

Demolition work has commenced and is due to be completed on November 24th. Site will be ready for contractor in January 2010.

5.5.3 Rorie Hall – a mix of up to 27 units, comprising of 1 and 2 bed amenity properties.

This is a cleared site, and no ground condition issues have been raised in the initial site survey work. The design brief for this site has been prepared incorporating the homes for varying needs standard and the use of telecare technology.

6. Communications

6.1 Since the inception of this project all updates on the delivery programme has been reported to the former Housing New Build Project Board. All future updates will now be reported to the Housing and Environment Committee.

6.2 A range of consultation events took place in the communities concerned where residents were invited to provide comment on the draft sketch designs of the planned new homes. Staff have continued to attend Community Council meetings and provide feedback to residents on the project to date. Further consultations have taken place with RSLs, who are currently developing housing programmes across the City in order to share experiences and knowledge and input to our high spec designs.

The feedback from residents has been positive and the plans have been well received with people recognising the need for more quality family homes in the city

7 REPORT AUTHOR DETAILS Paula Mann and Maria Thies 01224 523155/522146 [email protected]/[email protected]

Supe

rvis

ors

Des

ign

Team

(Arc

hite

ctur

al)

Des

ign

Team

Pet

erC

orbe

ttG

wen

Thom

son

CD

M-C

(Arm

our&

Par

tner

s)S

afet

yP

lan

Man

ager

(EG

reen

)A

rthur

Bar

rieE

ileen

Sm

ithE

lect

rical

Eng

inee

r(TB

C)

Pro

g&

Mon

itorin

g(F

Pat

erso

n)R

ober

tChr

istie

Lynn

McG

owan

Mec

hani

calE

ngin

eer(

TBC

)P

rinci

palA

rchi

tect

(TS

mith

)A

strid

McL

eod

Stru

ctur

alE

ngin

eer(

WA

Fairh

urst

)C

onsu

ltanc

yM

anag

er(S

Pat

ullo

)M

icha

elB

one

Cle

rkof

Wor

ks(T

BC

)C

olin

Hun

ter

Qua

ntity

Sur

veyo

r(TB

C)

File

PRO

JEC

T:

PEER

No

:

1623

306

1320

274

1118

251

815

2229

613

2027

310

1724

317

1421

285

1219

262

916

2330

714

2128

411

1825

18

1522

18

1522

295

1219

263

1017

2431

A B B B C C C C C C C C C C D D D D D D D D D D D D D D D D D E E E E E E E E G G H H H H H J J J J J F K52

wks

K L L L L

CD

M20

07R

equi

rem

ents

Trad

esFo

rtnig

ht/C

hris

tmas

Hol

iday

s

37D

ays

10w

ks10

wks

Clie

ntA

ppro

valR

equi

red

2w

ks

2w

ks

4w

ks

10w

ks10

wks

Dem

oliti

on/E

nabl

ing

Wor

ks

Pre

para

tion

ofC

ontra

ctB

ills

(Bill

ing)

Con

tract

ors

Des

ign

Mak

ing

Goo

dD

efec

tsP

erio

d(M

GD

)

Tend

erPe

riod

Inte

rvie

ws

Con

stru

ctio

nC

onsu

ltanc

y

Pha

sed

App

licat

ion

6w

ks

Dem

oliti

onon

Site

(Byr

onP

ark)

Pre

Tend

erE

stim

ated

Cos

t

Col

lect

ion

ofP

re-C

onst

ruct

ion

Info

rmat

ion

HS

EIn

itial

Not

ifica

tion

App

oint

CD

M-C

Sco

ttW

arra

nder

(3N

O.S

ITES

X£3

.5M

=£1

0.5M

)D

EVEL

OPM

ENT

CO

STQ

uant

ityS

urve

yor:

TBC

CD

M-C

:A

rmou

r&P

artn

ers

6864

-BYR

ON

PAR

K68

65-H

AYT

ON

RD

6866

-RO

RIE

HA

LLS

truct

ural

:WA

Fairh

urst

Jul-0

9

Trades Fortnight

Aug

-09

Feb-

10Ja

n-10

Sep

-09

Nov

-09

Oct

-09 11

wks

Christmas Holidays

Sch

eme

Des

ign

Ele

ctric

al:

TBC

DOM

RIBA

Stage 01

PTQ

Eva

luat

ion/

Ass

esm

ent

Adv

ise

Suc

cess

ful/U

nsuc

cess

fulS

ubm

issi

ons

Adv

ertis

ein

OJE

U(3

7D

AYS

)P

TQC

lose

s

Dem

oliti

onB

illin

g(B

yron

Par

k)

NEW

BU

ILD

HO

USI

NG

(3N

O.S

ITES

)S

uper

viso

r:P

eter

Cor

bet

6w

ks

Dem

oliti

onC

ostA

ppro

val

Brie

fFin

alis

ed

Dem

oliti

onP

roba

ble

Cos

t(B

yron

Par

k)

PTQ

Pre

para

tion

OJE

UA

dver

tPre

para

tion

Dem

oliti

onB

uild

ing

War

rant

(Byr

onP

ark)

Bui

ldin

gW

arra

nt

Cra

igSt

irrat

STA

GE

DES

CR

IPTI

ON

Out

line

Prop

osal

s

Site

Inve

stin

gatio

n

Ince

ptio

n-B

riefR

ecei

ved

Est

Cos

t(P

reD

esig

n)or

Bud

getC

onfir

mat

ion

8w

ks

5w

ks

8w

ks

CLI

ENT

/CLI

ENT

DEP

AR

TMEN

T

Pla

nnin

gAp

plic

atio

n

Com

pile

H&S

File

(CD

MC

)

Feed

back

Prje

ctA

ppra

isal P

lann

ing

&P

olic

yS

vcs

-Adu

lts

Pre

Tend

erC

ostA

ppro

val

INST

RU

CTI

ON

2w

ks

6-7

wks

10w

ks

RE

QU

ES

TR

efR

efC

OM

MIT

TEE

Stage 05

Pra

ctic

alC

ompl

etio

n

Dra

win

gsto

Stag

eE

-Arc

hite

ctur

al

Stage 02

Est

imat

edC

ostA

ppro

val

Est

imat

edC

ost

D&

BC

ontra

ctor

App

oint

ed

Ope

ratio

nson

Site

Pre

para

tion

ofIT

TD

ocum

ents

Stage 04

Hou

sing

Stage 03

Dra

win

gsto

Stag

eE

-Mec

hani

cal

Dra

win

gsto

Stag

eE

-Stru

ctur

al

Invi

tatio

nto

Tend

er(IT

T)

Dra

win

gsto

Stag

eE

-Ele

ctric

al

Clie

nts

Req

uire

men

tsPr

epar

atio

n

Man

dato

ryS

tand

still

Post

App

oint

men

t

Tele

phon

eN

oC

onta

ct

Mec

hani

cal:

TBC

Arc

hite

ctur

al:s

eeab

ove

5280

56

Clie

nts

Req

uire

men

tsFi

nalA

ppro

val

Mar

-09

2009

/201

0W

EEK

CO

MM

EN

CIN

GM

ON

DA

Y

Tend

erR

epor

tto

Com

mitt

ee

Sch

eme

Des

ign

Issu

edto

CD

M-C

May

-10

Dem

oliti

onon

Site

(Hay

ton

Roa

d)

Apr

-09

Clie

ntA

ppro

valt

oA

ppoi

ntC

onsu

ltant

s

Jun-

09M

ay-0

9A

pr-1

0M

ar-1

0D

ec-0

9

App

oint

Con

sulta

nts

Des

ign

and

Bui

ldC

ontra

ctor

Tend

erEv

alua

tion

Pre

pof

Con

stru

ctio

nP

hase

Pla

n

Out

line

Prop

osal

sA

ppro

val

Sch

eme

Des

ign

App

rova

lC

omm

unity

/Ele

cted

Mem

bers

Con

sulta

tion

Sec

ured

byD

esig

nLi

ason

Cle

rkof

Wor

ks:

TBC

Mob

ilisa

tion

DES

IGN

&B

UIL

DPR

OJE

CT

PRO

GR

AM

ME

Res

ourc

esM

anag

emen

tS

tNic

hola

sH

ouse

,Bro

adS

treet

,Abe

rdee

n,A

B10

IGY

Telle

phon

e:0

1224

5234

19Fa

csm

ile:0

1224

6454

55M

inic

om:0

1224

5223

81

8-12

wks

Han

dove

rofD

esig

nan

dC

onst

ruct

ion

ofPr

ojec

tto

Prin

cipa

lCon

trac

tor

The

App

oint

edC

ontr

acto

rwill

beR

espo

nsib

lefo

rPro

gram

min

gan

dC

o-or

dina

ting

wor

ksfr

omA

ppoi

ntm

entO

nwar

ds-T

his

Sect

ion

ofth

ePr

ogra

mm

eis

Ther

efor

eIn

dica

tive.