1 monitoring and evaluation john hough rbec environment & energy practice workshop almaty, 6-9...
TRANSCRIPT
11
Monitoring and Evaluation
John HoughJohn Hough
RBEC Environment & Energy Practice WorkshopRBEC Environment & Energy Practice Workshop
Almaty, 6-9 October 2004Almaty, 6-9 October 2004
22
Purpose
1.1. AccountabilityAccountability
2.2. Management Decision MakingManagement Decision Making
3.3. Lesson LearningLesson Learning
33
GEF Project Monitoring & Evaluation
ActivityActivity ResponsibilityResponsibility TimeframeTimeframe
Logframe with Logframe with Indicators, Baselines and Indicators, Baselines and TargetsTargets
Design teamDesign team During project designDuring project design
M & E PlanM & E Plan Design teamDesign team During project designDuring project design
Inception ReportInception Report Project TeamProject Team During Inception PhaseDuring Inception Phase
Activity PlanActivity Plan Project TeamProject Team AnnuallyAnnually
PIR / APRPIR / APR Project, CO, RCU, PTAProject, CO, RCU, PTA AnnuallyAnnually
TPRTPR Country OfficeCountry Office AnnuallyAnnually
Mid-term, Final, ex-Post Mid-term, Final, ex-Post EvaluationsEvaluations
Country Office + Country Office + Independent EvaluatorsIndependent Evaluators
Mid point, end, 2 years Mid point, end, 2 years post completionpost completion
Terminal ReportTerminal Report Project TeamProject Team 1 month before end1 month before end
AuditAudit Executing AgencyExecuting Agency AnnuallyAnnually
44
Other GEF Monitoring & Evaluation
• SMPR – Secretariat Managed Project ReviewSMPR – Secretariat Managed Project Review
• Programme Study – by focal areaProgramme Study – by focal area
• Performance Study – OPS 2, OPS 3, etcPerformance Study – OPS 2, OPS 3, etc
• Thematic Review – eg. Private Sector, MSP’sThematic Review – eg. Private Sector, MSP’s
• Replenishment TargetsReplenishment Targets
• Tracking ToolsTracking Tools
• OtherOther
55
Sources / Standard Text
66
Adaptive Management
77
Using Adaptive Management
• Requires effective monitoringRequires effective monitoring
• Requires effective indicatorsRequires effective indicators
• Requires measuring of indicatorsRequires measuring of indicators
• Requires review of progress (PIR / APR / Requires review of progress (PIR / APR / TPR)TPR)
• Requires changes in approaches, strategies Requires changes in approaches, strategies and activities - Annual Activity Plansand activities - Annual Activity Plans
88
Risk Management
• In the process of being introduced in In the process of being introduced in UNDP-GEFUNDP-GEF
99
Project Risk Classification• New ProjectsNew Projects
– StandardStandard
– RiskyRisky inherant level of complexityinherant level of complexity
– Size – large or multicountrySize – large or multicountry
– Technically complexTechnically complex
– InnovativenessInnovativeness
– Multiple sources of financingMultiple sources of financing
external risks and assumptionsexternal risks and assumptions– Government commitment, political will, institutional coordinationGovernment commitment, political will, institutional coordination
– Capacity of national executing agencyCapacity of national executing agency
– Passage of critical policies and legislationPassage of critical policies and legislation
– Enabling environmentEnabling environment
– Disbursement of cofinancingDisbursement of cofinancing
– Political and economic factorsPolitical and economic factors
– Natural disastersNatural disasters
Reclassified after the first year of implementation and annually thereafterReclassified after the first year of implementation and annually thereafter
1010
Risk Classification
• Ongoing ProjectsOngoing Projects– StandardStandard
– RiskyRisky
– Problem ProjectProblem Project
– Project in DangerProject in Danger
• Based onBased on– Inherant level of complexityInherant level of complexity
– External risks and assumptionsExternal risks and assumptions
– Implementation difficultiesImplementation difficulties
– Progress towards objectivesProgress towards objectives
1111
Project Risk Checklist
• Project assumptionsProject assumptions
• External environmentExternal environment
• Project management issuesProject management issues
• Effectiveness delays – start up, disbursementEffectiveness delays – start up, disbursement
• Executing Agency / Country Office capacityExecuting Agency / Country Office capacity
• Implementation arrangementsImplementation arrangements
• Delivery, procurement, disbursementsDelivery, procurement, disbursements
• Monitoring and evaluationMonitoring and evaluation
1212
Assessing Risks(GEF M&E unit)
High Risk (H)High Risk (H) 76 - 100% 76 - 100%
Substantial Risk Substantial Risk (S)(S)
51% - 75%51% - 75%
Modest Risk (M) Modest Risk (M) 26% - 50%26% - 50%
Low Risk (L)Low Risk (L) 0% - 25%0% - 25%
Probability assumptions may fail to hold or materialize:Probability assumptions may fail to hold or materialize:
1313
Remedial Actions
• Modified Delegation of Authority letterModified Delegation of Authority letter
• Mandatory / increased frequency of project Mandatory / increased frequency of project visitsvisits
• More frequent reportingMore frequent reporting
• Changes in projectChanges in project
1414
Approval required for Changes to Project
ChangeChange Action RequiredAction Required
Project ObjectiveProject Objective Request to the GEFSEC for approvalRequest to the GEFSEC for approval
Project OutcomeProject Outcome Request to the GEFSEC for approvalRequest to the GEFSEC for approval
Cancellation after CEO EndorsementCancellation after CEO Endorsement
Termination during ImplementationTermination during Implementation
Inform the GEFSECInform the GEFSEC
Implementing Arrangements eg. Executing Implementing Arrangements eg. Executing Agency, Primary Institutional Agency, Primary Institutional Responsibilities, Supervisory Committee Responsibilities, Supervisory Committee responsibilities or compositionresponsibilities or composition
Consultation with the Regional CoordinatorConsultation with the Regional Coordinator
Inputs / Budget – more than X% shifted Inputs / Budget – more than X% shifted between input categoriesbetween input categories
Report through the PIRReport through the PIR
Retro-fitting indicatorsRetro-fitting indicators Report through the PIRReport through the PIR
Implementation targets and / or datesImplementation targets and / or dates Report through the PIRReport through the PIR
Project OutputsProject Outputs Report through the PIRReport through the PIR
Closing DateClosing Date Report through the PIRReport through the PIR
Project ActivitiesProject Activities Adjust Annual Work PlanAdjust Annual Work Plan