1 IT PROJECTS (UNDER CAO/FOIS) PROGRESS AND CONCERNS AUGUST 2006

Upload: laurel-nicholson

Post on 12-Jan-2016

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 1 IT PROJECTS (UNDER CAO/FOIS) PROGRESS AND CONCERNS AUGUST 2006

1

IT PROJECTS(UNDER CAO/FOIS)

PROGRESS AND CONCERNS

AUGUST 2006

Page 2: 1 IT PROJECTS (UNDER CAO/FOIS) PROGRESS AND CONCERNS AUGUST 2006

2

STRUCTURE OF PRESENTATION

1. OVERVIEW

2. AREAS REQUIRING BOARD’S INTERVENTION

3. PROJECT SPECIFIC DETAILS

Page 3: 1 IT PROJECTS (UNDER CAO/FOIS) PROGRESS AND CONCERNS AUGUST 2006

3

OUR TASK - THIS YEARSoftware User/SRS specifications, interaction with field

officers and CRIS, testing and field trial.

Deployment of hardware and connectivity equipments

i) TSS equipment = 4600*

ii) Routers = 500* Modems = 1700* pairs

Lan Extenders = 1013* pairs V-SATs = 950*

Humanware 9500 men to be trained

Connectivity and power supply

Sites = 1151*

Terminals = 3984*

Site identification and preparation

Sites = 1151*

Roll out Hand holding and commissIoning

*Plus issues related to 569 sites, 600 routers, 1200 pairs modems, 187 Lan Extenders, 235 VSATs, 616 terminals & 1400 TSS equipments that were commissioned till last year.

Page 4: 1 IT PROJECTS (UNDER CAO/FOIS) PROGRESS AND CONCERNS AUGUST 2006

4

GROWTH OF IT PROJECTS ON IR

IR’s capital budget for IT is Rs. 273 crore in 2006-07

It is projected to increase to about Rs. 900 crore to Rs. 1200 crore by 2010 – 2011

To make this scale of operation possible, requirement of space and other facilities for CRIS and FOIS organization needs to be significantly increased

Page 5: 1 IT PROJECTS (UNDER CAO/FOIS) PROGRESS AND CONCERNS AUGUST 2006

5

OUTLAY FOR PROJECTS UNDER CAO/FOIS

YEAR INVESTMENT

(Rs. in Crores)

Last 5 years’ average (2001-2006)

26.30

2006 – 2007 100 (approx.)

Page 6: 1 IT PROJECTS (UNDER CAO/FOIS) PROGRESS AND CONCERNS AUGUST 2006

6

IMPORTANT PROJECTS1. COA (Control Charting)

2. FOIS (Freight Operations Information System)

3. CMS (Crew Management System)

4. ICMS (Integrated Coach Management System)

Page 7: 1 IT PROJECTS (UNDER CAO/FOIS) PROGRESS AND CONCERNS AUGUST 2006

7

MAJOR ISSUES NEEDING BOARD’s INTERVENTION

CONTROL CHARTING

DATA LOGGER - INTEGRATION WITH CONTROL CHARTING (COA)

ALL PROJECTS

V-SAT – PERFORMANCE & EXPANSION

DISASTER RECOVERY SITE WITH STAND BY V-SAT HUB AT SC

POWER SUPPLY – CONNECTION FROM AT SUPPLY/STATION GENERATOR

POSTING OF OFFICERS - SUITABLE BACKGROUND, THEIR EXCLUSIVE USE FOR PROJECTS, CONSULTAION WITH CAO

INTEGRATED BUILDING COMPLEX(CAO & CRIS) – SANCTION ON OUT OF TURN BASIS

CMS

EDs COMMITTEE - TO RESOLVE DIFFERENCE IN PRACTICE OVER ZONES

INTEGRATION OF LOBBIES – BY ZONES BEFORE NOV. ‘06

Page 8: 1 IT PROJECTS (UNDER CAO/FOIS) PROGRESS AND CONCERNS AUGUST 2006

8

STATUS – CONTROL CHARTING (COA)

Pilot project under trial at Madurai and Trivandrum divisions of SRDOMs/SrDOMs visiting TVC/MDU and their reports being sent to CRIS continuously for necessary changes/enhancementsTender for customization of software for IR under finalization in CRIS. Tender for hardware and roll out to 23 divisions also under finalization in CRIS (Phase I)Strategy for roll out – In three phases Phase I – SR, SCR, SWR, CR, ECOR, SECR Phase II – WR, WCR, NCR, NR, NWR Phase III – SER, ER, ECR, NER. NFR(all detail at http://it.indianrail.gov.in)

Page 9: 1 IT PROJECTS (UNDER CAO/FOIS) PROGRESS AND CONCERNS AUGUST 2006

9

CONTROL CHARTING (COA) – TYPICAL CHARTChart and Advance Plotting

FOIS COIS NTES CMS

Page 10: 1 IT PROJECTS (UNDER CAO/FOIS) PROGRESS AND CONCERNS AUGUST 2006

10

ISSUES – CONTROL CHARTING (COA)

Integration with dataloggers (1437 already installed & number growing)

Integration with FOIS, COIS, CMS and other public interface systems like NTES, Call centers etc

Record keeping of Control chart information – policy for archival

Page 11: 1 IT PROJECTS (UNDER CAO/FOIS) PROGRESS AND CONCERNS AUGUST 2006

11

IMPACT ON TARGET – CONTROL CHARTING (COA)

Board’s target for IR (76 locations/ 284 boards) – Mar 2007

Latest review with CRIS indicates that software and hardware may become available by Dec 2006

Roll out @ 7 locations per month

Mar 2007 21 locations

Jun 2007 42 locations

Dec 2007 76 locations

Page 12: 1 IT PROJECTS (UNDER CAO/FOIS) PROGRESS AND CONCERNS AUGUST 2006

12

DECISION/ASSITANCE-COA

Telecom and C&IS directorates to resolve the issue of supply of data by datalogger vendors to enable development of interface of COA with networked dataloggers

Safety and C&IS directorates to help freeze archival policy

Page 13: 1 IT PROJECTS (UNDER CAO/FOIS) PROGRESS AND CONCERNS AUGUST 2006

13

ISSUES-FOIS

V-SAT INSTALLATION AT 214 TMS SITES

EQUIPMENTS AVAILABILITY

RAILWAY’S INVOLVEMENT

CHANGED TRAFFIC PATTERN

Page 14: 1 IT PROJECTS (UNDER CAO/FOIS) PROGRESS AND CONCERNS AUGUST 2006

14

FOIS TMS Module524* locations on IR (all details at http://it.indianrail.gov.in)

214 locations on VSAT

324 locations online covering 376 sites

126 locations printing RR online covering 176 sites

Around 1100 PCs and 400 printers supplied so far

668 PCs and 612 printers under supply (within 45 days)

*(3 locations of SR – 1 as P2, 1 closed, 1 HOM port location didn’t commission at all.)

Page 15: 1 IT PROJECTS (UNDER CAO/FOIS) PROGRESS AND CONCERNS AUGUST 2006

15

VSAT – BASIC FACTSON 21/12/04 BOARD (ML/MT/FC) APPROVED SETTING UP OF RAILWAY HUB & PURCHASE OF VSATs BY IRPMU WITH FOLLOWING FEATURES:

1. MASTER EARTH STATION IN KU BAND WITH AUTOTRACKING2. 200 VSAT TERMINALS WITH DATA & VOICE CAPABILITY3. SETTING UP OF NMS NETWORK4. PAYMENT TO DOT FOR COMMERCIAL/CAPTIVE VSAT SERVICES

WITH CUG CAPABILITY5. HIRING OF QUARTER TRANSPONDER6. AMC WITH OEM FOR MAINTENANCE SUPPORT FOR HUB &

TERMINAL7. CAO/FOIS TO MONITOR PROJECT & IRPMU TO NOMINATE ONE DY.

CSTE EXCLUSIVELY8. HIRE VSAT WITHIN 3 MONTHS & SETTING UP OF A HUB WITHOUT

AFFECTING FOIS TERMINAL

Page 16: 1 IT PROJECTS (UNDER CAO/FOIS) PROGRESS AND CONCERNS AUGUST 2006

16

TMS VSAT locations

214 TMS locations have to be

commissioned on VSATs by IRPMU

Railway Board’s target was June 2006.

IRPMU’s revised target is Sept 2006

74 VSATs covered upto 17.8.06

Page 17: 1 IT PROJECTS (UNDER CAO/FOIS) PROGRESS AND CONCERNS AUGUST 2006

17

IMPACT ON TARGET-FOIS

V-SAT DEPENDENT TMS SITES(214) WILL TAKE LONGER TO STABLISE

RESPONSE TIME ISSUES (1500 vs700 msecs)

CHANGE IN HUB FROM VENDOR’S TO OUR OWN (Realignment of each dish)

Page 18: 1 IT PROJECTS (UNDER CAO/FOIS) PROGRESS AND CONCERNS AUGUST 2006

18

Problems relating to the VSAT Network

Response time excessive – timed out if data packet size exceeds 1000 bytes

Voice communication yet to be provided

Video conferencing facility between CRIS, Railway Board and zonal railway HQs required

Page 19: 1 IT PROJECTS (UNDER CAO/FOIS) PROGRESS AND CONCERNS AUGUST 2006

19

GENERAL ISSUES- V-SAT

HECL CONTRACT - 235 (± 25%)

Requirement as of now - 477

HUB CAPACITY-500 (CAN GO UPTO 1000)

TRANSPONDER HIRING ISSUE

Page 20: 1 IT PROJECTS (UNDER CAO/FOIS) PROGRESS AND CONCERNS AUGUST 2006

20

DECISION/ASSITANCE-FOIS

Board’s directive for AT/generator supply from station to TMS site

Nomination of 2 Rates Inspectors by each zone to CAO/FOIS for verification of referential database and testing of software changes due to rates circulars

Page 21: 1 IT PROJECTS (UNDER CAO/FOIS) PROGRESS AND CONCERNS AUGUST 2006

21

STATUS-CMS

Detailed estimate of Rs 38.16 crores sanction by Railway Board.

302 lobbies to be covered, out of which 259 are integrated lobbies (presently around 60%).(all details at http://it.indianrail.gov.in)

Target for completion March 2007

Page 22: 1 IT PROJECTS (UNDER CAO/FOIS) PROGRESS AND CONCERNS AUGUST 2006

22

STATUS-CMSApplication under development and testing for Freight module Coaching, shunting and pilot module Suburban module

Site Preparation Lump sum amount sanctioned @ Rs 1,31,728 for major and Rs

82,890 for minor lobbies Target for readiness Aug 2006

Terminal Equipment Under vetting Target of Phase I supply - Dec 2006

Datacom Equipment Under vetting. Will be procured through CRIS

Training Core group and core implementers will be trained at CRIS Core group identified on all 16 zonal railways Training labs being set up at 5 locations

Page 23: 1 IT PROJECTS (UNDER CAO/FOIS) PROGRESS AND CONCERNS AUGUST 2006

23

ISSUES - CMS

Difference in interpretation of Board’s circulars by zonal railways in calculation of running allowance

Integration of lobbies

Page 24: 1 IT PROJECTS (UNDER CAO/FOIS) PROGRESS AND CONCERNS AUGUST 2006

24

IMPACT ON TARGET-CMSBoard’s target – 302 sites by Mar 2007Latest review with CRIS indicates software and hardware will be available only by Dec 2006. Going by the FOIS and other roll out experience, commissioning of 30 sites per month would be a reasonable target

March 2007 100 sites (DLI MUMBAI routes - 3)

Dec 2007 202 sites

Page 25: 1 IT PROJECTS (UNDER CAO/FOIS) PROGRESS AND CONCERNS AUGUST 2006

25

DECISION/ASSITANCE-CMS

Nomination of Committee of ED s of Electrical, Mechanical, Personnel & Finance for practice to be adopted for computation of running allowance and other issues / business reengineering

Details of sample issues

Page 26: 1 IT PROJECTS (UNDER CAO/FOIS) PROGRESS AND CONCERNS AUGUST 2006

26

STATUS-ICMSEnhanced scope

Punctuality Module Module is being tested on NDLS & MAS

Coaching Stock Management Module Being implemented in three phases Software ready and under field trials at Nizamuddin &

Chennai Ready for roll out

Timetabling Module Time table simulation module’s system requirements

under discussion

Page 27: 1 IT PROJECTS (UNDER CAO/FOIS) PROGRESS AND CONCERNS AUGUST 2006

27

Enhanced scope (contd)

Coaching Stock Maintenance Module Scope of Mechanical module has been enhanced from

capturing of coaching depot maintenance related activities to automation of C&W department

It covers 154 depots & 975 coaching locations. It covers 331 depots & 973 electrical locations. Scope of Electrical Maintenance module defines only 8

technical modules developed by NR under MIS projects. It also does not give assessment of hardware & user specifications.

STATUS-ICMS

Page 28: 1 IT PROJECTS (UNDER CAO/FOIS) PROGRESS AND CONCERNS AUGUST 2006

28

ICMS – Coaching Stock Management Module

Phase I – 114 terminals at 41 locations Target for implementation 31st Aug 2006

Phase II - 78 terminals at 34 locations Target for implementation 31st Oct 2006

Phase III - 128 terminals at 58 locations Target for implementation 31st Dec 2006

(all details at http://it.indianrail.gov.in)Training 186 staff from 136 locations trained so far Training labs being set up to take care of additional training needs

Equipment Thin clients and printers supplied to all locations Datacom equipment- 57 LAN extenders supplied. Rest under supply 14 locations commissioned – NR-1, WR-9, SECR-3 & SR-1 107 locations have been provided connectivity. Target likely to be met

Page 29: 1 IT PROJECTS (UNDER CAO/FOIS) PROGRESS AND CONCERNS AUGUST 2006

29

ISSUES-ICMSFreezing the scope of Mechanical & Electrical Maintenance Modules – Railway Board

Supply of datacom equipment by CRIS & commissioning of 59 VSAT locations

450 pair modems PO placed. Supply in a month

144 pair LAN extenders

Supply completed

112 routers TC negotiation

Page 30: 1 IT PROJECTS (UNDER CAO/FOIS) PROGRESS AND CONCERNS AUGUST 2006

30

IMPACT ON TARGET-ICMS

Three months delay due to supply of UPS and datacom equipment

Mar 2007 Phase I & II – 192 locations

Jun 2007 All 320 locations

Page 31: 1 IT PROJECTS (UNDER CAO/FOIS) PROGRESS AND CONCERNS AUGUST 2006

31

DECISION/ASSITANCE-ICMS

C&IS directorate to facilitate freezing of scope for Mechanical & Electrical Maintenance Modules in view of dropping of work from MIS

C&IS directorate to sanction & release funds for time tabling module.

Page 32: 1 IT PROJECTS (UNDER CAO/FOIS) PROGRESS AND CONCERNS AUGUST 2006

32

GENERAL ISSUES -INFRASTRUTURE

INVESTMENT

SPACE-BLDG

MANPOWER

DISASTER TOLERANCE – VSAT HUB

ISSUE

Page 33: 1 IT PROJECTS (UNDER CAO/FOIS) PROGRESS AND CONCERNS AUGUST 2006

33

GENERAL ISSUES -TRAINING

CURRICULAM IN TRAINING INSTITUTES-TRAFFIC,MECHANICAL,ELECTRICAL-MPP DTE’S ROLE

ADDITIONALTRAINING CENTERS –5 (DLI,SC,BB,HWH,TPJ)

Page 34: 1 IT PROJECTS (UNDER CAO/FOIS) PROGRESS AND CONCERNS AUGUST 2006

34

Increase in strength of FOIS and space requirement

Year

Approx IT budget

(Rs. Crore)

FOIS manpower

(total)

Manpower based

in HQ

Bare seating

space (sq m)

Support space

Training areas, central control

room etc.

Total space

requirement (sq

m)

2006-07 300 264 140 420 420 210 1050

2007-08 360 317 160 480 480 240 1200

2008-09 450 396 200 600 600 300 1500

2009-10 540 475 240 720 720 360 1800

2010-11 650 572 290 870 870 435 2175

2011-12 800 704 360 1080 1080 540 2700

Page 35: 1 IT PROJECTS (UNDER CAO/FOIS) PROGRESS AND CONCERNS AUGUST 2006

35

Projected growth of manpower in CRIS

0

100

200

300

400

500

600

700

800

900

1000

1100

1200

2006 2007 2008 2009 2010 2011

Year

Trainees

Procurement staff

Support staff

IT/HW

Help Desk

N/W

DBA

Implementers (full-time)

Developers

Managers

Page 36: 1 IT PROJECTS (UNDER CAO/FOIS) PROGRESS AND CONCERNS AUGUST 2006

36

SPACE - CRIS location

Page 37: 1 IT PROJECTS (UNDER CAO/FOIS) PROGRESS AND CONCERNS AUGUST 2006

37

SPACE – Area with Railways

Page 38: 1 IT PROJECTS (UNDER CAO/FOIS) PROGRESS AND CONCERNS AUGUST 2006

38

Required facilities for expansion

Secure areas in redRestricted areas in orange Open access in

green

Page 39: 1 IT PROJECTS (UNDER CAO/FOIS) PROGRESS AND CONCERNS AUGUST 2006

39

THANK YOU