1 project management – unit 4 – part 1 cost model acwp: actual cost of work performed: actual...

10
Project Management – Unit 4 – Part 1 Cost Model ACWP: Actual cost of work performed: Actual costs in performing the work so far. BCWP: Budgeted cost of work performed: The budgeted (planned) cost for the work performed so far. BCWS: Budgeted cost of work scheduled: The planned profile of expenditure against time for the project. CPI: Cost performance index: The ratio of the value of the work to the actual incurred cost: CPI = BCWP:ACWP BCTC: Cost to complete: Budgeted cost of work still to be achieved. CV: Cost variance: A measure of performance in cost terms: CV = BCWP – ACWP ECAC: Estimated cost at completion: The projected completion cost of the project. ECD: Estimated completion date: The date at which the project is estimated to be completed. PB: Project Budget. The budgeted cost of work performed when the project is completed. SPI: Schedule performance index: The ratio of the work performed to the work scheduled: SPI = BCWP/BCWS SV: Scheduled variance: The difference between the budgeted cost of work performed and work scheduled: SV = BCWP - BCWS The Typical Cost Model in Project Management The problem with managing expenditure In Project Management is that you have to see the whole iceberg

Upload: kathryn-blake

Post on 02-Jan-2016

216 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: 1 Project Management – Unit 4 – Part 1 Cost Model ACWP: Actual cost of work performed: Actual costs in performing the work so far. BCWP: Budgeted cost

Project Management – Unit 4 – Part 1 Cost Model1

ACWP: Actual cost of work performed: Actual costs in performing the work so far.

BCWP: Budgeted cost of work performed: The budgeted (planned) cost for the work performed so far.

BCWS: Budgeted cost of work scheduled: The planned profile of expenditure against time for the project. CPI: Cost performance index: The ratio of the value of the work to the actual incurred cost: CPI = BCWP:ACWP

BCTC: Cost to complete: Budgeted cost of work still to be achieved.

CV: Cost variance: A measure of performance in cost terms: CV = BCWP – ACWP ECAC: Estimated cost at completion: The projected completion cost of the project.

ECD: Estimated completion date: The date at which the project is estimated to be completed.

PB: Project Budget. The budgeted cost of work performed when the project is completed.

SPI: Schedule performance index: The ratio of the work performed to the work scheduled: SPI = BCWP/BCWS

SV: Scheduled variance: The difference between the budgeted cost of work performed and work scheduled: SV = BCWP - BCWS

The Typical Cost Model in Project Management

The problem with managingexpenditure In Project Management

is that you have to see the whole iceberg

Page 2: 1 Project Management – Unit 4 – Part 1 Cost Model ACWP: Actual cost of work performed: Actual costs in performing the work so far. BCWP: Budgeted cost

Project Management – Unit 4 – Part 1 Cost Model2

tp - 1 5 5

tp - 2 7 12

tp - 3 9 21

tp - 4 11 32

tp - 5 15 47

tp - 6 20 67

tp - 7 30 97

tp - 8 45 142

tp - 9 48 190

tp - 10 45 235

tp - 11 43 278

tp - 12 40 318

tp - 13 30 348

tp - 14 20 368

tp - 15 15 383

tp - 16 10 393

tp - 17 5 398

Example Data

Page 3: 1 Project Management – Unit 4 – Part 1 Cost Model ACWP: Actual cost of work performed: Actual costs in performing the work so far. BCWP: Budgeted cost

Project Management – Unit 4 – Part 1 Cost Model3

Example using Data

100

200

300

400

Pla

nn

ed C

ost

01 3 5 7 9 11 13 15 17

Time Period (tp)

Actual Costof

Work Performed

Budgeted Costof

Work Performed

Date ofcalculation

Budgeted Costof

Work Scheduled

Budgeted costto

Completion

Costvariance

Page 4: 1 Project Management – Unit 4 – Part 1 Cost Model ACWP: Actual cost of work performed: Actual costs in performing the work so far. BCWP: Budgeted cost

Project Management – Unit 4 – Part 1 Cost Model4

Calculations

1. Actual cost of work performed = €270

2. Budgeted cost of work scheduled = €390

3. Budgeted cost of work performed = €240

4. Cost performance index = BCWP:ACWP = €240:€270 = 1:1.125

5. Budgeted cost to completion = BCWS – BCWP = €390 – €240 = €€150

6. Cost variance = BCWP – ACWP = €240 – €270 = € –30

7. ECAC = BCWS x CPI = €390 x 1.125 = €438.75

Using the data on the previous slide and calculating from the mid point of time period 9

Page 5: 1 Project Management – Unit 4 – Part 1 Cost Model ACWP: Actual cost of work performed: Actual costs in performing the work so far. BCWP: Budgeted cost

Project Management – Unit 4 – Part 1 Cost Model5

Positive costvariance

Negative costvariance

Monitoring Costs – Cost Variance (CV)

Base Cost LineBCWS

o Remember:– This exercise is based on the S curve – the budgeted cost of work

scheduled for the project. Actual expenditure invariably follows.

Time periods

Plannedcost

CV is a value that should be regularly updated throughout the lifeof the project and is the difference between BCWP and ACWP

Page 6: 1 Project Management – Unit 4 – Part 1 Cost Model ACWP: Actual cost of work performed: Actual costs in performing the work so far. BCWP: Budgeted cost

Project Management – Unit 4 – Part 1 Cost Model6

Remember this?

0

20

40

60

80

100

120

140

160

1 2 3 4 5 6 7 8 9 10 11

Alpha

Beta

Actual

Work Package – Activity ID

Days

Page 7: 1 Project Management – Unit 4 – Part 1 Cost Model ACWP: Actual cost of work performed: Actual costs in performing the work so far. BCWP: Budgeted cost

Project Management – Unit 4 – Part 1 Cost Model7

Managing Time and Cost

Cost

Time period

Days

Time period

Cost

Time period

Days

Time period

Example 1 Example 2

Cost

Time period

Days

Time period

Example 3

Page 8: 1 Project Management – Unit 4 – Part 1 Cost Model ACWP: Actual cost of work performed: Actual costs in performing the work so far. BCWP: Budgeted cost

Project Management – Unit 4 – Part 1 Cost Model8

Comparing the Planned and Actual Values of Work Completed

Planned month end points

Actual month end points

Slack et al. Ed 5. pp514

ACWP Actual cost of work performedBCWP Budgeted Cost of Work performedBCWS Budgeted cost of work scheduled

CV = Cost varianceSV = Scheduled variance

VALUE OF WORK COMPLETED

BCWSBCWP

SV

C V

ACWP

AC

TU

AL

EX

PE

ND

ITU

RE

€100,000

€100,000

Page 9: 1 Project Management – Unit 4 – Part 1 Cost Model ACWP: Actual cost of work performed: Actual costs in performing the work so far. BCWP: Budgeted cost

Project Management – Unit 4 – Part 1 Cost Model9

Estimating Costs at Completion (ECAC)

o Depends on what assumptions the PM chooses to make about the cost of work still to be performed

– Assumption 1. The work still to be achieved will be done at the budgeted cost, the original estimate ECAC = PB – CV

– Assumption 2. (Probably more realistic) is that the remaining work will be performed at the same cost / budget factor that has been observed in the work performed so far ECAC = PB * (ACWP/BCWP) ~ this is sometimes known as

the cost performance index (CPI)

o Cost to completion (CTC) (NB. not the cost at completion) since the cost so far is ACWP, the estimated cost of the work to be done CTC = ECAC - ACWP

...

...

...

Page 10: 1 Project Management – Unit 4 – Part 1 Cost Model ACWP: Actual cost of work performed: Actual costs in performing the work so far. BCWP: Budgeted cost

Project Management – Unit 4 – Part 1 Cost Model10

Summary

o Developing the cost model

o The use of S Curves

o Monitoring cost variance