1 it projects (under cao/fois) progress and concerns august 2006
TRANSCRIPT
1
IT PROJECTS(UNDER CAO/FOIS)
PROGRESS AND CONCERNS
AUGUST 2006
2
STRUCTURE OF PRESENTATION
1. OVERVIEW
2. AREAS REQUIRING BOARD’S INTERVENTION
3. PROJECT SPECIFIC DETAILS
3
OUR TASK - THIS YEARSoftware User/SRS specifications, interaction with field
officers and CRIS, testing and field trial.
Deployment of hardware and connectivity equipments
i) TSS equipment = 4600*
ii) Routers = 500* Modems = 1700* pairs
Lan Extenders = 1013* pairs V-SATs = 950*
Humanware 9500 men to be trained
Connectivity and power supply
Sites = 1151*
Terminals = 3984*
Site identification and preparation
Sites = 1151*
Roll out Hand holding and commissIoning
*Plus issues related to 569 sites, 600 routers, 1200 pairs modems, 187 Lan Extenders, 235 VSATs, 616 terminals & 1400 TSS equipments that were commissioned till last year.
4
GROWTH OF IT PROJECTS ON IR
IR’s capital budget for IT is Rs. 273 crore in 2006-07
It is projected to increase to about Rs. 900 crore to Rs. 1200 crore by 2010 – 2011
To make this scale of operation possible, requirement of space and other facilities for CRIS and FOIS organization needs to be significantly increased
5
OUTLAY FOR PROJECTS UNDER CAO/FOIS
YEAR INVESTMENT
(Rs. in Crores)
Last 5 years’ average (2001-2006)
26.30
2006 – 2007 100 (approx.)
6
IMPORTANT PROJECTS1. COA (Control Charting)
2. FOIS (Freight Operations Information System)
3. CMS (Crew Management System)
4. ICMS (Integrated Coach Management System)
7
MAJOR ISSUES NEEDING BOARD’s INTERVENTION
CONTROL CHARTING
DATA LOGGER - INTEGRATION WITH CONTROL CHARTING (COA)
ALL PROJECTS
V-SAT – PERFORMANCE & EXPANSION
DISASTER RECOVERY SITE WITH STAND BY V-SAT HUB AT SC
POWER SUPPLY – CONNECTION FROM AT SUPPLY/STATION GENERATOR
POSTING OF OFFICERS - SUITABLE BACKGROUND, THEIR EXCLUSIVE USE FOR PROJECTS, CONSULTAION WITH CAO
INTEGRATED BUILDING COMPLEX(CAO & CRIS) – SANCTION ON OUT OF TURN BASIS
CMS
EDs COMMITTEE - TO RESOLVE DIFFERENCE IN PRACTICE OVER ZONES
INTEGRATION OF LOBBIES – BY ZONES BEFORE NOV. ‘06
8
STATUS – CONTROL CHARTING (COA)
Pilot project under trial at Madurai and Trivandrum divisions of SRDOMs/SrDOMs visiting TVC/MDU and their reports being sent to CRIS continuously for necessary changes/enhancementsTender for customization of software for IR under finalization in CRIS. Tender for hardware and roll out to 23 divisions also under finalization in CRIS (Phase I)Strategy for roll out – In three phases Phase I – SR, SCR, SWR, CR, ECOR, SECR Phase II – WR, WCR, NCR, NR, NWR Phase III – SER, ER, ECR, NER. NFR(all detail at http://it.indianrail.gov.in)
9
CONTROL CHARTING (COA) – TYPICAL CHARTChart and Advance Plotting
FOIS COIS NTES CMS
10
ISSUES – CONTROL CHARTING (COA)
Integration with dataloggers (1437 already installed & number growing)
Integration with FOIS, COIS, CMS and other public interface systems like NTES, Call centers etc
Record keeping of Control chart information – policy for archival
11
IMPACT ON TARGET – CONTROL CHARTING (COA)
Board’s target for IR (76 locations/ 284 boards) – Mar 2007
Latest review with CRIS indicates that software and hardware may become available by Dec 2006
Roll out @ 7 locations per month
Mar 2007 21 locations
Jun 2007 42 locations
Dec 2007 76 locations
12
DECISION/ASSITANCE-COA
Telecom and C&IS directorates to resolve the issue of supply of data by datalogger vendors to enable development of interface of COA with networked dataloggers
Safety and C&IS directorates to help freeze archival policy
13
ISSUES-FOIS
V-SAT INSTALLATION AT 214 TMS SITES
EQUIPMENTS AVAILABILITY
RAILWAY’S INVOLVEMENT
CHANGED TRAFFIC PATTERN
14
FOIS TMS Module524* locations on IR (all details at http://it.indianrail.gov.in)
214 locations on VSAT
324 locations online covering 376 sites
126 locations printing RR online covering 176 sites
Around 1100 PCs and 400 printers supplied so far
668 PCs and 612 printers under supply (within 45 days)
*(3 locations of SR – 1 as P2, 1 closed, 1 HOM port location didn’t commission at all.)
15
VSAT – BASIC FACTSON 21/12/04 BOARD (ML/MT/FC) APPROVED SETTING UP OF RAILWAY HUB & PURCHASE OF VSATs BY IRPMU WITH FOLLOWING FEATURES:
1. MASTER EARTH STATION IN KU BAND WITH AUTOTRACKING2. 200 VSAT TERMINALS WITH DATA & VOICE CAPABILITY3. SETTING UP OF NMS NETWORK4. PAYMENT TO DOT FOR COMMERCIAL/CAPTIVE VSAT SERVICES
WITH CUG CAPABILITY5. HIRING OF QUARTER TRANSPONDER6. AMC WITH OEM FOR MAINTENANCE SUPPORT FOR HUB &
TERMINAL7. CAO/FOIS TO MONITOR PROJECT & IRPMU TO NOMINATE ONE DY.
CSTE EXCLUSIVELY8. HIRE VSAT WITHIN 3 MONTHS & SETTING UP OF A HUB WITHOUT
AFFECTING FOIS TERMINAL
16
TMS VSAT locations
214 TMS locations have to be
commissioned on VSATs by IRPMU
Railway Board’s target was June 2006.
IRPMU’s revised target is Sept 2006
74 VSATs covered upto 17.8.06
17
IMPACT ON TARGET-FOIS
V-SAT DEPENDENT TMS SITES(214) WILL TAKE LONGER TO STABLISE
RESPONSE TIME ISSUES (1500 vs700 msecs)
CHANGE IN HUB FROM VENDOR’S TO OUR OWN (Realignment of each dish)
18
Problems relating to the VSAT Network
Response time excessive – timed out if data packet size exceeds 1000 bytes
Voice communication yet to be provided
Video conferencing facility between CRIS, Railway Board and zonal railway HQs required
19
GENERAL ISSUES- V-SAT
HECL CONTRACT - 235 (± 25%)
Requirement as of now - 477
HUB CAPACITY-500 (CAN GO UPTO 1000)
TRANSPONDER HIRING ISSUE
20
DECISION/ASSITANCE-FOIS
Board’s directive for AT/generator supply from station to TMS site
Nomination of 2 Rates Inspectors by each zone to CAO/FOIS for verification of referential database and testing of software changes due to rates circulars
21
STATUS-CMS
Detailed estimate of Rs 38.16 crores sanction by Railway Board.
302 lobbies to be covered, out of which 259 are integrated lobbies (presently around 60%).(all details at http://it.indianrail.gov.in)
Target for completion March 2007
22
STATUS-CMSApplication under development and testing for Freight module Coaching, shunting and pilot module Suburban module
Site Preparation Lump sum amount sanctioned @ Rs 1,31,728 for major and Rs
82,890 for minor lobbies Target for readiness Aug 2006
Terminal Equipment Under vetting Target of Phase I supply - Dec 2006
Datacom Equipment Under vetting. Will be procured through CRIS
Training Core group and core implementers will be trained at CRIS Core group identified on all 16 zonal railways Training labs being set up at 5 locations
23
ISSUES - CMS
Difference in interpretation of Board’s circulars by zonal railways in calculation of running allowance
Integration of lobbies
24
IMPACT ON TARGET-CMSBoard’s target – 302 sites by Mar 2007Latest review with CRIS indicates software and hardware will be available only by Dec 2006. Going by the FOIS and other roll out experience, commissioning of 30 sites per month would be a reasonable target
March 2007 100 sites (DLI MUMBAI routes - 3)
Dec 2007 202 sites
25
DECISION/ASSITANCE-CMS
Nomination of Committee of ED s of Electrical, Mechanical, Personnel & Finance for practice to be adopted for computation of running allowance and other issues / business reengineering
Details of sample issues
26
STATUS-ICMSEnhanced scope
Punctuality Module Module is being tested on NDLS & MAS
Coaching Stock Management Module Being implemented in three phases Software ready and under field trials at Nizamuddin &
Chennai Ready for roll out
Timetabling Module Time table simulation module’s system requirements
under discussion
27
Enhanced scope (contd)
Coaching Stock Maintenance Module Scope of Mechanical module has been enhanced from
capturing of coaching depot maintenance related activities to automation of C&W department
It covers 154 depots & 975 coaching locations. It covers 331 depots & 973 electrical locations. Scope of Electrical Maintenance module defines only 8
technical modules developed by NR under MIS projects. It also does not give assessment of hardware & user specifications.
STATUS-ICMS
28
ICMS – Coaching Stock Management Module
Phase I – 114 terminals at 41 locations Target for implementation 31st Aug 2006
Phase II - 78 terminals at 34 locations Target for implementation 31st Oct 2006
Phase III - 128 terminals at 58 locations Target for implementation 31st Dec 2006
(all details at http://it.indianrail.gov.in)Training 186 staff from 136 locations trained so far Training labs being set up to take care of additional training needs
Equipment Thin clients and printers supplied to all locations Datacom equipment- 57 LAN extenders supplied. Rest under supply 14 locations commissioned – NR-1, WR-9, SECR-3 & SR-1 107 locations have been provided connectivity. Target likely to be met
29
ISSUES-ICMSFreezing the scope of Mechanical & Electrical Maintenance Modules – Railway Board
Supply of datacom equipment by CRIS & commissioning of 59 VSAT locations
450 pair modems PO placed. Supply in a month
144 pair LAN extenders
Supply completed
112 routers TC negotiation
30
IMPACT ON TARGET-ICMS
Three months delay due to supply of UPS and datacom equipment
Mar 2007 Phase I & II – 192 locations
Jun 2007 All 320 locations
31
DECISION/ASSITANCE-ICMS
C&IS directorate to facilitate freezing of scope for Mechanical & Electrical Maintenance Modules in view of dropping of work from MIS
C&IS directorate to sanction & release funds for time tabling module.
32
GENERAL ISSUES -INFRASTRUTURE
INVESTMENT
SPACE-BLDG
MANPOWER
DISASTER TOLERANCE – VSAT HUB
ISSUE
33
GENERAL ISSUES -TRAINING
CURRICULAM IN TRAINING INSTITUTES-TRAFFIC,MECHANICAL,ELECTRICAL-MPP DTE’S ROLE
ADDITIONALTRAINING CENTERS –5 (DLI,SC,BB,HWH,TPJ)
34
Increase in strength of FOIS and space requirement
Year
Approx IT budget
(Rs. Crore)
FOIS manpower
(total)
Manpower based
in HQ
Bare seating
space (sq m)
Support space
Training areas, central control
room etc.
Total space
requirement (sq
m)
2006-07 300 264 140 420 420 210 1050
2007-08 360 317 160 480 480 240 1200
2008-09 450 396 200 600 600 300 1500
2009-10 540 475 240 720 720 360 1800
2010-11 650 572 290 870 870 435 2175
2011-12 800 704 360 1080 1080 540 2700
35
Projected growth of manpower in CRIS
0
100
200
300
400
500
600
700
800
900
1000
1100
1200
2006 2007 2008 2009 2010 2011
Year
Trainees
Procurement staff
Support staff
IT/HW
Help Desk
N/W
DBA
Implementers (full-time)
Developers
Managers
36
SPACE - CRIS location
37
SPACE – Area with Railways
38
Required facilities for expansion
Secure areas in redRestricted areas in orange Open access in
green
39